Weekly Report for
Week Ending April 21, 2005
The LIGO Executive Committee
Agenda for Monday April
25, 2005 will be:
(Meeting time: 10:30 am Pacific Time)
- Announcements
- Comments on Weekly Report
- LSC Issues (Saulson)
- LIGO Lab Operations
- Administration
(Lindquist)
- Sites (Raab,
Zucker, Shoemaker)
- Commissioning
(Fritschel), Detector (Coyne)
- Campus Research
Facilities
- 40 Meter
(Weinstein)
- TN, ( Libbrecht)
- LASTI (Shoemaker)
- Data Analysis and
Computing (Lazzarini)
- R&D and Advanced LIGO
(Shoemaker)
- CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION AS NEEDED
Special Items:
Special Announcements:
Safety Review at Hanford May 2, 2005.
Weekly
Report Highlights
LSC Issues (Saulson)
No report
LIGO Laboratory
Administration (Lindquist)
Status of LSC MOUs (Petrac)
LSC MOUs and Research Plans and Progress Reports
- LSC
MOUs / Attachment updates for Feb. 15 2005 through Aug. 15, 2005: The updates for all active
Attachments for all current non-LIGO LSC groups are in the sign-off by the
LSC Spokesperson / P. Saulson.
Non-LSC MOUs
SITE TELECONFERENCE (Lindquist)
A site teleconference was held on Thursday, April 7, 2005. The
following issues were among those discussed:
- Action
No. 124: The Tax Tree has been provided to Fred Raab. Comments have been returned and
are being incorporated. The
revision will be distributed for comment and then used to update the
Procedures Manual in an effort to get that document distributed.
- Travel
Training for Livingston: Ed to contact Bonnie and check with Travel
People at Caltech to ascertain schedules.
- The
list of assigned actions updated through March 10, 2005 will be found Here.
PROPERTY MANAGEMENT (Chargois)
>From: Ed Chargois <chargois_e@ligo.caltech.edu>
- Assisted
the Detector Group (H, Armandula) with packing and shipping of two (2) AR
coated Substrates (BS01-02 and BS02-06) to Stanford University (R.Route)
for absorption measurements.
Account Number P204296.
- Assisted
the Detector Group (P. King) with shipping of a Signal Analyzer, Serial
Number 46506, to Stanford Research Systems for repair. Account Number P204324.
- Assisted
General Computing with packing and shipping of a Dell Laptop Computer to
LLO, R.Riesen/S.Roddy. L.
Jones previously used this computer.
Account Number P204275.
- Campus
Property Inventory Continues.
DOCUMENT CONTROL CENTER (Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- packages:
in - 10, out - 7
- faxes:
in - 29, out - 21
- No
special projects to report.
COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman, Salone)
>From: Esther Cunningham <esther@ligo.caltech.edu>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Reconciled
12 pcard transactions for the month of April 2005 totaling $3,639.16 and
submitted to management. Obtained copies of missing invoices and the
obtained the credit for the educational discount from New Focus that was
not applied to the original invoices.
- Prepared
the Release of Claims and submitted it to MLD.
- Completed
change order #160 to Triad for a rate increase change. No additional funds
were allocated. Requested and received updated certificates.
- Cancelled
the Pratt requisition as it has already been renewed on the pcard.
- Working
on the order to Mitsubishi.
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Florence Kaufman <fkaufman>
- Received
notification that NSF has approved the balance of the funds for FY05. Responded to request from
Sponsored Research to show how these funds should be allocated to the
budgets in the LIGO accounts.
- Completed
and sent out reports for DIA, Low Noise, MIT GRID, and AJL.INT awards as of
the end of March 2005.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)
>From: irena@ligo.caltech.edu (Irena Petrac)
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- There
appear to be additional issues with the LSU/NSF lease amendment as raised
by LSU's attorney. Sandy
Pool, Caltech Associate General Counsel, is pursuing these issues and
hopes to have resolution shortly.
In the meantime, we do not have an executed amendment. [Whoops, late breaking news: Ed
just spoke to Sandy Pool, and he had just received the executed amendment
to the LSU/NSF lease. Sandy
will bring the lease by tomorrow, and Ed will mail copies--pel.]
- The
LLO SEC architect, EDR, has pre-qualified six construction contractors to
bid on the Sec construction.
EDR will submit the 50% completion drawings tomorrow, and they are
still on track to submit the 100% drawings by the end of May.
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
- Processed
the paper work for nine (9) new/revised trips. At this time there are thirty (30) new trips that need
to be completed and ticketed before the paper work can be completed. Assisted several LIGO personnel
with their travel arrangements using their P-Cards and made several
reservations for outside visitors coming to LIGO/Caltech for meetings
and/or workshops. LIGO will
be sponsoring thirty-eight (38) SURF Students this summer and I have
already started arranging these trips. We have twenty-six (26) coming to LIGO/Caltech, seven
(7) to LIGO/Hanford, and five (5) to LIGO/Livingston.
- Completed
seventeen (17) Expense Reports and there are four (4) reports yet to be
done. I continue to contact
travelers who have outstanding Expense Reports (more than one (1) month
old) to ask for their cooperation in sending me their receipts so that
these can be closed in a timely manner. Presently there are three (3) reports more than 30 days
old.
>
- No
special activities to report.
>Dorothy Lloyd
- Nothing
significant to report..
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
PROPOSALS and REPORTS (Lindquist)
The Annual Report for the Visitors Program is basically complete and entered
into FastLane ready to “push the button.”
A proposed draft has been distributed for outlines for the Annual Report for
Operations and a Proposal for an Extension for FY 2007 and FY 2008. Some comments have been returned. We will begin working these documents
pretty furiously between now and August 1.
DCC Steering Committee (Lindquist)
No document management systems demonstrations could be scheduled this
week. We did meet to discuss
status and possible system demonstrations next week (April 27, 2005).
Two document management systems demonstrated so far appear promising,
OpenEDMS and Synergy. Synergy only
supports an Internet Explorer web browser and appears closely married to
Microsoft applications. It does
work well on Internet Explorer.
The system is polished and would require minimal training. They have provided a quote for a
FireFox version at some extra cost.
Some have tested Synergy with other browsers, and they do not appear to
work.
OpenEDMS does not guarantee that browsers other than Microsoft Explorer will
work, but they are poised to release a LINUX version. It was noted that the higher cost systems tend to provide
the support for multiple browser platforms.
Two additional document management systems are interesting. Agile (GO Engineering) is scheduled for
a demonstration next Wednesday. GO
Engineering already gets high marks for their support of some of our CAD
systems and they seem motivated to help us.
The other possibility is a document management system developed by Xerox
called TokOpen. On the surface it
appears to meet our general requirements.
Linda has forwarded our requirements and general vendor questions to the
TokOpen representative for a cost estimate. It appears we would require several of the modules to meet
our requirements, which may place this system on the higher priced end.
We will coordinate the demonstration for Agile next week and will distribute
additional information as it becomes available.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- No
special activities to report.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
- Nothing
significant to report. There
will be a safety audit at Hanford on May 2, 2005. A proposed agenda has been
distributed for comment.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of Commissioning Activities at LIGO
Hanford Observatory (Landry)
Highlights from this week in elogs are bulleted below:
4K IFO
- a
thermal camera could not see
the heat produced by the interferometer on the 4k ITMX
- cavity
pole measurements using techniques other than ringdowns were begun
on the 4k, and continued here
- saturations
in demod boards may produce upconversions:
a study to replicate wind-induced noise suggests this
- the
x-arm thermal compensation system (TCS) central heating calibration is
comprehensively reviewed in this elog,
complete with handy background material and artwork. Later, the y-arm
was done.
- g-factor
measurements continue apace
- carrier
and sideband buildup during IFO powerup are plotted
2K IFO
- ASPD1
was modified
after the photodiodes were characterized
- shot
noise was measured on the 2k, input to a simple noise
budget
- the
2k main oscillator was swapped, with zero
effect on the noise
- new
DARM filters mean the 2k calibration has to be updated
- larger
unity gains on 2k WFS are being applied,
as was recently done on L1. Followup for WFS2 was sketched here.
- One
of the mainline experiments performed this week was the power-up into the
interferometer. Power was ultimately increased
to 2.8W, but unfortunately this had almost no effect on the calibrated
noise curve. Instead, another noise source is exposed, possibly
oscillator phase noise, and the shot noise is likely below the SRD.
- 39.33MHz
is seen
on the 2k AS photodiodes
Outreach (D. Ingram)
LHO, the Tri-City Astronomy Club and Columbia Basin College's Moore
Observatory joined forces for a National
Astronomy Day program that was well attended in spite of cloudy weather
that prevented sky viewing. Thanks to several LHO staff who helped.
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
No report.
Initial LIGO Detector Science & Engineering
(Coyne)
CDS
see also the CDS weekly meeting minutes in the commissioning archives
CDS Software
no report
CDS Hardware
LSC RFPD
Ben Abbott
1) Todd is working on some PDs that will be tuned to 24.5
MHz and 29.5 MHz.
2) I ordered boxes from Compac. They should be ready
for machining in 6 weeks.
E-O Fiber-based Timing Link
Peter King
I have spent quite a bit of time trying to understand how to drive the
serial data analyzer that we rented to measure the timing jitter from the
electro-optic fiber-based timing system. The instrument did not have the
latest bug fixes in the firmware, which led to some measurements bombing out
every now and then. Things have been sorted out now and measurements of
the fabricated units can proceed.
(no other reports)
DMT
John Zweizig
This week I have been generating data quality segments for
Wind (LHO ony so far) acoustic noise and optical coupling between IFOs (i.e.
when H1 is lock and H2 in unlocked). I have also started to upgrade DMT
infrastructure with the goal of generating ONline data quality information for
S5.
PSL
PeterKing
The long-term photodetector test continues. So far so good. No
obvious problems.
Dave Grimmett tested out a little signal processing circuit for me.
The transfer functions were within expected values and the unit performed just
fine. Although there was a slight problem with the power supply.
Optical Contamination Cavities
Lee Cardenas, Liyuan Zhang
OTF Lab. (W. Bridge) No Change
Cavity # 1
This chamber still locked with two samples, white
Ceramabond, and disks of TRA-BOND #2254 color light brown epoxy. Cavity is
clean! We are waiting on new samples to be tested for contamination.
Absorption Test Measurement prototype in standby
Scatterometer system in progress
\We have completed so far the scanning of the following fused silica
mirrors: 4ITM04, 4ITM05, AND 4ITM08 and the one that give the lowest
scattering loss ~30ppm is the 4ITM05 and this is the one we'll
concentrate to do the rest of the measurements.
The new HEPA is ready to be installed after wiring completed for power.
The Quantronix 60 watt laser It is shut
down for now
OTF Lab at Lauritsen ROOM 38
Cavity #3
The contamination test for (20) pieces of Glenair Micro-D-connectors still
in progress. Cavity is locked and
we are taking measurements for absorption and ring down for contamination
loss every day. So far so good. It needs another month and a half to go before
the test is completed.
Cavity #2 in progress
40 Meter Interferometer (Weinstein)
IFO commissioning:
- Having
fixed a bunch of problems, Osamu has once again succeeded in
DC-transmission locking of both arms while the dual-recycled Michelson
(DRMI) is locked, thus controlling all 5 length degrees of freedom. Lock
holds for up to ~ 5 minutes at a time.
- It
was taking a while to lock the Y arm; Osamu concluded that this was
because the arm is too quiet (in the middle of the night, with STACIS
off). He tried pushing ITMY with the LSC system and was able to acquire
lock quickly.
- This
is interesting: seismic noise is so low at night that we need to push the
mirror to lock! Is it believable? Rana, Rob and Monica measured mirror
velocity with a free-swinging Michelson; at 6pm (rush hour) it was around
3 um/s. In the middle of the night, it could be 10x less; to be measured.
If this is right, it means that we need neither STACIS nor a suspension
point interferometer.
- Osamu
is now working on using POX and POY to transfer control of the arms from
the DC offset transmission lock to RF lock, so that we can smoothly move
the arms to their resonant peak; at that point, we hope to achieve power
recycling and RSE (if we can hold lock long enough!).
- The
problem with POX and POY is that the signals from the 2 arms are almost
completely coupled; so it is hard to keep control. Work will begin soon on
getting good CARM and DARM signals in the presence of the DRMI.
- Steve
and Osamu made more tests of the noise on ITMX, which seems anomalously
high. There is a large coupling from pitch and yaw motion to the side OSEM
sensor. Perhaps the OSEMs are optically coupled to one another? They
turned on and off individual OSEM LEDs and saw no anomalous
cross-couplings from OSEM to OSEM. From ringdowns, there's no evidence of
mechanical problems like touching. Perhaps the side OSEM magnet is
mis-placed somehow?
- Osamu
found that the clearest monitor of the noise from ITMX motion to the main
beam comes from the SP QPD, despite a lot of extraneous noise there. He
was able to reduce the noise by reducing the OSEM damping gain on ITMX.
Noise on the oplevs was also reduced. We conclude that the damping gain
was too high, tying the optic too tightly to the shaky stack. Osamu will
try to optimize the damping gain of ITMX, and then try to do the same for
the other optics.
- Dan
is preparing to move the SP RFPDs from the SP table to the AP table (much
shorter beam path). He and Bob ran some cables. The RF cables need to be
heliax; Bob will order some more.
- Monica
is working on calibrating LSC signals using a method suggested by Rana.
- If
we implement a suspension point interferometer, we'll want to actuate on
the stacks to lock it, thus reducing the differential motion between the
ITM and ETM tables in each arm. We plan to actuate using the STACIS PZTs.
Virginio is drawing up a plan and proposal. He has figured out how the
STACIS boards work and where a signal can be brought in. Steve has had no
luck getting schematics from the STACIS manufacturers (TMC).
- Riccardo
proposes replacing the STACIS with inverted pendula as a platform for
actuation. Steve forwarded information on the chambers and stacks to Ric
so that he can make a design proposal.
- If
we implement a suspension point interferometer, we'll borrow some of the
light power now going to the "initial pointing" beams. Steve and
Virginio measured the power in those beams (around 9 mW from a 1.5 W input
beam). and calibrated the QPD_SUMs that monitor them.
IFO modeling and DC detection development:
- Monica
found a problem with her use of the PSD module in e2e by comparing with
transfer functions of e2e data computed in matlab. She now knows how to
use the PSD module correctly.
- Monica
is modeling the transfer function from Mach Zehnder noise to the AP port.
- Monica
is using the implementation of radiation pressure in e2e to
understand/simulate the optical spring effect.
- Rob
continues to study quantum noise and Tom Corbitt's code.
- Rob
continues to develop controls wrappers for Finesse.
- Important
side projects, waiting in the wings: (1) design and implementation of DC
detection system, including output mode cleaner, mode matching telescope,
DC photodiode; (2) possible suspension-point interferometer; (3) servo to
keep RF sidebants at resonant peak in the mode cleaner; (4) commissioning
the new ASC system, including initial pointing servo and WFS; (5) analysis
of and reduction in Mach Zehnder noise; (6) calibration of all LSC
signals, noise analysis in various IFO configurations; (7) common mode
servo; (8) suspension diagonalization, coil balancing; (9) suspension
damping gain optimization; (10) calibration of all OSEM dofs, oplevs, LSC
signals, ASC signals.
PSL:
- Dan
is trying to determine the causes of ISS drifting and saturation. There is
a complex coupling between the ISS and the PSL FSS, Mach Zehnder, and Mode
Cleaner. He will try to develop good diagnostics and maybe a slow loop (or
alarm) to re-acquire lock in the Mach Zehnder when the ISS saturates.
- Ben
will look into getting a spare ISS board to see if it works better than
the one we have, which has large offset drifts.
Electronics, controls:
- Osamu
noted that the TRX, TRY QPDs have insufficient dynamic range to function
both during lock acquisition and control. He changed resistors on the QPD
heads to change the gains. He noted a lot of dust on the QPD photodiodes!
- Osamu
noticed that the EPICS x/y plots for the QPDs come from EPICS monitoring,
not the front end, and they have large offsets and thus are not reliable.
Ben is working on getting front end monitoring signals (whose offsets are
zeroed) into the EPICS plots.
- We
rely on ezcademod for various lock acquisition and diagnostic studies.
However, it sometimes gets garbage numbers (due to flaky ethernet
connections?) causing the front end to crash, requiring reboot and
re-alignment; a big problem. Rob will see if we can fix the ezcademod code
(in consultation with Stefan and Alex) and replace the suspected ethernet
hub.
- On
Thursday, Ben helped Sander place his FO Timing link modules in place in
both ends, and the vertex SUS crate. They were not powered up, or cabled
in, just set in place. Bob ran FO cables to the various racks.
- Then
on Friday, Ben and Jay and hooked up and tested the FO timing link. Simple
tests showed that it is functioning. More in-depth testing will be
performed by Sander once he learns how to use the test equipment that he
rented.
- Ben
replaced the 1mm photodiode in the 166MHz RFPD at the AP, and it now works
again. It looks like the photodiode got fried.
- Ben
has filters boards for the frequency multiplier circuit. He will stuff and
test it soon.
- Ben
is getting a new 166MHz RFPD for the SP, and Dan and Bob will run the
cables. The electronics chain and LSC software should all be in place for
it.
- Ben
is checking on progress in new RevB coil drivers for our BS, PRM, SRM.
Some components are no longer available and they may be able to scavenge
parts for 2 of the 3 boards.
Bake oven Lab:
- Bob
made 2 doz pin plates for hybrid osems for janeen.
- Bob's
bake oven lab will be ripped apart to put in new large air bake oven (for
AdvLIGO suspension work). The lab will be shut down through May.
Everything should be back up by June 15, when Bob is scheduled to be
baking a large AdLIGO load.
- Bob
has obtained a work order and met with the shops, and is rearranging some
equipment and storing supplies, in preparation for the remodeling and installation
of the large oven.
- Bob
has constructed a new seven channel temperature/ vacuum controller for
oven "E".
- Bob
has received and is baking the parts for a Optical Coating Jig for Helena.
- Bob
expects to receive a LOS Structure tomorrow, Thursday, to clean and Bake
from Hanford.
Thermal Noise Interferometer (Black)
Nothing significant to report this week.
LASTI (Ottaway)
No report.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
FFT simulation
(Hiro) Addendum to the talk
given last week was circulated to the commissioning group. The note demonstrates that the phases of Carrier and Sidebands, not only the magnitude,
are insensitive to input beam mode
status. The note also contains a
table of various overlapping integral of Carrier and Sidebands.
Keita wanted to run FFT himself
for his analysis, so a simple setup was provided for him to carry out FFT runs
easily.
Some FFT runs are going to
relate various losses in Core Optics and the Carrier recycling gain.
Outreach: Input Optics simulation
(Biplab) Helped Sany Yoshida
and his students at Southern Louisiana University to solve all outstanding
problems and issues related to proper integration of the Input Optics
simulation set-up inside SimLIGO. The Feedback to Mode Matching Telescopes(MMT)
and study of the effects of MMT motion on interferometer are the next steps.
Mechanical simulation
(Mark Barton) I continued to
run test cases on the E2E boxes I built to represent the AdvLIGO triple and
quad pendulums. I also took delivery of and have been reviewing a Mathematica
package by Ben Lee (of David Blair's group at University of Western Australia)
which implements violin modes in a quite different way from the
beads-on-a-massless-wire approach I've been pursuing. He solves the full
equation for an elastic beam with mass under tension for the modes in the
frequency range of interest and then combines the results with the output of my
pendulum toolkit to give realistic thermal noise plots.
Simulation Framework for Advanced LIGO
(Matt) Worked on simulation
framework for Advanced LIGO. Thus
far this is only a shell; a collection of placeholders to be filled in by the
designers of each sub-system.
Documentation on the organizational structure of the simulation is also
underway.
Simulation of 40 m interferometer
(Monica) Solved the problem of
discrepancies between e2e and Twiddle transfer functions for minor signals: the
psd module works fine when the system is stable. Previous simulations started at a trigger time too short for
the minor signals, so the first averages done by the psd module were not
trustable. Minor signals take longer to get stable than the main signals
because their cavity pole is at a lower frequency than the one of the main
signals that have been recovered from the beginning.
Simulation with e2e of the
effect of the Mach-Zehnder noise in terms of DARM degree of freedom: results
are compared to the simulation done by Seiji Kawamura with Finesse.
Squeezed Light in e2e ?
(Biplab) Exploring the
possibility of implementing the 2-photon formalism for simulation of quantum
fields inside interferometer models [Ref. Corbitt, Chen, Mavalvala,
LIGO-P030070] in e2e without making too much modification in code at this point
of time to test some elementary results related to the use of squeezed light
for reducing shot noise.
e2e programming
(Hiro) Codes are being
developed for the fast dual recycling cavity simulation and for the support of
different time steps [generalization of the Analogue to Digital
Converter(ADC)and the reverse (DAC) process] transparently.
Alfi
(Bruce) - Working on speed
issues for save and node validation.
- Many minor misc items brought up by users currently
using Alfi heavily.
(Melody) Continuing on fixing
existing Problem Reports. Currently working on the user interface for allowing the user
to choose the display for primitive nodes: graphic or text. Working on an option to display the rename/delete dialogs to
be displayed only once. Modified
the FUNC_X document for review.
Data Analysis Activities (Lazzarini)
Charlton:
I have written a script to
automate running the stochastic pipeline in Condor. The script takes as input:
1) a file containing the list of science segments obtained
from SegWizard (the same jobs file used by stochastic.m)
2) the stochastic search parameters file (the same
parameters file used by stochastic.m)
3) some other parameters to tell it where to put the
products and produces:
a) frame cache files suitable for stochastic.m
b) a DAG file for running the stochastic analysis jobs
Cache files will only be generated if they don't already exist, except if the
--force option is enabled. This saves having to talk to the LSC datafind server
every time the stochastic pipeline is run. This has now been checked into CVS in the matapps hierarchy.
Further minor changes will probably be necessary as we discover problems/annoyances.
Other activities:
-
code review for the stochastic group
-
reviewing GWDAW paper for CQG
Creighton:
I finished an improved work unit validator for Einstein@home that now rejects
only 0.3% of results, rather than 1% for the previous validator. I've also committed a validator
comparison program that can compare the results of any two (or more) versions
of the validation code.
Mendell:
Validation of the StackSlide code is going well. I had planned to post a report
on this on the CW/pulsar group investigations page this week, and hope to do
that before next week's CW/pulsar telecon.
Mandic:
I worked on a set of scripts and routines in tcl and matlab designed to calculate
the coherence and transfer functions between two channels on very long
time-scales (e.g. the calculation for all of S4 can be done in less than 1
hour). I used the code to study the correlation between H1 and H2 AS_Q
channels, the inter-site correlations (AS_Q-AS_Q, AS_Q-PEM, and PEM-PEM
channels at LLO and LHO), and the OPLEV-AS_Q correlations at LLO.
Some of the results are posted in the stochastic ILOG.
Shawhan:
-
Worked on finalizing S2 untriggered LIGO-only burst search
paper.
-
Fixed the ldasjob package in LIGOtools to capture job
information properly for all LDAS connection methods, including the
"persistent" socket connections, which are now used by default.
Yakushin:
Working on rearranging waveburst offline infrastructure to make it easier to
use and review.
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS:
Worked on PR 2724 for the
controlMonitorAPI's client to allow the modification of resource variables.
ALso worked on PR2617 to fix the headers for resource variables and PR 2336 to
allow sorting of data by clicking on a table's column.
Discovered with the help of
Greg Mendell that the changes to the createRDS command to support a more
flexible set of input frames through the use of a new framequery option are
still buggy and introduce several unexpected failures and results. Will need to
resolve this this week.
Fixed PR2799 so that FrVerify
now displays checksum values with an error is found.
Fixed PR1976 to provide clearer
error messages from inconsistent ILWD object dimensions.
Closed out PR2814 to document
and update SINSTALL rules to fix FIREFOX security hole.
Worked on several PRs that are
associated with enhancing LDAS commands to allow for compression of frames
produced by LDAS and to make the default to compress these frames.
Began testing code for PR2751
to allow logging of the md5sum values for all frames generated by LDAS's
createRDS command. Also began testing code for better support of untested
compilers in the build of FrameCPP (PR2813) and code for improving the history
structure for frame files written by LDAS associated with PR1388.
Ran the weekly integration and
system tests on LDAS version 1.5.45.
Found the problem in the test script that was causing the lsync test to
fail two thirds of the time and fixed it. Added verification of default
compression levels to the compression tests. Investigated why the old
frame-to-ilwd tests were no longer running and updated them to work with newer
APIs in LDAS, but need to find the input data for running the jobs lost with
Isaac.
TCLGLOBUS:
Fixed the problem with callback
functions that need to receive a correct
result after completing the FTP operation. Those functions are:
a. globus_ftp_client_size(),
b. globus_ftp_client_cksm() and
c. globus_ftp_client_modification_time()
Placed new web documentation on how to download, build and install TclGlobus
in preparation for the first alpha release (May 1, 2005). Worked on verifying nightly tarball distribution
(will do some more testing this week).
OSG:
Discovered one of the issues
preventing Condor jobs from running on the worker nodes - the VO accounts had
not been replicated onto the worker nodes.
Also discovered that the inet.d
was starting up multiple copies of several OSG services, probably due to a bug
in the upgrade procedures.
Still an issue with submitting
jobs remotely and with using the OSG-GK for third party GRIDFTP jobs.
Responded to questions from OSG
leads concerning the plans for LSC Grid3 computing resources after passing
response through the Computing Committee. A follow-up set of question has just
been received which will require a second round of discussion with the compute
committee and the OSG.
Hardware Systems (Anderson)
Caltech
(Phil Ehrens)
- Incidental
support of Subversion users.
- PR
#2818 - mpiAPI is blind to wrapper API initialization failures. CLOSED
- PR
#2791 - getFrameData and concatFrameData data should support compression.
They do now, via the new -compression type and -compression level options
to these two commands.
Default values are controlled by the new frame API resource
variables ::FRAMEDEFAULTCOMPRESSIONMETHOD and ::FRAMEDEFAULTCOMPRESSIONLEVEL. Documentation to follow
shortly. FEEDBACK
- PR
#2788 - The output action should support creating frames with compression
enabled. A side effect of the
fix for PR #2791 was the default creation of compressed frame files,
partially satisfying this problem report. Ongoing work is being done to
extend the output type syntax to support specification of compression mode
and level. ANALYZED
- Migrated
my desktop workstation from the Solaris box "dziban" to the
Fedora Core 3 box "tarazed". Fedora Core 3 does not support
termcap, so some console applications did not migrate cleanly.
(Stuart Anderson)
- Working
with Sun on a few SAM-QFS 4.3 issues.
- Working
with Scott Koranda on an LDR queue starvation problem.
- Continued
working on standardizing the cluster matlab installation.
- Started
testing loaner 10Gigabit Ethernet cards.
MIT
(Keith Bayer)
- Tested
and reset matlab licenses on ldas for grid and ldas-pcdev1.
- Getting
T3 units put onto existing maintenance contract.
Livingston
(Igor Yakushin)
- T3
u1d2@t3-13 failed.
- Got 5
replacement drives from Maxtor (to replace 160Gb and 200Gb drives they
sent me two 250 Gb and three 300Gb drives).
Hanford
(Greg Mendell)
- A
special FSR (Free Spectral Range) RDS data set for S4 is being generated
at CIT. The data set is also being published at CIT and is currently being
transferred to LHO. The channels included are LSC-AS3_Q_1FSR,
LSC-AS3_I_1FSR, LSC-AS4_Q_1FSR, LSC-AS4_I_1FSR, LSC-AS3_Q_2FSR,
LSC-AS3_I_2FSR, LSC-AS4_Q_2FSR, and LSC-AS4_I_2FSR for H1, H2, and L1.
- Otherwise,
I am working on enhancements to the createrds driver scripts.
(Ben Johnson)
- Finished
bourne shell version of lscsoft user env init script. Still need to
complete csh version.
- Fixed
some matlab problems that Keith Thorne brought up. Namely updating
license.dat to reflect the new curve fitting toolbox license, and updated
ldas-pcdev1's environment to be current with ldas-grid's.
- Testing
new lfnChangePSet code, to help alleviate the LDR queue starvation at
Caltech.
- I've
been mirroring the cluster disks with dd, such that /dev/hdb is an exact
mirror of /dev/hda. /etc/fstab has been reconfigured with device names
instead of LABEL entries.
- Publishing
FSR data at Caltech and retrieving it from CIT. Started new 'CIT_S4' pset.
General Computing (Wallace)
MIT:
(Keith)
- Upgraded
Myron's computer to XP
- Setup
daily backup utility to 2nd hdd
- Continuing
LDAP investigation
- Added
guest account for visitor (travasso)
- Looked
into printing trouble
Livingston:
(Shannon)
- Working
on the new router. Enough
hardware has trickled in this week for me to be able to get it going. I hope that in the next few days I
can make the switch over.
This should improve stability. I have had some issues with the Syskonnect cards &
drivers, and also a couple of Linux/Dell compatibility problems, but they
are mostly resolved. I will be
working some late nights until I get this going. I will make the switch over late at night when it will
not affect any one. This
router will take the place of three pieces of hardware right now - the WAN
router, the PIX for GC networking, and the CDS router. By consolidating I hope to fix
some buggy behavior on our network.
- Starting
to revisit the the NIS+/LDAP and mail server replacement issues. I am working on setting up a test
server in between working on the router. Over the next few days I will be
testing and compiling notes on this.
- Fixed
a problem on abundance which was causing issues with an rsync process. Added some new rules on our
firewall which will improve logging and will also send me an alert if any
windows machines on site start scanning windows ports on the internet.
- Going
through more Sun documentation on LDAP, RBAC, BSC, Sun Java Enterprise
Messaging & Calendar servers.
- Spent
quite a while on the phone tracking down invoices for Pcard this week. Most vendors are simple, some are
all but impossible to get a hard copy of an invoice out of them.
Hanford:
(Christine)
- Network
usage can be seen at http://www.ligo-wa.caltech.edu/~christin/mrtg/
198.129.208.1_198.129.78.122.html
- Set
up a new laptop. Ordered a
new desktop.
- Tracked
down a runaway print job which a user started but then didn't know which
computer they were logged into when they started the print job.
- Restored
from backup tape a file which a user accidentally deleted.
- Researched
and found a "How To" document for a user who wanted to password
protect folders in their public_html.
- Purchased
and installed a new Matlab toolbox on the license server. Reviewed a quote for renewal of
the Matlab maintenance contracts.
- Left
several phone messages and sent an email to my contact at Amerion regarding
my request for information on our requested backup network. Reviewed a proposal from another
vendor for a network connection from Richland to Seattle.
- Trying
to get some answers from the Caltech mail room regarding a package that
was mis-directed to them and then sent to me and now the vendor is
refusing to pay shipping.
- Preparing
for a planned power outage next week. Richard is installing some generators which will power
all the main GC servers and network equipment.
- Discussing
with Shannon what's needed to come up with a standardized security
topology.
- Repaired
some epics database problems in the Vacuum Controls Systems which showed
up when the systems were re-booted.
CIT:
(Mike)
- Dave
Beckett: Swapped out his old computer. This required me adding additional
hardware to his new computer; plus software, transferring over users
email, and old data to new computer.
- Irena
Petrac: Computer died due to a hardware failure. I replace her PC with a
newer computer. This required a complete rebuild, and loading additional
software, plus setting up users preferences, and recovering data from
defected PC.
- PRISM:
Worked on putting together a website showing step by step instructions on
how to setup a user's local desktop with a VPN connectionto LIGO and too
connect to PRISM Project Management Software.
- Spam
filters: Continued maintenance on the Spam filters, especially whileLarry
was attending his conference, & continuing to help out through out the
week.
- Janeen
Romie: Reload Solid Works, added some additional software to workstation/laptop,
and trouble shooting additional issues with these units.
- Updating
our IP database. While I'm getting the require information off these
computers, I am also updating service packs and Norton Anti Virus engine
to 9.0; regarding the Windows boxes. I am almost done with W/B, but still
have to attend to Millikan, Wilson House, 40 Meter, Synchrotron, Downs,
Lauritsen and all labs. Yes I have a long ways to go.
- Took
an inventory and ordered supplies for all HP printers, through out the
project.
- Other
misc. onsite/phone user support.
(Veronica)
- LSC: Updates of the webpage for papers
under review.
- LIGO: Compressed the footage of the last
software presentation for the DCC.
The stream pointer is posted at the LIGO website. Prepared a form for online vacuum
bake requests for the 40m.
Prepared a set of high-resolution images for the Smithsonian. Updated the PAC website. Troublehot and made updates to the
roster database.
(Larry)
- Working
on a number of new orders for units to be replaced in the server room. Purchased and delivered a number
of misc. computer support items.
Sent out a notice concerning Dell notebook power supply units. According to Kent Dell was very
responsive and replaced his power supply without any problems. Working on the purchase of the
modem pool replacement.
- Performed
maintenance on a number of accounts. Locked up a few accounts. Minor changes made on a server in
the 40M.
- Spent
time repairing E2E servers. The heat in the room has taken its toll on the
disk drives. One unit has been repaired and is back on-line. In the process
of repairing the other two units. Both will need a complete rebuild once
the hardware has been checked out.
- Assisted
Irena with a number of items in getting her going again on her pc.
- Worked
a couple of issues in the server room. Mostly cabling and new server installs.
- Working
on the fiber installation to the sub-basement. Still no word on when the
work will be done. Did a
short walk through for different items with the PMA group. They are checking
on the fire suppression test as well as the additional air-conditioning that
it needed.
- Did
some leg work for Albert on the network change over for Hanford. No major discoveries were made.
- Assisted
Mike in auditing the computer systems. Still some work to go on that project.
- Continual
work on the mail filters.
Mail Statistics April 14-20, 05
Allowed
Messages 19,911
Virus
Messages 4,421
False
Positives 222
Denied
Messages 16,611
Total
Messages 36,522
Advanced LIGO and Supporting R&D (Shoemaker)
Systems and Management
No report this week.
Seismic Isolation
From: Ken Mason kmason@ligo.mit.edu
No report this week.
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
Completed the detail drawings for the tablecloth assembly. Now
working on the tablecloth assembly.
From: ctorrie ctorrie@ligo.caltech.edu
UPPER STRUCTURE
The machining of all of the parts for both structures has
been completed and the welding of the first upper structure has started. There
are a couple of interface issues that have still to be resolved. The engineers
at RAL and Glasgow are supporting us on this effort.
LOWER STRUCTURE
The main body of the lower structure is going to be done in
an outside shop. 4 companies have been chosen to supply quotes for this work.
The other parts for the lower structure will be completed in the next few
weeks.
ASSEMBLY / MOCK INSTALLATION TOOLING
Several parts have been purchased and are in the Physics shop to aid us with
the mock installation of the Quad in the proposed clean room at Caltech.
From: Ken mailand kmailand@ligo.caltech.edu
I have worked with Helena
to produce an air bake oven specification for the LASTI parts. The Grieve Co.
quote is ~$18,700. for 36x36x60 size, ~two other quotes pending. this should
work for all part sizes except the round rail Oddvar is designing.
We have received 4’” S.Stl. stock for the lower suspension installation arm
fabrication, and one set of the roller bearing with lip seal for the pivot
shaft. I have started the
detailing of the component arm parts, and making a list of the purchased parts,
bearings etc.
Core Optics
From: Helena Armandula ahelena@ligo.caltech.edu
Generated specs for a Class 100 modular clean room to be used during the
LASTI Quad assembly. Received 3
bids for the construction; the PO is ready to
be placed; the time for delivery and installation is about 4 weeks.
Working with K. Mailand to adquire an air bake oven. Waiting for the last
bid (due by the end of the week) to place the PO.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
Parts from the faulty circuit board were salvaged and placed onto a correct
circuit board. Initial testing did not reveal anything untoward. Exposure testing will start later this
week.
Auxiliary Optics
From: Michael Smith smith@ligo.caltech.edu
BS DIFFRACTION LOSS
I completed the analysis of the BS geometric and diffractive losses for the
input beam from the power recycling mirror and from the signal recycling
mirror. I computed the loss for the range of BS parameters with thickness
varying between 50 to 72 mm, and diameter varying between 350 to 400 mm. The
results are summarized in LIGO-T050066-00. The loss results are smaller than
the preliminary results I reported on 4/13/05 because I had used a Gaussian
beam with a waist of 60 mm at the midpoint of the arms. The calculations were redone
with the correct beam waist of 11.49 mm at the midpoint of the arms, which
produces a 60 mm beam size at the ITM mirror.
The diffractive power loss fraction for the baseline BS geometry (t = 60 mm,
D = 350 mm) is 9.90 E-5.
The diffractive power loss fraction is 2.2 times smaller for a slightly
larger diameter BS geometry (t = 60 mm, D = 370 mm) is 4.42 E-5.
Other Laboratory R&D
Juri
I’m working on my simulation program in order to improve the locking
procedure: now it is able to lock the cavity in its fundamental mode but not
with maximum power. I understood what seems to be the problem but not well
understood the best solution. Moreover
I received the maps of the new Mexican Hat mirrors made by LMA and I’m running
my program to obtain the predictions of the beam shape for our cavity once we
will install these new mirrors. Collaborating with Marco on the experimental setup for our
interferometer.
Marco (19Apr)
After the analysis of the input beam I aligned the cavity (still the
classical one). It was more difficult than before the lab closure but it has
been completed even better than before. I also checked up all the servo
electronics. Meanwhile I’m
studying the best configuration for the input optics to get a 4mm waist on the
input mirror. Next step will be to re-lock the cavity.
Creep experiment: we are taking data at the temperature of 40oC.
Riccardo
Working with Calum on IP design.
For additional information about this report, contact Stan Whitcomb or Phil Lindquist