Weekly Report for
Week Ending May 5, 2005
The LIGO Executive
Committee Agenda for Monday May
9, 2005 will be:
(Meeting time: 10:30 am Pacific Time)
- Announcements
- Comments on Weekly Report
- LSC Issues (Saulson)
- LIGO Lab Operations
- Administration
(Lindquist)
- Sites (Raab,
Zucker, Shoemaker)
- Commissioning
(Fritschel), Detector (Coyne)
- Campus Research
Facilities
- 40 Meter
(Weinstein)
- TN, ( Libbrecht)
- LASTI (Shoemaker)
- Data Analysis and
Computing (Lazzarini)
- R&D and Advanced LIGO
(Shoemaker)
- CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION AS NEEDED
·
CR-050004 Adjusting FY 2005 Budgets to
Reflect Actual Costs through First Half
Special Items:
Special Announcements:
Weekly
Report Highlights
LSC Issues (Saulson)
no report
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Petrac)
LSC MOUs and Research Plans and Progress Reports
(LSC Attachment updates (for Feb. 15, 2005 through Aug.15,
2005) and Progress Reports through Feb. 15, 2005)
- Attachment
updates for all active LSC groups are in LSC/LIGO sign-off/Saulson and
Barish
- Progress
Reports for all active LSC groups are in DCC for web posting.
SITE TELECONFERENCE (Lindquist)
A site teleconference was held on Thursday, May 5, 2005. The following
issues were among those discussed:
- Budgetary
Issues -- Expenditures through April total approximately 15 million
which effectively represents half way point due to time lag. Still running less than same period last
year mostly due to HEPI expenditures last year. Labor running at about 85 percent of
budget to date. Difference is
primarily in contract labor.
Projection to end of year is $30 million plus non-recurring charges
(Amaldi,
- Advanced
LIGO, special Observatory maintenance items, et.)
- Action
#130 -- TAX Tree is done, but has not yet been sent.
- Action
#131 -- Convenience Check limits have been increased to be more
consistent with P-Card limits.
Action CLOSED.
- Safety
Audit at Hanford -- Completed.
Considered productive.
- The
list of assigned actions last updated May 5, 2005 will be found Here.
PROPERTY MANAGEMENT (Chargois)
>From: Ed Chargois <chargois_e@ligo.caltech.edu>
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- packages:
in - 16, out - 6
- faxes:
in - 25, out - 28
- No special
projects to report.
COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman, Salone)
>From: Esther Cunningham <esther@ligo.caltech.edu>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Completed
change order #32 to Excel and submitted it to the vendor and received the
signed copy back.
- Completed the Purchase Order to TPS for
the convection oven for the 40M Lab.
- Completed
the Purchase Order to Datum for the face plates for Calum.
- Followed
up with the vendor on the cancellation request of the laser purchased for
Laser Mill which had already shipped to Caltech. The vendor is still in
the process of getting back to me on the request for order cancellation.
The order has been billed to my credit card.
- Completed
change order #15 to Sydney Meshkov and sent out the revised consulting
agreement.
- Submitted
the monthly Purchase Order closeout report for April 2005.
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Florence Kaufman <fkaufman>
- Completed
and sent out the reports for the following Awards as of the end of April
2005:
- FY2005
Operations
- Visitors
Award
- Outreach
Award
- MIT.GRID
- Low
Noise
- DIA
- AJL.INT
- Prepared
schedule for budget modifications for unfilled positions for the second
quarter of FY2005.
- Prepared
Cost Transfer to correct travel expenditure in the 40 Meter fabrication
account.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)
>From: irena@ligo.caltech.edu (Irena Petrac)
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- Evaluation
of the exhibits to be provided by the Exploratorium is being conducted to
divide them into two groups. This
is being done because the LLO Science Education Center will not be ready
to have the entire complement installed.
When the quantity configuration has been agreed to, a contract
modification will be issued reflecting the change and the payment terms.
- The
SEC architect, EDR, has compiled a list of eight contractors to receive
qualification statements. Five of
the contractors have worked previously with EDR, and three were
recommended by an architect in the area, Holly and Smith. When the qualification statements are
received, they will be reviewed and the contractors to receive the RFQ
will be selected
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
>
- Planning
and reconciling many challenging trips for Barry.
>Dorothy Lloyd
- No
report.
- Jim continued
with data entry in the LIGO database and helping out in the DCC.
PROPOSALS and REPORTS (Lindquist)
We “pushed the button” on the Visitors Program Annual
Report. The NSF has accepted the report
and approved our funding for the next year.
As mentioned during the Executive Committee meeting on Monday, April 11,
2005, LIGO must submit an Annual Report for Operations by August 1, 2005 and
this annual report must be accompanied by a request for a two year extension
(FY 2007 and FY 2008) as well as a justification for why Caltech/MIT should be
continued in the role of management of LIGO.
I have proposed and distributed a general outline and assignments.
DCC Steering Committee (Lindquist)
The document management system steering committee met on May 5, 2005 to
regroup, evaluate where we stand with regard to the systems that have been
demonstrated, and to plan where we should go from here. We are currently favoring two vendors,
Synergy and Agile. Agile is
significantly pricier than Synergy but offers engineering oriented features
that we may or may not be able to use effectively. The next step is to contact some references
and run further hands-on tests of the two.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
- I
have distributed change request CR-050004 adjusting the FY 2005 budgets to
reflect (primarily) actual costs through the first half of the fiscal
year. I propose to discuss this
request during the executive committee meeting scheduled for Monday, May
9, 2005.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- No
special activities to report.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
Completed a successful safety audit of the LHO. Several important agreements were achieved,
including a new "policy" for use of Work permits at the LHO and the
definition of an "eye-safe" power "threshold" for
"scattered-source" beams.
Also, the remaining open items from the 2004 safety audit were discussed
and "closed" at the 2005 audit meeting. However, the latest audit did generate a new
list of action items, which will be distributed next week along with a draft
audit report.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of Commissioning
Activities at LIGO Hanford
Observatory (Landry)
Commissioning highlights from this week in Hanford are bulleted below, pertaining to
general, 4k and 2k issues, respectively.
- Selected
epochs of Conlog data have been archived
(excluding science and engineering runs). This saves disk space but
may impact
selected queries on times older than six months.
- Astrowatch: data are archived periodically based on
the IFO "up" bit, an indicator that the IFO is in near-science
mode ("everything but setting the science mode flag has been
done"). Recently the up bit has not
been set, owing to the PSL out of nominal status. We have to fix
the PSL and ensure the robustness of the up bit so as to not unnecessarily
limit Astrowatch data. Later, the up bit
definition was temporarily modified to exclude the PSL status field.
- A
document on S4 correlations between 2k and 4k AS_Q channels, and
correlations between AS_Q and PEM channels, was posted.
Coupling observed between IFOs is predominantly
acoustic.
- The
spare PSL laser was sent to LLO as the main laser there spontaneously
dropped in power and needed service
4K
IFO
- Photodiodes
on ISCT4 were serviced. ASPD2 was replaced.
ASPD4 was problematic
in a way different from other PDs: in sweeping
the alignment of the beam onto the photodiode, good and bad regions were
not found, as was observed in PDs with burn
spots. While the dominant noise was shown to be upstream of the demod, the anti-aliasing board was also suspect.
- The
new 30W CO2 TCS laser has arrived, and preparations are underway for
installation, alignment and commissioning. Upcoming tasks regarding
the upgrade from 8W to 30W are bulleted in the following work
permit
- A
comparison of data from various (old) 4k locks, with different thermal
compensation status are summarized
here
2K IFO
- After
the current shunt was replaced last week, the next task on upgrading the
2k PSL was to install the latest version of the ISS. This was
started in the latter half this week, and necessitated modifications and
alignment to the optical layout on the PSL table (including revamping the
MC power-in PD path), so the task is taking a little longer than initially
expected.
- Work
started on the IOO WFS: phases and setup of the PDs
was varied and different from other configurations that it was suspected
something was either wrong with the detectors or simply misset (now appears to be the latter).
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
No report.
Initial LIGO Detector Science & Engineering
(Coyne)
CDS
see also the CDS weekly meeting minutes in the commissioning archives
CDS Software
no report
CDS Hardware
LSC RFPD
Ben Abbott
1)
The boxes are on order, and should be in about 7 weeks
from now.
2)
Todd or I will test the PDs
that he has made to date, and we will ship them to the sites soon.
3)
Vern, Rich and I are talking tomorrow morning to
discuss possible changes to the ASI input on the PD, and how these may affect
the PCB. Once this is resolved, I will send off for another PCB run.
FO
Link
Sander
Liu
- The parts for LLO are being
packed up and will be shipped today. Installation is scheduled for next
week.
- The source of the excess
jitter may be the optic receiver used. Further testing is needed to
confirm.
Peter
King
I
have been going over the numbers given to me by Jay for the timing
jitter requirements. Sander Liu and I measured the timing jitter of the
existing system in the 40m Lab.
[Note
by D. Coyne: Measured to be larger than expected, but within requirements.]
DMT
John
Zweizig
This
week I continued to benchmark the Quad Opteron box as
a potential platform for online DMT use. I was able to run 29
monitor processes in parallel on a test box borrowed from ldas. The monitors read frame data from shared
memory (using the DMT online data distribution mechanism) and
there was no apparent contention for resources. The 2.2GHz Opteron
processors are ~3 times as fast for the DMT applications as the 750MHz
UltraSparc machines (this is a little surprising
given the differences in the architectures).
PSL
PeterKing
I
had left a message and e-mail with Dan Feehan of Lightwave with regard to repairing S/N #108
under warranty.
TCS
Mike
Smith
I
revised the ACAD drawing for the 30W TCS system.
Optical Contamination Cavities
Lee Cardenas, Liyuan Zhang
OTF Lab. (W. Bridge)
Cavity # 1
We have prepared and cleaned one set of
70ppm REO mirrors. We
introduced this new mirror into the cavity, made new laser
alignment and locked the cavity.
The laser power is now 134mw instead of the 180mw with the
previous ATF mirror. The ring down is 21microsecond instead
of 22 microsecond.
We are setting up the equipment to measure the absorption.
Absorption Test Measurement prototype -- in progress
We have made the frame to hold the new HEPA in place. Now the new HEPA that goes on top of the
enclosure is in place and running. New alignment to bring both the HeNe and Nd:Yag
laser beam to meet at the same point on top of the mirror
surface is in progress Scatterometer
system -- in standby
The Quantronix 60 watt laser -- In
progress
Preparation for the large mirror absorption test: We have found another leak from the aperture
holder solder seal. Very tiny leak from the solder seal. We took apart the
laser cooling and removed the aperture holder and cooling and
re-soldered the seals and after several trials the leak has
stopped completely.
We have re-assembled the cooling system and run the laser again
and recovered the alignment and the power is ~32 watt @ 30 amps
the mode might be OK, but we are working on it as now to improve it.
OTF Lab at Lauritsen ROOM 38 -- No
Change
Cavity #3
The contamination test for (20) pieces of Glenair Micro-D-connectors still in progress. Cavity is locked and we are taking
measurements for absorption and ring down for
contamination loss every day. So far so good. It needs
another month for the test to be completed.
Cavity #2 -- no
change
40 Meter Interferometer (Weinstein)
IFO commissioning:
- Osamu
continues to work on improving the DC-transmission locking of the arms. He
measured the rms motion of the arm lengths at 1:30am,
and got (5-8)*10^-8 mrms above 0.01Hz for YARM
and maybe 10 times higher for the XARM. He worked on optimizing the
damping gain on ITMX, but it didn't help much; ITMX still doesn't damp
very well. If the servo doesn't catch on the first fringe, it kicks the
optic, so that it takes many more fringe sweeps to catch again.
- Rob
continues to develop plans for making a smooth transition from
DC-transmission locking of the arms to CARM and DARM, using Finesse
modeling as a guide.
- Rob
and Dan measured the sign of the LSC signals for the ETMs,
in order to be able to know how to hand control off to CARM and DARM.
- After
losing the mode cleaner on Thursday (see below), Osamu re-aligned
everything upstream: the PMC, the frequency reference
cavity, and the Mach-Zehnder; in all case,
significant improvements in transmitted beam were acheived.
- Steve
and Osamu did some re-layout of the MC reflected beamline,
replacing some 1" optics with 2". They would have replaced more
mirrors, but CVI sent the wrong mirrors (for green, not 1064; they're out
of stock on the 1064 mirrors).
- So
far, we have re-laid-out almost all of the essential beamlines
in the last couple of weeks: MCR, AP, POB, TRX, TRY.
- Because
of the MC problems after the AC test, Dan postponed the relocation of the
SP RFPDs from ISCT-SP to ISCT-AP. He will do it
by the end of this week.
- Monica
has been taking data with arm locks in order to calibrate the DARM and
other LSC signals.
IFO modeling and DC detection development:
- Virginio has finished a coarse design of a suspension
point interferometer for the 40m, and is writing it up.
- Monica
continues to work on e2e simulations of error signals sweeps for the 40m,
with artificially short arms, to make quasi-DC sweeps for comparison with
Twiddle. Osamu wrote a Mathematica routine to
export Twiddle sweep data for direct comparison with e2e. There are still
some normalization problems to work out.
PSL:
- Steve
and Dan measured the laser power with the calorimeter, at the first
power-limiting polarizing beam-splitter after the main beam exits the MOPA
box. They measured ~6 watts dumped and ~3 watts transmitted. There's also
a known loss of ~1.0 watt betwen the MOPA and
the beamsplitter (measured a year or 2 ago).
Thus, there's 10.2 watts out of the MOPA box. The monitoring PD in the
MOPA box reports 11.2 watts, so the EPICS database was modified to report
the measured value of 10.2 watts.
- Steve
then measured the PSL power at the periscope where the beam exits the PSL
table and enters the vacuum chamber. The uncalibrated
Newport
power meter was measuring 1.45 watts there. He measured 1.26 watts with
the calorimeter.
- The
ISS continues to saturate frequently. This seems to be associated with the
Mach-Zehnder PZT running out of range, sue (it
seems) to a drift in the MZ arm length difference due to temperature
changes. This might be due to temperature-dependent OPL changes in the Pockels cells; one arm has 2 Pockels
cells, the other has one, so we are thinking about putting a compensating
crystal in the other arm. But, meanwhile, we need an alarm or alert when
the MZPZT drifts out of range, so that we can break MC lock, re-center the
MZ PZT, and re-acquire lock of the MZ and MC in a controlled manner. Dan
is working on that.
- Dan
found and fixed a bug in his ISSautoreset
script: when you turned the ISS servo off (eg,
to measure PSL power) the script would turn it back on after a minute. Now
if the user turns off the loop switch, the script will not reset it.
Electronics, controls:
- Last
Thursday, Steve turned off the air conditioner for ~2 hours in the IFO
hall (which warmed up by ~2 degrees C), to see what effect it had on the
MC RF frequency difference (we monitor the 33 MHz RF transmission and
reflection from the MC and see evidence that the MC length is changing by
microns). Well, it made a big mess, and we didn't learn much... But the MC
wouldn't come back up, afterwards. Turned out that *many* op amps on the
MC demod board and
servo board were burned out (on the MC Servo board, one of the LT1125s
blew, a nd all three of the LT1128s blew. On the I&Q Demod board, an
LT1125 blew.) Ben and Osamu spent several days finding and fixing them.
This probably was due to an unknown problem with the Sorensen power supply
or supplies), which may or may not have anything to do with the AC. Ben
will check the power in that rack.
- We
have been monitoring the 33 MHz RF transmission and reflection from the
MC, in terms of the frequency difference between actual and resonant
(MC_FREQ_DIFF). We see large (~100 Hz) changes between MC locks, smaller
(~20 Hz) daily variation, and smaller (~7 Hz) variations with 20 minute
periods. We believe that these are all from different causes, including
both MC length drifts and PSL frequency drifts. The 7 Hz variation seems
to be correlated with the PSL FRC temperature MINCOMEAS. We're thinking
about ways to correct this.
- Virginio is working with Rana
on a coordinated effort to diagonalize the MC
suspension controllers and coils.
- Osamu
reports that the DC-offset-lock of the arms is not easy, because of excess
noise on the QPDs at the ends. There seems to be
a grounding problem with these QPDs. When the
ground shield is connected to the rack, the C1:LSC-TRX_IN1
signal becomes around an order of magnitude noisier. Jay and Ben did a
search for the causes of this noise, but we haven't located it yet.
- Ben
has finished testing the 166 MHz RFPD for the SP beamline;
he will deliver it it tomorrow.
- Todd
has finished working on the 166MHz I&Q demod board for the new 166MHz PD, has tested it and
delivered it to Ben. He will bring it over with the PD.
- Ben
fixed a bad LEMO cable on the ITMX LL OSEM. Osamu thinks the ETMX UR OSEM
may also be bad; Ben will check it.
- We
expect 4 new Rev B coil drivers (for PRM, SRM, BS,
spare) from Todd in the next week.
- Rob
found that the ETMX CPU was running around 58-59 usec
(out of 61 usec). No timing delays were evident,
but nonetheless a reboot of the CPU fixed this "phase delay". It
may be due to a problem in the fiber optic timing link; under investigation.
Lab Infrastructure:
- Our 6 month old HP2550LN color laserjet
printer broke and Larry and Mike replaced it with an old, noisy HP4500N
unit. Larry is trying to get the HP2550LN repaired and returned to
us.
Bake oven Lab:
- Carpenters
are tearing up walls in the South Annex to allow for the installation of a
new large air bake oven for AdLIGO suspension
development.
- Bob
is assembling new PDs and LEDs
for new AdLIGO OSEMs.
- Bob
is working with Calum on building optics table
legs for the Synchrotron suspension lab,
- Bob
is working with Jay, Janeen and Calum on OSEM cables for quad suspensions.
Thermal Noise Interferometer (Black)
Nothing significant to report this week.
LASTI (Ottaway)
Laurent Ruet
reports:
I have adapted the mathematical model of the
one dof
modal control/estimator to n dof. I had to use
a very different method and use state space format instead of transfer
functions matrices but it works now a lot better. I can now study the stability
of the loop and see how a bad modeling affects it. I think I will be able to
test the control loop on the pendulum next week.
Richard Mittleman
reports:
We have been working on the BSC support structure ground noise amplification
problem (BSSGNAP). There are a number of entries in this weeks
ilog. So far we haven't isolated the problem, but
there are many hints.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
Weekly Physics Meeting
Hiro presented a preview of the SimAdvLIGO
package being developed by Matt. After
that he presented some FFT results for simulation of the g-factor measurement
by Rick Savage et al at LHO. Viewgraphs available at http://www.ligo.caltech.edu/~e2e/ME2ET/Minutes05/050505/
Commissioning Support
(Hiro)
The effect of the mirror phase maps on the g-factor measurements by Rick,
Keita, et al., was studied using FFT.
The summary is available at http://www.ligo.caltech.edu/~hiro/talks/g-by-FFT.pdf.
The phase map affects the g-factor measuments
in two ways.
(1)
Without mirror
tilts, the average ROC(ITM) is shifted by 30-50m due to the furface aberration. The average mirror curvature is
determined by fitting the phase map
measured in 7.5cm radius, while the beam sees smaller area. This
difference introduces this difference.
(2)
When a mirror is
tilted (in the simulation, ETM was tilted), the ROC changes
by 30-50m for a tilt of 1 micro radian. When the surface is smooth, the
mirror tilt does not affect the g-factor measurement.
The
magnitude of the measurement t0 measurement variation in the
g-factor measurement is several 10m, so it can be explained by this
mirror surface aberration.
(Biplab) As reported by Rana
in LLO elog, implementation of a proper Gouy telescope for WFS1 remedied a number of problems
encountered earlier. Probably some more
adjustments in other WFSs would also be
necessary (according to FFT simulation), even though no immediate reasons
for doing so has arisen yet for LLO WFS system.
SimAdvLIGO
(Matt Evans) Matt has delivered SimAdvLIGO, a framework of the advanced LIGO simulation package.One major guide line is that the
software organization is the same as hardware organization. One table
holding sets of optics is represented by one box, cables carrier, digital
or analog signals are represented by one connection lines, etc.
It has many place holders and empty boxes, but the major structuring
was finished. Matt tested the closed loop behavior and confirmed that
the loop is working. Hiro summarized the
products and the infrastructure in the e2e weekly meeting.
Matt will come back to Caltech on June 3rd,
and the model will become fleshed out and hopefully will be usable
for simple, yet important tasks, such as the linear or alignment
actuation study.
Simulation of 40meter interferometer
(Monica) The implementation of a new Twiddle function made by
Osamu allows writing raw data of the error signal sweeps. After
having collected all the Twiddle results for the sweeps in the
resonant point region, the comparison with sweeps (DC response) simulated
with e2e package for the 40m can be done. The comparison of the error
signal sweeps requires a DC response from
the e2e package, so a 4m arm long is used in the e2e simulation instead of
40m as a good compromise between simulation speed and adiabatic case.
2-photon model in e2e
(Biplab)
Have gone through relevant literature to make a tentative list of what we
need to do and take care to implement 2-photon model in e2e for studying
squeezed states. Started correspondence with Yanbei
Chen to understand and clarify various issues.
modeler
(Hiro)
In order to support the new SimAdvLIGO, modeler code
is being updated. Major changes are
(1)
different time step support - modules like digital filter
between ADC and DAC sees proper digitized time step automatically.
(2)
merging of
setting and macro
(3)
fast dual
recycling module
(4)
better modal model to simulate more complicated system
- like different losses seen from AR or HR sides.
It will take several months to complete these modifications. The
priority will be determined by the progress of the SimAdvLIGO
package by Matt.
Alfi
(Bruce) Reworking the
implementation of bundle generated connections. Both a speed and a
modular design issue.
(Melody) Continuing
on fixing existing Problem Reports. Currently working on the user
interface for allowing the user to choose the
display for nodes: graphic, node name, or a multiline
comment.
Data Analysis Activities (Lazzarini)
Charlton:
This week I have been working on matlab code to
compare calibrated strain data with the (frequency-domain) calibrated
strain produced in the stochastic background analysis pipeline. The purpose of
the exercise it to look for errors or differences in the strain calculated
by the two methods.
Creighton:
I started looking into a bug in the LAL 2d mesh tiling routines, whereby
they occasionally get trapped in an infinite recursion.
Mandic:
I worked on understanding the features in the coherence between H1
and H2 strain channels during S4. I observed that the H1ASQ-H2ASQ features
can be found in the coherences between the ASQ channels and the
microphone or ISCT-accelerometer channels. On the other hand, such
features could not be observed in coherences of the ASQ channels with
magnetometers or with the mains-monitoring channels. Hence, the coupling
of the features observed in the H1ASQ-H2ASQ coherence is likely acoustic
or mechanical in nature.
Mendell:
I have added to the CW/pulsar S2 StackSlide
investigations page: http://www.lsc-group.phys.uwm.edu/cgi-bin/enote.pl?
nb=puls2stackslide&action=view&page=last showing the results of a study of the
power spectrum of exact pulsar signals vs. the power spectrum in the
approximation that the amplitudes and frequency of the signal are constant
during each SFT. This approximation is widely used by the CW group.
Conclusion: The mean relative difference between the approximate and
exact signal power is near zero, though the mean absolute difference may tend
to be positive, indicating some bias towards the approximation over-estimating
the power. However, this conjecture comes from a few outliers,
the statistics are not good enough to say for sure. If true, this would only
have an effect on the predicted StackSlide power and
maybe the predicted F-statistic. The approximate form of the signal also
predicts the bin with maximum power incorrectly about 4% of the time, but the
actually power loss due to this is much smaller, since this happens when the
frequency is between two bins, and the power in neighboring bins differs by
only a few percent from that in the bin with maximum power. Thus, this should
have an effect on StackSlide, Hough, and F-statistic
at much less than the 1% level. I am also working on further validation
of the StackSlide code to prepare for the generation
of S3 and S4 results.
Shawhan:
- Reviewed existing data quality information for the S4
run.
- Made a catalog of lock losses during the S4 run, and
defined PRELOCKLOSS data quality flags.
- Studied dips in the stored light in the arm cavities
during S4, which tend to be associated with
glitches in AS_Q. Many of these occur near
the end of a locked stretch, so it seems prudent to omit the last
~30 seconds of each locked stretch. I am currently working on defining LIGHTDIP data quality flags.
- Generated segment list for re-running WaveBurst on S4 data.
- Critiqued an analysis in progress to look for
gravitational waves associated with the giant gamma ray flare from SGR
1806-20.
- Checked the total observation time of the S2 binary
black hole inspiral
search.
Lazzarini:
Working with Tinto and Sutton on an extension of the Gursel-Tinto
algorithm to develop a detection and estimation algorithm for an arbitrary
network of detectors. This will
yield a model-independent estimator of source h-plus, h-cross, and source
location. It is essentially a extension of the
r-statistic concept to an arbitrary network of global detectors. Interested readers may find the following
movies I made interesting (NOTE: these are very large files!;
some PCs may not be able to view them - caveat lector):
http://www.ligo.caltech.edu/~lazz/distribution/LSC_DataDir1/LIGOmovies/
GT_ReconstructvsSNRPosition.avi (<- supposed to be
PC compatible)
http://www.ligo.caltech.edu/~lazz/distribution/LSC_DataDir1/LIGOmovies/
GT_ReconstructvsSNRPosition.mov (<mpeg)
http://www.ligo.caltech.edu/~lazz/distribution/LSC_DataDir1/LIGOmovies/
GT_MovieAitoffv2.avi (<- supposed to be PC compatible)
http://www.ligo.caltech.edu/~lazz/distribution/LSC_DataDir1/LIGOmovies/
GT_MovieAitoffv2.mov (<mpeg)
This is still a work in progress....
Weinstein:
- Reviewing
S2 BNS analysis and paper
- Working
with Lisa and Duncan on ringdown search
Yakushin:
Data analysis:
1)
Tuning quadruple
coincidence LIGO-GEO waveburst script;
2)
Modifying waveburst to run on the new S4 MDC frames.
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS:
- Work continued on PR 2825 to address the issue of not
properly reporting time ranges where there are frames files that
should be reported. Currently have a fix that is being tested on
tandem-V.
- Worked on PR 2724 concerning the modification of
resource variables and PR 2617 which is related and concerns the
headers for these resource variables. Adding the ability to source
columns with a single mouse click in the controlMonitorAPI's client.
- Successfully completed system and integration testing
for LDAS 1.5.60 and updated the results on the webpage.
TCLGLOBUS:
The first alpha release of Tcl/Globus is nearing
announcement. The tarballs have been ready for a couple of days but a
request for rpms has delayed the announcement.
Also a few issues with the documentation on how to build the alpha release have
been discovered and are being addressed today.
There is significant pressure in the GRID community to migrate to
the new Globus GT4 release which came out last
week. This was discussed that both the GriPhyN and OSG meetings. A review
of the changes to Globus components used by Tcl/Globus
between the current 3.2.x version and the new GT4 version suggests that this
should be a nearly transparent port for Tcl/Globus.
Fixed FTP client, completign the
callback SWIG wrapper function. The function had mis-matched arguments when passing the value back to the
TCL layer. Updated chapter in thePDF
document for Globus FTP client.
Created a debugging model for all test cases so its easier for end-users to know what cases to implement in the new
model
GRIDCOMPUTING:
Attended the GriPhyN all-hands
meeting at Argonne National Lab. Presented LIGO talks for status
and planned use of technologies that have come out of the GriPhyN/iVDGL Projects.
Discussed the formation of collaborative activities with Univerity
of Chicago, ANL, and ISI to evolve LIGO's current
usage and to help guide the development of the virtual data language based
on experiences.
Attended the OSG Consortium Council face-to-face meeting at UW
Madison to discussOSG by laws, governance
procedures, reports from integrations, deployment
and operations activities as well as the interim executive board. Funding
agency prospects and stategies for overseeing
proposal activites were also discussed.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Did some research about modification/changed/creation
times in SAM-QFS. Determined that the
problem we'd noticed (modification times not updating on the MDS for files
being appended to by a shared client) has been fixed in 4.3.
- Got STK to look at drive 57 (CIT). Diagnostics
reported no problem and the drive has been working since.
- Made an entry in releaser.cmd
(weight_size = 0.0) at CIT to get the releaser
to ignore file size (and hence implement an LRU algorithm for releasing files).
- Working on getting new(!) S2
RDS frames to tape. Also using this opportunity to clean up CIT archiver.cmd.
- Continued to reinstate dual copy at CIT.
Ongoing.
- Finished copying some "missing" (at CIT)
E10 rds data from LHO using tar/globus-url-copy.
Working on getting this to tape at CIT.
(Phil Ehrens)
- Various minor tasks in support of LDAS.
- Ongoing analysis of applicability of DOE/GRID proxy
cert use with Subversion/Apache. Determined that security level of proxy certs is incompatible with security level of full user
cert challenge protocol. Even when the certificate chain is fully visible
to openssl, there is a problem with the proxy
cert being issued by a user and not a CA. Elevating the authority of
user certs in the same context where
authoritative CA certs are used is probably not
good. A way of separating the authority level is probably possible. The
inconsistency in the use of certificate nomenclature between various
software suites is the primary difficulty.
- Installed Solaris 10 on the "samtest"
machine in anticipation of testing a new Sun 10 Gbit
Ethernet card.
(Stuart Anderson)
- Further adjusting of Condor configuration to handle a
large number of jobs.
- Ran failed test of 10GigE host-to-host test between
Solaris/Suse quad-Opteron
machines in Millikan/Bridge. The next step is to
run between Solaris/Solaris in the same building.
- Running LDR to catch up on Astrowatch
data.
MIT
(Keith Bayer)
- Added new scsi
drive to dmt machine lancelot
(this drive will be backed up).
Livingston
(Igor Yakushin)
- node70 failed, probably bad
drive.
- Transferred h(t) S4 data
from CIT to LLO.
- Transferred SG6_S4 MDC frames from PSU to LLO.
- Discovered a strange behaviour
of LSCdataFind when a client on ldas-grid@LLO queries the server on ldas@LLO through GC interface: if the queries are
followed one after the other, some of them fail, but if there is
"sleep 1" between queries, they succeed. When client
is running on my desktop or at CIT and using the same server at ldas@LLO there is no such problem, if client is
running at ldas-grid@LLO and queries server at
CIT, again there is no such problems. Most likely there is some hardware
network problem in GC that affects the communication between ldas@LLO and ldas-grid@LLO.
Hanford
(Greg Mendell)
Several enhancements to the createrds.tcl and createrdsGUI.tcl
scripts have been completed
1)
Added options
that allow the merging of data from different frame types and IFOs. This will be used to merge GEO data with LIGO
data.
2)
Added a better
gap checking algorithm (should only get "short frames" now when a
true gap in the input data exists) and an option to align output frame start
times with the output framefile length. Thus, a
rule can be used to find any normal (i.e. non-short) frame file based on its
GPS start time, which will be a multiple of the duration of data in that
file. Changes have been checked into CVS:
CVS/Root=:pserver:anonymous@gravity.phys.uwm.edu:2402/usr/local/cvs/ lscsoft CVS/Repository=dsorun/contrib/createrds/scripts.
In this directory see README.createrdsAndcreaterdsGUI
for further details and createrds.rsc for an example
resource file.
(Ben Johnson)
- Dusting
off old S3 data corruption notes. The stochastic group asking questions
about 16Hz.
- Touched
last of "old" A4 data. All old A4 data should be at
Caltech by now.
- Working
on new AstroWatch archiver
GUI/system. It should allow for better comments, auto-elogging
of intervals+comments, and a auto-archive
timout in case the button doesn't get pushed.
- Attempting
to get the certificates updated for the various servers; ldas-grid, ldas-gridmon, and
ldas-pcdev1.
- Sent
off "1 Year + Option" Sun Service Contract P.O. to Dorothy Lloyd
May 4 afternoon.
- Getting
h(t) frames from Caltech. H1/H2 frames completed.
L1 frames transferring today.
- Publishing
S3 L1 LLO RDS data on the cluster. The original copy+publish
process was not completed for some reason.
- Helping
diagnose why the conlog_up script does not
consider recent data to be "UP". The issue appears that the PSL
status bit is bad, the reasons are murky. Possibly due to bad EPICS code.
General Computing (Wallace)
MIT:
(Keith)
- Continuing LDAP work (when time permits)
- Setup accounts for new grad student (Nickolas Fotopoulos)
- Installing darcs software
on cadwalader
Livingston:
(Shannon)
Busy with a network installation for CDS. See Livingston
report.
Hanford:
(Christine)
- Network usage can be seen at http://www.ligo-wa.caltech.edu/~christin/mrtg/
198.129.208.1_198.129.78.122.html
- Two scanners seem to have suffered from the power
outage last week. Both are visible
from the PC, but will not scan and will not communicate with the scanning
software. The manufacturer has been contacted for support on one
which is still under warranty. The other I will try a complete
reinstall of drivers and software.
- A SCSI cable on the tape drive used to backup user
files is reporting errors. The main file and e-mail servers will be
powered down in order to replace the cable.
- Tom Villani of NoaNet dropped by for a visit on Tuesday. Tom is
promoting an alternate WAN connection between Richland
and Seattle
which we are looking at.
- Spent some time trying to figure out why a Sun
workstation would not recognize one of the printers. Finally ended
up putting the printer in the hosts table on the Sun and then it
worked. Still don't know why communicating with this one printer was
different than the other printers.
- Downloaded some recent versions of software from
Caltech ITS. Ordered some software upgrades. Renewed the
maintenance on several Matlab licenses.
Purchased the latest version of Partition Magic along with 10 more
licenses. The number of dual boot Windows/Linux computers
is growing.
- Other misc. user support.
CIT:
(Mike)
- Worked on the swapping out a printer from the 2nd
floor of W/B, and moving it to 40 Meter. This took most of the day
cleaning up this printer, and adding an additional network card to enable
users to print from both, 113 & 115
subnets.
- Continued to work on two visitor workstations,
loading XP and working on setting security and loading GC software.
- Worked on wiping two laptops to give to PMA. Ed Chargois is aware of this, for these are surplus
laptops.
- Helena Armandula: Her
laptop died. After trouble shooting this issue, I called Dell's tech
support to get another other board for this unit. This issue has
been resolve, and user is back up and running.
- NTSRV's: Ran end of month
ghost backups.
- Ghost Server: Burning critical images to DVD, and
removing them from the server afterwards. This will allow additional
disk space for additional backups.
- Continued to work on a NTSRV that is loaded with 2000
server. This server is to be use for an apache webserver.
- Rerouted many network cables in the server room.
- Other user support that included the usual support:
Printers, Software, E-mail, and some networking issues.
(Veronica)
- LSC: Website updates. Installed the website for
the upcoming meeting.
- LIGO: PAC website updates.
High-resolution images for the NSF and a popular-science publisher.
Compressed the video of last week's software demo. Working on
changes to the roster database utilities to update the authorship list.
- Project Science: Moved the files over to
TMT. Waiting to hear whether our help is needed with installing
and configuration.
- CaJAGWR: Website
updates and user support.
- Initiated work on the new LIGO MIT web site.
(Larry)
- Worked on a number of purchase items. All items have
been received and delivered.
Received quotes for a number of computer systems to be installed in
the server room. Still working on a SUN quote. Renewed the license for the FEMLAB
package.
- Worked with Mike in replacing the printer in the 40M.
Still in the process of getting their unit repaired. There were a
number of logistical issues that had to be worked out with different
companies. We are now waiting for HP to supply a shipping container
to have the unit shipped to their repair facility. We still have not
been able to find out why they will not just send out a fuser kit and
have it replaced in the field like they do with the other printers. Moved a number of computer monitors
around to new locations.
- Helped Stuart with some testing of a 10GigE board.
This opportunity allowed the OS upgrade to be done on the sandbox, so
even though the board did not work something positive did come out of
the time spent.
- Working on getting power to the computer room for
next weeks scheduled power outage. West Bridge
and Bridge annex are scheduled to be down all day on May 14.
- Working on recabling in the
computer room. Punched a new hole in one of the racks and started
moving cables. Mike has swapped a number of them over. Now we just
need to install a couple of cable trays to get the cables organized.
- Performed the monthly backups on the user accounts.
Started the full backups on the servers. Just 12 more to go. Restored a couple of file systems for
different users.
- Worked on cleaning up a number of user accounts.
Cleaned off a couple of Gigabytes of disk space. Presently,
generating a new list of user accounts, no longer active, to get
approval for removal.
- Working on a couple of documentation items. A new
Computer Usage Policy and NIS+
setup for Linux are two that are in process.
- Worked on getting the mail servers back on-line. The
end-user server was down for a couple of hours with a disk problem.
This outage showed that there is more dependency between the e-mail
servers than there should be.
Discovered that backup server for the mail servers no longer
exists, so that is now a new project to get going on.
- Working on a couple of new hardware items for
travelers. If they work it should facilitate their being able to
communicate electronically.
- Worked on a number of enduser
machines to get them back on-line.
- Between Mike and Larry over two hours a day is spent
on the spam filters, checking for false positives. Difference between
spam e-mail and legitimate is getting grayer.
Mail
Statistics for April 28 thru May4, 05
Accepted
Messages 17,958
Rejected
Messages 23,598
Virus
Messages 1,245
False Positives 373
Total
Messages 41,556
Advanced LIGO and Supporting R&D (Shoemaker)
Systems and Management
From: Carol Wilkinson <wilkinson@ligo-wa.caltech.edu>
Development Progress Updates
Progress updates through April 30, 2005 on development of advanced LIGO
subsystems have been completed using a new process for collecting the update
information. Updated files will be available on May 10 at the usual web site:
·
See http://www.ligo.caltech.edu/~tfrey/index.html
for a complete listing of all project related cost and schedule data.
Advanced LIGO Planning:
Work is progressing on recalculating bottoms-up estimates for the costs and shedule for the Advanced LIGO construction project. Work to
date has concentrated on SEI fabrication and the Facility Mods
and Installation subsystems. Fabrication and installation costs and schedules
for the remaining Advanced LIGO subsystems will be scrubbed in the next two
months. Subsystem leaders should be prepared for a planning session in that
time window. The goal is to have the new overall project costs and schedule by
the end of June
The web pages with advanced LIGO planning information, including the cost
book, will be revamped and password protected to make the information more
accessible to planners and less accessible to the general public. The cost book
itself is being recreated in a different format.
Seismic Isolation
From: Ken Mason kmason@ligo.mit.edu
no report this week
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
Advanced LIGO Suspensions
Checking drawings for Calum.
Working on a tablecloth dummy for the ETF quad.
Participated in the installation fixtures review this
morning.
Met with JoAnn Hasbach and Calum in the
Synchrotron yesterday to give JoAnn a heads up about
the clean room that will be installed there in a few weeks. Discussed a
few safety related issues and other small things.
Met with Ric Paniagua
about the tablecloth details. Will include on the drawing the mounting
holes for the ECDs and mark up the top plates of the
top mass to include the vertical stops.
Compiling input from a number of SUS team folks for design progress (formally
Primavera updates) for Carol and Dwight
Provided updated budget info to Carol, Dennis and David.
Participated in a meeting on charging of optics, hosted by
Gregg Harry, during the regular SUS weekly slot. Representatives from Moscow Univ.,
the Univ. of Glasgow, Stanford, Caltech and others
reported on research.
From: ctorrie ctorrie@ligo.caltech.edu
From: Ken mailand kmailand@ligo.caltech.edu
I have worked with Helena
and purchase order was released for an air bake oven with 3’x 4’x
5’ internal dimensions. The delivery is promised in 5 to 6 weeks.
I have worked with Bob Taylor re. the installation
at the 40 meter site, with an oven dimensional drawing, the location set up,
and electrical and venting prep work has begun.
I have requested quotes on a cleaning station, and bake oven combination,
these quotes is expected w/in 2 weeks, this system will have the capacity for
all the large Advanced LIGO parts.
A completed preliminary articulated arm fixture was discussed at the
Wednesday meeting, and comments and suggestions are being incorporated into a
revised arm design.
From: "Mark
Barton" <mbarton@ligo.caltech.edu>
This week I finished coding the dSpace controller
software which will be used to run the quad prototype being assembled at
Caltech, and started working with Mohana and Paul to
interface it to the electronics.
Core Optics
From: Gregg Harry
<gharry@ligo.mit.edu>
Flavio Travasso has
joined us at MIT to work on our thermal noise effort. This week, we sent the CSIRO coating with
intentionally poor stoichiometry to Stanford for
annealing. In its place, we hung a sample with silica/tantala
coating from CSIRO with the substrate commercially polished instead of superpolished. The lowest two modes, the butterflies
(or farfalla as we now call them), have been found
and rungdown. The Q's are 3.92 +/- 0.04 E5 and
3.55 +/- 0.09 E5, compared to 4.4 +/- 0.1 E 5 and 4.5 +/- 0.1 E5 for the superpolished sample. This difference is probably not
due to the polish, but further data is needed to be sure.
From: Helena Armandula ahelena@ligo.caltech.edu
CSIRO
Last Friday, CSIRO visited Caltech. We had a telecon
with several members of the Coating Development Group. We used the opportunity
to discuss coating issues related to CSIRO's work. We decided to anneal the poor stoichiometry coating sample at Stanford to evaluate any
"Q" changes. GariLynn will make interferometer
measurements on the coated part before the annealing, absorption will be
measured also.
CSIRO is finalizing their research to produce a low stress coated sample.
Next, they will coat 2 "Q" substrates of each type with the
regular 30 layer design; the samples will be used for different annealing
experiments.
LMA
Jean-Marie will start the coating calibration runs next week in preparation
for coating the TNI mirrors. The fixtures were promised now by the end of next week.
Still is quite possible to get the mirrors finished by the end of May-1st week
in June.
There is a "Q" measurement system now at LMA being calibrated. So
far, they have a very close correlation with our measurements, agreement is not
with an specific "Q" number, but with the
percentage of improvement seen between different coatings.
Jean-Marie will look into the coating design suggested by DeSalvo/Pinto, he is in the
process of refining coating simulations.
Adv. LIGO SUS
The indium cold welding to join flags and magnets works in principle, but,
the procedure needs to be up-graded to be deemed reliable. I am looking into possible improvements,
I am considering to enhance the indium bonding with a silicate bonding?
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
The newest hardware revision of a high power photodiode was tested at the
280 mA level. The heatsinking
appeared sufficient, as the case is just slightly above ambient
temperature. Testing at the 500 mA level will
start once some connector components arrive which will enable completion of
another photodetector.
Auxiliary Optics
From: Michael Smith <smith@ligo.caltech.edu>
BS DIFFRACTION LOSS
I recalculated the BS geometric and diffraction losses using ZEMAX, with the
input beam from the power recycling (PR) mirror centered on the BS HR surface;
this minimizes the loss from the signal recycling (SR) mirror direction and
also minimizes the total loss. The loss was studied as a function of BS
diameter and thickness, for the case of no lensing in
the reaction mass (RAM) in front of the ITM. I completed the loss calculations
for an alternate BS model that incorporates a lens element into the reaction
mass (plano-convex, with R = 9m); this reduces the
beam size at the BS from 60mm to 46.7mm. This change allows a smaller BS for
the same amount of loss obtained with no lensing in
the RAM.
The total loss (in Watts) with 1 W input from the PR mirror and from the SR
mirror for two possible choices of BS dimensions, with the standard
configuration and the alternate configuration are summarized below:
Table 1 : BS Loss
Comparison for Two Dimensions
BS DIMENSIONS PR
LOSS TOTAL SR LOSS TOTAL D/t
t = 60mm, D = 350 mm 3.94 E-4 1.01
E-3 5.8
t = 60mm, D = 370 mm 1.61 E-4 4.18
E-04 6.2
Table 2: Alternative Design, BS Loss Comparison for Two
Dimensions
t = 40mm, D = 260 mm 5.69 E-4 1.18
E-3 6.5
t = 50mm, D = 300 mm 9.10 E-5 2.18
E-04 6.0
Other Laboratory R&D
From:
"Erika D'Ambrosio"
<ambrosio@ligo.caltech.edu>
Marco (3May)
I placed a 10 degrees wedge on the transmitted beam from the folder mirror.
The acquired beam shapes don't shown any astigmatism.
Noise is dominating for TEM00 profile, while TEM10 couplings are strongly
affected by misalignments. I also took
many spectra by cavity length scans: after several comparisons it seems there
is some not-understood "drift effect" that made non-linear the
spectrum sampling. In order to identify
each peak seen on these spectra today I assembled a dithering servo loop to
lock the cavity on the Airy peak: for a while I wasn't able to lock the
cavity. End mirror PZTs
cables were fixed and their work was good.
Creep experiment: long run at 40 C: average position stable at 6.97 mm
almost every day.
Juri
I completed the analysis of the expected beam shape using the LMA Mexican
Hat mirror maps 5008 and 5009 and the results are available as "Beam shape
analysis for the mirrors 5008 and 5009"in http://www.ligo.caltech.edu/~jagresti/ . I
used my program for eigenmodes calculation in the
case of non-symmetric cavity to find the transverse modes frequency
distribution for our FP cavity (with spherical end mirror); the results are in
perfect agreement with the theoretical analytical formulas for Laguerre-Gauss modes. This was a necessary step in order to
test the procedure to extract the frequency spectrum from the eigenvalue problem because in the case of Mexican Hat
mirrors we don't have an analytical formula for that. The comparison with the
experimental spectrum is still under investigation.
Justin
Currently making ring down experiments for q-factor determination of the
steel flex joints. After realizing a slight miscalculation, a correct resonance
of the flex joints has been found.
For additional information about this report, contact Stan Whitcomb or Phil Lindquist