The LIGO Executive Committee meeting for July 4, 2005 is
cancelled due to the holiday.
No report.
LSC MOUs and Research Plans and Progress Reports
No site teleconference was scheduled for Thursday, June 29, 2005.
>From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
>From: Cleveland Mak mak_c@ligo.caltech.edu
|
Week Ending June 30, 2005 |
In |
Out |
|
Packages |
19 |
5 |
|
Faxes |
27 |
8 |
>From: Esther Cunningham <esther@ligo.caltech.edu>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
>From: Florence Kaufman <fkaufman>
>From: Gina Salone <gsalone@ligo.caltech.edu>
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
>Irene Baldon
>Julie Hiroto
>Dorothy Lloyd
LIGO must submit an Annual Report for Operations by August 1, 2005 and this annual report must be accompanied by a request for a two year extension (FY 2007 and FY 2008) as well as a justification for why Caltech/MIT should be continued in the role of management of LIGO. We are assembling and editing the report.
We reviewed the requirements matrix relative to three document management systems, Synergy, Xythos, and DocDB. We are going to revise the formal version of the matrix and distribute for additional precision in some of our evaluations focusing on those areas that truly discriminate between the various applications. We will also be setting up teleconferences to address specific questions with Xythos and Synergy.
Our next scheduled meeting will be on Wednesday, July 13, 2005. We may attempt short ad hoc meetings with Synergy and Xythos prior to that meeting..
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
>From: Bill Tyler tyler@ligo.caltech.edu
Scheduled additional Baseline eye exams and conducted LIGO
safety briefings for new students and LIGO visitors.
Early this week the replacement ITMX optic was re-hung after the bake, without incident and in good alignment on the wire. The LVEA was transitioned to laser safe as of Tuesday night and the vent commenced Wednesday morning. The vent time was approximately 17h, considerably longer than first envisioned. Initial observations indicated the ITMX, ITMY and BS optics were covered in a thin film of dust. The ITMX was swapped, and the ITMY was drag-wiped. Both procedures were slowed by problems with static charge buildup on the optics, and some procedural items such as the difficulty of making OSEM adjustments given the current design (Adv LIGO please note).
Read more on the vent in upcoming elogs.
We are holding out for more data on the scattering and upconversion before erecting the arm cavity baffles in the end (and ultimately, mid- and corner-) stations.
Interferometer operation in low-noise mode has mostly been recovered from previous week lightning strike and power trips. The inspiral range during last night's astrowatch was around 6 Mpc. Noise on a 5 V power supply coupled to the interferometer output through the length and angle sensing electronics and was eliminated from the ifo spectrum by changing the voltage which goes to the voltage regulators in the crate. The cause of noise is not known yet and under investigation. The interferometer operates with two anti-symmetric port photo-detectors at the moment due to the electronics problems with the whitening board. The whitening electronics is expected to be repaired today.
Nothing of substance to report this period.
As a continuation of the Snort/ACID install from last week, I found out that BASE (Basic Analysis and Security Engine) has replaced ACID and is currently under active development. So, I installed BASE. It is much like ACID (based on the same code) but is a bit more refined and there are several bugfixes and new features. They are actively working on a total rewrite for v. 2. I also installed the "bleeding-edge" snort rules from bleedingsnort.org. This turned out to be extremely valuable. It has detection rules for spyware, ssh scans, etc. It has increased by double the amount of detections snort sees, but the false alarm rate is very low. Turns out we had 4 machines here infected with spyware that I did not know about which were "phoning home" many times daily. I will end up putting together a quick howto for everyone and will likely set up a similar system for LHO. This is a very valuable item to have on the network.
Redeployed the support.ligo-la.caltech.edu
web server.
I have reinstalled the helpdesk software
there and I am working on configuring it. All of the printer, licensing,
and other support info is back online. This machine suffered a hardware
failure months ago, however there was not much desire to redeploy it until
recently. Lisa would like to start using it and with the influx of
support issues due to SURF students, teachers, etc. that we have here right now
it will make it easier for me to track support issues again. Worked on a server
for most of a day trying to troubleshoot a hardware issue. Never was able
to determine where the exact problem was. Seems like it may be a bad CPU
or a problem with the motherboard. I will likely just mothball it or try
to build a workstation out of the remaining good parts.
snort
alerts in the last 24 hours:
27
ssh brute force attempts
1,869
suspected port scans
4,411
detected spyware/malware packets mostly from 2 infected hosts.
218
hits on non-allowed web pages
1,106
IIS httpd hack attempts
1
attempted trojan installation
Reinstalled a Fedora Core 3 workstation for a SURF student that was hosed due to improper package removals by their mentor. Somehow all of the Xorg stuff got removed. Reinstalled with a full install and apparently now the software that was required for the surf student will now compile.
Developing a map of CDS signals so that from a topdown view a signal could be traced from its origin to its destination. I hope this mapping will help in troubleshooting hardware electronics that require instant acces to the signal flow diagram.
Presented "Status of S4 untriggered burst search" at Amaldi6 conference.
See also the CDS weekly meeting minutes in the commissioning archives
No report
Ben Abbott
RF photodiodes: 8 PDs have all been tested. They need to go through final assembly, and then they can be shipped out. This will be accomplished shortly. There are 4 tuned to 24.5 MHz, and 4 tuned to 29.5MHz.
No report
No report
Mike Smith
I am in the process of re-calculating the edge diffraction from the arm cavity baffle.
No report.
Jay: Installed the daq at the TNI and showed it to Kate.
Akira: Found one source of electronic noise in the
bond-noise experiment and reduced it. Helped teach SURF students how to align
and lock the TNI.
Chinyere: While waiting on the new mirrors, learned how to
align and lock the TNI, and how to take closed-loop transfer function
measurements in both the (relatively simple) reference cavity system and the
(much more complex) TNI. She is now reading Bode's original paper on gain-phase
relationships and stability in control systems.
She also read a paper on Pound-Drever locking and modeled the error
signal in MATLAB, before the other SURF students arrived.
No report.
(Biplab)
(Bruce) Continuing work on major upgrade of iLog entry creation tool.
(Melody) Continuing with fixing the Problem Reports (PRs). Finished working on PR 448 - don't allow blank port input settings. Now working on PR 483 -"check into new way to display java remotely"
Charlton:
Chatterji:
I have updated and made the following software packages available in the Matlab CVS repository:
Studying the prospects of applying the Q Pipeline to auxiliary and environmental channel data for the purpose of detector characterization and vetoing. Currently working on trigger production for environmental channels during the S3 run.
Continued working with Sahand Hormoz (SURF) to implement an extension of the Q pipeline to target a specific position on the sky. We are currently developing prototype code to understand the issues involved in such a search.
Mendell:
StackSlide work has been on the backburner for a week. I have been working
with a SURF student to understand the calibration near the Free Spectral Range
Frequency for a project with Rick Savage and Malik Rakhmanov. I also met with
Sukanta Bose and students and postdocs from
Searle(visiting from ANU)
Implemented colored noise null stream method; results consistent with expectations; algorithm substantially slower due to per-frequency-bin construction of the null streams. Explored Shurov's simulated data and matlab applications from the new LIGOtools release. (One small thing to note is that MATLAB's default PSD windowing is completely unsuitable for IFO PSDs due to massive leakage.) Broke up null stream implementation to return detector square- and cross-terms separately. Shows that "butterfly" features due solely to square terms and rings due solely to cross-terms.
However, must be recombined for global extremum to be the source position--rings are ambiguous otherwise. Planned for 'production' implementation by Leo, with Patrick, Shurov and Massimo.
Sutton:
Since returning from
Yakushin:
Presented "Status of S4 untriggered burst search" at Amaldi6 conference.
Zanolin:
LDAS development systems were shutdown for two days this week to resolve an email issue that resulted from combining all the /scratch filesystems into one common filesystem and to all the system administrators to also experiment with a second change to the file- systems to share /export from QFS which revealed several configuration issues with QFS that prevented LDAS from running jobs. Both issues associated with the two file system changes have been resolved to the point that LDAS can be run successfully again, although we are seeing a performance degradation after these change of about 10 percent.
The swig wrapped function getFrameNumber has been restored. It will only operate on frame files that have a table of contents. If the frame file does not have a table of contents, then an exception is thrown (PR#2846).
Reworked the documentation describing the swig wrapped functionn DetectorProc2container to explicately warn the developer not to release the frame file pointer before making this call as the DetectorProc pointer is shallow (PR#2845).
Corrected the code for creating RDSs to explicately check for non-NULL FrRawData pointer. This allows for the generation of RDSs when the frame only has FrProcData elements (PR#2848).
Reworked many of the test scripts to make better use of the /scratch/test/frames file system. Each of the tandem systems now has its own directory for create RDS commands that want to write to the /scratch file system (/scratch/test/system/tandem-{i-v}).
This resolved the issue with the /scratch file system change by LDAS system admins which resulted in the 60000 emails being sent out by LDAS over the past weekend.
Attempted to fix a memory leak in the dataConditionAPI by adding call-chain clean up code to the Tcl layer. This fixed the leaking of call-chain objects but introduced a four times larger leak of element objects. The call-chain fix will need to be backed out until a better solution can be found.
Added email blocking code to the controlMonitorAPI so that no emails will be sent out from any of the LDAS Tandem systems where experimental code is first tested.
Updated documentation to provide instructions on all user command tests, node tests and search user tests.
Conducted system and integration testing on LDAS build 1.6.24. No issues with test results. Continued developing frame-2-ilwd test.
The 0.2.0 alpha release of LDAS is being made available today to the LSC. It support both Globus Toolkit 3.2 and Globus Toolkit 4.0, as well as Redhat 9 and Fedora Core 3. The distribution is available as source and RPMs for GT3.2 and as source for GT4.
Successfully configured Condor high-throughput job manager on the osg-itb cluster including the head node and seven worker nodes.
Performed limited testing of Condor jobs in the Condor vanilla environment.
Fixed boot scripts so head node of osg-itb starts up daemons for Globus gatekeeper, gsiftp, MonALISA, MIS-CI, Ganglia, and Condor. Configured ganglia web front-end so that cluster node performance charts can be reviewed at URL: http://osg-itb.ligo.caltech.edu/ganglia/index.php
Installed GUMS software on osg-itb and began reviewing the detailed configuration documentation.
Also, PSU has registered as the OSG VO for LIGO and begun the process of setting up a VOMS server for LIGO which will allow for simplier management of user certs on all grid resources.
Discussed strategies at this week's LSC Computer Committee Teleconference for the LSC's participation in the annouced solicitation for pre-proposals to the OSG.
Caltech
(Dan Kozak)
(Phil Ehrens)
(Stuart Anderson)
(Igor Yakushin)
(Greg Mendell)
One that shows available tape space in the archive at LHO is here
(Keith)
(
27 ssh brute force attempts
1,869 suspected port scans
4,411 detected spyware/malware packets mostly from 2 infected hosts.
218 hits on non-allowed web pages
1,106 IIS httpd hack attempts
1 attempted trojan installation
(Christine)
(Mike)
(Veronica)
(Bruce)
(BS) Ilog Development: (4.0 days)
(Larry)
|
Mail Statistics |
June 23-29, 2005 |
|
Rejected Messages |
14,985 |
|
Virus Messages |
1,186 |
|
False Positives |
199 |
|
Accepted Messages |
104,649 |
|
Total Messages |
119,634 |
from Dennis Coyne
See also:
See also the RODA status web page
See the "Interfaces" section of the AL Systems web page
Residual Gas Assay (RGA)
See also the Vacuum Bake Lab
Bob Taylor
High-Irradiance, Contamination-Exposure Cavities
Lee Cardenas, Liyuan Zhang
|
Cavity (Location) |
Material/Item |
Start |
End |
Comments |
|
Cavity #1 (OTF Lab, Bridge) |
MMG nickel plated Nd-B-Fe magnets (Helena Armandula, SUS ) |
~6/8 |
TBD |
Added 40 small Nd-B-Fe magnets into the cavity |
|
Cavity #2 (OTF Lab, Lauritsen) |
NA |
NA |
NA |
No Change cavity is close to being ready for samples |
|
Cavity #3 (OTF Lab, Lauritsen) |
OSEM emitter & photodiode 40 of each, (Dennis Coyne, SUS ) |
~6/10 |
~9/10 |
No Change So far the ring down & absorption measurements indicate that there is no change. |
|
Queue Priority 1 |
2 Cleaned 50ppm transmission mirrors, 1 in dia., REO coated -- |
TBD |
TBD |
witness samples for the LHO vertex volume (added in 6/29/2005 vent) |
|
Queue Priority 2 |
OSEM Flexi-circuit cable, qty ~ 45 (Helena Armandula, SUS) To be supplied by Univ.
Birmingham (Stuart Aston); |
TBD |
TBD |
DuPont
Flexible Circuits. The whole part to be constructed of 'flexi' i.e. no
'rigid' sections. (Stuart Aston, (document link: http://www.dupont.com/fcm/products/H-73244.pdf Coverlay (x2): Kapton (LF0110) (document link: http://www.dupont.com/fcm/products/H-73245.pdf DuPont Pyralux Series - Kapton / Acrylic Adhesive system. (document link: http://www.dupont.com/fcm/products/H-73246.pdf |
|
Queue Priority 3 |
Stepper Motor (Riccardo DeSalvo, possible SUS or ISC use) |
TBD |
TBD |
Stepper Motor sample had been placed into Cavity #1: Power dropped from 175 mW to ~25 mW after introducing the stepper motor sample, and continues to decrease. It is very hard to keep cavity locked. The stepper motor may have contaminated the mirrors. Will re-test when a cvity becomes available again. |
Large Item Cleaning Plan/Facility
Ken Mailand
|
Date |
Subsys |
Review |
Topic(s) |
Enabling event(s) |
Schedule motivation |
|
|
Jul 7 |
SEI |
BSC Critical Design Review 3 |
review basic requirements, interfaces & dynamic coupling |
available analysis/reports |
timely decision on proceeding with SEI/BSC prototype for LASTI for integration with the SUS quad prototype |
scheduled |
|
Jul 11-13 |
SYS |
SYS Mtg |
|
|
scheduled |
|
|
12-Jul |
SUS |
PDR, Review 2 |
Electronics
req & design; Focus is on the front end electronics ( |
|
|
scheduled |
|
Jul 19 |
ISC/40m |
40m DC Readout Review |
DC readout experiment |
|
|
scheduled |
|
~Aug, 05 |
SEI |
HAM Critical Design Review |
Recommendations w.r.t. HAM prototype development based on ETF results |
Completion of SEI/BSC critical design reviews; LSC review of ASI HAM configuration design |
timely decision on proceeding with SEI/HAM prototype |
|
|
~Sep |
SUS |
PDR, Review 3 |
Quad design |
Completion of the quad controls prototype assembly; |
timely transfer, to RAL & UB efforts, of lessons learned from the controls prototype |
|
|
~Nov |
SUS |
PDR, Review 4 |
Quad Installation |
Completion of installation at LASTI |
Inform
the |
|
|
~Dec |
SUS |
PDR, Review 5 |
Triple design |
Available SUS/US staff |
Enable SUS/US final design phase |
|
|
~Feb |
SUS |
PDR, Review 6 |
quad
controls prototype test results |
completion of LASTI testing |
timely incorporation into final design effort on the noise prototype |
|
|
TBD |
SUS |
PDR, Review 7 |
BS, FM/ITM
SUS design |
design work completion (has yet to start on FM/ITM, not mature for RM) |
|
|
|
Sep |
AOS |
Stray Light Control, DRR/CD |
|
SYS PDR? |
primavera late finish 6/15/05 |
|
|
TBD |
AOS |
Thermal Comp., DRR/CD |
|
SYS PDR? |
|
|
|
~Oct |
SYS |
PDR, Review 1 |
Engineering
& Implementation ('generic') Requirements; |
completion of generic requirements definition; completion of first draft of ICD; revision to optical layout; establish integrated opto-mechanical equipment layout |
timely system level definition enables/helps define subsystem reqmnts & design |
|
|
~Dec |
SYS |
PDR, Review 2 |
CDS
Infrastructure |
Sufficient
CDS requirements & concept work (also 7/11-13 mtg) |
CDS
Infrastructure is key to subsystem electronics req. |
|
|
~Sep |
IO |
PDR Review 1 |
Faraday Isolator |
SYS PDR? |
|
|
|
~Jan |
IO |
PDR Review 2 |
Electro-Optic Modulator |
|
|
|
|
~Mar |
IO |
PDR Review 3 |
Mode Matching Telescope |
Determination
of whether a stable recycling cavity will become part of the |
|
|
|
TBD |
COC |
PDR |
|
SYS PDR? |
|
|
From: Ken Mason kmason@ligo.mit.edu
We have good results from the Nastran model of the BSC structure at LASTI. We are now adding the concrete floor and vacuum chamber to see their effect on the rest of the structure.
Quotes for the SEI/SUS test stand from Southbridge Sheet Metal and Lavallee Machine have been recieved. The last quote from HT Machine is expected early next week.
Brian Lantz presented the results of his work on softening the ISI blades. Joe and Oddvar will verify the new blades fit into the existing design with no major modifications before we ask ASI to make the design changes.
From: Janeen Romie romie_j@ligo.caltech.edu
Working on the LASTI MC spacer design. We'll utilize the structure shim and make associated parts that will bolt to the shim to speed delivery to LASTI. Dave Ottaway provided me an optic specification for the dummy mass for the quad controls prototype and I've put in a purchase order for it. This optic will fit in the metal mass for LASTI. It has a 4 week lead time.
Working on some issues for Carol.
Provided feedback to Dennis on an ICD of his.
Met with Ian and Tim this morning about noise prototype issues.
Answered some questions about the SOS suspension for Bram.
From: ctorrie <ctorrie@ligo.caltech.edu>
Please reference the following link for photos of some of this weeks work
http://www.ligo.caltech.edu/~ctorrie/pictures/QUADJULY2005-02/QuadJULY2005-02.html
Most of the structural components are due either today or on the 5th of July. The upper structure has ~ 1 week of post welding work to be done. Before this can be started it will firstly go into an oven for 6 hours at 350 F (stress relief). This should be completed by July 5th.
Tim Hayler is visiting form RAL next week for 7 days. Ian Wilmut and one of the designers is visiting from RAL on the 13th of July for 7 days.
I have been preparing the upper and lower structure assemblies on the PDMWorks vault to allow RAL to have access to our as built configuration. RAL have prepared 2 technical notes associated with lessons learned from the controls prototype and we are reviewing these with them.
No design meeting this week. We met instead to discuss the overall assembly of the quad ETM controls prototype. This will be released to the Vault later this week.
From: Ken Mailand kmailand@ligo.caltech.edu
The LIGO large part bake oven: expect arrival Thursday 6-30.
Making a S/W layout of the end station and photon calibrator beam clearances; also simplified S/W drawings of the Adv. LIGO optical component assemblies for import to Zmax, for Mike Smith.
From: Jay Heefner <jay@ligo.caltech.edu>
From: Bill Kells
<kells@ligo.caltech.edu>
The Australians are here now and we have commenced ongoing discussions on the parametric instability. I have got some initial results on running the FFT code to resonate HTMs in arms so that the true, self consistent, loss of such modes (due to finite mirror dia.) can be determined (a crucial parameter in calculating the parametric instability thresholds). We aim at reconciling these and other parameters with what the Australians have been using in publications: attempting to get a consistent statement for the AdL config.
Another aim of mine is to go over their recent writings in enough detail to fairly referee one of them (which P. Saulson has asked me to do).
From: Peter King pking@ligo.caltech.edu
No report this week
From: Michael Smith smith@ligo.caltech.edu
Aabeg has completed
thin lens and thick lens models of the OPTLEV receiver using ABCD matrix
formulation. I am awaiting help from Ben
Abbot for the QPD readout.
I was able to insert an IGES model of the quad SUS as a CAD object into my Zemax non-sequential ray model of the LIGO Vertex. The SUS can be viewed as a wire-frame model or as a shaded solid. Shasta has almost completed the assembly of the BRDF apparatus.
Ken M. is helping me create a Solid Works model of the conceptual ring heater and the elliptical baffle to be attached to the quad SUS.
From: Riccardo DeSalvo desalvo@ligo.caltech.edu
Juri
I used my modified version
of Bench2 to study the optimization of Advanced LIGO in order to take full
advantage of the lower thermal noise using Flat Top beams. I’m writing
the proceedings for the SPIE conference where I will present the status of our
Mexican Hat cavity prototype.
Anamaria and David:
So far we have been trying to set up the four systems of maraging, Cu-Be, LM001 and LM002. We are designing an excitation method that will excite the 4 systems identically at the same time (probably an electromagnet). And we are waiting for the LVDT's and glassy metal blades to arrive. We will measure the Q factor behavior of the 4 metals for comparison.
John
Due to the works in the lab most of this week was spent computing. I finalized the design of the improved mode-matching telescope though at present Marco and I have decided not to implement it. We are currently experimenting with a ‘top hat’ input beam created by focussing only the central part of a large Gaussian beam (over which the intensity should be relatively constant). This technique showed promising results yesterday. We saw some of the best profiles to date, however a clear fundamental still eludes us. We also noticed that as the resonances of the cavity become stronger the distance between modes decreases. I have also been developing Matlab code to filter noise from 2D experimental profiles and perform a non-linear fit. Once complete this should allow quick comparisons with theory. So far my investigation has been limited to data taken when the cavity used spherical mirrors; I hope to extend this analysis to MH data this week.
Chiara
I'm working on new mechanical set-up to test our horizontal attenuation system in order to measure its transfer function, I’m changing the actuator used to shake the system, and the supports for soft springs attached under the table.
Riccardo
Back from Amaldi,
Please find our
presentations and the draft of the first paper:
Justin and Sean,
This week we have been reviewing the both the experimental procedure and the data analysis for finding the Q factor in the newly designed flex joints. Next week we will begin the testing of the single crystal silicon flex joints. We will also be preparing for the experiments that must be completed under vacuum.
Francesca
I arrived to Caltech last week. In order to make my project I'm studiyng Lab View and Maddalena's thesis.
For additional information about this report, contact S. Whitcomb or P. Lindquist