Weekly Report for
Week Ending May 12, 2005
The LIGO Executive Committee meeting for May 16, 2005 is
cancelled due to the meting of the LIGO Staffing Committee.
Special Announcements:
Weekly
Report Highlights
LSC Issues (Saulson)
No report.
LIGO Laboratory Administration (Lindquist)
STATUS OF LSC MOUs (Petrac)
(LSC MOU updates for Feb. 15, 2005 through Aug. 15, 2005)
All Attachment updates for all active LSC groups are in the final sign-off
stage/PIsLSC MOUs and
Research Plans and Progress Reports
SITE TELECONFERENCE (Lindquist)
A site teleconference was held on Thursday, May 12, 2005. The following items
were among those discussed:
- Exploratorium
-- Installation of exhibits is covered in the contract for Livingston, but
it is not included for Hanford.
- The
list of assigned actions updated through May 5, 2005 will be found Here.
PROPERTY MANAGEMENT (Chargois)
>From: Ed Chargois <chargois_e@ligo.caltech.edu>
- Nothing
significant to report. Caltech's
campus inventory is ongoing
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
- Continued
participating in the DCC Steering Committee effort. Completed action items from last meeting
of providing access links and references for both Synergy and Agile. Set up several conference calls for the
week of May 23rd with clients from both systems for reference and
questioning by the committee members.
- Met
with Cindy and began planning the SURF orientation for mid-June.
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- packages:
in - 13, out - 8
- faxes:
in - 35, out - 18
- No
special projects to report.
COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman, Salone)
>From: Esther Cunningham <esther@ligo.caltech.edu>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Working
on the maintenance renewal with Pacific Coast Office Products for the fax
machine.
- Followed up on pending deliveries for the
campus and the sites. The Mitsubishi battery backup for LLO is shipping
today.
- Completed
change order #7 to George Stokes and sent out the change to the vendor.
- Completed change order #14 to Venturi Staffing and submitted the change to the
vendor. Received the acknowledgement.
Awaiting for a copy of the current
insurance policy.
- Completed
change order #10 to Southern Enterprises which removed funds of $127.90
from LIGO.EPI 1. The change has been sent and acknowledged by the vendor.
- Made
arrangements for a credit to be issued by Office Depot for an incorrect
item ordered.
- Made
arrangements for the return of the laser to LaserMill.
The credit is expected to be issued upon receipt of the laser.
- Completed the internal modification to
accommodate payment of the 25% prepayment for the clean room module.
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Florence Kaufman <fkaufman>
- Requested
that several new accounts be set up - Tasks 2.14, 3.14 ,
2.2.6, 2.8.27 and 3.8.27.
- Requested
closure of several fabrication accounts.
- Requested
expenditure type correction for misclassified equipment purchase.
- Revised
Budgets to reflect approved change request to reduce budgets for unfilled
labor positions.
- Updating
account number list to reflect various additions and account closures.
- Working
with Gina and Dot to move or close certain encumbrances so that
fabrication accounts can be closed per Managers' requests.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)
>From: irena@ligo.caltech.edu (Irena Petrac)
- Nothing
significant to report (See above).
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- LHO
has determined to install the exhibits from the Exploratorium with their
own staff. Under the terms of the
contract, LHO would have to pay extra for the Exploratorium to provide
these services. The LLO exhibits
include installation and technical support in their pricing.
- The
schedule for the LLO
Science Education
Center has been
revised. The current schedule calls
for completion of a draft 100% drawing package by June 2, a final review
completed by June 10, release of the RFQ on June 13, a job walk on June
29, and bids received by July 12.
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
>
- Continued
to process travel and reconciliations for the Director, and preparations
for the Program Advisory Committee meeting (PAC-18) next week at LLO
>Dorothy Lloyd
- No
report.
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
PROPOSALS and REPORTS (Lindquist)
As mentioned during the Executive Committee meeting on Monday, April 11,
2005 and last week in the status report, LIGO must submit an Annual Report for
Operations by August 1, 2005, and this annual report must be accompanied by a
request for a two year extension (FY 2007 and FY 2008) as well as a
justification for why Caltech/MIT should be continued in the role of management
of LIGO. I have proposed and distributed a general outline and
assignments.
DCC Steering Committee (Lindquist)
The document management system steering committee met on May 12, 2005 to
review the status of actions assigned.
We are in progress on on-line tests of several systems and are also
scheduling teleconferences to check references.
Next week L. Turner will be attending AIIM conference.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
- On
May 9, 2005 the Executive Committee recommended approval of change request
CR-050004 adjusting the FY 2005 budgets to reflect (primarily) actual
costs through the first half of the fiscal year. The change request
will be forwarded to the Deputy Director for approval.
- has
submitted a change request (CR-050005) for DMT Hardware Expansion. I will format and distribute copies to
the Executive Committee prior to the next meeting.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- A
LIGO Staffing Committee meeting is scheduled for Monday, May 16,
2005. The DRAFT agenda for the
meeting has been posted. All files are posted and up-to-date on the
web page.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
No report.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of Commissioning Activities at LIGO Hanford Observatory
(Landry)
Commissioning highlights from
this week in Hanford
are bulleted below, pertaining to general, 4k and 2k issues, respectively.
- Astrowatch in theory: we're trying to include more
detailed information on the state of the IFO(s) and LVEA when archiving astrowatch data to tape, both in elog
and archive comments, so it will be easier to reconstruct the site status
after-the-fact.
- Astrowatch in practice: GRB 050509b,
a Z=.22 burst on Sunday night (gpstime
799646432), found H1 midway through a 22h lock at 4.8Mpc in range (i.e. no
TCS applied). H2 was locked but only in Acquire++ mode.
- the
LVEA leaked a small amount of rainwater
- Optical
lever photodiodes are saturating on many of the optics in the LVEA, so
that we'll install ND filters in front of their lasers. We've been
close to saturation before, so that we might saturate a single quadrant
under poor centering. Curiously, now well centered optical lever
beams saturate multiple photodiodes - possibly related to the temperature
in the LVEA?
4K
IFO
- Photodiode
work has been motivated in part by the discovery of burn spots on ASPDs. Recall that during S4, one fast shutter
was not closing properly and caused burn spots on ASPD2 and 3. This
may be the cause of enhanced sensitivity to acoustic noise during S4: the
IFO becomes sensitive to the beam position on photodiodes. ASPD2 has
been replaced. ASPD3 soon will be. Initially this week the IFO
was running on three photodiodes, as ASPD4 had been turned off (see
previous weekly). Later, ASPD4 was replaced (electronics
problem). The fast shutters were found to be in backwards, and were
to be flipped around.
- Thermal
Compensation System (TCS): the high-power 30W laser (a replacement for the
existing 8W unit) was installed
on the x-arm. Initial concerns that the chiller had insufficient
cooling power were unfounded, as the operating
temperature of the head was in the acceptable range of 18-23
degrees. The TCS annulus beam is thinner than expected, ie. (ro-ri
<< r). First illumination on the ITMX showed that we could at
least recover 6.7Mpc ranges, however, there is a lot more testing to do,
in particular at IFO incident laser powers in excess of 4W into the mode
cleaner. Brief, hour-ish locks at 5W into
the MC, and up to 4W on the TCS, were achieved
and speculated
upon.
- Seismic
upconversion studies: boosts made previously
were tested, and did not cure the upconversion
problem.
2K IFO
- H2
was down for an upgrade to the ISS, bringing the machine closer in line
with the 4k setup. First the beam being sent into the main
interferometer was aligned and centered
on the periscope. Next the ISS was installed and commissioned,
running with a unity gain frequency of 96kHz
(gain = 28dB), and a phase margin of 59 degrees. The IFO returned to
decent inspiral ranges beyond 3Mpc on Friday
night.
- When
the mode cleaner returned to locking after the ISS work, there was
evidence of a shift
in yaw alignment. Strangely, correcting this yaw offset with IOO
WFS increases the power both in transmission and on reflection, something
that is not supposed to happen. Relocking the MC on the weekend
proved problematic:
tandem boots of IOCs and appropriate burt restores seemed
critical.
- ISS
teething problems were observed.
Power levels in the IFO have been drifting
some 10-15% and arm powers have been up at 3000; this was initially
attributed to some quirk of the current shunt/ISS installation, however,
read on.
- The
2k laser power output was measured to be changing by 10%. This
causes problems for the MC, refcav etc.
This problem may require a swapping out of the NPRO (the only spare of
which is the aging unit that is coming from LLO). Through the week
the laser continued to yield mixed performance, running
well at times with stable powers and poorly at other times with
varying power. Photodiode power supply problems may account for
some, or perhaps all, of the problems noted here. A PS fuse was
replaced and we're now assessing the situation.
- MC
WFS continue to be investigated - they're highly variable in gain,
leading WFS2 to be later modified
and replaced
- Local
damping on 2k optics was adjusted
- acoustic coupling was observed to be worse at ISCT10
than ISCT7; worse than S3 by a factor of 2 at certain frequencies.
May be due to ugly beam - structure, clipping, poor overlap.
DAQ
- the IFO Epics status system was moved
back from h0statman to iotardis. A newer,
faster and more reliable h0statman IOC is sought.
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
L1 Interferometer (Zucker)
Several major equipment upgrades in progress, so far mostly
successful:
- The
CDS network and switch hardware was upgraded to GigE
- One
new framebuilder is in place and the second is
under construction.
- The
new fiberoptic CDS timing system was installed
and full characterization done of the previous system and the new one. At
this writing the new system's timing performance is poor and not
understood. We are maintaining both setups in parallel so we can switch
back and forth.
- The
main laser was pulled out and shipped back to Lightwave
for emergency surgery (it was limping due to a suspected diode failure a
couple weeks ago). We installed the hot Hanford spare, since our LLO spare was
itself anemic (Thanks Doug and Rick!). New laser has loads of juice; we
are back on track to explore the realm of high power.
- The
AWG equipment was installed at the end stations to support the photon
calibrators.
- After
some more timing system diagnostics, Rolf and Alex are geared up for
upgrading the LSC code to the newest rev this weekend.
Education and Outreach (Thacker)
- Completing
preparations for LEPAC meeting 5/20;
- Completing
preparations for LEN meeting 5/21;
- Participated
in AAPT organizational meeting at LLO; provided minutes
- Completing
preparations for exhibit training at LLO 5/18 & 5/19
Site Safety and Security (Riesen)
Nothing of substance to report this
period.
Mechanical Engineering (Spjeld)
AdL Quad SUS Installation Fixtures
- FEA
of transport table with additional side loads complete
- Completed
advisory comments based on design review issues
- Modifying
models to reflect standard Al I- and T-beams
- Looking
into using an alternative distributor for linear drives
- Detailing
of machine drawings in progress
AdL SEI Engineering
- Review
of tolerances and off-the-shelf parts on Ad SEI drawings in progress
General Engineering
- Redesign
of HAM door removal tool in progress
LLO General Computing and LIGO Computing Security (Roddy)
Helped install the CDS networking hardware last Thursday. There were a couple of issues with the
installation, but overall it went smoothly.
This reminded me of the importance of having a dedicated laptop with all
necessary cables to interface with the various networking hardware on
site. There was a long delay while we
figured out which cable was needed to interface with the switch. There were a few problems bringing up some of
the CDS computers due to NFS cross mounts, etc.
Had some GC issues that coincided with the timing of the CDS network upgrade
that originally was suspected to be related, but later found not to be. It was originally thought that the Fore box
that provided an interface to the LVEA GC computers was the culprit and was
disconnected, but later found not to be the issue. The problem seemed to go away when the Fore
box was disconnected but appeared later that afternoon. I then switched to a different network card
on the router and rebooted after editing the appropriate files, which also
seemed to fix the problem, however the problem appeared again over the
weekend. After coming in to
troubleshoot, I suspected a bad port or GBIC on the core switch on GC. When I moved the interface to different
port/GBIC, the problem resolved itself and has not appeared again.
Had a discussion with Rai, Dave, Harry O., Rolf,
and Rusyl about the logical network placement of
several machines including the RGAs, beam centering,
FMCS, etc. It was decided that for machines
that do not provide active feedback into the CDS system, they should be removed
from CDS and/or GC and placed into a dedicated private network which would be
NAT routed to the internet. This
provides a layer of security while still allowing them to get updates,
etc. Also, this removes a fair amount of
"threat" to the CDS system and simplifies things greatly.
Various user support issues as usual.
Setup a laptop for Bonnie. Helping her with the Macromedia software and a few of its quirks so
she can continue developing the replacement web page(s) for LLO.
Need to schedule some downtime on the border router at LLO so as to install
another network card and change the configuration on one card. This will change
the number of net cards the OS sees and as such will require
reconfiguration. Should
be approximately 30 minutes downtime.
Working with Dave on the long term configuration of the
CDS VLANs and possibility of incorporating the GC
LAN.
Working with Dave also on setting up an "out of band" VLAN and LAN
for network devices, including the CDS switches so as to remove TCP/IP
connectivity from them on the CDS network.
This will likely be coordinated with the additional private LAN for the
RGA machines, etc.
Fixed some issues with the Maple installation here on the
Suns.
Ordered a list of various hardware, etc.
HPLF, Optics Modeling, Data Analysis and L1 Commissioning (Franzen)
1) HPLF
news: Last friday I tested
the laser for the first time since it was returned to LIGO Livingston.
Unfortunately, the outcome was not good. After slowly increasing the pump
current to its maximum value and waiting for ten minutes, I heard the the fan sound change its characteristics and a sudden
spark. While ramping down the current I started to smell that something was
burning. During the following telecon with IPG Photonics we were informed that it will
probably not help to change output wavelength from 1064 nm to 1070 nm. The
laser has now been shipped back to IPG for diagnostics.
2) I
have been helping out Peter King with the PSL laser swap out and continued my
study of the PSL table power losses.
3) Continued
to think about how to implement a REFL port beam drift compensation system.
CDS software (Khan)
no report
LDAS/Condor Sysadmin and Burst Analysis (Yakushin)
Data storage/Condor/LDAS admin:
1) Tracked
down the problems with LSCdataFind (reported last
week) to incompatibility of LSCdataFind client with
the following setting (needed by gridFTP): export
GLOBUS_TCP_PORT_RANGE=40000,45000 One possible
solution is to wrap LSCdataFind in a script that
unsets GLOBUS_TCP_PORT_RANGE.
2) /frames
and /dmt file systems are in the process of being
reconfigured to better support small files.
3) Transferred
SG6_S4, SG15_S4, SG17_S4 burst MDC frames from PSU. Transferring the second version of GEO S4
frames to LLO.
Data analysis:
1) Reran
waveburst using the newest science segment list on
DARM_ERR, h(t), AS_Q. Comparing the results.
2) Modifying
waveburst scripts to run on the new MDC frames
produced by PSU.
3) Preparing
for the waveburst review meeting next week.
Initial LIGO Detector Science & Engineering
(Coyne)
from Dennis
Coyne
CDS
see also the CDS weekly meeting
minutes in the commissioning
archives
CDS Software
no report
CDS Hardware
Fiber Optic Timing Link (Sander)
- Installation
at LLO has started.
DMT
PSL
PeterKing
- Lee packed
up 10-W laser S/N #119 for shipment to Lightwave.
- The
high power photodetector testing
continues. No problems so far.
Optical Contamination Cavities
Lee Cardenas, Liyuan Zhang
OTF Lab. (W. Bridge)
Cavity # 1
We have a set of 70ppm REO mirrors introduced into the cavity. Cavity is
locked. The laser power is the same
134mw. The ring down is
21microsecond. Absorption measurement is
in progress.
Absorption Test Measurement prototype in progress. New alignment completed and both HeNe and Nd:Yag
laser. Beam meets at one point on top of
the mirror surface. Absorption test
performed on the 4ITM05 mirror -- please check here
for results.
Scatterometer system in standby
The Quantronix 60 watt laser In progress
Major! water leak from the supply line from the
building, It flooded the lab. It has been taken care of already. The laser
power supply got wet and it shorted out.
We have replaced some of the burned cables and the main circuit breaker
got damaged. Have
restored operation of the 30W laser as of Thursday evening. In the interim (fearing that the laser would
take time to restore, the ITM optic has been moved to the Fizeau
interferometer for measurement.
OTF Lab at Lauritsen ROOM 38 No Change!
Cavity #3
The contamination test for (20) pieces of Glenair Micro-D-connectors still in progress. Cavity is locked and we are taking measurements for
absorption and ring down. So far so good. Two
more weeks to go before test to be completed.
Cavity #2 no
change
40 Meter Interferometer (Weinstein)
The 40 meter Technical Advisory Committee (40m TAC) met on Thursday. Osamu
presented a status report: see: http://www.ligo.caltech.edu/~omiyaka/20050513_40m_meeting.ppt, http://www.ligo.caltech.edu/~cit40m/Docs/20050513_40m_meeting.pdf
Thermal Noise Interferometer (Black)
In our last report, Akira had achieved first lock in the bond-noise
experiment. However, there were some oscillations in the servo. He has since
made some changes to the servo and now it behaves quite well. The pendulum oscillations
are reduced considerably by the feedback. There is plenty of phase margin at
the unity gain frequency (25 Hz at almost the maximum gain), and he managed to
take a clean transfer function by relocating the summing junction. He is now in
the process of pumping down to take data on steel wires in vacuum.
LASTI (Ottaway)
Laurent Ruet reports:
I tested the vertical new control loop (estimator + modal control) on our
triple pendulum here. The damping worked perfectly and exactly like we
expected, the re-injection of noise has not been tested yet since we need to
find a procedure to test it correctly.
While doing these tests, I notice we probably have a part rubbing on the pendulum,
I can use the osems and an offset as a temporary
solution, but we'll need to open the tank and check that.
I am now trying to use the control loop for the longitudinal and pitch direction....Unfortunately
I have to figure out the method once again since this case is a lot more
complicated than the previous one, the coupling between rotation and
longitudinal motion makes the situation a lot more complex and the fact the
modal matrix is very ill conditioned and is difficult to solve (in simple words
I have a lot of trouble separating rotation from translation in the control).
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
Weekly Physics Meeting
We mainly discussed the current
work and future plan for the input optics simulation being done by Sany Yoshida nad
his group. Specifically, we discussed results obtained for the effect of motion
of mode-matching telescopes on fields in the interferometer.
SimLIGO and FFT work
(Biplab)
Studying how exactly Quadrant Photo-diodes work in conjunction with the regular
Wave-Front-Sensors (WFS) to control beam-direction and beam splitter motion.
Another related question is: how beam shifts in transverse direction could
affect the interferometer performance in various possible ways.
With Rana
discussed FFT results for WFS 2, 3 and 4: After the improvement in WFS1 at LLO,
do we need to tune Gouy phases in other WFSs as well to reduce possible mixing of signal
contribution of the target degrees of freedom with that of other unwanted
degrees of freedom? Rana thinks the mixing is not so
much of a problem as long as the inversion of sensing matrix can be done.
Simulation of 40 meter interferometer
(Monica) Error signal sweeps
have been reproduced with e2e simulation for DC response in order to compare
them to Twiddle ones. The agreement is good in the
linear region of the error signals; there are still some mismatchings
due probably to the arm length used in the simulation. Up to now sweeps have
been done with a shorter arm (4m); longer arm (40m) takes longer time but
simulations with the real 40m setup will be perfomed
as next step.
modeler
(Hiro)
Continued work on improvement of modeler code.
Alfi
(Bruce)- Continuing work on new
implementation of bundle generated connections.
- Adding the capability to define expected bundle
content at bundle input ports on otherwise unconnected root base boxes.
(Melody) Continuing
on fixing existing Problem Reports.
- Currently
working on the user interface for allowing the user to choose the display
for nodes: graphic, node name, or a
multiline description.
- Worked
on allowing box file nodes to be able to display an icon (jpg or gif).
Data Analysis Activities (Lazzarini)
Creighton:
I fixed a bug in the LAL 2d
mesh tiling routines, changing a < comparison to <=. Occasionally, when two
independently-calculated numbers happened to be nearly equal, the code would
get stuck in an infinite loop.
Mendell:
Joe Betzwieser
and I have worked to validate the StackSlide code
using fake data sets that are for the times and duration of the S3 and S4 runs.
We are working on further validation using the S3 HW injected pulsars in the
real data. I have put a report on our progress on the pulgroup
S2
StackSlide Investigations page.
Shawhan:
- Continued
studies of "light dips" during the S4 run, comparing them
against KleineWelle triggers to evaluate veto
efficiency and success ratio for various dip size thresholds.
- With
Gaby Gonzalez, made final corrections to the S2 binary neutron star inspiral paper before its posting as a gr-qc preprint.
Sutton:
My limited time at work over
the past week was split between LIGO-TAMA and theory work on network
analyses. For LIGO-TAMA I set up a small
web page detailing the TAMA data conditioning, which was the last significant
issue the review committee was concerned about.
I also updated and distributed the LIGO-TAMA bursts paper. The main
change was to quantify the uncertainty in the efficiencies and their effects on
the upper limits; this was done with Laura Cadonati. Finally, with Lazzarini
and Tinto I've made some progress on understanding
"optimal" methods for coherent network searches for bursts.
Yakushin:
1) Reran
waveburst using the newest science segment list on
DARM_ERR, h(t), AS_Q. Comparing the results.
2) Modifying
waveburst scripts to run on the new MDC frames
produced by PSU.
3) Preparing
for the waveburst review meeting next week.
Lazzarini:
Held a brief
meeting of the Calibration Committee to review status of S4 calibration.
An interim S4 v2 release will be available very soon.
Continued working with Sutton
and Tinto on the extension of the Gursel-Tinto
algorithm to arbitrary network dimensions. We identified a statistic made up of
the N(N-1)/2 detector cross correlation pairs that can
be used to serve both as a threshold detector and a soruce
localization algorithm.
LIGO Data Analysis System
Software Systems (Maros for Blackburn)
*LDAS:*
Work continues on cmonClient to improve its handling of resource variables.
Included in these changes are PR2724 which deals with the modifying of resource
variables, PR2617 which deals with displaying of column headers, and PR2336
which deals with sorting columns based on selecting a column. Currently these
changes are on tandem-iii for evaluation.
The command used by cmonClient to retrieve information from the diskcacheAPI about existing segments of data has been fixed
(PR2825). The "Cache View" tab will now display the correctly when
communicating with a diskcacheAPI that has the
correction.
The weekly system testing of
LDAS was done on ldas-1.5.66 and the web pages were updated with the results.
*TCLGLOBUS:*
Many of FTP client test cases
have been reworked to use a more informative debugging model which allows the
level of debugging to be set via the environment variable TEST_VERBOSE_MODE.
With this rewrite, many negative test cases where used to ensure the correct
error message was being generated and reported
properly.
The web pages have also been reworked to fix
navigational inconsistencies. Also, a page was added describing the alpha
(0.1.0) release of TCLGLOBUS.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Finished
getting new S2 RDS frames to tape at CIT/LHO/LLO.
- Continued
to reinstate dual copy at CIT, still ongoing.
- Working
on getting some "missing" (at CIT) data (E10/M5/postS3) from LHO
using tar/globus-url-copy. Getting close to done with this.
- Created
a bunch of grid accounts and closed out these (and other) tickets with the
Penn State problem tracking system.
- Handed
off the clean up of all gridmap-files to Phil;
gave him the "addgriduser" script so
he'd know where the various grid-mapfiles live.
- Fixed
weird NFS(?) problem on CIT ldas-grid
where reading files in /archive would hang even after they were on
disk. umount/mount fixed it.
- Installed
SAM-QFS 4.3.11 on samtest (Solaris 10) and began
testing.
(Phil Ehrens)
- Adopted
responsibility for host and datarobot
certificate renewal of LHO grid capable machines.
- Adopted
responsibility for grid-mapfiles of LSC machines
and began drafting specification for grid-mapfile
installation and propagation of grid user infrastructure. There are still
some areas of this that I don't quite understand, but I am making good
progress.
- Worked
with Stuart Anderson to analyze and fix various hardware issues in the
LDAS-DEV, LDAS-TEST, and LDAS-CIT systems.
(Stuart Anderson)
- Help
with Solaris 10/10GigE/SAM-4.3 testing at Caltech.
- Started
transferring GEO S4 version 2 calibrated frames.
- Kept
up with several Caltech cluster maintenance issues.
Livingston
(Igor Yakushin)
- Tracked
down the problems with LSCdataFind (reported
last week) to incompatibility of LSCdataFind
client with the following setting (needed by gridFTP):
export GLOBUS_TCP_PORT_RANGE=40000,45000 One possible solution is to wrap LSCdataFind in a script that unsets
GLOBUS_TCP_PORT_RANGE.
- /frames
and /dmt file systems are in the process of
being reconfigured to better support small files.
- Transferred
SG6_S4, SG15_S4, SG17_S4 burst MDC frames from
PSU. Transferring the second version of GEO S4 frames to LLO.
Hanford
(Greg Mendell)
- Targets for nodes, air conditioning, and power for
the LHO LDAS cluster for S5 have been set. I will be working Richard
McCarthy, John Worden, and LIGO and local consultants to finalize the
plans to meet these targets this summer.
(Ben Johnson)
- I
have gotten the astrowatch archiver
to e-log the segments and comments submitted by the operators. I still
need to implement a timeout facility, and at least bring the auto e-log
mechanism down to Livingston.
- Working
on getting the publishing script to make its segment publication choices
to be made a la the createRDS scripts. This will
allow it to publish non-sequentially.
- Reading
up on the new 3510/3511 firmware. I particularly like the sound of the new
"check media" command. It may be much lower impact than
"check parity". It's similar to the 3ware function, but the
manual says that it will regenerate parity if a block on a single disk is
bad.
- Rebooted
a down node (47), which had "bad DIMM" symptoms, though it
rebooted properly on a powercycle.
General Computing (Wallace)
MIT:
(Keith)
Nothing to
report.
Livingston:
(Shannon)
- Helped
install the CDS networking hardware last Thursday. There were a couple of issues with the
installation, but overall it went smoothly. This reminded me of the importance of
having a dedicated laptop with all necessary cables to interface with the
various networking hardware on site.
There was a long delay while we figured out which cable was needed
to interface with the switch. There
were a few problems bringing up some of the CDS computers due to NFS cross
mounts, etc.
- Had
some GC issues that coincided with the timing of the CDS network upgrade
that originally was suspected to be related, but later found not to
be. It was originally thought that
the Fore box that provided an interface to the LVEA GC computers was the
culprit and was disconnected, but later found not to be the issue. The problem seemed to go away when the
Fore box was disconnected but appeared later that afternoon. I then switched to a different network
card on the router and rebooted after editing the appropriate files, which
also seemed to fix the problem, however the problem appeared again over
the weekend. After coming in to troubleshoot, I suspected a bad port or
GBIC on the core switch on GC. When
I moved the interface to different port/GBIC, the problem resolved itself
and has not appeared again. -Had a discussion with Rai,
Dave, Harry O., Rolf, and Rusyl about the
logical network placement of several machines including the RGAs, beam centering, FMCS, etc. It was decided that for machines that do
not provide active feedback into the CDS system, they should be removed
from CDS and/or GC and placed into a dedicated private network which would
be NAT routed to the internet. This
provides a layer of security while still allowing them to get updates,
etc. Also, this removes a fair
amount of "threat" to the CDS system and simplifies things
greatly.
- Various
user support issues as usual.
- Setup
a laptop for Bonnie. Helping her
with the Macromedia software and a few of its quirks so she can continue
developing the replacement web page(s) for LLO.
- Need
to schedule some downtime on the border router at LLO so as to install
another network card and change the configuration on one card. This will change the number of net cards
the OS sees and as such will require reconfiguration. Should be approximately 30 minutes
downtime. Working with Dave on the
long term configuration of the CDS VLANs and
possibility of incorporating the GC LAN.
- Working
with Dave also on setting up an "out of band" VLAN and LAN for
network devices, including the CDS switches so as to remove TCP/IP
connectivity from them on the CDS network.
This will likely be coordinated with the additional private LAN for
the RGA machines, etc.
- Fixed
some issues with the Maple installation here on the Suns.
- Ordered
a list of various hardware, etc.
Hanford:
(Christine)
- Network
usage can be seen at
http://www.ligo-wa.caltech.edu/~christin/mrtg/198.129.208.1_198.129.78.122.html
- Things
are moving forward on the new network connection. Our current contract is being extended 3
months. I have the first bid for a
backup provider and two more companies have asked for information to bid
on the backup. The time for cut
over to the new GigE network is now August.
- Investigated
pricing and lead time for a 10/100 card for the main router which would
be used to connect the proposed backup 10 Mb path.
- Started
preparing for the SURF student arrivals.
One student arrived this week the others show up mid June.
- Helped
a user migrate his e-mail from his old computer to his new laptop.
CIT:
(Veronica)
- LSC: Updates to the June meeting
website. Working on the
registration page script. Working
with MIT on the redo of the website.
- LIGO: Roster database troubleshooting and
updates. Website updates.
- CaJAGWR: Website
updates and user support.
(Mike)
- Visitor
Workstations: I loaded, and setup 5 workstations this week for surf
students. This includes loading OS and all General Computing Software.
- Continued
to work the Spam filters with Larry Wallace.
- I
swapped out the printer from the 2nd floor W/B. This got replaced with DCC's old 8550 printer. Ed Chargois
gave me a hand with this. This also included, me having to reload print
drivers for all users on the 2nd floor.
- Continued
to burn ghost images to DVD. These images are from the NTSRV'S.
- Started
loading additional computers for surf students.
- Move
equipment around in cubicles to make room for surf students. We ended up
turning in some of this equipment to CIT.
- Calum Torrie: I installed
Solid Works 2005 for him. This is for testing purposes before I upgrade
all our Solid Works users to 05.
- Much
other user support that mostly included software,
and some OS issues.
(Larry)
- Placed
a number of procurements to replace computers in the Computer room in
Bridge Annex. Both Unix and Windows based
machines.
- Performed
a couple of network tests using a cell phone as a modem. Thanks to Barry
and Dennis for letting me use their phones. The network service provided
with their cell phones worked out better than planned. The access rate was
better than our regular dial-in service. Installation of the s/w though is
a long and tedious process.
- With
the modem pool going down on a regular basis, we are now checking it daily
to make sure it is up and running. Unfortunately, the problem only shows
up when trying to dial in, so checking via the network doesn't really let
us know when there is a problem with the system.
- Assisted
a couple of users recover their systems after they had crashed out of
them.
- Worked
a couple of logistical issues concerning the power outage for this
weekend. Also, involved in working out air-conditioning issues for the
computer room. The PMA group is working on getting additional air put in.
- Moved
a number of systems around to different offices. Started moving E2E
machines to a office with air-conditioning. We
will move the application server this weekend.
- Moved
old equipment that is to be turned-in to CIT to a central point for
pickup.
- Took
care of a couple of printer problems. Hardware reset on the printer and in
a couple of cases modification of the print driver and setup for the enduser was needed.
- A
number of meetings with the DCC group. Mostly, looking at possible
applications to be used for the new DCC system.
- Worked
with Mike on the spam filters. This last week was a lot better in that we
spent a lot less time going through them than the week before.
Mail Statistics May 05 - May 11, 05
Reject
Messages 16,134
Virus
Messages 1,290
False
Positives 261
Accepted
Messages 18,429
Total
Messages 34,563
Advanced LIGO and Supporting R&D (Shoemaker)
Systems and Management
Adv. LIGO Systems
from Dennis
Coyne
See also:
AL Systems web
page
AL Systems email archives
Planning
Carol Wilkinson and Dwight Carter continue to work on scrubbing/revising the
construction project cost estimate.
Records Of Decision or Agreement (RODA)
See also the RODA status web page
Requirements
Interface Issues
See the "Interfaces" section of the AL Systems web page
- Continuing
coupled SEI/Quad dynamics analysis in modal basis -- a report is being
prepared.
- A
small group (GariLynn Billingsley, Dennis Coyne,
Peter Fritschel, Bill Kells,
Mike Smith, Phil Willems)
have been working on establishing the size of the beamsplitter
and are close to a recommendation. A report will be issued in a couple of
weeks.
Reviews/Meetings
- Held
a monthly systems meeting; meeting notes to be posted soon
- Held an quadruple suspension installation fixtures review.
Review notes will be issued soon by the chairman, Doug Cook. Good review
with a go-ahead to build prototypes after some minor issues &
suggestions are addressed.
- Peter
Fritschel is arranging a 3-day Systems meeting
at Caltech in the week of July 11th. Topics will include: Stable recycling
cavities, CDS infrastructure, Lock acquisition & modulation scheme,
Modeling of power induced instabilities, and Reassessment of HAM seismic
isolation requirements..
Seismic Isolation
From: Ken Mason <kmason@ligo.mit.edu>
We have several efforts going to measure and model the BSC structure to
better understand the ground noise amplification in the piers. Rich Mittlemon is making measurements between the ground, pier,
and chamber. He has posted his results on the LASTI Ilog.
We have also created a finite element model of the BSC structure which will
allow us to see the effect of structural changes. The finite element model was
originally created in Algor. We converted the model
to Nastran after finding out that Algor's
dampers did not work and we could not create transfer functions.
Suspension
From: Janeen Romie
<romie_j@ligo.caltech.edu>
Checking drawings for Calum.
Finished a tablecloth dummy assembly and detail drawings for
the ETF quad. Calum has reviewed them.
Participated in the follow-on installation fixtures review last thursday.
On Friday, I met with Carol, Peter F., Mike Smith and others about the
costing for the production input and output mode matching telescopes and input
and output mode cleaners. I've submitted redlines to the cost book per the
decisions of the group and forwarded them to Jay for redlining the production
electronics. The decision was made to change the cost book to reflect a
monolithic output mode cleaner design and to add one more suspended photodiode
and one more SOS-based input mode matching telescope. I'm working with Carol on
cost book details.
Met with the design team on Friday concerning the
interface ring design between the upper and lower structures. The
meeting was useful and all problems seem to be ironed out, with no changes to
the upper structure drawings, which are with the machine shop now.
From: ctorrie <ctorrie@ligo.caltech.edu>
Weekly Report (2 weeks)
Upper Structure
Preparing drawings / parts now that we are going to dip braze the structure.
Remaining parts for the c-ptype
With Russell Jones moving onto CO2 laser work in Glasgow I have been working to finish off the
parts associated with the lower structure assembly. this
should be completed by Friday. I am also working with Tim Hayler
and the rest of the suspension team on the remaining drawings and parts for the
suspension parts, deadline of Friday.
Lower Structure face plates
These are currently being made by a local machine shop.
Visits
Ian Wilmut and Norna are
visiting next week
From: Ken mailand
<kmailand@ligo.caltech.edu>
The installation arm fixture document T050073-00 with added recommendations
from the Wednesday 5-4 meeting included, was sent to
the DCC out ref. T050073-01.
I’m working on a report for the large item cleaning / baking station. The pros and cons of doing the work in-house at LLO, or contracting
the work to LA local vendors, including costs, and other issues.
Core Optics
From: Helena Armandula
<ahelena@ligo.caltech.edu>
Generated a procedure to be used to qualify the new large
oven. At this time is being reviewed by Ken Mailand.
From: Bill Kells <kells@ligo.caltech.edu>
All ongoing issues I am participating in looking at:
- focusing
PRC
- full modeling [validation] in FFT by Dominquez hill
group.
- ongoing understanding of the net HR loss: the
scattering mystery.
- Now
we have a gold mine of data from the testing of H1 ITM replacements.
- this is being continually siftted
with an eye toward Adl requirements: loss
cleaning, scatter.
- Identifying
coatings that satisfy both the Adl Q and optical
loss requirements.
- Looking
once again at HR uniformity an figure specs. vis a vis
Rick S. recent g factor variation measurements. What does this mean for
us?
etc. etc.
From: Gregg Harry <gharry@ligo.mit.edu>
We have finished measuring modal Q's on the CSIRO silica/tantala
coating that was made using xenon ion bombardment rather than the usual argon.
MODE FREQ.
(Hz) Xenon
Q Argon Q (for comparison)
Butterfly 2697.6 3.17 10^5 4.4
10^5
Drumhead 4075.7 2.68 10^5 3.3
10^5
2nd
Butterfly 6143.0 3.35 10^5 4.0 10^5
12 9434.6 2.68 10^5 4.1 10^5
13 9438.3 2.65 10^5 5.5 10^5
It was hoped that the heavier xenon ion bombardment would result in a denser
coating with reduced mechanical loss, but clearly the opposite happened (for
the mechanical loss). The microstructural reasons for this are not clear.
We will continue to look for a few days more for any higher modes, just for
fun (to better bridge the frequency gap to the lowest mode of the thick sample
at 20 kHz), while waiting for the zero stress coating from CSIRO. We also will continue measurements on the
commercially polished CSIRO silica/tantala coating.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
I went over the PSL costing sorting out which items fell into the Lab's
scope according to category. In addition
the currency exchange factor was updated.
A stab was made at the spare components necessary for the 200-W laser.
Auxiliary Optics
From: Michael Smith <smith@ligo.caltech.edu>
BS DIFFRACTION LOSS
The geometric and diffraction losses caused by bonding flats on the BS
appear to be negligible, with reasonable flat dimensions. With BS dimensions D
= 370 mm and t = 60 mm, a vertical flat with a 7.5 mm radial cut, results in
approximately 20 microwatt power loss in the transmitted arm with the signal
recycling mirror input, and approximately 5 microwatt power loss with the power
recycling input for a 1 W input to the IFO.
Adding a lens element at the reaction mass (RAM) in front of the ITM to
reduce the spot size at the BS is not a good idea. The RAM lens (plano-convex, with R = 9m) steers the beam at the ETM
significantly: 0.1 mm displacement of the input beam at the RAM results in 20
mm displacement at the ETM.
SURF
I am making preparations for the two SURF projects this summer: optical
lever receiver, and BRDF measurement. I have not been able to locate a lock-in
amplifier to borrow.
Other Laboratory R&D
From: "Erika D'Ambrosio"
<ambrosio@ligo.caltech.edu>
Marco (11May)
Working on the servo loop implementation. I added
an integrator stage in the previous servo amplifier already used to side-lock
the cavity. Then it was locked on some high order modes; the transmitted signal
was very noisy or very weak. We didn't yet find a good compromise. Pushing the
mirrors by piezo actuators the cavity alignment was
definitively lost: it seems to me that the applied stress modifies the mechanical behavior of the mirror
alignment system (in other words, pushing the mirrors we are loosing the
elasticity of the mirror support).
Juri
I'm working on the calculation of coating thermoelastic
noise for finite size test masses when a flat top beam is used to read the
mirror surface position; this analysis is part of the planned investigation in
the study of the thermal noise suppression using flat top beam, which was
presented in the Aspen 2005 GWADW conference.
For additional information about this report, contact S. Whitcomb or P. Lindquist