Weekly Report for
Week Ending May 19, 2005
The LIGO Executive
Committee Agenda for Monday, May
23, 2005 will be:
(Meeting time: 10:30 am Pacific Time)
- Announcements
- Comments on Weekly Report
- LSC Issues (Saulson)
- LIGO Lab Operations
- Administration
(Lindquist)
- Sites (Raab,
Zucker, Shoemaker)
- Commissioning
(Fritschel), Detector (Coyne)
- Campus Research
Facilities
- 40 Meter
(Weinstein)
- TN, ( Libbrecht)
- LASTI (Shoemaker)
- Data Analysis and
Computing (Lazzarini)
- R&D and Advanced LIGO
(Shoemaker)
- CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION AS NEEDED
- CR-050005
-- Expansion of the DMT hardware infrastructure
Special Items:
- Annual
Report Assignments and Due Dates
Special Announcements:
Weekly Report Highlights
Livingston--After the previous week laser swap, the
power into the Mode Cleaner was increased to 5 W and the low noise spectrum was
recovered, with SenseMon reporting an inspiral range just over 10 Mpc.
LSC Issues (Saulson)
No report
LIGO Laboratory Administration (Lindquist)
MOU Amendments, MOU Attachment Updates, and Progress Reports
MOU Attachment updates for LaTech, Loyola, Penn State,
Stanford and Trinity LSC groups are signed-off. The documents are in DCC awaiting archiving and web posting.
Note: As reported earlier, all Progress Reports for all active LSC groups
are in DCC awaiting archiving and web posting.
Virgo: MOU Amendment No. 1, and Attach. No. 5 and No. 6 (combined
data analysis) are in final review by LSC and Virgo/Saulson
and Mours.
EGO: Attach. No. 2 (preliminary investigation of flat beam profile Fabry-Perot Interferometer concept) is signed-off. The
document is in DCC awaiting archiving and web posting.
SITE TELECONFERENCE (Lindquist)
There was no site teleconference was held on Thursday, May 19, 2005. The list of assigned actions updated through
May 5, 2005 will be found Here.
PROPERTY MANAGEMENT (Chargois)
>From: Ed Chargois <chargois_e@ligo.caltech.edu>
- Provided
assistance to the Detector Group (H. Armandula)
by packing, shipping, and preparing a Commercial Invoice and related US
Customs document for one (1) Fuse
Silica Substrate, serial number 41TM1, to CSIRO (R. Netterfield),
Lindfield, Australia. Account Number P204296.
- Provided
assistance to Thermal Compensation Preliminary Design (P Wllems) by providing the necessary documentation for
the return of a Laser and Power Supply to Laser Mill (A. Barrett), Hyde Park, MD. Account Number P443660.
- Provided
assistance to the Detector Group (H. Armandula )
with packing and shipping of one (1) coated mirror, serial number
MMT14K04-1, to Stanford
University (Dr. R.
Route), Account Number P204296.
- Caltech's
campus inventory is ongoing.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
- Attending
AIIM Conference.
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- packages:
in - 12, out - 8
- faxes:
in - 30, out - 18
- Began
processing documents from the PAC Meeting at Livingston.
COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman, Salone)
>From: Esther Cunningham <esther@ligo.caltech.edu>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Issued
the purchase order for the fax maintenance agreement. The vendor will be
submitting the invoice for the prepayment for the year.
- Assisted
Odvar in obtaining quotes for the IDC actuators
from several distributors. We have received several quotes.
- Completed
change order #3 to LaCour to remove available
funds of $10 for close out of LIGO.EPI 1.
- Followed
up on the status of the Datum order which was awaiting receipt of payment
to proceed.
- Completed
change order #20 to REO to add funds for the optics fabrication.
- Followed
up on pending Release of Claims which 3 have been submitted and close out
completed. There are 4 subcontracts still pending the Releases.
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Florence Kaufman <fkaufman>
SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)
>From: irena@ligo.caltech.edu (Irena Petrac)
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- The
applicable members of the LIGO staff have received their new AccuConference cards and PIN's
for use in reservationless
teleconferencing. The transition
from Raindance to AccuConference
will be complete by May 31.
- The
list of LIGO account authorizers and approvers has been transmitted to
Purchasing Services for use in the TechMart
program for purchasing. Training on
the use of the TechMart system begins on June
13. This list will be posted on the
LIGO web site.
- Purchase
of a new copier for the 6th floor of Millikan is
now underway. Delivery is expected
by the end of this month.
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
- Processed
the paper work for twenty-six (26) new/revised trips. At this time there are eight (8) new
trips that need to be completed and ticketed before the paper work can be
completed. Assisted several LIGO
people with their travel arrangements using their P-Cards and made several
reservations for outside visitors coming to a LIGO site for meetings
and/or workshops. LIGO will be
sponsoring thirty-eight (38) SURF Students this summer and all but three
(3) have been completed. We have
twenty-six (26) coming to LIGO/Caltech, seven (7) to LIGO/Hanford, and
five (5) to LIGO/Livingston.
- Completed
thirteen (13) Expense Reports and there are eleven (11) reports yet to be
done. I continue to contact
travelers who have outstanding Expense Reports (more than one (1) month
old) to ask for their cooperation in sending me their receipts so that
these can be closed in a timely manner.
Presently there are three (3) reports more than 30 days old. Travel Audit's new policy of accepting
only original signatures seriously holds up the process of closing
reports. I have one (1) awaiting signature
at this time. Reconciled
forty-seven (47) P-Card charges for the week requiring telephoning hotels
and car rental agencies to verify which traveler used my card and for what
amount.
- Coordinated
and initiated the opening of thirty-seven (37) new cards with the selected
new teleconference company, AccuConference. New card holders have been sent their
new information and I'm presently in the process of mailing out their
wallet-size cards. The old RainDance
account will be closed as of May 31, 2005, and each holder of a RainDance card has been asked to return their
wallet-size card to me and destroy any information containing their
account number on the old card that they may have printed out.
>
- Nothing signifiant to report.
>Dorothy Lloyd
- No
report.
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
PROPOSALS and REPORTS (Lindquist)
As mentioned during the Executive Committee meeting on Monday, April 11,
2005, LIGO must submit an Annual Report for Operations by August 1, 2005
and this annual report must be accompanied by a request for a two year
extension (FY 2007 and FY 2008) as well as a justification for why Caltech/MIT
should be continued in the role of management of LIGO.
I propose the following
general outline and assignments. Note that for most topics I will need a
summary of work accomplished over the past year as well as a bullet list of
work planned for the next year. I
would like to have contributions by Friday, June 17, 2005. Please keep
contributions modest in size (a few paragraphs to a page or two). I
propose to raise this as a discussion point during the Executive Committee
Meeting on Monday.
DCC Steering Committee (Lindquist)
No meeting this week while members of the committee are off at conferences,
PACs, etc. Next week we have scheduled
teleconferences with references provided by a couple of potential vendors.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
- Change
Request CR-050005 has been distributed for consideration during the
next meeting of the LIGO Executive Committee. The request is for the expansion of the
DMT hardware infrastructure. The
cost estimate is $70K---split 60/40 between the Hanford
and Livingston observatories respectively
($78K in the original change request).
The proposed change provides additional computing nodes for online
monitors, an upgrade of the development and testing machines, and network
upgrades with better security.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- A
staffing committee meeting was held on Monday, May 16, 2005. Minutes is
progress. All files are posted and
up-to-date on the web page.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
As the result of discussions at the recent LHO safety audit, it was agreed
that all non-administrative tasks will require a LHO Work Permit prior to start
of the task. To help make the work
permit process successful, John Worden has prepared and put-on-line, the LHO
Visitors "Work Permit Guidance" document for use by both the Control
Room Operators and LHO visitors. The LHO
Work Permit Guidance document has been submitted to the DCC as LIGO-M050194..
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of Commissioning Activities at LIGO Hanford Observatory
(Landry)
Commissioning highlights from this week in Hanford are bulleted below, pertaining to
general, 4k and 2k issues, respectively.
- DDT-contaminated
soil is being moved from Horseshoe Landfill (near the Nike missile silo on
Rattlesnake) to the Hanford
site via the Y-barricade. The result will be about 45 dumptruck loads per day past LHO on route 10, for a
total of ten days.
- Analysis
of S2 data with the Hough transform yields outliers at 70.12Hz and
harmonics in multiple IFOS. Investigations
find the base frequency in VME crates. In addition to specifice lines, this study finds broadband coherence
near 100Hz and below, with AS_Q and magnetometers.
- The status
of acoustic enclosures for the REFL ports is discussed. Both 2k and
4k REFL ports will receive an acoustic enclosure in the near future.
- DTT
was upgraded,
adding features and correcting bugs
4K
IFO
- Thermal
compensation dominated the commissioning on the 4k. Early in the
week, a brief lock at a record (H1) 9Mpc range was recorded. Transfer
functions of TCSX to ASI_CORR show a change in polarity when
increasing the TCS power above 4.7W. This caused problems with servo
stability. Work at a lower TCS power and a modification to the power
supply made for some improved
performance. Angle instabilies were discovered while working with the
TCS.
- The
PSL power saga
is described.
2K IFO
- The
new crystal oscillator was installed and warmed up over the weekend.
Next it was commissioned,
improving
the noise above a kHz. We expect that we are now shot noise limited
at high frequencies.
- Higher
power: we're now routinely running at 2X the S4 power into the MC.
Note this had been tried previously (briefly) but had no effect on noise
curve: now, the remaining noise is at least exposed. We need noise
budget, and this is getting worked on this week.
- WFS
and SUS scripts have been copied to LHO for tuning purposes. One
allows the WFS output matrix to be diagonlized.
e.g. it will allow us to ramp WFS2A separately
from WFS2B. The latter's unity gain frequency could then move to 3hz, instead of its current paltry 0.1Hz. This
could reduce AS_I by factor of roughly 30, as seen at LLO, suppressing low
frequency fluctuations. Likewise, scripts for large optic SUS diagonalization were employed. Angular noise coupling
was measured for the noise budget.
- An
H2 IOO PZT board was repaired
Outreach (D. Ingram)
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
L1 Interferometer (Frolov)
After the previous week laser swap the power into the Mode Cleaner was
increased to 5 W and the low noise spectrum was recovered, with SenseMon reporting the inspiral
range just over 10 Mpc.
There are currently 11 W available from the laser and 6 W available into the
Mode Cleaner. Two optics on the psl
table were replaced to reduce the losses and the laser temperature was
scanned to maximize power output.
Investigation of the sidebands around the 120 and 180 Hz power lines
revealed that they are coming from up-conversion of the 6 and 10 Hz low
frequency peaks in ASQ. Suppression of the low frequency peaks around 6 and 10
Hz with additional resonant gain digital filters reduced the sideband peaks of
the 120 and 180 Hz below the broadband level. Other noise investigations that
were done but did not uncover noise sources: the additional filtering of the
SPOB signal which is used to track the ifo
optical response, and the LOS local side damping.
The ringdown of the ITMX suspension wire
fundamental mode was remeasured. The results are
consistent with earlier measurements. It was established that radiation damping
does not affect the measurement, by measuring the ring down with both a simple
Michelson ifo and the full ifo.
The spare LOS bias module was tested and electronics oscillations were found
between 5 and 7 MHz; these could affect the ifo noise.
The new Y end station heater controllers were installed. The 1 Hz sidebands
of 60 Hz are no longer in the magnetometer spectrum. The eagerly awaited
upgrade of the remaining heaters in the X end should remove the 60 Hz sidebands
in DARM.
The latest software was installed on all CDS real-time front ends and new hepiepics, susepics, and iscepics. The new software supports double precision floats
throughout the filter calculations and signal transfers thru the LSC/optics
chain. Both frame builder computers were upgraded and tested. The back up frame
builder had to be bypassed due to check sum errors, isolated to an intermittent
network card. A replacement network card
was ordered.
L1 Commissioning (King)
I helped measuring the timing jitter of the electro-optic timing
system. The results from the serial data
analyzer still puzzle me as the eye diagram was all out of whack, which
suggests that there was a problem during the measurement. However the instrument consistently reported
a factor of two greater timing jitter than for the
copper-based setup.
Education and Outreach (Thacker)
- Assisted
in exhibit installation; (7 exhibits)
- Assisted
in Exploratorium exhibit training 2-day workshop
- Presented
talk on LIGO SEC outreach to LIGO PAC.
Site Safety and Security (Riesen)
Replaced defective
Laser Safety System controller at the X-end station. Re-set the
main security gate and fixed software changes so the gates will open
automatically when leaving the site. The
Laser Safety System is now fully functional throughout the site. Rounding up and repairing defective IR
viewers. Waiting for 2nd quote for
getting the staging building's crane functions updated. Found no laser or site safety concerns this
reporting period.
Mechanical Engineering (Spjeld)
AdL Quad SUS Installation Fixtures
- Received quote on IDC linear drives from three
distributors.
- Looking at alternative drive configuration to avoid
binding.
- Manufacturing drawings of completed parts in progress
- Addressing design issues raised in design review
committee report
AdL SEI Engineering
Review of tolerances and off-the-shelf parts on Ad SEI drawings in progress
LIGO Outreach
Building
Pendulum Exhibit
Designed and estimated mass of truss support sections for pendulums
General Engineering
- Redesign
of HAM door removal tool in progress
LLO General Computing and LIGO Computing Security (Roddy)
HPLF, Optics Modeling, Data Analysis and L1 Commissioning (Franzen)
1)
HPLF news: The
again broken IPG Photonics 100 W laser was received and examined by the
manufacturer. During Monday's telecon (May 19) we
were informed that the core fiber was burned and needs to be replaced. The IPG stuff are
not sure what caused the failure but speculated in back reflection or power
fluctuations in our lab. We are not so convinced. The laser is now being repaired
for another round.
2)
Took part in
commissioning activities aimed at increasing the PSL output beam power.
3)
Writing on to me
assigned parts of an UF AdvLIGO Input Optics
Preliminary Design Review document.
CDS software (Khan)
Worked with Rolf and alex on the code and Frame builder
upgrade. This new upgrade involves changing the floating point point variable from single precision to double precision
format and also the size of the daq channel name
length is increased from 40 to 255 characters.
Developed a
new stat screen for the TCS servo.
LDAS/Condor Sysadmin and Burst Analysis (Yakushin)
Data archiving/Condor/LDAS admin:
1)
/frames and /dmt have been rebuilt to support better small files. The
corresponding data was restored from tape.
2)
Last Friday there
appeared a smell of burned plastic in the LDAS room. The problem was traced to
some burned isolation on the cable in the power panel. The cluster was turned
down to reduce the power load until the power panel was repaired on Monday. Now
everything is back to normal.
Data analysis:
1)
Participated in
the waveburst review face to face meeting at LLO on
Monday and Tuesday.
2)
Preparing FOMs, documentation and tests requested by the waveburst review committee.
3)
Processing SG15
burst MDC frames.
Initial LIGO Detector Science & Engineering
(Coyne)
CDS
no CDS weekly meeting (conflicted with PAC meeting)
CDS Software
no report
CDS Hardware
Ben Abbott
LSC RFPD: Todd or I will
begin testing the PDs that he has made soon.
DMT
John
Zweizig
This
week I spent upgrading the dmt online machine system
software at LHO. I also
began a configuration change which is prompted by security and reliability
concerns. The most fundamental change is to stop using the two
original E450s as processing nodes and devote them entirely to providing
the necessary dmt support services and as for
communications between the DMT processes and external services and
clients.
PSL
PeterKing
The high power photodetector testing continues. No
problems so far.
4ITM05 Metrology
GariLynn Billingsley
Completed the HR surface figure measurement with the Fizeau interferometer. The surface
profile image and other data for this optic here.
The required rms is < 0.8 nm over the central 80mm
with tilt, power and astigmatism subtracted. The value for 4ITM05 is 0.44nm
rms. I think this is still limited by our current (new)
calibration. As we measure more optics with this configuration the
calibration will get better and we will get a lower number for the rms.
Many of the CSIRO optics (4ITM06 comes to mind) had an rms
over the central area of ~0.2nm rms.
The piece showed more of the "streaks" that we have
seen before. The "streaks" are the same as have been seen before and
after coating; we believe they are a part of the surface. We
suspect they may have been caused by the Liquinox
cleaning since they do not appear in any of the CSIRO data sets, and their
instrument is certainly sensitive enough to see these. All of our optics have been cleaned with Liquinox
before coating. We have got some tests underway to try to verify whether it was
the Liquinox.
Lee Cardenas, Liyuan Zhang
An bulk
absorption scan was made at a depth of –2 inches.
The next measurement will be a coating absorption scan.
40 Meter Interferometer (Weinstein)
- The
40 meter Technical Advisory Committee (40m TAC) met on Thursday. Osamu
presented a status report (G050265-00): see: ppt or pdf.
- Dwight
Carter and Carol Wilkinson have assembled a
40m experimental work schedule in Primevera
(following closeout of the 40m construction work schedule).
IFO commissioning:
- After
the re-layout of the SP beamline, some changes
to the POX & POY, and new end Thorlabs DCPDs, Osamu and
Rob have re-locked the dual-recycled Michelson (DRMI, arms blocked). The
SP DDM signal and MICH
dither are a little noiser
than before; Looks like more ground loop noise. Under investigation.
- Osamu
changed the MICH
dither lock frequency from 1230 to 1050 Hz, to be less sensitive to 60 Hz
harmonic noise. Hoping for better dither signal tonight.
- Osamu
measured the carrier reflectivity of the arms: for x-arm, it's 84.0%, y-arm is 86.4%. (spec is
93%). This means we will get a recycling gain of ~6, and an undercoupled PRC. There is obviously an anomalous
source of loss, maybe due to dust or other scattering centers on the
mirrors; it is made more severe by the high finesse of the cavity. The
mode matching into the arms is not yet well tuned; with better mode
matching the reflectivity will be even lower. But it should be noted that
offsets in the measurement of DC power are big, so there is a rather large
error in these measurements.
- Dan's
work on re-location, re-layout, re-alignment and re-commissioning of the
SP RFPDs is complete. A third SP RFPD, at 166 Mhz, has been installed and
placed on a proper mount (borrowed from LLO). The PD and electronics have
been fully checked out by Ben.
- Osamu
and Steve plan to simplify the layout of POX and POY on the ISCT table
sometime this week. They're waiting on a few more 2" optics.
- Monica
continues to work towards calibrating LSC signals by exciting ITMX and
ETMX with xarm locked, and measuring the
response at AP 166 MHz. She's getting numbers that are comparable to what
is seen at the sites, ~ 5e-9 m / count of LSC-ETMX_EXC.
- Virginio and Monica measured the ringdown
time constant for the arm transmitted power. They rapidly switched the
light power by flipping the sign on the PSL frequency stabilization servo,
and then measured the exponential decay of the light transmitted through
the arms. They got 55 microsecond decay time, which is consistent with the
design spec finesse of 1255 (T_ITM = 0.005). However, this does not take
into account the decay time of the mode cleaner, which is in between the
PSL and the arms (which should have tau ~ 45
microseconds).
- Rob continue to teach the lock acquisition code new tricks.
He has implemented CARM & DARM, using TRX +- TRY, and has acquired
lock on both arms using this. He's working on code to dynamically change
the control scheme, switching between different CARM/DARM signals
depending on the state of the interferometer.
- Rob
has implemented a "digital bell": he uses a high-Q filter module
in the front end software to generate a sinusoidal signal for
dither-locking the Michelson, without using the arbitrary waveform generator
(AWG). This greatly reduces the traffic on the reflective memory network.
It can be easily turned on and off from the LSC EPICS screen. It seems to
work well.
IFO modeling and DC detection development:
- Monica
continues to study and compare 40m DRFPMI error signal sweeps (DARM and
CARM) in both e2e and Twiddle, and now gets very good agreement in mode
cases. Small discrepancies are likely due to small differences in the demod phases.
- Monica
continues to study the implementation of radiation pressure in e2e, and
its application to optical spring effects at the 40m. She's trying to
repeat some optical spring simulations done by Hiro
some time ago.
- Now
that Monica's e2e simulation of the 40m DRFPMI optical plant is rather
well tested and validated, she is focusing on the development of the
control plant.
- Virginio completed a design for a proposed T050076-00.pdf
Suspension-Point-Like-IFO (SPLIFO) for the 40m arms, using the STACIS
isolators to actuate on the stacks.
Electronics, Controls:
- Efforts
to reduce the noise from various signals needed for lock acquisition, have
led to a more global assault on ground loop problems at the 40m.
- It
was found that all racks had been grounded to the wall at the kill
switches installed by Caltech electricians (in addition to being grounded
to the isolation transformer that supplies the power to all the racks).
This is a great way to make ground loops! We plan on disconnecting all
these additional grounds in the next few days.
- All
optical tables have been grounded to the vacuum envelope, for safety. If
any electro-optics on the tables are
accidentally grounded to the table, this is a great ground loop. Steve is
replacing all these grounding cables with ones that ground through a 1 MOhm resistor.
- Bob
is checking for any ground loops at the rack cross-connects, and any
ground connections between racks. Ground shields of inter-rack cables
should only be connected at one end. So far, Bob has found and fixed
several problems on cross-connects. Should be finished with the LSC/ASC
racks by end of week.
- Steve
is surveying the paths whereby electro-optics on the tables get AC power,
to ensure that they have ground isolators and trying to ensure that they
are plugged in to the same rack that processes their signals. Auxilliary devices (cameras, mech
shutters, OSAs) are plugged to wall ac power.
- Ben
is drawing up a master plan and documentation for grounding and shielding
in the lab.
- Jay
is thinking about the design of ground isolating signal distribution
boxes to safely get signals to scopes in the control room.
- Ben
and Rob installed new RevB coil drivers on the
remaining three suspension controllers: PRM, SRM, BS.
They fully check out and are now in service. They re-aligned the optics
using the oplevs as a reference, and reduced the
gains on all the drive path filter banks to account for the increased
drive in the new coil drivers. Rob will re-balance the coil gains in the next
few days.
- The
pitch bias for the ITMY RevB coil driver was
insufficient to take out the large pitch in that optic. The drive path was
still experiencing large length-angle coupling, especially during/after
dither lock. Osamu has modified the bias path resistors on the coil driver
to permit a larger pitch bias setting. Currently, all signal path
resistors on 7 coil drivers are 100 Ohms. All bias path resistors are 430
Ohms except ITMY, which Osamu changed to 100 Ohms.
- The
front end readout of the Thorlabs PDA 520's at
the X and Y ends is now fully operational, and these signals are available
for, and used in lock acquisition (DC transmission lock of the arms).
These PDs are not noticably
faster than the QPDs we had been using, but they
are much less noisy. We may want to replace them with a faster (smaller
aperture) PD.
- Ben
still needs to get the DC signals from all RFPD monitor/control cables
into the front end ADCs without the use of an auxilliary
DC signal cable (which causes ground loops). He'll get that done this
coming week.
- Ben
is updating the drawings for the rack electronics for the digital
suspension controllers (DSC), the ends, and the LSC and ASC systems, to
reflect the many changes that have happened over the last year.
- Jay
and Peter King measured the jitter on the fiber timing links installed in
the lab, at the vertex and at the two ends. Results are documented in the
elog. Clearly, the fiber distribution system
adds jitter, but the jitter at vertex is about the same as at ends, so it
isn't degraded by the "long" fiber run. And the jitter is about
what might be expected given the parts used. It's tolerable for us, but
could have been done better, using parts for 200 Mbaud links instrad of 50 Mbaud links. We do have anecdotal evidence is that
this new system is better than what we were getting using 40m long copper
cables; we haven't been rebooting the crates at the ends as much as
before.
- We
await Rolf's return to get the IPANG QPD signal into the front end ASC
system.
- Still
need to hear from the authors of ezcademod, to
fix the problem that when garbage goes in, ezcademod
spits out NaNs, which go into the front end and
crash it.
- Until
the Thorlabs DCPDs
were installed, we were using the DC signals from the QPDs
at the ends, which were very noisy. Rana, Jay,
and others worked on fixing up the QPD interface boards so that the
signals are properly filtered, and ground loops reduced, and the board is
in conformity with the most recent DCN.
- Last
week we discovered that autoburt had not been
running since March 16, when the op140m computer was rebooted. Autoburt was restarted on May 11.
Bake oven Lab:
- Bob's
bake oven lab had a big hole cut in the wall to permit the installation of
the large new air-bake oven. It's now been temporarily re-sealed, awaiting
the delivery of the oven (3-4 weeks). Bake oven lab mods
to accomadate the new oven are proceeding ahead
of schedule.
- Bob
continues to work with Calum and company at the AdLIGO suspension lab in the synchrotron building.
Thermal Noise Interferometer (Black)
From Helena:
Advanced LIGO Coating Development
Talked to JMM. Delivery of the
TNI mirrors is still scheduled for the 1st-2nd week in June. Coating
calibrations are under way. He is also
manufacturing a container to preserve the coating properties during shipping.
As a side note, he informed me that US
customs do not allow wood containers to be shipped to the US from
overseas because of termite problems.
For lower mechanical loss coatings, JMM tried
cobalt as dopant; it did not work well, the optical
absorption was very difficult to control, he discarded this material.
Research is under way with a new alloy.
Annealing of this coating produced some crystallization resulting in higher
than desired optical absorption. They are working with the annealing parameters
to improve it.
From
Akira:
Added two new magnets to improve eddy-current
damping, and started putting together required vacuum hardware to pump out.
LASTI (Ottaway)
No report.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Biplab Bhawal)
SimLIGO Study
(Biplab)
Studied the effects of transversal shifts of mirrors on the
noise curve. SimLIGO could hold the lock well
even for a shift of 1 cm (may be more - need to test) on end mirrors, if such
shifts are done slowly over time (tried 1mm/sec).
(Sany
Yoshida and his students)
As the table top motion, they
used to use the accelerometer output instead of the simulated motion to make
the simulation more realistic and to include effects which are not properly
included in the simple seismic motion model. Now after HEPI having been installed,
they started to use geophone data based on the advice of Joe Giaime. The first trial was successful.
The development of the pendulum
model with violin modes developed by Virginio was taken over by Sany. The validations in simple cases were done and it
seems to be working. The development environment, Maple, has been installed at
LLO and Sany can now develop the code himself.
The input beam simulation with
realistic MMT is still going on. There are some issues not well understood.
This has been discussed at the e2e weekly meeting and some suggestions were
given to trace the problem.
Simulation engine code development
(Hiro)
Hiro
is working on the simulation engine code to implement features for the advanced
LIGO simulation. One new feature added
is a generic and modular framework to support different time steps. By using this feature, subsystems with
difference bandwidths can be mixed together with different time steps being
used in different subsystems.
Simulation of 40m Interferometer
(Monica) Error signal sweeps
have been simulated with e2e using the right 40m arm-length; the agreement with
Twiddle is good especially when the demodulation phases are exactly 0 (Inphase) or PI/2 (Quadrature);
That is the case for the demodulated signal at the dark port both at 33 MHz and
166 MHz.
ALFI
(Bruce, Hiro)
Bruce has been working on the
refinement of the new data stream management in ALFI, called bundle. A version was implemented, but it turned out
to be too slow when checking missing links.
Hiro and Bruce discussed about various
possibilities to make the implementation modular and faster. Bruce is trying to complete the new
implementation.
(Melody) Continuing
on fixing existing Problem Reports.
Currently working on the user interface for allowing
the user to choose the display for nodes:
graphic, node name, or a multiline
description.
Worked on
revising the Rename dialog to include the available choices.
Working on
allowing primitive nodes to be able to display an icon from a jpg or gif file.
Data Analysis Activities (Hiro Yamamoto for
Albert Lazzarini)
Gregory Mendell
I have checked into lscsoft/lalapps CVS, under the /src/pulsar/StackSlide
directory, code with two new options. The code can now create sky bands perpendicular
to any point on the sky, and the first option allows this to be either the
Earth's average acceleration vector, generating sky bands similar to those used
during the PowerFlux search, or the galactic pole
(for generating sky bands parallel to the galactic plane). The second option
allows the removal of instrument lines from SFTs
using code borrowed from the Hough search.
Peter Shawhan
- Spent
time reviewing pulsar analyses
- Currently
attending the Statistics for Gravitational Wave Data Analysis (GravStat) workshop at Penn State
Philip Charlton
- Finished
matlab script to compare band-limited RMS of
AS_Q*response with official calibrated strain. This has been checked into
CVS under matapps/src/searches/stochastic/CrossCorr.
- So
far I've run the script on all S3 data for H1 only (took a couple of days
using only a single processor). This shows that the differences in RMS
from the two methods are around +/-5% but there are a number of large
excursions (assuming it's not a bug in the script).
Patric Sutton
Last Friday the bursts review committee met to discuss the LIGO-TAMA bursts
paper, and decided that all major issues have been resolved. Since then I've been doing final minor
edits. I've also met with Lazzarini and Tinto for further
discussions of the inverse problem for bursts.
Right now I'm in Vancouver
for the 11th CCGRRA (Canadian relativity) conference.
Vuk Mandic
- I
studied the accessibility of the Pre-Big-Bang models of cosmology to the S3
H1L1 result. I also examined the expected improvements in S4 and S5 and
Advanced LIGO, and I compared these results to the bound from Big-Bang Nucleosynthesis.
- I am
also preparing to run the stochastic code on S4.
Igor Yakushin
Data archiving/Condor/LDAS admin:
- /frames
and /dmt have been rebuilt to support better
small files. The corresponding data
was restored from tape.
- Last
Friday there appeared a smell of burned plastic in the LDAS room. The
problem was traced to some burned isolation on the cable in the power
panel. The cluster was turned down to reduce the power load until the
power panel was repaired on Monday. Now everything is back to normal.
Data analysis:
- Participated
in the waveburst review face to face meeting at
LLO on Monday and Tuesday.
- Preparing
FOMs, documentation and tests requested by the waveburst review committee.
- Processing
SG15 burst MDC frames.
LIGO Data Analysis System Administration
Software System (Kent Blackburn)
LDAS:
Continued to develop functionality for the next release of
LDAS scheduled for the first of June. Due to time constraints several of
the C++ specific enhancements had to be postponed for the next release. These
involve the diskCacheAPI and the frameCPP
library. All critical createRDS development has been
completed. This has been reported to the DASWG.
Completed developement on PR2221 dealing with 0
dimension ilwds printing random data. Verification
with the nightly build is all that is needed to complete this problem report.
Removed documentation for functions which are no longer a
part of the frameAPI.
All of the functions dealt with the DAQ mode for frame access that was
deprecated when the TOC mode was supported (PR2817).
Checked in code for PR2617 - column headings for resource vars and PR 2336, sorting of data by clicking on column. Still working on PR 2724 to allow addition of new resource vars.
Completed all system and integration testing on LDAS
version 1.5.74.
Updated the test results website. Due to hardware
failure over the weekend test jobs began to fail at 6:30AM on Monday. All other
tests passed.
TCLGLOBUS:
Discovered a
memory leak in the code which required a rework of the callback interface to
allow for deallocation of memory. Found
several other memory leaks in the code not related to callbacks.
As a result of fixing these
memory leaks, identified sevarl places where memory
was being improperly released and causing segmentation faults. These were also
fixed.
Began developing new tests to more closely track the
memory usage of the code. These
new tests also incorporate new debugging mechanism at both the TCL and the
SWIG/C levels.
Completed the revision of the GLOBUS FTP Client and I/O
test cases to now use the new debugging mechanism. Still working on the
updating of the GLOBUS XIO test cased to use the new debugging mechanism and to
check for memory leaks.
OSG/GRID:
Described the OSG plans for
proposal generation and blessing through the OSG executive board and council
with the LSC Computer Committee at this weeks teleconference.
Hardware System (Anderson
Stuart)
Caltech
(Dan Kozak)
- Converted
LLO /frames & /dmt to use md devices for better small file support.
- Set
up LLO new fb0 with SAN/SAM and configured the filesystems.
- Worked
with Alex on LLO fb0 FC problem (looks like one port of their dual 2Gb FC HBA is bad).
- Copied
"new" S2 RDS frames to CIT cluster and published them in ldas-gridmon's LDR.
- "fixed" LLO damaged tape (by reading it with tcopy...).
- Working
clearing up fallout from stuck tape HL1024 at LHO (got shipped back with
drive, I'm retrieving files from the CIT archiving and copying them to
LHO).
- Ditto
for data on damaged tape LL0184 at LHO.
- Continuing
to fill in "missing" (at CIT) postS3 data from LHO using tar/globus-url-copy.
Getting close to done with this.
- Keeping
track of problems with the process used above (tar/globus-url-copy)
where files are showing up corrupt at the other end.
- Started
rearchiving some trend and dmt
files at LHO to free up tape space (lots of underutilized tapes).
(Phil Ehrens)
- Replaced
two failed hard disks.
- Ongoing
work to rebuild LDAS-TEST node 3. An onboard IDE controller failed and
both hard drives were left in a bad state.
- Fully
documented desktop Linux installation and configuration. Partially scripted the configuration
process. Prepared nice webpage for same.
- Configured
machine "spud" after upgrading hard disk from 10 Gb to 160 Gb.
- built 2.6.12pre2 linux kernel
and installed on all LDAS-CIT cluster nodes to reduce NFS related
downtime.
- Determined
that B drives in LDAS-TEST nodes 6 and 7 were cloned from larger drives
and are not usable. Node 7 has had a new B drive cloned, node 6 to follow
today.
(Stuart Anderson)
- Worked
on several LDAS-CIT cluster stability issues:
·
kernel crashes from
heavy NFS I/O.
·
Condor performance limit for high rate of file open().
·
disk utilization from
100's of matlab coredump
files.
- Identified
and repairing holes in missing CDS minute trend frames.
- Replicated
Burst MDC frames from PSU via LDR.
- Cleaned
up SAM-QFS prestager script to be more robust.
- Released
S4 L1 RDS data from being pinned to disk at CIT to free up several TB of
generic cache space.
- Monitoring/maintaining
LDR at CIT as it catches up on Astrowatch data.
MIT
(Keith Bayer)
- Added
several users.
- Got
quote for 5U 24 bay dual-Opteron rackmount pcraid.
Livingston
(Igor Yakushin)
- /frames
and /dmt have been rebuilt to support better
small files. The corresponding data
was restored from tape.
- Last
Friday there appeared a smell of burned plastic in the LDAS room. The problem was traced to some burned
isolation on the cable in the power panel. The cluster was turned down to
reduce the power load until the power panel was repaired on Monday. Now
everything is back to normal.
Hanford
(Ben Johnson)
- Most
of the week taken up with gathering data to make a quantitative
statistical argument about the magnitude of the S3- dataValid
problem.
- Ejected
19 tapes from a list given by Dan some time ago. Replaced them with 19 new
tapes.
- Discovered
that some S3 raw data was missing. It exists at CIT so Dan is restoring it
presently.
- Refining
AstroWatch GUI. It is now elogging
reliably. Planning on adding a "History/Resubmit" mechanism,
plus enlarging the comment box.
General Computing (Larry Wallace)
MIT:
(Keith)
- Continued
work on LDAP have login and passwd command
working on both Solaris and Linux automounting
works only on Solaris so far working on replication (it stopped working this
week)-Patched several windows machines
Livington:
(Shannon)
See Livingston
weekly.
Hanford:
(Christine)
- Network
usage can be seen at http://www.ligo-wa.caltech.edu/~christin/mrtg/
198.129.208.1_198.129.78.122.html
- Refurbishing
some older computers and moving other computers around to create work
spaces for the SURF students.
- Replaced
a bad disk in a PC out in the common area.
The computer will be rebuilt with Windows XP.
- Set
up a Sun Blade 1500 for a user to replace a Sun Ultra10 that is having
hardware problems.
- Researched
what is involved in having a multihomed
network. This is because I have
been looking into the possibility of having a backup WAN connection that
would not be part of the ESnet.
- Other
user support for printing problems, virus problems, and AutoCAD
installation problems.
CIT:
(Mike)
- -Bob
Taylor: Worked on his computer trying to clean up spyware/aware,
but got know where. I ended up having to reload his workstation from
scratch. I am still working with him to get some of his old preferences
setup.
- -40
Meter: Worked on the B/W printer, which ended up having a dead jet direct
card. I had a backup jet direct card that worked. They are back up and
printing B/W.
- -Worked
the Spam filters and e-mail servers with Larry.
- -Visitor
workstation: Finished up reloading and updating 7 more workstations. I
have two on my office that I need to get ghost images of, and will put
these back into their cubicles on the 2nd floor of W/B. This gives me a total of 13 workstation's
for Surf Students.
- -I
setup a complete workstation in 355 W/B.
- -I
loaded a sun workstation Solaris 10, for my office.
- -Updating
our IP database.
- -Irene
Baldon: Email problems. I ended up spending a
couple of hours trying to get Eudora from downloading 5000 old email
messages to her local desktop. I have installed Thunderbird, and have
cleaned up the mail server.
- -Solid
Works 2005: Updated Janeen Romie's
laptop to 2005. One down five to go.
- -Additional
onsite/phone user support that included networking, printing, and software
issues.
(Veronica)
- LIGO: Working on the website updates for
Advanced LIGO. The old pages were
generated by MS Office and I want to rewrite them into a more manageable
format. Website updates for the PAC
meeting. Various updates of the
LIGO website. User support for
Julie with media playback in a ppt
presentation. Security patches on
videoconferencing pc. Roster
database update / troubleshooting.
- LSC: Website updates for the observational
results and the June meeting.
- CaJAGWR: Compressed
and posted the video of the last week's talk. Taped and compressed another talk given
this week. Website updates and
support.
(Larry)
- Purchased
a number of misc. items in preparation for the power outage. Purchased a couple of peripherals for
different users. Checked on
existing orders. A number of computers have been shipped and the SUN units
are still in process. Placing an
order for a replacement UPS in the server room. Delivered a number of items that had
been received. Reconciled p-card. Went over a couple of contracts for
other groups on the project.
- The
electrical shutdown preparations and actual shutdown did take up some
time. The preparations paid off.
All of the core servers and network boxes were kept up and running during
the scheduled outage. There were a
few minor problems on bringing equipment back on-line once power was
restored. During the outage
batteries were replaced in a UPS and a couple of sandbox servers were
brought up to date with their patch levels. One E2E server from the 3rd
floor was moved to the basement because of heat problems.
- Worked
a number of SURF student issues with Cindy, Mike and others.
- Working
with DCC on evaluation of some s/w packages they are looking at.
- Spent
time repairing a disk containing some of the home accounts. After the second repair job and testing
it was discovered that the disk is having some hardware problems. The
replacement disk is basically DOA so I am now building another replacement
disk. I am running out of spares and have ordered another one. After talking with Seagate we need to
build a SCSI box running windows in order to use their diagnostic s/w for
their disk drives. They will not just exchange them anymore.
- Moved
a couple of systems around for different people.
- Working
with the LDAS group to get a couple of minor cron
issues cleaned up. Phil E. has
setup a standard linux install that we will test
out in the near future. We want to have the GC computers using the same
basic configuration that the LDAS group is using.
- Working
with PMA on a number of networking and air-conditioning issues.
- Assisted
a number of users with various problems.
Cleaned up a few more accounts and setup a couple of new accounts.
- Setup
a cron job to monitor a few processes and make
sure they keep running.
- E-mail
issues have been interesting this past week. Mostly just more spam getting
through now that we've relaxed some of the rules. A couple of client
machines are now using Thunderbird in place of Eudora in order to
eliminate problems of e-mail getting caught in a cycle of resending
itself.
Mail
Statistics for May 12-18, 05.
Rejected
Messages 13,661
Virus
Messages 2,998
False
Positives 367 (In actuality many of these were
not)
Accepted
Messages 18,168
Total
Messages 31,829
Advanced LIGO and Supporting R&D (Shoemaker)
Systems and Management
No report this week
Seismic Isolation
From: Ken Mason kmason@ligo.mit.edu
From: Jay Heefner <jay@ligo.caltech.edu>
Noise measurement s on the capacitive position sensors continue. ADE has
been contacted in an effort to determine the source of the 24Hz peak that is
seen in the noise spectrum.
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
Norna Robertson joined us here at Caltech for the
day yesterday. It was a very fruitful visit in that we assembled all of the
suspended masses and discussed various suspension topics. Ian Wilmut from RAL is here for the week. His help is greatly
appreciated.
Checking drawings for Calum.
Marking up tablecloth for ECDs.
Working with Carol on redlining the cost book. Also talked with her and Norna yesterday
about the proposed items to review for the DRR Update next month.
Met with Mike Gerfen, Dennis, Ian and Calum about the upper structure dip brazing problem. Weld
preparation configurations to assure full penetration welds were agreed upon
and then documented by Calum. He also ran analyses to
confirm that the slight reduction in cross sectional area at the welds, which
was offset by the slight reduction in mass, did not affect the first three
resonant modes.
From: ctorrie
ctorrie@ligo.caltech.edu
Structure
We are back to welding the upper structure. Problems came up with the dip
brazing process for vacuum. The structure will now be chamfered to prepare it
for welding. We have shown in FEA that this should be okay wrt
the stiffness, full results to folllow.
Progress is going very well on the lower structure.
Suspension
Janeen, Norna, Ian and I
have been preparing all of the suspended parts. We now have all of the
suspended stages prepared and assembled!
From: Ken mailand
kmailand@ligo.caltech.edu
Adv. LIGO
I have completed a draft of the pros and cons of doing the Adv. LIGO large
part cleaning and baking work in-house at LLO, vs. outside local vendors,
including costs, and other issues.
Core Optics
From: Helena Armandula
ahelena@ligo.caltech.edu
Advanced LIGO Coating Development
Talked to JMM. Delivery of the TNI mirrors is still
scheduled for the 1st-2nd week in June. Coating calibrations are under
way. He is also manufacturing a container to preserve the coating properties during shipping. As a side note, he informed me that US
customs do not allow wood containers to be shipped to the US from
overseas because of termite problems.
For lower mechanical loss coatings, JMM tried cobalt as dopant;
it did not work well, the optical absorption was very difficult to control, he
discarded this material.
Research is under way with a new alloy. Annealing of this coating produced
some crystallization resulting in higher than desired optical absorption. They
are working with the annealing parameters to improve it.
From: Gregg Harry
<gharry@ligo.mit.edu>
We spent the week finding and fixing some electrical noise problems on the Q
measuring appartus. This is still in progress,
but some improvements have already been made and more are anticipated next
week. We have also begun characterizing a superpolished
sample that has the same CSIRO silica/tantala coating
as the commercially polished one we are measuring now. This will allow
for a direct test of how much the substrate polish effects
the mechanical loss.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
Parts from a faulty high power photodetector board
were salvaged and stuffed onto a new board.
Auxiliary Optics
From: Michael Smith smith@ligo.caltech.edu
No report this week
Other Laboratory R&D
Juri
I’m working on the modeling of
coating thermoelastic noise for finite size mirrors
and the noise reduction using a Flat Top beam. Moreover I spent some time with
Marco for the analysis of experimental data from our cavity.
Chiara
Arrived in Caltech and after the
bureaucratic procedures and informative meetings, I started working with Riccardo on the experimental set-up for taking measurements
of transfer functions of the horizontal attenuation system prototype for the
40m interferometer.
Innocenzo Pinto
Summary of work done at TWG.
Genetic synthesis below 15ppm using
30% less tantala than current LIGO design obtained
(14.5ppm) . Compared to
"nearest" stacked quarter wavelength design yielding comparable
(16ppm) reflectivity cuts tantala 24% off. Compared to "nearest" stacked
quarter wavelength design using same amount of Tantala
outperforms it in terms of transmissivity (235ppm). Trend toward stacked doublet configuration (Tantala equidistributed among
layers, optical thickness each doublet close to lambda/2) observed. Performance almost equivalent. General stacked doublet synthesis explored. Two degrees of freedom (optical thickness of doublet, thickness
ratio Ta/Si). Silica noise
taken into account. Estimated 3% measurement (and process) uncertainty in
Ta/Si loss ratio merges strict optima with those
constrained by condition optical doublet thickness = lambda/2. Universal design curves transmissivity
vs. total noise curves for relevant values f number-of-layers drawn, and
parameterized in Ta/Si thickness ratio (design nomograms). General
relation between coating transmissivity and (infinite
structure) bandgap structure investigated. Hints for
future research (stacked multiplets, more than two
materials, fractal multiplets) singled out. Presentation and paper draft being written.
Marco
Still working on
understanding the beam characteristics of the Gaussian profiles in the MH
interferometer. Switching to the MH mirrors probably in 2
weeks. Creep stationary.
For additional information about this report, contact Stan Whitcomb or Phil Lindquist