Weekly Report for Week Ending April 28, 2005



The LIGO Executive Committee Agenda for Monday May 2, 2005 will be:

(Meeting time: 10:30 am Pacific Time)  

  1. Announcements
  2. Comments on Weekly Report
  3. LSC Issues (Saulson)
  4. LIGO Lab Operations
      • Administration (Lindquist)
      • Sites (Raab, Zucker, Shoemaker)
      • Commissioning (Fritschel), Detector (Coyne)
      • Campus Research Facilities
        1. 40 Meter (Weinstein)
        2. TN, ( Libbrecht)
        3. LASTI  (Shoemaker)
      • Data Analysis and Computing (Lazzarini)
  5. R&D and Advanced LIGO (Shoemaker)
  6. CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION AS NEEDED

Special Items:


Special Announcements:

 


Weekly Report Highlights


LSC Issues (Saulson)


no report


LIGO Laboratory Administration (Lindquist)


STATUS OF LSC MOUs (Petrac)

LSC MOUs and Research Plans and Progress Reports

LSC updates for Feb. 15, 2005 to Aug. 15, 2005 and Progress Reports through Feb. 15, 2005

  • All updates for all active outside-LIGO LSC groups are in the LIGO/LSC sign-off / Saulson
  • All Progress Reports have been submitted..

SITE TELECONFERENCE (Lindquist)

A site teleconference was held on Thursday, April 7, 2005.  The following issues were among those discussed:

  • Budgets/Actual Costs -- end of April data not final yet, however still looks as though we are running under about $500K for recurring Operations.
  • Safety Review at Hanford -- good to go next week.  For Livingston looking towards next Fall.
  • Property -- We have separate a Cooperative Agreement for Operations and a Grant for Outreach.  Plan will use some of the Outreach Grant for some furniture for the Outreach Center.  Do we have to tag such items separately in the Caltech property system?  Propose to design some tags for use on Non-OPs procured materials.  Everything on OPs will use the existing tags.
  • GSA Vehicles -- will request nine-passenger van for Livingston.
  • P-Cards -- one of the Hanford P-Cards has been cloned and is roaming around Indiana.  Bank of America is pursuing issue.  People should be cautious.
  • The list of assigned actions updated through April 28, 2005 will be found Here.

PROPERTY MANAGEMENT (Chargois)

>From: Ed Chargois <chargois_e@ligo.caltech.edu>

  • Nothing significant to report.

DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

  • No report.

>From: Cleveland Mak <mak_c@ligo.caltech.edu>

  • packages: in - 20, out - 15
  • faxes: in - 35, out - 24
  • No special projects to report.

COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman, Salone)

>From: Esther Cunningham <esther@ligo.caltech.edu>

>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

  • Completed the purchase order for the purchase of the modular clean room for the Synchrotron Lab.
  • Completed change order #31 to Excel for the contractor to install the Smart UPS at LLO.
  • Placed the credit card order for the laser and then cancelled the order upon the request of the researcher.
  • Placed standard purchase orders as requested for Caltech.  Received several invoices for payment. Some were handled through the purchase order system and the others were paid through Pcard.

>From: Gina Salone <gsalone@ligo.caltech.edu>

  • Nothing significant to report.

>From: Florence Kaufman <fkaufman>

  • Worked on updating monthly reports for the end of April.
  • Submitted two Fabrication requests and associated Task Set Up Forms for Timing Systems at Hanford and Livingston.
  • Financial reports can be found at: http://docuserv.ligo.caltech.edu/~fireport. (For passwords contact Florence)

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

>From: irena@ligo.caltech.edu (Irena Petrac)

  • No report.

>From: Ed Jasnow <jasnow@ligo.caltech.edu>

  • The review of the 50 percent complete drawing package from the architect for the Livingston SEC, EDR, was held on Wednesday, April 27.  Several key issues remain to be resolved, with responses due to the architect by Wednesday, May 4.
  • The procurement process for the LLO SEC was reviewed with the architect, and agreement was reached.  They will select several construction firms to be invited to submit qualification credentials.  These credentials will be reviewed, and based on that review firms will receive the RFQ and submit bids, which will be publicly opened.  Additionally, it was agreed that a pre-bid conference would be held two weeks after receipt of the RFQ.

SUPPORT (Baldon, Hiroto, Lloyd)

>Irene Baldon

  • Processed the paper work for twelve (12) new/revised trips.  At this time there are twenty-six (26) new trips that need to be completed and ticketed before the paper work can be completed.  Assisted several LIGO personnel with their travel arrangements using their P-Cards and made several reservations for outside visitors coming to LIGO/Caltech for meetings and/or workshops.  LIGO will be sponsoring thirty-eight (38) SURF Students this summer and I have already started arranging these trips.  We have twenty-six (26) coming to LIGO/Caltech, seven (7) to LIGO/Hanford, and five (5) to LIGO/Livingston.
  • Completed ten (10) Expense Reports and there are eight (8) reports yet to be done.  I continue to contact travelers who have outstanding Expense Reports (more than one (1) month old) to ask for their cooperation in sending me their receipts so that these can be closed in a timely manner.  Presently there are three (3) reports more than 30 days old.  I have one (1) waiting signature at this time.  Reconciled thirty-three (33) P-Card charges for the week.  This required telephoning hotels and car rental agencies to verify which traveler used my card and for what amount.

>Julie Hiroto jhiroto@ligo.caltech.edu

Nothing significant to report.

>Dorothy Lloyd

  • Processed the usual invoices for payment. Tracked and followed up on invoice problems. Reviewed and recorded payments processed by Esther the week of April 18.
  • Processed requisitions for standard purchases, payment requests and change orders. For more detail see Cost Schedule Control Systems report by Ruth Brambilla.
  • Jim continued with data entry in the LIGO database and helping out in the DCC.

PROPOSALS and REPORTS (Lindquist)

No progress to report this week.  The Annual Report for the Visitors Program is basically complete and entered into FastLane ready to “push the button.”  Will be helping Fred Raab with the I2U2 Proposal, which is collaboration with Fermi Lab for some outreach activity.

A proposed draft has been distributed for outlines for the Annual Report for Operations and a Proposal for an Extension for FY 2007 and FY 2008.  Some comments have been returned.  We will begin working these documents pretty furiously between now and August 1.

DCC Steering Committee (Lindquist)

[Some comments excerpted from comments provided by D. Shoemaker. –pel]  Scott Reedy of Go Engineering demonstrated the Agile Document Management System on Wednesday, April 27, 2005. It appears that the system might work very well for LIGO.  The system targets a development and manufacturing environment more so than other systems that we have looked at.  The workflow tools are particularly complete and flexible. There are built-in mechanisms for QA checks, tracking installed hardware, redlining using built-in tools, and the like.  URLs to documents are not directly delivered, but a URL for the 'file card' from which the document can be found as an attachment is available -- one more click. It is not set up to publish to the open web, and for those documents which should be completely open, we would need to have a separate step outside of Agile (but one that sounds relatively straightforward to implement). This may cause us to rethink what we want to be public and what is not, for better or worse. An ORACLE database is used, but it is managed by Agile and we would not need any local expertise.

Cost may be an issue.  Engineering help will be required to "sell" this approach based on the added capabilities that the system would provide for them.

CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)

  • No open change requests.

HUMAN RESOURCES (Akutagawa)

>From: Cindy Akutagawa <cindy@ligo.caltech.edu>

  • No special activities to report.

Quality/Safety (Tyler)

>From: Bill Tyler tyler@ligo.caltech.edu

Nothing significant to report.  Seems like all is as ready as it is going to be for the LHO Safety Audit on Monday (2 May).


LIGO Hanford Observatory (LHO) and Interferometer Operations (Raab)


Summary of Commissioning Activities at the LIGO Hanford Observatory (R. Savage)

Highlights from this week's elogs:

General

  • The corner station was completely powered down early Tuesday for preventative electrical systems maintenance but was mostly back on-line by noon Wednesday.
  • Dust monitor power supplies were moved in efforts to reduce 60 Hz coupling.

4K IFO

  • efforts to provide reliable monitors of TCS input power continued.  The X-arm TCS power adjustment polarizer was found to be loose in its mount
  • ASPD2 was removed for assessment of damage during S4 resulting from a slow-actuating shutter
  • Cavity pole measurements performed via the ringdown method.

2K IFO

  • H2 commissioning plans for the next several weeks were summarized
  • in efforts to understand power scaling, power levels were measured at several output ports
  • the temperature of the pump laser and mode-hop-free region in the H2 NPRO was adjusted

LIGO Livingston Observatory (LLO) and Interferometer Operations (Zucker)


L1 Interferometer (Frolov)

The L1 interferometer's inspiral range improved to 10 Mpc last week, after it was found that the of non-resonant sideband modulation frequency was 10Hz away from being an exact 5/2 multiple of the resonant sideband. This was producing both a line around 100 Hz and some broadband noise, which dropped away with this simple adjustment.

The anti-symmetric port WFS Gouy phase telescope was modified in attempt to improve the WFS1 optical gain. The first modification was not successful due to the reduction of the beam size on the photo detector. The design was modified and new lenses were ordered to allow adjustment of the Guoy phase without adversely affecting the beam diameter.

Other interferometer noise investigation and improvements:

  • the test mass coil driver noise was measured. The only anomaly was the two ETMX coils that have oscillation around 300 Hz. This is under investigation.
  • the pre-mode cleaner board was upgraded to have more DC gain and larger range.
  • the modulation depth of both resonant and non-resonant sidebands was reduced to investigate possible RF saturations. There was no change in the low frequency part of the interferometer noise spectrum indicating that we are not limited by saturations. The noise at the high frequencies increased due to dark noise.
  • the reflected port wave plate beam dump was replaced to reduce back scattering.
  • the PSL chiller was placed on rubber vibration isolators to reduce the noise coupling.
  • an attempt to turn off the optical lever dumping was not successful.  There is not enough angular control gain in the WFS alone at the moment.  Additional filtering of the optical lever signals did reduce the noise at some frequencies between 30 Hz and 50 Hz, but did not reduce the broadband noise that was thought to be from optical levers.
  • the new Mode Cleaner and Common Mode servo boards were installed. Both electronics hardware and the epics screens were tested. The Mode Cleaner and the full interferometer have been locked with new electronics but not in common mode yet.
  • the notch on the FSS servo board was modified to reduce the effect of acoustic resonaces of the phase correcting Pockels cell on the loop transfer function.

Education and Outreach (Thacker)

  • Three school groups visited this week (185 students, 8 teachers, 25 parents)
  • Email solicitations went out to candidates for Local Educators Network; meeting will be held 21 May. About 10 teachers/administrators have signed on to date.
  • Discussed 50% Design submittal with architects for Science Education Center; drainage plan due by 8 May to Livingston Parish Planning Commission.

Site Safety and Security (Riesen)

Nothing of substance to report this period.

Mechanical Engineering (Spjeld)

AdL Quad SUS Installation Fixtures

  • Completed remaining FEA
  • Completed design review  report; meeting scheduled for 5/4
  • Contacted shop for  quote on linear drives; still waiting
  • Assembly details in  progress

LLO Outreach Facility ­ Pendulum Exhibit Wall

  • Awaiting feedback from exhibit  artists on final pendulum design
  • Awaiting drawing on pendulum  attachment interface design from architects

General Engineering

  • HAM chamber door  removal tool; different design approach?
  • Machine drawings for  door removal tool in progress
  • Converting SolidWorks models of BSC to 3DS files for NSF movie

LLO General Computing and LIGO Computing Security (Roddy)

Added two fiber interfaces to the router tuesday night which required about 10 minutes of downtime.  This is the flashed card that Syskonnect sent from Germany that finally arrived with a bug fix.  However, it only works in one of the two PCI-E slots.  I have emailed them and they claim to be aware of the problem and have since released another patch which requires flashing the EEPROM on the card.

Working on a security package that will be installed on the router.  It will work as a basic IDS on the border which should give me an idea of the number of portscans, etc. that we see on a regular basis.  It also has the ability to automatically block offending IPs.  I will have to make sure that it has a facility to whitelist some addresses before I enable it.

Still working on an LDAP/mail server migration.  Some parts of it are in place and some of the configuration is done.  This will likely take a couple more weeks to finish testing and possibly roll over to it.

Several user support issues this week.

Working on renewing our Matlab license maintainence.  Received a formal quote yesterday.

Working a Maple software issue with the Caltech license server.  For some reason we cannot authenticate against their license server, even though the software@caltech folks claim there is no filtering on those ports by address.

HPLF, Optics Modeling, Data Analysis and L1 Commissioning (Franzen)

1)      HPLF news: The 100 W laser survived the 7 days burn-in test in constant current mode and another 2 days burn-in test in constant power mode. This means that the laser is now all clear for shipping back to LLO. We have also obtained a LabView code from IPG, which will be used for controlling and monitoring the laser during long-term testing.

2)      Performed additional Melody AdvLIGO  mode cleaner simulations by changing the diameters and thicknesses of the mirrors a little in order to study the stability of the solutions as requested by D. Reitze. No significant changes were observed and I will resume writing up a report.

3)      Was assigned to study and come up with a solution of the REFL port beam drift which has been recently been observed at higher laser powers.  This drift is probably caused by thermal lensing in the Faraday Isolator downstream polarizer causing a beam deflection around 1 mrad. An inventory of PZT  available at the site was made and two was found. Have been trying to identify them and is setting up a test station in order to measure their range of motion.

CDS software (Khan)

no report

LDAS/Condor Sysadmin and Burst Analysis (Yakushin)

Data archiving/Condor/LDAS:

  • Collecting the necessary information for LDAS room upgrade for S5 and behond.

Data analysis:

  • Testing and debugging LIGO-GEO quadruple coincidence script for S4.

Initial LIGO Detector Science & Engineering (Coyne)


CDS

see also the CDS weekly meeting minutes in the commissioning archives

CDS Software

no report

CDS Hardware

Jay Heefner reporting

 

Fiber Optic Timing Link (Sander)

  • Testing of the link on the bench and in the 40M shows a jitter on the 4MHz clock of ~35nsec which would correspond to an input-referred noise of ~500nV/rtHz for the pentek. This is ~x10 higher than what we were shooting for.
  • Sander feels that it may be the transmitters and receivers and he is looking for faster devices.
  • Testing will continue.

Peter King

The timing jitter for the timing system, in its various incarnations, was measured.  The mean jitter for the 4 MHz clock straight out of the Brandywine was measured to be 0.676 ns.  For the system with the clock fanout board, 2.627 ns and for the system using the electro-optic link, 25.268 ns.

ISS (Flavio)

  • Flavio and Dave are testing 2 boards.

Elect Shop (Todd)

  • 5 LSC PDs ready for test. 5 more in the queue.
  • Todd is working with the DCC committee.
  • Building additional PD interface boards.

Ben Abbott

1) Todd has finished stuffing 5 of the 24.5MHz PDs, and is working on some more that will be tuned to 24.5 MHz and 29.5 MHz.

2) I am tuning a 61.2MHz PD for LLO.

3) I have put an order in the machine shop to make more of the ISS PD bodies so that I will have plenty to give to the sites for the newer configuration.

DMT

John Zweizig

This week I have been evaluating the V40Z  (Solaris quad opteron box) as a possible online DMT computation platform. The DMT software installed on an LDAS V40Z box after solving a few minor problems. Preliminary benchmarks indicate that the Opteron performance is close to that of the Sun sparc after scaling by clock frequency (i.e. the 2.2 GHz Opteron executes DMT code about three times as fast as the 750MHz ultrasparc-III).  Still to be determined is whether the V40Z box can handle 10s of DMT processes in parallel and whether the shared memory data distribution mechanism runs efficiently on the new platform.

PSL

PeterKing

After a suspected problem with the shutter in the 40m Lab 10-W laser, a shutter sub-assembly was requested from Lightwave.

TCS

Mike Smith

TCS

I verified analytically the beam sizes Dave Ottaway calculated, for the modification of the 4K TCS system with the 30W CO2 laser. I created a ZEMAX model of the new 30W TCS system.

Using the ZEMAX TCS model with paraxial Gaussian beam propagation, I can evaluate the effect of a limiting aperture on the visibility of Phil Willems' proposed mask design with radial spokes. It appears feasible to place a limiting aperture in the vicinity of the first periscope mirror. This aperture will pass the central Gaussian heating beam with negligible attenuation and will provide a simple means for changing the visibility of the projected spoke pattern on the ITM.

Ken Mailand

I gave Phil Willems information tuesday on the photo etching method of producing the laser mask.

Optical Contamination Cavities

Lee Cardenas, Liyuan Zhang

OTF Lab. (W. Bridge)   No Change

Cavity # 1

This chamber still locked with two samples, white Ceramabond, and disks of TRA-BOND #2254 color light brown epoxy. Cavity is clean  We are preparing the REO mirrors to be tested for contamination. These mirrors were tested for absorption at Stanford after different cleaning procedure.  We will make our own cleaning procedure and introduce it into the cavity.  These mirrors were tested before and found to have a large scattering

Absorption Test Measurement prototype in standby

Scatterometer system  in progress

\We have completed the scanning of the fused silica mirror: 4ITM05,  (scattering  loss ~30ppm ) for transmission.  Results of data will be released by Dr. Zhang

We are making the frame to hold the new HEPA in place.

The Quantronix 60 watt laser    In progress

Preparation for the large mirror absorption test

We have re-wired the power supply connection to match the power phase from the building.  We made all the cooling connections and turn on the laser.  Laser power is ~32 watt @ 30 amps of current.  It is stable good mode.

OTF Lab at Lauritsen ROOM 38 

Cavity #3 

The contamination test for (20) pieces of Glenair Micro-D-connectors still in progress.  Cavity is locked and we are taking measurements  for absorption and ring down for contamination loss every day. So far so good It needs another month for the test to be completed.

Cavity #2  no change


40 Meter Interferometer (Weinstein)


IFO commissioning:

  • Osamu is working on improving the speed of arm locking. The arms lock in only one fringe crossing when using RF locking with POX and POY. However, when the dual-recycled-Michelson (DRMI) is already locked, we need to use the transmission DC-offset locking, using the signal from the TRX and TRY QPDs. The QPDs are very noisy, and it takes many fringe crossings to grab lock. So, Osamu and Ben are looking at the source of the QPD noise. They found a ground loop on the cable between QPDY and interface board. Fixing this reduced the noise considerably. More improvement is possible.
  • Dan and Bob ran cables for three SP-beamline RFPDs being relocated to the ISCT-AP table. They took care to minimize potential ground loops. Dan plans to move the RFPDs on Friday.
  • Monica is working on calibrating LSC signals using a method suggested by Rana. She was able to lock the two arms (one at a time) in order to measure the ratio of the LSC excitations for the ITMs and ETMs. This info will be used to calibrate the DARM control signal.
  • The optical tables at the two ends (ISCT-ETMX and ISCT-ETMY) were re-laid-out by Dan, with help from Steve and Osamu, to reduce clipping, number of mirrors, replace some mirrors from 1" to 2", etc. Steve labelled all the cables. Steve and Dan measured the light power transmitted through the ETMs with the PRM misaligned and one arm locked (the other blocked); with 1.5 Watts on the PSL periscope, there was ~225 uW entering the optical table. Osamu calculated that this corresponds to transmission of around 5-7 ppm through the ETMs, close to specs. Dan is drawing up the changes, to be fed to Mike's ACad drawings.
  • Ben and Jay installed a thermocouple on 40m floor near the mode cleaner MC2 stack, to see if such variations are correlated with apparent mode cleaner length fluctuations (as monitored by the 33 MHz reflection from the MC). After 2 days, it shows a trend which may be indeed correlated with the MC frequency difference. Under investigation.
  • We are considering several options for locking the mode cleaner length to the 33 MHz sidebands, both during and between MC locks. This includes: heating up the 13 meter MC tube; servoing on the temperature of the frequency reference cavity, and servoing on the RF frequency itself.

IFO modeling and DC detection development:

  • Monica succeeded in using e2e to calculate the transfer function from Mach Zehnder displacement noise to the GW signal for the full DRFPMI with slightly unbalanced ITM reflectivities. Her results agree well with Seiji's calculations using Finesse.
  • Monica and Virginio are simulating error signal sweeps with e2e. The signals are rather complex due to the fact that the mirrors are sweeping faster than the arm time constants. In order to compare with the DC simulations from Finesse & Twiddle, They will try slowing down the mirrors in the simulation, or shortening the arms.

PSL:

  • The MOPA mechanical shutter in front of the power amplifier failed, and we could not bring the laser back up after an accidental trip. After some careful poking around by Osamu, the shutter started working again. Meanwhile, Peter King gave us a spare shutter assembly, and Steve ordered a spare brand new one from Lightwave.
  • Ben is building new ISS PDs for all sites, including the 40m.

Electronics, controls:

  • Osamu pointed out large offsets in the SP QPD signals. Jay and Ben looked at the QPD and its Interface Board, and found that the offsets were being caused by oscillations in the QPD head. These oscillations were fixed by adding compensation capacitors as per a DCN for that board. No offsets are needed anymore.
  • Ben has tuned an RFPD to 166 MHz for the SP beamline. It needs to go through the test procedure, and it will be delivered.
  • Todd is almost finished working on the 166MHz I&Q demod board for the new 166MHz PD at the SP.
  • The ITMX LL OSEM front end readback was not working. Ben removed the cable, re-soldered the LEMO connectors, electrical taped the solder cups, and re-installed the cable. It now works fine.
  • New RevB coil drivers for our BS, PRM and SRM require an obsolete part. Ben and Todd are scavenging parts from our old (pre-RevB) coil drivers; so we should have enough parts for the 3 new RevB coil drivers plus spares.
  • Some EPICS settings did not come back when rebooting crates. QPD whitening settings did not come back: this is a known problem with the 4116 DAC driver; Rolf will supply new driver code.
  • PRM and SRM oplev laser diodes both died (after some 1500 hrs). Steve replaced them and has spares.
  • Sander's new FI timing link was installed last week and has been in use since then. It was tested by Sander, Peter King, as well as Jay & Ben. It has excess jitter noise and big glitches, but the front end still functions. Under investigation.

Lab Infrastructure:

  • The particle counter (which also measures room temp and humidity, and we rely on it for diagnosing temp-related problems) stopped working 9 days ago; after a few power cycles, Steve got it working again.
  • Bob is pulling out some temporary cables in the lab that are no longer used to try and keep down the clutter on the floor and in the cable trays.

Bake oven Lab:

  • Bob is working with the shops on the bake lab remodeling to accomodate a new large air-bake oven for AdLIGO suspensions. They removed the old electrical circuits and plumbing yesterday 4-26 and took down a partial wall today 4-27. Tomorrow they will began drywall repair and painting by Tuesday of next week. The space for the new air bake oven should be done well ahead of schedule.
  • Bob completed two bake jobs on Tuesday morning and has shipped out a LOS structure to LHO and delivered a coating jig & counter weight to Helena.
  • Bob assisted Helena in the assembly of the Coating Jig on Wednesday.
  • Bob met with Mohana on wiring the OSEMs to the Quad Suspentions of testing.
  • Bob has received some photodiodes and emitters for cleaning and baking from Dennis. He will began this next week if the ongoing work in his lab will permit.

Thermal Noise Interferometer (Black)


This week, Helena checked on the status of the mirrors with advanced coatings, and they are on schedule for an end-of-May delivery.

Akira achieved first lock in the bond-noise experiment. There are some oscillations in the control servo whose origins we do not yet understand, but this is a common occurrence when putting together a new experiment. Seismic isolation is quite good, and residual noise in the pendulum is small enough that the shadow sensor stays more or less in the linear regime, even with the loop open. Akira is in the process of measuring the transfer functions of the servo to compare with expectations, and he is able to do so without closing the loop.

Jay and Alex are almost finished with the data logger for the bond-noise experiment, lacking only an inexpensive GPS receiver with a hardware interface. They expect to have something by next week, but if not, they can run temporarily with a function generator in place of the clock.

There was a lively discussion at the TNI meeting on Thursday about whether or not we should switch from 4"x4" mirrors to the 3"x1" mirrors used in Q measurements. The hope was that by standardizing on a common mirror size, there might be cost or schedule savings. All indications are that there are not. Going to 3"x1" mirrors at the TNI would require retooling of both the TNI suspensions and Jean-Marie's coating chamber, and the savings in material cost are expected to be comparable to the retooling costs, if not smaller. At this time, the best course of action appears to be to continue using 4"x4" optics for direct, broadband noise measurements.


LASTI (Ottaway)


LASTI Weekly (Ruet, Mittleman, Mason and MacInnes)

We have been investigating the ground noise amplification in the BSC support structure. Measurements have been taken of ground motion to the motion of the top of the pier in 6 DOF, a report will be on the Lasti ilog in the near future.

The sys-id  of the BSC in a pseudo-advanced LIGO configuration. Design of the control laws has started.

Ken is working on a FEA model of the BSC support structure and some nice progress has been made this week.


Data Analysis and Computing (Lazzarini)


Simulation and Modeling (Bhawal)

LHO 2k Interferometer Carrier Recycling Gain

(Hiro) Based on various FFT runs and analytic calculations, details of IFO including mode matching etc, seem to affect little on CR recycling gain, except for the mirror surface phasemap.

The recycling gain can be written as follows, which has only major contributions included. (No phase map effects included) gain = 4 / T(RM) / ( 1 + Lxy )^2 4/T(RM) is the maximal recycling gain, which is 142 using T(RM) =0.028.

Lxy is due to various losses. Using T(BS) = R(BS) = 0.5, Lxy is written as 2 * ( Lx + Ly ) / ( T(ITM) * T(RM) ) where Lx = Loss by ITMx + Loss by ETMx + Transmission of ETMx, same for Ly.

Based on FFT runs, mirror surface phase maps tend to reduce the gain by around 20%.

The major factor is the loss in the arm. Loss per arm per bounce of around 50ppm accounts for the recycling gain of 70-90. Based on FFT with mirror phase maps, the loss per arm for 4k IFO should be around 100ppm, not 150ppm, to have the measured CR recycling gain of 45.

Wave Front Sensor at LLO

(Biplab) Worked with Rana and Matt on optimization issues of WFS. As is known (elog Jan 27), WFS at LLO is working even though its Gouy phase settings are not at the optimal values obtained from FFT studies. We tried to have a proper telescope scheme that can provide the desired 90 degree Gouy phase shift to the beam in between the beam-splitter and WFS1. Suggested a solution with 2 reasonable lenses but it needs large (of the order of meter) optical path that cannot be easily accomodated on the bench.

Matt came up with another nice solution with 3 stronger lenses that could reduce optical path but strong lenses might have other issues to deal with. Also, it shows that anything that allows smooth adjustment of Gouy phases requires at least 50 cm of optical length after the position of 1st lens on bench (fixed due to other constraints) in theptical path leading to WFS1.

FFT simulation

(Hiro) Working with Keita and Rick to estimate the effect of the surface roughness on the g-factor measurement.  Provided a setup on halfdome for Keita to run FFT himself, and provided a minimal documentation.

Simulation of 40 meter Interferometer

(Monica) Preliminary simulations of sweeps for error signals have been done with the e2e package for the 40m interferometer,  but the used velocity is still too fast to investigate the DC response of the real interferometer. A slower velocity needs longer simulations if one maintains the 40m configuration. Just to verify the DC response, one can use the trick to slow down the velocity and at the same time decrease the length of the arms; in this way the simulation will be faster.

Simulation framework for Advanced LIGO

(Matt) Continued work on simulation framework for Advanced LIGO.  Some boxes now have contents, others remain placeholders to be filled later. Draft documentation on the organizational structure of the simulation is done, but more detail is required.

Modeler

(Hiro) I modified modeler codes to support the work of Matt building the advanced LIGO detector simulation.

Alfi

(Bruce) Working on speed issues regarding bundles for save and node validation.

(Melody) Continuing on fixing existing Problem Reports.  Currently working on the user interface for allowing the user to choose the display for primitive nodes: graphic or text.  Implemented an option to display the rename/delete dialogs to be displayed only once.

Fixed PR 466: external view window size change no longer affects the internal view window size.

Checked in all modified codes to CVS.

LDAS Software Systems (Maros for Blackburn)

LDAS:

cmonClient is being enhanced by addressing the issues related to PR 2724 (modify resource vars), PR2617 (headers for resource vars) and PR2336 (sorting of data by clicking on column). These changes will be part of the nightly builds by early next week.

Ran the weekly integration and system tests on LDAS version 1.5.53. All tests passed without incident. Updated compresstest to verify default compression.

TCLGLOBUS:

Must effort is going into the documentation process in preparation for the first alpha release of the software due out either Friday or Monday.  The documentation changes include full installation documentation including:

  • how to build needed 3rd party software
  • I/O and FTP Client sections for the TclGlobus tutorial.

Several test cases for FTP Client have been added to verify checksum, partial and extended file copy.

LDAS System Administration (Anderson)

Caltech

(Dan Kozak)

  • Figured out the discrepencies between the data holdings of the CIT nodes vs. ldas-gridmon's LDR and RLS and had Scott Koranda fix it.
  • Made some small improvements to lag plot.
  • Working to get Sun/STK to fix/replace broken 9940 tape drive.  New support contract==discovery of new social engineering techniques to actually get the work done.
  • Reinstating dual copy at CIT.  Mostly this amounts to making second copies of the S4 data, but I'm having to do it in chunks so that it won't hold up second copies (and therefore releasing) on new data.
  • Working on getting old LHO data that never made it to CIT copied.  Currently working on E10 rds data.
  • Some postS3 RDS data arrived via LDR and tape.  I'm comparing them and if the comparison is successful, deleting one of them.
  • Configured CIT's /archive/home to go to tape.

(Phil Ehrens)

  • Worked on a number of LDAS issues to support the impending release.
  • Continued work to integrate svn/Apache with grid proxy certificates.
  • Studied the grid certificate management protocols and documented the creation, installation and verification of client, server, and proxy certificates.

(Stuart Anderson)

  • Working on Astrowatch data management.
  • Modified the Condor configuration to support shorter running jobs.
  • Moved a few CIT cluster users to a different home directory server to balance disk utilization.
  • Investigated the first set of S4 h(t) frames and found a few issues with the metadata in the files which triggered a few problems with LDAS.

MIT

(Keith Bayer)

  • Replaced primary harddrive on cluster node 68.  Tried to use system imager to clone another cluster node but couldn't figure out how to only clone initial disk and not 200GB 2nd drive in the box.  So, I bailed and just did a dump/restore.
  • Added several more users to cluster.

Livingston

(Igor Yakushin)

  • Collecting the necessary information for LDAS room upgrade for S5 and behond.

Hanford

(Greg Mendell)

  • I am finishing up a planning report for the LDAS LHO and LLO power and air conditioning requirements for S5 and beyond.  I plan to also finish changes to the createrds scripts that I have been working on today and start testing them.  More about this next week.

(Ben Johnson)

  • Assisted Greg Mendell with power consumption/AC plans for [S5,S5+) computer room.
  • Published Xavi's h(t) frames at Caltech.
  • Helping track down publishing/LDR issues which are causing some A4 files to not be transferred.
  • Assisted PSU with the publishing process.
  • Resurrected the shell that used to be node100 (HDD swapped with node139 (old ldas-grid) some time ago). The power switch appears to have problems.
  • Continuing work on making publishing Gap-Free(tm). Something createRDSesque will be the future.

Data Analysis Activities (Anderson)

Weinstein:

  • Working with Lisa and Duncan on ringdown search
  • reading and reviewing S2 BBH paper and analysis results

Yakushin:

  • Testing and debugging LIGO-GEO quadruple coincidence script for S4.

Shawhan:

  • Made final modifications to the S2 LIGO-only untriggered burst search paper.
  • Archived old conlogger data files to free up disk space at the observatories.
  • Reviewed PowerFlux continuous-wave search code.
  • Modified 'readMeta' utility to handle 8-byte integers.

Mandic:

I continued working on understanding the LLO-LHO coherences in S4. I observed that (uncorrelated) glitches can lead to features in the coherence plots that appear significant. I also continued studying the S4 H1-H2 coherence - by studying coherences with PEM channels I hope to identify the structures observed in the H1ASQ-H2ASQ coherence plot.

General Computing (Wallace)

MIT:

(Keith)

  • Continuing to setup LDAP test network as time permits
  • Ran benchmarks on various GC hardware
  • Ordered replacement webserver machine (SunBlade 1500)
  • Ordered various computer parts

Livingston:

(Shannon)

  • Added two fiber interfaces to the router Tuesday night which required about 10 minutes of downtime.  This is the flashed card that Syskonnect sent from Germany that finally arrived with a bug fix.  However, it only works in one of the two PCI-E slots.  I have emailed them and they claim to be aware of the problem and have since released another patch which requires flashing the EEPROM on the card.  Working on a security package that will be installed on the router.  It will work as a basic IDS on the border which should give me an idea of the number of portscans, etc. that we see on a regular basis.  It also has the ability to automatically block offending IPs.  I will have to make sure that it has a facility to whitelist some addresses before I enable it.
  • Still working on an LDAP/mail server migration.  Some parts of it are in place and some of the configuration is done.  This will likely take a couple more weeks to finish testing and possibly roll over to it.
  • Several user support issues this week.
  • Working on renewing our Matlab license maintainence.  Received a formal quote yesterday.
  • Working a Maple software issue with the Caltech license server.  For some reason we cannot authenticate against their license server, even though the software@caltech folks claim there is no filtering on those ports by address.
  • Was out all day Thursday.

Hanford:

(Christine)

  • Network usage can be seen at http://www.ligo-wa.caltech.edu/~christin/mrtg/198.129.208.1_198.129.78.122.html
  • Moved some computers around to prepare for the power outage.  Tried to get all my servers in one room and on the UPSs in the server room.  The plan was to power the UPSs from generators, keeping all the network equipment and main servers running through the outage.  Turned out the generators couldn't provide clean enough power for the UPSs so everything ended up getting shutdown.
  • During the shutdown, I cleaned up some wiring in the server racks and redistributed power more evenly over the three UPSs.  Also, removed some old computers and cleaned up the Computer User Room.
  • When power came back everything came back on-line without any problems.  It took me 30 minutes to have the network and all GC computers back up.
  • Since the smaller UPSs performed so poorly, they will be replaced with a larger 7.5 kVA UPS.
  • Received a price quote to review from Amerion for a backup network path between Richland and Seattle.
  • Other miscellaneous user support.

CIT:

(Mike)

  • Project Management: Did some final work on the VPN server, and continued to work on a step, by step instruction cheat sheet for users to setup their local workstations. Carol Wilkinson, and Dwight Carter are now able to access the VPN server, and login to the PRISM software.
  • IP Database: Finished up going through a majority of the computers located in W/B. This also included running OS & Security updates on all window boxes.
  • Surplus couple of computers & laptops. I wiped the hard disks clean and took out few parts that I needed for other working computers that users are currently using.
  • Found two visitor workstations that were infected with viruses. This will require a complete rebuild on both of these units. I have started the reloading process.
  • Linda Turner: Order a new replacement CDRW/DVD ROM drive from Dell.
  • Continuing to work the Spam filters with Larry Wallace.
  • Much other onsite/phone user support, that included setting up users accounts, trouble shooting software, and printing issues.

(Veronica)

  • LIGO:
    • Working with Carol Wilkinson on the AdvLIGO-related databases and web interfaces.  Carol, Dwight and I went through the existing costbook database, P3, their web outputs, and the steps required for their maintenance.  The long-term plan is to redesign the database and redo the webpages.
    • Videotaped the s/w demo by Agile for the DCC.  Will post the stream as soon as I process the tapes.
    • Prepared high-resolution images for a publisher.
    • Updates to the PAC and other webpages.  Finished the website for Barry and shipped it off to Julie.  Roster database updates.  Windows servers security audits.  Installed a printer driver for Marco / Yuri.
    • Working on the regeneration of the authorship list for S3.
  • LSC:  Working on the website for the upcoming LSC meeting.
  • Project Science:  Working on transferring the website over to the TMT.

(Larry)

  • Checked on a number of purchases. All of the orders checked on are just late in shipping but the orders did go through. Distributed a couple of orders that have arrived.  In the process of obtaining quotes for a number of different computers to be used in the server room. All are designated for specific purposes with a couple to be used as upgrades to existing servers.
  • Getting the license issues checked out to see if CIT Matlab license can be used at the Observatories. We should have the needed information from Caltech by next week.  Working a couple of network related issues with Christine and Albert. Along that line CIT did inform us that they could not supply IP addresses for the Observatories.
  • Finally, put a new quad cpu sandbox on-line. After multiple rebuilds, the problem turned out to be a typo in one of the initializing scripts. A few people have been asked to test out the box. We already know that it needs more memory.
  • Spent a full day looking for some documents on an old deleted account. Once again that account has been burned to CD and distributed to the people that would have use for it. A couple other copies were made and put in storage in-case the CD's are lost again.
  • Assisted Irena with a couple of computer issues. The application used to launch some of her programs needed to be reconnected to the shortcut icon and a couple of drives needed to be mapped on the system.
  • Working on a number of logistical issues, with Carol W. and the rest of the group, to cover some of the Advanced LIGO planning and support. We will be providing mostly background support for the planning group.
  • Worked a number of different computer issues for different people. Put in some more support for the E2E group with at least a few days worth of work still needed to get their equipment back up to par.
  • The usual account and maintenance support.
  • The spam filter work has been increasing. However, more people have been supplying addresses that they would like to have white-listed and that does help drop the number of e-mail messages we need to check.

 

Mail Statistics for April 21-27, 05

Rejected Messages                                            21,691

Virus Messages                                                   3,863

False Positives                                                       229

Accepted Messages                                          20,698

Total Messages                                                 42,389


Advanced LIGO and Supporting R&D (Shoemaker)


Seismic Isolation

From: Ken Mason kmason@ligo.mit.edu

SEI Structure:

A BSC finite element model has been created in Algor to help explain the pier amplification and model possible solutions.

Myron has begun assembly of the spring characterization fixture supplied bt ASI. We had to order special nonstandard keenserts which were missing. I also ordered "dummy" blades of 4140 steel to test the operation of the fixture.

Thermal bars were ordered for the large and small actuators in preparation for additional thermal studies to be done by a UROP student over the summer

Suspension

From: Janeen Romie <romie_j@ligo.caltech.edu>

Advanced LIGO Suspensions

Working on schedule updates, project status and budgeting for our meeting with Carol and Dwight.

Checking drawings for Calum.

From: Ken mailand <kmailand@ligo.caltech.edu>

I have worked with Helena to produce an air bake oven specification for the LASTI parts.  The Grieve Co. quote is ~$18,700 for the CAH series oven, 36x36x60 size, we have two other quotes, both higher, for equivalent features, HEPA filters etc.

We have received 4’” S.Stl. stock for the lower suspension installation arm fabrication, and one set of the roller bearing with lip seal for the pivot shaft.  I've nearly finished the detailing of the component arm parts, and  list of the purchased parts, bearings etc.

Core Optics

From: Helena Armandula <ahelena@ligo.caltech.edu>

Adv. LIGO SUS

Modular Clean Room

The P.O was placed for the modular clean room, manufacturing started.

Oven

We are waiting for the last modified (changed dimensions) quote to place the oven PO

Pre-Stabilized Laser

From: Peter King pking@ligo.caltech.edu

Testing of the new photodetector boards was on hold as I was busy with the electro-optic timing system measurements.  However the initial prototype testing continues.  The photodetector has been running for over two months now at over 250 mA without any problems.

Auxiliary Optics

From: Michael Smith <smith@ligo.caltech.edu>

BS DIFFRACTION LOSS

I am revising the BS model by incorporating a lens element into the reaction mass (plano-convex, with R = 9m) in front of the ITM to reduce the beam size at the BS from 60mm to 46.7mm. This change significantly reduces the total loss of the input beams from the power recycling and signal recycling directions with the baseline dimensions of the BS (350mm dia, 60mm thickness). Also, the power recycling beam position on the BS HR surface is placed at the center of the surface; this minimizes the power loss from the signal recycling direction.

Other Laboratory R&D

From: "Erika D'Ambrosio" <ambrosio@ligo.caltech.edu>

Juri

I fixed the locking problem in my simulation program, now the gain factor is exactly what expected from theory, given by the mirror parameters.  Moreover I used the two maps, 5008 and 5009, provided by LMA for our Mexican Hat mirrors, in my simulation of the FP cavity and I found a considerable difference in the expected beam profile due to the fact that after the corrective coating treatment, both mirrors present a slightly deviation from theoretical ideal shape which affects substantially the beam shape. This effect can be partially corrected with a mirror tilt and I calculated the tilt angles using the best interpolating plane on the differences between the ideal and the real mirror profiles in the central area. Running some simulations for the characterization of the cavity with the spherical end mirror and comparison with data collected by Marco.

Marco

I'm continuing the cavity characterization. In particular the alignment has been improved so that we collected data of the lowest Laguerre-Gauss transverse modes. I also tested PZTs and driver behavior: their correct working allowed a first scanning and the collection of the first spectra of the cavity resonances. From the g-factors point of view, our cavity is nearly-confocal and so very degenerate. It can explain, for example, the strange residual of the TEM10 that looks like a TEM22.  Next step should be improving in the beam profile acquisition and in the servo lock through a transmission signal and laser modulation (Matt's suggestion) or mirror dithering lock technique, in order to "clean" the beam from cavity degeneracy locking on the peak of the Airy function.

Riccardo

Juri AGRESTI, Erika D’AMBROSIO, Riccardo DESALVO, Daničle FOREST, Patrick GANAU, Bernard LAGRANGE, Jean-Marie MACKOWSKI, Christophe MICHEL, Jean-Luc MONTORIO, Nazario MORGADO, Laurent PINARD, Alban REMILLIEUX, Barbara SIMONI, Marco TARALLO. Phil WILLEMS

Mesa beams are optical modes of cavities with nonspherical mirrors designed to broaden the beams impinging on the mirrors. One of their advantages over Gaussian beams is that they are less sensitive to thermal noise fluctuations, especially thermoelastic noise, because of their broad and flat distribution over the optics.  They also have steep tails for minimizing diffractive losses at the optics edges and reducing sensitivity to beam centering offsets. We review the features of mesa beams and the cavities that produce them, outlining how they can improve gravitational wave interferometer sensitivity. The Advanced LIGO choice of fused silica substrates for the core optics, has changed the case for mesa beams from Thermo-Elastic Noise reduction to coating thermal noise reduction and triggered a new set of optimization studies. We present the latest data from our prototype mesa beam cavity at Caltech, aimed to test this new technology and validate its expected behavior.

Influence of different beam shapes on different kinds of Thermal Noise.

Juri Agresti, Riccardo DeSalvo

Thermal noise of the test masses is one of the most important noise sources limiting the sensitivity of advanced interferometric gravitational wave detectors. The mirror’s surface thermal fluctuations are averaged according to the beam intensity profile. A large radius, flat-top beam with steep edges is expected to have better averaging properties with respect to the conventional Gaussian beam. We present direct calculations of the spectral density of thermal noise contributions from various sources (coating and substrate Brownian and thermoelastic thermal noise) for various sizes of test masses and different beam profiles. We evaluated sensitivity and “reach” improvements that can be expected from the next generation of detectors using non-Gaussian beams with Flat Top profile.

OPTIMIZING MULTILAYERED DIELECTRIC MIRROR COATINGS FOR THERMAL NOISE

J. Agresti, G. Castaldi, R. De Salvo, V. Galdi, V. Pierro, I.M. Pinto

The current design for dielectric mirrors consists typically of quarter-wavelength alternating SiO2 and Ta2O5 layers. The sensitivity of Gravitational Wave interferometers is usually limited by the Thermal Noise (TN) of the mirror coating. The TN power spectral density is roughly proportional to a weighted sum of the two constituents TN-wise, the usual quarter-wavelength design, which maximizes reflectivity, does not yield the best sensitivity.  We undertook a series of numerical experiments using a genetic optimization engine, seeking for a required transmissivity with minimal TN.  Preliminary results showed that the Genetic Algorithm (GA) evolves toward results close to periodic half-wavelength bi-layers with a reduced fraction of Ta2O5 and an increased number of layers N. The quasi-periodic stacks determined by the GA offer small performance improvements than the corresponding fully periodic, optimized-Ta2O5 fraction, solution.  We investigated the design of half-wavelength period coatings where the SiO2-Ta2O5 thickness ratio is left as a free design parameter. We obtained families of trade-off curves in the transmissivity-TN plane, for different values of N, parameterized in the Ta2O5/ SiO2 thickness ratio . For fixed transmissivity, the minimal noise corresponds to well-defined values of N.  We investigated the sensitivity to random errors in the dielectric layer thicknesses.

Design and prototype tests of a Seismic Attenuation System for the Ad-LIGO Output Mode Cleaner

A. Bertolini, R. DeSalvo, C. Galli, G. Gennaro, M. Mantovani, S. Márka, V. Sannibale, A. Takamori, C. Torrie

To achieve its design performance, both present LIGO and Ad-LIGO will need an Output Mode Cleaner (OMC). Although suitable vacuum chambers (LIGO HAM) are readily available, a seismically attenuated platform to provide adequate seismic isolation of the optical table is still necessary. One of the most straightforward and cost effective solutions is a passive seismic attenuation option, derived from the SAS concept. We completed a conceptual design, fit for the LIGO HAM vacuum chambers and built prototypes of the critical components. This single-stage, passive attenuation unit, has expected performance matching the requirements set for the LIGO, and even Ad-LIGO optical tables. It is also fully compatible with the baseline active attenuation systems designed to isolate the Ad-LIGO core optics. Design parameters and initial prototype test results are presented in this talk. The system passive performance can be improved, if necessary, by implementation of an additional but simple active attenuation loop at marginal additional cost.


For additional information about this report, contact Stan Whitcomb or Phil Lindquist