Weekly Report for
Week Ending September 15, 2005
The LIGO Executive
Committee Agenda for Monday September
19, 2005 will be:
(Meeting time: 10:30 am Pacific Time)
- Announcements
- Comments on Weekly
Report
- LSC Issues (Saulson)
- LIGO Lab Operations
- Administration
(Lindquist)
- Sites (Raab,
Zucker, Shoemaker)
- Commissioning
(Fritschel), Detector (Coyne)
- Campus Research
Facilities
- 40 Meter
(Weinstein)
- TN, (
Libbrecht)
- LASTI (Shoemaker)
- Data Analysis
and Computing (Lazzarini)
- R&D and Advanced
LIGO (Shoemaker)
- CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION
AS NEEDED
Special Items:
Special Announcements:
Weekly Report Highlights
LSC Issues (Saulson)
No report
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
- Received
modifications to MOUs as requested by the Review
Panel for the following: University
of Texas at Brownsville,
Trinity University,
Columbia University,
Northwestern University, Southeastern Louisiana University, Pennsylvania
State University, and IUCAA.
Non-LSC MOUs (Lloyd)
SITE TELECONFERENCE (Lindquist)
- A
site teleconference was held Thursday, September 15, 2005. The following issues were discussed:
- Budgetary
Issues—budgets are being prepared for FY 2006. We will need to identify what hardware
budgeted in FY 2005 was procured or fabricated, what has not been
purchased but will need to be carried forward into FY 2006, and what will
never be procured. We must also scrub
FY 2006 procurements. A number of
people are currently involved in this review.
- There
are no open action assignments. The
list of assigned actions updated through September 01, 2005 will be found Here.
PROPERTY MANAGEMENT (Chargois)
>From: Ed Chargois <chargois_e@ligo.caltech.edu>
- Nothing
significant to report.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
- Drafted
a first-cut for the contract between LIGO-DCC and FileHold
Systems, Inc. for attaining Synergy 4.0 and consulting services for the
migration of the current DCC system and setup of the new system.
- Typed
in all the abstracts for electronic publications from 1951 through
1999. This represented 150
abstracts. Will hopefully finish
the abstracts for the remaining electronic publications--2000 through
2005. Following the electronic
versions, will pull hardcopy publications that have an abstract and add
those to the database.
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- Working
on determining, which "P" documents in the DCC have 'abstracts'
included within the document. These
abstracts are then being entered into the database by Linda.
- Assisted
in sending out two RFQ's for the Fabrication for
Advanced LIGO Seismic Isolation System.
- Assisted
in sending out Time and Material Price Contract for the relocation of LDAS
@ LLO.
- Total
volume of handling incoming/outgoing packages was much higher than normal..
- Activity:
|
Week Ending
09/15/05
|
In
|
Out
|
|
Packages
|
33
|
19
|
|
Faxes
|
27
|
25
|
FINANCIAL SYSTEMS (Cronin, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Issued
the order the purchase of the trailer for LLO and the corresponding wire
transfer.
- Working
on the new order for the PBX telephone system for LIGO Hanford which is
being completed today.
- Working
on reducing the number of blanket purchase orders that are soon to expire
at the end of this month. It looks like we may be closing about 6 blanket
orders that had very little activity within the last year. I have
confirmed that all of the six vendors do accept Caltech's mastercard, and also one time purchase orders. It
looks like we'll only be looking at extending the MCI blanket at this
time.
- Working
on the new subcontract for the Time and Material contract with Excel for
LLO.
- Working
on coordinating the renewals of the subcontracts expiring
this fiscal year end.
- The
deadline for any FY2005 orders to be encumbered this fiscal year is
tomorrow, Friday, September 16, 2005.
>From: Florence Kaufman <fkaufman>
- Indirect
Costs which had improperly been assessed on SURF student charges and
participant support costs have now been reversed.
- Prepared
a spreadsheet showing FY06 budget numbers compared to FY05 budgets at a
summary level.
- Prepared
and sent out reports for the DIA Award, Conference Account at Hanford, US-India
Award, Low Noise Award, MIT Grid Award, Visitor Award, and the
discretionary accounts at Hanford and Livingston.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence.)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone
<gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- The
low bidder for the LLO
Science Education
Center, Cangelosi-Ward, has revised his bid as a result of the
revised specifications and drawings received from the architect, Eskew-Dumez-Ripple.
The proposed contract will be forwarded to the NSF for approval,
with a letter explaining the cost growth and budget sheets showing the
re-distribution of the Outreach funds.
- Excel
Corporation received their contract for the relocation of the LDAS
equipment at LLO.
- A
travel trailer was procured for LLO due to the lack of available hotel or
motel space in the Baton Rouge
area due to Hurricane Katrina. This
trailer is temporary, and will be turned over to the GSA as surplus
equipment when rooms become available.
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
- Processed
the paper work for two (2) new/revised trips. At this time there are ten (10) trips
completed or in the works but are awaiting the necessary paper work to
enter the P-Card system.
- Due
to Hurricane Katrina there were several trips to LIGO/Livingston that were
either completed or were in the works and needed to be canceled or
rearranged. All tickets were either
refunded or applied to other trips and all car and hotel reservations were
released. I've been attempting to
assist Janeen Romie
with temporary housing until her Escrow closes but as of this writing the
hotels in the Baton Rouge
area are still not accepting any reservations due to the Louisiana
Attorney General's order that Evacuees are to be housed before all
reservations.
- Completed
twenty-six (26)Expense Reports and there are
seven (7)reports yet to be done. I
continue to contact travelers who have outstanding Expense Reports (more
than one (1) month old) to ask for their cooperation in sending me their
receipts so that these can be closed in a timely manner. Presently there are four (4) reports
more than thirty (30) days old. I
have two (2) reports awaiting signature at this time. Worked on copying and recording all the
expense reports completed last week to be sent to Travel Audit for final
auditing and payment.
>
>Dorothy Lloyd
- Monday
and Tuesday I processed two weeks worth of invoices (all received while I
was on vacation) for payment and followed up on problems. Updated contract
invoice log for the period July 18 through August 26.
- Processed
requisitions for standard purchases and payment requests. For more detail
see Cost Schedule Control Systems report by Ruth Brambilla.
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
PROPOSALS and REPORTS (Lindquist)
Additional material for request for supplemental funding for Operations for
FY 2007 and FY 2008 is in process.
DCC Steering Committee (Lindquist)
Purchase Orders fo new
document management software, support, and the hardware to put it on are in
process.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
Nothing
significant to report this week.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of Commissioning Activities at LIGO Hanford Observatory (Landry)
Some commissioning highlights
are linked below:
4K IFO
- there is no ezcableservo: the
4k REFL1 and REFL2 paths were rephased via hard wire. The link includes
some nice cookbook points for doing this, including pitfalls.
Additionally, SPOB was rephased, too
- a glitch
in the TCS power on the Y arm was coincident with a significant range
drop; this may or may not be causal
- the
IOO WFS1 head was replaced
and tuned
- Sensemon, autocals and noise
budget code yield
very similar noise curves and binary inspiral
ranges
- [this
bullet entry by Bill Kells, regarding testing of
the ITMX that was removed from H1 in late June - ML] Another week, and another round of ITM07 HR absorption scans.
The results quoted so far have been determined to be stable under changes
in pump beam chopper fequency (= thermal
diffusion length). Although on the low side, the scans we have taken,
including a fair sampling of "hot spots" could be interpreted to
be responsible for a large portion of the H1 thermal lensing.
What we can say is that the hot spots we have identified do contribute a
dominate fraction of the average HR surface absorption. Our calibration
is, after all, too uncertain to conclude the true absolute average.
Pinning this down will be next. -BK
2K IFO
- the
7.7 New Ireland Papau New Guniea
quake disrupted locking on Friday
- the refurbished laser arrived on Monday. It was installed
successfully on Monday. Losing some power
initially, it was stable and fully
functional by Wednesday.
- ISCT10
was refloated without impacting the binary inspiral range negatively. Pressure
changes causing the table to then drift were attributed to the effect of
opening the door to the table and the subsequent temperature and pressure
effects on the regulators.
DAQ and CDS
- photon
calibrator excitations were added
to frames in preparation for S5
- a
mod to the new timing
system has made it less sensitive to diurnal temperature variations
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
General:
As reported last week and confirmed below, LLO is functioning normally. However
the local housing infrastructure remains strained by the many families
displaced by Hurricane Katrina. LLO has now secured *limited* temporary housing
for mission-critical visitors, and has scheduled a few visits to resume at the
end of the month. Please contact Mike with questions.
We are pleased to welcome Dwayne Giardina as our new network systems administrator. Dwayne
comes from a background in networks and application development at MCI in Mississippi, and will be
working with Shannon and Igor on general computing and LDAS cluster support.
L1 Interferometer (Frolov)
The interferometer's longest lock this week
was almost seven hours. Inspiral range was 8 to 8.5 Mpc during that lock stretch. Day time locking was limited
to short stretches no longer than 20 minutes, likely due to on site digging
(water pipeline to connect our new well) and increased microseismic
motion from Hurricane Ophelia in the Atlantic. This increased ground motion
also caused one of the HEPI systems to trip several times a day over the last
several days.
Other interferometer work this week:
- started the installation of the anti-symmetric port
dust covers. The covers were test assembled on the table to make marks for
the cables and the beam, and to check for interference with other
elements.
- started commissioning of the reflected port active beam
centering system. The hardware, which includes the PZT mounted mirrors and
electronics, was first tested in the llo optics
lab and then installed on the interferometer. Characterization of the open and closed
loop performance is underway.
CDS (Bogue)
- Removed
spurious 'H0' channels from the l1iscepics burt save request. Confirmed that we now can burt restore l1iscepics with
full success.
- Worked
with Mike Fyffe shuffling equipment in the MSR. Because of this equipment move,
l1iscepics, l1hepiepics, l1susepics and l1tcsepics were down for a
while. Worked with Tom Evans to get
the front ends back up and cheery after these machines were brought back
up.
- Installed
an LTO autoloader and 2 raid systems on llo1. These are not yet configured. I am currently testing all of the disks
for the arrays to make sure they are good.
- Because
of the hardware change of control3 (due to hurricane) the CDS matlab licenses were not working. Right now, matlab
is using the GC licenses until I can migrate the
CDS licenses.
- Worked
on a script to automate the control7 login process.
CDS Code Support (Khan)
- Prepared
the documentation for the L1ISC_Network, describing the reflective memory
network loops present in the CDS system.
- Updated
the TCS Servo medm screens for the prepation of the TCS servo implementation.
- Prepared
Stat screens that include hepi tidal settings.
Education and Outreach (Zucker,Thacker)
Discussions with architects
EDR and construction contractor regarding cost reductions for proposed SEC
construction contract.
Site Safety and Security (Riesen)
- Started
Laser/Site safety orientation for Dwayne Giardina
(including laser base line eye exam), and Janeen
Romie.
- A
procedure for getting the LSS server operational after a computer crash
has been written and now resides in the Operator's "How To"
folder on the operators computer.
This is temporary until the new hardware and software has been
installed.
- Site
security camera replacement parts have been ordered and are being directed
to Mike Fyffe.
- Found
no concerns with either laser or site safety this period.
- Volunteered
to instruct CPR/first aid for the American Red Cross 2 afternoons for two
weeks in light of their shortage of manpower after Hurricane Katrina.
- The
HPLF 100 watt laser has not been turned on since Katrina due to manpower
needs with the IFO. A spare 100 watt laser should arrive within 2 weeks.
LLO General Computing (Dwayne Giardina-- Shannon
is away)
Replacement of disk in Harry's laptop not
successful, as image creation on external USB drive failed. waiting on
additional memory for this laptop. will try to create image again after memory arrives. Hopefully can start it
Friday afternoon since it will take several hours.
HPLF, Optics Modeling, Data Analysis and L1 Commissioning (Franzen)
- Tested
the Piezo Jena PZT mirror holders with 2 inch
mirror mounted in the optics lab. Installed them on ISCT1. See the elog for details.
- HPLF
news: Due to the above activities I did not have time to run any HPLF
tests. News is that IPG Photonics has almost finished the 100 W laser
back-up system.
Mechanical Engineering (Spjeld)
- dimensioning
machine drawings for Quad SUS installation jig - finishing redesign of HAM
door removal tool - converting remaining active project files to SW 2005
and resolving errors
LDAS/Condor Sysadmin and Burst Analysis (Yakushin)
Storage/Condor/LDAS admin:
- Got
a quote from StorageTek to help to move tape
robot to the temporary location in the high bay. The most likely scenario
is: StorageTek would remove tape drives and the
extension door from the tape robot, secure the arm, put
the robot on a pallet (which they provide, it has a ramp and holes to
attach the tape robot with bolts). We rent a forklift that can reach all
the way up to the second floor and use it to move the tape robot to the
temporary LDAS location. StorageTek would
reassemble the robot. As a backup solution I am also investigating the
possibility for StorageTek to do a complete move
including a forklift.
- The
most likely dates for the move to the temporary location are Sept 26-28. I
have scheduled StorageTek to come on Monday,
Sept 26 and the nodes to be moved from the warehouse to the site on the
same day.
- Firmware on tape robot have been upgraded to 3.09. Firmware on tape robot drives have been upgraded to
1.35.402.
- Restored
metaserver after the disk failure.
- Got
1020 tapes for S5.
- Spending
time with Dwayne to get him started with LDAS part of his duties. In
particular I'd like him to be responsible for monitoring and replacing all
the disks in nodes and T3s.
- Purchasing
2 year Gold contract for the FastIron 1500
network switch.
- 3
failed disks in 3510 were replaced. No data loss or interruption.
- Stored
partition and disk images of linux servers in
/archive/backup/images to simplify the recovery after a disk failure.
Data analysis:
Working on updating waveburst online infrastructure that was used in S4 to be
ready for S5.
Initial LIGO Detector Science & Engineering (Coyne)
CDS
see also the CDS weekly meeting minutes in the commissioning archives
CDS Software
Rolf Bork
- Revised
Fast ADCU code is complete and installed at LHO. Daniel is going to test
this new software.
- Revised
ADCU software to record excitation channels to photon calibrators. This
code is now running on LHO 2K.
- Revised
ETM code, per Landry request, with additional filter bank for useismic control. This software, along with startup
sequencing software loaded at LLO last month, will be loaded on LHO 4k on
Monday.
CDS Hardware
Jay Heefner
Refl Beam Stabilization
- One
chassis has been tested and shipped to LLO for installation. It should
arrive by 9/15. 2 more chassis are in process for LHO. They should be
ready in 1 week.
- All
of the databases and screens have been completed for H1 and H2.
- The
epics filter module code has been compiled for H1 and H2.
Ben Abbott
LSC
RFPD
- Todd
is stuffing boards to complete the delivery of new RFPDs
to the sites. He has been held up by some components that are
discontinued. The last of them arrived today, and will be stuffed
this week.
Fast Shutter
The second prototype fast shutter was completed this week. It is working well with ~66% attenuation
happening in around 1.2 ms. I will see what can be done to start
reliability testing, and production on this type of unit. ,
ISS PDs:
I've picked up the bodies from the anodizer, and
have begun assembly of the three units that are needed at Hanford.
DMT
no report
PSL
nothing significant to report
4ITM07
GariLynn issued a report (T050178-00) for comment,
with a brief summary of our findings to date regarding 4ITM07, the optic
removed from H1, ITM-X position, in June 2005 due to high absorption. The
document also contains urgent recommendations for further measurement at the
observatory in order to isolate the cause of the absorption.
Helena Armandula
Tested the carrying aluminum case and shipping container of ITM07 to
evaluate the possible contribution of the containers to mirror contamination. The results are reported in T050175-00-D.
TCS
Ken Mailand
Cheryl received a quiet chiller flow meter mounting bracket at LHO and will
set it up this week.
40 Meter Interferometer (Weinstein)
IFO commissioning:
- Osamu
has been working on locking the dual-recycled Michelson with one arm
(DRMI+XARM, YARM blocked), since it should be much easier to lock than
DRMI+DARM+CARM during the day.
- He
believes that the difficulties in acquiring lock are due to a considerable
amount of excess noise on the XARM error signal (with DRMI locked), at the
level of 1e-10 m RMS. After some work, he reduced the RMS noise by factor
10, to ~ 1e-11 m RMS. He estimates that locking the full IFO will require
an additional reduction in RMS noise of a factor ~3.
- There
was considerable MC2 suspension noise around 16 Hz; reduced by reducing
the MC length gain and applying a resonant gain stage in the XARM loop.
Broadband noise and many peaks around 100 Hz also show up in the MCL error
signal, probably due to PSL table vibrations; reduced somewhat be
modifying the XARM loop filters. Many peaks which don't show up in the MCL
error signal, presumably from vibrations of in-vac
components in between MC and IFO (MMT, PZT mirrors).
- After
the reduction in XARM noise, Osamu was finally able to lock the XARM with
a DC offset, switch to the RF signal from POX, smoothly reduce the XARM
offset to zero, and resonate the beam in the XARM
with the DRMI locked. The power buildup was in good agreement with what is
expected from the model (including the arm losses as measured). The lock
was fairly stable and lasted for 11 minutes, despite the trucks going by
just outside. Next: try to do the same with the YARM, and then DARM+CARM.
- Rob
tried "kick & pull" locking Tuesday night. First he locks
the dual-recycled Michelson (DRMI), then DARM (RF signal, no offset) and
CARM (DC signal with offset). Then he turns off (holds) the DC CARM servo
and turns on the RF CARM servo, gently kicks the CARM degree of freedom
and then pulls it back to slow it down, and watches the signals (hoping
that the RF CARM servo will catch and lock). No success, but lots of data
to look at.
- Dan
and Monica are working on developing a noise budget for the 40m (building
on Ryan's summer work).
IFO modeling:
- Rob
has employed his Finesse model to investigate what happens to the length
control signals when the PRC is undercoupled (as
appears to be the case for us). There is no significant qualitative
change, but the signals all get smaller (ie, a
gain reduction). He estimates that the observed arm reflectivity of 85%
(which results in an undercoupled PRC with a
gain of 5 instead of the design of 14) is consistent with round-trip
losses of 200 ppm. Much larger than we'd hoped
for, but not unbelievable.
- Monica
is working on her report for Advanced VIRGO. She'll be in Europe for STAIC and other meetings, in October.
DC detection development:
- Following
suggestions from the 40m team, Mike Smith has modified the ACad drawing of the in-vac
beam paths in the DC readout beamline.
- Mike
has updated the parts list for the DC readout beamline,
and is preparing quotes.
- Alan
has submitted a budget and schedule/milestones for the DC readout
experiment, to Carol & David.
- Mike
and Helena are exploring options for obtaining quality mirrors for our
output mode cleaner.
- Jay
is looking at the signal paths for the output mode cleaner sensing and
control, and is beginning make some detailed drawings.
Electronics, controls:
- Dan
wrote up a how-to document on balancing the coils on our suspended optics
(the ones that have oplevs).
- Dan
is working on implementing a script for suspension diagonalization
(pos to angle and angle to pos) for our mode cleaner optics, using our MC
length and angle sensors. This is important because Osamu has identified
significant amounts of frequency noise and beam jitter arising from our
mode cleaner suspensions.
- Ben
built an analog divider circuit for the CM servo, stuffed, tested and
delivered earlier this week.
- Ben
got all of the RFPD DC signals that are acquired to come via the P2
backplane connectors in the LSC rack, rather than from separate cables from
the PD, in an attempt to reduce 60Hz noise-producing ground loops. All the
seaparate cables are disconnected and tagged.
- Ben
is making a bunch of ISS PDs, including spares
for the 40m. He and Todd are preparing a bunch of RFPDs
for the sites and for the 40m.
- Ben
continues to develop a fast beam shutter, for the sites (S5) and for the
40m. His 2nd prototype starts attenuating the beam in ~1.2 msec.
- Jay
is thinking about how to redo the (currently inadequate) power for the LSC
rack.
- Jay
and Alex are repairing the CPU that we use for the suspension EPICS
monitoring (c1losepics). We currently have a temporary CPU, which is not
configured properly. He hopes to get the repaired system in, in the next
few days.
Lab Infrastructure:
- Steve
says that our maglev turbopump will fail at any
time (it is 15 years old) and is getting quotes for a replacement.
- Our
laser safety glasses disappear at an alarming rate (please return the one
you took!). Steve is investigating inexpensive replacements.
Thermal Noise Interferometer (Black)
We have spent the past couple of weeks double
checking our measurement of the loss angle in silica/doped-tantala
coatings. Our initial conclusion that the loss angle in the
coating is 1.3e-4 stands. This is slightly better than the expected
value of 1.7e-4, but it is within the range of values expected, based on
independent ringdown measurements of the mechanical
Q's of similar samples.
LASTI (Ottaway)
LASTI Weekly
This week the remaining support table and the optics table were removed from
the BSC chamber and we are currently planning on going to vacuum. The new dome
stand support makes working in the crowded high bay considerably easier. Once
we are under vacuum we will continue our final commissioning of the PSL.
Laurent and Rich are currently in Caltech preparing the second triple
suspension for its re-location to LASTI and assisting with the shakedown of the
Quad.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
Weekly E2E Physics Meeting
Sany Yoshida presented his plan of work for SimAdLIGO (Seismic isolation, Triple/Quad suspension, Dual
Recycled Michelson) and SimLIGO (Mode cleaner work,
Violin dynamics) models of e2e.
E2E as Educational tool
Soumya Mohanty of Univ. of Texas
at Brownsville
is interested in using E2E and its GUI interface as an educational tool. Hiro, Biplab and Sany Yoshida supplied him related information and
presentation materials related to such efforts, in particular, at SouthEastern Louisianna Univ.
Advanced LIGO Seismic Isolation
(Sany Yoshida) Continued working on e2e modeling
of AdvLIGO seismic isolation. Looked at the BSC
seismic model (state space representation) provided by Brian Lantz and
confirmed that it can be incorporated in our e2e model. Converted
Brian's ABCD (state space) matrix into ASCII format so that it can be included
in an e2e file.
FFT studies
(Biplab) On request from Ju
Li (Univ. of Western Australia)
calculated diffraction losses for a few more modes. She needs such numbers for calculations
of parametric amplifications. Results
from ordinary FFT with varying resolution and Adaptive-grid method of FFT
calculations are being compared and analyzed.
Simulation of 40m Advanced Interferometer
(Monica) Characterization of the optical parameters for 40m arms is in
progress: The estimation of the 40m relative mirror velocities (XARM and YARM)
is done analyzing raw data of the transmitted light and the Pound-Drever signal at the symmetric port demodulated at 166 MHz.
Two methods of velocity reconstruction are used and then the values obtained
for mirror velocities are inserted in e2e simulation to compare the agreement
between raw data and simulation.
Dual Recycled Michelson
(Sany Yoshida) Started a project
to convert the scalar (plane wave) model of dual recycled Michelson developed
by Hiro to a modal model. On campus of SLU, Ryuta Sasabayashi (a new SLU Master
Course Student) collected related references to understand the basics about the
modal model and dual recycled Michelson interferometer.
Alfi
(Bruce)
- Testing
JProfiler as a tool to enhance Alfi performance in general.
- Researching
and experimenting with graphics options in Java and Alfi
in order to increase the speed of Alfi when
being displayed remotely on an X server.
(Melody)
Continuing with fixing the Problem Reports (PRs). Working
on PR 474: view all windows in a miniature mode. Finished first workable
version of the feature.
Data Analysis Activities (Lazzarini)
Mandic:
I studied the S4 H1L1 stochastic hardware injections. I identified a bug in
the code used to calculate these injections, which introduced a delay in the
injected signal at LLO as compared to the signal injected at LHO. After correcting for this delay, the signal
was successfully recovered.
With Peter Shawhan, we wrote the first version of
the code to be used for the S5 hardware injections. The goal of this code is to
inject the burst and inspiral signals continuously
(injecting zeroes most of the time), using a predetermined schedule file.
I also started working with Lars Bildsten (and
Stefan, Albert and Stan) on calculating the expected stochastic background from
LMXBs.
Mendell:
I have completed and checked into LAL and LALapps,
changes mentioned in last weeks report that speed up the StackSlide
Monte Carlo simulations.
Specifically: 1. changed the SFTclean.* files in
the LAL utilities package to fix a few minor bugs and a make random parameters
variable the last argument to the LALCleanCOMPLEX8SFT function; 2. in the GeneratePulsarSignal.* files in the LAL inject package I
added Dterms as a parameter to the LALFastGeneratePulsarSFTs function so that this now injects
a fake signal onto a band 2*Dterms bins wide (rather
than across the entire input SFT band) centered on the signal frequency in each
SFT, in the same way as is done in LALDemod; 3. updated the StackSlide code to use
the above changes in LAL, and added options to the weightFlag
and testFlag that can speed up Monte Carlo
Simulations. StackSlide users will need to update LAL
next time they update the StackSlide code from LALApps CVS.
Mike Landry and I will meet with Peter Shawhan, Teviet Creighton, and Phil Willems
at Caltech on Sept. 28 and 29, for a two day StackSlide
code review F2F meeting. Progress of the reviews continues to be reported on
this page (with the usual PULG access):
Shawhan:
- Wrote
LAL code to handle segments and segment lists.
- Worked
on revising the "state vector" and "science mode"
logic with Dave Barker, Rick Savage, and Keith Riles.
- Helped
Vuk Mandic with
preparations for S5 hardware injections.
- Reviewed
StackSlide pulsar analysis.
- Modified
SeqInsert to allow server and client to be on
different computers, following discussions with John Zweizig
about S5 DMT configuration.
- Gave
SURF student Sarah Caudill feedback on a draft of her final report.
Yakushin:
Working on updating waveburst
online infrastructure that was used in S4 to be ready for S5.
LIGO Data Analysis System
Software Systems (Maros for Blackburn)
LDAS
The effort of compiling ldas for Solaris 10 and
Fedora Core 4 continues. STLport 5 RC 5 has been
compiled for both Solaris 10 and Fedora Core 4. The lam, xerces
and Object Space libraries have been rebuilt using this version of STLport. The LDAS code base needed to be modified to adhere
to the stricter definition of the STL library as specified in the C++ standard.
The largest impact was with slice_arrays. Currently,
all code compiles but not all unit tests pass.
The integration of TCLGlobus into LDAS continues.
The controlMonitorAPI (client and server) was
extended to support additional monitoring functions such as job statas and status.
Trying to extend the basic globus xio sockets to handle certificate authentication causes a
failure in the xio_register_open call. It is being
investigated and should be solved by next week.
It was also discovered this week that the tight loop of the client needed to
have a rework in how TCLGlobus registered and handles
registering TCLGlobus events. More
on this in the TCLGlobus section.
TCLGlobus
It was discovered this week that there is a subtle difference in how wish
and tclsh process events registered by applications.
As a result, the code has been enhanced to dynamically detect if it is running
wish or tclsh and take the appropriate action. This
solution works for all invokations of tclsh and wish. To ensure continued proper functionality,
all unit tests are being converted to run once with tclsh
and once with wish.
OSG/GRIPHYN/IVDGL:
A. Inspiral work flows on OSG - ITB
Using a patched version of the OSG 2.1 release of the VDS with components
from vds-binary dated 20050901.tar.gz.1, a 603 node inspiral pipeline DAG was run on the LIGO_CIT_ITB cluster.
However, the condor_sub_dag process halted during the
DAG execution due to faulty components and was manually restarted via the
rescue dag during testing to complete the work flow.
Using the latest nightly build of September 14 from the vds repository, a fresh version of vds client tools was installed on verruca. The following worker node components were
updated on the LIGO_CIT_ITB cluster to determine if a patch process would be
possible: dirmanager, kickstart
and transfer. A condor_sub_dag process halted after
successfully executing 602 nodes of the 603 node inspiral
pipeline. Documentation of this problem
for the vds development team
is underway.
In preparation for testing at UWM OSG PROD site, Brian Moe was furnished the
LIGO VO URL. Subsequently a test has confirmed the capability of authenticating
and executing simple fork jobs submitted from the Verruca
hosted Inspiral work flow test bed and the UWM OSG PROD cluster.
B. GUMS and PRIMA configuration:
Eliminated a problem due to entries for usaltlas and uscms VOs in the gums server throwing exceptions. Updated the VO Members DB in the GUMS server with the entities from
the added VOs. Generated a grid-mapfile for the set of VOS that are mapped and determined
that name='usatlasProd' and its associated groupMapping resulted in no entries in the gridmapfile for usatlas users. Insufficient documentation exists on the
"Atlas Privilege use and configuration for OSG" OSG Twiki sites for non-ATLAS sites to configure Atlas
privileges. Communications with the author of the Twiki
document is planned to explore role-based authentication models for GUMS/VO and
PRIMA.
C. On-going monitoring and systems administration.
Performed a yum update of the LIGO_CIT_ITB cluster and rebooted all nodes.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Got
the final details of our Sun support contract hammered out with Ray Gedert (Dynamic Systems) and filled out the PR and
gave it to Dorothy Lloyd.
- Participated
in the Synchrotron 215 changes/moves, including removing Cat5 bundles and
boxing them for shipping, re-racking nodes, moving ldas-cit
to Booth, rerouting fibre patches to support ldas-cit in Booth, reconfiguring network interfaces on
ldas-cit and dataserver-cit
- Did
more work getting my personal environment back to normal after moving to
FC4 (sending mail in particular).
(Phil Ehrens)
- Installed
host, datarobot, and ldap
certs on Verruca.
- Killed
errant java processes on Verruca that were consuming all cpu in the
execrable busy-wait routine. They were waiting for a pid to exit that did not exist. Foolish java.
- Moved
tons of hardware around and out of the refrigerator in Synchrotron. Pulled
cables, affixed tarps with tape. Installed a number of the removed servers
in the machine room on the Millikan 6th floor.
- Investigated
3dm2 and cli software from 3ware and
successfully installed and tested all of it on ldasdatatest1. Copied tarballs to ldas-sw:/ldcg_admin with a README file included. These utilities can be used with any
3ware raid controller card on any intel
32 or 64 bit platform.
- Replaced
bad HD on Peter Shawhan's desktop machine Garrak.
- Synched
all current scripts with svn repository on dziban.
- Replaced
all drives on Controller 1 of ldasdatatest1 with new Seagate 400Gb HD's.
Investigating configuration options.
(Stuart Anderson)
- Shutdown
and shipped/relocated several computers from 215 Synchrotron including 70
nodes now on their way to LHO.
- The
LDAS-CIT cluster is now running with just 1 node for test purposes until
the computer room upgrade in Synchrotron is completed.
- Monitoring
the increased (~50%) network performance for gridFTP
transfer of LHO IFO frame files after the recent GigE
WAN upgrade at LHO.
- Observed
and reported another Condor schedd crash bug.
- Decommissioned
the penultimate hybrid SRL/LIGO computer at Caltech (jelly).
- Monitoring
and coordinating activities associated with the Synchrotron computer room
upgrade.
MIT
(Keith Bayer)
- Gathering
performance metrics for new 5U pcraid unit.
- Coordinating
LSCDataFind configuration with Junwei.
- Initiating
contact with MIT HVAC for 5Ton liebert a/c install.
Livingston
(Igor Yakushin)
- Got
a quote from StorageTek to help to move tape
robot to the temporary location in the high bay. The most likely scenario
is: StorageTek would remove tape drives and the
extension door from the tape robot, secure the arm, put
the robot on a pallet (which they provide, it has a ramp and holes to
attach the tape robot with bolts). We rent a forklift that can reach all
the way up to the second floor and use it to move the tape robot to the
temporary LDAS location. StorageTek would
reassemble the robot. As a backup solution I am also investigating the
possibility for StorageTek to do a complete move
including a forklift.
- The
most likely dates for the move to the temporary location are Sept 26-28. I
have scheduled StorageTek to come on Monday,
Sept 26 and the nodes to be moved from the warehouse to the site on the
same day.
- Firmware on tape robot have been upgraded to 3.09. Firmware on tape robot drives have been upgraded to
1.35.402.
- Restored
metaserver after the disk failure.
- Got
1020 tapes for S5.
- Spending
time with Dwayne to get him started with LDAS part of his duties. In
particular I'd like him to be responsible for monitoring and replacing all
the disks in nodes and T3s.
- Purchasing
2 year Gold contract for the FastIron 1500
network switch.
- 3
failed disks in 3510 were replaced. No data loss or interruption.
- Stored
partition and disk images of linux servers in
/archive/backup/images to simplify the recovery after a disk failure.
(Dwayne Giardina)
- Master
disks in nodes 18, 28, 33, 36, 43, 50, 52, 55, 59, 62, 65, 69 were
replaced with slave disks from nodes 3, 4, 5, 6, 9, 8, 10, 11, 12, 13, 14,
15 respectively. ( all replaced master disks were
out of warranty, from February 10, 2003 ).
The slave disks in the above mentioned nodes were replaced with new
disks.
- Noticed
a bad slave disk in node 7, needs to be replaced.
Hanford
(Greg Mendell)
- The
LDAS HVAC upgrade at LHO continues. The LHO LDAS cluster was down for two
days this week to upgrade the electrical panels. This has been completed.
Brazing of refrigerant pipes for the HVAC has started. We will then have 2-3 days of downtime
next week to install the new HVAC unit, if it arrives as scheduled on
Sept. 22. The downtime will be announced to the DASWG.
- I
have restarted RDS generation of astrowatch data at LLO. I have also removed L1:LSC-AS_Q from the Level 3 RDS channel list. All Level
3 RDS frames with GPS start-time greater than or equal to 808645888 (Aug
21, 2005 02:51:15 CDT) no longer contain L1:LSC-AS_Q.
(H1:LSC-AS_Q and H2:LSC-AS_Q were
removed in previously at LHO, as documented in last weeks report.) The LLO
Level 3 RDS channel list for astrowatch data now is:
|
L1:LSC-DARM_ERR
|
1
|
|
L1:IFO-SV_STATE_VECTOR
|
1
|
|
L1:IFO-ACTIVITY_TYPE
|
1
|
|
L1:IFO-ACTIVITY_STATE
|
1
|
|
L1:IFO-ACTIVITY_INDEX
|
1
|
(Ben Johnson)
- The
first panel in the LDAS room has been upgraded to 125A breakers. We now have 72kW (90kW * 80%) total
usable power.
- Fixed
two nodes which did not come up after power was restored to LDAS room.
- Working
with Sun on fixing the L700 + SAM-FS import/export problem.
- Testing/learning
Solaris 10's firewall, IP Filter.
- Reading
up on Globus 4's web services framework (WSRF).
General Computing (Wallace)
MIT:
(Keith)
- Continuing
to monitor spam filter - feedback is positive
- Troubleshooting
campus network routing problem showing up with at least two ip addresses in our subnet
- Spec'd and ordered thinkpad
for new postdoc
- Clearing
off space on main gc fileserver
Livingston:
(Dwayne)
Replacement of disk in Harry's laptop not successful, as image creation on
external USB drive failed. Waiting on additional memory for this laptop. Will try to create image
again after memory arrives. Hopefully can start it Friday afternoon since it will take several
hours.
Hanford:
(Christine)
- Network
usage can be seen at http://www.ligo-wa.caltech.edu/~christin/mrtg/198.129.208.1_198.129.77.10.html
- The
contract for the 10 meg backup network connection
was signed and delivered on 9/12.
The circuits have been ordered in the Westin building in Seattle. The circuit from LHO to PNNL has been
tested. The only hold up is two
media converters which have been lost in transit. They are somewhere in the Tri-Cities,
but the shipping company is unable to find them. The tentative date for completion of the
backup network connection is now Monday, 9/19.
- One
of our color laser printers recently died.
I've spent many hours on the phone with the repair technician
trying to troubleshoot the problem.
The technician thinks the problem is either firmware of the
formatter board. She will be out
Friday to install the new parts.
- Lots
of user support for printing problems and e-mail problems.
- Created
a couple new user accounts and added some e-mail aliases.
CIT:
(Veronica)
LIGO: Finished the website for
the NSF review, moved over the pages for past reviews. Updated the Advanced LIGO
website. Updates of the LIGO
website and the MIT mirror page. Installed
patches and upgraded NAV on Windows servers, with some troubleshooting in the
process.
LSC: Working on the website
for the November LSC meeting. Updates of the LSC publications database.
(Christian)
- Synchrotron:
A workstation was infected with a virus this week. I was able to remove
the virus and installed Norton Anti virus 10 and Zone Alarm.
- Wilson
House: I called Dell to have Benjamin Abbot's CD-Rom replaced.
- 1
Floor E/B: I upgraded Julie Hiroto and Stan
Whitcomb to Adobe Acrobat 7.
- 3
Floor W/B: I replaced Helena Armandula's old CRT
monitor with a new LCD monitor.
- Surf
Student - Two surf students needed Math lab R14 and Ansys
9 loaded on their workstation.
- Configured
two new laptops with the standard Ligo image to
go into the loaner pull.
- Other
misc.: I continued to provide onsite software/phone support.
(Mike)
- Worked
with Ares Corporation on the PRISM/PRIMAVERA Server. I finally have the
server up and running with the licensing issues that I was having. This
also required some adjustments to the VPN server and on the client side to
resolve a DNS issue.
- Synchrotron:
IO computer name picked up a virus. Discovered by ITS security, I pulled
this unit off the Network and turned it over to Christian.
- Finished
up some work on Rich Abbott's laptop.
- Worked
more on the Ghost backup server. I have the server loaded, but I am having
problems with the SATA drives recognizing the size of these disks. I have
some more research to do on this.
- Other
misc. user support.
(Larry)
- With
the end of the fiscal year coming, there has been a lot of purchase
related activity. Mostly misc. items for the end users. Working on SUN contract renewals. They
should be wrapped up by the first of next week, all of the changes have
been sent in. Still have a few s/w
contract renewals to work on. A
number of new equipment items have been received and delivered. Items will
continue to trickle in over the next couple of months. Still have a number of laptops and a
couple of desktop computer left to order this week.
- Working
on a number of logistical issues in getting things moved over to the new
computer room. Because of recent changes to the building, electrical power
and air-conditioning have become an issue with the additional space. We
should be able to make things work.
- Worked
out some logistically issues for the network in the Synchrotron. It now
appears the network will be down for a few short periods and not for a
full month.
- Repaired
a number of E2E computers. All just minor items dealing with configuration
files.
- Moved
a number of computer items around. We now have a few locations that will
need new computer installations once the old units are removed.
- Continual
work on cleaning up accounts and adding new accounts. Still a lot of
e-mail alias cleanup work to do.
- Spent
time monitoring a number of systems as well as cleaning up rogue processes.
- E-mail
has been a big issue this past week. People are complaining about spam
getting through, so we have been adding more filters. Spent a couple of hours going through
the log files for one user receiving random duplicate messages. So far, no
indication of the mail server generating duplicate messages.
Mail Statistics Sept. 8-14, 05
|
Mail Statistics
|
September 14, 2005
|
|
Rejected Messages
|
14,552
|
|
Virus Messages
|
1,160
|
|
False Positives
|
167
|
|
Accepted Messages
|
17,465
|
|
Total Messages
|
32,017
|
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Project Management
from Carol
Wilkinson
Progress Updates
Progress updates for Advanced LIGO subsystem development for the period from
July 1 through August 31 are complete and will be posted on-line by Monday,
Sept. 19.
Meetings & Reviews
Future near term planned meetings & reviews are indicated in the table
below. Report from the 40M DC Readout
Review held July 19, 2005 is available: LIGO-T050168-00-R. Changes since last report are listed in blue.
|
Date
|
Sub sys.
|
Review
|
Topic(s)
|
Enabling event(s)
|
Schedule motivation
|
Status
|
|
Jul 11-13
|
SYS
|
SYS Mtg
|
CDS infrastructure & HAM
Isolation Req’s
|
|
|
Report in progress
|
|
12-Jul
8-11 PT
|
SUS
|
PDR, Review 2
|
Electronics req & design;
Focus is on the front end electronics (UK) -- limited Digital
controls/electronics (US) review
|
|
|
Report in progress
|
|
Oct 19
|
SUS
|
SUS PDR
Review 8
|
Ribbon/Fiber/Ear/ Bonding PDR
|
Completion of the ribbon, fiber, and ear and fabrication
and bonding design and processes
|
|
Panel and date
selection under way.
|
|
~Oct
|
SEI
|
HAM Critical Design Review
|
Recommendations w.r.t. HAM
prototype development based on ETF results
|
Completion of SEI/BSC critical design reviews; LSC review
of ASI HAM configuration design
|
Delay
until requirements are revised. timely decision on proceeding with SEI/HAM
prototype
|
Delayed
from Aug.
|
|
~Oct 12
|
SEI
|
HAM SAS
PDR
|
Review modeling, analysis, design for HAM soft
system
|
Revised HAM SEI requirements.
|
Timely decision for proceeding with HAM SEI prototype.
|
|
|
~Oct
|
SYS
|
PDR, Review 1
|
Engineering & Implementation ('generic') Requirements;
Interfaces
Revised Optical Layout
Optomechanical Layout
|
completion of generic requirements definition; completion
of first draft of ICD; revision to optical layout; establish integrated opto-mechanical equipment layout
|
timely system level definition enables/helps define
subsystem reqmnts & design
|
|
|
~Dec 8
|
SUS
|
PDR, Review 3
|
Quad design
|
Completion of the quad controls prototype
assembly; shipping to LASTI
|
timely transfer, to RAL & UB efforts, of lessons
learned from the controls prototype
|
Delayed until shipping to LASTI.
|
|
~Dec
|
SYS
|
PDR, Review 2
|
CDS Infrastructure
Stable Recycling Cavities
Lock Acquisition
Modulation Scheme
Power Induced Instability
|
Sufficient CDS requirements & concept work (also
7/11-13 mtg)
E2E Modeling for AL
40m Progress on Acq. & Mod.
|
CDS Infrastructure is key to subsystem electronics req.
Stable cavity is key to IO MMT design
|
|
|
~Jan
|
IO
|
PDR Review 1
|
PDD, Faraday Isolator, modulators, mode cleaners, mode
matching design, Mach-Zender
|
SYS PDR?
|
|
Work
delayed on
FI, allows more
systems to be
reviewed
|
|
~Jan
|
SUS
|
PDR, Review 5
|
Triple design
|
Available SUS/US staff
|
Enable SUS/US final design phase
|
Quad controls PT
takes preced.
|
|
~Jan 25
|
AOS
|
AOS DRR/CD
Review 1
|
Stray light control, PO
mirror and telescope, optical lever, initial alignment system
|
SYS PDR?
|
Delay stray light control review until other systems can
be reviewed at the same time.
|
Delayed from
Oct. to allow review of
add. systems.
|
|
~Feb
|
SUS
|
PDR, Review 4
|
Quad Installation
|
Completion of installation at LASTI
|
Inform the UK final design & noise
prototype design effort ASAP
|
Delayed shipping schedule
|
|
~Feb
|
SUS
|
PDR, Review 6
|
quad controls prototype test results
ribbon process/design
|
completion of LASTI testing
|
timely incorporation into final design effort on the noise
prototype
|
|
|
~Feb
|
COC
|
PDR
Review 1
|
Metrology, handling
fixtures
|
Review and
select vender and in-house metrology
|
Need handling fixtures for UK substrates arriving in Dec and
Jan 05
|
Work delayed
|
|
~Mar
|
IO
|
PDR Review 2
|
Adaptive mode matching, Mode Matching Telescope
|
Determination of whether a stable recycling cavity will
become part of the AL
baseline; SYS PDR 2
|
|
Waiting
for stable
RC decision
|
|
TBD
|
AOS
|
AOS DRR/CD Review 2
|
Thermal Comp., Photon drive
|
SYS PDR?
|
|
Moved
forward
for timely finish
of AOS CDR’s
|
|
TBD
|
SUS
|
PDR, Review 7
|
BS, FM/ITM SUS design
RM design
non-cavity SUS
|
design work completion (has yet to start on FM/ITM, not mature
for RM)
|
|
|
|
~May
|
COC
|
PDR
Review 2
|
Cleaning Process, Optics prelim. design
|
SYS PDR?
|
|
|
From: Rolf Bork rolf@ligo.caltech.edu
AdvLigo:
Computer for quad suspension controls is due to ship by the end of this
week.
Requested a quote for a PCI-X expander chassis.
Such a unit would allow us to remote the ADC/DAC I/O cards from the computer
chassis. The multi-AMD64 processor computers we plan to use are rather loud
(due to the cooling requirements), so it may be desirable to place them somewhere
other than in the main equipment racks.
Performing some more testing on the Miranet
network cards as a possible replacement for reflected memory (RFM) in future
systems. These are 2GHz, full duplex, realtime
networking boards. They would have advantages in cost (about 1/3 the price of
RFM) and are configured in a switched fabric rather than the ring architecture
of RFM. The primary test we want to run is to determine whether or not the Framebuilder could handle the network packets from all of
the front ends in a timely manner. The RFM has the advantage of a 64MByte
buffer that is filled in by all of the front ends and then simply DMA
transferred by the Framebuilders.
Waiting on more info from Dave Ottoway
on the Lasti installation plan. We need this
so we can better plan the CDS infrastructure required to support the quad
suspensions, ISI, etc. As part of this, we are also waiting on the write up
from Nergis on the system she wants implemented at Lasti.
From: Jay Heefner
<jay@ligo.caltech.edu>
AdL SUS
- System
drawings for the quad controls tests at LASTI using PCI based LIGO
controls have been started and are 75% complete. They will be completed
once the testing of the new PCI-X based ADC and DAC modules has been
completed. ADC and DAC boards are due by 9/20.
- Preparations
for my Oct 1-7 visit to Birmingham
are in progress.
AdL SEI
- Prototype
amplifiers for the in-vacuum GS-13 have been shipped to the ETF for test.
Initial tests show improved noise performance for the GS-13.
- System
drawings for the LASTI installation of the ISI are 75% complete.
Seismic Isolation
From: Ken Mason kmason@ligo.mit.edu
Advanced LIGO Seismic Structure Procurement Status
Bid packages have been sent to machine shops and fabricators for all stage
0, stage1, and stage 2 parts. Quotes are expected to be in by 9/30/2005.
The actuator tooling design has been completed. A Request for Quote has been
put together for the actuator subassembly machined parts and tooling.
A meeting was held this week with Joe Hanson (LLO) and Southern Enterprises
to go over drawings, inspection, and shipment of the LASTI test stand. They
expect to meet the delivery date of 10/14/2005 as long as there are no
unexpected delays from subcontractors hit by the hurricane.
ASI has confirmed that they will be finished with the blade modification
redesign next week on schedule.
From: "Joseph A.
Giaime" jgiaime@ligo.phys.lsu.edu
Suspension
From: ctorrie <ctorrie@ligo.caltech.edu>
Advanced LIGO Suspensions
CONTROLS PROTOTYPE QUAD SUSPENSION
The workshop should be finished the re-works by early next week. Mark, Jay, Mohana and I managed to control the single chain (quick
fix) Quad with its 6 local control osems, more to follow. We also worked on a couple of single
pendulum bench tests to aid with the understanding of the "flexure
theory".
MODE CLEANER SUSPENSION
Laurent and Rich have assembled most of the 2nd mode cleaner.
SECOND STRUCTURE
The second quad structure should be finished and ready to ship to Stanford
by the end of the month. Tim Hayler is visiting from
RAL at the start of October to help us carry out some resonance tests prior to
the shipment to Stanford.
INSTALLATION FIXTURES
We received a quote for the installation fixtures and I am now working with
Ken Mailand and Oddvar
(remotely from Norway)
on finalising a few drawings and updating a couple of
parts before work begins on the parts.
From: Ken mailand kmailand@ligo.caltech.edu
I finished looking over the HAM SAS drawings, for fits and
dimensions/tolerances etc.
Core Optics
From: GariLynn Billingsley <Billingsley_G@ligo.caltech.edu>
For Advanced LIGO this week; we're working on budgets.
Ed Jasnow has drafted a letter to the NSF
informing them of the upcoming transfer of blanks, purchased using the UK AdL funds, from the UK. The four ITM blanks have
been ordered and are scheduled to arrive in December.
From: Helena Armandula ahelena@ligo.caltech.edu
From: Bill Kells <kells@ligo.caltech.edu>
We have had further meetings on the issues of PI, and closely related TCS
strategies. One result is that I am explicitly looking into the relative
numbers for attainable instability thresholds for various candidate ifos (particularly Gin-Gin, and 40m..... they are comparable !). I is taking some
refined effort to fairly portray the comparision. Soon (e.g next Gin-Gin advisory mtg.)
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
The frequency response of one of the high power photodetectors
was measured and had an unexpected feature of a peak at 1.6 MHz. This did
not show up in the PSpice model and I have been
trying to track down its origin. Whilst the noise performance was as
expected, the bandwidth was lower than expected. I have not sorted out why this is so.
The Innolight NPRO power supply control signals to
the laser were examined to see which one would be appropriate for attaching an
hour meter to. I could not find any that were applicable without
attaching the laser that also made sense. Connections to the ON/OFF
switch were not possible.
LZH made some progress in resolving the issue of the spatial mode of the 200-W
laser. It is possible that previous reports/measurements of the spatial
profile were optimistic. After further modeling of the resonator, they
feel they have a better understanding of the resonator behavior. Currently the laser produces 150 W with a good
spatial profile in the full configuration.
I have also been looking into clean room assemblies for use inside the laser
area room, as the plan is to have a low-dust environment around the laser.
Especially after various mishaps that have occurred at LZH with spots being
burned onto mirrors.
Auxiliary Optics
From: Michael Smith smith@ligo.caltech.edu
SLC
Gave Hiro a list of
interferometer parameters so that he can model the scattered light noise for
ADLIGO.
Other Laboratory R&D
Alberto
We spent the last week trying to
improve the measurement of the GAS filter TF. The transfer function is quite
noisy at high frequencies. We expect to observe a plateau in that region due to
the saturation of the percussion point compensation. We have to look at the
phase to confirm whether we cross the critical threshold between
overcompensation and undercompensation. A dip should
appear in the plot when we are overcompensating, but it is not easy to
distinguish it in the saw-like transfer function we have now above 20 Hz.
Facing all the measurement we got till now, we had the confirmation that it is
not just noise. At the highest frequencies the accelerometers are more
sensitive to the acoustic noise coming from the speaker through the air, but
most of the peaks and dips are due to mechanical resonances of the whole
complex excitation system. We made many efforts to damp at least the biggest
ones. We used some bungee cords to fasten the rods between the speaker shaker
and the frame of the filter and we killed a couple of big resonances. We also
attached some masses through Velcro stripes to the rods and it worked very
well. Some resonances we can move around but not kill completely. Thanks to
these kinds of modifications we got a much better transfer function. We
probably can't do anymore improivement because of the
non-negligible mechanical complexity of the system.
Anyway we are hovering below 80 dB,
if we extend the 1/f^2 line to the frequency at which the phase flips we infer
as much as 90 dB. At this attenuation level, we see appearing the resonances
due to the spring effect on the wire which hold the payload and the internal
blade resonances that we can't remove without adding other mechanical parts.
What we can do now is try to shift
the transfer function’s plot to the low frequencies by introducing Maddalena’s electromagnetic anti-spring circuitry and
tuning the resonant frequencies of the blades towards 30 mHz. To this end we have fixed some problems in the
old circuit board and it should now work again. We are going to start to test
it today.
Ilaria
I assembled the four legs of the
pendulum between two tables: one below the main flex joint base and the other
on the the small flex joint base with the program
Solid Works. I imported it in Ansys where I meshed
the assembly, applied the Standard Earth Gravity, I choose the boundary
conditions and I controlled the contacts. I studied the "load bend":
for this test I changed the density of the form at the top of the pendulum,
varying the mass between 370 Kg and 1100 Kg. The results show that the
frequency is inversely proportional to the mass, according to the theory and
the experimental results; moreover with a mass of 1100 Kg, the frequency is
about 0 Hz. This means that a mass of 1100 Kg on the real pendulum let it fall
to the ground. I’ve studied the higher frequency leg resonances which are
qualitatively in agreement with the measurements. Extending
their study to different conditions. I`ve just
started the same simulation with a small flex joint of diameter 1.5 mm. I`m also studying a way to obtain the transfer function
with Ansys to set up the IP counterweights.
Juri
I calculated the sensitivity of the nearly concentric Mexican Hat cavity to
cavity-length offset or background curvature offset for the MHC mirror. The
results show that the beam shape is greatly affected by these issues and put
tight constraints on the mirror manufacturing and on the precision on the
cavity length measurement (the cavity length and the nominal radius of
curvature must agree to 0.3% or less).
I worked with Francesca on the data analysis on the hysteresis
measurements for the GAS blades.
Francesca:
I'm continuing the analysis of the hysteresis
data.
John
I am working on quantifying the influence of mirror tilts on the mesa beam
profile. Numerous data sets have been taken and analysis is underway. Stability
and repeatability are causing concern when trying to compare small angular
displacements. Some backlash has also been found in the system’s piezo. To compare experimental work to
the calculations of D’Ambrosio, Thorne et al.
I must have an accurate calibration of the PZT actuators, this is underway. I
have also started thinking about my final report.
Maria Paola
I got 30 V pk pk winding
a new transformer with 200 coils on the primary winding and 1200 coils on the
secondary one with the new bigger core, but I achieved this result at a very
low frequency (about 600 Hz). I also replaced the diode bridge with another
rectifier, made of two diodes and two capacitors, since the diode bridge gives
a continuous voltage which is only a half of the pk pk value. Nevertheless, the maximum voltage obtained is
only 10 volts at the end of the rectifier, and this is probably a matter of
loads, since the 10 MOhm resistance of the probe I
use to see the signal on the oscilloscope is still too high, and I need to have
a bigger resistance, so as to avoid losing voltage.
Chiara
I put the first load (624 Kg) on the four 40m prototype Inverted Pendula and I tested the flatness of this top plate. I
mounted under this table three DC motors with parasitic springs, the position
of the top plate could be centered using the parasitic springs tuning.
Waiting for the accelerometers to become free.
I’m studying some details about the HAM SAS project.
Akiteru
The first TAMA SAS tower installed in TAMA, proceeding
with tests until next tower installation.
Maddalena
30 mHz GAS filter paper
final review preprint received from NIM.
Valerio
I'm trying to correct some inconsistencies found in the transfer function
matrix of my SimMechanics model of the HAM-SAS.
In the same time I'm trying to translate the SolidWorks
model of the HAM-SAS inverted pendulum section, developed by Ilaria, to SimMechanics. This
will allow us to improve significantly the quality of the complete model.
For additional information about this report, contact Stan Whitcomb or Phil Lindquist