Weekly Report for Week Ending September 29,
2005
The LIGO Executive
Committee Agenda for Monday October
3, 2005 will be:
(Meeting time: 10:30 am Pacific Time)
- Announcements
- Comments
on Weekly Report
- LSC
Issues (Saulson)
- LIGO
Lab Operations
- Administration
(Lindquist)
- Sites
(Raab, Zucker, Shoemaker)
- Commissioning
(Fritschel), Detector (Coyne)
- Campus
Research Facilities
- 40
Meter (Weinstein)
- TN,
( Libbrecht)
- LASTI
(Shoemaker)
- Data
Analysis and Computing (Lazzarini)
- R&D
and Advanced LIGO (Shoemaker)
- CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION
AS NEEDED
Special Items:
Special Announcements:
Weekly
Report Highlights
LSC Issues (Saulson)
No report
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
- Completed
all the changes received so far and posted them, along with two of the new
MOUs (University
of Sannio
at Benevento/University of Salerno
and University of Texas at Austin).
- Submitted
the MOUs listed below for approval to proceed
with obtaining signatures. (These MOUs were
accepted by the review panel, ready as submitted or with changes that I
have now made.)
- ACIGA,
Balearic, CaRT, CEGG, Columbia, GEO600, IUCAA,
Michigan, Moscow, NAOJ,
Northwestern, Oregon, Penn State, SLU, Sannio,
Southern Univ, Stanford, Syracuse, TexasB
- The
following MOUs were also accepted (pending
modifications) by the review panel and will be processed and posted as I
receive them:
- Carleton
College, Louisiana Tech, LSU, Florida, Goddard, Hobart & William
Smith, IAP, Loyola, Rochester, Trinity Univ, Univ of Washington, Washington State, University of
Wisconsin, Milwaukee
Non-LSC MOUs (Lloyd)
SITE TELECONFERENCE (Lindquist)
- A
site teleconference was held Thursday, September 29, 2005. The
following issues were discussed:
- The
list of assigned actions updated through September 01, 2005 will be found Here.
PROPERTY MANAGEMENT (Chargois)
>From: Ed Chargois <chargois_e@ligo.caltech.edu>
- Nothing
significant to report.
DOCUMENT
CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- Working
on "P Document Project"
- Assisted
in sending out the contract for the Construction of the Science Education
Center at LLO to Cangelosi Ward General Contractors.
- Assisted
in sending out two RFQ's (Fabrication for Vacuum
Housings for Pod Assemblies and Fabrication for Actuator, Locator
Sub-Assembly and Tooling)
- Total
volume of handling incoming/outgoing packages was much higher than normal.
- **Update
on Scanning Project** - The remaining boxes of account files are still
being scanned and book-marked.
These should be done fairly shortly (end of this week or early next
week). The next set of boxes we
will be tackling is 16 boxes of Larry Jones' old files that were stored in
the sub-basement.
- Activity:
|
Week Ending
09/29/05
|
In
|
Out
|
|
Packages
|
35
|
14
|
|
Faxes
|
13
|
18
|
FINANCIAL SYSTEMS (Cronin, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Received
several TechMart requisitions submitted directly
from LIGO Hanford Observatory for the purchase of goods. The orders were placed quickly and there
were no delays. The orders went out and Hanford was notified of the estimated
delivery dates.
- Purchased
a turbo pump from Osaka Vacuum. Completed the internal modification to
change the expenditure type on this order.
- Completed
the no-cost extension of the MCI blanket order which covers the payment of
the LIGO server modem. This was the only blanket purchase order on the
list that has been extended for the new fiscal year.
- There
are several blanket purchase orders that will be closed out after the new
fiscal period begins. Alternate methods are available and this change in
ordering goods or paying invoices is not estimated to impact the level of
service provided nor delay the purchase of goods.
- Completed
change order #3 to Raytheon for the new System Administrator and routed it
for approvals.
- Placed
several orders purchase orders for fabricated goods and for equipment
which have long lead time. The orders are booked with the vendors and are
in process.
- Completed
change order #30 to Waveprecision for the order
of the fused silica substrates.
- I
have several tax credits pending to be issued by vendors while they
research and approve the issuance of the credits. The vendors charged
sales tax on orders for the off-site facilities that should be exempt.
- The
five-year maintenance agreement has been issued to Dynamic Systems. We
would have to give notice to the vendor latest by January 31, 2006 if we
wish to cancel the service for Year 2.
I have notified Dan Kosak and also noted
it in my calendar to raise the question in January 2006 before the 60 days
lapse into the new maintenance year.
The rate for Year 2 will be approximately $46K and is considerable
so we need to be proactive and make a decision before Year 2.
- Made
arrangements for several items returned on credit card purchases.
Coordinated the returns and am waiting for the pending credits to be
issued.
- Completed
the monthly purchase order reports and submitted them to management.
>From: Florence Kaufman <fkaufman>
- Worked
on updating reports for September.
- September
report for Ops & R&D will include a column showing the current
FY06 budgets. This can be used to
compare the budgets with the FY05 budgets as well as the expenditures
through September, to check for reasonableness of the FY06 budgets.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence.)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone
<gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow
<jasnow@ligo.caltech.edu>
- The
contract for the construction of the Livingston LIGO
Observatory Science Education
Center has been sent
to Cangelosi-Ward for signature. When the contract is executed and
performance and payment bonds have been submitted, a formal Notice to Proceed will be issued.
A formal kickoff meeting has been tentatively scheduled for the
second week in October.
- The
architect for the LLO SEC has been requested to submit a proposal for the
performance of construction management for the full period of
construction.
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
- Processed
the paper work for six (6) new/revised trips. At this time there are eight (8) trips
completed or in the works but are awaiting the necessary paper work to
enter the P-Card system.
- Completed
ten (10)Expense Reports and there are twelve
(12)reports yet to be done. I
continue to contact travelers who have outstanding Expense Reports (more
than one (1) month old) to ask for their cooperation in sending me their
receipts so that these can be closed in a timely manner. Presently there are six (6) reports more
than thirty (30) days old. I have
four (4) reports awaiting signature at this time. Worked on copying and recording all the
expense reports completed last week to be sent to Travel Audit for final
auditing and payment.
- Reconciled
thirteen (13)P-Card charges for the week,
requiring telephoning hotels and car rental agencies to verify which
traveler used my card and for what amount.
>
>Dorothy Lloyd
- Processed
the usual invoices for payment and followed up on problems. Reviewed and
recorded payments processed during the months of July and August.
- Processed
the usual requisitions for purchases over $10K and standard POs, as SOS
buyer, for those under.
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
PROPOSALS and REPORTS (Lindquist)
Additional material for request for supplemental funding for Operations for
FY 2007 and FY 2008 has been prepared ready for final review and forwarding to
the NSF.
DCC Steering Committee (Lindquist)
Purchase Orders for new document management software, support, and the
hardware to put it on are in process.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- No
special activities to report.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
No report.
LIGO Hanford Observatory
(LHO) and Interferometer Operations (Raab)
Summary of Commissioning Activities at LIGO Hanford Observatory (Landry)
Interferometers were decidedly touchier this week. Problems on the 4k
were due in part to excess AS_I, the origin of which is not yet understood, but
may be due to DC misalignment in the IFO, or perhaps reduced gains in WFS
paths. ASPD4 had been swapped out because of burn spots, but the swap did
not induce the excess AS_I as it is high (and different) on other PDs. See the ASPD checkout and discussion in the
first 4k bullet below.
Some commissioning highlights:
- fast
channels have been successfully written to frames, and were confirmed to
behave as expected, in that gain and phase paths did what they're supposed
to do
4K IFO
- The
AS_I servo signal has been latching during startup of TCS servo: there is
excess AS_I, the signal saturates and latches as there is a sign flip and
the servo no longer drives the error signal to zero. Non-linearity
found to be worse in ASPD3 and 4, than in the other two AS PDs. The TCS servo was modified
in light of the ASI woes. PDs and
electronics were investigated:
the upshot is, the electronics are working as
advertised and not responsible for the AS_I problem. Batches of PDs vary in there specifications, however, which may
contribute to our problems. ASPD positions and beam sizes are shown
in this schematic.
- improvements
in oscillator phase noise coupling over the last eight months are
described (we're a factor of 3-10 better than in Feb 04)
- When
testing the new POPI servo that uses POS as an error signal and the fine
actuators for feedback (intended to mitigate scattering in end stations),
ETMX was rung up and stuck
electrostatically. As per the Montana quake this summer, the optic
was later freed
by shaking and partially venting the BSC. Seismic upconversion was studied:
a model was made and POS data employed to predict the effect of scattering
in EYon IFO noise. The POPI servo was
later closed,
and some results
were elogged: the 1.2 and 2.1Hz stack modes are
quashed by 3-4dB in displacement, but some noise creeps up between the two
resonances.
- the
CM servo began acting
up
2K IFO
- frequency
noise was assessed
for the H2 noise budget
- initial attempts at high (6W) power failed
on the 2k, as SPOB and arm powers went the wrong way. A second
attempt was made, with similar results, once ASPD4 was removed from the
loop. From 3W upwards, there is no indication we get more
power into IFO, e.g. for a 40% increase into IFO, we get no increase in
the calibration line amplitude, and ~20% drop in SPOB and arm power.
Feh. A suspicion is that there is too much
RF in these PDs and saturations are present.
- the
common mode unity gain frequency was found to be too low
DAQ
- IRIG-B
was broken,
causing h1awg to flash red and junk to be sent out of the calibration line
excitation point point
- Testing
of the state vector for S5 is underway
Outreach (D. Ingram)
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
L1 Interferometer (Frolov)
Interferometer commissioning and low noise running restarted on Monday
following the four day shutdown for Hurricane Rita. The work on the reflected
beam stabilization (RBS) continues to be the main commissioning activity.
Initially the mechanical resonances of the PZT actuated mirror mounts appeared
very strongly in the the interferometer dark port
signal. With an addition of damping material between the PZT and the mount the
resonance peaks have been dramatically reduced and no longer appear in the ifo noise spectrum. The estimated
contribution from the pzt motion to the ifo noise is close to a factor of
ten below the current noise floor and could be further reduced by additional
electronics filtering. After resolving electronics interface issues the RBS control
loops were closed. The initial test results with both the single bounce beam
from the recycling mirror and the fully locked interferometer have shown that
the system is operational and can follow the Faraday isolator thermal drift up
to 4 W ifo input power. Integration into the
interferometer control system, performance optimization, and testing at higher
power is underway.
Other commissioning activities this week included:
- the
measurement of arm cavity ring downs confirmed earlier measurement of the
cavity poles
- the
test of tilt correction on HEPI HAM1 showed only marginal improvement
above 1 Hz
- the
test mass suspension electronics noise budget was produced in anticipation
of it becoming a dominant noise source after the upcoming ifo commissioning effort in October
CDS (Bogue)
- Worked
with Rusyl, Mike, Harry and Danny on shutting
down in preparation for hurricane rita.
Since we didn't lose power, CDS had no major complications as a result of
the hurricane. - Did a full switchover from the primary to the backup framebuilder. Created a written procedure for how to
do this. This procedure does not
yet include how to create the sam qfs mounts on the backup. I will work with ldas
to get that part of the procedure in place.
- Worked
on a problem with the sense mon
displays that the operators use. Apparently, DMT dropped new code that
contained changes to existing channel names. All of our plots that use the affected
channels are now broken.
- Added
channels to the daq to support the new RBS
system.
- Continued
troubleshooting problems with the new disk arrays.
CDS code support (Khan)
No report.
Education and Outreach (Thacker)
No report.
Site Safety and Security (Riesen)
Rich is on vacation this week.
LLO Computing and Network Security (S. Roddy)
- Most
of the last week has been spent working on testing a transition from NIS+ to LDAP. This has been needed for quite some
time. I started on it a while back
and it was then placed on the back burner for a while. I will also deploy some of the Sun
Enterprise software at the same time as the LDAP transition. This is a long and complex deployment
and I have at least 50 hours into this already, and I still have a ways to
go. I have successfully migrated
accounts from NIS+
to LDAP, gotten LDAP working via SSL, installed
the messaging server and calendar server.
At which point I learned there were a few mistakes made in the
beginning. I am now starting over
with a fresh install of Solaris and should have things going by early next
week. There are some nice benefits
to going to the enterprise software, not the least of which is getting rid
of NIS+
which Sun has been threatening to end support for.
- Installed
Norton AV 10 on several machines.
- Testing
Norton 10 for the Mac. Seems OK so
far... Once I am satisfied there
are no major bugs, I will have our Mac users install it.
- Received
the new Dell for Ken. He seems
happy with the new machine.
- Received
the new Laser Safety computer yesterday.
It is in the MSR and needs to be installed with Win XP.
LLO General Computing and LDAS Support (D. Giardina)
- Assisted
Janeen Romie with
printer setup.
- Assisted
Bonnie Wooley with updating some html documents.
- Ordered
replacement disk for last bad disk in T3-13 (spare).
- hdb failed in node28,
replaced with new disk. this disk is still under warranty and will be returned.
- Returned
two disks (from nodes) that were still under warranty; awaiting replacements.
- LDAS
equipment move and ensuing troubleshooting of various problems encountered
when systems were brought back up.
HPLF, Optics Modeling, Data Analysis and L1 Commissioning (Franzen)
Ken has been working exclusively on the detector RBS project, reported under
L1 commissioning.
Mechanical Engineering (Spjeld)
- accessing
the PDM Vault and updating the Quad SUS install fixtures models and
drawings
- converting
drawings for the kinetic pendulum wall to pdf
files and working on assemblies
- working
on redesign and drawings for the HAM door removal tool
LDAS/Condor Sysadmin and Burst Analysis (Yakushin)
LDAS moved downstairs. It took three days: the system went down on Monday afternoon
and came back on Thursday afternoon. At first glance, everything seems to be
working.
Initial LIGO Detector Science & Engineering (Coyne)
CDS
see also the CDS weekly meeting
minutes in the commissioning
archives
CDS Software
Rolf Bork
A number of change requests for software have come in during the past week:
- Change
the input to the useismic filter on LHO4k ETM
from the position filter output to the position filter input. This is done
and will go in today.
- Changes
to have the LSC front end trigger the fast shutter while attempting to
maintain lock by switching automatically to ASPD5. This is a more complex
change that is still in progress. We plan to put the Epics part of the
change on to LHO2k today, with the front end code to follow in the next
few days.
- Updated
the daqLib software to provide a decimation
filter for 64x decimation (previous code only had up to 32x decimation
support). Filter definition was developed by Rana.
This change is needed to record suspension 16K signals at 256Hz. This is
being installed on LHO2k today for all large optic controllers..
- M.
Evans requested a change to filter module software to try and prevent
integrator run away. This change was put in as a compile option and will
only be loaded on LHO2k LSC today as a test.
- Modified
a version of the LSC code to output the DARM_CNTRL signal through a Pentek DAC channel. The idea is to get an independent
analysis of the noise seen in this signal in the DAQ by using a hardware analyzer.
This code is loaded on to the LHO4k LSC, but I have not heard of any
results as yet.
- Along
with updating all of the LHO2K front end software today, we are also
looking at switching the associated epics to the latest version. Some
systems are not responding well to that change at the moment, so we may
revert to the older version. This epics change is only for the Linux
boxes.
CDS Hardware
Jay Heefner
Refl Beam Stab
- The
modified chassis has been installed at LLO. New chassis for LHO will be
started as soon as operation of the modified chassis is verified.
DMT
no report
PSL
Peter King
A way was found to incorporate the capacitance changes as a function of applied
bias voltage for a photodiode in PSpice. I have
not had a chance yet to actually implement it in a circuit simulation. In
addition some breadboarding of a discrete photodiode
front-end was done. Comparisons with the model will be made.
An 80 MHz VCO is being dusted off for shipment to LASTI. Contrary to
what I first thought, the unit is an addition and not a replacement.
Dennis Coyne
Peter Fritschel, Stan Whitcomb and I visited JDS Uniphase to discuss continued maintenance support for the LIGO
10W lasers. JDSU is focused on commercial product and so can't perform any
further development work in support of LIGO. However they are willing to
support continued refurbishment with the stockpile of matched SDL pump diodes
reserved for LIGO lasers. It seems that this will be sufficient for the
duration of the S5 run at least. A plan for maintenance/refurbishment will be
proposed by JDSU. Internally LIGO Lab is also planning for the post-S5/pre-AL
laser needs.
40 Meter Interferometer (Weinstein)
Osamu is at LHO for a couple of weeks to help with pre-S5 commissioning.
IFO commissioning:
- Rob,
Osamu and Rana have been working on bringing the
IFO into full lock with resonant arms. Osamu was able to transfer control
of CARM from DC to RF at POX and/or POY pickoff RFPDs,
but has not yet succeeded in switching control to SP 166.
- Rob
and Rana tried several things to aid in reducing
the CARM offset. These include: smoothing over the transition from
high-gain to low-gain in the DC signal from the transmitted PD; changing
the 'optical plant compensation' filters in the CARM bank; lowering the
DARM loop UGF and changing its filters to avoid instability as the light
power increases; checking carefully for coil driver saturations. Most of
their changes helped. But, noise continues to drive large power
fluctuations and lock loss before full arm resonance is acheived. Noise reduction efforts continue.
- Rana measured the relative gain of the MCL and MCF
components of the MC servo, and the frequency of the length/freq
crossover. He measured it to be ~ 90 Hz. He then lowered the crossover to
~60 Hz, near the peak of the phase bubble, which reduced the frequency
noise as measured by the XARM error signal in the 60-100 Hz region.
- Rob
and Rana continue to hunt for different lock
acquisition strategies, both for the 40m and for AdLIGO.
IFO modeling:
- Monica
continues to work on locking studies with her 40m/AdLIGO e2e simulation.
She is simulating sweeps through arm resonances in the full IFO, at
various velocities, and plotting properly normalized signals to look for
the largest and most promising ones for controlling CARM.
- Rob
is developing his AdLIGO Finesse modelling tools, and sharing them with Rana and Peter Fritchel.
DC detection development:
- Mike
Smith is in the process of making final part drawings for the OMC. The
Solid Works model was set up parametrically, so the mode cleaner length
can be changed and the parts will adjust automatically to accomodate. Ken Mailand is
helping him analyze the normal modes of the structure with Algor.
- Steve
has been looking into the availability and pricing of brass for the output
mode cleaner, which should have better-damped internal resonances. It is
also vacuum compatible, relatively easy to machine, relatively low cost,
and relatively low thermal expansion.
- Steve
has spec'ed vacuum feedthroughs
for the in-vac DC PD electronics can.
- Rana suggests building as much of the in-vac DC beamline as possible
on a single breadboard, so that it can be pre-aligned in air before
installing into the output optic chamber.
- Rana and Ben have been looking at a different DC PD
circuit design to handle hundreds of mW of input
light power. They will route the resulting current into a high-power
vacuum-compatible resistor, which will produce up to 5 watts of heat, sinked to the table.
Electronics, controls:
- Dan
has finished the diagonalization of the three
mode cleaner suspended optics (M1, MC2, MC3) and has updated the output
matrix for all 3 MC optics. He attributes improved noise at the bounce
mode to his efforts.
- Dan
is now taking measurements to evaluate the improvement in coupling between
POS-PIT-YAW in the MC suspensions. This is important because the MC
alignment servo injects frequency noise onto the beam due to ANG->POS
couplings, so the gain is turned way down. Next, Dan will see whether the
MC alignment servo gain can be turned back up.
- A
limitation on the MC suspension diagonalization
is the large bias voltage applied to the suspension PIT and YAW,
especially on MC3. Dan and Ben are now getting RevB
coil drivers onto the MC suspensions, to eliminate this problem.
- Rob
and Dan found and jiggled a flaky cable on the MC3 satellite amplifier
box. They will get Bob to replace the connectors or the whole cable.
- Rob
wrote some scripts for gain matching the transmitted light QPDs and thorlabs PDs, so that the length sensing system can switch
between them smoothly.
- Rana suggests suppressing 60 Hz/harmonics coming in to
the LSC demod boards through the RFPD cables, by
winding the RF lines around ferrite donuts, and maybe even coupling
through 1:1 transformers.
- Rana suggests adding passive filters to the LSC signal
whitening boards to suppress HF noise, as is done at the sites.
Thermal Noise Interferometer (Black)
Nothing significant to
report this week.
LASTI (Ottaway)
This week we welcomed a new graduate student into the lab. Brett Shapiro has
joined our group, he intends to do a Master degree in Mecahnical Engineering with a thesis in LASTI related work.
His first task will be to characterize the Quad when it arrives and extend the
controls work done by Laurent to cover the quad. Welcome Brett
!!
Work continues on the suspended cavity and its use to characterize the the frequency noise of the PSL. This will continue until we
vent in Mid October to install new optics and the second triple.
We have decided to modify the length of the suspensions that are used in
LASTI SOSs. The aim of this is to shift the pendulum
frequency from 1.0 Hz to 0.7 Hz. The reason for this is to shift the resonant
frequency to the "hole" in our seismic spectrum. There is approximately 3 X less motion at 0.7 Hz as there is at
1.0 Hz. These modified SOSs will be installed and
tested during our next vent.
The triple will be shaken down and prepared for installation in the next few
weeks. In addition to this we are ordering an optical fiber system to port the
PSL light to the Xend HAM for the triple and future
LASTI tests.
Rich Mittleman reports:
WE have implemented a feed forward system from the BSC chamber to the HEPI
actuators, the filters are designed. WE are waiting for the construction that
is taking place on the alley behind the building to stop so that all of our
sensors are not saturated.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
E2E Weekly Physics Meeting
Sany Yoshida presented the seismic isolation model
(based on a model by Brian of Stanford) they are preparing using e2e modules
and results from some preliminary runs. Physics behind modal model
implementation in e2e modules was also discussed.
Mechanical Simulation
(Mark Barton) This week I spent investigating the mystery of why the quad
pendulum control prototype was unstable in pitch. The suspicion was that we
were somehow not correctly allowing for the stiffness of the wire. The Matlab model of
the suspension neglects the wire stiffness and assumes all the pitch restoring
force is gravitational. To get a suitably low fundamental pitch frequency under
these assumptions requires that for each mass, the attachment points for the
wires coming down from above be about 1 mm above the COM, and those for the
wires continuing down below be about 1 mm below the COM. To maintain this
frequency with stiff wire, the attachment points have to be adjusted in the
unstable direction by relatively large amounts, of up to 5 mm for the upper stages.
Clearly, small errors in the theory can be the difference between success and
failure.
The theory we were using was given in a paper Cagnoli
et al., 2000. To check it I used my Mathematica toolkit to analyze a large number of toy
models, including one-, two- and four-wire simple pendulums, and a double
pendulum with the top mass hinged about a transverse axis and the bottom mass
suspended by four wires. Calum and I also built a
two-wire pendulum in the lab. It turns out that we were applying the corrections
correctly for the most part, except in the top two stages where the wires are
further apart transversely at the top than at the bottom. In such a case, the
flexure correction has to be reduced by a factor Cos[theta]^ (3/2), where
theta is the angle to the vertical. However this is a relatively modest
correction and it's not clear whether it explains the whole problem. I published all of the toy models, plus some
variants on the quad and triple models used for the present study and others
that had been in the queue on my models page at http://www.ligo.caltech.edu/~mbarton/SUSmodels/
FFT studies
(Biplab) -- Had communication with Pablo Barriga (of University
of Western Australia) who
now confirmed that his results are now matching with my results for diffraction
losses of various modes in Advanced LIGO.
Earlier, in some cases, he was getting numbers contradicting my results
that the actual(FFT) diffraction losses are more than what one can get from
simple 'tructated Gaussian' approximation. The problem
was traced down to improper choice of window size and resolution which was
affecting his results especially for higher order modes.
AdvLIGO seismic isolation modeling
(Sany Yoshida) Made an e2e box to
test the ABCD (sate space) matrix provided by the Stanford group. This
matrix takes 87 inputs (ground motion x,...etc) and
computes 94 outputs (stage_1_x,... etc). To test the box file, provided white
noise to only one input port keeping all other inputs to be zero. The box file
gives non-zero values at several output ports. The result of this computation
is being examined.
Simulation of 40m Advanced Interferometer
(Monica) Characterization of the optical parameters for one single arm (Dual
Recycled Michelson + XARM): the relative mirror velocity has an order of
magnitude of 1e-7 m/s, the estimated Finesse is 5
times the expected value (1200) for a single arm because of the Power Recycling
gain. Comparison with the analytical prediction and with e2e will be done next.
Test of lock acquisition stategies (operating
point and Common-mode ARM offset reduction): some filters have to be added and
also a better model for the seismic motion taking into account the stack
resonances. Thinking
of new lock acquisition strategies.
AdvLIGO dual recycled cavity modeling
(Biplab and Hiro) Biplab started making a front-end summation-module code in
e2e for the dual-recycled Michelson cavity by incorporating Hiro's
stand-alone code (based on his calculations) into e2e. There are some build-problems
(seems to be unrelated to the code) which we are trying to solve.
(Melody) Assisting Biplab in
trying to figure out his e2e build problems.
(Sany Yoshida) Deepened our
understanding on the basic mathematical expressions for the scalar (plane wave)
model of dual-recycled cavity.
Started converting these expressions to the corresponding expressions
based on the modal model, by replacing scalar parameters (such as mirror
reflectivity) to corresponding matrices.
ALFI
(Bruce)
- Reviewing
and updating E2E web site documentation and Alfi
documentation for the release of Alfi 6.
- Working
on a secondary alternative to starting Alfi via
Web Start for those who may only be able to use Alfi
remotely displayed on an X server.
(Melody) Continuing with fixing the Problem Reports (PRs). Working
on PR 474: view all windows in a miniature mode. Currently working on a
better algorithm to display the windows.
Data Analysis Activities (Lazzarini)
Chatterji:
Continued development of QMon, a
DMT version of the Q Pipeline.
Reviewing proposed work plans for a planned PRD publication detailing burst
search activities within the LIGO/Virgo joint data analysis working group.
Mandic:
I worked on the paper examining the accessibility of the pre-Big-Bang models
of stochastic GW background to LIGO. The paper is nearing the point where it
could be submitted for publication.
I am also preparing to calculate the long-term H1-L1 coherence (in DARMERR
channels) using the LHO cluster. The goal is to do this at high resolution
(1e-3 Hz) and search for the 1 Hz and the 0.25 Hz lines, observed by Mike
Landry and others.
With Peter Shawhan, I started preparing for the
hardware injections.
Shawhan:
- Helped
SURF students Sarah Caudill and Sebastian Cassel
with final versions of SURF reports.
- Committed
new LAL code to handle segments and segment lists.
- Wrote
a program to apply vetoes for inspiral analysis.
- Major
effort to review StackSlide pulsar analysis,
including face- to-face review sessions with Greg Mendell
and Mike Landry (visiting from Hanford) and Teviet
Creighton and Phil Willems.
Sutton:
My main focus this week was developing and testing Maria Principe's network
simulator codes for modelling bursts searches. The package is now fully functional, though
it could still use some refinement and optimization for speed. We used the simulator to reproduce the
network false rate and efficiency results for the LIGO-TAMA S2 analysis. We're now coordinating with Ray Majumder and Cannon at UWM to model excess power searches,
as another test of the package, and also to provide guidance for their S4 and
S5 analyses.
On the side, I wrote a matlab script to compute
the efficiency of the S3 LIGO-only bursts search in terms of the SNR an optimal
filter would see (instead of the traditional hrss). This is intended for the S3 bursts paper
Lindy Blackburn is writing.
Weinstein:
- careful
reading of Chad's
ASI Veto paper for Amaldi
- review
of final mods to S2 BBH paper
- review
of proofs of S2 BNS paper
- Working
with Lisa on ringdown search, calculation of
peak strain from energy conservation.
- Working
with new students Drew, Pinkesh and Caryn on starter projects.
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS
LDAS has been shown to work successfully under Solaris 10 (PR#2896) and Fedora
Core 4 (PR#2897). The remaining packages that had compilation issues after the
full rebuild of /ldcg for both Solaris 10 and Fedora
Core 4 have now been resolved. These included the building of emacs 21.4a and gnuplot 4.0.0.
The building of acroread in /ldcg
for Solaris 10 has been removed as it is now provided in /usr/sfw/bin.
The building of xemacs for both Solaris 10 and Fedora
Core 4 has been removed since emacs has been
successfully compiled for Solaris 10 and is installed by default for Fedora Core
4.
I have tried without success to recreate crashing of the frameAPI when the frame output
directory has been removed (PR#2886). This test was only done on a tandem (2 box) system. Later today, I will try to reproduce the
problem on the development system.
Incorporated functionality to support TclGlobus
into the genericAPI so common code could be used for
both the controlMonitorAPI and the under development managerAPI changes to use GSI sockets.
The controlMonitorAPI server and clients now
support authentication and data transimisiton using TclGlobus. This functionality is now under development
within the managerAPI.
System and Integration tests were performed on LDAS version 1.7.45. A few
changes were made to the test scripts to allow proper execution under Solaris
10 and Fedora Core 4. Results of testing have been added to CVS.
TCLGLOBUS
Completed all TclGlobus unit
tests on Solaris 10 and Fedora Core 4 with GCC 3.3.6 as well as Solaris 9 and
Fedora Core 3 for backward compatibility. TclGlobus CVS has
been tagged with 0.3.0 release. /ldcg/lib contains TclGlobus 0.3.0 shared libraries for LDAS main development
on the LDAS-DEV system. Currently working on building the RPMs
for this tagged version.
TclGlobus 0.3.0 online documentation has been updated
with the latest information regarding this release.
OSG/GRIPHYN/IVDGL
(Inspiral work flows on OSG-ITB)
Obtained replacement components for condor_submit_dag
and dagman from the Condor support team for a bug
related to false DAG cycle abort. Installed these for testing on Verruca.
Assembled VDS binary and script components from the vds-worker-package for VDS 1.4.x release candidate 2.
Created a web page for UWM and PSU systems engineers.
This page is served from http://osg-itb.ligo.caltech.edu/Inspiral/
Mods_for_the_LIGO_Inspiral_pipeline_w_Condor_6.7.7_OSG.html
Attempted to test gencdag (Pegasus Planner) from Verruca but LDAS infrastructure required by Duncan Brown's
components is not available due to changes made by Stuart Anderson on Wednesday
September 29.
(GUMS and PRIMA configuration)
Created an OSG Twiki page "LIGO Priviledge Use for OSG" to provide information for other OSG VOs that want to support LIGO VO users on their CEs (compute elements). Sent the URL to
an OSG project manager for publication on the OSG Twiki
site.
(On-going monitoring and systems administration)
Creating file systems on 8 new hard disks added to the LIGO-CIT-ITB cluster.
NFS mounted /usr2/shared/app and /usr2/shared/data on all Worker Nodes. This results in an additional 1.6 TB of
storage for supporting OSG users.
Left /usr1/shared/tmp NFS mounted on all Worker Nodes as that location has a
cache of the Inspiral_pipeline data which is
optimized for OSG testing of Inspiral-dag.0 without requiring the two hour pre-fetch
of data from RLS.
Provided text to the OSG public relations group at Fermilab to be used in a poster at the Super Computing
Conference in November.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Finished
cleanup of all RLS entries at CIT.
All entries are now syntactically correct and at least plausible
semantically.
- Got
back to work on cleanup of /archive, getting old files into the correct
location.
- Installed
2 port KVM switch in Powell-Booth.
- Participated
in Solaris 10 installation on ldas-cit (gateway)
and dataserver-cit and
reinstallation/configuration of many services.
- Patched
ldas-cit and dataserver-cit
to SAM-QFS/QFS patch 4.4.2.
- Helped
with getting fibre channel devices back on line
at LLO after they were moved.
(Stuart Anderson)
- Started
upgrading LDAS-CIT to Solaris 10 and FC4.
- Upgraded
SAM-QFS at CIT to version 4.4.2.
- Upgraded
ldas-sw to Solaris 10.
- Investigating
Solaris 10 security settings.
- Working
with Sun on SAM-QFS mutli-threaded mmap application issue with the /proc filesystem.
MIT
(Keith Bayer)
- Continuing
to troubleshoot nfs cluster bottlenecks.
- Setup
several accounts on ldas-grid.
Livingston
(Igor Yakushin)
- LDAS
moved downstairs. It took 3 days: the system went down on Monday afternoon
and came back on Thursday afternoon. At first glance, everything seems to
be working.
(Dwayne Giardina)
- Ordered
replacement disk for last bad disk in T3-13 (spare).
- hdb failed in node28, replaced
with new disk. this
disk is still under warranty and will be returned.
- Returned
two disks (from nodes) that were still under warranty; awaiting
replacements.
- LDAS
equipment move and ensuing troubleshooting of various problems encountered
when systems were brought back up.
Hanford
(Ben Johnson)
- Installation
of the 22 Ton Liebert is commencing today.
- A
second file in the past 9 days was found to be published with the wrong
md5sum. This seemes correlated with errors on
the T3 units. Investigating...
- Continuing
to work with Sun on the L700 import/export problem.
- Replaced
power supplies in two previously supplyless
nodes. The final node of this pair will come online when sufficient
cooling has been restored to the room.
- Continuing
work with IP Filters. I believe I have recreated the tcpwrappers
ruleset on gateway@LHO;
though I can't install it on that server until it is upgraded.
General Computing (Wallace)
MIT:
(Keith)
- Installed
/ configured laptop for postdoc
- Investigated
e-mail troubles
- Created
gc account for new grad student
- Ordered
matlab toolbox for grad student
- Investigated
MAC laptop being dropped from wireless
- Working
with Ken on his x64 XP to create PDF documents.
Livingston:
(Dwayne)
- Assisted
Janeen Romie with
printer setup.
- Assisted
Bonnie Wooley with updating some html documents.
(Shannon)
See Livingston Report
Hanford:
(Christine)
- Network
usage can be seen at http://www.ligo-wa.caltech.edu/~christin/mrtg/198.129.208.1_198.129.77.10.html
- The
above mrtg graph is not showing all the
bandwidth being used. I'm still
investigating.
- The
media converters needed to complete the 10mb/s backup network circuit from
Amerion to ESnet in Seattle were
delivered on Tues. Amerion and ESnet tested the
circuit through the Westin building in Seattle,
but were unable to get a link through to PNNL in Richland. Testing and turn on of the circuit
continues today. At a yet to be
determined time, the primary GigE circuit will
have to be turned off to completely test the 10mb/s backup network.
- Helped
a user map network drives on WinXP.
- Rebuilt
a Win2k computer three times, still installing application software. A photo card reader attached to the PC
corrupted the Win2k system files when the photo card was put into the
reader upside down. Unfortunately,
it took me three tries before I realized the problem.
CIT:
(Mike)
- Upgraded
Flexlm Licensing server for Ansys.
- Upgraded
the PDMWORKS Vault for Solid Works.
- Went
around updating Symantec Anti-virus software to version 10.0. The old version 9.0 has problems
updating. We were able to get West
Bridge and Wilson
House done. Christian gave me a hand with this.
- Finished
up burning DVD's of old NTSRV ghost images.
- Worked
on a DCC issue with Antares. Users could not
connect to the database. This was
because the database needed to be compacted, debugged and then I had to
reboot the server.
- Spam
filters: continued work on the spam filters.
- Ran
network cables from Bridge Annex server room to across the hallway to move
servers to this area to power up additional servers. This was a big job pulling these cables
due to the obstacle course I had to go through.
- Other
misc. user support.
(Veronica)
- LSC: Most time was dedicated to working with
the MIT ecommerce provider to finalize the online payment application for
the November meeting. We added more
payment options, which caused an error message that required
troubleshooting on the provider's end.
The application has been integrated into the website and is in the
production mode. Posted updates to
the meeting's website. Updated the
database of the LSC publications.
Posted several new papers at the website of the LSC-reviewed
papers.
- LIGO: Website updates. Roster database updates. Dealt with an issue of a group of DCC
processed documents not accessible at a public search webpage. Ran the troubleshooting utilities but it
didn't seem to resolve it. With the
new system coming up soon, it was decided to find a temporary workaround
rather than invest much time and effort in fixing this issue.
- Project
Science: Last-minute updates to the
website of the upcoming workshop.
It will run Oct 2 through 6.
(Christian)
- Dan Kozack: Configured new laptop with the standard Ligo image.
- Kent
Blackburn: Configured new laptop with the standard Ligo
image.
- Linda
Turner: Configured new laptop with the standard Ligo
image.
- Wilson
House: Updated workstations and laptops to Norton 10.
- W/Bridge:
Updated workstations and laptops to Norton 10.
- E/Bridge:
Updated workstations and laptops to Norton 10.
- Working
on setup and configurations of a couple of new desktop machines.
(Larry)
- Still
working things out on the SUN maintenance contract. There were a number of
different issues at CIT on how the contract should be issued. Hopefully, it is all clarified and we
should be able to get it through the system. Made a number of misc. orders for
different people. It looks like we will be ordering a few more
workstations for the programmers.
The Dual Core units are still on back-order.
- Assisted
Ed C. with a number of property issues. Mainly, just tracking items down
and getting them tagged.
- Assisted
Mike in getting some cables run to room 19. Also, arranged to have the
electrical shop run a power cable over to the room for us. Getting things
through the ceiling to the room is a difficult process.
- Installed
a couple of computer systems and delivered a number of items to different
people. We've been able to get a number of CRT monitors swapped out with LCD
units.
- Spent
a number of hours going through mail logs to get some issues cleared
up. This information was used to
track down the source of a duplicate e- mail issue and to verify that some
messages had not made it to the mailserver and
were not lost in the filtering system.
- Setup
a couple more new user accounts. Still getting SURF students checked out.
- Began
installing equipment into room 19. This included setting up a couple of
new racks.
- The
usual user support.
Mail Statistics for Sept. 22-28, 2005
|
Mail Statistics
|
September 22-28,
2005
|
|
Rejected Messages
|
19,790
|
|
Virus Messages
|
1,992
|
|
False Positives
|
13
|
|
Accepted Messages
|
15,368
|
|
Total Messages
|
35,158
|
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO and
supporting R&D
Systems and Management
from Dennis
Coyne
See also:
AL Systems web
page
AL Systems email archives
Records of Decision or Agreement (RODA)
See also the RODA status web page
- nothing
significant to report
Requirements
- DCN
E050036-00 signed to release M030162-A, a revision of the UK Scope
document.
Interface Issues
See also the "Interfaces" section of the AL Systems web page
- nothing
significant to report
Systems Design/Support
- Verified
by analysis that gravity induced sag on the test masses will not be a
problem; for details see T050184-01
Vacuum Compatibility & Preparation
Residual Gas Assay (RGA)
See also the Vacuum Bake Lab
Bob Taylor
- Lee
Cardenas and I have been cleaning some of the Quad tooling and parts for Calum.
- I
have built and repaired 10 Hybrid OSEMs for the
Quad and I am in the process of wiring them to their cable harnesses.
- On
Monday I installed the new Temperature controller on the big air bake oven
and yesterday I programmed it.
- Today
I have begun the first checkout and bakeout of
the air bake oven at 70c. for 48 hrs. , I will do
the bakeout in three steps 70c, 120c, 250c. Then Helena and I will run the qualification
tests.
- I
have ordered the coax connectors from Acu Glass
for the electrostatic drive.
- I
have begun repairs on oven "C" witch has bad roughing pumps.
(The pumps are on order.)
High-Irradiance, Contamination-Exposure Cavities
Lee Cardenas, Liyuan Zhang
|
Cavity
1.
(Location)
|
Material/Item
|
Start
|
End
|
Comments
|
|
Cavity #1
2.
(OTF Lab,
Bridge)
|
MMG nickel plated Nd-B-Fe magnets (Helena Armandula,
SUS )
|
~6/8
|
TBD
|
No Change
Cavity re-alignment is in progress due to power drop and oscillation.
~2 more weeks to
completion
|
|
Cavity #2
(OTF Lab, Lauritsen)
|
NA
|
NA
|
NA
|
No Change
cavity is close to
being ready for samples
|
|
Cavity #3
(OTF Lab, Lauritsen)
|
plan to introduce
samples tomorrow:
OSEM Flexi-circuit cable, qty ~ 45
(Helena Armandula, SUS)
supplied by Univ. Birmingham
(Stuart Aston)
|
~6/10
|
~9/10
|
DuPont Flexible Circuits. The whole
part to be constructed of 'flexi' i.e. no 'rigid' sections. (Stuart Aston,Univ.
of Birmingham, SUS/UK
subsystem)
- Start Laminate: Kapton (LF8515)
(document link: http://www.dupont.com/fcm/products/H-73244.pdf
Coverlay (x2): Kapton
(LF0110)
(document link: http://www.dupont.com/fcm/products/H-73245.pdf
DuPont Pyralux Series - Kapton /
Acrylic Adhesive system.
(document link: http://www.dupont.com/fcm/products/H-73246.pdf
--------------------------------------------------------------
OSEM
emitter & photodiode 40 of each, (Dennis Coyne, SUS
) Test has been completed. Results to be posted by Liyuan
Zhang soon.
|
|
Queue
Priority 1
|
2 Cleaned 50ppm
transmission mirrors, 1 in dia., REO coated --
|
TBD
|
TBD
|
witness samples
for the LHO vertex volume (added in 6/29/2005 vent)
|
|
Queue
Priority 2
|
Stepper
Motor (Riccardo DeSalvo,
possible SUS or ISC use)
|
TBD
|
TBD
|
3.
Stepper
Motor sample had been placed into Cavity #1: Power dropped from 175 mW to ~25 mW after introducing
the stepper motor sample, and continues to decrease. It is very hard to keep
cavity locked. The stepper motor may have contaminated the mirrors. Will
re-test when a cvity becomes available again.
4.
To be rebaked soon using the self-heating capability of the
stepper motor (not just the oven heater controls)
|
From: Rolf Bork rolf@ligo.caltech.edu
- The
ADC/DAC modules for the quad controls arrived on Monday. I only had a few
hours yesterday to start work on the software drivers for these PCIX
cards. I got as far as being able to initialize the ADC, trigger it, and
read some samples. The hope is to have the ADC drivers to a point by the
end of next week that we can start some noise/performance measurements on
them.
- Jay
and I are working on the cost estimates for the Lasti
CDS systems, with an initial estimate out today or tomorrow. A document
will follow which further describes the CDS systems in the estimate.
- I
placed an order yesterday for the PCIX expansion chassis for the quad controls.
Since in-house developed I/O modules and a serial uplink to the host
computer (as suggested by the AdvLigo CDS
meeting) are at least a year away, it was opted for Lasti
to try and do something similar that is commercially available. This PCIX
expansion 4U rack mount unit has 7 PCIX slots. It connects back to the
host using a PCI express serial link (4 lanes at 2.5GHz full duplex/lane),
and a PCIexpress card in the host. To the
software, it will appear as if the I/O cards are on the internal computer
PCIX bus. At present, this will allow us to mount the I/O chassis and
cards 10m from the host computer. Fiber
links will be available in a few months to extend the range. The host
computer we are planning to use has one 4 lane and two 16 lane PCIe slots, along with a couple of PCIX slots for our
network cards.
Seismic Isolation
From: Ken Mason kmason@ligo.mit.edu
Advanced LIGO Seismic Structure Procurement Status
|
Assembly
|
Status
|
|
|
Top Assembly Components
20007970-A
Stage 0 Assembly
2000795-A
Stage 1 Assembly
20007825-A
Stage 2 Assembly
20007825-A
|
RFQ complete, awaiting bids. Quotes due 9/30.
RFQ complete, awaiting bids. Quotes due 9/30.
RFQ complete, awaiting bids. Quotes due 9/30.
RFQ complete, awaiting bids. Quotes due 9/30.
|
|
|
Stage 0-1 Spring Assembly
20007878-A
Stage 1-2 Spring Assembly
20007890
|
We have recieved the design for
the blade modifications from ASI on CD's. We are currently checking the design
and analysis and will meet with ASI to review. We will be creating
fabrication drawings from their models. Fabrication drawings for the blade
springs are complete.
Maher Limited holding maraging steel for blades and
flexures
|
|
|
GS-13 Pod Assembly
20007810-A
L-4C Pod Assembly
20007820-A
STS-2 Pod assembly
20007941-A
|
Geophones, seismometers and lockers are in house.
RFQ complete, awaiting bids for vacuum housings. Quotes due 10/16
RFQ complete for machined components. Quotes due 10/16
RFQ required for internal pod harnesses.
|
|
|
Stage 0-1 Kinematic Lock
20007941-1-A
Stage 1-2 Kinematic Lock
20007941-2-A
|
Tooling design complete.
RFQ complete, awaiting bids. Quotes due 10/21
|
|
|
Stage 0-1 Actuator Assy.'s
20007966-A
20007967-A
Stage 1-2
Actuator Assy.'s
20007968-A
20007969-A
|
Tooling design complete.
RFQ complete, awaiting bids. Quotes due 10/21
|
|
|
Stage 0-1 Standoff Pin
Stage 0-2 Alignment
Tower and Washer
Stage 2 Keel Plate Alignment
Tower
Blade Pre-Load Tooling
Blade Calibration Fixture Modifications
LASTI Test Stand and Spreader Bar
|
Solidworks part files exist for
the standoff pin and alignment towers. They will require a dimensioned
drawing and checking prior to soliciting bids.
The blade pre-load tooling and calibration fixture tooling will require
redesign following the redesign of the blade springs by ASI.
Purchase order for test stand issued to Southern Enterprises. Delivery to MIT
by 10/16
|
|
Suspension
From: "Mark Barton" mbarton@ligo.caltech.edu
This week I spent investigating the mystery of why the quad pendulum controls
prototype was unstable in pitch. The suspicion was that we were somehow not
correctly allowing for the stiffness of the wire. The Matlab
model of the suspension neglects the wire stiffness and assumes all the pitch
restoring force is gravitational. To get a suitably low fundamental pitch
frequency under these assumptions requires that for each mass, the attachment
points for the wires coming down from above be about 1 mm above the COM, and
those for the wires continuing down below be about 1 mm below the COM. To
maintain this frequency with stiff wire, the attachment points have to be
adjusted in the unstable direction by relatively large amounts, of up to 5 mm
for the upper stages. Clearly, small errors in the theory can be the difference
between success and failure.
The theory we were using was given in a paper Cagnoli
et al., 2000. To check it I used my Mathematica toolkit to analyze a large number of toy
models, including one-, two- and four-wire simple pendulums, and a double
pendulum with the top mass hinged about a transverse axis and the bottom mass
suspended by four wires. Calum and I also built a
two-wire pendulum in the lab. It turns out that we were applying the
corrections correctly for the most part, except in the top two stages where the
wires are further apart transversely at the top than at the bottom. In such a
case, the flexure correction has to be reduced by a factor Cos
[theta]^(3/2), where theta is the angle to the
vertical. However this is a relatively modest correction and it's not clear
whether it explains the whole problem.
I published all of the toy models, plus some variants on the quad and triple
models used for the present study and others that had been in the queue on my
models page at <http://www.ligo.caltech.edu/~mbarton/SUSmodels/>
From: Janeen Romie romie_j@ligo.caltech.edu
Advanced LIGO Suspensions
Working with Helena and Caroline on documentation required for the
Ribbon/Fiber/Ear PDR on Oct 19th. Documentation is due on Oct 5th.
From: ctorrie <ctorrie@ligo.caltech.edu>
Quad Controls Prototype
The single chain quad was still successfully suspended after 48 hours. While
trying to install the osems anther two LED's failed.
At this point we decided to stop and start taking the suspension apart to
prepare for the assembly with the reaction chain.
After discussions at the weekly SUS meeting and a subsequent meeting in the
lab it is believed that some changes need to be made to the "GEO box"
to offer more protection to the LIGO LED's. Bob Taylor is going to fix the
broken osems this week. We also discussed the wiring
and decided to make changes so that it everything will be the same as for
LASTI.
The fully assembled quad plus reaction chain should be suspended by early
next week.
With help from Bob Taylor and Lee Cardenas we have started to clean the
various tooling assemblies and to clean and bake the spare parts of the quad
suspension.
2nd Structure for Stanford
Lee and I have been preparing the second structure for LASTI. Everything
should be ready in good time for Tim's visit, see below.
Quad Noise Prototype
From next week the hosting of the design meetings, on a Monday, will be
taken over by RAL. Over the last couple of weeks noise discussions have
dominated these meetings.
Installation Fixtures
I now have a set of drawings from Oddvar and a
price estimate from Mike Gerfen in CES. The next step
is to hold a meeting with Dennis, Ken and Mike to discuss a few aspects prior
to starting cutting metal. From Norway,
Oddvar has been sending information and drawings to
support this effort.
Visits
Norna is visiting on Tuesday to help with the
assembly of the quad and to discuss the "flexure point theory". Tim Hayler is visiting from RAL for 10 days from the 10th of
October to help with the resonance tests on the second structure and to run
through the "3 and 1" assembly procedure.
From: Ken mailand kmailand@ligo.caltech.edu
Chiller flow meter mounting brackets will be complete, and sent to Cheryl at
LHO tomorrow 9-29.
I have reviewed transport table detail drawings for Calum.
I did an OMC Algor for Mike Smith, and
demonstrated the use of the program to him.
From: Helena Armandula <ahelena@ligo.caltech.edu>
The bonding of magnets to flags and holders using indium are failing often.
Rework takes a long time because the surface preparation is quite intricate.
Also, during cleaning, the nickel plating on the magnets gets affected by the
hydrochloric acid solution causing the coating to bubble and separate from the
magnet material.
So, I have been investigating the possibility of using Sodium Silicate as
binder.
Initial tests are encouraging. I have been looking at different (solution)
concentrations and expediting cure by baking.
One of the bonds, the only one I handled after bonding, is strong enough to
withstand a manual pulling, this is a good sign since the parts are not flat,
at the edges, I can see light between the bonded surfaces.
From: Jay Heefner jay@ligo.caltech.edu
AdL Quad Controls
Modified one channel of the GEO PD amp to try to reduce
the number of LED failures. The present design has the anode of the LED
tied directly to the +15V supply so that any inadvertant
connection of the OSEM head or touching of the pins can cause large currents to
flow through the LED. The modified design places a 200 ohm resistor in series
with the supply line and limits currents to less than the 75mA max rating of
the LED. Other component values in the circuit were also modified to compensate
for the addition of the limiting resistor.
System layout and wiring diagrams for the LASTI version of the controls are
90% complete. Completion is pending acceptible
performance tests of the PCIX ADC and DAC cards that we received this week.
Jay will be in Birmingham next week for
design discussions with our UK
partners.
AdL SEI
- 6
more GS-13 pre-amps have been completed and sent to Stanford. In addition,
we fabricated, tested and shipped an amp of our own design for test. If it
works we will be able to use these amps instead of buying GEOTECH amps and
modifying them.
- LASTI
ISI controls system diagrams are complete pending successful tests of the
PCIX ADC and DAC boards.
LASTI Controls
- Cost
estimates for the future LASTI controls including SUS, SEI and pondermotive experiments are in progress.
Core Optics
From: Bill Kells <kells@ligo.caltech.edu>
Hiro has completed an independent check
calculation of the "full ifo" PI
(parametric instability) feedback field. It agrees with what I had calculated.
This seems to confirm a significant discrepancy with the original Braginsky/Vyachanin theory expression (which has been
always used since, eg, by Blair). We will be trying
now to sort this out with Vyachanin.
Also I've been working with Phil on the thermal heat up scenerio
for AdL. That is, what is the best strategy for cold opitcs ROC so that they perform reasonably well on the way
up to full power.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
A couple of quotations for modular in-plant offices and clean rooms were
received that would duplicate the setup currently at LLO. Whilst the price
of the enclosure has not changed much, associated items such as labor and
freight have.
Auxiliary Optics
No report this week.
Other Laboratory R&D
Juri
I worked on the tilt sensitivity of our cavity in order to understand the
discrepancy between the theoretical prediction and the real data. The flatness
of the input and folding mirror seems to be a crucial issue in understanding
the experimental data behavior. Using the actual map of the input mirror (as
well as an ideal saddle shape mirror) the results of the FFT simulations are
getting closer to the experiment. With this configuration we can explain a
factor of 1.5-2 in the tilt sensitivity respect to the perfect flat input case.
The analysis with the actual folding map is in progress.
Chiara
I made the calibration for the two accelerometers that I have to use in the
measurement of the transfer function of the system and I worked on the
electronic set up. I put both the
accelerometers on the top plate in order to evaluate the twist mode of the
table.
I worked also to prepare the maraging steel wires for the hardening process.
Valerio
I'm still working on the SimMechanics model of the
HAM-SAS suspension. Thanks to the help of Virginio
Sannibale, we have a better understanding of the
simulation tool and we are probably going in the right direction to solve the
inconsistencies of the model. We have also contacted Mathworks
because we are going to buy three licenses of the blockset.
These new licenses will be linked to the existing MATLAB Caltech licenses.
Maria Paola
I spent the last week preparing my presentation and writing my final report.
My next and final step is to start thinking about how to control the motor,
using RCL filters and FET switches. Initially I just have to test switches
connecting them to the coils of the motor and injecting current into the coils
through them, and that's what I'm doing now, together with the fix of the whole
system, since sometimes something doesn't work anymore and I guess I still have
problems of bad connections and soldering. Afterwards, I will try to make the
motor work with 2 FET switches in order to have current and then steps in both
directions, and eventually I can try to connect an RCL filter and see what happens
when the frequency changes.
This is the last week I'm going to spend here in US, and I'm on the whole
satisfied of this work, not so much for the results I have achieved, but surely
a lot for all the practical things I've learnt to do.
I want to thank Riccardo one more time for his
constant help and for his contagious cheerfulness and optimism, and all of you
for making this
wonderful holiday unforgivable for me.
Ilaria
I completed simulations of spring box with Ansys
and now I’m working on transfer function of the IP. Unfortunately the
results Ansys gives me are not in the range I chose,
so harmonic frequency does not match the graph. I`m going to send an e-mail to Ansys to solve the problem.
For additional information about this report, contact Stan Whitcomb or Phil Lindquist