Weekly Report for
Week Ending September 1, 2005
The LIGO Executive Committee meeting for September 5,
2005 is cancelled due to the Labor Day holiday.
Special Announcements:
Weekly
Report Highlights
LSC Issues (Saulson)
No report.
LIGO Laboratory Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
LSC MOUs and Research Plans and Progress Reports
- No
report this week (vacation).
Non-LSC MOUs (Lloyd)
- No
report this week (vacation).
SITE TELECONFERENCE (Lindquist)
A site teleconference was scheduled for Thursday, September 1, 2005. The following issues were among those
discussed:
- Budgets--Through
August we project that we will book $24.5 million in expenses. Last year for the remainder of the year
we had $4.6 million in additional expenses. Based on that we project on the order of
$30 million for FY 2005. Reasons
for the decrease relative to last year include $1.9 million less on EPI
and $800 K less on Seismic Isolation.
In addition we spent less on Detector Fabrication. However, we have just approved
proceeding with the seismic isolation prototype for LASTI, and there will
be additional hardware expenses that have not been reflected in this
simple forecast..
- Relocation
of LDAS Equipment—Because of hurricane Katrina we have delayed
the due date for of proposals to Thursday September 8. Livingston expressed concern about the
handling of the computers once they get to Louisiana. The trucking company will unload
them. However, instructions have
been issued to hold the equipment in Houston
until things get sorted out.
- Property--NSF
Annual Report for property is just about done. Not due until the end of the month.
- Louisiana
(Katrina)—Reports indicate that there is absolutely no
indication that the government has figured out what to do with one million
refugees. LSU is providing shelter
for ill and special needs people.
Large encampments may have to be constructed somewhere. Travel, lodging, water, etc. are all a
problem. Stan has issued the
following email:
Until further notice, no one should plan to go
to the LIGO Livingston Observatory until the
situation there has stabilized. There are no accommodations available,
and the staff there has their hands full dealing with the situation. I repeat, all travel to LLO should be put on
hold until further notice.
The site network is still down,
probably due to an interrupted fiber connection. No email is available to Livingston. LIGO personnel are advised to use telephones
to communicate. Be patient, multiple
tries might be necessary. They do have
the fax machine going and FedEx. Do not
use UPS. FedEx has been reliable
throughout. We also discussed setting up
a temporary phone connection for email service.
P-Card reconciliations will be done by Caltech for Louisiana this month.
- The
list of assigned actions will be found Here.
This list has not been visited for several months. Action 124 concerning a procedure
manual is closed. The decision tree
for taxes has been provided and Hanford
accepted the document. Action
126 to work out P-Card reconciliation timing issues with Caltech
Administration is closed. This is
an issue that we apparently cannot win.
Action 130 to check with the International Scholar’s
Office concerning the rules for VISAs for students and scientists already
at Caltech is closed. Attempts to
contact the office elicited no response.
Action 131 was previously closed.
PROPERTY MANAGEMENT (Chargois)
>From: Ed Chargois <chargois_e@ligo.caltech.edu>
- Provided
assistance to LDAS Group (S. Anderson)
with arranging the relocation of 140 Computers and 4 Electronic Cabinets,
from CIT to LLO. This equipment was
scheduled to arrive on 9/6, but due to the conditions caused by the
hurricane, delivery is postponed until further notice. Account Number LIGO.DAT 1.5.1
NSFLIGO.FY02ON.
- Provided
assistance to the PSL (P. King) with the purchase of new labels for PSL
LIGO II. Account Number LIGO.BUS 1.2 NSFLIGO.FY02ON.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
>From: Cleveland Mak mak_c@ligo.caltech.edu
- No
report (personal day).
COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Completed
the change order to Hereaus Optics for the Suprasil 311 and 312. Awaiting for the vendor acknowledgement
and estimated delivery date.
- Closed
out open purchase orders, completed the purchase order monthly close out
report for August 2005, and submitted it to management. The blanket
purchase orders are current and unexpired.
- Released
the hold on the laser order with Point Source and proceeded with the order
according to the original specifications which the vendor is willing to
accommodate us in meeting our requirements. Provided the researcher with the details
of the previous laser orders to assist the end user in determining whether
the damaged lasers would be covered under warranty.
- Followed
up on the credit for the sales tax that was charged by the vendor and is
pending being credited by the vendor. There are several invoices pending
payment until the appropriate credits are received.
- Reconciled
the billed p-card transactions charged on my credit card. There is only one
order pending reconciliation which is the order to Newegg. It will be
reconciled after the confirmation of goods is received and the approval
for payment is provided.
>From: Florence Kaufman <fkaufman>
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- The
date for the receipt of the quotations for relocation of the LDAS
equipment at LLO has been moved back from September 1 to September 8 due
to Hurricane Katrina.
- Due
to Hurricane Katrina, the low bidder for the LLO Science
Education Center,
Cangelosi - Ward, had not received any revised prices from his
subcontractors. They have indicated
that they will continue to press their subs for these prices.
- The
offices of the architect for the LLO SEC, Eskew- Dumez - Ripple, were
severely damaged by the hurricane. They will be looking into setting up a
temporary office in Baton Rouge.
- Sandy
Pool introduced his replacement as LIGO counsel, David Flores, to Stan
Whitcomb, Phil Lindquist, and Ed Jasnow on Thursday. David has been with Caltech OGC for many
years and is very experienced in contracts. Sandy
has become Caltech's Director of Gifts and Estates.
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
- Processed
the paper work for five (5) new/revised trips. At this time there
are three (3) trips completed or in the works but are awaiting the
necessary paper work to enter the P-Card system. Assisted several
LIGO people with their travel arrangements using their P-Cards and made several
reservations for outside visitors coming to LIGO/Caltech or one of the
LIGO sites.
- Monitored
situation at Baton Rouge and New Orleans Airports
and hotels in the Baton Rouge
area due to damage from Hurricane Katrina. I have had to rebook
three (2) trips at this time and expect to have more in the near
future. At this time United Airlines is estimating that the New
Orleans Airport will be closed for at least one (1) month, Baton Rouge
Airport is open to limited air traffic and the hotels/motels in Baton Rouge
cannot guarantee any reservations due to the Louisiana Attorney General's
directive that no hotel/motel can turn anyone out of their room even if
they have exceeded their original reservation dates.
- Completed
twenty-eight (28) Expense Reports and there are five (5) reports yet to be
done. I continue to contact travelers who have outstanding Expense
Reports (more than one (1) month old) to ask for their cooperation in
sending me their receipts so that these can be closed in a timely
manner. Presently there are two (2) reports more than thirty (30)
days old. I have two (2)
reports awaiting signature at this time. Worked on copying and
recording all the expense reports completed last week to be sent to Travel
Audit for final auditing and payment.
>
- The
NSF Review of LIGO is scheduled for November 9-11, 2005.
- Stan
is working on a proposed agenda; Tom Lucatorto is preparing the charge for
the review panel members; these should be ready in early September, and
then we will begin creating and publishing the NSF Review 2005 Webpages.
- Irene
has set aside a block of rooms for the review panel at the Courtyard
Marriott. Rooms may be reserved by
contacting the Old Pasadena Courtyard directly (626-403-7600), requesting
"In-House Reservations" and indicating the reservation is for
LIGO-NSF Review-Caltech Group.
- Dinner
is still being decided.
>Dorothy Lloyd
- No
report (vacation).
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
PROPOSALS and REPORTS (Lindquist)
The Proposal for an Extension to FY 2007 and FY 2008 and Supplemental
Funding for LIGO Operations was previously reported as submitted to the
NSF. The NSF has requested additional material. Contributors to the
Annual Report have been providing additional material. We are assembling the information provided.
DCC Steering Committee (Lindquist)
Change Request CR-050008 for funding to upgrade the LIGO Document Management
System was approved. We are preparing a
statement of work and purchase order.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
- The
following change requests have been approved:
CR-050007, LDAS Operations,
Increase Power and Air Conditionaing at the Sites
CR-050008, Replace LIGO Document
Management System
The minutes for the LIGO Change
Control Board meetings held on July 25 and August 8, 2005 can be found at: M050269-00-P.pdf
The original signed copies of the
minutes and the change requests have been sent to the DCC.
- We
conducted a meeting of the LIGO Change Control Board Wednesday, August 31,
2005 to discuss Change Request CR-050009.
The Seismic Isolation Critical Review Committee issued a report
(LIGO-M050035-01-M) recommending that we proceed with the fabrication and
testing of the ASI version of the BSC seismic isolation prototype at
LASTI. Approval of this change
request releases the remaining funds allocated to begin fabrication. The change request was approved. Minutes are being prepared.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- A
Staffing Committee meeting was held on Monday, August 29, 2005. The minutes and action items from the
Staffing Committee meeting have been posted on the SC web page. All files for the Staffing Committee are
up-to-date and posted on the SC web page.
- Prepared
numerous appointment and reappointment memos for various Visitors, Post
Docs, and Staff.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
No report.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of Commissioning Activities at LIGO Hanford Observatory
(Landry)
During evening hours, H1 ranges were above 10Mpc. Daytime running however
saw low frequency noise upconverted into the gravity wave band, reducing binary
inspiral ranges by about a Mpc. Lowest noise for the week corresponded
to about 11.6Mpc.
The last few days of H1 running are depicted here
in this range plot.
Some highlights from the elog are linked below:
- REFL
acoustic enclosures are being installed. First the 2k enclosure was
installed this week and now awaits light pipes; next week the 4k REFL
table receives its enclosure
- we
still await the shipment of the refurbished H2 laser
- a
new fibre optic-based timing system was tested.
Some analysis
of the test has been performed and the results look good, although some
small glitches (some hundreds of ns, some only tens of ns) are being
investigated.
4K IFO
- coherence
observed between AS_Q and the POB signals suggested some MICH and PRC damping filter tuning
was in order.
- ASQ4
has a mobile dark
noise level
- Astrowatch
continues: it is comforting to note that GRBs occur
while we're at 11Mpc
- as
it was likely being underestimated in the noise model, the 4k shot noise reassessed
2K IFO
- the
crystal oscillator was fixed
with a power supply being swapped out
DAQ
- new
Framebuilder code and a new RFM (reflective memory) configuration were
implmented, in part to account for the new naming convention for DMT
channels. Of course the new channel names caused some confusion through
the week.
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
No report (skeletal operations due to hurricane Katrina).
Initial LIGO Detector Science & Engineering (Coyne)
CDS
see also the CDS weekly meeting minutes in the commissioning archives
CDS Software
Rolf Bork
- Alex
is working on the changes requested for the fast ADCU.
- There
is a pending request to add a filter bank to the H1 end station code to
drive the fine actuators. This work will start once we have the final
details from Mike Landry.
CDS Hardware
Ben Abbott
LSC RFPD
1) Todd is stuffing boards to complete the delivery of new RFPDs to the
sites.
2) A PD (S/N 1133) arrived from Livingston
that I need to diagnose to find where its excessive dark current is coming
from. I suspect that it is similar to the mysterious LHO problem that
arises when the can is cut.
Fast Shutter
The first prototype fast shutter was tested this week, and things look
promising. I am able to see delay times on the order of 550
microseconds. A laser was aimed at a photodiode just past the shutter,
and the delay was measured between the spike of voltage seen across the coil of
the shutter when the switch was pushed, and the beginning of the signal
attenuation from the photodiode. The light was totally blocked after ~1.1
ms. I made no effort to optimize this time by focusing the beam, nor do I
have a good measure of the width of the beam, but it appeared to be ~ 1 - 2mm
on a laser card. Due to a problem with the first prototype, I am going to
make a second one to continue my testing.
ISS PDs
The anodizing shop has said that the parts for the ISS PDs are finished and
ready for pickup.
DMT
no report
PSL
Peter King
I have been trying to get servicing documentation for the RTE-140M chiller. The "service"
manual from ThermoElectron is pretty much only a guide on how to disassemble
the chiller, not how to repair it. Otherwise I have not received anything new
from their technical staff, especially by way of circuit schematics.
TCS
Ken Mailand
I'm designing and making brackets to mount flow meters to be added to the
laser chillers at LHO, per Cheryl Vorvick's request.
ITMx (ITM07) Absorption
GariLynn Billingsley (Liyuan Zhang, Lee Cardenas)
4ITM07, removed from the Hanford
4ITM-x position in June of this year, has been scanned for absorption using a
high resolution grid. This scan incorporates a new lock in amplifier,
allowing us to account for different phase change from the higher
absorbers. For this scan the max scale absorption was 40ppm.
Results can be found at http://www.ligo.caltech.edu/~coreopt/Scatter/4itm07_hrabs2_11.pdf
where page three shows us that some 250 points out of 32761 points had an
absorption of 40ppm or more. In order to account for the absorption predicted
by the interferometer measurements, the saturated points would have to have an
average absorption in the range of 2000 ppm.
Another high resolution scan will be made, with the upper limit on the
sensitivity set much higher.
LHO ITMx Baffle Glass Contamination
Helena Armandula
Second baffle glass test report:
Received the glass baffle test report on a second spot analyzed. The
report is in the DCC OUT under T050145-00-D.
The new XPS (X-ray Photoelectron Spectroscopy) analysis was done on a second
spot on the glass baffle side that showed a faint haze. This is the baffle's
surface facing the mode cleaner. A higher concentration of Na (sodium) is also
observed on this side. Appears that only one side of the baffle is contaminated
with sodium.
40 Meter Interferometer (Weinstein)
It's the end of the summer. We said goodbye to Ryan, Marcus, David, Ju Li,
and Seiji. Thanks for visiting, for all your help and good work, and for your
comraderie!
IFO commissioning:
- After
the ETMX OSEMs were adjusted during last week's vent, Dan adjusted the
ETMX coil balancing and output matrix f2a filters, and also diagonalized
the input matrix (Shihori's method).
- Osamu
now finds that ETMX noise is significantly reduced in pitch, and there's a
small improvement in yaw. The X arm control noise used to be much worse
than Y arm; after we fixed ITMX it became much better, and comparable to
the Y arm. Now, after fixing ETMX, the noise hasn't gotten noticibly
better; it's still comparable to the Y arm.
- Now,
MC2 is one of the noisiest suspensions, and Osamu believes it is
responsible for a noticable beam jitter in MCT that may be contributing to
our lock acquisition difficulties. Dan will work next on balancing and
diagonalizing MC2.
- Osamu
has been locking the IFO in various configurations, including PRFPMI. He
believes our lock acquisition difficulties stem from a large amount of
excess noise, origin unknown, that shows up even in single-arm lock
(suggesting frequency noise or electronics). He's now concentrating on
noise hunting with single-arm lock, or DRMI+1 arm.
- Osamu
is working on commissioning the fast analog path for the common mode
servo. He found several problems with the board; it looks like it was
partially modified by someone but not finished. He fixed these problems,
and tried it with one arm locked; he saw a significant reduction in noise.
- Now
he's trying to make the common mode servo work during lock acquisition, not
just once lock is acquired, which was what it was designed for. He needs
to find a way to normalize the analog signal from the IQdemod board to the
arm transmitted power; he and Ben are working on an analog divider.
- Rob
wrote some LSC code to implement a "kick and pull back" of the
CARM degree of freedom, to try to get it from the DC offset to the RF
no-offset state. Will try it out soon.
IFO modeling and DC detection development:
- Monica
is implementing suspensions in her AdLIGO e2e code.
- Monica
is working on modeling signal sweeps with Malik's parameterization, and
estimating mirror velocity.
Electronics, controls:
- Osamu
encountered problems using the AWG or anything that makes use of the test
point manager. Also, the frame builder couldn't see test points. Alex
investigated, fixed the frame builder problem, and suggested we reboot
control computers to recover the proper operation of the test point
manager. This seems to have worked, but the cause of the problem, and the
proper way to recover from it, remains a mystery.
- Ben
did a quick survey of the state of the DC readouts from the LSC RFPDs.
Currently, there are three DC readouts set up to be drawn from the P2
connector on the back of the LSC Interface boards' Eurocard crates. Two
more are needed, and these cables have been made, and await connection.
Once these other two cables are connected to the P2 Interface card, all
five will replace the signal that is now being taken from the DC OUT
connector on the RFPD box; and these cables will be removed. This whole
procedure should eliminate a possible source of ground loop 60Hz noise.
- Ben
continues to develop fast mechanical shutter prototypes for the sites and
for the 40m. Delay times of order 550 µsec. See his report elsewhere in
this Weekly.
- Ben
reports that new LSC RFPDs are being stuffed for the sites and for the
40m.
Lab Infrastructure:
- Steve
has determined that TP1 is overburdened during pump downs because it's
backing turbo pump, TP2, is conduction-limited. He is planning on
installing a spare dry scroll pump to back TP1 during pump downs.
- Steve
has turned off the cryopump following last week's pump down, and is
regenerating it.
Thermal Noise Interferometer (Black)
No report.
LASTI (Ottaway)
Seismic Isolation report (Rich M)
We tested out a simple vibration isolation system for an optics table. We used a commercially available constrained
layer device between the legs and the table. The first results are on
today’s LASTI
ilog.
We also tried to modify the flagpole resonance of the BSC chamber by butting
a beam between the chamber and the building wall; there are pictures on the LASTI ilog
from Friday august 26th. It turned out not to have any effect due to the fact
that the wall was moving with the chamber.
An entry will appear on the ilog in the near future.
We are continuing to work with the optical lever which was installed on the
BSC to understand the twisting that the support beam undergoes.
PSL (Dave O and Thomas C)
Small suspended cavity has been locked and the shakedown of the PSL
continues so that the PSL can be an independent facility.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
SimAdvLIGO
(Hiro) Working to fill unfinished parts of the advanced LIGO simulation
package, including seismic isolation system.
Simulation of 40m Advanced Interferometer
(Monica) Suspensions have been added to the e2e package for the 40m in 2
different ways (i) using the primitive sus3Dmass module and (ii) using a simple
filter (double pole and a polepair at 1 Hz,Q=5).
Diffraction loss in Advanced LIGO
(Biplab) Studying diffraction losses for Laguerre Gaussian Modes in Advanced LIGO cavity using matlab FFT
code.
modeler
(Hiro) Fast dual recycling Michelson cavity code development still going on,
together with refinements of algorithms in Mathematica taking the precision of
double real variable into account. E.g., Expressions like ( 1 - (1-epsilon)^N )
/ epsilon, where epsilon is small number does not work with this form when N is
large. Not physics, but boring
programming issues.
Alfi
(Bruce)
- General
organizing to move to new computer system.
- Reorganization/prioritization
of remaining Alfi PRs.
- Working
on Alfi node dependency tree and easy access to associated dependent nodes
(PR 268).
(Melody) Continuing with fixing the Problem Reports. Currently fixing PRs 496 and 498.
Data Analysis Activities (Lazzarini)
Mandic:
I have run the first-pass stochastic analysis on the S4 H2L1 data, along
with the coherence calculation for the H2L1 pair. After cleaning the data, the
H2L1 pair reaches theoretical sigma of 4.9e-5 (for Hubble parameter h=1). The
CC and sensitivity integrands seem reasonable. Combination with H1L1 pair
(which had sigma of 2.2e-5) should yield about 10% improvement over H1L1 alone.
I have examined the hardware injections for S4 H2L1 and obtained similar
results to the H1L1 pair: one pre-calculated injection was successfully
recovered, and one "on-the-fly" seems to have 2-sec offset.
I started looking at the possible implications of the S4 result on the
various cosmological and astrophysical models of stochastic GW background.
I have also started working on the hardware injection code that we would
like to implement for S5.
Mendell:
The StackSlide code review continued on Fri. Aug. 26. An update on how the
code defines the reference time that defines the initial signal frequency at
the SSB was checked into LALapps CVS yesterday, making the StackSlide code
consistent with similar updates made in LAL. Also, using the StackSlide code, I
have posted evidence of one Hz lines in the S4 L1 data, in the L1:LSC-DARM_ERR,
L1:LSC-DARM_CTRL, and L1:LSC-AS_Q channels.
(At Hanford,
so far the StackSlide code has seen these lines in the H1 data only, and only
in the H1:LSC-DARM-CTRL channel.) A
report is on the pulgroup investigations page here:
http://www.lsc-group.phys.uwm.edu/cgi-bin/enote.pl?nb=puls4general&action=view&page=10
Shawhan:
- Went
over proofs for S2 LIGO-only untriggered burst search paper, and returned
corrections.
- Held
a meeting of the CaJAGWR Executive Committee to plan for the coming year.
- Wrote
LAL code to parse a string to get a LIGOTimeGPS value.
- Currently
writing LAL code to work with segment lists.
Sutton:
Since returning from Canada
on Tuesday I have been studying the construction of a metric for power-based
searches with chirplet test waveforms; this is part of my "LIGO
cheese" study. I'm also getting up
to speed on recent developments in the network analysis and network simulator
projects.
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS:
Continued developing new functionality in the controlMonitorAPI's client and
server using the tclglobus interface package. Able to open socket to server and
read in the data downloaded but still have to resolve why cmonClient is spinning in infinite loop.
Upgraded LDAS-DEV to the newest DB2 database (version 8.2.2); fixed tcl code
to process job after dataRecvReaper has completed when data object arrives
later than tcl command. This situation is seen in the insertion test with db2
8.2.2. Once fix identified, upgraded the Tandem 3, 4, and 5 systems to use
8.2.2 (Tandem 2 had already been upgraded).
System testing with the new IBM DB2 identified several failure modeds in the
weekly system and integration tests. These were traced to a few bugs in the TCL
source code which have now been fixed.
Successfully compiled all required packages used by LDAS for Solaris using
GCC 4.0.1:
Have been successful with compiling LDAS except for the python support
library for the diskcacheAPI.
Successfully compiled all required packages used by LDAS for Fedore Core 4
using GCC 4.0.1
Successfully compiled all of LDAS with this tool set. All but one unit test
pass. The unit test is in the datacondAPI and is under investigation.
Actively investigating why zombies still exist at the C++ layer. The
signature is different from what has been seen before. More debugging will be
added to get the full picture.
TCLGLOBUS:
Worked closely with Kent and LDAS developers to develop and test a testbed
client server that will function similar to the requirements on the
controlMonitorAPI in LDAS and eventually the managerAPI. This revealed several
issues with existing TclGlobus client/server tests which had to be updated to
use host certificates and CA certificates on the server side.
Attempted to get TclGlobus to work under RedHat 9. Was not successful.
Since Redhat 9 has been dropped by the LIGO and is not supported by anyone,
decided to migrate support over to Fedora Core 4. This is now the operating
system to be used in development. Fedora Core 3 will continue to be supported.
OSG/GRIPHYN/IVDGL:
Successfully produced an Inspiral DAG from an Inspiral DAX using latest
client tools from Duncan Brown on kitalpha. However, daily upgrades, patches
and downloads have been necessary from the VDS team and Duncan for the last
three days to produce this result.
Components are changing rapidly. An additional fix from the VDS engineer has
been promised today (Sept 1, 2005) for the latest bug discovered by Duncan after the COB on
Aug 31. Hope to have a stable DAX to DAG
client tool set by next week but this has been an on-going problem for the last
three weeks.
In anticipation of a stable DAX to DAG client tool set on kitalpha, work
with Stuart and Duncan
proceeded to create a Globus-G client submission facility on
verruca.ligo.caltech.edu to demonstrate condor_submit_dag on OSG for an
Inspiral DAG;. This facility will demonstrate use of Condor-G as a potential
submission facility for LIGO OSG users.
Testing of the Condor-G/Verruca submission facility with LIGO-CIT-ITB
will begin next week. Condor-G supports submission of a Condor DAG to a service
supporting a Globus gatekeeper with a Condor job-manager such as LIGO-CIT-ITB.
Successfully tested a GUMS server on tclproxy.ligo inter-operating with the
LIGO VOMS server at PSU to generate a
grid-mapfile of the current users in the DB of the LIGO VOMS for the
LIGO-CIT-ITB testbed.
Perfomed a yum update on LIGO-CIT-ITB and rebooted all nodes. New
kernel-smp.i686 2.6.12-1.1376_FC3 was installed.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Worked
with Ray Gedert on another draft for updating our Sun support
contract. We getting close--I
expect one more revision will do it.
- Updated
CIT's dodump script to use /var/sam (rather than /usr1).
- Tested
Ben's updated LSCdataFindServer.
- Installed
SAM-QFS 4.3.15 at CIT (all SAM-QFS & QFS boxes).
- Helped
with shrinking CIT cluster.
- Copied
all S3/S4 L1/L3 data to IDE RAID and added those PFNs to LDR.
- Worked
on SAM problem with scanlist getting large and archiving getting wedged.
(Stuart Anderson)
- Upgraded
the CIT/LHO/MIT clusters to LDG-3.5 and Glue-1.0.
- Verified
the fix to allow Condor to checkpoint jobs on the latest Linux kernel and
upgraded the CIT cluster to that kernel.
- Worked
with Phil Ehrens and Dan Kozak to ship out 140 cluster nodes to LLO, which
are now in a temporary hold in Houston
for 2 weeks as a result of Katrina.
- Worked
with Phil Ehrens and Dan Kozak to upgrade 9 IDE-RAID servers to FC4 and
stage the S3/S4 L1/L3 RDS data.
- Created
another 70GB filesystem for SAM logs and metadata dumps.
- Work
on extending the computer facilities at Caltech has started. The adjacent room is now stripped.
MIT
(Keith Bayer)
- Cluster
upgraded with latest LDG/Glue/lscsoft-user-env.
- pcraid#9
rebuilt with FC4.
- Fixed
pcraid#4 unit with degraded raids on both cards.
- Swapped
disks from node43 to a healthy cluster node as it was hanging every two
hours with no log messages - I suspect mainboard troubles as the RAM
passed memtest-x86 tests.
Hanford
(Greg Mendell)
- Orders
have been placed for tapes to archive the first year of S5 data.
- The
LDAS HVAC upgrade at LHO has started with some electrical work and
measurements for the refrigerent pipes.
- (Ben
Johnson)
- Added
two users to the cluster.
- Helped
modify the ligo.[c]sh user profiles so that they work at all LIGO lab
sites (via a switch based on /etc/ldasname).
- Printed
reams of Solaris 10 documentation. I've set up a lesson plan for myself,
which I will go through the next several days/weekend.
- Fixed
a bug in the LSCdataFind server at Caltech. Working with Brian Moe on
making an overall better "Post Processing" algorithm for the
server.
- Ran
media check on *all* (including global spare) 351x disks here. No problems
occurred.
- Received
support quote from Foundry networks for our switch. Both silver and gold
levels.
General Computing (Wallace)
MIT
(Keith)
- Fixed
several small problems with spamd firewall box
- Preparing
to bring spamd box on-line today
- Added
new postdoc Edith Innerhofer to gc
- Moved
Protel CAD pc over to highbay and ordered replacement graphics card for it
- will strip the o/s after card comes in
- Working
on rebuilding desktop pc
- Reinstalled
XP on late model thinkpad
Livingston:
(Larry for Shannon)
- Dealing
with recovery from the storm. See Livingston report.
Hanford:
(Christine)
- The
transition to the new WAN connection is going well. PNNL has tested their connection from Richland to ESnet in Seattle without any problems. They are using BGP with ESnet in order
to keep both the old ATM circuit and the new GigE circuit running
simultaneously. This allows testing
of the new circuit without any network disruption on the old circuit. I will be testing my GigE circuit today
from Noon to 2 p.m. PDT. There
should not be any network down time during the testing.
- The
backups from last night have not finished due to a disk error. I'm trying to track down the source of
the error and may need to replace the disk.
- Other
misc. user support
CIT:
(Christian)
- Barry
Barish needed to have his workstation upgraded from Office 2000 to 2003 to
match his laptop.
- Bill
Tyler's machine was infected with a virus which caused his Eudora email
not to function correctly. I was able to restore all of his emails and
deleting the infected files.
- Millikan:
replaced 2 toner cartridges on HP 5000n printer.
- Called
Dell to have the motherboard and keyboard replaced on Linda's laptop. I
also reinstalled Windows XP and restored data back to laptop.
- Installed
Office 2004 on Riccardo's laptop.
Other misc.: continued onsite software/phone support.
(Mike)
- B/A
Server Room: Swapped out KVM switch.
I monitored the server room while the chilled water system was
shutdown for maintenance.
- NTSRV:
Still working on loading a server for Primavera/Prism software to run. A
lot of work involved here.
- Ghost
Server: Freed up some disk space to run the NTSRV end of month ghost
backups.
- Started
working on loading a new NTSRV to replace our old Ghost Server.
- Patrick
Sutton: Laptop would not boot. The system files ended up getting
corrupted. I was able to correct this issue, but found that the hard disk
has bad sectors which will have to be replaced. I have called this into
Dell, and should be receiving a new hard disk sometime this week.
- Barry
Barish: Worked on backing up his laptop, plus testing some additional
peripherals to run a disk to disk back up. This has been taking around 3 +
hours to backup using ghost. Going disk to disk I was able to have a
complete backup in 54 minutes.
- Spam
Filters: Continued work, going through spam filters searching for false
positives.
- Additional
user support working with printer, networking and email issues.
- Added
additional users to wireless access point list.
(Veronica)
- LSC: Updates to the papers under review
database, minor tweaks of the code.
Addressed issues related to the last meeting's online payment
system.
- LIGO: Roster database update. Advanced LIGO schedule updates. MIT website updates. LIGO website updates.
- Project
Science: Workshop website
updates. Updates to prevent
frequently updated pages from being cached. User support.
(Larry)
- Worked
a number of procurements. Mostly, new equipment for the server room. A number of servers needed to be
upgraded and we are adding a new sandbox for the E2E group. Purchased, a few more racks. One for the
additional equipment and one to replace a larger rack to give us more
space in the server room. Purchased
a number of misc. items for other groups.
Delivered a number of received items and having Christian work on
some of the new travel laptops.
- Assisted
Mike on a number of PC issues. One interesting note is that some of the
tools for backing up and restoring files, will not work correctly unless
the disk is defragmented.
- Worked
a couple of security issues. Virus problems account for two of them and
one was a false alarm.
- Started
the monthly backups. Still a number of user directories and servers to be
backed up.
- Assisted
a couple of users with some minor application issues.
- Continue
checking out the SURF students and assisting them in getting their data
together so they can have some sort of access to it in the future.
- As
a note Keith Bayer has done some testing with a dual core unit. The dual core did improve the CPU
performance for the user. However, the disk access has proved to be a
bottle neck and Keith is now resolving that issue.
- Working
on the logistical issues concerning the upcoming work at the Synchrotron.
We will have a two month loss of network connectivity during the
construction period.
- Continue
work with the spam filters.
E-mail statistics for August 25-31, 2005
|
Mail Statistics
|
September 1, 2005
|
|
Rejected Messages
|
20,116
|
|
Virus Messages
|
652
|
|
False Positives
|
199
|
|
Accepted Messages
|
11,820
|
|
Total Messages
|
31,936
|
Advanced LIGO and Supporting R&D (Shoemaker)
Systems
from Dennis
Coyne
See also:
AL Systems web
page
AL Systems email archives
Records Of Decision or Agreement (RODA)
See also the RODA
status web page
GariLynn Billingsley submitted RODA M050397-00, "Core Optics Sizes
(including TMs, BS, FM, RM). Pending review & approval.
Intended RODAs, not yet written:
- in
situ, elevated temperature bake out
- OSEM
count RODA
- SUS/UK
work scope
- sensors
on lower quad stages/OSEMs
- BSC
optics table with more & larger holes (3/8" hoels on 1"
centers)
Requirements
nothing new
Interface Issues
See also the "Interfaces" section of the AL Systems
web page
nothing new
Systems Design/Support
Issued
questions from SUS/UK Electronics PDR committee for the SUS team to
respond. Among the questions for the
SUS/UK Electronics design are some additional electronics design/practice
guidance, which will be incorporated into a revision of the Generic
Requirements document, E010613-01
and the SUS Subsystem Universal Requirements Document, T000053-03
Vacuum Compatibility & Preparation
Residual Gas Assay (RGA)
See also the Vacuum Bake Lab
Bob Taylor
- I
have been working with Calum, Mark and Helena on the test Quad Suspension.
- I
will complete the cabling for the Quad suspension OSEMs By Friday, I have
one more cable to build.
- I
met with Lee Cardenas and He will be covering for me while I am on
vacation. (Sept. 4 to Sept. 16)
- I
have one bake job in progress for Helena
that will be scanned on Friday. The data will be available on the bake lab
web site Friday.
High-Irradiance, Contamination-Exposure Cavities
no report
Advanced LIGO Project Management
from Carol
Wilkinson
Progress Updates
Sub-system leaders are preparing progress updates for Advanced LIGO
subsystem development for the period from July 1 through August 31. Updates are
due September 10th. Estimate-to-complete information is also being
collected to flesh out the budgets for the remaining development work.
Seismic Isolation BSC Prototype
Fabrication of the seismic isolation BSC prototype has re-started after approval
by the LIGO Executive Committee on August 31, 2005. The approval to proceed is
based on the recommendations from the SEI BSC Critical review report,
LIGO-M050025-01. The prototype will be assembled and tested LASTI in late
summer and fall, 2006. The initial stand-alone testing in air and in vacuum is
planned to be complete in time for the December, 2006 integrated testing with
the suspensions test mass noise prototype being fabricated by the UK and
US suspensions teams.
Meetings & Reviews
- Future
near term planned meetings & reviews are indicated in the table below.
- Report
from SUS Requirements Update Review held on June 15, 2005 is available:
LIGO-M050216.00.
- The
final report from the SEI BSC Critical Review held in January and July,
2005 is available, LIGO-M050025-01.
SUS Ribbon/Fiber/Ear/Bonding PDR added ~Oct 19.
|
Date
|
Sub-
sys
|
Review
|
Topic(s)
|
Enabling event(s)
|
Schedule motivation
|
|
|
Jul 7
8:30-10:30 PT
|
SEI
|
BSC Critical Design Review 3
|
review basic requirements, interfaces & dynamic
coupling
|
available analysis/reports
|
timely decision on proceeding with SEI/BSC prototype for
LASTI for integration with the SUS quad prototype
|
Report complete
M-050025-01-M
|
|
Jul 11-13
|
SYS
|
SYS Mtg
|
CDS Infrastructure & HAM Isolation
Requirements
|
|
|
Report in progress
|
|
12-Jul
8-11 PT
|
SUS
|
PDR, Review 2
|
Electronics req & design; Focus is on the front end
electronics (UK)
-- limited Digital controls/electronics (US) review
|
|
|
Report in progress
|
|
Jul 19
8-10 PT
|
ISC/40m
|
40m DC Readout Review
|
DC readout experiment
|
|
|
Report in progress
|
|
~Aug, 05
|
SEI
|
HAM Critical Design Review
|
Recommendations w.r.t. HAM prototype development based on
ETF results
|
Completion of SEI/BSC critical design reviews; LSC review
of ASI HAM configuration design
|
timely decision on proceeding with SEI/HAM prototype
|
|
|
~Sep
|
SUS
|
PDR, Review 3
|
Quad design
|
Completion of the quad controls prototype assembly;
|
timely transfer, to RAL & UB efforts, of lessons
learned from the controls prototype
|
|
|
~Sep
|
IO
|
PDR Review 1
|
Faraday Isolator
|
SYS PDR?
|
|
|
|
Oct 19
|
SUS
|
SUS PDR
Review 8
|
Ribbon/Fiber/Ear/ Bonding PDR
|
Completion of the ribbon, fiber, and ear and fabrication
and bonding design and processes
|
|
|
|
~Oct 19
|
AOS
|
Stray Light Control, DRR/CD
|
|
SYS PDR?
|
primavera late finish 6/15/05
|
|
|
~Oct
|
SYS
|
PDR, Review 1
|
Engineering & Implementation ('generic') Requirements;
Interfaces
Revised Optical Layout
Optomechanical Layout
|
completion of generic requirements definition; completion of
first draft of ICD; revision to optical layout; establish integrated
opto-mechanical equipment layout
|
timely system level definition enables/helps define
subsystem reqmnts & design
|
|
|
~Oct
|
COC
|
PDR
Review 1
|
Metrology
|
Review and
select vender and in-house metrology
|
|
|
|
~Nov
|
SUS
|
PDR, Review 4
|
Quad Installation
|
Completion of installation at LASTI
|
Inform the UK
final design & noise prototype design effort ASAP
|
|
|
~Dec
|
SUS
|
PDR, Review 5
|
Triple design
|
Available SUS/US staff
|
Enable SUS/US final design phase
|
|
|
TBD
|
SUS
|
PDR, Review 7
|
BS, FM/ITM SUS design
RM design
non-cavity SUS
|
design work completion (has yet to start on FM/ITM, not
mature for RM)
|
|
|
|
TBD
|
AOS
|
Thermal Comp., DRR/CD
|
|
SYS PDR?
|
|
|
|
~Dec
|
SYS
|
PDR, Review 2
|
CDS Infrastructure
Stable Recycling Cavities
Lock Acquisition
Modulation Scheme
Power Induced Instability
|
Sufficient CDS requirements & concept work (also
7/11-13 mtg)
E2E Modeling for AL
40m Progress on Acq. & Mod.
|
CDS Infrastructure is key to subsystem electronics req.
Stable cavity is key to IO MMT design
|
|
|
~Jan
|
IO
|
PDR Review 2
|
Electro-Optic Modulator
|
|
|
|
|
~Feb
|
SUS
|
PDR, Review 6
|
quad controls prototype test results
ribbon process/design
|
completion of LASTI testing
|
timely incorporation into final design effort on the noise
prototype
|
|
|
~Mar
|
IO
|
PDR Review 3
|
Mode Matching Telescope
|
Determination of whether a stable recycling cavity will
become part of the AL
baseline
|
|
|
|
TBD
|
COC
|
PDR
Review 2
|
|
SYS PDR?
|
|
|
Seismic Isolation
From: Ken Mason kmason@ligo.mit.edu
Advanced LIGO Seismic Structure
ASI has started updating the solid model with the blade design changes. They
anticipate the design will be completed next week. The final design is then
sent back to the analysis group to verify it meets our requirements.
We recieved approval to proceed with fabrication of the BSC prototype from
the CCB. The drawings and specifications for the large machined parts along
with a list of machine shops capable of machining these parts has
been sent to Ed Jasnow.
The test stand is being built by Southern Enterprises
Suspension
From: Ken mailand kmailand@ligo.caltech.edu
I spoke to Brian Adam at NTS los
Angeles re. cleaning and baking of Adv. LIGO large
parts. Brian can clean to the CC-1246D spec., they air bake, and also have
vacuum bake capability for our large parts at Santa Clarita.
I'm designing and making brackets to mount flow meters to be added to the
laser chillers at LHO, per Cheryl Vorvick's request.
From: Rolf Bork
<rolf@ligo.caltech.edu>
Worked on improving the PCI I/O speeds in the dual CPU processor to be used
for the LASTI quad suspension. Individual PCI read/writes (64 bit words) were
taking 1.5usec/300nsec, respectively. I modified the code to use DMA accesses.
The DMA setup takes about 2 µsec, but then the 64bit words stream at
30nsec/word. Using this method, I could read all 64 channels of our ADC card in
just under 3 µsec. Still using the LSC code as the test benchmark, it runs full
up (with I/O) in 18usec.
Began work on the actual quad suspension software. I have the basic EPICS
interface code and MEDM screens up and running. I am now beginning work on the
real-time front end software.
The computer that will be used at LASTI is on order. It should arrive next
week. It is a dual Opteron, 2U rack mount unit with 4 PCI-X slots and one
legacy PCI slot.
Core Optics
From: Helena Armandula ahelena@ligo.caltech.edu
No report this week.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
The OEM Innolight NPRO laser arrived yesterday (Tuesday). It hasn't
been taken out for a test drive so far. The interface is a little
different from the Lightwave models we're more familiar with.
A common-base amplifier front end for a photodetector circuit was
breadboarded and tested. Initial problems that suggested that the
configuration would not work were tracked down to being a problem with the base
not being correctly grounded. Whilst the circuit may have provided extra
bandwidth, the circuit gain appeared to be a lot lower. The configuration
was an interesting exercise at least.
Auxiliary Optics
From: Michael Smith smith@ligo.caltech.edu
No report this week.
Other Laboratory R&D
Alberto
Last week we found many resonances of the system at high frequencies (>
10Hz) due to the intermediate structure which sustains the first two LVDTs.
Because of these the accelerometers were unable to detect the effective
response to oscillations. However the transfer function as obtained from the
LVDTs at low frequencies was good. So we worked on the prototype to make it as
it was used by Kenji Numata for the same kind of measurements. So we built a
new mechanical system to inject the noise more directly at the base of the
blades in order to avoid as much as possible the intermediate structure. We got
off the rods and now we are trying to obtain the expected plot, the one with
the saturation at 60 dB above 10 Hz. Then, if we succeed, we will add the rods
to study the effect. I think that we could do that by the and of the week.
Akiteru
Today we prepared the first TAMA SAS tower for transportation to the TAMA
west end building. It will be installed on Thursday, unless it rains.
Riccardo
Defining the HAM SAS assembly procedure for the Request For Proposal. The prototype would be factory assembled,
tuned and tested, then disassembled, UHV cleaned, reassembled retuned and
baked, ready for installation in LASTI.
Submitted HAM seismic attenuation Amaldi-6 paper available at www.ligo.caltech.edu/~desalvo/AMALDI-6-OMC-P050024.pdf
or www.ligo.caltech.edu/~desalvo/AMALDI-6-OMC-P050024.doc
John
Theoretical work is in progress to compare the mesa beam parameters to those
expected from our cavity. I have been
working in the lab trying to improve the mesa beam profile of last week. I have
managed to improve the transverse mode spectrum without a commensurate
improvement in the field distribution. Profiles are somewhat mesa-like in one
direction but gaussian in the other. I
will try switching back to dither lock this week. I have also been performing various tasks
related to Marco’s thesis, including taking various measurements in the
lab and theoretical work.
Barbara
submitted Mex-Hat interferometer Amaldi-6 paper available at www.ligo.caltech.edu/~desalvo/Amaldi6_Flat-Top-P050024.pdf
or www.ligo.caltech.edu/~desalvo/Amaldi6_Flat-Top-P050024.doc
Maria Paola
I managed to obtain a pk-pk voltage of about 7 volts, and about a 3.5 DC
voltage after the diode bridge, only using the thinner wire I have ordered (I'm
still waiting for the bigger bobbins and pot cores to be delivered), so I think
that once I get all the stuff I will be able to produce a DC voltage of 6 volts
or more. Next week I hope to finish the first step of my work (the feeding of
the motor) and to start the second one (the control of the motor).
Francesca
I worked with Alberto.
On Monday (day and night) I
took measurement of hysteresys of my system. I send a sinusoidal input on the
coil producing the driving force and I read the position by the LVDT signal. I
repeated more times the measure varying the amplitude, the frequency of the
signal and also the weight on the load, in order to see as these changes
affected the system.
Juri
I made the calculation of
diffraction losses with the LIGO-I parameters using the eigenmodes integral
equation for cylindrically symmetric mirrors and compare these results with the
clipping approximation for the Laguerre-Gauss modes. The result is that the
real diffraction losses are higher than those calculated using the clipping
approximation. The same is true for Advanced-LIGO parameters.
I’m studying the
possibility of solving numerically the eigenmodes integral equation for a
circular mirror but using Cartesian coordinates.
Chiara
I gave some help to Alberto to assembly all the stuff for his
measurement. We also worked in machine
shop to make same mechanical parts for his set up. I’m studying the project for the
Advanced LIGO Seismic Isolation System for the HAM chamber.
Valerio
I’m trying to
evaluate the transfer function matrix of my SimMechanics model of the HAM
suspension. By comparing this matrix
with the transfer functions measured on the prototypes, we’ll be able to
determine the quality of the model.
Ilaria
I have just finished to complete the pendulum in each detail. The only thing
I have not sketched yet is the counter weight. When I`ll start the simulation
with Ansys I`ll add the suitable weight to get better seismic attenuations.
Marco
I’m writing my thesis and doing some analysis on the beam shape and
propagation properties in order to compare our data with the expected beam
characteristics.
For additional information about this report, contact S. Whitcomb or P. Lindquist