Weekly Report for
Week Ending June 2, 2005
The LIGO Executive
Committee Agenda for Monday June
6, 2005 will be:
(Meeting time: 10:30 am Pacific Time)
- Announcements
- Comments on Weekly Report
- LSC Issues (Saulson)
- LIGO Lab Operations
- Administration
(Lindquist)
- Sites (Raab,
Zucker, Shoemaker)
- Commissioning
(Fritschel), Detector (Coyne)
- Campus Research
Facilities
- 40 Meter
(Weinstein)
- TN, ( Libbrecht)
- LASTI (Shoemaker)
- Data Analysis and
Computing (Lazzarini)
- R&D and Advanced LIGO
(Shoemaker)
- CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION AS NEEDED
- There
are no open Change Requests
Special Items:
Special Announcements:
Weekly
Report Highlights
LSC Issues (Saulson)
No report
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Petrac)
LSC MOUs and Research Plans and Progress Reports
Non-LSC MOUs
SITE TELECONFERENCE (Lindquist)
No site teleconference was scheduled for Thursday, June 2, 2005.
- The
list of assigned actions updated through May 26, 2005 will be found Here.
PROPERTY MANAGEMENT (Chargois)
>From: Ed Chargois <chargois_e@ligo.caltech.edu>
- Nothing
significant to report.
DOCUMENT CONTROL CENTER (Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- packages:
in - 15, out - 3
- faxes:
in - 19, out - 13
- No
special projects to report.
COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman, Salone)
>From: Esther Cunningham <esther@ligo.caltech.edu>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Completed
change order #1 to Purchase Order 1065466 to
Technology Unlimited for the renewal of the maintenance agreeement for the Cannon document scanner through
5/31/06.
- Completed
change order #3 to the Amerion subcontract for
the 3 month extension of internet service for LHO. Submitted the change to
Larry Allaway at Amerion.
- Placed
the Sun Microsystems orders for the computer servers for the LIGO Hanford
and Livingston Observatories.
- Working
on completing change order #38 to Northrop Grumman for routing.
- Working
on change order #3 to Ezus Lyon.
- Changed
the poetas on encumbered funds on computer
maintenance charges, as requested.
- Completed
change order #26 to the Galli and Morelli subcontract to add funds to cover a pending
invoice.
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Florence Kaufman <fkaufman>
- Updating
monthly financial reports [for the end of May].
- Provided
information for a sales tax audit.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)
>From: irena@ligo.caltech.edu (Irena Petrac)
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- Efforts
are underway to increase the spending limits for site staff authorized to
write convenience checks. The
initial effort was too increase the limit from $7,500 per month to $30,000
per month, but both Caltech and Bank of America are reluctant to go that
high. Agreement has been reached to
increase the limit to $15,000 per month.
- In
the meantime, it is recommended that all vendors for the sites be
encouraged to accept P-Cards.
Caltech staff is willing to work with the vendors' merchant banks
to set up credit card accounts.
- Progress
continues to be made on the RFQ for the LLO SEC, with the final document
still scheduled for release in the middle of June.
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
>
Nothing signifiant to report.
>Dorothy Lloyd
- No
report (vacation).
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
PROPOSALS and REPORTS (Lindquist)
LIGO must submit an Annual Report for Operations by August 1, 2005 and this
annual report must be accompanied by a request for a two year extension (FY
2007 and FY 2008) as well as a justification for why Caltech/MIT should be
continued in the role of management of LIGO.
I have prepared and distributed a general outline and assignments. I have requested contributions by Friday,
June 17, 2005. The outline and schedule
were presented during the Executive Committee meting on Monday, May 23,
2005. I am now distributing a first
iteration of a budget model for FY 2006, FY 2007, and FY 2008.
DCC Steering Committee (Lindquist)
We were given a demonstration by Xythos here at
Caltech on Wednesday morning. Xythos comes to us a little late in the process but is of
interest because their application is tailored for the educational and research
environment.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- No
special activities to report.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
Nothing
significant to report this week.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of Commissioning Activities at LIGO Hanford Observatory
(Landry)
Our top priority on commissioning
remains H1; we have several (2) weeks to reach a binary inspiral
range of ~10Mpc, or face the prospect of breaking the vacuum and swapping out a
core optic. Highlights of the commissioning week are bulleted below.
4K IFO
- The
power into the mode cleaner was increased to its highest to date,
6.8W. Locking the full interferometer and servoing
the TCS by hand, a brief lock was achieved, on the order of 5m. A
long lock stretch at a lower power (4.6W into the MC) was also achieved,
in part with a TCS servo applied. Here the ASI_CORR servo sign flip
noted in previous weeklies was again observed, but seems to depend on the
IFO thermal history.
- We
have noted a decrease in H1 binary inspiral range, that we can't now account for. In our
nominal low-noise configuration, we used to reach 8Mpc, now we're at 7Mpc.
- WFS1
some times oscillates
6-7Hz and causes the IFO to unlock. WFS1 was ill-behaved and the gouy phase was suspected to be wrong, here,
and here.
- The
new MMT2
hold sequencer monitors sensor position information for the optic and
servos the pitch and yaw sliders to minimize alignment drift
- new
code expected LSC/ASC soon
- S4
calibration studies indicated some dewhite
channels were not like the others, leading to this dewhite
repair
2K IFO
- Early
in the week, a noise
curve (which includes a noise budget) showed progress at high frequencies,
with 1.8W landing on the modecleaner.
Later, a short lock was obtained with higher
power
into the mode cleaner (2-3W), plus TCS annulus heaing
(200mW in X and 400mW in Y). The displacement
noise at 2kHz, given the power we're at (3W into
the MC), suggests we will beat the SRD at high frequency when we go to
full power.
- New
ASC filters
reduced a peak at 25Hz in DARM_CTRL, which was coherent with pitch and yaw
signals in wavefront sensors
- A noisy
fast shutter on ISCT10 caused lockloss.
The excess shutter noise
was attributed to an errant BNC connection.
- The
new POY detector on ISCT10 was connected
up and phases were set.
The new REFL PD on ISCT7 was installed,
too.
- Bumpless filter code was installed, allowing for
the loading of coefficients for filters that are not on, without inducing
a transient in the filter module output
- Coil
driver transfer functions were made, then fit in matlab,
and compensation filters constructed
and loaded
- resonant gain filters added to the DARM loop reduce
exess noise at 30 and 35Hz.
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
No report
Initial LIGO Detector Science & Engineering
(Coyne)
from Dennis
Coyne
CDS
see also the CDS weekly meeting
minutes in the commissioning
archives
CDS Software
no report
CDS Hardware
Ben Abbott
Three PDs were shipped to Livingston,
and are now acting as the spares for the AS port.
DMT
no report
PSL
PeterKing
The high power photodetector testing
continues. No problems so far.
An attempt at circularising the output of an NPRO
was not particularly successful. Whilst a large amount of the astigmatism
was removed, the beam was still elliptic. Mechanical constraints did not
allow the cylindrical lenses to be positioned any closer. The rest of the
optical train is being set up.
ITM Replacement Preparation (ITM05)
Helena Armandula, Liyuan Zhang, Lee Cardenas
Absorption measurement for HR and AR
sides have been completed:
http://www.ligo.caltech.edu/~lzhang/4itm05/4itm05_hrabs_2.pdf
http://www.ligo.caltech.edu/~lzhang/4itm05/4itm05_arabs_2.pdf
Started etching the AR side of ITM05. At this time the
reflection on the AR coating went down from 2400 ppm
to ~1800 ppm after intervals of 5, 10 and 20 minutes
of "cooking". The surface is being scanned overnight to assess
uniformity.
TCS Quiet Chiller
Ken Mailand
I have checked with the Sporlan Valve engineer regarding
intermittent supply valve non-closure in the chiller circuit at LHO. Given our setup, everything seems to be well
within the normal of the valve operating specifications.,
and he has no answer for us. Sporlan only suggests we check the valve electrical
controller, and also check fluid for contaminate particles, on going.
40 Meter Interferometer (Weinstein)
Bob received an award for 35 years of service to Caltech. Congratulations,
Bob!
IFO commissioning:
- Rob
has been working on improving the dither signal for MICH. Previously, we
used DC signals from the DC test out tap of the LSC RFPD's,
but these produce nasty ground loops. Ben installed boards from Rich Abbot
wich tap the DC signals from the LSCPD interface
board backplanes. Rob reports that the dither signals are now much
cleaner. He was able to easily lock the dual-recycled michelson (DRMI) with the new dither signals,
then switch to the double-demod (DDM) RF signal.
- On
Friday, Rob had an epiphany, which he quickly verified using Finesse: the
MICH signal can be derived from REFL_Q (SP 33 MHz I) much more cleanly
than from the dither, even when demod phases are
not precisely tuned. He feels that we no longer need the dither signal.
One can lock the DRMI using SP 33Q (REFL_Q) for MICH, SP 33I (REFL_I) for the PRC, and
the POB DDM signal for SRM. Then all demod
phases can be tuned up well, and control can be switched to DDM for all
short degrees of freedom.
- Rob
finds that it is not completely necessary to tune up the demod phases every night; he has been able to easily aquire lock of the DRMI without re-tuning (except for
the SRC signal at POB, which does require retuning every night).
- Further,
once all the demod phases are tuned up, Rob
found that all 5 degrees of freedom can be brought into lock "at
once": leave both arms unblocked, all servos on (SRC with PO DD, PRC
with SP DD, and MICH with SP 33Q; XARM offset-locked with TRX, YARM offset
locked with TRY). Wait ~ 2-3 minutes, all 5 degrees of freedom aquire lock. Then switch MICH from SP 33Q to AP DD. Turn on LF
boosts for short DOFs. Then switch to DARM: =
(TRX-TRY)/(TRX+TRY) with zero offset, and CARM =
(1/sqrt(TRX) + 1/sqrtTRY) (offset, far from SP33I). At this point,
everything is locked, but the arms are not at full resonance. Then reduce
the CARM offset, watch REFLI rise. But, as arm resonance peak approaches,
CARM begins to oscillate and lock is lost.
- Rob
and Rana can repeat this sequence many times per
night, each time trying different CARM loop filter shapes,
to try to minimize the oscillation as CARM zero offset is approached. Each
night for the last few nights, they've gotten closer. The CARM OLTF UGF is
around 200 Hz.
- On
Wednesday night, they got close enough to zero CARM offset to see what
they think is the detuned RSE peak, moving from 5 kHz to the design value
of 4 kHz as they approached zero offset. This is the first evidence we've
seen for detuned RSE.
- Monica
is writing up he work on calibrating the LSC
signals.
- Virginio has written a document on Optical
Cavity Time Constant Measurement with Two in Series Optical Resonators
in order to be able to extract the ringdown time
of the arm cavities when the mode cleaner cavity is "in the
way". Using two different methods, he measures the YARM finesse to be
1344 and 1412 (spec is ~ 1200).
IFO modeling and DC detection development:
- Monica
has modified her e2e 40m simulation to take POX and POY signals from the
600 ppm AR coating of the ITMs.
- Monica
is learning about how to implement Rob's front-end LSC code into e2e as
"plug and play", including all the front-end digital filtering.
Electronics, controls:
- Rob
finds that the LSC front end cpu
can run close to the max of 61 microseconds in some configurations. He
will need to change the structure of the LSC code to make it run faster.
- Ben
has commissioned the new DC signals from the LSC RFPDs
that now come from the LSC PD interface board backplane. He is supplying
DC signals (for dither and other LSC uses) from the AP, POB, SP, POX, and
POY RFPDs. He did a survey of the whitened
signals that were hooked up to the LSC Whitening boards to find out which
connectors corresponded to which signals in DTT. He then looked at the
same signal that was being split through two front panel channels, one
coming from the RFPD DC SMA, and the other coming from the P2 Connector of
the LSC PD Interface. The P2 signal seemed to be quite a bit noisier than
the old signal. Later, he found out that these two channels of the
Whitening board have different filtering, and could account for the
difference seen. Tomorrow, he will do a test with both signals alternately
through the same channel.
- Rana installed Matt Evan's EZ / TDS Software so that
Dan can use it for the suspension diagonalization.
He plans to also update all the EZCA code.
- Rana downloaded IFO configure
scripts from Hanford,
and has set up a PSL FSS Autolocker script. He
plans to do the same for the PMC and the Mach-Zehnder.
He's working on other autolocking and autoalignment scripts.
- Steve
has grounded all optical tables to the vacuum envelope via 1 Mohm resistors; because there are
other path, he measures 0.3 Mohm to the
vacuum envelope. The PSL and SP tables, however, are dead shorts.
- In
order to further isolate the optical tables (to minimize the chance of
ground loops) Steve and Bob installed some beam tube insulators, and they
plan to replace the table enclosure walls with plastic ones, being made in
the shop.
- Steve
and Ben plan on disconnecting all the secondary grounds on the rack power
kill switches; they were a mistake!
- Dan
was at LHO all last week, diagonalizing
suspensions using Matt Evan's TDS tools. He plans to run coil balancing
and output matrix diagonalization code on the
40m suspensions, next.
- Bob
ordered some electronics supplies (solder, solder wick and the like).
Thermal Noise Interferometer (Black)
No report.
LASTI (Ottaway)
No report.
Data Analysis and Computing (Wallace for Lazzarini)
Simulation and Modeling (Bhawal)
E2E weekly Physics Meeting
Sany Yoshida presented more results on simulation
of a suspended locally-controlled mirror experiencing violin modes.
WFS1 for H1
(Biplab)
Interacted with Keita and Rana who are working on
H1 Wave Front Sensor(WFS). From the current
measurements (by Joe) of the parameters of the optical path leading to WFS1, it
seems the WFS1 is not at the optimum Gouy-phase
position. In the days of Luca Matone ...I remember
that it was set to the desired value of 90 deg to get maximum signal but
something might have changed in between. Plots are posted in elog (June 2). This could be the spoiling factor for the
recent problems observed especially in WFS1. Keita plans to correct it.
Out-Reach
(Biplab)
Assisted Sany Yoshida and his
students in their simulation of Input Optics system.
Code development
(Hiro)
Still working on updating the modeler code for the advanced
LIGO simulation, mainly to support multile time steps
transparently and to implement the fast simulation of a dual recycling cavity.
The design of C++ based FFT program using tools developed for e2e is also in
progress.
Alfi
(Bruce)
Completed new bundle content caching implementation. Includes cache updating due
to user inputs. Now working to enhance the speed of
these methods.
(Melody)
Currently working on the user interface for allowing the
user to choose the display for nodes: graphic, node name, or a multiline description. Worked on
allowing primitive nodes to be able to display an icon from a jpg or gif file.
Worked on saving the display information into the box files.
Continuing with modifying the parser to contain the node's descriptive
labels.
Data Analysis Activities (Wallace for Lazzarini)
Charlton:
- This
week I've mainly been analysing S4 data,
comparing strain calculated in the frequency domain (using the response
function) with Xavi's time-domain h(t) data. The time-domain h(t)
appears to be much better in S4 (compared to S3) but there are still
differences with the frequency-domain strain. The band-limited RMS for the
time-domn strain is about 3% smaller than that
for the frequency-domain strain.
- Made
some fixes to code for the generating stochastic pipeline cache and DAG
files.
Shawhan:
- Prepared
for LSC Meeting and Burst Group face-to-face meeting.
- Reviewed
pulsar analyses.
- Final
proofreading of S2 LIGO-only untriggered burst
search paper.
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS
- Completed
testing of the 1.6.0 release of LDAS at LHO by conducting a 4 day createRDS generation challenge. All tests passed
flawlessly. The CVS repository for LDAS has now been reopened for software
development towards the 1.7.0 release in support of "Astrowatch" testing in mid July.
- Due
to hardware failure on the LDAS-DEV system here at Caltech, we were unable
to conduct any system and integration testing of our development code
since last Friday. The hardware
failure has been resolved and the component in question is being
configured. We hope to be back up
for software testing this weekend.
- Added
"lsof" path to resource files for the lightWeightAPI, metaDataAPI,
and the eventMonitorAPI.
- Fixed
line wrapping and parsing of resource variable bug in the genericAPI that was impacting the display of data in
the controlMonitorAPI's GUI.
- Began
making code changes for Solaris 10 (currently LDAS support Solaris 9, but
the system administration group for LDAS would like to migrate to Solaris
10 soon).
TCLGLOBUS
- Fixed
XIO GSI test case. The problem is the conversion of the NULL pointer to a
string "NULL" instead of true pointer at the SWIG layer. We put
a conditional check to handle this case.
- Found
the problem why our previous asynchronous client/server test cases not
working. The problem is we release
the Tcl variable resources for read buffer too
soon before making
use of it for write buffer. Still making code changes to fix
this issue.
- Modified
several test cases to have an option for testing memory leaks by adding
extra resource variables.
- Modified
FTP client third party transfer test case to handle the case when the sever is not responding. The fix is to have a
timeout condition.
- Built
and compiled TclGlobus against Fedora Core 3
using both threaded and non-threaded versions.
- Extended
configure.ac file to detect differences between Globus Toolkit 3.2.x and Globus
4.0.0. Then built TclGlobus against the threaded
version of Globus Toolkit 4.0.0. This lead to
the correction of a conceptual error in the TclGlobus
dealing with the threaded versus non-threaded versions of the Globus build.
It also required modification to the completion detection for
several of the test programs so that they would function for both Globus 3.2.x and 4.0.0. Still need to conduct more testing
against Globus 4.0.0 before declaring the port
to this release a success, but its close now.
GRID/OSG
- Discussed
the possibility of developing a "virtual
machine" software installation environment for OSG know as the
"Edge Services Activity" at the OSG Council telecon
this week. This would be a very useful mechanism for LIGO to move LIGO
software onto an OSG Grid Cluster without having to go to the effort of
migrating important LIGO software into the VDT or OSG cache. This
mechanism is being evaluated by several of the high energy experiments as
well. Further discussion will be needed before this is turned into an
official OSG activity, but it looks very promising.
- Handed
off several key points to our collaborators (ISI) to be presented at the
OSG applications meeting this week. This will outline our successes with
Grid Computing for the binary inspiral search
coded on grids and our plans to migrate to Grid3/OSG with these
applications.
Hardware Systems (Ehrens for Anderson)
Nothing to report
General Computing (Wallace)
MIT:
(Keith)
- Configuring
new webserver
scsi
bus troubles seem to have cleared up
configuring print
spooler
configuring web
server
will not try to use
this box as test case for LDAP as it was taking too long to work out all the
details
- Adding
urops to gc
- Still
working on ldap (as time permits)
currently have a
hybrid system with both Sun native
ldap
and opensource ldap modules
required for sun
machines. linux
boxes simply use opensource ldap
libraries (that come
preinstalled).
- Moving
Dell GX260 desktop into Queue lab to replace old pc
Livingston:
(Shannon)
- Changed
out the failed hard drive on the ilog server
over the weekend. Had some problems
with the OS picking up the new drive and adding it to the RAID. The solution is to NOT use the Solaris
Management Console and only use the command line for restoring a mirrored
drive in RAID 0.
- Working
again with bell south to find our fiber problem. They shot the fibers with an OTDR on
Wednesday and claim everything is OK.
The router has stopped passing packets again a couple of times and
I am not sure if we have more than one problem right now. I have stopped seeing receive errors on
the connection which were present for the last couple of weeks and into
Monday, but it has gone down a couple of times. Rebooting the router this morning seemed
to bring the connection back up. It
is still somewhat of a mystery and I will have to do some more
troubleshooting. Made some
additional changes to the firewall last night also.
- LSU
notified me yesterday that they will have some planned downtime in the
next 30-60 days to do some router/switch upgrades. Depending on how they do this we may see
downtime on the order of minutes, or as much as an hour or two. They will notify us well in advance.
Hanford:
(Christine)
- Network
usage can be seen at
http://www.ligo-wa.caltech.edu/~christin/mrtg/198.129.208.1_198.129.78.122.html
- Setup
two more Sun Blade 1500s in the Computer Users room.
- Lots
of purchases for other projects and for GC.
- Contacted
PocketiNet for a quote on our backup network.
CIT:
(Mike)
- Loaner
Pool: Reloaded another laptop for the loaner pool, and turned this into Ed
Chargois for loaning purposes.
- Calum Torrie: Reloaded his
laptop due to many OS, and software issues. This was a Win2000 load that I reloaded
to XP, plus installed many engineering packages, and transferred users data over as well.
- Solid
Works/Pdmworks: Installing and updating our
Solid Works users to the current version of pdmworks
which is 2005 SP.3.1. This took up
a lot of time this week. First upgrading the pdmworks
server and then installing the new client on the users.
- Janeen Romie: I had problems
installing the pdmworks client on her laptop. This required a complete re-install of
Solid Works. I also had to clean up the registry and clean up many
directories that were associated with Solid Works.
- Spent
a lot of time on the mail servers due to the clamd
process not running. The mail server most definitely has a problem.
- The
usual maintenance on the spam filters.
- NTSRV's: Ran end of month ghost backups on pherkab, antares,
pc72, pictor, m91, and amaldi.
- DCC:
work on a database issue with the public search feature not working. After trouble shooting this issue it
turned out to be a drive mapping that somehow was disable.
- Much
other user support that included issues with email, printing, and
software.
(Veronica)
- Finished
AdvLIGO website updates.
- Updated
the roster database.
- Updated
the LSC June Meeting website.
I was out of office on sick leave most of the week.
(Larry)
- This
has been a busy week with purchases. Resolved a couple of issues with the Pcard group. Still have a number of items to
reconcile. Ordered a number of
computers and other items for different people on the project. Received the SUN, Dell and ASA orders.
Now getting the machines ready for distribution. Ordered and received a number of misc.
items. Most of the items have been distributed.
- Spent
time reviewing a couple of the vendors that the DCC has been looking at. Also, attended a couple of the demos of
the vendors.
- Spent
time working on special backups and finished up the regular monthly
backups of the user accounts. Still have the server backups to wrap up. Discovered another bad disk and presently
working on getting it replaced.
- Still
working a number of different issues going on with the air-conditioning
upgrade to the building. The fiber installation in the sub-basement is now
taking place. Still no word on augmenting the air in the computer room.
- Assisted
a number of users with different problems. Configuration issues mainly. Installed G77 on a server with SUSE as
the OS. The multiple CPU boxes are being used more. After this summer we
should be able to see if we need to purchase any more the GC area.
- E-mail
has been taking up a lot of time this past week and appears that it will
be the main project for the next week or two. The spam filter and
anti-virus programs are not working properly. They die at random times and
there are no error messages or other processes indicating any problems. Presently,
we are monitoring the processes and having them restart automatically.
This is just a temporary work around to give us time to get a solution to
the problem.
E-mail statistics May 26 -June 1, 05
Accepted
messages 13,929
Virus
messages 996
False
Positives 162
Rejected
messages 16,274
Total Messages 30,203
Advanced LIGO and Supporting R&D (Shoemaker)
Systems and Management
from Dennis
Coyne
Systems
See also:
AL
Systems web page
AL Systems email
archives
Records Of
Decision or Agreement (RODA)
See also the RODA
status web page
Requirements
Interface Issues
See the
"Interfaces" section of the AL Systems web
page
- Justin
Greenhalgh, Janeen Romie and Dennis Coyne have been collecting interface
requirements & data for the SUS review in June.
Vacuum Compatibility
Residual Gas Assay
(RGA)
See also the Vacuum Bake Lab
Bob Taylor
- I
have completed the bake out of the Emitter and Photo diodes that have been
vacuum relief drilled.
- I am
repairing the SRS RGA for oven C and will be leak testing and scanning
that oven by the beginning of next week.
- I am
writing a rough draft of the Qualification Procedure for the new Air Bake
Oven that should arrive some time in the next two weeks.
- The
construction of the removable wall in the bake lab is done and the lab is
ready to receive the new oven when it arrives.
High-Irradiance,
Contamination-Exposure Cavities
Lee Cardenas, Liyuan Zhang
|
Cavity
(Location)
|
Material/Item
|
Start
|
End
|
Comments
|
|
Cavity #1
(OTF
Lab, Bridge)
|
new set of 70ppm REO mirrors
|
NA
|
NA
|
174 mW
laser power, compares well with 180mW with previous
ATF mirrors. Cavity is ready for samples
|
|
Cavity #2
(OTF Lab, Lauritsen)
|
NA
|
NA
|
NA
|
cavity is close to being ready
for samples; completion on hold for other priority work
|
|
Cavity #3
(OTF Lab, Lauritsen)
|
Glenair Micro-D connectors (qty=20)
|
3/2
|
~6/3
|
Cavity is locked and we are
taking measurements for absorption and ring down every day.
test will be completed this week
|
|
Queue
|
OSEM
emitter & photodiode
|
~6/6
|
~9/6
|
In vacuum testing currently
|
|
Queue
|
Stepper
Motor
|
TBD
|
TBD
|
RGA outgassing
vs temperature taken, ready for cavity
|
Large Item
Cleaning Plan/Facility
Ken Mailand
- Finished
a cost outline for Adv. LIGO parts cleaning, in house vs. vendor.
- Large
bake oven to be placed in the 40m Lab is on schedule for delivery next
week.
- Mike
Gerfen is adding some hole and tap features to
the two test plates to make them identical as possible for the FTIR test
to qualify the large air bake oven for the 40m lab annex.
Meetings & Reviews
- Future
near term planned meetings & reviews:
|
Date
|
Subsystem
|
Review or Meeting Title
|
|
6/?
|
SUS
|
Requirements & Interface Update
(enable SUS/UK
final design efforts in parallel with SUS/US completion of the quad controls
prototype and preliminary design)
|
|
end of
June?
|
ISC
|
40m DC readout experiment plan
review
|
|
7/11
|
SYS
|
Systems Issues Summit Meeting
PASTE PF's agenda here
|
|
?
|
AOS
|
AOS: Scattered Light Control
Design Requirements Review (DRR)
|
|
?
|
COC
|
?
|
AdL CDS
The prototype AD7679 ADC to FPDP board is operational. The FPDP interface
appears capable of handling the full 570Ksps for the ADC. Noise measurements are in progress, but there
appears to be a "hidden feature" in the BUSY bit used by the ADC that
is interfering with the acquisition. Jay has a call in to Analog Devices.
Seismic Isolation
From: Ken Mason kmason@ligo.mit.edu
No report this week
From: "Joseph A.
Giaime" jgiaime@ligo.phys.lsu.edu
For three days during the week of July 11 - 15, Peter Fritschel
is planning a meeting at Caltech to discuss updates to the Adv LIGO design.
The topic most relevant to this group is: Reassessment of HAM seismic isolation
requirements: the HAM platform vibration requirements were set to be the same
as for the BSC, for simplicity/commonality, but it seems likely that the HAM
platform does not need to be as quiet as the BSC in some bands; what do we
really need, and what are the implications for the SEI design?
Follow up actions from Review:
Let's proceed as though the plan will be followed. Here are the tasks
that need immediate attention in order not to slip our schedule:
- Performance
modeling of 2-stage system (BTL), leading to choice of stage 0-1 spring
stiffness and approximate blade geometry.
- definition of ASI job, followed by interaction with Ed Jasnow to produce amendment/change order to contract.
(KM & JG)
- Produce
overall LASTI BSC SEI mechanical procurement plan (produced by KM &
OS, reviewed by DC, sent to Jasnow for bid spec
preparation.)
Jay will soon get 8 boards for GS-13 refit.
LLO HEPI work:
- Work
on HAMs continues: IIR high-pass and blended
loops performance looks OK in y direction. X direction blending does
not help except frequencies above a few hertz, and not much.
- Brian
O'Reilly and Rich Mittleman will put their heads
together to decide where exactly the twist-coupling cross term will connnect in the HAM HEPI
diagram. Then Brian will discuss the needed code changes with
Rolf.
LASTI investigation of the 10+ Hz HEPI noise shoulder
- Rich
thinks that the 10 Hz feature is something like a flagpole mode of the BSC
vacuum tank. He is not yet sure how the coupling occurs (probably
through the floor). The floor near the piers is instrumented and he
is working the problem.
- Dennis
has some references on how to model flexing of concrete floor patches, and
will provide these to Ken Mason.
Adv LIGO SEI electronics
- Jay
needs to get with Ken to verify that the wiring harness fits up through
the platform design.
- Single
ADE fine displacement sensor still exhibits the 24 Hz peak; Jay has
discussed this with ADE, and has returned the four sensors in the first
fine set of four to them for service.
From: Jay Heefner <jay@ligo.caltech.edu> .
AdL SEI
- Four
of the capacitive positon sensors have been
returned to ADE. Jay will call them later in the week
to find out if they have any data on the source of the 24Hz noise
bump.
- Meanwhile,
4 more sensors and amplifiers are being assembled in the test rig.
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
Advanced LIGO Suspensions
Working on the Universal SUS DRD. Placing POs for some of the final suspension parts. Following up with the two campus machine shops for parts.
From: ctorrie <ctorrie@ligo.caltech.edu>
No report this week
From: Ken mailand kmailand@ligo.caltech.edu
Finished a cost outline for Adv. LIGO parts cleaning, in
house vs. vendor. Large bake oven
to be placed in the 40m Lab is on schedule for delivery next week. Mike Gerfen is
adding some hole and tap features to the two test plates to make them identical
as possible for the FTIR test.
Core Optics
No report
Advanced LIGO SUS
The installation of the new Class 100 cleanroom in
the Synchrotron lab will start next Wednesday and is expected to be finished
and certified by Friday.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
AdvLIGO PSL
A problem was noticed with the 500 mA photodetector in that the observed responsivity
of the diode is somewhat less than the expected 0.75 A/W. Cleaning the
protective window did help a little but I think that scatter from the window
might be part of the problem.
In the lasers working group monthly telecom LZH reported that further tests
were conducted on the high power laser. The ring laser configuration was
restored and injection locked, ie the AdvLIGO configuration. A good beam profile was
measured before 2 fibres were burned. The fibre bundle was inspected; the remaining 8 fibres were okay. Problems with mechanical stress on
the fibre connector caused one fibre
to be damaged. In the case of the other fibre,
back reflections from the high power laser caused the epoxy holding the Teflon
holder to heat up. Both fibres were
successfully re-cleaved and put back into service.
In addition progress was made on a rod amplifier design that might be part of
an Initial LIGO laser upgrade. 34 W of power was achieved in a single-pass
configuration with 3 NdYV04 rods pumped with three 30-W diodes.
At the AEI experiments continue on the power stabilization. Improvements were made to the DC voltage
reference used in the experiment.
A pre-modecleaner cavity was used in the high
finesse mode for both the in and out-of-loop photodetectors.
The setup is housed to provide some acoustic shielding, with the option of
going into vacuum if need be.
Auxiliary Optics
From: Michael Smith smith@ligo.caltech.edu
No report this week
Other Laboratory R&D
Juri
I wrote a Mathematica notebook to implement the
calculations for coating thermoelastic noise in the
finite mirror case using two different approaches for the calculation of the dissipated
energy which is used in the Levin approach to thermal noise calculations. Now
I’m checking the compatibility of these two methods and the limit of
infinite test mass using Gaussian beam; after I will calculate the noise
reduction using Flat top beam.
Chiara
I took some preliminary measurements of the resonant frequencies of the
horizontal attenuation system mounted in the Synchrotron, changing the loads
from 600 Kg to 1460 Kg. I made a fit of the data which shows an expected zero
frequency around 1600 Kg. Now I’m
adding load little by little in order to have enough data in the low frequency
region near zero. Moreover I’m taking classes in the Machine Shop to
learn how to use many instruments for the productions of mechanical parts.
Marco (01Jun)
We are still working on gaussian beam data: tried
different models to fit tri-dimensional profiles but no relevant results. Phil
ordered another folder mirror to avoid ghost beam overlap with the main
profile.
I’m studying a different approach to the beam analysis through image
filtering and smoothing techniques: work in progress.
For additional information about this report, contact Stan Whitcomb or Phil Lindquist