Weekly Report for Week Ending April 14, 2005


Exec. Comm. Agenda

Highlights

LSC

Administration

Hanford Observatory

Livingston Observatory

MIT

Caltech

Detector

40 Meter

TNI

LASTI

Data Analysis

Adv. LIGO Development

Past Weekly Reports


The LIGO Executive Committee meeting for April 18, 2005 is cancelled due to the LIGO Laboratory Staffing Committee meeting.


Special Announcements:


Weekly Report Highlights


LSC Issues (Saulson)


No report.


LIGO Laboratory Administration (Lindquist)


STATUS OF LSC MOUs (Petrac)

LSC MOUs and Research Plans and Progress Reports

  • Nothing significant to report.

For a web page summary showing the status of LSC MOUs and associated Attachment updates see: http://www.ligo.caltech.edu/~irena/Revstatus/Reviewstat.doc

Non-LSC MOUs

  • No report.

SITE TELECONFERENCE (Lindquist)

A site teleconference was held on Thursday, April 14, 2005. The following items were among those discussed:

  • Procedure Manual: (Action #124), A decision tree (taxes) was sent to F. Raab yesterday.  Minor comments are being returned and a wider distribution is encouraged.
  • Program Advisory Committee (PAC) Meeting: A meeting of the LIGO Program Advisory Committee has been scheduled in Livingston for May 18 and 19.  Preparations are underway.
  • The list of assigned actions updated through March 10, 2005 will be found Here.

PROPERTY MANAGEMENT (Chargois)

>From: Ed Chargois <chargois_e@ligo.caltech.edu>

  • Nothing significant to report.  Campus Inventory ongoing.

DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

  • Continued to work with sales representatives for upcoming presentations of their software systems.  Met with Stu Meyer for DocuWare, John Redenbach with Synergy and Michael Yim with CDG.  I also followed up with Ren and Mickey of Altimate following their presentation last week.
  • Received the audio CD of last week's meeting with Altimate and have been slogging through it and creating a transcript of it.  I originally was seeking to extract questions asked and answers given, as well as tracking those items that "could be enabled" and might incur additional costs.  However, extracting the question without the context of the conversation was less than helpful, so I'm trying to get a more complete transcript to better create a question and answer matrix to compare across the companies presentations.

>From: Cleveland Mak <mak_c@ligo.caltech.edu>

  • packages: in - 17, out - 6
  • faxes: in - 28, out - 24
  • Completed process/filing of all 2004 Travel File folders.
  • No other special projects to report.

COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman, Salone)

>From: Esther Cunningham <esther@ligo.caltech.edu>

>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

  • Tracked down several lost shipments for credit card orders that did not make it to their destination. Returned a wrong shipment sent from the vendor and made arrangements for the exchange.
  • Renewed the Primavera software support agreement for 2005/06.
  • Received the order acknowledgement for the REO change order 19 which ordered the fabrication and coating of the substrates.
  • Followed up on pending Release of Claims. Received one more and closed the file. There are seven Releases still pending acknowledgement from the vendors, and a request to close out one more subcontract.

>From: Gina Salone <gsalone@ligo.caltech.edu>

  • Nothing significant to report.

>From: Florence Kaufman <fkaufman>

  • Worked on updating monthly reports.
  • Looking into what the appropriate expenditure type should be for SURF students.  In the past, we have used an expenditure type that is subject to Caltech's Indirect or Overhead rate, the issue is whether expenditures for these students would qualify to be treated as Participant Support costs, which would make them exempt from the Indirect Cost.  [E. Jasnow has scheduled a meeting with the Office of Sponsored Research –pel]
  • Financial reports can be found at: http://docuserv.ligo.caltech.edu/~fireport. (For passwords contact Florence)

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

>From: irena@ligo.caltech.edu (Irena Petrac)

  • Nothing significant to report.

>From: Ed Jasnow <jasnow@ligo.caltech.edu>

  • We still have no word on whether or not LSU has executed the amendment to its lease with the NSF that covers the building of the Science Education Center at LLO.  The Office of General Counsel (Sandy Pool) is pursuing this.
  • The latest design change for the LLO SEC has been approved, with the 50% submittal date moving back one week.  EDR will submit a revised schedule showing the impact of this change.  It is not expected to be a 1:1 slip.

SUPPORT (Baldon, Hiroto, Lloyd)

>Irene Baldon

  • The usual plus catching up!

>From: Julie Hiroto <jhiroto@ligo.caltech.edu>

  • Updating web pages for B. Barish and working with V. Kondrashov to create a new look for those pages.  Barry's on-line calendar is up-to-date.  And there are many trips to plan and reconcile.

>Dorothy Lloyd

  • Processed the usual invoices for payment. Tracked and followed up on invoice problems. Reviewed and recorded payments processed by Esther the week of April 4.
  • Processed requisitions for standard purchases, payment requests and change orders. For more detail see Cost Schedule Control Systems report by Ruth Brambilla.
  • Attended demonstration and question/answer session on TechMart, due to go live on campus in June.
  • Jim continued with data entry in the LIGO database and helping out in the DCC.

PROPOSALS and REPORTS (Lindquist)

The Annual Report for the Visitors Program is basically complete and entered into FastLane ready to “push the button.”

A proposed draft has been distributed for outlines for the Annual Report for Operations and a Proposal for an Extension for FY 2007 and FY 2008.  Some comments have been returned.  We will begin working these documents pretty furiously between now and August 1.

DCC Steering Committee (Lindquist)

The DCC Steering Committee participated in demonstrations of two different systems on Wednesday (April 13, 2005).

DocuWare presented the first system.  This system runs on a Windows 2000 Server (SQL).  The code is in escrow (this is insurance against the company going out of business).  The system demonstrated seems designed for a much more secure and inward looking environment that that which we need.  Does not support immediate distribution of a fixed URL pointer to a document.  Viewing can be done from any browser.

The second system was presented by Synergy.  This system runs on a Microsoft Windows SQL 2000 Server.  The only browser certified is Internet Explorer, which could be a serious issue for us.  Several on the committee will test other browsers.  Other than that, the system seemed pretty slick.

We want to set up two more demos and are considering next Wednesday (April 20th) at 8 am and 1 pm.

CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)

  • No open change requests.

HUMAN RESOURCES (Akutagawa)

>From: Cindy Akutagawa <cindy@ligo.caltech.edu>

  • No special activities to report.  The next staffing committee is scheduled for April 18, 2005.

Quality/Safety (Tyler)

>From: Bill Tyler tyler@ligo.caltech.edu

·       Nothing significant to report for Safety and QA.


LIGO Hanford Observatory (LHO) and Interferometer Operations (Raab)


 

Summary of Commissioning Activities at LIGO Hanford Observatory (Landry)

Absorption and g-factor measurements were the order of the day, for most of the week, on the 4k.  Site-wide, 4k and 2k-related elog highlights are bulleted below:

  • While the experiment was not quite completed, coupling to test mass magnets by ambient magnetic fields induced by various sources appears to minimally impact 60Hz noise.   Fans, heaters, optical lever supplies, RGAs and fine actuator supplies are less likely a problem; the word is still out on lights and annulus ion supplies.
  • HAM5 annulus iop pump problems (more on diagnosis here) meant that HEPA fans had to be left running for an extended time
  • the GRB alarm was upgraded to include the satellite source
  • chilled water stopped chilling when a carpentry shop breaker tripped

4K IFO

  • an observed reduction in H1 range was attributed to various sources, possibly 6Hz and/or 35Hz noise.
  • only ~1mW of POY is observed: this is not where the 4k recycling gain is being lost
  • 4k spot size measurements were summarized.  Later, a correction was logged.
  • That would be analysis: the POY port sideband carrier analysis system was restored

2K IFO

 


LIGO Livingston Observatory (LLO) and Interferometer Operations (Zucker)


 

L1 Interferometer (Frolov)

---------------------------------------------------------------------

The interferometer input power increase and the coil driver upgrade reported last week yielded improved interferometer noise performance. The power into the interferometer was increased by more than a factor of two from the S4 level. The best inspiral range is close to 9 Mpc now.

 

There was finally evidence seen of thermal distortion from the main 1064 nm beam at the maximum input power of 4.6 W (incident on the mode cleaner). Heating power from the 10.6 micron thermal compensation system was reduced by about a factor of two to accommodate this.

 

Work on the frequency stabilization servo continued this week. The fss bandwidth is still not up to the designed value with the new laser (300 kHz vs 500 kHz).

 

Education and Outreach (Thacker)

---------------------------------------------------------------------

2 outreach programs were provided this week

 

SURF student list for this summer has been finalized

 

Concept of a Local Educator's Network has received excellent support from teachers contacted to date. 1st meeting tentatively set for May 21st.

 

We supported a LA DOE teacher training workshop on at risk students. (support included facilities + introduction by me on what LIGO is and does).

 

Site Safety and Security (Riesen)

---------------------------------------------------------------------

1. Updated all laser user signage.

 

2. Issued 6 replacement swipe cards (defective cards).

 

3. Qualified Hartmut Grote (GEO) as an LLO Laser Operator.

 

4. Ordered traffic sign for auditorium parking and auditorium location.

 

5. During site walk through found no laser safety concerns. Found trip hazard conditions at the X-end, Y-end, corner station CDS rack room, and LVEA (TCS areas, HAM 2 area, and ISCT-4 area). The optics lab and the mechanical room had chemicals that are not stored properly. I am in process of contacting the responsible people.

 

6. The Y-end experimental lab is ready for cleanup and relocation of the equipment to the corner. This area has not been active for some time as it interferes with interferometer operations; the tests previously sited here will be relocated to other site lab spaces and resurrected.

 

7. Conducting an in-house property audit (will be on-going for at least 2 weeks).

 

8. Work is continuing on the 5 malfunctioning site security cameras.

 

9. We are gathering, sorting, and containing  our chemical and solid waste for future disposal.

 

LLO Mechanical Engineering (Spjeld)

---------------------------------------------------------------------

 

AdL Quad SUS Installation Fixtures

 

-        Completing re-design; design review meeting scheduled for 4/25

-        FEA of all components approx. 80% complete

-        Will start on machine drawings after design review

 

AdL SEI Engineering Effort

-        Machine and assembly drawings of blade pre-load tooling complete

-        Additional tooling documentation in progress

 

LLO Outreach Facility ­ Pendulum Exhibit Wall

 

-        Received quote from Cardinal Aluminum

-        Completed model with pendulum load carrying, bearings and shafts

-        Preliminary design of lock-down mechanism complete

-        FEA of components in progress

-        Provided architect with pendulum mass and moment estimates

-        Awaiting attachment interface design from architect   

 

General Engineering

 

-        Attempting to convert SolidWorks models of BSC to 3DS files for NSF movie

 

LLO General Computing and LIGO Computing Security (Roddy)

---------------------------------------------------------------------

-Helped John Thacker with Norton Ghost on setting up backups.

 

-Reinstalling a Windows laptop for Allen Sibley

 

-Working on getting subscribed to various security mailing lists

 

-Spoke with CDS candidate Matt Rippa.

 

-Finished setting up a few more machines on CDS to log to the central Syslog server.

 

-Working with Syskonnect still on the bad fiber card for the new firewall, and ordered a 4 port Cu Gbit card.

 

-Ordered a UPS for the lab rack.  Working with Rus and Bernie on a power source for it.

 

-Looking into some software that Mike Pedraza told me about for Windows patch management for both CDS and GC.

 

-Still looking into RBAC and BSM - allows extremely fine grained control and replacement for su/sudo.

 

-Working with Caltech on a licensing issue and also getting more software from them under the CIT licensing.

 

HPLF, Optics Modeling, Data Analysis and L1 Commissioning (Franzen)

---------------------------------------------------------------------

1) HPLF news: Mike Zucker visited IPG Photonics (April 11) in order to investigate how the 100 W laser repair is progressing. He was told that IPG has redesigned and assembled the laser and that IPG now believes it is going to work without any more failures with the output wavelength still at 1064 nm. The seven day burn-in test had just started during Mike's visit (14 hours) and the engineers also said that they plan to ship it in approximately two weeks if everything works out. Rusyl W. and Rich R. have been designing and installing a over-temperature interlock system in the HPLF which will prevent the laser from running if the room temperature exceeds a certain set point. This is basically to exclude any further questions regarding insufficient cooling of the laser being the cause of any future failures.

 

2) Since my migration from Red Hat to Fedora Core 3 a few weeks ago I have encountered some serious compability problems between matlab and femlab running on FC3, both required for my melody AdvLIGO MC simulation work. I am desperately trying different approaches in order to get back on track, but we might have to get another femlab subscription or even worse pay for Red Hat Enterprise.

 

CDS software (Khan)

---------------------------------------------------------------------

1) Upgraded three Sun workstation to Solaris 9 operating system.

 

2) Helped Valera in setting calibration values for wfs and diagnosing TCS problems.

 

LDAS/Condor Sysadmin and Burst Analysis (Yakushin)

---------------------------------------------------------------------

Data archiving/Condor/LDAS:

 

The condor nodes were down for half a day on Tuesday for AC work.

 

Data analysis:

 

1) On  reviewers' request computed std values for table VI in S2 burst paper (central time and frequency reconstruction of hardware injections). Noticed that some signs in the table got changed somewhere along the editing process.

 

2) On Erik's request, took a closer look at how well S4 hardware injection properties (central time, frequency, hrss) were reconstructed by waveburst online high threshold analysis:

http://ldas-pcdev1.ligo.caltech.edu/~igor/S4HWINJ/index.html

Noticed that there is obviously a time delay introduced between the sites (I was not aware of that and thought that triple coincidence injections were done exactly at the same time at all the sites). Peter confirmed that was really the case:

http://www.lsc-group.phys.uwm.edu/cgi-bin/bag-enote.pl?nb=

burs4simulations&page=9

 

3) Working with John and Sergey to put waveburst into DMT CVS (the most important part of it, WAT, was already in DMT repository, however, postproduction scripts, online and offline scripts were not) in preparation for the waveburst review.

 


Initial LIGO Detector Science & Engineering (Coyne)


 

CDS

see also the CDS weekly meeting minutes in the commissioning archives

CDS Software

no report

CDS Hardware

Fiber Optic Timing Link (Sander)

==================================

- 40 M parts are ready to install.We have 4 receivers that will be installed in the LSC, ETMX, ETMY and vertex suspension crates. When more receivers are completed we will install the remainder of the system. Receivers are required for IOO front end, 2 more vertex SUS frontends, ASC and PEM ADCU crates. The PEM ADCU crate is optional.

- Installation will begin today and testing will begin next week when the serial data analyzer is received.

DMT

no report

PSL

PeterKing

In the news, Lightwave Electronics was recently acquired by JDS Uniphase.

 

A new Pockels cell mount was drawn up after taking into account the experience obtained from last week's trip to LLO.  It avoids having to find the right height pedestals ... etc.

Optical Contamination Cavities

Lee Cardenas, Liyuan Zhang

OTF Lab. (W. Bridge)   No Change
Cavity # 1
This chamber still locked with two samples, white Ceramabond, and disks of TRA-BOND #2254
color light brown epoxy. Cavity is clean.  We are waiting on new mirrors to be tested for contamination.  

Absorption Test Measurement prototype  in standby.

Scatterometer system  in progress
We have made a complete new alignment of the entire optical train

after installation of a new beam splitter and introduced a pin holes
and beam have been collimated.  More precise mode  match done.
We have installed an integrating-sphere to collect the scattering beams
from the mirror. So far,we have checked a 1.00"inch 70ppm mirror and took
the scan and it give us a total beam scattering
of ~ 22 uv(microvolts) in the Lock-in-amplifier which represents
~ 4 ppm of scattering loss.  This is the best for this mirror and
this is our base of scattering loss.
We have installed the fused silica 2ITM04 in the scatterometer
and so far it reads ~75uv(microvolts) of scattering loss.

We have received a new HEPA unit which will be installed ASAP
on top of the scatterometer enclosure.

The Quantronix 60 watt laser is shut down.

OTF Lab at Lauritsen ROOM 38  Cavity #3 
The contamination test for (20) pieces of Glenair Micro-D-connectors still in progress.
Cavity is locked and we are taking measurements  for absorption and ring down
 for contamination loss every day. So far so good.

The small vacuum pump is leaking oil from the oil chamber gasket seal.

Cavity #2  in standby.

 


40 Meter Interferometer (Weinstein)


  • IFO commissioning:
    • Osamu couldn't lock the dual recycled Michelson (DRMI) last Monday night. He found a huge 60 Hz peak in the POB RFPD, due to a ground loop from the RFamp power supply. He switched back to a linear power supply and the problem went away. He found a bunch of other problems: the AWG didn't work, but rebooting the front end fixed it. The POB RFPD 133 MHz demod is still too noisy; still under investigation, suspect the RFamp. The AP RFPD is broken; to be fixed. Now the DRMI is back to being pretty stable.
    • Osamu locked the DRMI Wednesday night, and waited for the arms to lock (DC offset transmission lock). It came into lock twice over 2 hours, holding for ~ 5 minutes (so that all 5 length degrees of freedom were controlled, but the arms weren't fully resonant and there was no PR gain or RSE). We need to tune up the alignment, and develop more robust CARM and DARM signals. (We also need to fix our ITMX, see below; and perhaps implement a suspension point interferometer, see below).
    • Osamu set up a system to continuously monitor the resonance of the 33 MHz RF sidebands transmission through the mode cleaner, using a 30 kHz dither at the MC servo error point and a lockin amplifier. This monitor channel is now being logged to frames. During lock, this signal wanders by ~ 7 Hz (out of 33 MHz) over 30 minutes. In between locks, this can change by 10's or hundreds of Hz. Rather than change the RF sideband frequency to compensate, it should be possible to feed back on the PSL frequency in some way, eg, PSL reference cavity temperature (as in the tidal servo). Under study.
    • Steve & Osamu modified the POB table optical layout: they repositioned the oplev laser & PD; replaced IR beam mirrros & lenses with 2" ones; and Changed incident angles to have less mirror loss. They will order 2" BS to put 10% of the light onto QPD & camera.
    • Dan is planning the re-positioning of the SP LSC RFPDs from the SP table (far away) to the AP table (much closer, room has been made for it). Osamu replaced the first SP stering mirror on AP table from 1" to 2", and he and Steve ordered a 2" BS to pick off most of the light at the AP table to get it into these repositioned SP LSC RFPDs, while sending a bit of it down to the SP table for monitoring (QPD, CCDs, WFSs).
    • Steve and Rana tried to calibrate the oplevs by yawing the TMs until the IR beam hits the suspension cage of the optic 40 m away, and recording the effect on the oplev. But this exceeded the oplev range. So, we'll try other methods.
    • Rana started a process to calibrate the length control signal of the ITMs by swinging through Michelson fringes and then do a swept sine measurement of AP166_Q / SUS-LSC_EXC for both ITMs. He got part-way through the procedure. Monica will follow up.
  • IFO modeling and DC detection development:
    • We continue to think about implementing a suspension point interferometer to lock the ITM and ETM tables together, to make it easier to lock the high-finesse arm cavities. A pick-off from the main beam would resonate in a low-finesse cavity made up of mirrors fixed on the ITM and ETM tables. We can DC lock it in transmission, by actuating on the stack with the STACIS system. Jay is looking into a simple way of implementing a servo, using front-end code on linux-in-a-box with ADCs and DACs. He thinks he knows where to add the signal in the STACIS electronics, upstream of its internal PZT drivers. Virginio is beginning to think about the optics and the full system.
    • Student Marcus Ng is working with Rob on the design of the output mode cleaner for the DC detection experiment.
    • Rob continues to study quantum noise in signal recycling; he's running Thomas Corbitt's code.
    • Monica has confirmed that her Twiddle & Finesse models agree with each other, and they both agree with e2e except in the case of some small off-diagonal signals. She's not sure why but Hiro has been alerted.
    • Monica is now working on developing her e2e model of the 40m control plant. She awaits a dual-recycling summation cavity primitive from Hiro, and will test that when it is ready.
  • PSL:
    • Jay zeroed the offset on ISS servo, which now seems to be saturating less frequently. We still don't know why the sites don't complain about this; perhaps our prototype board is bad, or one of the opamps on it is bad/drifting.
  • Electronics, controls:
    • The SP and AP beams move around a lot, and this has been traced to a noisy ITMX. Rob, Osamu and Steve have run a large number of tests to diagnose the problem. There's clearly excess noise in the OSEM pitch, at 2-3 Hz; and there's clearly a lot of coherence between the side OSEM sensor and the OSEM pitch & yaw. They've taken transfer functions from coils to sensors, they all seem to work ok. They did sensor ringdown measurements; nothing strange there, no sign of mechanical contact or excess loss. They swapped satellite amps, cables between racks, etc; the problem always stays with the suspensions; so it's in the chamber somewhere, between the vacuum feedthroughs and the OSEMs. Steve checked the resistance to ground and the inductance of all the coils; all ok. No shorts between coils. By turning on LEDs one at a time, they verified that they knew which OSEM goes with which OSEM cable. They noticed that the OSEM LEDs are oriented differently in the ITMs than in all other optics, but ITMY is fine and ITMX is not. One theory is that one of the OSEM lenses and/or filters is broken or knocked off. More tests are in progress. If we can find out what's wrong, we may want to vent to fix it.
    • Jay and Ben have checked out virtually all of the ASC system with interfaces for 3 WFSs. The in-vac pzt controls for input beam steering will work. Still some hardware (Jay) and software (Rolf) to get the IPANG QPD into the front end ASC system.
    • Jay is working on the hardware and Rolf on the software for getting the thorlabs PDs at the two ends into the front-end LSC system.
    • Sander has a test plan for his fiber optic timing distribution system. He plans to re-install the system into the 40m this week. He needs to order a couple more fibers and receivers for a couple more crates.
    • We continue to have problems with the front end, requiring reboots of the DSC, LSC, ASC systems. Theis is presumably due to either timing glitches or RFM flakiness. If the former, it will hopefully go away when the new fiber optic timing system is installed.
    • Rob had problems rebooting the front-end systems, likely due to either flaky eithernet cables or hubs. Will keep an eye on it.
    • We await new RevB coil drivers for the remaining 3 core optic suspensions. Jay notes that the high-current buffers are not available and there may only be parts for 2 new coil drivers. CDS needs to redesign the coil drivers and satellite amplifiers to use different, more available, parts.
    • The Coherent OSA head was fixed at Wilson House and is back in the lab, not yet tested.

Thermal Noise Interferometer (Black)


 

Progress continues, slowly but surely, on the bond-noise experiment. We have a number of projects "in the pipeline," but for most of them we are waiting on samples.

 


LASTI (Ottaway)


 

Excess Pier Motion (Mittleman, Ruet)

After removing all of the stack springs and most of the mass (Myron and Lee) we remeasured the "pier amplification" and found that it was the same as with the stack installed.

 

There is an entry in the Lasti ilog (4/7/05) showing the first results and an entry (4/13/05) detailing the stack removal procedure.

We are continueing to explore the detailied resaons for the noise enhancement and possible solutions

 

LASTI Infrastructure (Mason, Ottaway and Ruet)

Completed the design and placed on order the solid stack. Modifications were made to fasten the l4-c geophones during testing of the quad controls prototype.

 

Given the situation with the vacuum bake ovens in LIGO Lab. It was decided that this solid spacer will be airbaked by a commercial vendor and can serve as a  path finder for this technique being used for Advanced LIGO Seismic.

 


Data Analysis and Computing (Lazzarini)


-----------------------------------

Data Analysis Activities (Anderson)

-----------------------------------

 

Weinstein:

- Working with Lisa Goggin and Duncan on S4 ringdown search.

- Read and commented on near-final S2 BNS paper.

- Read and commented on near-final S2 PBH paper.

- Reviewing S2 BBH papers, talks, and elog pages.

 

Mendell:

Ihave been working with Virginia Re and Joe Betzwieser to understand how the analytic formulas for the StackSlide power given in StackSlideHoughStatistics.pdf (aka LIGO-T050003-00-W) compare with the actual measured power.  It has been found that the analytics formulas can over-estimated the power by 10-15%.  These are derived from the approximation that the signal has constant amplitude and frequency during the duration of one SFT (typically 1800 s), and this approximation is the source of the discrepancy.  The code has been validated by showing that it does go to the correct SFT frequency bin for a given template, and thus is indeed working properly.  A report on this will be given to the CW/pulsar group.  I have also added an important option to the code that provides an easy way to validate that the code is checking the correct bins for the power.  The updated code has been checked into LALapps under the lalapps/src/pulsar/StackSlide directory.

 

Shawhan:

* Spent a lot of time catching up with the email which arrived while I was on vacation last week...

* Reviewed pulsar analyses and presentations to be given at the APS Meeting.

* Someadditional editing of the S2 untriggered burst search paper based on comments from reviewers.

 

Yakushin:

1) On  reviewers' request computed std values for table VI in S2 burst paper (central time and frequency reconstruction of hardware injections). Noticed that some signs in the table got changed somewhere along the editing process.

2) On Erik's request, took a closer look at how well S4 hardware injection properties (central time, frequency, hrss) were reconstructed by waveburst online high threshold analysis:

http://ldas-pcdev1.ligo.caltech.edu/~igor/S4HWINJ/index.html

Noticed that there is obviously a time delay introduced between the sites (I was not aware of that and thought that triple coincidence injections were done exactly at the same time at all the sites). Peter confirmed that was really the case:

 

http://www.lsc-group.phys.uwm.edu/cgi-bin/bag-enote.pl?nb=burs4simulations&page=9

3) Working with John and Sergey to put waveburst into DMT CVS (the most important part of it, WAT, was already in DMT repository, however, postproduction scripts, online and offline scripts were not) in preparation for the waveburst review.



--------------------------------

Simulation and Modeling (Bhawal)

--------------------------------

 

Weekly E2E Physics Meeting

---------------------------

Sany Yoshida presented results he got after implementing Violin modes (based on Virginio's model) in e2e last week. There was also discussion about proper way of mode matching of input beam to SimLIGO. Mark Barton talked about "Adding Violin Modes to the Mathematica Pendulum Models". Viewgraphs of both presentations are available at:

http://www.ligo.caltech.edu/~e2e/ME2ET/Minutes05/050414/

 

Mode matching in LHO and LLO

---------------------------------------------

(Hiro) The following physics were studied and was reported at the weekly commissioning meeting. (G050229)

 (1) effect of the replacement of the ITMx at LHO4k

 (2) differences using different input beams at LLO (A) matches with the arm when ITM is cold and (B) matches with the arm when ITM is hot.

 

 As a follow-up calculation, various overlapping of Carrier and Sidebands are calculated and circulated in the commissioning group. Also, FFT results together with a match script is provided so that results can be calculated which are not provided in the summary table being circulated.

 

Mechanical simulation

----------------------------

(Mark Barton) This week I added basic support for violin modes to my Mathematica AdvLIGO triple and quad pendulum models. To approximate the continuous distribution of mass in the wires, I used 5 beads, each of mass 1/5 that of the whole wire, separated by 6 massless wire segments, each of compliance 1/6 that of the whole wire. (The number 5 came from advice by Virginio Sannibale and is the minimum required to model the first 3 violin modes with tolerable accuracy. The number is hardwired into the model, but can be changed easily enough by cutting and pasting some fairly formulaic code.) To avoid introducing longitudinal modes, each bead was geometrically constrained to move on a plane at right angles to the vector between the endpoints of the wire as a whole. To keep the number of degrees of freedom manageable, I only applied this treatment to the final 4 wires supporting the optic. This produces 4 wires x 5 beads x 2 axes = 40 new DOFs, for a total of 58 for the triple and 64 for the quad.

 As one would hope, the augmented model reproduces the low-frequency modes exactly but now has moderately realistic violin modes. The predicted frequencies are quite close to reality: about 10% low for the first three harmonics (although rather worse for the top two). This is about as much development as needs to be done for the purposes of use in E2E. For completeness it would be nice to implement damping properly, but this will require new features to be added to the modelling toolkit, to allow different damping at the each end of a wire element.

 

Simulation of 40 meter Interferometer

------------------------------------------------

(Monica) Finesse confirmed Twiddle results about discrepancies of minor signals between e2e and Twiddle. Those discrepancies were still there after the e2e simulation of the Dual-Recycled Michelson Interferometer (just the central part of the IFO, no arms): so there is something wrong in the simulation or just in the computation of minor signals. To check if discrepancies come from the use of the PSD (Power Spectral Density) module, analysis of the time series data obtained with e2e has been done with a Matlab program implemented by Virginio to calculate transfer functions. The main signals have been recovered while minor signals show a different behavior with respect to e2e. The Matlab program will be checked again as up to now is still noisy.

 Future implementation of the radiation pressure in the e2e 40m model to evaluate the effects of optical springs.

 

Dual recycling summation cavity module

-----------------------------------------------

(Hiro) C++ version is being developed based on the previous calculation (T040062).

 

State Space implementation in modeler

-------------------------------------------

(Hiro) The speed has been dramatically improved and a system with violin modes can be simulated faster than real time. Right now, LIGO simulation runs 100 times slower than real time due to the optics calculation, so this state space module speed is no problem. Mark Barton found a case suggesting a bug of the code, and it is being traced

.

 

Alfi

----------------

(Bruce) - Finished node validation for the checking for and simple navigation to unresolved connections.

        - Working on speed issues in the updating of connection widget data types on various bundle related user actions.

 

(Melody) Continuing on fixing existing Problem Reports. Currently working on the user interface for allowing the user to choose the display for primitive nodes: graphic or text.

 

---------------------------------

LDAS Software Systems (Blackburn)

---------------------------------

 

 Corrected the CRC checksum calculation for pre-Version6 frames. This fixes an issue seen with FrVerify. It is being fully tested and should be available early next week.

 

Worked on generating MD5 sum values (PR2751). The core of the code is in place. More time is needed for testing and debugging. This code should also be available early next week.

 

Added new user (Igor) to the GDS CVS repository.

 

Added E12 and S4 time ranges to the controlMonitorAPI's client for one click selection per PR2810 request. Started working on the request to have a single button in the controlMonitorAPI's client that would allow all user commands to be tested at once per PR 2812.

 

Ran LDAS integration and system tests on LDAS version 1.5.38. and noticed that the lsync test is failing in a non-deterministic way  that has not been seen before.

 

Added new regression test to merge RDS frames from differing processing paths as part of the fix for PR 2807. Began working on a test to verify that the default compression level is now "one" instead of "six".

 

TCLGLOBUS

 

Worked on Globus FTP Client third party transfer functionalities. MIT GSIFTP server (ldas.mit.edu) is refusing a connection request to pull the file from ldas-cit.ligo.caltech.edu. Need more investigation.

 


Worked on completing test cases for Globus I/O and FTP Client functions.

 

OSG GRIDS

 

 Responded to inquiry from OSG operation group regarding LIGO's migration plans for moving onto the OSG GRID, in particular the plans for migrating iVDGL Grid3 hardware onto OSG. This was coordinated with the LSC Computer Committee.

 

-------------------------------------

LDAS System Administration (Anderson)

-------------------------------------

 

Caltech

-------

(Dan Kozak)

* Verified that the list of S4 frame files in LDR at CIT exactly matches what is in /archive/frames/S4.

* At LHO, dealt with /archive filling up because A4 data was not configured to be archived to tape.  Part of the fun here involved figuring out how to get the releaser to work again (it had given up trying).  umount /archive + mount /archive seems to have done the trick.

* Still trying to figure out the discrepencies between the data holdings of the CIT nodes vs. ldas-gridmon's LDR and RLS.

* Created outstanding grid accounts.  Worked on improving script to do this.

* Converted lag plot to PDT.

 

(Phil Ehrens)

* PR#2807 - createRDS command should not restrict GEO frame file names to follow a LIGO convention in order to merge.  I extended the cresteRDS command to make use of the more general -framequery syntax used by other frame API user commands. This makes it possible to specify ifo/type/channel sets in combinations not possible heretofore. CLOSED.

* PR#2800 - createRDS -compression level default should be 1. CLOSED.

* PR#2791 - getFrameData and concatFrameData data should support compression. Investigated problem and discovered that C++ layer work is required in order to implement this. Passed the ball back to Ed Maros. OPEN.

* PR#2788 - The output action should support creating frames with compression enabled.  No mechanism exists to do this at present. The C++ layer of the datacond API will need to be modified, as will the frame API C++ layer, before any Tcl code can be written in the interest of solving this PR.

* Replaced some disk drives in the cluster and test systems.

* Ongoing investigation of use of grid proxy certificate objects for Subversion certificate authentication.

* Minor user support for Subversion repository.      

 

(Stuart Anderson)

* Continued testing on SAM-QFS 4.3 which resulted in SUN fixing a slow queue management algorithm.

* Received and installed 2 test 10Gigabit Ethernet cards in a Quad Opteron Solaris 10 machine.

* Various cluster maintenance tasks.

* Intalled matlab V6 and V7 in a standard location on all the Lab clusters.

* Upgraded Ganglia to version 3.0.1.

 

MIT

---

(Keith Bayer)

* Switched matlab license file to point locally.

* Added several more accounts.

* Updated packages (via yum) on ldas-pcdev1 so that matlab will run.

* Started thinking about tearing down the rack in NW17-037 which includes the DMT Sun boxes (lancelot/enoki) and the grape cluster.

* getting quote from ASA for another pcraid (seems easiest thing to do for testing NFS) - we'll need another one soon anyways.  Probably more than that for S5.

 

Livingston

----------

(Igor Yakushin)

* The condor nodes were down for half a day on Tuesday for AC work.

 

Hanford

-------

(Ben Johnson)

* The room came close to overheating this past weekend, which resulted in the manual shutdown of 2 full node racks. The ultimate cause appears to have been worn and very loose fan belts on both Liebert air conditioners. The room now has adequate cooling.

* The /archive filesystem filled up because I failed to add the A4 directories to the archiver.cmd file. This may have precipitated an OOM condition on gateway on Sunday. The system has now recovered and is currently working.

* One of the nodes failed to power up after the air conditioners were fixed. I am presently investigating.

 

---------------------------

General Computing (Wallace)

---------------------------

 

MIT:

(Keith)

-Requested new ip address for highbay pc

-Patched windows computers

-Continuing to investigate LDAP when time permits

 

Livingston:

(Shannon)

-Helped John Thacker with Norton Ghost on setting up backups.

-Reinstalling a Windows laptop for Allen Sibley

-Working on getting subscribed to various security mailing lists

-Spoke with CDS candidate Matt Rippa.

-Finished setting up a few more machines on CDS to log to the central Syslog server.

-Working with Syskonnect still on the bad fiber card for the new firewall, and ordered a 4 port Cu Gbit card.

-Ordered a UPS for the lab rack.  Working with Rus and Bernie on a power source for it.

-Looking into some software that Mike Pedraza told me about for Windows patch management for both CDS and GC.

-Still looking into RBAC and BSM - allows extremely fine grained control and replacement for su/sudo.

-Working with Caltech on a licensing issue and also getting more software from them under the CIT licensing.

 

Hanford:

(Christine)

 

CIT:

(Mike)

-Out sick half the week.

-NTSRV's: Ghosted all NTSRV's for end of month backups.

-Loaded 2000 Server for George Stokes to run Apache web server to replace (Antares) this is an on going project.

-Work a little with Ares corp. working out some licensing issues for the PRISM software.

-Holding down the fort while Larry is out this week attending a conference.

-Misc. onsite/phone user support.

 

(Veronica)

- LIGO:  Videotaped and compressed software presentations for the DCC.  The streams are posted online.  The 1.5+ hr presentations were too big to fit onto a DVD.

Loaded the security patches onto the Windows servers.

Updated the PAC18 website.

Working with Julie on website updates for Barry.

Troubleshoot the DCC search engine.  Mike and I ran a diagnostic utility and were able to bring it back up with minimal downtime.

Working on moving the Amaldi3 conference website to ligo.org.  Rewriting the original ASP so that they can run on an Apache server.

Preparing high-resolution images for a Smithsonian publication.

Updates to various webpages.

- LSC:  Posted a batch of updates to the page for papers under review.

Posted a page for the elections of LSC representatives. 

Updated the roster database, assisted Irena in LSC mailing lists and roster database-related issues. 

Posted late submissions to the March meeting talks webpage.

 

(Larry)

-Made a number of minor purchases. A couple of USB pocket drives have been ordered. They have become a little more popular for backing up the notebook computers.

-Worked on a number of accounts. This includes adding and removal. Also cleaned off the data of a couple of old accounts.

-Assisted Irena in resolving a LSC database access problem. There was a communication issue between her PC and the application.

-Spent more time testing the modem pool. Still appears to have some problems but the change made at SBC has definitely improved the situation.

-Builta portable tape unit. We can now restore 4MM and 8MM tapes using the same box. It was built from a number of left-over items including a unit supplied by PMA.

Also, spent a couple of hours restoring data for different people.

-Continual work with the spam filters.

Mail Statistics April 7-13, 05

Accepted Mail   22,232

Rejected Mail   12,788

Virus Mail       4,853

False Positives    157


Total Mail      35,020


Advanced LIGO and Supporting R&D (Shoemaker)


Systems and Management

No report this week.

 

Seismic Isolation

 

From: Ken Mason <kmason@ligo.mit.edu>
 
SEI Structure:
We have received the hardware ordered by ASI prior to the contract close out. This includes all parts for the spring calibration fixture. Myron has inventoried the parts and has begun assembly of the calibration fixture.

Ed Jasnow has verified with the maraging steel supplier that the slab on reserve is large enough to accommodate an increase in the blade spring width.

Suspension

From: Janeen Romie <romie_j@ligo.caltech.edu>
 Advanced LIGO Suspensions
Working on the detail drawings for the tablecloth assembly.                                                      

Participated in Justin's Gray Areas meeting on Tuesday concerning outstanding issues for the DRR.

 
From: Ken mailand <kmailand@ligo.caltech.edu>
I have worked with Helena to produce an air bake oven specification for the LASTI parts.
The Grieve Co. quote is ~$12,500. for 48x48x72 size, ~two other quotes pending.

We have received 4’” S.Stl. stock for the lower suspension installation arm fabrication.
I have started the detailing of the component arm parts, and making a list of the purchased parts, bearings etc.
 

From: ctorrie <ctorrie@ligo.caltech.edu>


ADVANCED  LIGO SUSPENSIONS


Lower Structure
I have been working with Russell on the lower structure. The face plates are with a local machine shop, via Mike Gerfen, for quote. The final detailing of the drawings will be completed by tomorrow. I hope to have the quote today. we are still planning on 2 structures

Overall Assembly
The interface between the upper structure and the suspension and the interface between the lower structure and the upper structure has been completed. (This involved 3 groups) Russell and I found a few interface related issues. These have been discussed with RAL and the rest of the group and the drawings have either been updated or will in due course.

LIGO Movie
Nothing to report

Workshop
There have been some delays this week as both of the RAL engineers have been on vacation and several questions came up about their parts. Tim is now back and these should hopefully be resolved by tomorrow.

Assembly Tooling
I have been working on a series of parts that will help us assembly the quad here at Caltech. These are now with Ric in the Physics Shop.
These will be needed for both the "dirty" and "clean" build planned for Caltech.

PDMWorks and SolidWorks
Yesterday I met with Bob Weber, with the Palomar Observatory group at Caltech, to talk about PDMWorks and SoildWorks. We exchanged observations and Bob showed me how they are using their vault. We agreed to meet again in a month or so. Mike Perreur-Lloyd is setting up a vault and SolidWorks suite for LISA in the UK and we have also agreed to keep in touch on this topic. in the next moth or two I think we will consider moving to SolidWorks 2005.


Design Meeting
http://www.ligo.caltech.edu/~ctorrie/QUAD_ETM/quad_etm_setup_page2.html

 

Core Optics

 

From: Helena Armandula <ahelena@ligo.caltech.edu>

No report this week


Pre-Stabilized Laser

From: Peter King pking@ligo.caltech.edu

 

No report this week

Auxiliary Optics

 

From: Michael Smith <smith@ligo.caltech.edu>


ADV LIGO

 

BS DIFFRACTION LOSS

I have modeled the BS in ZEMAX and have preliminary results for the geometric and diffraction losses of the input beam from the power recycling mirror (PM) through both arms to the ETMs; and the geometric and diffraction losses for the injected beam from the signal recycling mirror (SM) through both arms to the ETMs. I have almost completed modeling the range of BS parameters with thickness varying between 50 to 72 mm, and diameter varying between 350 to 400 mm.

 

Preliminary results for the ADVLIGO baseline; t = 60 mm, D = 350 mm are shown below for 1W power input ( the model assumes that the PM input beam enters and exits symmetrically about the centerline of the BS, this gives maximum input into the arms of the IFO):

 

                                geometric       diffracted      total

PM transmitted arm              1.74E-4         45E-6           2.19E-4

PM reflected arm                0.90E-4         25E-6           1.15E-4

PM both arms                    2.64E-4         70E-6           3.34E-4

diffracted power loss is approx. 1/4 of geometric power loss

 

SM transmitted arm              1.37E-3         2.34E-4         1.60E-3

SM reflected arm                0.67E-3         1.29E-4         0.795E-3

SM both arms                    2.03E-3         3.63E-4         2.40E-3

diffracted power loss is approx. 1/5 of geometric power loss

Other Laboratory R&D

From: Riccardo DeSalvo desalvo@ligo.caltech.edu


Marco & Juri

 

Received the Mexican Hat mirrors from LMA Lyon

Redesigning input beam for MH interferometer: we have studied the laser

profile getting the beam waist and its astigmatism. We also found a

rough deviation from the ideal diffraction-limited gaussian beam

described by a m-square factor sensibly greater than 1.

Marco designed a new telescope to fix astigmatism and mode match our FP

with spherical end mirror (f=400mm instead of 200).

Creep experiment: still taking measurements at 40 degrees. Position

pretty stable

 

Alessandro Cacciani, visitor from Universita’ Roma I

 

at this stage of my stay I am still gathering information from different people to see how to contribute to LIGO. In addition to Riccardo, I am in touch with Peter King, Bill Kats,and, particularly with the groups of the 40m Interferometer (Rana Adhikari) and Data Analysis (Alberto Lazzarini and Rejean Dupuis). Presently, I am reading the documents these two last groups have provided.

On top of the above I am preparing a seminar on Solar Gravitational Red Shift measurement.

 

Riccardo

Measuring performance of IP legs for OMC SAS.

 


For additional information about this report, contact S. Whitcomb or P. Lindquist