The LIGO Executive Committee meeting for July 18, 2005 is
cancelled due to the Staffing Committee meeting.
No report.
LSC MOUs and Research Plans and Progress Reports
A brief site teleconference was held Thursday, July 14, 2005. The following issues were discussed:
>From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
>From: Cleveland Mak mak_c@ligo.caltech.edu
|
Week Ending July 14, 2005 |
In |
Out |
|
Packages |
28 |
6 |
|
Faxes |
19 |
28 |
>From: Esther Cunningham <esther@ligo.caltech.edu>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
>From: Florence Kaufman <fkaufman>
>From: Gina Salone <gsalone@ligo.caltech.edu>
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
>Irene Baldon
No report.
>Julie Hiroto
>Dorothy Lloyd
LIGO must submit an Annual Report for Operations by August 1, 2005 and this annual report must be accompanied by a request for a two year extension (FY 2007 and FY 2008) as well as a justification for supplemental funding. A draft of the annual report has been made available to the members of the executive committee for their review and comments. A first draft of the budget and proposal for FY 2007 and 2008 has been entered into FastLane and provided to management for comment/adjustments.
There was no meeting this week. Our next scheduled meeting will be on Wednesday, July 20, 2005
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
>From: Bill Tyler tyler@ligo.caltech.edu
Nothing significant to report except for the new LIGO Rule that SURF Students are not qualified to be escorts for visitors in the Laser Hazard Area/Zone.
No report.
The interferometer locking continues to be difficult during the day due to
the logging within 200 meters from the corner station. There was also no
interferometer locking on weekend due to the hurricane Dennis. The low noise
spectrum is still about 20% worse than the best reference. The last night inspiral range was 8.5 Mpc with
the same calibration which produced to the best reference of 10.5 Mpc (the calibration uncertainty for the reference was
10%). The broadband excess noise is under investigation now. The commissioning
during the last three days is limited by the ifo instability which appears to be in the angular
controls but the cause maybe elsewhere in the electronics or heating of the
optics by the beam or the TCS.
Other interferometer commissioning activities: - there is an intermittent
1/f2 (white noise force) in the darm noise
spectrum which was first attributed to the ITM bias module. The noise still
appears to be in the spectrum intermittently even after the bias module
replacement.
Continued working with SURF and RET personnel 2. Continued work on Outreach
webpage.
We held a contractor briefing and walkthrough on Thursday afternoon. Five of
the six invited bidders attended, indicating an encouraging level of interest
as well as healthy competition. Bid opening is scheduled for the week of August
3 at LLO.
Photos of the fiber damage can be seen at http://www.ligo-la.caltech.edu/~sroddy/fiber-photos/.
Working on a replacement DHCP server that will
authenticate users. Several times
over the last few weeks I have had to try and track down a user via MAC address
and was unsuccessful. This should solve that problem.
Working with Lisa on some network architecture issues for
CDS/GC. Should
be able to solve some problems soon.
Still haven't found an easy way to get decent reports out of snort for IDS
sensor reporting. The web console works
great, but there is no way to get a structured report out of it suitable for a
weekly report.
In 14 days we had 17,301 ssh
brute force attempts on the network.
I think I have most of the spyware remnants
cleaned out. Still
trying to associate a user with some of the network traffic.
1) HPLF:
The laser is at IPG Photonics for evaluation and repair. So far no news.
2) Have
helped Valera Frolov to
install the MC WFS relief code from LHO at LLO. Will test it as soon as
possible.
1) Continuing
work on mapping of the CDS signals. The mapping is done with the help of medm screens designed in a hierarchical fashion. From a top
down view, different block diagrams identify the functionality of the system
and the interconnects. The essential part is to
identify the location of faults in case of a signal malfunction.
2) Help
operations in routine maintenance including bringing up the system from power
shutdown.
1) Collected estimates for AC and power upgrade from Allen and Rusyl;
2) Upgraded controller and disk firmware on 3510;
3) Dan upgraded QFS on dataserver and gateway;
4) Upgraded linux kernel on the nodes, ldas-grid and ldas-pcdev1;
5) Condor
and LDR were upgraded;
6) Running dd to mirror hda to hdb on the nodes revealved potential problems with 25 disks (although the corresponding nodes are still operational but the disks seem to be about to fail);
7) Replaced
faulty memory on node31;
8) Installed second fiber channel card and second GigE card into dataserver;
9) Reconfigured nodes and dataserver so that nodes communicate with /archive/home and /archive/frames through different network links;
10) Old backup dataserver died (I have not looked yet why).
1) Together with Sergey found a bug in the quadruple coincidence waveburst script (manifested in incorrectly reconstructed properties of triggers for V1, the most noticable of which was timing);
2) Reran
corrected quadruple coincidence waveburst script on
the simulated LIGO-VIRGO data. Generated ROC, efficiency and other FOMs for SG235 injections and noise triggers. The results
look self-consistent now.
With a great help by Biplab Bhawal,
we performed detailed e2e analysis of the effect of input beam pointing
fluctuation on IFO performance. Keeping the seismic inputs to Core Optics off
(by suppressing the suspension point input to all COC), we gave seismic motions
to MMT1 MMT3 and studied the resulting effects (a) COC cavitiesÅf
Length Sensing Control on and (b) COC cavitiesÅf LSC
and Optical Lever on. For the seismic input to the MMTs,
we used EnvFull.box (the standard floor motion box
used by the current SimLIGO). ASC of COC was not used in this analysis.
Main findings we have so far are as follows. (1) When the seismic motion are
given to all three MMTs simultaneously, the resultant
excitation to higher order mode of the input beam to COC is up to 2.2% (vs.
0.04%, 0.1% and 1.6 % when the seismic motion is given to only MMT1, MMT2, and
MMT3 at a time, respectively). (2) Under all these conditions, the arm cavity
remains locked as long as the LSC is turned on. However, if the seismic motion
is an order of magnitude higher than the nominal level (resulting in 78% of
input beam optical power excited to higher order modes when MMT3 only is
moving), the arm cavity loses lock even if both LSC and Opt Lev controls are
turned on. (3) When the Opt Lev control is turned on in addition to LSC, the
DARM/CARM error signals increase by three/two orders of magnitude,
respectively, as compared with the LSC only case. In this analysis, the Opt Lev
is placed on the BSC piers. (4) If the Opt Lev is placed on an ideally quiet
table [i.e., no seismic noise to the Opt Lev with the other conditions the same
as (3)], the DARM/CARM signals decrease two/two orders of magnitude as compared
with condition (3). This indicates that the Opt Lev picks up the pier motion
and causes the excess noise in the CARM and DARM. Comparison of (3) and (4)
indicates that the noise increase associated with the pier motion picked up by
the Opt Lev is comparable to the case when only MMT2 is moving due to the
seismic input.
from Dennis Coyne
see also the CDS weekly meeting minutes in the commissioning archives
Rolf Bork
Finished testing the latest HEPI software, which includes tilt correction. This will be installed at LLO next week.
Rich Abbott
Setting up a trip to LLO for the first two weeks of August.
no report
Peter King
In debugging a high voltage amplifier, where there was a problem with the gain, it was found that a blown OP-27GS was not totally blown so that things still marginally worked. The part was replaced and everything is as it should be.
Helena Armandula
Note from D. Coyne: A plan for analysis of the ITMx optic just removed from H1 due to anomalously high absorption (~15 ppm) is being prepared by a group led by Bill Kells. The first step will be confirmation of high absorption in the Reflection/Transmission Scanner system at Caltech. Another HR absorption scan through the center is underway.
Liyuan Zhang, Lee Cardenas
We checked the HR absorption of the 4ITM07, an 11x11 mm scan was done at 80 mm from the center and compared with the same scan of 4ITM04, unfortunately, no huge absorption was observed. We also did a cross check with a 3" dia. mirror (MMT14K04) provided by Helena, its HR absorption is about 1ppm, recently measured at Stanford. All three scans are put in the histogram below. Comparing to Stanford's result of MMT14K04, it looks like that our calibration (which is based on the mean of absorption of a 1" cavity mirror) is about 2 x smaller.

David Blair, Ju Li, and Seiji Kawamura are
visiting for the summer. Please make them welcome!
We will have a review of our plans for a DC readout experiment, next Tuesday
July 19, at 8-10 Pacific. All are welcome to participate. Contact
ajw@caltech.edu for details.
Since our last report, we have finished gluing
the magnets on the new mirrors. We have removed the sapphire mirrors and their
suspension wires from the North Arm Cavity (NAC), and we have installed the
(thinner) suspension wires and both fused-silica masses. We are now in the
process of balancing the new mirrors and doing the coarse alignment.
Chinyere has finished her matlab
calibration code, and it accurately models the transfer functions of both the
servo filter and the open- loop gain, as measured with the interferometer
locked. She presented a talk on her work to the group in preparation for her
final SURF presentation. Kate also gave a presentation on how we know the
losses in a coating are in the tantala layers.
No report.
Shivanand, SURF student of Sany Yoshida summarized his work in a talk "Effect of the beam pointing fluctuations in the input beam". Following that Doug Fettig, Biplab's SURF student talked about his work on the effects of transverse Shifts of beam or optics on LIGO.[Viewgraphs at http://www.ligo.caltech.edu/~e2e/ME2ET/Minutes05/050714/ ]
(Melody) Worked on several problems in building the E2E software: one involved a Linux FC4 compile error and the other a different format of "gcc --version".
(Bruce-last week) Continued work on major upgrade of iLog entry creation tool.
(Bruce-this week) Misc issues in the Alfi problem report database.
(Melody) Continuing with fixing the Problem Reports (PRs). Continued fixing PR 483 - "check into new way to display java remotely".
Charlton:
Chatterji:
Discussed the application of the Q Pipeline to detector characterization efforts with Keith Riles. Considering the possibility of a DMT version of the Q Pipeline for control room use real time trigger generation.
Contributing description on near term extensions to burst search methods for inclusion in LSC white paper.
Continued working with Hormoz on an extension to the Q Pipeline to target positions of interest on the sky. We are currently testing the initial implementation of such a pipeline.
Continued working with Sutton, Tinto, Searle, Stein and Lazzarini on coherent network search. Contributed code for reading frame data, resampling of data to a common sample frequency, zero-phase high pass filtering and whitening, and amplitude spectral density estimation.
Helping to debug and test the initial implementation of such a pipeline.
Continuing trigger production for S3 detector characterization and veto studies.
Creighton:
This week I upgraded the Einstein@home validator to test angular separation rather than angle differences when comparing sky positions of sources. I also began to add more verbose reporting of invalid results.
Mendell:
An update on the StackSlide search of S4 data has been posted on the password protected investigations page: http://www.lsc-group.phys.uwm.edu/cgi-bin/enote.pl? nb=puls4stackslide&action=view&page=2
Shawhan:
Sutton:
I've spent most of the last week setting up the simulations infrastructure for the CIT coherent network analysis pipeline. This allows the user to add a wide variety of GWBs and also uncorrelated noise glitches to the data analysed by the pipeline. Thanks to a lot of work by Chatterji, Searle, and Stein, the pipeline is now functional (from frame data to sky maps); we're currently debugging it. I've also been studying chirplets as maximum-entropy burst signals, and their application to modelling the sensitivity of bursts searches over the LIGO cheese. Finally, last week I did a simple estimate of the upper limit that could be derived from a LIGO-TAMA joint S3-DT9 bursts search, and compared to it upper limits from other LIGO searches. This will be used to help decide what collaborative work we'll do with TAMA in the near future.
Weinstein:
Enhanced the FrSample program to generate some test frames needed for completing Frame to ILwd test (PR#1736).
Have analyzed and made changes for the new leap second on Jan 1, 2006 (PR#2856). The leapsecond file used by cmon and as a backup for LDAS has been modified as well as the static table in the General::GPSTime class. This work has only been verified on a tandem system and will be moved to ldas-dev early next week.
The code base for supporting the new flag -metadatacheck (PR#2824) has been added and tested on a tandem system. User documentation still needs to be written. Once this is done, the code will be moved to ldas-dev.
Studies continue on the diskcache's blindness to files on /archive file system (PR#2722). It does appear that this is caused by locks not being released when a constructor throws an exception. I am enhancing the debugging capabilities to verify this condition.
Fixed one of the types in resource file for getFrameElements under the controlMonitorAPI.
Added code to cvs to cleanup defunctJobs and swig callchain commands (PR2844) that are causing callchain objects to leak.
Currently testing code in diskcache to control the amount of duplicate emails. The code has been in place for sometime, but regression tests have been needed.
System and Integration Testing: ran system test for ldas build 1.6.36 and updated test results to dev and cvs. Fixing fracc6.tcl verification for Proc tRange data. Working on fr2ilwd test with Ed.
FrSample needs to be able to generate frame file with channel of only 1 data type. Fixed dcmangle to create /tmp/dcmangle if it does not exist.
Began to populate the new PR category for resource files added with the changes that will be needed in the next release of LDAS.
Began working on the Globus GASS Copy package. A total of 37 functions exist in globus_gass_copy.h header file. Of these, 27 functions have been wrapped and tested on RH9 and FC3. Five functions have been wrapped, but they have not been tested (complete this by today). There are five other functions that are for Globus internal use so we will not support them.
Also begain working on theGlobus GASS Transfer package which has 64 functions to be wrapped up and tested.
Successfully tested inter-operability between the LIGO VOMS server at PSU with LIGO Gums server at Caltech. Retrieved entries from VOMS and received Group Mapping from GUMS to associate FQDN for users with Group VO LIGO using "gums generateGridMapfile" on the prototype cluster system node.
Began configuration of PRIMA for system node. More work is required to properly configure the GUMS server to authorize VOMS entries on a PRIMA-enabled Globus gatekeeper.
Discovered firewall rule changes required to enable Tomcat 5 and Apache to communicate via a TCP port. Discovered that the Proxy required by GUMS is the deprecated Globus Toolkit 1 proxy. This can be created by using the form: "grid-proxy-init -old".
Learned how to query the MySQL backend of GUMS in order to verify the user population within the database fields.
The iVDGL compute resources that were previously
operating under the GRID3 grid showed up on the OSG production gridcat map this week as preparations continue for the OSG
roll out consortium meeting to be held next week in
(Dan Kozak)
(Phil Ehrens)
(Stuart Anderson)
(Keith Bayer)
No report -- vacation
(Igor Yakushin)
(Greg Mendell)
(Ben Johnson)
(Keith)
On vacation
(
(Christine)
(Mike)
(Veronica)
(Bruce)
Ilog Development: (3.0 days)
Christian)
(Larry)
Mail Server Statistics for July 7-13,05
|
Mail Server Statistics |
July 7-13,05 |
|
Rejected Messages |
23,492 |
|
Virus Messages |
1,338 |
|
False Positives |
253 |
|
Accepted Messages |
15,792 |
|
Total Messages |
39,284 |
from Dennis
Coyne
See also:
See also the RODA
status web page
See the
"Interfaces" section of the AL Systems web
page
HAM isolation requirements
CDS Infrastructure & related topics:
Viewgraphs and minutes will soon be placed on the AL SYS web site under Meetings
Residual Gas Assay (RGA)
See also the Vacuum Bake Lab
Bob Taylor
High-Irradiance, Contamination-Exposure Cavities (Lee Cardenas, Liyuan Zhang)
No change
|
Cavity 1.
(Location) |
Material/Item |
Start |
End |
Comments |
|
Cavity #1 2.
(OTF
Lab, Bridge) |
MMG nickel plated Nd-B-Fe magnets (Helena Armandula,
SUS ) |
~6/8 |
TBD |
No Change So far
daily ring down & absorption measurements indicate that there is no
change. Added 40 small Nd-B-Fe magnets into the cavity |
|
Cavity #2 (OTF Lab, Lauritsen) |
NA |
NA |
NA |
No Change cavity is close to
being ready for samples |
|
Cavity #3 (OTF Lab, Lauritsen) |
OSEM
emitter & photodiode 40 of each, (Dennis Coyne, SUS ) |
~6/10 |
~9/10 |
No Change So far
daily ring down & absorption measurements indicate that there is no
change. |
|
Queue Priority 1 |
2 Cleaned 50ppm
transmission mirrors, 1 in dia., REO coated --
|
TBD |
TBD |
witness samples
for the LHO vertex volume (added in 6/29/2005 vent) |
|
Queue Priority 2 |
OSEM Flexi-circuit cable,
qty ~ 45 (Helena Armandula, SUS) To be supplied by
Univ. Birmingham (Stuart Aston); |
TBD |
TBD |
DuPont Flexible Circuits. The whole part
to be constructed of 'flexi' i.e. no 'rigid' sections. (Stuart Aston, (document link: http://www.dupont.com/fcm/products/H-73244.pdf Coverlay (x2): Kapton
(LF0110) (document link: http://www.dupont.com/fcm/products/H-73245.pdf DuPont Pyralux Series - Kapton /
Acrylic Adhesive system. (document link: http://www.dupont.com/fcm/products/H-73246.pdf |
|
Queue Priority 3 |
Stepper
Motor (Riccardo DeSalvo,
possible SUS or ISC use) |
TBD |
TBD |
3.
Stepper
Motor sample had been placed into Cavity #1: Power dropped from 175 mW to ~25 mW after introducing
the stepper motor sample, and continues to decrease. It is very hard to keep
cavity locked. The stepper motor may have contaminated the mirrors. Will
re-test when a cvity becomes available again. |
from Carol
Wilkinson
Progress updates for Advanced LIGO subsystem development for the period from
May 1 to June 30 are due July 14. Sub-system leaders will be asked to work up
Estimate-to-Complete the development portions of their sub-systems – due
end of July.
Future near term planned meetings & reviews are indicated in the table below.
BSC Critical Design Review 3 was held July 7, 2005. Report in progress.
No Change since last week:
|
Date |
Subsys |
Review |
Topic(s) |
Enabling event(s) |
Schedule motivation |
|
|
Jul 7 |
SEI |
BSC Critical
Design Review 3 |
review basic
requirements, interfaces & dynamic coupling |
available
analysis/reports |
timely decision on
proceeding with SEI/BSC prototype for LASTI for integration with the SUS quad
prototype |
Report in
progress |
|
Jul 11-13 |
SYS |
SYS Mtg |
|
|
Report in progress |
|
|
12-Jul |
SUS |
PDR, Review 2 |
Electronics req & design; Focus is on the front end electronics ( |
|
|
Report in progress |
|
Jul 19 |
ISC/40m |
40m DC Readout
Review |
DC readout
experiment |
|
|
scheduled |
|
~Aug, 05 |
SEI |
HAM Critical
Design Review |
Recommendations w.r.t. HAM prototype development based on ETF results |
Completion of
SEI/BSC critical design reviews; LSC review of ASI HAM configuration design |
timely decision on
proceeding with SEI/HAM prototype |
|
|
~Sep |
SUS |
PDR, Review 3 |
Quad design |
Completion of the
quad controls prototype assembly; |
timely transfer,
to RAL & UB efforts, of lessons learned from the controls prototype |
|
|
~Nov |
SUS |
PDR, Review 4 |
Quad Installation |
Completion of installation
at LASTI |
Inform the |
|
|
~Dec |
SUS |
PDR, Review 5 |
Triple design |
Available SUS/US
staff |
Enable SUS/US
final design phase |
|
|
~Feb |
SUS |
PDR, Review 6 |
quad controls prototype
test results |
completion of
LASTI testing |
timely
incorporation into final design effort on the noise prototype |
|
|
TBD |
SUS |
PDR, Review 7 |
BS, FM/ITM SUS
design |
design work completion
(has yet to start on FM/ITM, not mature for RM) |
|
|
|
Sep 28 |
AOS |
Stray Light
Control, DRR/CD |
|
SYS PDR? |
primavera late
finish 6/15/05 |
|
|
TBD |
AOS |
Thermal Comp.,
DRR/CD |
|
SYS PDR? |
|
|
|
~Oct |
SYS |
PDR, Review 1 |
Engineering &
Implementation ('generic') Requirements; |
completion of
generic requirements definition; completion of first draft of ICD; revision
to optical layout; establish integrated opto-mechanical
equipment layout |
timely system
level definition enables/helps define subsystem reqmnts
& design |
|
|
~Dec |
SYS |
PDR, Review 2 |
CDS Infrastructure |
Sufficient CDS
requirements & concept work (also 7/11-13 mtg) |
CDS Infrastructure
is key to subsystem electronics req. |
|
|
~Sep |
IO |
PDR Review 1 |
Faraday Isolator |
SYS PDR? |
|
|
|
~Jan |
IO |
PDR Review 2 |
Electro-Optic
Modulator |
|
|
|
|
~Mar |
IO |
PDR Review 3 |
Mode Matching
Telescope |
Determination of
whether a stable recycling cavity will become part of the |
|
|
|
~Oct |
COC |
PDR Review 1 |
Metrology |
Review and select vender and in-house metrology |
|
|
|
TBD |
COC |
PDR Review 2 |
|
SYS PDR? |
|
|
Rolf Bork
Rich Abbott
Put together agenda for the CDS infrastructure meeting and am presently writing a document that summarizes the content of the meeting. Several action items have been generated from the meeting, Jay is volunteered to put together a plan for using some of the new architecture ideas for testing at LASTI. Vern volunteered to put some thought to a library of sorts containing standard LIGO approved design solutions for electronics that might allow us to repeat successes and avoid past failures.
From: Ken Mason kmason@ligo.mit.edu
A meeting was held with ASI to discuss changing "softening" the stage 0-1 and stage 1-2 spring assemblies. Brian Lantz generated a design using a program given to us as part of the original contract from ASI. Oddvar Spjeld then took the new spring sizes and fit them into the BSC solidworks model. We will be meeting again tuesday to discuss cost and schedule.
A procurement strategy for the seismic structure has been generated which breaks down responsibilities for preparing bid packages and interfacing with suppliers.
From: Janeen Romie romie_j@ligo.caltech.edu
Tim Hayler from RAL joined us for a week here at Caltech. He went home yesterday. Ian and Joe from RAL came yesterday for another week and a half. Their visits are greatly appreciated. We all met with Mike Gerfen yesterday to discuss the upper structure progress and dimensioning/tolerancing. Mike said that the work has gone more slowly than he had hoped and plans for it to be completed on Friday. Calum has managed the lab tasks through next week such that we can work around that delay. We are working on the lower structure now.
Attended the SUS
Working on the spacer assembly for the LASTI mode cleaner.
Working with Betsy on getting a number of spare parts for LHO.
From: ctorrie ctorrie@ligo.caltech.edu
Tim Hayler was visiting from RAL last week to work on the upper and lower structure. Ian Wilmut and Joe O'Dell are visiting this week from RAL to work on the assembly of the quad suspension. One of the last items, the upper structure, should be finished its post welding machining stages by Friday. Lots of photos to follow.
From: Ken mailand kmailand@ligo.caltech.edu
Making simplified S/W drawings of the Adv. LIGO optical component assemblies for import to Zmax, for Mike Smith, and converting Mechanical Desktop LHO full site layout to S/W
From: Bill Kells <kells@ligo.caltech.edu>
My work has been entirely dominated by:
1. The critical effort to understand the [absorptive] properties of ITM07. Our preliminary partial scans have indicated no anomalous HR absorption. However there was significantly high fine dust contamination. Nothing on the AR side yet (other than it seems clean per visual insepection), nor on bulk absorption. So, this effort may be protracted since we are not immediately finding properties consistent with the in situ symptoms.
2. Review of the parametric instability issue. For me this is amounting to a rather full re-assesment of the theory, and circumstances for LIGO and Adl. A lot is being uncovered which was not properly appreciated before. I am constantly in discussion with the visting Australians. I believe they are learning a lot, and many claims will (or ought to ) be revised.
From: Helena Armandula ahelena@ligo.caltech.edu
After removing the aluminum cover, observed the sides of the mirror covered with a heavy layer of dust and smudges.
Inspected the AR surface with a high intensity light source in situ. Given the white background at the bottom of the aluminum case, surface imperfections were hard to see. Did not see evidence of a film, however, I noticed what appeared to be a cleaning smear, which can look like a film but in a localized area. There were a few pieces of lint and quite a few speckles of dust on the surface.
Removed the mirror from the case and placed it on a mirror holding plate (dark background). I saw speckles of dust covering uniformly the entire AR surface.
Turned the mirror to inspect the HR side, did not see a film but a very heavy layer of fine dust particles uniformly distributed and a few pieces of lint.
To be able to compare this mirror surface with the surface of other mirrors, Bill Kells suggested making an inspection, under the dark field microscope, following the inspection routine performed on other optics, like ITM04 and 40 m mirrors, when we were trying to evaluate scatter.
Moving the microscope across the optic, starting and finishing at ~1.5" from the edge, I looked at 36 subsequent (4mm field of view) areas and counted the amount of scatter points observed. Because I did not clean the optic I was not able to distinguish well between a dust particle and/or a coating/glass point scatter. The points ranged from 5 micrometers to 19 micrometers in dia., most falling into the 5 micrometers category.
Magnification was 5x.
In ITM07 the minimum of scatter points seen per area were 35, the maximum 94 and I took 36 readings.
As comparison, when I looked at ITM04, I saw quantities of points (per field of view) ranging from 13 points maximum to 1 point minimum. I took 47 readings.
From: Peter King pking@ligo.caltech.edu
Maik Frede (LZH) gave me some information about the pump diodes used in the current laser design, although he did note that there was a possibility that the pump diodes would change. Nevertheless I contacted JenOptik asking for other information.
From: Phil Willems <willems@ligo.caltech.edu>
We have fired up our 25 W carbon dioxide laser and are beginning measurements of its intensity noise spectrum using a Boston Electronics photovoltaic cell. We have successfully reengineered a conference projector to run with the multimirror array externally accessible and are preparing to remove the cover to test it to exposure to 25 W of CO2 radiation. We have learned that while the projector is designed to toggle each micromirror at roughly 200Hz, this feature is only for the convenience of the projector and the mirror array can be run in fixed orientations for long periods of time, as needed for AdLIGO.
From: Michael Smith <smith@ligo.caltech.edu>
Aabeg has assembled the OPTLEV receiver apparatus and is beginning alignment. I am awaiting help from Ben Abbot for the QPD readout.
Shasta is in the process of aligning the BRDF apparatus.
I am in the process of designing the output mode matching telescope and
updating the optical beam lines.
From: Riccardo DeSalvo
desalvo@ligo.caltech.edu
John
Still working on fitting experimental data to theory both 2d intensity profiles and frequency spectra.
Also performing frequency analysis to determine noise sources in our experiment. When using side-lock we see strong (and as yet unidentified) peaks in the 30-40Hz region. Using a dithering lock, peaks are seen at 120Hz and harmonics thereof. These results are based on measurements taken over nine seconds at a sampling rate of 10,000Hz. Over the coming week, longer data sets will be produced (once a broken PC as been repaired). We may also try different techniques to excite resonances in the structure.
The reflection/transmission coefficients of the cavity mirrors have been experimentally measured. Input 0.9620, Folder 0.9988, MH 0.9990 . These results will permit us to calculate the finesse of the cavity for different modes, perhaps explaining why it is difficult to lock to the fundamental.
Chiara
I will start with the test for horizontal attenuation system with four legs, so I'm working on new mechanical set-up. We made the hardening process (100 hours, 435 celsius degrees) for the eight new joints and then we have measured the hardness. The result of this measurement shows that the hardness of these joints is high (56 of the C- Rockwell scale).
Juri
I finished writing the paper which will be published in the proceedings of the SPIE conference "Optics and Photonics".
It will be posted soon for LSC review. In this paper I reported on the status
of our experiment on
Francesca:
Alberto and I controlled the maraging cooking. I'm studying Lab View using some demo files and I'm trying to understand how to implement a real-time PID control system for the low frequency electromagnetic anti-spring actuator.
Marco (12Jul)
Since cavity spectrum shows the first two peaks very close to each other and
the best beam profile looks like a linear superposition of the theoretical
TEM00 and TEM01, I decided to switch to the dither lock scheme: no
Alberto
I have just completed a first draft of the drawings of the damping arm I'm working on. While I'm waiting for the delivery of the carbon fiber pipes, I'm designing the spring junctions. In order to extend the surface available, I'm trying to find the way to fix the flex joints to the springs through a plate bolted in central point. I expect to have the definitive designs to send the constructors by the end of this week.
For additional information about this report, contact S. Whitcomb or P. Lindquist