Weekly Report for
Week Ending May 26, 2005
The LIGO Executive Committee meeting for May 30, 2005 is
cancelled due to the holiday.
Special Announcements:
Weekly
Report Highlights
LSC Issues (Saulson)
No report.
LIGO Laboratory Administration (Lindquist)
STATUS OF LSC MOUs (Petrac)
LSC MOUs and Research Plans and Progress Reports
- MOU Attachment
updates were signed-off for: Balearic Islands University,
Moscow State
University, NAOJ-TAMA, Northwestern University,
University of Oregon, Southern University, Southeastern Louisiana University, Texas University at Brownsville,
Vassar College,
and Washington
State University. The documents are in DCC awaiting
archiving and web posting. [Note,
the DCC is jammed up with preparations for the LSC meeting and the
activities related to evaluating potential new document management
applications. We are discussing
with General Computing priorities and ways to break the log jam. –pel]
SITE TELECONFERENCE (Lindquist)
A brief site teleconference was conducted on Thursday, March 26, 2005. The
following items were among those discussed:
- Action
124: Review Procedure Manual materials and provide comments. The
decision tree for paying taxes has been provided.
- Livingston SEC Invitation for Bid: It was reported that Ed Jasnow has a lot of actions assigned. We are trying to reconcile
Caltech’s General Provisions with those suggested by the Archetect/Engineer.
There is more home work to be completed before the bid package is
ready. The architect is on
schedule. Target is second week in
June for sending out request for bids.
- TechMart Training: Caltech is exploring the possibility of
using Web-X to train staff at the sites.
It was noted that if sufficient time is not dedicated ahead of the
training session to set up and test, most of the training time will be spent
messing with Web-X. A “dress
rehearsal” is required. Also
Web-X apparently does not work well on Macs.
- Operations
Adjustments for S5: It was noted that there will be budget
needs to cover the costs of travel for Science Monitors during S5. P Lindquist will issue first iterations
of the budget models for FY 2006 – FY 2008 so that task managers can
begin looking at the areas that will need attention.
- The
list of assigned actions updated through March 26, 2005 will be found Here.
PROPERTY MANAGEMENT (Chargois)
>From: Ed Chargois <chargois_e@ligo.caltech.edu>
- Nothing
significant to report.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- packages:
in - 17, out - 9
- faxes:
in - 33, out - 13
- No
special projects to report.
COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman, Salone)
>From: Esther Cunningham <esther@ligo.caltech.edu>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Followed
up on the quotes obtained for Oddvar.
- Mailed
out the Release of Claims to close out the subcontract with Kratochwill under Change order #3.
- Obtained
invoices and copies of credit memos for billed pcard
transactions. Reconciled the charges billed to date. Followed up on the
pending credit for the return of the laser. Followed up on the status of
older pcard transactions that are still open.
- Requested
for an account to be set up for Caltech with LNL Anodizing for new
requests that are anticipated by LIGO through Central Engineering
Services. The account has been set up.
- Completed
change order #21 to REO and submitted it to the vendor.
- Working
on completing the change order to Amerion to
change the date of performance.
- Completed
the purchase order. close out report for May 2005.
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Florence Kaufman <fkaufman>
SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)
>From: irena@ligo.caltech.edu (Irena Petrac)
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
- Processed
the paper work for five (5) new/revised trips. At this time there is (1) new trip that
needs to be completed and ticketed before the paper work can be
completed. Assisted several LIGO
people with their travel arrangements using their P-Cards and made several
reservations for outside visitors coming to a LIGO site for meetings
and/or workshops. LIGO will be
sponsoring thirty-eight (38) SURF Students this summer and all but three
(3) have been completed. We have
twenty-six (26) coming to LIGO/Caltech, seven (7) to LIGO/Hanford, and
five (5) to LIGO/Livingston.
- Completed
twenty (20) Expense Reports and there are four (4) reports yet to be
done. I continue to contact
travelers who have outstanding Expense Reports (more than one (1) month
old) to ask for their cooperation in sending me their receipts so that these
can be closed in a timely manner.
Presently there are two (2) reports more than 30 days old. I have no reports awaiting signature at
this time. Reconciled forty-four
(44) P-Card charges for the week requiring telephoning hotels and car
rental agencies to verify which traveler used my card and for what amount.
- Coordinated
and initiated the opening of thirty-seven (37) new cards with the selected
new teleconference company, AccuConference. New card holders have been sent their
new information their wallet-size cards. Each card holder has the
capability of entering their account in order to observe/manage it. The old RainDance
account will be closed as of May 31, 2005 and each holder of a RainDance card has been asked to return their
wallet-size card to me and destroy any information containing their
account number on the old card that they may have printed out. Continued to track Raindance
Teleconference billing and assisted users with any problems that they
might have incurred.
- Booking
travel, updating web pages, processing payments.
>Dorothy Lloyd
- Nothing
significant to report.
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
PROPOSALS and REPORTS (Lindquist)
LIGO must submit an Annual Report for Operations by August 1, 2005 and this
annual report must be accompanied by a request for a two year extension (FY
2007 and FY 2008) as well as a justification for why Caltech/MIT should be
continued in the role of management of LIGO.
I have prepared and distributed a general outline and assignments. I have requested contributions by Friday,
June 17, 2005. The outline and schedule
were presented during the Executive Committee meting on Monday, May 23, 2005.
DCC Steering Committee (Lindquist)
We have conducted teleconferences with references provided by Synergy and
AGILE document management systems. We
have scheduled an additional reference teleconference tomorrow morning for the
SYNERGY system.
We were given a walk through of the Xythos
document management system this afternoon via WebX
session. We have scheduled a
demonstration by Xythos here at Caltech next
Wednesday morning. Xythos
comes to us a little late in the process but is of interest because their
application is tailored for the educational and research environment.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
Minutes for the change control meetings held on May 9, 2005 and May 23, 2005
(during the normally scheduled meetings of the Executive Committee) have been
prepared and submitted to the document control center (LIGO-M050200-00-P).
- CR-050004 Operations 2005 Second Quarter
Adjustments: The request
reflects adjustments for positions that were budgeted but not filled
during the first half of FY 2005 plus corrections, increases to reflect
the large number of SURF students accepted this summer, and $100K of
budget for a carry-forward commitment to the University of Florida, which
will not be used. In addition there
were a few planning changes incorporated to reflect reduced NSF funding
for FY 2005. On May 9, 2005 the Executive Committee recommended approval
of the change request and the change request has been approved. The original signed copy of the change
request is in the document control center.
- CR-050005 Data Monitor Tool (DMT) Hardware
Expansion Hardware Expansion:
The request is for funding to cover the cost of expanding the Data
Monitor Tool (DMT) hardware infrastructure. The estimated costs after some iteration
were estimated to be $70,000--split 60/40 between the Hanford and Livingston Observatories
respectively. The expansion
provides additional computing nodes for online monitors, an upgrade of the
development and testing machines, and an upgrade to the network providing
better security. This change
request has been approved. The
signed original of the change request is filed in the document control
center.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
The minutes and action items from the May SC meeting have
been posted. All files are posted and
up-to-date on the web page.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
Nothing significant to report this week.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of Commissioning Activities at LIGO Hanford Observatory
(Landry)
Commissioning continued apace
at Hanford this
week, with many visitors helping out on a variety of tasks. Some are
highlighted below.
- Coil
gains had migrated to weird values with each new hardware installation and
modification; gains are now common between H1 and H2 after a re-allocation
- H1 TCS
temperature spiked, owing to a (site) chiller shut
down
- Noise
budget software has been propagated to LHO. The script runs DTT
measurements and a matlab model to produce a
calibrated IFO noise, and apply the constituent noise curves to the same
plot. A work in progress, currently some curves are suspect, such as
the ISS noise.
4K IFO
- MMT2
suspensions acted crazy,
with sensors indicating large input pointing shifts, both glitches and
longer-term drifts. Initial
forensics showed no coil voltage problems. Later, the satellite
module was swapped
out, then the coil
driver, and last, the dewhitening and anti-imaging, without effect.
Could the mass be hung up somehow?
- The
AS2 demod phase was found to be way off, and the
AS2I spectrum was noisy, so that AS2 electronics were thought to be a
problem. Further checkout
found AS2 with excess low frequency noise; this went away once cables were
jiggled and reconnected
- TCS
had an 8h lock with continuous 4W TCS operation, with differential
annulus TCS control. The TCS team received beautiful new
"sunflower" annuli to test out.
- Scripts
and more scripts: WFS were diagonalized and the bandwidth of the loops
increased to 3
and 4Hz
- The 4k
failed
the pinky test, in which an end station pier is nudged to assess
backscatter into the IFO by transmission monitor components. The
result was new transmission
monitor lenses were installed.
- Electronic
sidebands are seen, much the same as at LLO, on H1 AS PDs. This may arise from interaction with the
61MHz oscillator, demod boards, and pickup by
ASI servo boxes.
2K IFO
- Coil
gains were adjusted to minimized
position to pitch and yaw coupling
- The
NPRO was mode-hopping
again. Later, the laser replaced
and quickly warmed to an output in excess of 7W. Next, the laser
power supply no longer talked to chiller; the power supply was damaged
during the restart and thus not responding to chiller via RS232.
Some links follow: on the power supply failure,
potential communication
problems, and the fact that the 2k was still
noisy after the laser fix.
- POY
and Non-resonant sideband REFL diodes were installed
- 2k
ASPD noise
had factor of 30 increase; probably something going wrong in the AS
whitening
CDS
- Linemon, a tool that allows for the demodulating
of lines and sending output to Epics channels (handy for trending) was
installed on the h0pemms IOC
- TDS
tools , a series of time-domain tools, are now available under CDS
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
L1 Interferometer (Frolov)
The upgrade of the end station heater controllers to match the LHO scheme
resulted in removal of the 1 Hz sidebands of the 60 Hz power line from the
interferometer noise spectrum. Now the 60 Hz power line itself is the largest
remaining feature in the spectrum.
Two anti-symmetric port photo-detectors that were in the low noise mode
developed large leakage currents between last Thursday and Friday. Upon
examination burn marks from the beam were found on the surface of the
photo-diodes. The safety shutter operation was verified - no malfunction was
found so far. The mechanism of the damage is still under investigation. The
interferometer returned into operation after switching to two undamaged photodetectors. The threshold of the safety shutter was
reduced by a factor of five.
The low frequency broadband noise below 100 Hz improved after the switch to
the new diodes. It isn't understood but backscattering from the damaged spots
or spatial beam nonuniformities coupling to motion
across the damage sites could be responsible.
The 5 V power distribution to the front end analog
electronics was upgraded to include field regulators at each crate. This should
improve reliability of the WFS system and reduce interactions between boards.
Reflected beam angular drift has been observed at high input power into the
interferometer and is attributed to the Faraday isolator thermal lensing. The beam
has to be steered on the WFS photo-detector but stays within the diode size on
the LSC detector. A new system to stabilize this drift is being designed.
A temperature scan of the main laser was done to maximize the power output.
We now have 6 W available into the Mode Cleaner.
Education and Outreach (Thacker)
Assisted with LIGO Education Program Advisory Committee (LEPAC) meeting,
Friday, 5/20 conducted Local Educators Network (LEN) workshop on Saturday, 5/21
met with locat teacher PD provider on Monday, 5/23
assisted in Tour for visitor (astronomer) from Williams College on Tuesday,
5/24
Site Safety and Security (Riesen)
I have found no site nor laser safety concerns this
reporting period. Completed
a full function checkout of the enhanced laser safety system at both end
stations. This concerns the
transmission monitors, photon calibrators, and the laser safety signage. Both end stations are fully operational. In-line transmission monitor shutters still
need to be installed at both ends.
Mechanical Engineering (Spjeld)
AdL Quad SUS Installation Fixtures
- Redesigning
vertical drive - lift arm interface
- Replacing
follower shafts with self-aligning linear bearings
- Manufacturing
drawings of completed parts in progress
- Addressing
design issues raised in design review committee report
AdL SEI Engineering
- Review
of Ad SEI drawings in progress
- SEI
Critical Review Meeting
LIGO Outreach Building
- Pendulum Exhibit
- Redesigned
support truss for pendulums
General Engineering
- HAM
door removal tool drawing sent out to quote
- Working
with John Thacker on poster updates
LLO General Computing and LIGO Computing Security (Roddy)
A drive failed on the Ilog server. Fortunately, it is a mirrored array and no
data was lost. I am having some problems
with the vendor in getting a replacement drive, but I am expecting it
tomorrow. It should have been here on
Tuesday. As long as the other half of
the mirror holds out, the ilog will stay up. Replaced the CDS NAT router and combined it
into the main GC router. Working on the
associated firewall rules, etc. that are needed due to
this. The new router seems to be working
really well now that the syskonnect bugs and the bad MiniGBIC have been taken care of. Working with Dave on some CDS security issues
and working on these reconfigurations.
Also working on some new configuration with the RGA machines, etc. as
discussed in the OCSC meetings. Added
scratch space to decatur and touro. There is several hundred gigs of space available now for
data. Revisiting snort
and IDS installation/configurations. I will have to work with Dave and
get this duplicated at Hanford. visibility into the
network traffic into CDS is a major concern due to time constraints on other
issues.
HPLF, Optics Modeling, Data Analysis and L1 Commissioning (Franzen)
1) HPLF
news: The 100 W IPG laser has been repaired
and returned to LLO.
An engineer is now visiting us in order to advice us
on the operation and to install some diagnostics software for us.
2) Designing
a REFL port beam stabilization system.
CDS software (Khan)
Worked with Rolf and alex
on the code and Frame builder upgrade. This new upgrade involves changing the
floating point point variable from single precision
to double precision format and also the size of the daq
channel name length is increased from 40 to 255 characters.
Developed a new stat screen for the TCS servo.
LDAS/Condor Sysadmin and Burst Analysis (Yakushin)
Data archival/Condor/LDAS:
Generated new set of possible layouts for
the LDAS room to consider.
1) The
minimal upgrade that would only be good for S5:
http://www.ligo-la.caltech.edu/~igor/POWER_HVAC_LAYOUT/v1/
LDAS_210_layout.1.pdf
2) Slightly
better version. Communication and LDAS rooms are joined, AC is rotated 90
degrees:
http://www.ligo-la.caltech.edu/~igor/POWER_HVAC_LAYOUT/v2/
LDAS_500_layout.2.pdf
3) The
ideal solution that also involves rearranging the racks 90 degrees:
http://www.ligo-la.caltech.edu/~igor/POWER_HVAC_LAYOUT/v3/
LDAS_500_layout.3.pdf
4) The
modification of the ideal solution (it is probably cheaper but at the expense
of wasted space) that would allow to reuse 30 tons AC needed for 210 nodes
later after S5 when we upgrade to 500 nodes:
http://www.ligo-la.caltech.edu/~igor/POWER_HVAC_LAYOUT/v4/
LDAS_500_layout.4.pdf
Sent final
numbers for power and AC requirements to Mike, Rusyl
and Allen.
Data analysis:
1) Comparing
waveburst S4 triggers (version 1) on DARM_ERR, AS_Q
and h(t) to decide which ones to use in the final
analysis.
2) Participating
in the waveburst code review. We had a f2f meeting at LLO last week, one telecon
this week and another one coming today.
3) Processed
SG15 burst MDC frames and discovered a problem: signal injections in SG15 were
often done too close to each other. Keith Thorne has regenerated the frames and
I am about to launch waveburst jobs on them.
4) Regenerating
S4 triggers using V2 calibration and some minor fix to the waveburst
code (during the waveburst f2f code review meeting we
discovered some unexpected feature that is corrected now) that could affect
reconstruction of low frequency long duration bursts, for example SG100Q100.
5) Preparing
my Amaldi talk for LSC review.
Initial LIGO Detector Science & Engineering
(Coyne)
from Dennis
Coyne
CDS
see also the CDS weekly meeting
minutes in the commissioning
archives
CDS Software
Rolf Bork
- There
was a bug noted by Peter and Daniel that the "bumpless"
filter coeff reload feature was not working
properly. Alex and I did some off-line testing and found a bug which would
allow the feature to work some, but not all, of the time. This has been
fixed and will be loaded at LHO today for on site testing. If the fix
works, then the remaining front end code will need to be recompiled and
installed.
- Alex
recently ported the fast ADCU software to our faster Linux VME processor.
However, this CPU is still not fast enough to do all of the data
calculations for the number of channels required by Daniel. One option we
are going to try is to run the fast ADCU calculations on a faster Linux processor
(non-VME). If this works, we could look at moving the ADC data to this
processor via the Front Panel Data Port (FPDP) on the ADC module to a
FPDP-PCI card in the PC (160MByte/sec link). We could also look at running
a fiber optic serial FPFP link, such that the PC could reside in the MSR
instead of near the ADCU VME crate.
- We
are currently testing a Sun V40Z computer for possible use as a Framebuilder. LDAS has suggested it would be good if
the Framebuilders could write compressed data
into frames to allow greater data storage and that this machine may have
the computational power to do it. So, we have a loaner unit from LDAS and
are trying to port the Framebuilder code, along
with the drivers for the various reflected memory network drivers. This is
not a straight port, as this is a multiple AMD64 bit processor unit
running some version of Solaris X86 instead of the usual Sun CPU Solaris.
CDS Hardware
Rich Abbott (at LLO)
Replaced ASPD 1, 2, and 3 due to damage
Replaced ASPD 4 demodulator board due to line spikes
Repaired ASPD 2 diode by replacing the diode element and
re-testing
Ben Abbott
I got a call that Livingston
had failures of photodiodes on Monday, and they needed three
replacements. I had a group of PDs here that
were assembled, but needed updating to the latest rev D. Todd and I
updated three of the PDs to the newest rev, and then
I ran them through their test procedures. Once the PDs
were all tested and final assembly of the enclosures had occurred, I shipped
them off yesterday with their associated paperwork. They should be
arriving this morning.
DMT
no report
PSL
PeterKing
The high power photodetector
testing continues. No problems so far. Another higher power (greater than 500 mW) NPRO laser was fired up to test another photodetector since the 10-W laser was no longer available.
The output beam of the NPRO was
characterized and circularized.
Vacuum Bake
Bob Taylor
- Completed
a vacuum bake Job for Betsy Bland ( LHO) for the ITMy
possible replacement:
- 25
Quartz Wire Standoffs. Shipped the Items Back to LHO.
4ITM05 Absorption Measurement
Liyuan Zhang, Lee Cardenas
(report edited & augmented
by D. Coyne)
A bulk absoprtion measurement was performed on the
4ITM05 optic (the optic which may be used to replace ITMx
on the LHO 4km interferometer). The scan was made at at
the middle layer (Z=-2" from AR) and is quite uniform at ~3ppm/cm: see scan.
After the measurement, we found two
small laser burns on the AR coating most likely due to dust on the mirror
surface. Therefore, we have decided to make coating absorption measurements on
some 1.0" diameter small mirrors first, as a test before we proceed with
the HR coating on the 4ITM05 mirror.
We have tested two 1.0" dia. mirrors,
intentionally made "dirty" to see if it will cause laser burns. One
mirror was left exposed for about 1 day in the lab and accumulated
"natural dust". The second mirror was 'littered' with particles from
clean room cloth (tissue?) and optics cleaning tissues. The mirror with
"natural dust" showed no sign of damage after the scan. The mirror
with optics tissue particles showed damage. Under the microscope we can clearly
see the pit left by the laser burn on the surface. Attempts to clean off the
burn mark were not successful.
We next plan to scan the 4ITM05 HR coating for absorption but only on the
perimeter outside of the 1/e radius of the beam and perhaps at lower power(?). We will make scans over ~1 sq. in at several locations
along the outer perimeter, but still within the region where the coating should
be uniform and similar to the central region.
40 Meter Interferometer (Weinstein)
IFO commissioning:
- Osamu
re-installed the MC length monitor (Freq_Diff);
(the IQdemod board that was being used was fried
a few weeks ago; Ben fixed it, and Osamu just now re-installed it). He
calibrated the signal: 0.76 count/ 100 Hz @ 33.2 MHz (ie,
if the monitor reads 0.76 counts, the 33 MHz RF sidebands are 100 Hz away
from being fully resonant in the MC). The reading varies from day to
night. When it's significantly off, we need to re-tune all the demod phases; so it's important to monitor (and
eventually, feed back on) this signal.
- Osamu
and Rob have been working nights, on lock acquisition. Typically, they
spend an hour or 2 to tune up the mirror alignment and the demod phases. The change of the demod
phases over a day is 5-10deg for AP 133 MHz and 199 MHz; 10-20deg for SP
133 MHz and 199 MHz. This is too much! It requires daily retuning of demod phases. It may or may not be entirely due to the
drifting of the mode cleaner resonant sideband frequency.
- After
tuning up, the dual-recycled Michelson (DRMI, arms blocked) typically
locks in ~ 10 seconds. They then unblock one arm,
and offset-lock it via DC transmission. They unblock the other and lock it
the same way. It takes a few minutes to get both arms offset-locked; often
they have to nudge ITMY to get it to cross a fringe. They can then switch
to CARM and DARM control using combinations of the DC transmitted light
(TRX and TRY). They then reduce the DARM offset to zero (no carrier at the
AS port). In this way, they can lock all 5 degrees of freedom 20-30 times
per night.
- However,
when they try to reduce the CARM offset to bring both arms into full
resonance, they find that the CARM servo starts to oscillate and lock is
lost. Rob did some modelling with FINESSE, and
has an explanation: When CARM is offset-locked,
it is detuned for the carrier. The coupled-cavity (PRM-CARM) pole,
normally ~ 100 Hz, is much higher (~1.6 kHz). As they reduce the offset,
the coupled-cavity pole lowers, until it passes through the CARM servo UGF
of ~ 300 Hz. The ensuing phase delay at the UGF causes CARM to oscillate
and lock to be lost. This scenario would not happen in AdLIGO
(where the detuned coupled-cavity pole is still below the CARM UGF). It's
a real impediment to smoothly transitioning from offset-locked arms to the
final configuration. We need to think hard for a solution. One possibility
being pursued by Rob is to compensate for the instability by changing the
loop shape.
- Monica
is writing up the results of her measurements for calibrating the ITM and
ETM response.
- Monica
and Virginio have a model for the decay time of
the light through the mode cleaner and arm cavity. They are plugging in
the numbers to get a measure of the arm finesse (the mode cleaner finesse
is known) and writing up the measurement.
IFO modeling and DC detection development:
- Monica
continues to study error signal sweeps in her e2e simulation of the 40m
optical plant. She is now working on the control plant for her e2e
simulation of the 40m. Ideally, the lock acquisition and control code
developed by Rolf and Rob for the front end controls can be "plugged
in" to the e2e simulation directly. She will work with Rob to see if
this can be made to work.
- A
draft version of a document, Proposal
for a Homodyne (DC) Detection Experiment at the LIGO Caltech 40-Meter
Laboratory is available for comment. We hope to have a design review
for this experiment when Mike Smith returns from vacation in mid-June.
Electronics, controls:
- DC
signals from our RFPDs currently get into our
front end electronics via separate cables from the DC-test-out port of the
RFPD head. They should, instead, come from the LSC RFPD interface board.
Ben got some PD interface Data Acq Boards
(D010005-00) from Rich Abbott which tap the
signals out from the LSC RFPD interface board P2 connector, and is wiring
them into our LSC whitening boards to get them into the front end. DC
signals will be available from ONE each of SP, AP, PO,
POX, POY. In progress.
- Rob
tried to establish a good CARM signal using the new 166 MHz RFPD at the
SP. He found large electronic cross-couplings from other PDs in the rack. We've seen this before,
they all talk to each other via unregulated power lines on the IQ demod boards. The fix is to power the demod circuit with regulated power. This ha been done
for several of the existing demod boards. Ben
will fix this new one.
- Rob
rebalanced the coil gains on the 3 new RevB coil
drivers (for SRM, PRM, BS).
- Steve
noticed that the OSEM coil voltages for the BS are drifting steadily over
many days. Under investigation.
- Osamu
noticed that the SRM seems poorly damped when the oplev
servo is switched off. There is evidence that the SRM, BS, and ITMX all
damp poorly for one reason or another. We need to diagonalize
the suspension controllers, systematically and correctly!
- Dan
is at LHO, diagonalizing all the digital suspension
controllers. Now that he knows how, we will ask him to do the same for our
10 DSCs, when he gets back. (Hopefully,
including coil balancing, input matrix, output matrix.)
Lab Infrastructure:
- The
air conditioning thermostat setting in the IFO hall was mistakenly changed
on Thursday, causing a several-degree change in the temperature. This
wreaked havoc on the PSL and mode cleaner. Steve re-set all the
thermostats in the hall to 70 C. The temperature was set back up on
Friday, and by Monday, Osamu was able to re-align and recover everything.
- Steve
finished grounding the ISC tables to the vacuum envelope via 1.2 MOhm resistors.
- Steve
has placed delrin electrical isolation between
the optical table and various components (thorlabs
520 PDs, ccd
cameras, optical spectrum analyzers, mechanical shutters).
- Steve
has labelled all the AC power sockets,
indicating whether it is conditioned rack power or unconditioned wall plug
power.
- We
plan to un-ground all the rack kill switches in the next week.
- Ben continues
to develop a document of the grounding and shielding for the 40m
electronics, racks, tables, chambers.
- Bob
finished checking and correcting the grounding problems in the cross
connects in the LSC & ASC racks 1Y2 & 1Y3 on Friday of last week.
Thermal Noise Interferometer (Black)
This week, Akira pumped out the bond-noise
chamber, locked the shadow sensor, and took noise data. While the system is
substantially quieter than it had been in air, our first in-vacuo
noise spectrum does not appear to be thermal noise
limited. The vacuum, however, holds nicely even with the pump off, and there
appear to be neither leaks nor substantial outgassing.
Helena checked with Jean-Marie on our optics with advanced
coatings, and he is on track for a mid-June delivery.
LASTI (Ottaway)
No report.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
E2E Weekly Physics Meeting
Sany
Yoshida presented results of e2e simulation for a locally damped suspended
Mirror that is experiencing violin modes. Violin modes were recently
implemented in e2e models by Sany using Virginio's mechanical model.
WaveFront Sensor (WFS) signals for H2
(Biplab)
After LLO, now we want to check if WFSs are well
optimized for thermal states in Hanford 2 Km interferometer too. Joe and Rana gave all parameters (elog
24th Tue) for the optical paths of WFSs. With
calculations done so far, not much of qualitative differences from 4km
interferometers have been observed. Most of the quantitative differences come
from recycling factors etc.
SimLIGO studies for mirror shifts
(Biplab)
Studied what happens if one of the end mirrors suddenly changes its transversal
position by about a micron. In case of such a vertical shift, the DARM
(Differential Arm) signals record clearly-visible signature and the subsequent
ringing down but such a clear signature is not present in case of a horizontal
shift. Studying what could make effects for 2 sides so different. Also,
studying how noise curves might change due to (constant) transversal shifts of
optics and/or beam.
Simulation of 40m interferometer
(Monica) The error signal
sweeps for the degrees of freedom have been simulated. A bad implementation in the
E2e code for the 40m of the pick off port has been pointed out: the
anti-reflectivity coating was missing and it will soon put into the simulation.
The control plant for the simulated
40m is under construction.
Code development
(Hiro)
Development of modeler codes to support the simulation for adv.LIGO. Designing the code
structure of the new C++ version of FFT.
Alfi
(Bruce) Bundle content caching
is being implemented in order to speed up the writing process for boxes with a
heavy use of bundled connections.
(Melody) Continuing
on fixing existing Problem Reports.
Currently working on the user interface for allowing the
user to choose the display for nodes:
graphic, node name, or a multiline
description. Worked
on allowing primitive nodes to be able to display an icon from a jpg or gif
file. Currently
working on saving the information into the box files and modifying the parser.
Data Analysis Activities (Lazzarini)
Charlton:
- Continued
working on my matlab code for comparing
stochastic pipeline strain with calibrated strain. I reported last week
that the RMS found by the stochastic pipeline was consistently a little
larger than that of the calibrated strain, and that there were a few
larger deviations at individual frequencies. Albert pointed out that the
calibration lines will be present in AS_Q but not in the calibrated
strain, which may account for some of the differences. I've added code to
mask out the offending frequencies. Some other minor bug fixes/changes
were made.
- Started
work on some scripts to display the results of the above comparison more
easily. Albert suggested using a 2-dimensional histogram (horizontal axis
being GPS time) so we can get a clear idea of the RMS differences over the
science run.
- Worked
with Keith Thorne on some issues with the Matlab
code used in my strain-checking code, stochastic.m
etc.
Mandic:
I calculated the Bayesian 90% UL on Omega_GW(100 HZ) as a function of
the spectral slope alpha for S3 H1L1. I also estimated such upper limits for
S4, S5, and AdvLIGO.
I continued studying the accessibility of the pre-Big-Bang models to LIGO.
Peter Shawhan and I formulated a proposal for the
S5 harware injections. The proposal includes a predetermined
schedule of injections, and a continuously running injection code, which
performs the injections according to the schedule and automatically switches
between science and injection modes (it also allows the operator to override
the injection).
Mendell:
I have checked into lscsoft/lalapps CVS, under the
/src/pulsar/StackSlide directory, updated code and
scripts for generating condor DAGs. Previous DAGs
results in estimated upper limits. New
options in the code allow iteration of the Monte Carlo Simulations until these
converge on a desired confidence level, and and the
DAG producing scripts allow the pipeline to start jobs with these options set.
The DAGs can now produce a converged upper limit,
though testing and further adjustments will be need to
produce final results.
Example results for the June LSC meeting are being generated.
Shawhan:
- Attended
Statistics for Gravitational Wave Data Analysis (GravStat)
workshop at Penn
State.
- With Vuk Mandic, planned
improvements in hardware injection software and scheduling.
- Reviewed
pulsar analyses / paper drafts.
- Planned
presentations for LSC Meeting and Burst Group face-to-face.
Sutton:
Last week I attended the 11th Canadian Conference on General Relativity and
Relativistic Astrophysics in Vancouver,
and gave a talk on LIGO and the search for GWs. I'm now working on the "LIGO
cheese" problem, mainly studying chirplets as
max-entropy waveforms. I've also revised
and circulated a draft of the LIGO-TAMA bursts paper that addresses all of the
new comments since the last review telecon. Hopefully this draft will be approved by the
executive committee.
Weinstein:
- lots of Inspiral analysis
review work.
- Working
with Lisa and Duncan on the ringdown search.
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS:
Spent the bulk of this week preparing for and release LDAS 1.6.0. As of
today, the release is in place at CIT, MIT, LLO, LHO.
LDAS-TEST will be updated today. MIT,
LLO, and LHO have all passed the post-release system testing. CIT has been
taken down for hardware upgraded which prevented completion of a few createRDS systems tests on that system, but other than
that, CIT is ready to go when the hardware upgrades are completed at the end of
this week. At LHO, Greg Mendell is currently
conducting extensive createRDS testing to further
challenge the new release in a real-world (astrowatch)
fashion. Greg has seen no issues at this time and expects to complete his
challenge by Friday.
This release primarily address enhancement requests to the createRDS command to allow better integration of frames
from different interferometers and to more cleanly handle data drop out issues
associated with input frames.
Other minor changes included an upgrade of the IBM Database to version
8.2.1, fixes to several GUI elements in the controlMonitorAPI
and a new option for the diskCacheAPI while scanning
duplicate datasets. Also, several packages in LDCG were cleaned up to be
removed if obsolete or upgraded to new versions.
Three new problem reports were filed in conjuntion
with the release of LDAS. Two of these
were in the controlMonitorAPI and associated with a
confusion of the difference between system site name and gateway hostname.
These two abstraction are degenerate on the LDAS
development system causing the bugs to not be discovered until after the
release. Only new enhancements were effected by these. The other bug is in the diskCacheAPI and has possibly been around but undetected
for some time. It is associated with the API incorrectly identifying a
subdirectory as changed under raw circumstances which we only learned how to
reproduce effectively this week. It is likely that this bug will not impact
normal operations of LDAS.
At the request of the burst group, the versions of LDAS and LAL/LALwrapper used for the LIGO-TAMA data analysis last summer
were tracked down for inclusion in an upcoming paper.
TCLGLOBUS:
Completed the revision of the Globus
XIO test cases to now user the new debugging mechanism which has been useful
for tracking down memory leaks.
Fixed the memory leaks related to asyncronous
calls using the client/server test cases and now have a new issue with memory
corruption. This is currently under investigation.
Continue to work on the problem with credential object not being properly
passed into the actual Globus function call in the
GSI client/server test case. This is also currently being investigated.
Made changes to the callback model to support threaded Globus
builds. This may be related to the
problems discussed above.
GRID COMPUTING:
Updated the
Linux kernel on our OSG gatekeeper. Restarting the computer after the
upgrade did not automatically restart the condor daemon and it had to be
manually started up. Unclear at this time why this happened,
but plan to investigate next week.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Retrieved/rearchived all files from bad tapes HL0164 &
LL0184 at LHO.
- Continuing
to fill in "missing" (at CIT) postS3 data from LHO using tar/globus-url-copy.
- Relabeled
some trend and dmt tapes at LHO to free up tape
space.
- Test
new firmware on test 3510 (/samtest) at CIT.
- Did
prep work for making CIT /archive use md devices
(plus upgrades of 3510 firmware, SAM, SAN).
(Stuart Anderson)
- Worked
with several Cluster Condor users to improve the efficiency of their
analysis code.
- Upgraded,
but not yet tested, Condor from version 6.7.3 to 6.7.7.
- Helped
with the SAM-QFS upgrade/reconfiguration at Caltech to support small
files.
MIT
(Keith Bayer)
- pcraid3 raid failed with multiple drive errors - lost
raid on 3ware 7500 card. Will
rebuild with FC3.
- Added
several accounts.
- Got
quote for T3's added to Sun support contract.
- Got
quote for new 5U RM dual opteron pcraid unit.
Livingston
(Igor Yakushin)
Generated new set of possible layouts for the LDAS room to
consider.
- The minimal upgrade that would only be good for S5:
http://www.ligo-la.caltech.edu/~igor/POWER_HVAC_LAYOUT/v1/
LDAS_210_layout.1.pdf
- Slightly better version. Communication and LDAS rooms
are joined, AC is rotated 90 degrees:
http://www.ligo-la.caltech.edu/~igor/POWER_HVAC_LAYOUT/v2/
LDAS_500_layout.2.pdf
- The ideal solution that also involves rearranging the
racks 90 degrees:
http://www.ligo-la.caltech.edu/~igor/POWER_HVAC_LAYOUT/v3/
LDAS_500_layout.3.pdf
- The
modification of the ideal solution (it is probably cheaper but at the
expense of wasted space) that would allow to reuse 30 tons AC needed
for 210 nodes later after S5 when we upgrade to 500 nodes:
http://www.ligo-la.caltech.edu/~igor/POWER_HVAC_LAYOUT/v4/
LDAS_500_layout.4.pdf
Sent final numbers for power and AC requirements to Mike, Rusyl and Allen.
Hanford
(Greg Mendell)
- I am
testing the RDS generation process, and new options available for createRDS jobs, using the newly released version of
LDAS, 1.6.0, and updated versions of the driver scripts.
General Computing (Wallace)
MIT:
(Keith)
LDAP work:
Automounting
on linux seems to cause kernel panics (perhaps it's
time to pass the automount map by hand..) crypt-md5
passwords work from both FC3 and Solaris 9 passwd
command works from both FC3 and Solaris 9 NIS+ password load into LDAP works as
well
- Added
new grad-student to gc (Jared Markowitz)
- Investigated
a little bit with Mac OSX
- Installed
and configured new SB1500 workstation (for use as new webserver
/ print server): troubleshooting SCSI bus errors on it installed latest
patch set from LSI - that might solve it
Livingston:
(Shannon)
- A
drive failed on the Ilog server. Fortunately, it is a mirrored array and
no data was lost. I am having some
problems with the vendor in getting a replacement drive, but I am
expecting it tomorrow. It should
have been here on Tuesday. As long
as the other half of the mirror holds out, the ilog
will stay up.
- Replaced
the CDS NAT router and combined it into the main GC router. Working on the associated firewall
rules, etc. that are needed due to this. The new router seems to be working
really well now that the syskonnect bugs and the
bad MiniGBIC have been taken care of.
- Working
with Dave on some CDS security issues and working on these
reconfigurations. Also working on
some new configuration with the RGA machines, etc. as discussed in the
OCSC meetings.
- Added
scratch space to decatur
and touro.
There is several hundred gigs of space
available now for data.
- Revisiting
snort and IDS installation/configurations. I will have to work with Dave
and get this duplicated at Hanford. Visibility into the network traffic into
CDS is a major concern due to time constraints on other issues.
Hanford:
(Christine)
- Network
usage can be seen at http://www.ligo-wa.caltech.edu/~christin/mrtg/
198.129.208.1_198.129.78.122.html
- The
previous years' SURF student home directories and files are now in an area
where they can be accessed from a web page. Created one generic user account which
the former students and mentors can use to login and modify any of the
files.
- Moved
some user home directories and files to new disks because some of the old
disks were getting full again. I
have one more empty disk available. This gives me some time to research and
purchase a larger disk system.
- Created
user accounts for this years SURF students.
- Rebuilding
two PCs by formatting the disk, installing Windows XP and all the standard
GC software.
- Purchased
and setup a new monitor for a user whose old monitor died.
- Working with technical support at Wolfram to fix our mathematica install. The latest version will not recognize
the license file.
- More
talks with Amerion and PNNL to finalize the
paper work for the Amerion contract extension
and work out details for the new network connection.
CIT:
(Mike)
- Cleaned
some network cables in Lisa Bogue's old office.
This allowed a network connection from the 125 subnet into my office, for
testing purposes.
- Installed
2U rack mount server with Larry, in one of the computer racks located in
our server room.
- Loaner
Pool: Loaded a laptop with OS and GC software. I also updated another
loaner laptop with software updates, and added security.
- Dennis
Coyne: Loaded an engineering workstation for him. This includes OS and
many engineering packages.
- Work
on updating General Computing's IP database.
This week I was able to do an inventory on Millikan's
PC/Sun workstation's. Now I need to record nodename, mac-address,
computer type/model, and location into our database. I still need to attend to 40 meter,
Wilson House, Sychrotron and all labs.
- Continued
work on Spam Filters.
- Onsite/phone
support, which includes printer, software, and some
networking issues.
(Veronica)
- LIGO: Website updates. Security patches on Windows
servers. Working on the makeover of
the Advanced LIGO Schedule Progress webpages. PAC meeting website updates. User support with Photoshop. Roster database update. Editing a video for Riccardo. Prepared a high-resolution image for a
publisher.
- LSC: Updates to the reviewed papers webpages. Updates
of the June meeting website.
- CaJAGWR:
Website updates / support.
- Project
Science: Issues related to the
website transfer to ITS and its continued support.
(Larry)
- Worked
a number of purchase issues. Equipment
purchased a few weeks ago has started to arrive. Installation of s/w and
distribution to end users should start next week. Working on a couple of misc. orders for
different people.
- Spending
a lot of time getting ready for the SURF students. Still have a number of
items to clean up and accounts to setup.
- Attended
a number of meetings concerning the DCC upgrade. So far things are looking
pretty positive.
- Modified
a number of user accounts.
- Rebuilt
a couple of disk systems. Working on getting the old disks replaced.
- Working
the heat issues with Bridge and Bridge Annex. Just a few more weeks to go
and the new air-conditioning system should be working. I've been informed
that they will wrap things up by the end of June. The computer room is not going to get as
much air as originally promised. It should be enough to get the existing
equipment powered up and going. I am already working with PMA in getting
more cool air for the room.
- Assisted
the TMT group with a couple of minor issues.
- Resolved
a couple of minor network and printer issues. The Campus phone technician
was in one of the network closets again and that caused a minor disruption
for a few people.
- Worked
the mail filters, and working on the logistics for changing out the mail services
in the not too far future.
Mail Statistics for May 19-25, 05
Accepted
Messages 17,474
False
Positives 212
Virus
Messages 1,268
Rejected
Messages 16,047
Total
Messages 33,521
Advanced LIGO and Supporting R&D (Shoemaker)
Systems and Management
From: Carol Wilkinson <wilkinson@ligo-wa.caltech.edu>
Advanced LIGO Project Management
Development Progress Updates
The next update exercise will be at the end of June for progress through
June 30, 2005. A teleconference for subsystem leaders on tracking budget
using Florence Kaufman's allocation and accounting worksheets will be held in
early June. Sub-system leaders will be contacted with details. Progress updates through April 30, 2005 on
development of advanced LIGO subsystems are available at the usual web site:
Advanced LIGO Planning:
Work is progressing on recalculating bottoms-up estimates for the costs and shedule for the Advanced LIGO construction project. Recent
re-estimates of SEI equipment costs and labor that have resulted in increases
in the overall project budget forecast have been partially offset by
significant reductions in projected SUS and COC fabrication costs. Fabrication
and installation costs and schedules for the remaining Advanced LIGO subsystems
will be scrubbed in the next month. Subsystem leaders should be prepared for a
planning session in that time window. The goal is to have the new overall
project costs and schedule by the end of June.
Advanced LIGO Reviews:
A Critical Review of the SEI BSC preliminary design was held on May 25. The
review committee report is expected in early June. Recent progress for
the ETF tech demo and results of modeling can be found at the review documents
site: http://ligo.phys.lsu.edu/SEI/May05Review
Systems and Management
from Dennis
Coyne
Systems
See also:
AL
Systems web page
AL Systems email
archives
Planning
- A development
schedule for SEI was shown at the SEI Critical Design Review in the
context of the fabrication timeframes and start of installation at the
observatories.
- Efforts
to refine the project costs & schedule continue.
- Supported
the ACIGA proposal for advanced LIGO support with scope, costing and
schedule information.
Records Of Decision or Agreement (RODA)
See also the RODA status web page
- The
RODA for a Draft MOU with ACIGA has been made obsolete (superceded) by
L050025-00 and M050196-00 (submitted to the DCC). This MOU was issued in
support of ACIGA's proposal for funding for
advanced LIGO support.
- A
draft RODA, M050174-01, "Requirements for SUS Features to Aid in
Initial Alignment" has been submitted by Ken Mason (AOS)
- A
draft RODA, M050175-01, "Initial Alignment Requirements on COC
Coating Reflectivity" has been submitted by Ken Mason (AOS)
Requirements
- A
small group has been looking into setting the Beamsplitter
(BS) size (GariLynn Billingsley, Peter Fritschel, Phil Willems,
Bill Kells, Mike Smith, Dennis
Coyne). Assuming no surprising results comes from the FFT model
confirmation of Mike Smith's Zemax analysis, the
BS will be recommended to be 370mm diameter, 60mm thick with 95mm long
flats for attaching the 'ears'. A RODA to follow soon, which will point to
the various supporting documents, generated
during this investigation.
Interface Issues
See the "Interfaces" section of the AL Systems web page
- Justin
Greenhalgh, Janeen Romie and Dennis Coyne met to discuss collecting all
SUS interface information into a set of documents with bilateral
agreements (i.e. SUS to each other interfacing
subsystem) in accordance with the SYS Interface Control Document (ICD)
outline. Much work is required to flesh out undefined interfaces; A list of action items and assignments has been made.
The plan (hope?) is that the more important items will be addressed in
advanced of the SUS Preliminary Design Update Review
Vacuum Compatibility
Residual Gas Assay (RGA)
See also the Vacuum Bake Lab
Bob Taylor
- Completed
the first Bake-out of 40 ea. Emitter & photo diodes and will proceed
to drill vacuum relief holes in the TO-18 cans for re bake.
Note: These are the first steps in vacuum qualification for the emitter
and photodetectors for the Adv. LIGO SUS OSEMs.
- Troubleshooting
the SRS for oven C . This oven will be down for
service for at least a week.
- Continue
to work with the campus shops to prepare the Bake Oven Lab for a new large
air bake oven installation.
Note: This large air bake oven will be used, with FTIR testing, to
prepare the large quad SUS structure for vacuum service at LASTI.
- Working
with Calum, Jay and Janeen
on the OSEM wiring of the Quad suspension.
High-Irradiance, Contamination-Exposure Cavities
Lee Cardenas, Liyuan Zhang
|
Cavity
(Location)
|
Material/Item
|
Start
|
End
|
Comments
|
|
Cavity #1
(OTF
Lab, Bridge)
|
new set of 70ppm REO mirrors
|
NA
|
NA
|
174 mW laser power,
compares well with 180mW with previous ATF mirrors. Cavity is ready for
samples
|
|
Cavity #2
(OTF
Lab, Lauritsen)
|
NA
|
NA
|
NA
|
cavity is close to being ready for samples; completion on
hold for other priority work
|
|
Cavity #3
(OTF
Lab, Lauritsen)
|
Glenair Micro-D connectors (qty=20)
|
3/2
|
~6/3
|
Cavity is locked and we are taking measurements for
absorption and ring down every day.
test will be completed next week
|
|
Queue
|
OSEM
emitter & photodiode
|
~6/6
|
~9/6
|
In vacuum testing currently
|
|
Queue
|
Stepper
Motor
|
TBD
|
TBD
|
RGA outgassing vs temperature taken, ready for cavity
|
Large Item Cleaning Plan/Facility
Ken Mailand Working on the 40m
Lab Air Bake Qualification, and met with Bob Taylor today to discuss details.
Mike Gerfen (Caltech machine shop)
is adding some hole and tap features to the two test plates to make them
identical as possible for the FTIR test to qualify the new air bake oven.
Meetings & Reviews
- Held
the 2nd Critical
Design Review of the SEI Subsystem Wed, 5/25
A report from the review committee is pending.
Synopsis (D. Coyne): Based upon tests of the technology demonstrator at
the Engineering Test Facility (ETF) at Stanford, the SEI subsystem is
shown to just meet requirements at 1 Hz, but fails to meet requirements
below 1 Hz and at 10 Hz. The SEI team offered explanations and potential
remedies for the performance shortfall. Costs are considerably higher than
planned. A schedule for the balance of development was presented.
- Future
near term planned meetings & reviews:
|
Date
|
Subsystem
|
Review or Meeting Title
|
|
6/?
|
SUS
|
Requirements &
Interface Update
(enable SUS/UK final
design efforts in parallel with SUS/US completion of the quad controls
prototype and preliminary design)
|
|
7/11
|
SYS
|
Systems Issues Summit Meeting
PASTE PF's agenda here
|
|
?
|
AOS
|
AOS: Scattered Light Control Design Requirements Review
(DRR)
|
|
?
|
COC
|
?
|
Control & Data Systems (CDS)
Data Acquisition (DAQ)
from Rolf Bork
- I
have been looking into some possible networking schemes for AdvLigo. In the future, we do not want VME crates or
processing in the VE areas or near the ADC/DAC modules. The ADC/DAC
modules instead would have some sort of data uplink on board (FPDP, gigE, fiber channel, etc) which must move data to/from
processors located elsewhere. In order to still make the 16 KHz loop
times, this data net must have minimal latency as well as speed. A couple
of us are going over to a local company today that makes 2Gbit full duplex
networks with advertised few usec latencies. It
may have advantages over our present RFM networks, including can be
configured as star network w/crossbar switching instead of ring and price
is about ¼ to 1/3 that of RFM networks.
- With
several systems due to go into LASTI over the next year, Jay and I are
starting to look at an integrated layout to fit these into a LIGO-like
system. Doing VME is out, just by cost, and new ADC/DAC modules will not
be ready in time. So, I think we need to develop something that proceeds
toward an AdvLigo layout for testing
w/capability of retrofit of new ADC/DAC and their data links.
from Ben Abbott
- I am
waiting for the arrival of a new VCO for the PLL for Jay's Daq-in-the-box.
Once it arrives, testing will resume.
Seismic Isolation
From: "Joseph A. Giaime"
<jgiaime@ligo.phys.lsu.edu>
Advanced LIGO:
Electronics: (Jay). looking for source of 24
Hz peak. Plots sent to Matt at ADE, got some feedback with suggestions of
things to check. 25 kHz modulation signal may be the source.
Work at LASTI:
- HEPI
control on the BSC (see LASTI ilog
for week ending 5/20/2005. Where are the noise plots?)
- BSC
HEPI controllers designed and tested, but not sensor correction.
Rich reports that the design was the same or easier than it was with the
stack in place. No need to make the sensor correction design.
Still some crosstalk that need to be ironed out
in Y and Z loops.
- Mass
driver measurements: 10 kg actuator mounted on vacuum flange, radially out. swept
sine measurements to ground and tank sensors. Assumption is that the force
- displacement TF from flange to ground (e.g.) is the same as the f - d TF
in the reverse direction.
- Ken
is still working on model; Nastran requires
manually constraining the connecting meshes. FEMAP?
- 1st
priority is to measure the first dozen modes w/o BSC chamber.
Work at the ETF:
- Brian
has been working on the model. He currently models the undamped dynamics, and has shown agreement with
resonance frequencies.
- The
two main goals for next Wednesday are:
- noise model compared with ETF results, extrapolated to
LIGO.
- expectation
of performance with softer vertical spring between stages 0-1
- Since
it is not easy to include the multi-rate FIR filters in the matlab model, Brian is using a set of IIR filters that
look the same high frequencies (i.e., 1 Hz and above.)
- Brian
O'Reilly will put together a set of calibrated spectra in 6 DOFs of one of the LLO BSCs,
with HEPI.
- Brian
and Corwin are thinking about strategies for shielding stage the stage 0-1
actuator fields from stage 2. Vertical stage 1 drive results in
stage 2 horizontal motion.
- Received
control desk 4.2, and they are trying to install it on their other dSpace system.
- William
East working on notch-ology, and is working on a
tool kit to make matlab notch design easier in
large quantities.
From: Ken Mason kmason@ligo.mit.edu
SEI Structure:
The
final phase of the SEI Critical Review was held on Wednesday.
Some highlights are:
Brian Lantz has shown he can get good isolation at 1hz and a design change to
the stage 1 springs is required to improve performance at 10 hz.
Measurements and modeling continues on the BSC structure to determine if
modifications are needed to the existing structure.
Dennis Coyne and Carol Wilkinson presented an updated schedule which would have
the prototype seismic isolation installed and tested in time for the UK
quad suspension testing.
The final report from the review committee is expected in two weeks.
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
Advanced LIGO Suspensions
Checking drawings for Calum.
Statusing
machine shop work. About to issue more POs for more parts. Reviewing documents for the
DRR Update. Working on redlines to the Universal SUS DRD. Met with Mike Gerfen on a number of machining and welding issues. E-mailed David McClelland
some background information for the mode cleaner costs.
Attended the SEI Critical Review
From: ctorrie <ctorrie@ligo.caltech.edu>
From: Ken mailand kmailand@ligo.caltech.edu
Working on the 40m Lab Air Bake Qualification, and met with Bob Taylor today
to discuss details. Mike Gerfen is adding some hole and tap features to the two test
plates to make them identical as possible for the FTIR test
AdL Controls
- Began
testing of the FPDP interface to the AD7679 ADC. Preliminary indications
are that the interface is working and we can read 18- bit data at the full
580Ksps. As soon as the interface is completely verified we will begin
noise tests on the ADC.
- Kicking
around various ideas for the slow and fast controls for AdL.
AdL SUS
Conducting transmission line effects experiment on GEO
electro-static driver.
From: "Mark
Barton" <mbarton@ligo.caltech.edu>
This week I worked with Mohana and Paul to connect
up and debug the electronics for the dual quad prototype at Caltech. We have
all the bits and pieces for the OSEMs on the top
three levels of the two chains except for two adapter cards that interface
between the DB37 connectors on the dSpace and the
IDC40 connectors on the anti-imaging boards. Mohana is having
these fabricated. With sufficient swapping of cables everything else seems to
work except for three drive channels, apparently due to a faulty LIGO-I
satellite amp.
Core Optics
From: Helena Armandula
<ahelena@ligo.caltech.edu>
Report from CSIRO - The report came from Mark Gross
In an effort to produce low stress coatings, the films were exposed to
subsequent annealing that seems to have damaged the coatings. The original plan was to try and get the net
film stress of a standard 30 layer mirror down to zero by step-by-step
annealing. Previous experiments done by CSIRO suggested that the net stress in
a silica/tantala multilayer could go from compressive
to tensile after annealing at temperatures up to 550C and hence at some point
must have gone through zero net stress. They now realize that this is true only
under certain circumstances.
CSIRO believes that during the annealing process, the silica material
changes far less than the tantala material. They found that tantala
films deposited in a standard IBS process have compressive stress which is
readily annealed out and can then easily become tensile with further annealing.
Silica films, however, are far more resistant to annealing and basically they
now see that even temperatures up to 600C will not anneal out the compressive
stress completely and at these sorts of temperatures re-crystallization of the
film, and certainly of other materials, may occur.
So, for the net stress to be annealable to zero,
they believe the film must contain a sufficient total thickness of tantala so that its net tensile stress (after sufficient
annealing) can balance the net compressive stress in the silica component of
the film. In the case of earlier experiments they were dealing with multilayers with about 40% total silica and 60% tantala. The standard 30 layer quarter-wave mirrors,
however, have the reverse of this. In other words, there is too little tantala in the film to balance the large compressive
component in the silica.
All this also suggests that if the same annealing conditions are applied to
multilayer films with differing thicknesses of each layer type, then the net
stresses obtained will be rather variable.
They have taken the coated samples to over 600 C (after 10 annealing stages)
and the net stress is still not zero. However, the films are now showing signs
of possible re-crystallization, and they will verify this by XRD.
For the purposes of testing a zero stress sample, the only way they can see
to achieve this is to use a silica/tantala design
that has more tantala in it (eg
1/8 lambda, 3/8 lambda) or to use something other than silica which also has
the ability to anneal to a tensile film (eg alumina).
After hearing the concept, at least , a couple of weeks back for optimizing
the various layer thicknesses in HR stack reflectors for the purpose of
minimizing thermoelastic noise, I have been doing
some studies of what this is likely to buy. So far I am working independently
of whatever Riccardo is up to (havent
officially come to understand that direction). The concept seems sound, so it’s
interesting to look at, and we have a nifty code for studying film stacks here
(written years ago by Hiro). I've got some
interesting results, which do indicate possible improvement (reduction of net Tantala thickness), but the best I've seen quantitatively
is only about ~15%.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
The pricing and availability of an OEM-version of the Innolight
NPRO laser was made. Enquiries were also made about the model number and manufacturer
of the laser pump diodes used in the 200-W laser. Maik
Frede will get back to me after returning from CLEO.
Auxiliary Optics
From: Michael Smith <smith@ligo.caltech.edu>
No report this week.
Other Laboratory R&D
Marco (25May)
Cavity successfully locked with the
implemented dithering servo loop scheme. Several transverse mode shapes were
collected and analyzed. I also performed the PZT calibration.
I’m studying different
collected data (profiles and spectra) in order to verify our capability to
understand the cavity behavior, before to switch to the MH mirrors. In order to
understand the profiles power density residuals I’m re-calibrating the
profiling camera with different test beams: a possible gain slope in the ccd array can affect our
evaluations. The last results indicate a slope < 5% intensity but with an
evident direction, the same showed by TEM10 profile.
Juri
Completed the
theoretical model for the coating thermoelastic noise
for finite size mirrors starting from the model found in literature for the
semi-infinite mirrors. Now writing a Mathematica notebook in
order to make calculations with Gaussian and Flat Top beams.
Chiara
Going through the experimental set-up for measurements of
transfer functions of the horizontal attenuation system prototype for the 40m
interferometer.
For additional information about this report, contact S. Whitcomb or P. Lindquist