Weekly Report for
Week Ending July 21, 2005
The LIGO Executive
Committee Agenda for Monday Jul7
25, 2005 will be:
(Meeting time: 10:30 am Pacific Time)
- Announcements
- Comments on Weekly Report
- LSC Issues (Saulson)
- LIGO Lab Operations
- Administration
(Lindquist)
- Sites (Raab,
Zucker, Shoemaker)
- Commissioning
(Fritschel), Detector (Coyne)
- Campus Research
Facilities
- 40 Meter
(Weinstein)
- TN, ( Libbrecht)
- LASTI (Shoemaker)
- Data Analysis and
Computing (Lazzarini)
- R&D and Advanced LIGO
(Shoemaker)
- CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION AS NEEDED
- CR
05007 for additional funding for LDAS power and HVAC at the sites
Special Items:
Special Announcements:
Weekly
Report Highlights
LSC Issues (Saulson)
no report
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Lindquist)
- Peter
Saulson has issued a call for revised MOUs due Friday, August 5, 2005 in preparation for the
MOU Review Panel meeting scheduled 22 August..
Non-LSC MOUs (Lindquist)
SITE TELECONFERENCE (Lindquist)
- A brief
site teleconference was held on Thursday, July 21, 2005. The following were among the issues
discussed.
- Science
Education Center (SEC)—the pre-bid conference was held last
Thursday. There were five potential
bidders and very few questions. An
addendum is in the works with clarifications and Davis-Bacon labor rates.
- TechMart Training—Bonnie is
working on a date for Livingston.
- The
list of assigned actions updated through May 26, 2005 will be found Here.
PROPERTY MANAGEMENT (Chargois)
>From: Ed Chargois <chargois_e@ligo.caltech.edu>
- Nothing
significant to report.
DOCUMENT CONTROL CENTER (Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
- Met
several hours with representatives from both Synergy and Xythos to identify all areas of the DCC system
requirements that needed development work in order to satisfy the stated
requirement and to determine the additional costs associated with each
item. Reviewed summary of final
costs with the DCC steering committee.
- Continued
to work on the MOU's inherited from the February
review cycle. Cleveland and I have
organized email through March and are about 2/3 of the way through the
pile. Numerous duplicate submittals
were found. This complicates the
process to determine which version is to be processed and posted. I hope to begin the posting of the MOU
and attachments on the web early next week.
- Designed
and prepared more than 25 reports for Caroline Cantley. She provided a list of nearly 30 authors
from which she needed a list of documents submitted by each since
2005. This request was completed
this afternoon.
- Working
on a draft executive summary of the activities, process, and final
recommendations of the DCC Steering Committee.
- Met
several times with Dorothy to help her with the set up and status of the MOUs. Will be
showing her how to merge multiple PDF files into one document.
- Made
calls to several shredding companies to determine the cost effectiveness
of outsourcing the shredding of the financial documents currently being
scanned. The lowest bid was $3.75
per box, which made outsourcing a best option.
- Set
up a new temp person for scanning.
Showed her how to scan, label the file, QA it, and bookmark
it. As soon as she finishes a
couple of months of account charges, I'll burn the CDs for them and add
the boxes to the pickup load for the shredding company.
- Burned
CDs of all 1998 account charges.
One set was given to Dorothy and another set retained for archive
in the DCC. This represented 12
boxes of paper ready for destruction.
When 1999 is completed, another 8 boxes will be ready to destroy as
well. Twenty boxes are required for
pickup by the shredding company, so as soon as 1999 is completed, we will
be 20 boxes lighter.
- Prepared
a report of all P and T documents in the database. All those that were in electronic format
were highlighted. Each electronic
document will be opened and a quick "search" on a word will be
initiated to determine if the document is text searchable or simply an
image file. All image files will be
OCR'd.
Additionally, documenst in the database
but not in any electronic format will be scanned and OCR'd.
Finally, a last check of the list against the shelf copies will ensure that no documents on the shelf haven't been added to the
database. Once this process
is completed, a DVD will be burned and the hard copies can either be
destroyed or put into box storage. Cleveland is working
on the P documents and I'm working on the T's. We each finished viewing and checking
about 200 documents of each category.
In anticipation of a new document management system, where text
search will be available, these two categories would be most helpful to
have 100 percent electronic ready.
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- Continued
with the organizing/processing of MOU's and
Progress Reports.
- Began
working on the multi-step task of transferring old account charges
documentation from paper to cd's. (A temp was hired this week to assist
with the project. She has been very
helpful and efficient.)
- Began
an audit of all electronic "P" documents to confirm that they
all are "OCR" ready so that text searches can be performed on
them.
- Activity:
|
Week Ending
07/21/05
|
In
|
Out
|
|
Packages
|
17
|
7
|
|
Faxes
|
17
|
13
|
FINANCIAL SYSTEMS (Cunningham, Brambila, Kaufman)
>From: Esther Cunningham <esther@ligo.caltech.edu>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Responded
to vendors' calls and met with the outside account rep for Newark who informed me of the new ROHS law going into
effect in Europe.
- Set
up the JPL work order for Helena Armandula.
- Prepared
the RFP package for LLO to replace some pipes.
- Completed
expenditure type changes as requested.
- Received
the signed Release of Claims for CSIRO and completed close out of
subcontract 1006029.
>From: Florence Kaufman <fkaufman>
- Three
Equipment Fabrication Requests have been submitted 2 for the HVAC
improvements for LDAS at the sites and one for the Pre Stabilized Laser.
- Cost
Transfer prepared per Terry Gunter's request to reclassify expenditure to
PMA discretionary account.
- Requested
correction of expenditure type for p-card purchase inappropriately
classified as Equipment.
- Sent
e-mail notifying Property Services department that p-card purchases should
be aggregated in the property records because the purchases, even though
made from different vendors, were part of the same system.
- Updated
projection for FY05 based on data through June 2005.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone
<gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow
<jasnow@ligo.caltech.edu>
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
- Processed
the paper work for thirty-six (36) new/revised trips. At this time there are eight (8) trips
completed but awaiting the necessary paper work to enter the P-Card system
and five (5) new trips that need to be completed and ticketed before the
paper work can be completed (hotel and car reservations made and prepaid
by my P-Card as well as advance checks made out. Assisted several LIGO people with their
travel arrangements using their P-Cards and made several reservations for
outside visitors coming to LIGO/Caltech or one of the LIGO sites.
- Completed
seven (7) Expense Reports and there are twenty-three (23) reports yet to
be done. I continue to contact
travelers who have outstanding Expense Reports (more than one (1) month
old) to ask for their cooperation in sending me their receipts so that
these can be closed in a timely manner.
Presently there are five (5) reports more than 30 days old. Travel Audit's new policy of accepting
only original signatures seriously holds up the process of closing
reports. I have zero (0) reports
awaiting signature at this time.
Reconciled seventy-eight (78) P-Card charges for the week requiring
telephoning hotels and car rental agencies to verify which traveler used
my card and for what amount.
>
- Entered
data for Annual Report updating on FastLane.
- Updated
existing web pages for Barry.
Reconciled previous travel reimbursements. Met with outside departments as training
resources. Continued work on
upcoming travel arrangements for Barry.
>Dorothy Lloyd
- No
report.
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
PROPOSALS and REPORTS (Lindquist)
LIGO must submit an Annual Report for Operations by August 1, 2005 and this
annual report must be accompanied by a request for a two year extension (FY
2007 and FY 2008) as well as a justification for supplemental funding.
The final draft of the Annual Report is being entered into FastLane. We are working on the Proposal for an
Extension and Supplement.
DCC Steering Committee (Lindquist)
We met this week to discuss current status and plans after having had
several weeks without a meeting. The
committee is basically ready to make a recommendation to the executive
committee. Linda Turner is preparing a
written summary of the document management committee’s findings and
recommendation.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
- Change
Request CR-050007 requesting additional funding for power and HVAC for LDAS
at the sites has been distributed and will be discussed during the
executive committee meeting on Monday, July 25, 2005.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- The next
Staffing Committee meeting is scheduled for Monday, August 29, 2005.
- A
Staffing Committee meeting was held on Monday, July 18. The minutes and action items from that
Staffing Committee meeting have been posted on the SC web page.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
Nothing significant to report for Safety and QA (I've been sick).
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary
of Commissioning Activities at LIGO Hanford
Observatory (Landry)
A decision on when to open
the gate valves on the 4k vertex will be made next Monday. Four ion
pumps are speeding the reduction in pressure, currently at 5e-8 Torr.
4K IFO
- progress on photon calibrators: EX was reinstalled
after a layout change, and access control sorted out. Note that as
per EY, arm cavity baffle structures occult a beam centered on the ETM, so
that the PC laser has to land about 4cm off-center of the end test mass.
2K IFO
- Work
on the 2k has restored some of the lost binary inspiral
range. The placement of a black glass beam dump on an ISCT9
periscope restored us back to 2.9Mpc. Tuning
of MICH
and PRC loops brought us further, to 3.3Mpc. Note that Sensemon ranges are out of date, and new response and
sensing functions will be produced shortly - but this week saw the best
binary inspiral ranges achieved on the 2k, those
on the order of 4.6Mpc (from Autocal and NoiseModel). The above-noted tuning of MICH and PRC loops
involved offloading some of the long-term alignment drifts of the FM's
onto the BS and RM. The 4.6Mpc noise spectrum is better than S4,
partly due to the recent oscillator change, plus double the power since
February (now, 3W into the MC, whereas during S4 we were at 1.4W).
- Thermal
compensation (TCS) work: the servo works on a stable, reasonable 2k IFO,
in the sense that it maintains a constant
calibration line amplitude. Inspiral
ranges with TCS were variable. Later in the week, we ran without
TCS and things improved - ranges were more stable.
- Absolutely
no singing in the mid-stations: acoustic coupling and failed 'pinky tests'
(where the tester gives a light pinky-push to transmission monitor piers,
etc) suggested the midstations as noisy coupling
sites. Multiple scattered light sites were found in the midstation end-test mass monitor QPD boxes.
Beams were dumped and the noise improved. As noted above, ranges in
excess of 4.5Mpc have been recorded e.g. this link
(an aside: the recently modified 2k strain goal yields a BI range of
8.8Mpc; scaling the 4k S5 goal/SRD (10Mpc/13.9Mpc) gives 6.3Mpc as an
informal 2k target for S5 (although there is no formal goal for H2 for the
run). Coherence
between AS_Q and the QPDs, before and after
dumping the stray beams, were recorded, showing
excellent improvements at acoustic frequencies.
- photon
calibrator work: access control was readied,
other progress was summarized,
- The
laser down for a while for 7kHz peak hunt
, still awaiting result as IFO to relock in low noise. More
on this peak.
- The
REFL 2 path on ISCT7 was reworked.
The REFL LO was found to be trouble
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
L1 Interferometer (Frolov)
Interferometer running is still limited by undiagnosed
angular control instability. Low-noise
mode can be gained with 3 W input power, but one to two
hours after acquisition the alignment drifts and the alignment controls can't
keep up with it. Diagnostics in progress.
The input test mass angular control bias
modules were found to have an intermittent failure mode which came from
insufficient protection of the PA85 amplifier. Modifications were made to the
bias electronics to eliminate this problem.
##MZ An ECN is being prepared to prescribe tests/mitigation for
this failure mode at LHO##
The 5 V power supply for the length and angle
sensing and control electronics was reworked once again to remove oscillations.
The Mode Cleaner WFS slow relief servo was
commissioned. This servo keeps the input beam aligned to the MC at DC when the
input power is low. When power is increased above 1 W the MC axis is aligned to
the input beam to counteracts the radiation pressure.
Education and Outreach (Thacker)
Conducted education outreach to two summer
camp groups Provided professional development to 15 middle school science
teachers.
Site Safety and Security (Riesen)
No report.
LLO General Computing and LIGO Computing Security (Roddy)
No report.
HPLF, Optics Modeling, Data Analysis and L1 Commissioning (Franzen)
1) HPLF:
The staff of IPG Photonics could not find any problem with the 100 W laser. They continue to test it and will also performed some
maintenance before shipping it back to us.
2) Have
been testing the MC WFS relief code.
3) Briefly
discussed the REFL port beam stabilization system with Rolf Bork who is
visiting LLO. Ordered black glass from Edmund Optics which will be used to
reduce back reflection of the transmitted part of the beam passing through the
periscope mirrors.
Mechanical Engineering (Spjeld)
AdL Quad SUS Installation Fixtures
- Completing
manufacturing drawings
AdL SEI Engineering
- Working
with Mike Pedraza on checking in ASI documents
to vault
LIGO Outreach Building
- Pendulum Exhibit
- Had
to redesign slightly due to interference with support structure
- Completing
design illustrations
- Working
on manufacturing drawings for quote
General Engineering
- Checking
new HAM door removal tooling in SW assembly
CDS code (Khan)
1) Helping
Sam and Valera
in implementing the Bull's eye detector. THe pico motor controller part has been added to the l1iool0
and database portion has been added to the l1ascauxl0.
2) Working
with Rolf on CDS upgrade.
LDAS/Condor Sysadmin and Burst Analysis (Yakushin)
The interferometer running is still limited
by the angular control instability. The
low noise mode can be gained with 3 W input power but
for time period of one to two hours after that the alignment drifts and the
alignment controls can't keep up with it.
The input test mass angular control bias modules were found to have an
intermittent failure mode which came from insufficient protection of the PA85 amplifier.
The modifications were made to the bias electronics to eliminate this problem.
The 5 V power supply for the length and angle
sensing and control electronics was reworked once again to remove the
oscillation.
The Mode Cleaner WFS slow relief servo was
commissioned. This servo keeps the input beam aligned to the MC at DC when the
input power is low. When power is increased above 1 W the MC axis is aligned to
the input beam to counteract the radiation pressure.
Initial LIGO Detector Science & Engineering (Coyne)
CDS
see also the CDS weekly meeting minutes in the commissioning archives
CDS Software
Rolf Bork
- Installed
new HEPI software at LLO this week. The new software incorporates tilt
correction feedback.
- Updated
all the front end code at LLO to include the latest library revisions,
including "bumpless" filter coeff reload. Also updated the ASC/IOO code with the
PIN ramping feature.
CDS Hardware
Jay Heefner
Refl Beam Stabilization: Began putting together the software for the LLO
beam stabilization system.
Ben Abbott
LSC RFPD: I'm expecting the boxes for the RFPDs to
arrive any day now. The boards will be sent off for stuffing shortly.
DMT
John Zweizig
This week I brought up the new V40Z DMT machines at LHO and installed the
development environment and DMT software for the new architecture. The current
DMT version was tagged gds-2.10.4. In addition to adding the new machines, the
LHO GDS (broadcast) network was upgraded to use Jumbo ethernet
frames (this required replacing the switch and the network interface cards on all
the GDSnet machines) and the DMT cluster was
reconfigured for better security and reliability.
PSL
PeterKing
I have been having some problems with a high voltage amplifier due to a few mis-stuffed parts and a solder bridge. These were
corrected and the amplifier now works as expected, although the output voltage
noise is a little higher than what I had expected.
ITM07 Optic
Helena Armandula
We can capture images from the dark field microscope once again. The video
camera needs to be replaced. At this time,
we have one on loan from the vendor for a few weeks until we procure a new
one. Since the camera model changed,
we'll need some new adapters also. Waiting for an estimate.
Baffle Inspection: I inspected the glass baffle and I did see a film. The
film looks more like stains, it was not even and, I am sure, the result of
cleaning. I see this effect when a
solvent does not dry properly. These
defects are seen on both sides of the glass.
Some are prominent, some more subdued.
Dust is also observed, not in the same amount as seen on the mirror,
because, the wrapping used for shipping removed quite a bit of it.
ITM07
An account has been set with the Analytical Chemistry Lab at JPL to perform
FTIR analysis on the mirror's surface.
40 Meter Interferometer (Weinstein)
IFO commissioning
- Rana, Rob, Ryan, Seiji and Osamu measured the
contribution of frequency noise to TRX when the IFO is locked with
DRMI+2arm with DC-offset on CARM. Coherence is pretty close to 1 around
20Hz and 100Hz. This can be a cause of losing lock when the CARM offset is
reduced. Steve and Osamu checked the contribution to frequency noise from
the Mach-Zehnder, and found it to be not
significant. Effort is now going in to reducing the frequency noise by
implementing a common mode servo.
- Rana discovered that the common mode servo "was
doomed" because the PSL frequency stability pickoff was misaligned
through thr AOM. He and Osamu realigned the beam
through the EOM and AOM to the reference cavity, ensuring that the beam
was double-passed through the AOM as it should be. They then readjusted
the gains on the PMC and FSS servos. The MC is now locking fine, and Osamu
is working on the common mode servo.
- Rob,
Rana and Osamu made a script called 'c1_cmstep'
to switch off CARM and handover control of L+ to the LSC-MC path. It seems
to work, but is not very stable; work ongoing.
- The
X arm has always been noiser than the Y arm.
Osamu measured the fluctuations are 3 to 8 times noisier than Y arm below
10Hz. This suggests that the damping of ITMX or ETMX is not performing
well, or maybe the seismic noise is much worse (directionality).
- Steve,
Rana, Ryan and Osamu tried tilting the optical
table on which ITMX sits. The three ITMX stack legs, which were on Stacis, were put on hard supports instead. Small (~0.5
mm) adjustments were made of the leg heights to tilt the stack and bring
the sensor values to with in nominal (0.8-0.9). The X arm noise did not
improve significantly.
- Dan
shut down the damping of all the suspensions for a night and took new data
on the suspension frequencies. There was no significant change to the
frequencies of the ITMX modes after the stack was tilted.
- David
Blair and Ju Li compared the Xarm
noise as seen at C1:LSC-XARM_OUT with and without
the side OSEM damping. The Xarm noise is
distinctly larger than Yarm below about 10Hz and
it was unchanged. This conclusively proves that the excess noise in the
X-arm is not caused by cross coupling of the side OSEM.
IFO modeling and DC detection development
- There
has been lots of work on the design of the DC readout system for the 40m,
in praparation for a design review.
- Ben
Abbott is proceeding with the design of the in-vac
DC photodiodes, including the mounts (working with Mike Smith) and the in-vac electronics (working with Rana
to be sure that it's appropriate for the currently envisioned needs).
- Jay
prepared a block diagram of the electronics required for the DC readout
system. Most of the controls uses existing spare
channels in our front-end system and EPICS system.
- Ben
sent off the gerber files to PCB Express for the
Piezo-Jena adapter boards for the in-vac PZTs that will be coming
in the near future. These are the same files as were sent off for the
boards currently installed on the in-vac
steering PZTs.
- Rob
and Marcus, along with Alan and Mike Smith, have developed the top-level
design parameters for the output mode cleaner, including the length,
layout, ROC of the curved mirror, finesse, etc.
- Mike
Smith is proceeding with the design, and preparation of POs, for the two in-vac PZT steering mirrors, output mode matching
telescope (OMMT), output mode cleaner (OMC), mounts for in-vac DC photodiodes, and auxiliary in-vac optics.
- We
had a review of the plans for DC readout at the 40m. Slides are here, in ppt and pdf.
The review committee chair, Ken Strain, is assembling the report. The
biggest concerns were about losses and scattering in the optical
components, especially the choice of CVI mirrors for the output mode
cleaner (they are higher loss and higher scattering than REO mirrors, but
require a much shorter lead time and are much less expensive). A common
refrain was: OK, try doing something cheap and quick, learn your lessons,
then do it better in a next iteration.
Thermal Noise Interferometer (Black)
No report.
LASTI (Ottaway)
SOS Test Cavity
This week we spend some time resurrecting our mini-test cavity. This will be
used to confirm the frequency noise performance of the PSL and will start the
build-up of control systems for the QND measurements using ponderomtotive
squeezing. A saturation problem was identified in one of the SOS controllers.
This will need additional study to determine its cause.
Modal and Estimator Control (Ruet)
I have finished to write the document about the
modal control and estimator loop (The idea we had to reduce the re-injected
sensor noise in advanced LIGO suspensions). I am waiting for comment from some readers
before I can make it a bit more official.
HAM Chamber Characterization (Ruet)
I have now started working on the HAM 10 Hz noise enhancement. We know this
noise is very likely coming from the crossbeam (it has been measured and tested
here in LASTI). I am now working on FEA for the gallwings
to see if we can identify the problem in siumation
and know how to improve the design. So far I have trouble with the software and
the meshing, the software works a lot easier with solid elements but those are
really inaccurate to analyze thin elements like the gallwing's
walls. It works a lot better with plate meshing but in that case I have trouble
to make a complete simulation with the tubes...So far it's either one or the
other, with advantages and drawbacks for both. I am still working on it.
Data Analysis and Computing (Anderson for Lazzarini)
Data Analysis Activities (Anderson)
(Greg Mendell)
I have been working with Joe Betzwieser and Mike
Landry to track down the one Hz harmonics found in the S4 LHO and LLO data. A
report will be given at next Tuesdays PULG telecon.
The next StackSlide code review is Friday, July 22,
at 9:15 PDT.
(Igor Yakushin)
1) Processed
SG18 and SG19 MDC frames with waveburst and
discovered that there is a problem with them: wrong hrss,
wrong beam pattern coefficients. PSU group is working to correct MDC frames.
2) Trying
to understand why we observe high variability of noise in LIGO-GEO waveburst triggers.
(Philip Charlton)
- Fixed
a parsing bug and some memory leaks in the metaio
library. Extended and updated
documentation for metaio and added more tests.
- Made
new post-processing Matlab script for the
stochastic analysis which reads in the same parameter file and job file
used by the analysis, so that we will always use a consistent set of
parameters. Have started testing the new pipeline with new V7 segment list
using Xavi's calibrated strain frame files.
(Shourov Chatterji)
- Extending
Q Pipeline code to allow more robust consistency tests for the S3/S4
double coincidence H1/H2 analysis.
- Continued
targeted sky search code development with S. Hormoz and coherent network analysis code
development with P. Sutton, A. Searle, L. Stein, and M. Tinto.
- Participated
in kleineWelle code review with L. Blackburn, A.
DeCridico, J. Zweizig,
and E. Katsvanounidis.
(Patrick Sutton)
Good news: I posted the LIGO-TAMA
S2-DT9 un-triggered bursts search paper to gr-qc/0507081. I've spent the rest of the week working on
efficient choices of sky positions to test in the coherent network analysis
problem, and in getting Maria Principe (new SURF student) started on making a
network simulation package.
(Antony
Searle)
Seminar preparation and delivery took up some time this week. Pipeline
significantly optimised, now runs about 20x faster
than original version. Several optimisations
still being worked on, including sky maps facilitating the reuse of expensive timeshifts, and trying a range alternative timeshifting implementation ideas.
Simulation and Modeling (Bhawal)
Code Developments
(Hiro)
- Modeler:
Resumed code development of the fast version of the dual recycling module.
- FFT:
Resumed the design of the major revision of the FFT program to be used for
the advanced LIGO simulation.
Alfi
(Melody) Continuing with fixing the Problem Reports (PRs). Fixed PRs 460, 467, and 470.
Investigating possible solutions for PR 483 - "check into new way to
display java remotely"
LDAS Software Systems (Blackburn)
LDAS
The GPSTime information used by LDAS has been
updated for the leap second on January 1, 2006 (PR#2856). This includes
modifications to the General::GPSTime class and leapsecond file used by cmonClient.
The blindness to files on /archive file system has been resolved (PR#2722).
The fix required releasing a mutex lock when opening
of a directory failed. An issue with unbalanced curly braces was also resolved.
LCDG upgrades:
1) OpenSSL was upgraded to version 0.9.8.
2) lftp was upgraded to version
3.2.1.
3) FrameL was upgraded to version 6r19.
4) FireFox was upgraded to version 1.0.5.
Currently working on failures experienced by Greg Mendel
while testing his createrds script on ldas-dev.
cmonClient - closed
PR2874 - submit button on a loop test did not reset from cancel. Force deletion
of a job directory if
it fails to work around file system problem on dev.
datacondAPI - fixed
cleaning of defunctJobs if there are no active jobs
in manager.
diskcacheAPI - closed PR 2855
- do not send duplicate email with the specified time limit
frameAPI - fixed cleaning
of defunctJobs if there are no active jobs in
manager.
System and Integration Testing: ran system test for ldas
build 1.6.36 and updated test results to dev and cvs.
Fixed fracc6.tcl verification for Proc tRange
data. Got a set of results with fr2ilwd by generating
file files with one set of data type via FrSample.
Wrote up resource file PR for mpiAPI
for use of FC3 LAM. Updated tandem-iii and tandem-iv mpi resource to use FC3 LAM.
TCLGLOBUS
Completed GASS Copy documentation (Robodoc
& tutorial).
Globus GASS Transfer
1) A
total of 64 functions from globus_gass_transfer.h
2) 11
functions associated with buffer management have been SWIG-wrapped manually.
Still writing Tcl test cases to
exercise synchronous and asynchronous GASS Transfer but/get/send_bytes/receive_bytes
functions.
OSG
Worked with the GriPhyN-LIGO
team to port the inspiral search code onto the OSG.
Significant progress was made with running the code on OSG, though a few issues
still remain. It was tremendously rewarding to see a LIGO Science Collaboration
search code utilizing computer cycles at Atlas, CMS, and other OSG grid sites.
For the OSG Consortium Meeting and OSG Roll Out of July 20, the test bed site was verified in compliance with OSG
requirements as determined by the site_verify script
run locally. The resource provider form was submitted to the OSG for the test
bed site. OSG personnel added the test bed site to the OSG ITB web page and
configured the GridCat application for remote
testing. GridCat indicates that the Globus gatekeeper, gsiftp and
Condor are available and that the proper locations for shared file systems are
published.
Debugged several Virtual Organization credential problems
including duplicate credentials for one individual added to a VOMS server and
an incorrect X.509 certificate being used by a LIGO investigator. This
indicates a need for a software daemon that daily examines both the gatekeeper
log and the tomcat Voms log to determine
authentication failure events due to credential problems. This software could
be of significant value in reducing Mean Time To
Repair (MTTR) in these instances.
Used VRVS conference framework and OSG power point
presentations for remote listening to plenary sessions of the OSG Consortium
meeting.
LDAS System Administration (Anderson)
Caltech
(Dan Kozak)
- Assisted
in converting LHO's /dmt
to use md devices. This is the last QFS filesystem
that needed this change.
- Cleaned
up old fibres and in Booth.
- Mounted
/archive on samtest.
- Moved
/archive/S2 to /archive/frames/S2, fixed up pfns
in RLS.
- Moved
/archive/postS3 to /archive/frames/A3.
- Continued
to replace failing 3510 disks at CIT as fast as Sun can ship them.
- Cleaned
up after node190 failure (recopied S4 L1 data, started md5sum'ing the
other frame data on the node).
- Provided
some assistance for LLO's fb0_frames 3510
upgrade.
(Phil Ehrens)
- Installed
new RMA motherboard into LDAS-CIT node 267 and returned it to the cluster.
Returned LDAS-TEST node 4 to the LDAS-TEST cluster (it had been serving as
LDAS-CIT node267 while that machine was out of service).
- Finished
testing dimm's using LDAS-TEST node 8 and
returned it to the cluster. 6 512MB
dimms were returned to Transcend under warranty.
- Transferred
5 computers and 2 monitors to Ed Chargois for
disposal.
- Cleaned
up shelves in Millikan 6th floor equipt room and moved several out-of-service computers
to the shelves in that room.
- Added
second HD to machine 'dziban' and moved it to
the Millikan 6th floor equipt
room, placing it on UPS power. Dziban is our Subversion (svn)
server. This machine was formerly
under my desk.
- Presented
a box full of 10-40 Gb
Hard Drives to Larry Wallace. These drives were stripped from the
computers that were marked for disposal. The memory dimms
from the computers marked for disposal were added to desktop machines in Millikan.
- Various
cluster related admin tasks. 4 drives were replaced within the last week!
- Minor
code written for LDAS to support use of Fedora Core LAM rpm based install.
- Supported
Duncan Brown's OSG (?) demonstration prep on machine kitalpha.
(Stuart Anderson)
- Reconnected
samtest to the SAN for Solaris10 testing of
SAM-QFS after a broken fiber pair between Bridge and Booth was repaired.
- Working
on various LDAS hardware upgrade plans.
- Reported
a few more Condor problems.
- Started
discussing LIGO/CACR/TeraVoxel collaboration in
light of Terragrid leaving Caltech.
- Tracking
widespread problem with FC3 2.6.12 kernel failing to boot on SMP machines,
e.g., https://bugzilla.redhat.com/bugzilla/show_bug.cgi?id=163437
- Helping
to coordinate LDAS-1.7.0 release and transition to FC3 version of LAM.
- Finished
move cluster users home directories from IDE-RAID to SAM-QFS.
MIT
(Keith Bayer)
- Reviewing
computer situation in NW17-017 w/r/t new cluster nodes from Caltech.
- Giving
up on 2 7500 ATA 3Ware cards in pcraid3 - request either the purchase of
new ATA cards or upgrade to SATA and purchase SATA drives.
- Installed
(and rebooted) new packages on ldas-grid
Livingston
(Igor Yakushin)
- Discussing
with Mike, Allen, Rusyl, Joe, Shannon, Stuart
and Albert the LDAS upgrade plan at LLO;
- Upgraded
SES, controller firmware and disk firmware on CDS 3510 unit; the first two
attempts to do so failed because the baud rate on the 3510's serial port
was set to an unexpected value.
Hanford
(Greg Mendell)
- I am
currently working with LDAS to test createRDS
jobs in anticipation of the upcoming new release of LDAS.
(Ben Johnson)
- Replaced
one bad T3 disk.
- Move of
ldas-pcdev1 to the new server will be complete today.
- Moved
the 3 biggest users of /dso-test to
/archive/home this week. The moves
went smoothly.
- Helped
out move from postS3 to frames/postS3 naming scheme at the 3 labs.
- Completed
remake of /dmt filesystem.
It now supports small files.
- Helped
Greg Debug some condor DAG log file problems.
Apparently, the code and/or Linux kernel and/or Solaris NFS now explicitly
states that condor dagman
can't get a proper lock on the log files now, when they're mounted on an
NFS filesystem.
General Computing (Wallace)
MIT:
(Keith)
- Worked
on print spooler (lprng) and trouble handling
text documents experimenting with the built-in filter 'ifhp'
along with external 'file' code that can handle stdin
files (Solaris /bin/file cannot)
- Continuing
work on spamd e-mail filter
Livingston:
(Shannon)
Will report next week.
Hanford:
(Christine)
- Network
usage can be seen at http://www.ligo-wa.caltech.edu/~christin/mrtg/198.129.208.1_198.129.78.122.html
- This
has been a busy week concerning the upcoming network upgrade. PNNL reports that they have already
tested their new hardware and fiber and everything seems to be
stable. PNNL will be ready to start
testing the Ligo connection in mid Aug. I asked that this be postponed until
after the LSC meeting. Several
options for a backup network have emerged.
I'm currently talking with ESnet about IP
addresses. ESnet
will not allow their IP addresses to be announced over a commercial ISP, however they will allow the IP addresses of an ISP
to be announced over the ESnet network. Still waiting for a formal quote and
proposal from PNNL for the primary network connection.
- Spent
some time trying to get going with the new TechMart
purchasing system.
- Configuring
a NAT router to be used at the LSC.
I'm also replacing the wireless access points in the auditorium.
CIT:
(Christian)
- East Bridge: setup computers for new
temp users that started this week. Also moved fax/scanner from 3 floor to basement.
- Millikan: replaced 3 toner cartridges on HP 5000n printer.
- Synchrotron:
Inventory of computers and updated the LIGO IP & Inventory Database.
- 40
Meter: Inventory of computers and
updated the Ligo IP & Inventory Database.
- RMA'd two hard drives back to the manufacture for
replacement. Both drives had bad sectors and couldn't be formatted. Other misc. onsite software/phone
support.
(Mike)
- Synchrotron:
Worked on surf student workstations trying to get a Data Acquisition cards
to work. I tried loading these cards on an XP installation, and got no
where. I ended up loading win 2000 with the current drivers from National
Instruments, and making some modifications to the registry, which worked.
- Surf
Students: setting up user accounts, trouble shooting network, email, and
software issues.
- Barry
Barish: Worked on his backup laptop trying to
fix a hardware issue. I ended up
swapping out the hard disk to another IBM that is almost identical to what
he had. Backed up his new laptop, but came across some bad sectors which
made it very difficult to backup. I successfully manage to complete this
backup. I will have to get his
drive replaced. Larry ordered an additional drive with the unit, however, it is on back order.
- Bridge
Annex Server Room: Larry and I swapped out a two UPS, and moved DHCP125
into the server room. I also
re-routed some network cables.
- Spam
filters: Working the spam filters with Larry.
- Ken Mailand: His workstation is having a hardware issue.
This looks like the hard disk is dying. I was able to get his drive to
startup again which allowed Ken back up his data. I am currently trying to
get a ghost image of his drive to dump to another drive. This is an on
going project.
- Ed Chargois: I gave Ed a hand getting surplus equipment
ready for transportation to pick up.
- Printers:
Took an inventory of all printers to restock print cartridges and other
supplies. I placed an order with Gina Salone.
- Other
misc. user/phone support.
(Veronica)
- LIGO: High-resolution images for a
publisher. Roster database
updates. Website updates. Video compression /conversion per user
request. Other web-related user
support.
- LSC: Posted new MOU templates, papers for
review. Other website updates. August meeting website updates, online
registration application troubleshooting and updates.
- Project
Science: Issues related to migrating
the website to be hosted at ITS.
- CaJAGWR: User
support.
(Larry)
- Purchasing
activities have varied this week. Reconciliation,
had a few items that took a couple of hours to get worked out to get the
numbers to match. Purchased a
number of cables, mice and other items in support of existing
equipment. Cleared up a printer
cartridge order for Mike.
- Finally,
HP is sending out a replacement part for a printer. Evidently, even after
the warranty paperwork is sent in, it still takes a couple of weeks for it
to get through their system.
Anyway, the printer for the 40M should be fixed by next week.
- Still
working air-conditioning issues. It looks like it will be awhile before we
have any resolution on that situation.
- Cleared
up a few issues in the sub-basement labs. They are setup to get a edge-switch installed. Fixed a couple of the PC's and got the
network connection going on one by resetting the configuration of the
unit.
- Assisted
a number of SURF students with different applications. Also, continuing work
on getting their computers configured for the work they are doing.
- Setup
a number of new user accounts for visitors and more SURF students.
- Assisted
Mike and Christian with a number of different PC related items.
- Assisted
the DCC with the temporary scanning setup.
Also, still working with the committee to determine the new DCC s/w
package to be used.
- Reconfigured
a couple of server systems while swapping out the UPS units and the
batteries of a UPS in the server room.
During the swap out discovered that a couple of servers are
starting to have problems and will need to be replaced in the not too far
future.
|
Mail Statistics
|
July 14-20, 2005
|
|
Rejected Messages
|
22,157
|
|
Virus Messages
|
437
|
|
False Positives
|
212
|
|
Accepted Messages
|
12,227
|
|
Total Messages
|
34,494
|
Advanced LIGO and Supporting R&D (Shoemaker)
Suspension
From: Janeen Romie <romie_j@ligo.caltech.edu>
Advanced LIGO Suspensions
Ian Wilmut and Joe O'Dell from RAL joined us this last
week to support the build of the quadruple pendulum suspension. We thank them
for their visit. As they had to leave yesterday afternoon, we pushed the
machine shops to provide us with the necessary parts to assemble the entire
quad suspension. We suspended the masses for a short time. You can see the quad
in the clean room on the video cam at: http://131.215.114.242/view/index.shtml
Other pictures of the quad being built may be found at:
http://www.ligo.caltech.edu/~ctorrie/pictures/QUAD%20JULY%2018th%202005/QuadJULY18th2005.html
http://www.ligo.caltech.edu/~ctorrie/pictures/QUAD%20JULY%209th%202005/QuadJULY9th2005.html
Stuart Aston from the University
of Birmingham will be
joining us on Monday for wiring of the electrostatic drive and setting up the
cabling for the osems, global and local. Bob Taylor
will also be supporting.
The spacer parts for the LASTI mode cleaner should be ready tomorrow. I'll
bring them to Bob for cleaning and baking. I'll send them to MIT after that.
The spacer is used to bring the optic up to quad optic height.
Last thursday, I had a
meeting with Carol and Caroline on the suspension schedule update.
From: ctorrie ctorrie@ligo.caltech.edu
From: Ken mailand kmailand@ligo.caltech.edu
From: Jay Heefner <jay@ligo.caltech.edu>
AdL SUS
- Began
system layout drawings for possible LASTI quad controls in light of last
week's AdL CDS architecture discussions.
AdL SEI
- Received
GS-13 pre-amp boards. Now waiting for a decision as to what amplifier
configuration to use.
- Received
remaining 10 capacitive position sensors and amplifiers from ADE following
upgrade.
- Continued
low frequency noise testing of the first 4 capacitive position sensors and
amps.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
AdvLIGO PSL
I received information from JenOptik about the
particular laser diodes used by LZH in the 200-W laser. There are now two
variants, a 30-W model and a 45-W model. The small quantity price is
approximately 2600 euros for the lower power version.
Shally Saraf informed me
that the output power of the laser on loan to Stanford is now approximately 6
W. He wanted to know what to do in order to increase the power back up to
10 W, other than the brute force solution of increasing the power amplifier
diode current. The last time we looked at the laser was just over 3 years
ago when the output power was 10 W.
There is still plenty of margin left on both
the NPRO diode current and the amplifier diode current.
Auxiliary Optics
From: Michael Smith <smith@ligo.caltech.edu>
OPTLEV
Aabeg has aligned the beam through the Oplev 3, 14meter EFL receiver lens assembly. He measured the
output spot size with a beam scanner. The output spot size is too large, and
will be reduced by reducing the input beam size with a beam reducing telescope.
Ben Abbott is in the process of providing the QPD read-out electronics.
SLC
Shasta has aligned the the BRDF apparatus. The AOM
driver failed and Peter King repaired it. Peter is helping her with the
amplitude modulation of the AOM output beam.
Other Laboratory R&D
Riccardo
Preparing the bid requests for the production of the LASTI
OMC HAM SAS system. Looking into the control problems with the help of Valerio Boschi and Virgo experts.
Juri
I calculated the diffraction losses of the first twenty modes of a Fabry-Perot cavity with Mexican hat mirrors using numerical
solutions of the eigenmodes equation for a cavity
with arbitrary cylindrically symmetric mirrors. I used the same program with
spherical mirrors in order to evaluate the difference between the “real”
diffraction losses and that found using the clipping approximation on the Laguerre-Gauss or Hermite-Gauss
expressions of the higher order modes of a spherical resonator. The results
show that using the nominal parameters for Advanced-LIGO spherical mirrors and
using Mexican hat mirrors which support a fundamental Mesa beam with the same diffraction losses,
the higher order modes of the Mexican hat mirrors cavity have smaller (even
more than one order of magnitude) diffraction losses. Now I’m studying the
generalization of the ABCD propagation law for general optical beam (Belanger
et al.) in order to apply this formalism to our Mesa beam experiment.
Francesca
In order to apply the Real Time control PID to Maddalena’s
thesis GAS filter system I tested a Labview program
simulating the input voltage of a LVDT with a voltage generator, and reading
the computer generated output voltage with an oscilloscope. I modified and run
this program in order to obtain the desiderate results. I found that Lab View
is able to make a real time control under 1 KHz (provided the computer is not
running other programs, if its only priority is to acquire and control the LVDT
voltage). During the test, we observed that the output signal was much too
noisy, we think that the a bit in the DAC acquisition
computer card is blasted, and so I will have to change it.
Chiara
I’m working on the mechanical set-up for the test of horizontal
attenuation system with four inverted pendula. In
order to better excite the system I’ll put under the bottom level of the
apparatus the three old “legs” obtained from the three inverted pendula used in the first test. Now I’m making
aluminum safety supports for these IP legs.
Marco (19Jul)
Coupling efficiency measurements were very affected by misalignments: we
have not been able to recover any cylindrical symmetry in the resonating beam
yet. Maximum coupling is about 20%, but it was achieved by different transverse
beam patterns. Thus, we are continuing these measurements in the lab.
John
I’m using various methods to determine the finesse of the cavity from
experimental data. These include fitting the Airy function to cavity spectra
and analyzing properties of the mirrors.
The computer in the OTF was damaged this week and all data was lost -
including our LabVIEW data acquisition program. I
have written an upgraded version which displays real time data and allows us to
perform frequency analyses in the lab. This will be beneficial if structural
resonances are to be studied in the future.
The previously designed mode-matching telescope did not form a practical
solution. The alignment tolerances of the lenses were too small. Having
discussed the problem with Mike Smith I am now working on a new solution.
Justin, Sean:
(last week report)
This week we have continued working on the 3D ANSYS analysis of the complete
system including both flex joints, the intermediate mass, and the test mass. We
have also been preparing for the experimental tests of the mono-crystalline
silicon flex joints.
Bill Johnson last week reported to us that reanalyzing our own Q-factor data
in LM001, he found the losses completely compatible with 1000 ppm of Hydrogen into the zirconium of the alloy, which is
natural to be there. He knows how to get it out of there, or use a non hydrogen
adsorbing formula (platinum instead of zyrconium) so
he anticipated a possible increase of Q factor of one, two or even more orders
of magnitude.
Jan Schroers offered to test on our blades a new
technique of pressure molding a LM001-like glassy metal. A
technique that would allow fabrication of springs of any size, up to tons if
needed. We will test soon tha blades that he
will try out for us.
Anamaria and David:
The glassy metal blades were assembled last week and we hung an amazing
amount of weight on them. The approximate weights were 3.5kg for Cu-Be, 10kg
for maraging, 20 for lm002 and 30 for lm001. We
should receive the Lvdt's soon and then the setup
will be complete.
Comment from Riccardo: Anamaria
and David, you are right, this is amazing, even scary to see on 50 mm long
blades. If you will measure smaller or equal losses and hysteresis
than Maraging, and we confirm the theoretical
expectations of negligible creep, this is the material of the future for the
mid-level mirror suspensions.
Glenmary, Linden
This week I've basically been trying once again to set up labview. We got a new computer that works well. Linden and I have also
been looking at Anamaria and Francesca's labview programs to see if they can help ours. The hydraulic wiring is almost complete.
glennie
Alberto
The carbon fiber tubes have been delivered and now I'm just waiting for the
pieces of the joints from the manufacturers. As I get them I will be able to
begin assembling the arm. Meanwhile I'm trying to find the best way to mount it
over the springs. I'm also making a rough estimate of the amount of
counterweight I will need according to the kinematics involved in the system.
Because of the measures I will have to do involve accelerometers, I'm checking
in the existing literature about these instruments in order to get more ease
with them.
Ilaria Taurasi and Maria
Paola Clarizia joined us from Universita
del Sannio in Benevento
(innocenzo Pinto’s group. Ilaria will work on
Ansys simulations of IP legs as a warm up, and mirror
thermal noise issues later. MariaPaola will work on wireless controls of a stepping
motor to be used at the top of the ad-LIGO quads to finely adjust the mirror
pitch and null the DC current from the voice coil actuators.
For additional information about this report, contact Stan Whitcomb or Phil Lindquist