Weekly Report for
Week Ending June 9, 2005
The LIGO Executive Committee meeting for June 13, 2005 is
cancelled due to the meting of the LIGO Staffing Committee.
Special Announcements:
Weekly
Report Highlights
LSC Issues (Saulson)
No report.
LIGO Laboratory Administration (Lindquist)
STATUS OF LSC MOUs (Petrac)
LSC MOUs and Research Plans and Progress Reports
Non-LSC MOUs
SITE TELECONFERENCE (Lindquist)
A site teleconference was held on Thursday, June 9, 2005. The following
items were among those discussed:
- Action
Item #131, Convenience Check Limits--(vs PCard) problem mentioned during previous meeting,
tried to get limit of $30K on convenience checks. After several iterations Caltech decided
to go to $15K for site managers and $7.5K for site heads. They want to pressure vendors into accepting
PCards and will provide assistance setting up
accounts. They want to minimize use
of convenience checks, which cause difficulties with auditors.
- TechMart is coming (out on June 20). Seems to be a hang up putting contract
personnel on the approved list. We
are working this issue.
- Landscape
Contractor for Hanford--Contract
prepared, should be issued early next week.
- The
list of assigned actions updated through March 10, 2005 will be found Here.
PROPERTY MANAGEMENT (Chargois)
>From: Ed Chargois <chargois_e@ligo.caltech.edu>
- Nothing
significant to report.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- packages:
in - 17, out - 6
- faxes:
in - 22, out - 17
- Processed
presentations from LSC Meeting at the University of Michigan.
COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman, Salone)
>From: Esther Cunningham <esther@ligo.caltech.edu>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Completed
the change order to Northrop Grumman and routed it for approvals.
Submitted it to the vendor for approval.
- Completed
change order #3 to Ezus Lyon.
- Received
the Release of Claims for Kratochwill and for
MLD Technologies. The subcontracts were closed.
- Working
on the new agreement for the landscaping at Hanford.
- Working
on the new order to Go Engineer for software, license, and maintenance.
- Working
with Helena
on setting up the new work order with JPL for testing.
- Received
a response from the last vendor that is interested in quoting for the
actuators.
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Florence Kaufman <fkaufman>
- The
monthly report for FY05 Operations and the report for the Outreach Award
as of the end of May have been completed and are posted on the network.
- Sent
out reports for the Visitor Program, Low Noise, MIT Grid, US India and DIA
Awards.
- Provided
comments re FY06 -08 budget model.
- Responded
to request re computation of MIT's Indirect Rate.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence.)
SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)
>From: irena@ligo.caltech.edu (Irena Petrac)
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- Discussions
between Ed Jasnow and the Livingston Science
Education Center
architect, Eskew - Dumez - Ripple, have
concluded with agreement being reached on a combination of the AIA
standard provisions and the LIGO general provisions to be used in the
construction RFQ. This RFQ is still
scheduled to be released this month, pending a successful review of the
100% drawings on June 22.
- A
modification is being prepared to the contract with the Exploratorium for
the second group (Group B) of exhibits for LLO. This modification is in the amount of
$496,614.00.
- Efforts
are being made to convince current vendors at the sites to accept
P-Cards. This is due to the fact
that the limit on convenience checks cannot be raised above $15,000 for the
site managers and $7,500 for the site heads. Also, there is the alternative of having
the invoices sent to Caltech (Ed Jasnow) with a
check processed to the vendors in three (3) days.
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
- PLEASE
NOTE: Returned Monday, June 6th,
from vacation and spent the better part of the past three (3) days
catching up on e-mail (293 unread e-mails), putting out fires and
generally organizing the outstanding workload.
- Processed
the paper work for zero (0) new/revised trips. At this time there are eight (8) new
trips that need to be completed and ticketed before the paper work can be
completed; and there are twelve (12) ticketed trips that need to be
processed, reservations prepaid by my P-Card and advance checks made out. Assisted several LIGO people with their
travel arrangements using their P-Cards and made several reservations for
outside visitors coming to LIGO/Caltech or one of the LIGO sites.
- Completed
four (4) Expense Reports and there are seventeen (17) reports yet to be
done. I continue to contact
travelers who have outstanding Expense Reports (more than one (1) month
old) to ask for their cooperation in sending me their receipts so that
these can be closed in a timely manner.
Presently there are three (3) reports more than 30 days old. Travel Audit's new policy of accepting
only original signatures seriously holds up the process of closing
reports. I have no reports awaiting
signature at this time. Reconciled
thirty-two (32) P-Card charges for the week requiring telephoning hotels
and car rental agencies to verify which traveler used my card and for what
amount.
>
- No
special projects to report.
>Dorothy Lloyd
- Processed
the usual invoices for payment. Tracked and followed up on invoice
problems. Reviewed and recorded payments processed by Esther for the
period of May 23 through June 3.
- Processed
requisitions for standard purchases, payment requests and change orders.
For more detail see Cost Schedule Control Systems report by Ruth Brambilla.
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
PROPOSALS and REPORTS (Lindquist)
LIGO must submit an Annual Report for Operations by August 1, 2005 and this
annual report must be accompanied by a request for a two year extension (FY
2007 and FY 2008) as well as a justification for why Caltech/MIT should be
continued in the role of management of LIGO.
I have prepared and distributed a general outline and assignments. I have requested contributions by Friday,
June 17, 2005. The outline and schedule
were presented during the Executive Committee meting on Monday, May 23,
2005. I have also distributed a first
iteration of a budget model for FY 2006, FY 2007, and FY 2008.
DCC Steering Committee (Lindquist)
We were given a presentation of the BTeV Document
Management System on Wednesday morning. BTeV is not a commercial system. It would come to us free of charge, but we
would have to install and maintain it.
We are currently re-reviewing the requirements list in light of what we
have learned while looking at five or so candidate systems.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- A
Staffing Committee Meeting is scheduled for Monday, June 13, 2005. The DRAFT agenda for the meeting has
been posted. All files are posted
and up-to-date.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
Nothing significant to report for Safety and QA this week.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of Commissioning Activities at LIGO Hanford Observatory
(Landry)
The hunt for 10Mpc continues to be the highest priority task at LHO. High-power
operation and thermal compensation studies were interspersed with WFS checkouts
and investigations into seismic up conversion.
We had lengthy test point woes, described here
and here,
which hamstrung investigations for several days during the LSC meeting.
Hanford DOE types performed a drop test Thursday morning. A 4-tonne
vessel intended to carry radioactive waste was dropped from a height of 7m in
the 300 area. Both IFOs were locked and we'll
look at these data for the calibrated pulse.
We may try pulling one of the ground connectors on LVEA building
power. The test is intended as part of the suite of 60Hz and broadband
(50-100Hz) noise investigations. The intent is to see if the ground
impacts the broadband noise observed in AS_Q, and thus requires both detectors
to be locked.
4K IFO
- WFS1
lens positions were modified
and the appropriate Gouy phase achieved.
WFS1 looks good and the optical gain is now restabilized.
- AS4
was problematic,
saturating ASI_CORR. Later the detector was repaired and rephased. We are now once again running on
all four photodiodes
- Thermal
compensation studies: code to maximize the calibration line, and hence the
optical gain in the cavities, was written and installed. The code
adjusts the TCS heat a little, trends the calibration line strength, and
then adjusts TCS as necessary. The process is a slow one, and thus
not necessarily what we want to do during production
running.
- Higher
IFO power (6W) remains difficult (only 20m locks achieved), and we still
have not found the proper WFS5 and ASI_CORR setting. Up to 4W
running is more stable.
- Later
in the week, a 4h
lock at 5.8W was observed
- Gouy phases of WFS3 and WFS4 were investigated
- VME
line investigation: lines seen in VME crates via magnetometers were still
observed when the VME front key was turned off - power is still available
to the fan.
2K IFO
- Like
the 4k, the 2k also has had bad settings on WFS1. For instance, the Gouy phase was wrong
- broadband
noise limits are range to pre-S4 values; we're down under 3Mpc (recall S4
was about 3.5Mpc)
- ASPD1
was repaired
- MC
transmitted power been moving sporadically
for forty-five days
Outreach (D. Ingram)
The community's response to El Cielo en Mayo on May 21 was great, with roughly 350
attending. The weather was terrible.
We hosted a Livingston-sized group of 90 Pasco 6th
graders on 5/25. Subsequent installation work brought the Giant
Slinky on-line, completing our set of Exploratorium
Exhibits
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
Commissioning overview (Frolov)
- The pre-stabilized
laser optical table rework was the main interferometer commissioning
activity this week. The power into the Mode Cleaner was increased to 8 W.
The phase correcting electro-optic modulator was rotated by 90 degrees to
follow the polarization flip on the optical table. The bandwidth of the
frequency stabilization servo can now be set to the design value in the
range 0.5-1.0 MHz.
- The
dark and shot noise were measured in situ for the
recently installed anti-symmetric port photo-detectors and the noise
budget was updated. The angle to length couplings for the test mass were
re-optimized (this update reflects the last coil driver modification).
- The
measurements of the angular noise and the Michelson and power recycling
cavity degrees of freedom noise coupling to the dark port are now
automated for the use in the noise budget.
- The
test mass suspension wire violin mode ringdowns
were measured in various conditions. Different interferometer power
levels, test mass angular offsets, and lock to lock variation were
investigated.
- The
measurement of the light scattered by the test mass was performed. The
data is being analyzed.
LLO mechanical engineering (Spjeld)
LIGO Outreach Building
Pendulum Exhibit
- Met
with Mike Z and John Thacker; discussed revised kinetic façade design
- Redesign
of truss, pendulum interface, roof-fender and lock in progress
- Plan
on having manufacturing drawings for quote ready in 1-2 weeks
General Engineering
- Received
one quote on HAM door removal tool; design awaiting approval
- Working
on illustrations of BSC and HAM for new educational posters
Safety & Security (Riesen)
- Found
and repaired bad input cabling in the LSS controller 02.07.13/14.
The bad input was coming from the staging bldg. fire alarm panel. System
fully operational (again).
- I now
have access to all Laser Safety System archived message log data from
11-3-2001 to present. The message log data is now being backed up
automatically on a weekly basis. Cleaned up the "input in
alarm" messages that were generated during normal work hours, thus
eliminating unnecessary message clutter.
- Performed
IR scan on all 5 laser tables and found no errant beams.
- Found
no site nor laser safety concerns this reporting
period.
- Requested
a re-quote for retrofitting the SB crane with soft start VFD's for all 3 axis.
- Did a
site recon mission searching for fire extinguishers with out-of-date
inspections. Found 4, they are being replaced with units with
current inspections.
Optics & HPLF (Franzen, Amin)
HPLF news: Continued to develop a LabView code for
monitoring and controlling the repaired 100 W laser. The code constantly checks
that the current, power and temperature do not exceed certain boundariesin which case the emission is immediatley
turned off. Hopefully this extra safety mechanism will minimize damage in the
event of future problems. The code also logs these parameters so we can more in
detail understand and prevent irregularities. So far it looks to be running
fine and we plan to start testing a series of high power polarizers.
The required three quotes for tip/tilt mirror PZTs
with electronics to be used for the REFL port beam stabilization system have
been received and forwarded to Peter Fritschel and
Rich Abbot who are in the process of placing an order. We discovered that the
system we have chosen is actually being used at the Caltech 40 m instrument!
They also provided us with some drawings for mirror mounting and more on which
we will base our design.
Scatter:
Since mid-last week, I [Rupal] have been aiding Gregg
Harry in acquiring scatter data from the large optics. Although data collection
appeared to be a rather simple matter, unanticipated probelms
arose. My primary difficulty was understanding Mr. Kell's analysis of the scatter data he obtained at LHO. Earlier
this week G. Harry consulted with Giame and Zucker regarding the data collected. We will need to take
data with perhaps a calibrated digital camera. At the moment, there is no
data supporting the theory the LLOs large optics exceed the LHOs large optics.
PSL:
Beginning on Tuesday of this week, I [Rupal] have
been assisting Rick Savage, Valery Frolov, and Vuk Mandic in PSL relay work. As seen in e-logs this week, we
rotated the broadband EOM to match the polarization of the E-field eminating from the MOPA, tuned the PMCs
MMT and periscope, changed and cleaned a few optics that were lossy, attempted to characterize the PMC, introduced large
aperture Ca polarizers to the IOO EOM chain, tuned
the FSS, and relocated the ISS PDs. At the moment,
there is a possible 8 W of optical power available for the MC.
Initial LIGO Detector Science & Engineering
(Coyne)
from Dennis
Coyne
CDS
see also the CDS weekly meeting minutes in the commissioning archives
CDS Software
no report
CDS Hardware
Rich Abbott
- Designed
and sent out for manufacturing, the panel and associated RF components to
be used as the frequency distribution point for the ASPDs
and ASI servo in the LSC rack.
- Began
testing the 5/2 frequency multiplier system purchased from Wenzel
Associates. Initial data shows extremely small amounts of
sub-harmonic distortion in the RF output. More extensive
characterization is needed. I will be measuring the input impedance
of the chain, the amount of back generated harmonics, spectral purity etc.
- Did
research for the Refl port beam stabilization
servo to decide which piezo actuator to
use. Putting through the purchase order.
- Wrote
DCN and updated schematics for the LOS Bias module
Ben Abbott
1) Three
PDs are ready for testing, and more will be on their
heels.
2) I
have some parts that need machining for the second wave, they will be sent to
the machine shop tomorrow.
3) I
have put together a final parts list, and will order the parts for the second
wave this week.
DMT
John Zweizig
This week I continued to install the online version of the DMT software on the LHO DMT nodes. The
installation is the first use on Solaris of the online autoconfigure/automake
scripts prepared by Junwei and also the first major
test of the development environment installed on the LHO machines after the
recent software upgrade. There have therefore been a few bugs/inadequacies that
are being addressed in the process.
PSL
PeterKing
Took delivery of a new Pockels
cell mount.
The optical train is still being set up after encountering some
discrepancies between the predicted values of spot sized and the measured ones.
The free-space beam propagation was re-measured.
Optic Micro-roughness Degradation
GariLynn Billingsley
We have determined that the micro-roughness of one LIGO optic (4ITM01,
uncoated) has definitely changed by slightly more than a factor of two due to
the cleaning process typically used just before coating. It is not yet clear
how much of the current scatter seen at the observatories can be attributed to
this type of change. It is also not yet determined if all LIGO 1 optics
suffered the same degradation since this piece was subjected to aggressive
cleaning.
ITMx, 4K Replacement Preparations
Helena Armandula
Document LIGO-T050094-01-D has been placed in the DCC detailing the
procedure used to bring close to specifications the AR reflection of
ITM05. The optic was cleaned and shipped
to Hanford. Traveler E050156-00-D.
The cleaning procedure to be used on this optic has been sent to Hanford (Betsy) for
review.
Liyuan Zhang, Lee Cardenas
The AR coating was etched. The final measurement for the AR coating is ~
1000ppm.(goal 900ppm +/- ~300)
The AR uniformity, RMS/MEAN ~2.5%, as compared with last etched mirror
2itm03 with a uniformity of ~20%
http://www.ligo.caltech.edu/~lzhang/4itm05/4itm05_arr_4_r1.pdf
During final clean up, Helena
found a small laser burn mark with haze around the burn area approximately
3/4" from the optic edge near the reference arrow mark. This mark should
not effect performance.
The mirror will be packed and shipped to LHO.
40 Meter Interferometer (Weinstein)
IFO commissioning:
- Rana finds that he is able to lock the entire IFO with
minimal tuning, even after a day or two with the IFO unlocked. It locks in
less than 5 minutes; then with a little alignment tweaking it locks
repeatedly in less than a couple minutes. So it seems the interferometer
is actually very stable and we don't have to do any serious tuning each
day.
- Rob
has produced Finesse models for CARM and DARM to verify the behavior of
the IFO with all 5 degrees of freedom controlled, but with CARM offset
from arm resonance. As the offset is reduced, the coupled-cavity pole is
reduced and passes through the CARM servo UGF, and lock is lost. The RSE
peak moves accordingly. His model seems to explain the behavior, and the
features of the CARM and DARM OLTF's,
qualitatively well. This will help in designing loop filtering to minimize
or eliminate the problem.
- Rob
and Rana found that it was easy to transfer
control of DARM to the RF signal at AP 166Q. In the LA mode #6, the DRMI
is controlled by the RF signals and CARM & DARM are controlled by
common and differential combinations of the arm transmitted QPD signals.
Although CARM is now locked far from resonance, DARM is at the carrier
dark fringe. They were able to use a script to do a smooth handoff of DARM
control from the DC to the RF signal at AP166_Q. They did this several
times; there is no transient. So now there's just one more signal to
switch to RF: CARM.
- In
preparation for a systematic diagonalization of
all the suspended optics controllers, Dan and Steve are measuring the POS,
PIT, YAW and SIDE pendulum frequencies of all 10 suspended optics, freely
swinging. There are a variety of anomalies. For example, the POS and SIDE
frequencies are well separated, with the SIDE frequency a bit higher than
POS, but on the SRM it's the other way around... under investigation.
- Rana implemented and tested scripts to do automatic
align/misalign of the IFO optics, as well as saving and restoring of
alignments in each of the many different IFO contfigurations
that we operate at. (Xarm, Yarm,
Michelson, PRMI, DRMI, & Full DRFPMI). He also created and exercised a
script for setting the MC WFS UGF. He also copied over some IFO Configure
screens and scripts from LLO, and is automating the IFO down steps and the
current lock acquisition steps.
- Steve
has recentered all of the oplevs,
and the arm transmitted QPDs, to Rana's alignment of 6/6/05.
- Monica
continues to work on a report about calibration of length sensing and excitation
signals.
IFO modeling and DC detection development:
- Monica
continues to work on measuring error signals slopes in her e2e 40m
simulation, and verify the Twiddle and Finesse predictions for the signal.
- Monica
gets good agreement between e2e and Twiddle/Finesse for the length sensing
signals from AP33Q and AP166Q, but not so good from SP33I and SP166I. The
discrepancy is likely due to the demodulation phases, so shee is trying to implement in e2e the algorithm used
in Twiddle to calculate the optimal demodulation phases.
- Monica
is working on e2e simulation of the OLTF's for
all the length control paths in the 40m IFO.
- Monica
and Virginio are working towards being able to
plug the length sensing and lock acquisition code in use on the 40m front
end (developed and maintained by Rob) directly into e2e. It is, of course,
not an easy task. They will work with Rob, and with advice from Hiro and Matt.
Electronics, controls:
- Ben
tested the readout of a single RFPD
DC signal, read in two
different ways. The first was from the SMA on the RFPD, and the second was
from the P2 connector of the LSC PD Interface. Once they both were read
through the same Whitening channel, they looked very similar. If there
were any differences, the P2 connector signal may have had a slight
reduction in 60Hz noise. We are now converting all of our RFPD DC signals
to readout through the P2 connector of the LSC PD Interface, to minimize
ground loops.
- Heat
sinks have arrived for the I&Q Demod boards. Ben will install them soon.
- Ben
disconnected the superfluous Earth GND connecting the Racks with the
shutoff switch panel. Now there are only three wires hooked up at both
ends, the isolated hot, neutral, and earth. The rack is no longer tied to
the local earth through the extra GND wire. This should help reduce ground
loop problems.
- The
IOO PZT steering board was not functioning correctly, so Ben brought it
back to the back shop, and fixed it. He then hooked up the IOO steering
PZT to the PZT Driver, and now it is possible to steer the input beam from
the control room.
- Our
LSC cpu is dangerously
close to max (61 usec) in some configurations. Rana deleted nearly every unused filter in the LSC
filter file. The total CPU time recovered is 4 microseconds.
- Bob
ordered insulating panels for the optics tables (in our ongoing effort to
reduce ground loops) and has given them to the machine shop for cutting
and drilling.
- Rana and Jay fixed an apparently dead OSEM sensor (MC3
UL) by unplugging- and replugging the connector.
The connector wasn't screwed in; we need to install screws on all of
these.
Thermal Noise Interferometer (Black)
No report.
LASTI (Ottaway)
From: Richard Mittleman
We have been investigating the BSC structural noise enhancement in the
10-20Hz range. The current best theory is that the flagpole resonances of the
vacuum, chamber are coupling to the support structure through the floor. We
have mapped out the motion of the floor when driven by a 10kg mass driver
mounted on the vacuum chamber. This data will be used to validate a FEA model,
which is being developed. There are a number of data plots displayed on the Lasti ilog over the last week.
We have been making progress on the model, which now runs in Nastran.
The solid stack assembly has been completed and assembled at the fabricator.
We are evaluating which cleaning technique will be used.
The design is complete for the LASTI test stand. Fabrication drawings are
being made.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
Commissioning Support
(Biplab) Worked on correcting Gouy
phase Telescope set-up with Keita for H1 interferometer's Wave-Front Sensor1
(WFS1). Analyzed other WFSs as well. Conclusions
are (details-> see elog June 7).
(A) No change necessary for WFS4 Gouy
telescope.
(B) To improve signals in WFS2 and 3
(i)WFS2: Better to change from
current setting of 180deg to 145deg
(ii)WFS3: Better to
change from current setting of 10deg to 150deg
Advanced LIGO Simulation
(Matt) Started analysis of SimADL (Advanced LIGO simulation) optical path lengths,
resonance conditions, and control possibilities. Once things are in order I
plan to implement a control scheme similar to the one in use at the 40m.
Simulation of 40m Advanced Interferometer
(Monica: Last Week) The pick-off port has now been correctly implemented in
the e2e package for the 40m,i.e, the extra losses due
to the AR coating (600 ppm) have been added. Also an e2e box to include the AR
coating on the mirrors has been created but it is not necessary to implement in
the simulation at the moment.
(Monica: This Week) Error signal slopes have been calculated to verify
Twiddle and Finesse predictions for the signal extractions matrix: still under
investigation. The algorithm used in Twiddle to generate the demodulation
phases is under study and will be implemented in e2e 40m package as SP33I and
SP166I channels don't match like the AP33Q and AP166Q for which the
demodulation phases are exactly 0 e pi/2. The simulation of an open loop
transfer function of the full interferometer is under test. An attempt to
understand how to plug and play the real 40m lock acquisition code in e2e 40m
package has just started.
Code development
(Hiro) Still working on modeler
for adv.LIGO. A version was tested by Matt and
several issues were found and fixed or being fixed. Fast dual recycling module
is being coded based on the matlab code.
Alfi
(Bruce) There are several areas in the Alfi's main
object, ALFINode which can be made more efficient to
speed response and save times. This is
what I am working on now.
(Melody) Finished with the user interface to allow the
user to choose the display for nodes:
graphic, node name, or a multiline
description. Worked
on allowing primitive nodes to be able to display an icon from a jpg or gif
file. Continuing with fixing the
Problem Reports(PR). Currently
fixing PR 473: Duplicated item placed outside of view.
Data Analysis Activities (Lazzarini)
Mandic:
I made a first attempt at the stochastic analysis of the S4 data. The
analysis was done including a time-shift in one of the detectors, as the main
goal at the moment was to study the data quality and to define the necessary
cuts, rather than to obtain the final estimate. The H1L1 pair seems very clean,
with the theoretical error of about 2.2e-5 over about 14 days of exposure. The
H1H2 result was not so clean - even the aggressive notching of coherent lines,
and including a time-shift, yields a 10-sigma result (with the theoretical
error of about 2.4e-6).
I continued studying accessibility of the pre-Big-Bang models to LIGO. I
started writing up some of the results.
Sutton;
I spent most of the past week at the LSC and burst group meetings in Ann Arbor. In particular, I presented a brief summary of
the CIT/JPL efforts at coherent network analysis algorithms for bursts
searches. Since returning I have
continued working on this problem, particularly the question of template
spacing.
Shawhan:
- Attended
the LSC Meeting and Burst Group face-to-face meeting in Ann Arbor.
- Made
final edits to the S2 LIGO-only untriggered
burst paper before submission to Phys. Rev. D.
- Reviewed
pulsar analyses.
Weinstein:
- Lots
of Inspiral review activity
- Trying
to run Javi's h(t) code
- Working
with Lisa on ringdown search
LIGO Data Analysis System
Software Systems (Blackburn)
Significant effort was put into the LDAS account management scripts to fix
some long standing issues. The default length for an account now is 2 years
(pr2808). Applying for an extension extends a user's account for a year
(previously 6 months) provided the extension would not cause the user's account
to be valid beyond 2 years from the day they apply for the extension. Also, a
user is now forced to select at least one site (pr2801) when applying for an
account. Finally, if a user's full name has an apostrophe (ex: O'Neil), the url sent to the LDAS account
administrators no longer gets truncated (pr2798, pr2797). This allows the
administrator to click on the link and get a web browser started to finalize
the request.
The index.cgi script which is responsible for
generating the site’s home page for LDAS has been corrected to prevent
the generation of a log message about an undefined variable being used
(pr2512). In addition to this, a favicon.ico was
generated for LDAS to prevent the web server from complaining about its
non-existence.
The frameAPI has been extended to understand many
file types (pr1904). The check is only
performed if a frame file is opened and corruption is detected. This allows for easier diagnosis of the
common problem of trying to use the frame library on
non-frame files.
All references to ERR have been removed from the LDAS code base (pr2820). This
is the only known issue that was discovered as users tried compiling frameCPP
under Solaris 10.
FrDumpObjects has now been extended to dump the FrTOC structure (pr2822).
The ilwd library no longer hangs on ilwd files that do not start with <?ilwd?> (pr1349).
Fixed the parsing and updating of multiple line resource file variables
associated with Problem Report 2837 by making code changes to both the server and client code for
the controlMonitorAPI, also required changes to the genericAPI.
Modified the display code for running all user commands
from the controlMonitorAPI's client so that intermediate
results are color coded in the test results page.
Completed system and integration testing of LDAS version
1.6.3 on the LDAS-DEV system. No
issues found.
Updated the Tandem 3, 4, and 5 developer's test systems to be able to run the 1.6.x
series of LDAS versions. Tested with integration and systems tests and
discovered a ICMP permissions problem for ldasbox3 (part of Tandem 3) which is currently being
worked on by system administrators.
TCLGLOBUS
Version 0.2.0 of TclGlobus was constructed this week.
It fixes all know issues with failed tests, memory corruption, and memory leaks
found in the 0.1.0 release. It also now supports Globus
4.0 (GT4) in addition to Globus Toolkit 3.2. The dependency on the TCL thread library have been removed,
greatly simplifying the distribution. It has now been shown to work with
out-of-the-box Redhat 9 and Fedora Core 3; No custom
installs of tools necessary. This is well in advance of the July 1 deadline set
by the DASWG for distributing 0.2.0.
The TclGlobus Project's development hardware is
being upgraded this week to Support multiple versions of Linux, starting with
an upgrade to Fedora Core 3. As a result
the announcement of the 0.2.0 release will be delayed until the box is back on
line since it is used to distribute the code.
OSG / GRID COMPUTING
David Meyers has joined us to work on Grid Computing and in particular on
the Open Science Grid Integration Testbed activity.
David comes to us from NASA Ames where he carried out similar Grid Computing
activities for NASA. David has completed his navigation of the Caltech new
employee processes and worked with Kent on developing a top level task
list and requirements list for the OSG testbed. He
has also been registered on the relevant OSG mailing lists. His first task was
to obtain an X.509 certificate and become familiar with Pacman
and the LSC DataClient. Please join me in welcoming David to our
group.
The OSG Consortium Meeting hosted by UWM's LSC
Group was announced this week. The meeting will take place July 20 and 21 with
an OSG Council Meeting follow on for July 22.
Hardware Systems (Ehrens for Anderson)
[Dan Kozak]
- (from
the week before) Converted CIT /archive to use md
devices, upgraded SAM on dataserver-cit/ldas-cit to 4.3.11, upgraded 3510
firmware to 4.11I, spent a long
time debugging problem with a wedged logical volume on the 3510 with the /archive metadata and
/export.
- Did
some cleanup related to the dataserver-dev root
disk failure (putting in necessary
NFS exports mostly)
- Moved
2 9940B tape drives to controllers 8 & 9 (from 2 & 3) on dataserver-cit
- Checked
for logical volumes on 3510s at L?O: there were none
- Discovered
failed 3510 controller at LLO and had Igor call it in to Sun
- Fixed
some wedged Linux NFS clients of /archive
- Freed
up some tape slots at LHO, working on doing more
- Replace
4 failed 3510 disks at CIT
- Continued
cleanup of /archive at CIT (merging in tapes shipped from LHO with postS3 data, among other
things)
- Dealt
with big CIT /archive failure:
The first problem I noticed was:
Jun 8 15:58:44 dataserver-cit
samfs: [ID 889405 kern.notice]
+NOTICE: SAM-QFS: archive: sam_wait_space: File system full - META ENOSPC
followed
by lots of these:
Jun 8 16:03:27 dataserver-cit
samfs: [ID 509738 kern.warning]
+WARNING: SAM-QFS: sam_bread: bp=304b7053960, blkno=5ae0, dev=7600000090,
+count=16384, error=5
and then dataserver-cit rebooted itself.
It seems that the 3510 that holds
the /archive metadata and ldas-cit's /export disappeared
from the fabric briefly. I ran samfsck -F on /archive when it came back up then remounted
it (two empty directories were all that showed up in /archive/lost+found). FrCheck of a few of the last LDR transferred files all
passed. /export needed to be remounted,
/scratch didn’t complain (probably no filesystem
activity during the time that the 3510 was offline). The SAM-QFS shared clients all required that sam-fsd be killed so that a new sam-sharefsd
could be started. I had to remember to
restart the NFS server on dataserver-cit (/archive
wasn't mounted when the system came up, so it didn't get exported so the NFS
server didn't start...I think) and now the cluster users can see their home
directories again.
My guess is that this was caused by
the work I was doing on 3510-10 (the test unit) which had managed to get itself
into a number of odd states and was connected to the main switch at the
time. I've disconnected it from the
switch and left it direct connected to olddataserver-cit
only.
- Restarted
all of LDR on ldas-cit after /export &
/archive were back online (all the daemons had died off).
[Phil Ehrens]
- Received
warranty replacement memory for ldas-cit node218
from ASA.
- Built
and configured machine 'Verruca' for Dave Myers.
- Built
and configured machine 'Spud' for Diego Fazi
from chassis and parts of decommissioned machines.
- Built
and configured machine m71 - this machine had been set aside due to
unreliable behavour, it would crash daily. It
turns out that the dimm in socket 1 was bad. I
replaced the bad dimm and ran memtest, and it is now a happy machine. Upgraded the cd-rom drive to a dvd drive, replaced the non-functional floppy
drive, and upgraded the HD from a 10 and a 20 to a refurbed
160.
- Replaced
drive 0:6 in datacache6.
- Created
a schema for backing up Linux installations that does not require similar geometry on the
target drive. The mbr, partition metadata, and
individual partitions are stored in compressed form and can be installed
either via dd or by mounting them as loop
devices and copying them. Still
some work to do to automate the backups fully and to integrate ssh for backing up (and restoring) over the network.
- Observed
Dan Kozak's valiant retrieval of the dataserver-cit filesystem,
and assisted minimally.
General Computing (Wallace)
MIT:
(Keith)
- Rebuilt
and patched late model thinkpad (570)
- Built
new print spooler (LPRNG) on emvogil-3
- Replaced
emvogil-3 Ultra10 with SB1500 to host new web address
- Moved
CVS and ilog repositories over to new machine
- Rebuilding
ancient thinkpad (560E)
- Building
backup ldap slave server
- Ordered
new laptop and assoc. equipment
- Added
several more urops
- Added
new grad student (Jared Markowitz)
- Reinstalling
/ patching Optiplex 260 desktop (XP) for lab use
Livingston:
(Shannon)
See LLO report.
Hanford:
(Christine)
- Network
usage can be seen at http://www.ligo-wa.caltech.edu/~christin/mrtg/
198.129.208.1_198.129.78.122.html
- Spoke
with PocketiNet about providing our backup
network. They are working on a
proposal and have suggested a wireless network into Richland. PocketiNet can
also connect to our spare fiber at PNNL, they
don't require us to get from PNNL into the APEL building in Richland.
- Setting
up computers, user accounts, office space and extra printers for use by
the SURF students and visiting teachers.
- Re-building
a laptop for the loaner pool with dual boot Windows XP and Fedora Core 3.
- There
are more old computers and monitors that will be disposed of later this
month when Ed Chargois visits. I have to label which ones are to be
disposed of and which are to be kept as spares.
- Helped
two users with e-mail problems.
Reset the password for one user.
Ordered some ergonomic and optical mice. Requested CDs for the latest version of Mathematica.
Other misc. user support.
CIT:
(Mike)
- Linda
Turner: Worked on an e-mail issue with Larry on Linda's laptop. This issue seems to be resolve for now.
- Visitor
Workstations: Loaded two more PC workstations for visitors one for Millikan, and the other Bridge Annex.
- Loaner
laptops: Reloaded two laptops for the loaner pool I am still loading
software to complete these units to have ready for loaning purposes.
- Spam
Filters: This week was more than the usual spam, which required much more
spent time on this job function.
- Barry
Barish: Problems with his laptop freezing up. After
trouble shooting this issue, it turns out that the motherboard needed to
be replaced. This has been taken care of.
- IP
Database: Spent some time updating the info on our Database. I have a lot
of work left on this project.
- Millikan: Larry and I ran a couple of network cables
in the Server Room from the CIT/LIGO Network Closet. This is for the new
"copier/scanner/printer" that is in place of their old one. Set
this up on Irene Baldon's workstation to load
drivers to run test to insure that this unit is working correctly.
- User
onsite/phone support that included loading additional software, printing,
e-mail, and some software issues.
(Veronica)
- LIGO: Finished the updates to the AdvLIGO Project Schedule subsystem webpages. Prepared a set of high-resolution images
for a popular science magazine.
Updated the roster database.
- LSC: Updates to the June meeting
website. Posted the meeting
presentations. Updates to the
'papers under review' webpages.
- CaJAGWR:
Troubleshoot the account's email to use IMAP rather than POP. User support.
(Bruce)
- (BS) Ilog Development (1.5 days)
Incorporating many requests made
over the past few months. Especially in
regards to the ability for users to easily place more than one image in an
entry.
(Larry)
- Worked
a number of procurement issues. Mostly, cleanup and checking on some
maintenance contracts. Working the
IDEAS licensing. There is some confusion on what has been delivered and
licensing. Hopefully, this will all be cleared up by the end of next
week. It appears that we will need
a couple more PC's for the developer group.
- Still
working logistical issues with PMA and the air-conditioning construction
group. Things are getting down to the testing time. Waiting for a report on the augmentation
of the air-conditioning in the computer room.
- Working
on the systems for the E2E group. The machines needed to have the disk
drives moved to new locations because of heating issues. This took more
time than planned in that a good portion of the machine needs to be taken
apart to get to the disk drives. Two units have had the hardware changes
made and presently installing the OS.
The OS installation on one unit has not been a fast one. It will be
reinstalled just to make sure something has not been missed.
- Assisted
Mike on debugging and checking out a number of PC's for different users.
He's been swamped getting systems ready for the SURF students.
- Setup
a couple of new user accounts and working on cleaning a few more off.
- Tested
out a couple of SCSI drives. So far they have passed the diags and one has been formatted for
installation.
- Assisted
Cleveland
in getting some documentation (boxes of it) moved to the sub-basement. Also, worked
at getting a couple of other offices cleaned up for the summer visitors.
- Worked
on some documentation and the yearly report.
- Worked
a number of e-mail issues. Mostly retrieval for different users.
Mail Statistics Jun 02-08, 05
Rejected
Messages 21,629
Virus
Messages 1,867
False
Positives 364
Accepted
Messages 14,091
Total
Messages 35,720
Advanced LIGO and Supporting R&D (Shoemaker)
Systems
from Dennis
Coyne
See also:
AL Systems web
page
AL Systems email archives
Records of Decision or Agreement (RODA)
See also the RODA
status web page
Requirements
- Issued
the "SUS Universal Requirements Document", T000053-02 (Janeen & Dennis)
- Issued
the "LIGO Generic Requirements and Standards" document,
E010613-01 (Dennis)
- Jay Heefner has been writing requiements
and interface definition for the SUS Electronics/UK PDR to be held Tue
7/12
Interface Issues
See the "Interfaces" section of the AL Systems web page
- Have
been collecting interface requirements & data for the SUS incremental
PDR review on the BSC Quad (focused on requirements) on Wed 6/15
Vacuum Compatibility
Residual Gas Assay (RGA)
See also the Vacuum Bake Lab
Bob Taylor
- I have
finished the bake jobs on the AL OSEM Emitter & Photodiodes and will
give them to Lee.
- I
repaired the SRS RGA on oven C.
- I
ordered the shielding for the OSEM leads on the Quad Suspension. I should
receive the shielding wire this week.
- I
have shipped four Turbopumps to Leybold for repair.
- I
have disassembled the Vacuum system plumbing and am awaiting the return of
the turbopumps to finish the repairs of oven C.
- I
have been working with Helena
and Ken on the new air bake oven Qualification Doc.
High-Irradiance, Contamination-Exposure Cavities
Lee Cardenas, Liyuan Zhang
[Remainder of Systems Report Corrupted]
From: Jay Heefner <jay@ligo.caltech.edu>
AdL CDS
Testing of the AD7679 shows that the input referred noise of
the device is on the order of 100nV/rtHz for frequencies greater than 200Hz
with a sample rate of 570Ksps. The floor may be lower, but the input amplifiers
provided by Analog Devices on the evaluation board have a similar output noise
level. The amplifiers will be changed and the noise around 100Hz will be
investigated. Testing was done using the AD7679 eval
board connected to a LIGO designed FPDP interface to a Pentium processor. The
interface is easily able to handle the 570KHz, 32-bit
transfers. Note: the ADC is 18 bits, but the FPDP interface is 32 bits wide.
Seismic Isolation
From: Ken Mason kmason@ligo.mit.edu
No report this week
From: "Joseph A. Giaime"
jgiaime@ligo.phys.lsu.edu
Agenda from the weekly SEI phone call
Electronics (Jay)
- ADE
has 4 fine sensors, but Jay hasn't got feedback yet from them.
- Other
4 fine sensors hooked up at Caltech, and look similar to other ones (24 Hz
bump). During warm-up, bump moves
from 40 -> 24 Hz or so.
- Cabling:
Ken sent routing info to Jay; they need to study that it will work. We should have a reasonably detailed
plan and drawing of the cable routing before releasing the mechanical
drawings.
HAM diagram changes (Dennis, Rich, Brian O)
- Team
has agreed on a new diagram. Brian
O'Reilly will ask Rolf to make the changes.
BSC Amplification (Rich, Pradeep)
- Rich
has analyzed the TF from the flange -> floor force -> displacement
experiment, and has posted an early result from this. Matlab
function 'griddata' has proven to be useful in
dealing with data of odd frequency spacing.
- He
has also posted data of the noise enhancement between the pier and the
crossbeam at MIT and LLO. The
enhancement is smaller at LLO, but the peak frequency is lower.
- Dennis
has posted his notes from earlier analysis of the LLO and LASTI floor and
pier resonances.
- LASTI
test stand (Ken)
- Ken
has posted drawings of his LASTI SEI/SUS test stand. He plans to complete the FE models and
analysis in the coming week. The
system need the ability to match the bumpy floor and yet have parallel and
level mounting bosses on the mock support tubes.
- Modeling
for softer springs (Brian L.)
- Brian
has assembled a dynamic model using the June '04 ASI design parameters
(i.e., the 8 cm offset between the CG of stage two and the actuator plane
in stage 2). His model is still
numerically unstable, so he's doing brain-stretching exercises to
visualize the 300+ state system. At the moment he still feels that we
won't reach the 2 × 10-13 m/√Hz at 10 Hz, largely due to the
measured excess HEPI platform noise at 10 Hz.
- Joe
needs to redo his noise estimate curves from the review in light of
Brian's results, and more carefully taking into account the vertical noise
expectations.
Procurement:
- We
still need to produce a procurement plan for the mechanical parts (KM, to
be evaluated by DC)
- KM
& JG need to negotiate with ASI an amendment to their contract to
rework the spring geometry. This
should be ready to go so unnecessary delay doesn't accrue when we set the
new blade parameters. See SEI log
entry 430 for the large spring shape discussed at Stanford and drawn by
Corwin in April.
From: Jay Heefner
<jay@ligo.caltech.edu>
AdL SEI
ADE has found the source of the 24Hz noise peak on the capacitive position
sensors. It is related to a circuit instability caused by the larger probes we
ordered. They are retrofitting the 4 units that we originally sent them to
test. We have also sent the other 10 units back for retrofit.
Suspension
From: Janeen Romie
<romie_j@ligo.caltech.edu>
Advanced LIGO Suspensions
- Working
on the Universal SUS DRD.
- Placing
POs for some of the final suspension parts. Following up with the two
campus machine shops for parts.
- Working
with Carol and Dwight on SUS organization in the cost book.
- Worked
with Justin and Dennis on Justin's requirements issues.
- Submitted
a PR to purchasing for 2 Solidworks seats and PDMWorks for all seats.
From: ctorrie
<ctorrie@ligo.caltech.edu>
SolidWorks and PDMWorks
We have now moved to SolidWorks 2005 and PDMWorks 2005. This was to allow us to come into line with
new collaborators who have purchased SolidWorks
recently. These include the Physics machine shop at Caltech, Birmingham and RAL (RAL will only use it as a
transfer tool). All of the CAD users at Caltech will now have full access to
the vault and we are testing the usefulness of the standalone version of PDMWorks with Helena.
With the machine shop using PDMWorks they can access
files directly and load the part files onto their CNC machines!
Quad Suspension
We are waiting on one part of the wire jig to be modified to allow us to
re-make the wire for the upper intermediate stage,
once this is done we will again look at the clamps used in this stage,
reference design meeting for more detailed discussion. The lower structure face
plates, with an off-campus shop, are progressing well and we plan to visit them
next week. The upper structure has had some manufacturing problems recently but
I believe we are now overcoming these and one of the structures is partially
welded.
Design Meeting
http://www.ligo.caltech.edu/~ctorrie/QUAD_ETM/quad_etm_setup_page2.html
Visit to Glasgow
and future visits.
I visited Glasgow
last week to talk to Mike and Russell about some items associated with their
effort towards the controls prototype. This effort has effectively finished
however Glasgow
are allowing them to work with me to complete the
work. As part of this Russell will visit Caltech later this summer.
Tim Hayler will also visit for a week later this
month and hopefully Ian Wilmut will come for a week
in July.
From: Ken Mailand
<kmailand@ligo.caltech.edu>
- Will
meet with Helena and Bob tomorrow to finish the 40m oven qualification
specification. The large bake oven
for the 40m Lab is on schedule for delivery.
- Mike
Gerfen is adding some hole and tap features to
the two test plates to make them identical as possible for the FTIR test.
- Adv.
LIGO large part oven / cleaning station spec. modified, and responses expected
later this week re. price and delivery estimates.
40m
Mike Smith’s lens focuser assembly parts delivered complete.
From: Jay Heefner
<jay@ligo.caltech.edu>
AdL SUS
Writing requirements documents for AdL SUS
electronics designs.
Core Optics
From: Gregg Harry <gharry@ligo.mit.edu>
We are continuing to measure modal Q's on the CSIRO silica/tantala coating with the commercially polished
substrate. So far we have:
Mode Freq Q
Drum 4151.27Hz (3.44+/-0.05)E5
13th 9383.35 (3.42+/-0.09)E5
14th 10557.94 (3.69+/-0.07)E5
These are a bit higher in Q than the equivalent CSIRO super polished sample. That would seem to indicate that the
substrate polish isn't playing much of a role, and the slight improvement may
be due to maturation of CSIRO's coating process.
From: Helena Armandula
<ahelena@ligo.caltech.edu>
Synchrotron Modular Clean Room
The Synchrotron lab was cleared to make room for the clean room installation
that was supposed to take place on Wednesday. An unforeseen mishap with a
Boeing clean room installation postponed our job until this coming Friday. The work is now expected to be finished by
next Wednesday.
Optical Cavity Vacuum Testing
MMG nickel plated Nd-B-Fe magnets that were
cleaned and baked were delivered to be tested for vacuum qualification.
New Air Bake Oven QualificationObtained an estimate
from JPL of ~$1K to run FTIR analysis to detect molecular contamination on a
"fired cleaned" piece of aluminum. The aluminum part will be provided
by JPL and is certified "clean". They will also perform a particle
count and particle identification analysis for which they'll provide a
certified particle free wafer.
From: Bill Kells
<kells@ligo.caltech.edu> :
- Conflicting
observations and measurements keep accumulating on the amount and origin
of the LIGO I arm cavity loss (and therefore the Net HR coating losses.
Adding to this is the recent result that one (uncoated) TM has been
measured to have significantly increased micro roughness (since its
original polish.... having been cleaned meanwhile). We are going into a
review of all the mapping, scattering loss, FFT modeling, and other
analysis to make sure there is consistency. Then, concomitantly plotting
new measurements to resolve the puzzles.
- Once
again the parametric instability (for arm cavity resonant light) has become
topical. Various people ( P. Willems,
Perth
group, with an eye on Gingin, myself) are
looking into now planning a feasible experiment to see this phenomenon.
First study: of the existing resonant cavities (say, 40m, OTF flat top
test facility, LIGO I, Gin-gin, etc.) which might uniquely be suited for a
demonstration. It seems unavoidable to conduct some direct investigation
into the nature of this, prior to full design of AdL.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
An mail alias was set up for the lasers working
group. I have not tested it out as yet.
Auxiliary Optics
From: Michael Smith <smith@ligo.caltech.edu>
BS DIFFRACTION LOSS
An updated technical report is being prepared.
SURF
I prepared a work area in the LIGO optics lab for the BRDF experiment and
the Oplev receiver experiment. I procured and
borrowed most of the equipment needed. Still pending is the purchase of a PDA
255 photodetector, the read-out display for the oplev QPD, and an AOM @ 40MHz.
The housing for the optlev receiver was made by
the CIT shop. All lenses were ordered and most are received. Two fixed-focal
length configurations will be built and evaluated: 33460 mm EFL, with an
angular semi-field of view of 150 microrad; and 13660
mm EFL, with an angular semi-field of view of 360 microrad.
The lens assemblies are approximately 300 mm long.
Other Laboratory R&D
From: Riccardo DeSalvo
desalvo@ligo.caltech.edu
Juri
I made several checks of my calculations for coating thermoelatic
noise, using the infinite mirror formula found in literature and using two
different approaches to the calculation of dissipated energy. Now the program
is running with a Flat Top beam sampling the surface of the mirror. Actually I’m calculating the thermal
noise for different test mass aspect ratios and beam radii keeping the total
mass and diffraction losses fixed. Results will be soon available, at least for
fused silica substrate.
Chiara
Going trough the measurements to test the horizontal
attenuation system; now I’m using two accelerometers and a spectrum
analyzer in order to measure the transfer function of the apparatus. For a better excitation of the bottom plane
we have leaned it on two cylindrical bars instead of fixed supports. Still taking classes in the Machine Shop.
Marco
Finished measurements of beam characteristics with
Gaussian beam and the new folding mirror. Switched to Mex hat mirror. Tuning up.
Special Late Breaking News (Riccardo)
During this afternoon we were able to adjust the input-cavity alignment and
get the first pseudo-mesa beam profiles (mirror # 05008). I attached a image
grabbed by the camera. The lock was very
stable. Cavity resonance is very sensitive to the input beam position. I took different profiles with different piezo-tilts.

For additional information about this report, contact Phil Lindquist