Weekly Report for
Week Ending March 31, 2005
The LIGO Executive
Committee Agenda for Monday April
4, 2005 will be:
(Meeting time: 10:30 am Pacific Time)
- Announcements
- Comments on Weekly Report
- LSC Issues (Saulson)
- LIGO Lab Operations
- Administration
(Lindquist)
- Sites (Raab,
Zucker, Shoemaker)
- Commissioning
(Fritschel), Detector (Coyne)
- Campus Research
Facilities
- 40 Meter
(Weinstein)
- TN, ( Libbrecht)
- LASTI (Shoemaker)
- Data Analysis and
Computing (Lazzarini)
- R&D and Advanced LIGO
(Shoemaker)
- CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION AS NEEDED
Special Items:
Special Announcements:
Weekly
Report Highlights:
LSC Issues (Saulson)
no report
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Petrac)
LSC MOUs and Research Plans and Progress Reports
Non-LSC MOUs
SITE TELECONFERENCE (Lindquist)
A site teleconference was held on Thursday, March 31, 2005. The following
items were among those discussed:
- FY
2005Costs—The costs at the end of March (this represents the end of
the first half of FY 2005) seem to be coming in a bit light, probably
because of the S4 Science Run.
- The
list of assigned actions updated through March 10, 2005 will be found Here.
PROPERTY MANAGEMENT (Chargois)
>From: Ed Chargois <chargois_e@ligo.caltech.edu>
- No
report (campus property inventory).
DOCUMENT CONTROL CENTER (Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
- Reviewed
numerous vendor responses for an EDMS system for the DCC, LIGO, and LSC
Collaborators and selected those that seemed to address most of the system
requirements and were within budget guidelines.
- Set
up demos from four companies--two for next week, two the following. Have set up individual times with
the presenters prior to the demo to explain in more detail what we currently
have and what we want a new system to do. Will complete a packet of LIGO-specific documents for
them to process on the fly using their own systems so we can compare
systems more easily.
- Working
to set up time with Doculabs at the AIIM Conference. This is a group of experts who are
neutral consultants who make themselves available to review requirements
of customers against potential
vendors and to give appraisals of individual software packages and
companies from past experience.
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- packages:
in - 19, out - 5
- faxes:
in - 22, out - 17
- Continued
to process LSC presentations.
- Began
to check if all LIGO Science Seminar presentations posted from 2004 to
2005 are in the DCC database system.
COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman, Salone)
>From: Esther Cunningham <esther@ligo.caltech.edu>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Florence Kaufman <fkaufman>
- When
a Cost Transfer is made in the Oracle system, the expenditure is
transferred as requested, however the encumbrance balance in the account
is not adjusted to reflect the expenditure transfer. As a result, the encumbrance
balance in the account to which the expenditure was transferred is
overstated while there encumbrance balance in the account from which the
expenditure was transferred is understated by the same amount. I referred this problem to
Caltech's Problem Resolution office to see if there was a way to solve it. The response was to recommend a
rather complicated fix that would have involved submitting another Cost
Transfer to reverse the original Cost Transfer. Esther Cunningham and Gina Salone have come up with a
simpler solution, which would reverse the original transaction and then
re-enter the transaction charging the expenditure to the correct account
number. We have successfully
tested this solution to correct a payment to the Exploratorium in March
that was charged incorrectly to the Hanford Outreach account instead of to
the Outreach Award. Yet to be
tested is whether this solution would work when the expenditure and
correction are not made in the same month, although our impression is that
this solution would work in this situation as well. I want to thank Esther and Gina
for coming up with this solution, which not only eliminates the need to
submit a Cost Transfer but also results in the encumbrance balances being
reflected correctly.
- Noticed
that the Visitor Program was being charged for Medical and Dental
Insurance premiums for a visitor even after the visit ended. Notified Cindy Akutagawa, who has
arranged to have 3 months of charges reversed.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)
>From: irena@ligo.caltech.edu (Irena Petrac)
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- The
architect/engineer for the LLO Science Education Center remains on
schedule for the production of construction documents by the end of June.
- Corrections
have been made in allocating expenses to the Exploratorium to the proper
site. Reversing the costs,
and re-distributing them to the proper account did this. This was in lieu of a cost
transfer.
- The
appropriately witnessed amendment to the LSU/NSF lease will be sent to LSU
today.
- The
web-based registration method for the LSC conference at LLO worked very
successfully. It will be
implemented for the LSC conference at LHO in August. This will remove the need for any
checking accounts at the sites.
SUPPORT (Baldon, Lloyd)
>Irene Baldon
>Dorothy Lloyd
- Processed
the usual invoices for payment. Tracked and followed up on invoice
problems. Reviewed and recorded payments processed by Esther the week of
March 21.
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
PROPOSALS and REPORTS (Lindquist)
The annual report and request for FY 2005 funding for the LIGO Visitor’s Program
will be due to the NSF at the end of April. I have prepared a first draft and distributed copies for
comment to key visitor contacts within the LIGO community. Have already received a number of
comments back. We should have no
problem making the deadline.
DCC Steering Committee (Lindquist)
The DCC Steering Committee met on March 30. L. Turner is setting up demonstrations with selected vendors
(see above). Our target date is to
finalize a recommendation by June 1.
Some work around may be required to support engineering needs leading up
to S5,
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- Minutes
and Action Items from March meeting have been posted.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
Nothing significant to report.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of Commissioning Activities at LIGO Hanford Observatory (Landry)
Selected elogs from the week of post-S4 are linked below:
- S4
calibration efforts during the post-run freeze were the dominant activity
until Tuesday.
Cavity
pole measurements differed from those taken Feb 4 last year.
- After
the thaw, efforts to understand which 4k optic or optics needs
compensation or replacement took place. These include steering
the 2k thermal compensation (TCS) laser onto a 4k optic (the beam is sadly
clipped in vacuum by the 2k optic structure). The clipping is at the
50mm level, as seen in this upside-down view
of the 4k ITMX as seen by the 2k TCS. Later in the week, central (in
detail) and annulus (at max power) TCS heating was recalibrated.
- 2k PSL instabilities continue. The 2k FSS transfer function was confirmed.
- full
double-precision floating point is used in the new H2 LSC code installed
Thursday
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
No report.
Initial LIGO Detector Science & Engineering
(Coyne)
CDS
see also the CDS weekly meeting minutes in the commissioning archives
CDS Software (Rolf Bork)
- The
new LSC code is ready to go (doubles in all calcs). This software has also
been updated to handle 4 more ASPD (compile option), so it is ready for
that if/once it is decided to add them. The new code requires change out
of EPICS and all suspension front end software to handle doubles from LSC.
It is scheduled to install and test this software on LHO2K tomorrow.
- Alex
has filter modules built into EPICS (Linux version). There is still some
discussion with Daniel on exactly how this will be used and possible
porting to vxWorks version of EPICS.
- Heard
from Phil Willems last week that 1/4Hz noise was seen in ASQ signals in S2
and S3 data. I asked him to try and verify if this is also seen in S4
data, as a fair amount of CRC checking was added to the Daq system prior
to S4. If this is still a problem, we will need to try and track it down.
- I've
been in contact with Mike and Peter on when the best time would be to make
another trip to LLO. Tasks include building/installing new Framebuilders,
LSC upgrades, gigE install and fiber timing install. It will either be
next week, or, most likely, May, as they have work already scheduled for
most of April.
CDS Hardware (Jay Heefner)
Fiber Optic Timing Link (Sander)
- All
components tested. Peter King is checking the test plan.
- Can
not get the test equipment for the original site tests for at least
several weeks. Sander will find out the date that LLO wants to install the
system and decide whether we can come up with an alternate set of tests.
LSC PD (Ben)
- Rich
and Ben are coming up with a total number needed for the sites. That
number is on the order of 30. Todd is working on some PDs that will be
tuned to 24.5 MHz and 29.5 MHz.
ISS (Flavio)
- The
ISS for H2 can be shipped tomorrow.
Elect Shop (Todd)
- 5
SOS coil drivers are ready for the 40M. 5 additional units are in fab.
Front panels for the modules are in house.
- 2
LSC PDs ready for test. 4 more are very close.
DMT
no report
PSL (PeterKing)
In characterizing some baseline noise measurements with the
SR785 signal analyzer, one set of measurements was affected by some magnetic pickup
whereas three previous measurements were not. Fortunately this only messed
up the region beyond 10 kHz, which is outside the region of interest for the
low-frequency intensity noise stuff I want to do. Thus far everything has
been characterized at low frequencies, the photodetector dark noise, instrument
noise floor and some reference resistors.
TCS Quiet Chiller (Ken Mailand)
I have given information on a larger chiller heat exchanger
to Cheryl at LHO, she wants to install it in one of the units for the 4KX arm.
Optical Metrology (GariLynn Billingsley)
The surface measuring interferometer has been calibrated, measurement of one
of the original LIGO pathfinder pieces repeats in power to about a half a
nanometer. The instrument appears to be more sensitive to vibration since
its refurbishment; it is difficult to get the same kind of repeatability as we
had when originally characterizing the LIGO optics.
In characterizing optics for potential replacement in H1, we've found
relatively higher scatter on BS06 and BS02, but aren't sure if the higher
signal is due to the 50% coating of the BS vs the HR of the ITMS. Liyuan
is trying to get a model working on that. It may also be time to switch
to an integrating sphere, so we can have a better chance at getting absolute
numbers for scatter.
In surface measurement BS06 shows marks, but is still in spec (http://www.ligo.caltech.edu/docs/E/E960100-D.pdf
). The marks appear to be smaller versions of the streaks that were seen
on 4ITM01 and 08. Helena will try cleaning to see if she can move or
remove the spots. You can see a preliminary phase map of BS06 at http://www.ligo.caltech.edu/~coreopt/Interferograms/BS06prelim.jpg
LIGO NSF Documentary Movie (Calum Torrie)
Oddvar, Ken Mason and I have been working with William Maher
to create CAD files of the seismic and suspension system for the LIGO movie
(both initial and advanced LIGO versions).
Optical Contamination Cavities (Lee Cardenas, Liyuan Zhang)
OTF West Bridge
Chamber # 3
Still pumping and cavity is locked.
We still waiting on the 1.00" mirrors to be tested. Cavity is clean.
60-watt laser for absorption test is in Standby
Scatterometer enclosure
We have been scanning the beam splitter two of them for beam
scattering. We have encountered some situation in terms of power shut-off
and building cleaning. Dr. Zhang
is releasing the result from previous scanning.
OTF at Lauritsen
Cavity#1 Chamber has 20 pieces of Micro-D-Connectors IN. The cavity is clean so far. We continue taking measurements for
Ring down and absorption every day.
Cavity #2 is in standby.
40 Meter Interferometer (Weinstein)
IFO commissioning:
- Osamu presented a status
report on work at the 40 meter lab, at the LSC meeting on March 22.
- Osamu made several attempts
to lock the arms with freely moving central part (PRM, SRM, BS) (our
standard approach to full lock is to first lock the central DRMI and then
add the arms; but the reverse approach might be promising as well). He
tried doing a DC offset lock of the YARM using the transmitted light (TRY)
normalized to the power in the POB DC. This didn't work well, due to (a)
saturation of TRY QPD; (b) oscillation of the servo due to high gain; (c)
the normalization failed to behave well when the signal recycling cavity
swung through resonance.
- He then tried to put
together a simple common mode servo to aid in locking one or both arms.
The signal at POX 33 MHz was fed into an SR 560 amp with a pole at 1 kHz,
actuating on the MC servo test input. Osamu found that the gain of the MC
servo was too low for this to work. He has some ideas for improving the
gain, but will set this project aside for now and go back to locking the
DRMI first.
- Osamu tried locking the DRMI
again but found that, despite all the work done over the last month, it
didn't lock. Something has changed / broke; Maybe alignment, maybe STACIS.
Under investigation.
- Last month, Rana worked on
minimizing the ANG -> POS coupling at high frequency in the mode
cleaner, by adjusting the angle output matrix in the three mode cleaner
suspended optics. Later, Virginio modified the coil output matrix and
filters for MC2 to minimize the POS -> ANG couplings. This probably
undid what Rana did; they will work together to fix it.
- But in the meantime, Osamu
sees that the ANG -> POS coupling is much reduced, and was able to
restore the gain on the MC WFS servo to bring the UGF up from 0.6 Hz to
several Hz. It should be at least 10 Hz; we hope that when Virginio and
Rana are done, we can turn the MC WFS servo system back up.
- Rana, Dan and Osamu are
proceeding with plans to re-layout the AP table, and move the SP LSC PDs
onto that table. All the required new 2" optics and other hardware is
in; they will work on it in the coming days. We decided that we probably
don't need an electro-optic shutter or even a fast mechanical shutter on
the SP beam line; we'll just put in a manual variable attenuator and work
with low power.
- Rob measured the MC and arm
cavity ring downs, and is analyzing the data.
- Rob measured the seismic
noise during the day and night. Now that Virginio has finished tuning up
the STACIS system, Rob will add the accelerometers back into the PEM
system.
IFO modeling and DC detection development:
- Rob presented the plans
for the Homodyne (DC) readout experiment at the 40-meter lab, at the
LSC meeting on March 22.
- Keita gave us a straw man
design for a 4-mirror output mode cleaner for DC detection. Rob and
student Marcus Ng are reviewing Keita's design, and will develop a final
design. Mike Smith will draw it up and order parts for the output mode
cleaner, mode matching telescope, and PZT steering mirrors. We're writing
up the design in preparation for a system review.
- Monica is developing a 40m
model for Finesse, to complement and test her e2e and Twiddle models.
- Virginio has been working
on the e2e mechanical simulation.
PSL:
- Our PSL tabletop ISS system
continues to saturate regularly. Jay will re-adjust the servo offsets to
reduce the problem. Our tabletop ISS was a prototype; we'll look into
getting a production version to see if it saturates less often. But it may
be that the cause of our saturation is the Mach-Zehnder... Or it may be
due to the strong correlation of the ISS photodiode with humidity (seen on
all PDs on the PSL table; a mystery!).
Electronics, controls:
- We have had several
failures of the front-end controls, leading (typically) to undampable
optics; this happens as often as once a week. It can be fixed by rebooting
the digital suspension controller systems. The obvious suspect is the
timing system; some kind of timing glitch causes channel hopping of the
OSEM sensor signals, and then loss of synch. (Anther possibility is some
corruption of the reflective memory network). We look forward to improved
fiber-optic timing signal distribution. Jay will also ask Rolf if the
modifications made to the ADC timing system for HEPI are worth
implementing here.
- Jay and Ben continue
testing the new ASC system. The signals propagate through the ICS110Bs
just fine, but there are a few small problems with the signal propagation
through some of the Pentek channels. These will be troubleshot this week,
and fixed. It should be ready for 3 WFSs, soon.
- 10 of the rev. B Coil
Driver panels arrived from Front Panel Express. Ben gave them to Todd to
use for the boards that are being made. We will then install 3 of them for
the PRM, SRM, and BS (we already have installed and commissioned them for
the ITMs and ETMs).
- Ben has finished packaging
the RF frequency multiplier circuit that was designed by Dan, Rana and
Steve. Initial testing shows some harmonics that need to be dealt with.
Ben is working on some filtration that might help.
- Ben installed the
reflective memory fiber that replaces the temporary fix that we installed
in the sosvme crate.
- The TRX and TRY QPDs have
noise above 1KHz that Ben has determined to originate somewhere after the
PD head. The grounding jumper of the output AD 620 is suspected by Rich,
and will be investigated this week.
- Jay is working on putting
the signals from the Thorlab PDs at the ends into the LSC front end
electronics, with a new board. Jay will figure it out and Rob will add the
signals to the LA code.
- Jay is also getting the
signals from the IPANG QPD into the ASC front end. We'll need new hardware
and software.
- A disk failed in our DAQ
RAID array, and was replaced.
- Steve reports that the
EPICS readings of some of the ion pumps and turbopumps are screwed up. Jay
will investigate. He will also look into implementing code by Dan to read
in more information about the ion pumps and turbopumps, and fix the EPICS
on/off toggle code.
- The noisy Coherent OSA head
was delivered to Wilson House to see if they can fix it.
- Jay is preparing a
PC104-based EPICS system which he will test at our LSC/ASC rack sometime
soon.
Computing:
- Alex and Jay have
completely re-invented the controls computing and networking at the 40m
lab!
- A NAT router appliance was
installed, so that the controls computers can get out of the martian
network and see the web (and the ilog!!!), but nothing can get in.
- A new Linux box with ~ 500
GB of RAID disks was installed, and is now the NFS server for our online
software on /cvs/cds; which is backed up via RAID. ALL operator and
embedded computers now point to this disk, instead of the old version on
op140m (Sun E450 running solaris).
- That new Linux box also
runs a web server so that we can run our conlog web interface; a
samba server to serve /cvs/cds to windows laptops; and a DNS/YP server to
share the /etc/hosts table and the user accounts.
- Actually, the DNS/YP
service is still running on op140m (Solaris); Alex will move it to the new
linux box and then turn op140m OFF.
- Alex installed two Linux
boxes were installed to function as operator consoles; they can run
EPICS/MEDM, dataviewer, ROOT, DTT. There are some problems, being
worked out.
- Our framebuilder
software is still in some private location on fb40m; it will be moved to
/cvs/cds on the new Linux box.
- Two of our wireless laptops
run Windows and are useful EPICS/MEDM displays. The third was converted to
Linux FC3 and works as a fully functional operator's console, with MEDM, dataviewer,
DTT.
- After all the changes to
the controls computers, Rob got all the always-running scripts running
again: (a) snapchecklist; (b) RGAlogger; (c) ISSautoreset;
(d) autolockMCmain40m; (e) conlogger. He also set up a script to
make RGA plots easily.
- Jay will try to reorganize
and clean up our EPICS state code, which is a mess.
Lab Infrastructure:
- Steve
cleaned and glued black glass beam dumps onto all of the RF PDs.
- Steve
and Bob performed maintenance on our three Leybold roughing pumps (first
time in 15 years). They changed the pump oil, and saw some oil vapor on
the intake hose; Bob has cleaned, baked and RGA scanned it. He put
ball-valve spigots on it to make the oil change easier next time. They
raised the entire rack of pumps to make it easy to put in and take out the
drain pans.
- Steve
cleaned carts & dollies around the lab, and provided them in key
places so that people can put equipment on them instead of putting them on
the tops of optical tables.
Bake oven Lab:
- The
new wiring in the south annex bake oven lab is now complete and Bob is
putting everything back together.
- Bob
installed a new internet-ready temperature controller for oven E.
Thermal Noise Interferometer (Black)
No significant progress to report this week.
LASTI (Ottaway)
Ken Mason reports:
Design and analysis is complete for the BSC solid stack, which will be used
to test the suspensions quad prototype at LASTI. Fabrication drawings are now
being made.
Lee Cardenas is at MIT to assist in the dismantling of the initial ligo seismic
isolation in the BSC chamber. The Hepi system has been locked in place, the
dome removed, and downtube has been lowered onto a stand isolating it from the
support table.
Laurent Ruet reports:
We have all (Myron, Lee, Rich and me) spend our week end working on the BSC,
we are a bit more than half way done (masses and optical table have been
removed and midle masses have been put back inside, springs have been reloaded
so that now we are have a "suspended BSC" again, now we need to bring
the clean room frame down again, remove the platform and put the dome back on
it ) On my side, I have finished
thee report about the triple, I am in the phase of reading, correcting
reading.............
Also worked a bit more on the mathematics of the estimator/control.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
Weekly Physics Meeting
Sany Yoshida presented his work at Caltech this week on
Violin modes in e2e model (details below). Viewgraphs: http://www.ligo.caltech.edu/~e2e/ME2ET/Minutes05/050331
) Mark Barton showed results for
some related issues in Mathematica simulation of suspension model of Advanced
LIGO. Hiro discussed some interesting results from FFT studies (details below).
Mechanical simulation
Sany Yoshida worked with Virginio to take over the single suspended mirror
modeling done by Virginio. Hiro worked with them to build e2e boxes. A few bug
fixes and speed improvements of the state space module were made.
Report from Sany: Virginio and
I worked on modeling of the violin mode for the LIGO I Large Optic Suspension.
Using a maple program previously written by Virginio, we first computed the
ABCD matrices to describe the dynamics in the state space representation. Then
we imported the resultant file to an e2e box file to compute the optic's motion for the pendular, pitch and yaw
degrees of freedom.
The current model (developed by Virginio) describes the violin motion in the
following fashion. The suspension wire consists of several segments (up to 15
segments can be used in the current version) each of which is modeled by a
massless string and a bob. Here the last bob represents the suspended optic and
has a different mass from the other bobs. The two wires can have different
lengths, and consequently, different stiffness.
To test the programs, we used white noise as input to the suspension point
and looked at the optic's motion for the pendular, yaw and pitch degrees of freedom.
In this run, we considered five segments (hence up to the fifth order of the
violin mode) for each of the two wires. The resultant power spectra seem to be
reasonable, showing the pendular, pitch and yaw peaks at the right frequencies,
and five peaks of the violin mode with splits consistent with the assumed wire
length difference.
FFT Studies
(Hiro) This work is to help the mode matching test at LLO and to understand
the possible mechanism of LHO2k high recycling gain: The mode matching of
fields in various conditions of interferometer was studied -
- Two
kinds of input beams: one, which matches with cold input mirror (ITM) arm,
and the other with hot ITM arm.
- Various
thermal states of ITMs, two ITMs cold, commonly heated and differentially
heat.
The FFT run results show the following.
- Carrier
(CR) is very stable both in Power Recycling cavity (PRC) and in arms,
almost insensitive to input beams and to thermal states of ITMs. The
curvature and beam size of CR in PRC are set to be the idealistic case,
regardless of the ITM thermal state and input beam.
- The
reflected CR field always have a ring structure (i.e., mixture of TEM00
and even higher order modes) is the input beam is not set to match with
properly heated ITMs.
One conclusion is that the input beam mode mismatching
to Core Optics (COC) shows up most prominently in the reflected field, and
fields in COC are insensitive to the input beam structure. Further study is going
on to understand some of the FFT results.
Commissioning Related:
(Biplab) Worked on two issues: (i) Why H2 interferometer recycling gain is
so good and why H1 cannot achieve a similar value. (ii) Modeling support to
Dave Ottaway for his spot-size measurements of POY beam at H1.
Simulation of 40m interferometer
(Monica) I'm using Finesse to resolve the differences between e2e and Twiddle
for minor signals. I still have some configuration problems but I already built
the 40m optical configuration in Finesse. In the meanwhile I'm calculating
numerical expectations of the power outputs with Mathematica. A new e2e box for the 40m e2e package
is under implementation: I want to substitute the IFO optical configuration
(the central part -> Dual Recycled Michelson) with one consisting of e2e's
'rec_sum' module plus the signal recycling mirror.
Alfi
(Bruce) Continuing work on recursive bundle content tracing and the processes
needed for unresolvable data types in partially connected bundle output.
(Melody) Working on fixing existing Problem Reports (PR). Finished fixing PR 449 (a cleanup
utility to delete ALFI backup files after a certain amount of time has passed).
Finished creating an option in the ALFI Preferences page to clear all files in
the backup directory.
Fixed a bug in the Primitives Properties dialog when associating a data file
for the primitive.
Data Analysis Activities (Lazzarini)
Charlton:
This week I have been performing simulations using my chirplet analysis code
on the LDAS grid machine. Each simulation generates an instance of noise + a
signal which is then analysed to produce a test statistic, which is the maximal
correlation of the data with a basis of multiscale chirplets. I am using the
ldas-grid machine to do a large number of simulations over a range of
signal-to-noise ratios.
Creighton:
I'm still working with the Einstein@home validator to see how much we need
to relax our constraints to get near-100% validation rates. In
particular, if our validation rates get close to 100%, we can reduce our
redundancy from threefold to twofold, for an effective 1.5 times increase in
computational power.
Mendell:
Progress on the StackSlide search was presented at the March 2005 PULG F2F
and LSC meetings; see DCC documents G050144-00 and G050145-00. Attended the 21st Pacific Coast Gravity
Meeting and gave an overview methods talk on the search for periodic
gravitational waves; see G050191-00.
Shawhan:
- Did
hardware signal injection studies after the end of the S4 run
- Followed
up on S4 online WaveBurst events
- Modified
guild and the 'ldasjob' package in LIGOtools to work with the revised
protocol for using persistent socket connections to the LDAS manager
- Released
a new version of the LIGOtools 'segments' package to fix some bugs in
segwizard that appeared when working with certain S3 and S4 segment lists
- Read
and commented on some GWDAW proceedings and analysis results papers
- Worked
on S2 untriggered burst search paper
- Reviewed
PowerFlux material for APS April Meeting
Sutton:
I've been analyzing the data from the new simulation runs of TFClusters that
I performed last week. I used the data to do Monte Carlo simulations of
the LIGO-TAMA network efficiency. These allowed me to quantify the impact
of various possible systematics, such as calibration uncertainties. I'm
now summarizing the results in a web page. In other news, I wrote up some
comments on the LIGO-AURIGA draft for the GWDAW 2004 proceedings. At Igor
Yakushin's request, I also distributed to him (and the bursts group) my
matlab codes for handling detector geometry, antenna responses, and MDC
parameter generation; these might be helpful in designing a new MDC frame
generation engine.
Yakushin:
1) Showed that 4 of the loud triggers produced by S4 online waveburst analysis
are due to the boundary wavelet transform artifact and disappear when one
increases the offset on the boundaries of the science segment from 4 to 8
seconds: http://ldas-pcdev1.ligo.caltech.edu/~igor/followup.html.
We should have done so for S3 analysis as well when the maximum wavelet
decomposition level was increased. However, we did not observe those boundary
artifacts in S3 because the data was very glitchy.
2) Participated in the Special telecon about follow-up studies of S4 online
WaveBurst events this Monday.
3) Redesigning the MDC production infrastructure. The problems with the existing
infrastructure: 1) very slow because datacon instead of Condor is used; 2)
respfilt function was designed for AS_Q calibration and we now use DARM_ERR; 3)
we need more advanced algorithms for beam pattern function and arrival time
computations that would take into account a) non spherical Earth model; b) all
the ifo and bar detectors; c) allow easy coordinate transformation between
Earth and world coordinate systems (useful for directional search); 4) existing
infrastructure is very hard to use and involves too many steps and scripts.
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS
During the LSC Meeting several people discovered a problem submitting jobs to
LDAS from behind the NAT router that was setup for the meeting. LDAS does not
test (hardware not available at this time) client side software from behind NAT
routers which introduce a persistent socket problem. Once the problem was
identified changes were made to the LDAS managerAPI to support connectivity to
clients from behind NAT routers. This fix was patched onto the existing 1.5.1
release of LDAS and placed at all LDAS sites.
Worked on several problem reports targeted for the 1.6.0 release of LDAS:
PR2221 - generic API getElement returns invalid string for empty element array
- Working
on setting up regression test.
PR2729 - FrVerify should verify metadata
- Have
support for validating the start time
- Have
support for validating the duration
- Have support
for validating the leap seconds
- Working
on validating the observatory information.
Did code review of some of the diskcacheAPI pending changes. The patch for fixing
the number of directories appears to be good. It will be tested on a tandem
system over the weekend and then on ldas-dev early next week. Still reviewing
the stride modifications.
Updated cmonClient resource to include a complete listing of user commands
for selection and support filter of DSOs for dataStandAlone also. Tested ldas beowulf search users and
nodes at lho, llo, cit and mit via cmonClient nodes/users test. All passed
except mit search user 9. Updated list of PRs to be included for ldas
1.6.0.
Testing: Ran system test on ldas 1.5.21. Got dataStandAlone and putStandAlone
scripts to run as regular tests on dev without running out of disk space.
Working on script to encompass all user commands. Tested the script on test, cit,
lho, llo and mit when Phil put in the manager patch for persistent sockets and
ldas was upgraded everywhere. Copy Peter's changes to ldasjob package for persistent
sockets to ldas and cvs the change.
TCL/GLOBUS
Fixed incorrect SWIG wrapping of Globus GASS cache package.
Worked on debugging Tcl script to provide an example on how to perform parallel
transfer using Globus FTP client & control.
OSG/GRID
Worked on two OSG configuration issues involving the Globus
Gatekeeper and the Condor-G scheduler left over from Naveen's original
configuration. Still not able to
run condor jobs on the system.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Found
a few problem files that LDR hadn't transferred and referred them Scott,
seems to have just been problems with changing the gpsStartTime in collections.ini.
- Worked
on getting the last files from the end of S4 to transfer via LDR, also
ended up referring to Scott.
- Began
testing SAM-QFS 4.3.
- Tested
performance differences between setting a 3510 cache to optimized for
sequential or random i/o. Doesn't make a big difference for our
application as best we can tell.
- Relabeled
LHO tapes to get them more archiving space.
- Cleaned
up grid account for Naveen (departing LIGO employee).
- Undamaged
a few files that had been marked damaged at CIT and verified that they
could be read correctly.
(Phil Ehrens)
- Replaced
failed disk drive(s) in datacache ide raid array.
- Returned
17 hard drives to Maxtor for warranty replacement.
- Initial
interaction with iVDGL certification authorities, toolchains, and
protocols.
- Test
builds and installs of Subversion with Apache support.
(Stuart Anderson)
- Tracked
down and fixed a reproducible kernel crash on the Linux cluster head node
at Caltech that was due to a known Linux kernel NFS bug that has been
fixed in newer 2.6 kernels.
- Tracked
down slow Condor performance problem (reading a file 1-byte at a time) and
submitted a problem report.
- Worked
on failed IDE-RAID drives.
- Coordinated
tracking down various grid software failures at multiple locations due to
expiring host/service certificates.
- Helped
with SAM-4.3 testing.
- Working
with Sun to track down a SAM-QFS migration bug related to switching our
systems over to supporting small files efficiently.
MIT
(Keith Bayer)
- Investigated
NFS trouble with new pcraid running FC3.
- Remove
certs for Naveen.
- Investigated
condor trouble @MIT. Turned off PREEMPT line in config file, seems
to allow jobs through now - still investigating this.
- Having
Sun put both T3 units on our yearly sun maintenance contract.
- Made
fedora yum changes.
Livingston
(Igor Yakushin)
- Installed
Ben's data archiving tools in the control room and on ldas side.
Configured ldas and dataserver machines for the corresponding AstroWatch
data to be archived by tape robot. Getting some feedback from the control
room. In particular Brian found some bug/feature of the script: if one
erases the last segment offered for archiving, the next time the GUI
starts, it would offer the last segment not from the beginning but from
the end of the previously rejected segment. The reason for such a behavior
is that GUI remembers the last time it was started and next time searches
the conlog starting from that time. One possible fix would be to allow a
user to choose starting from which time the conlogs should be searched.
- Helped
users with accounts and other issues during last week grid workshop at LLO.
- The
support contract with SUN is close to be formalized. SUN has already
received the PO number and my understanding is that we can already start
using the new contract.
Hanford
(Greg Mendell)
- Reports
on gaps in the S4 LHO and LLO data are here:
http://ldas.ligo-wa.caltech.edu/ldas_outgoing/GapChecker/
gapReportLHOS4End032405.txt
http://ldas.ligo-la.caltech.edu/ldas_outgoing/GapChecker/
gapReportLLOS4End032405.txt
Note that these reports show that
there are NO gaps in the LHO raw, L1, or L3 data. There are 15 gaps in
the LLO raw data, and 9 corresponding gaps in the L1 and L3 data. All gaps
appear to be associated with the LLO power failure and framebuilder reboots.
There were no LDAS createRDS job failures during S4!
- Ben
Johnson, Igor Yakushin, and myself have started the archiving and RDS
generation of post-S4 "Astrophysics" data, referred to as A4
data. This data is found at
LHO and LLO, under /archive/frames/A4. Publication of this data
has not yet begun. New web monitoring of RDS generation has also
been set up at these URLs:
http://ldas.ligo-wa.caltech.edu/ldas_outgoing/createrds/dsorun/contrib/createrds/monitor/rdsMonitor.html
http://ldas.ligo-la.caltech.edu/ldas_outgoing/createrds/dsorun/contrib/createrds/monitor/rdsMonitor.html
General Computing (Wallace)
MIT:
(Keith)
- Looked
into einstein@home rsync troubles
- Replaced
noisy fan on lot
- Investigated
windows desktop with virus trouble
- Setup
new lab dell pc
- Setup
new cad pc in myron's office
- Ordered
matlab 7.2 for highbay pc
- Ordered
backup hdd for postdoc
- Helped
get users onto new wireless setup in NW17
- Beginning
to investigate LDAP
Livingston:
(Shannon)
- Working
a strange e-mail issue for John Thacker. His inbox seems to be disappearing,
but not from the server, only on the client.
- Installed
a tape drive directly to Baronne and Ilog. The Ilog will be backed
up to a dedicated tape drive hopefully on a weekly basis. Baronne is the backup server and
needs to be restored in case of a hardware failure.
- Spent
hours cleaning and moving equipment in the computer lab so I can use it as
a lab again.
- Created
a quick howto for Windows Privacy Tools, GnuPG, Thunderbird and enigmail
for Windows users.
- Working
on Solaris 9 install/security docs.
- Setting
up a couple of computers in the lab for use in testing & documentation.
I plan to have one of each flavor, Windows, Mac, Sun, Linux, etc.
This will be useful for creating docs and for configuration and security
testing.
Hanford:
(Christine)
- Network
usage can be seen at http://www.ligo-wa.caltech.edu/~christin/mrtg/
198.129.208.1_198.129.78.122.html
- Installed
the latest version of matlab on the license server.
- Copied
some backup files to CDROM for a user.
- The
centralized syslog server is up and running. I still have a few more
computers to add as clients as well as all the printers.
- Provided
several users with information on how to retrieve their Netscape mail
boxes out of the Symantec antivirus quarantine and to prevent it from
happening again.
- Set
up some more Sun Blade 1500s for users.
- Started
getting the SunFire V120 server set up.
- Other
misc. user support.
CIT:
(Mike)
- PRISM
PM: I received the PRISM PROJECT MANAGEMENT software. I spent time reading
and planning the installation of this software. Ended up having to make
changes to the current VPN server configuration. I am in the process of
running tests with ARES Corp. system administrators, before we release
this set up for general use.
- Ken
Mailand: Updated Algor, which corrupted Solid Works, this required me to
update this software as well. This was very time consuming, contacting the
vender, getting an online account, to download software, licensing issues,
etc. etc.
- Loaded
another laptop for the loaner pool. This has been turned over to Ed Chargois.
- Worked
on setting up a cubicle for a new post doc, up on the third floor of W/B.
- Dave
Beckett: Swapped out a bad monitor for him, and finish up loading his updated
PC. I will be swapping out his old computer, sometime today.
- Larry
Jones: Ghosted his old workstation; and in the process of reloading this
computer, due to the OS somehow getting corrupted. This could be a hardware
issue as well.
- Other
onsite/phone user support that included printing/printers, and software
issues.
(Veronica)
- LIGO:
Installed the webpages for the PAC18 meeting. Working on the last of
the online request forms for the 40m website. LIGO seminars: Webpages updates, support for the
speakers in the setup of their presentations. Even though we only
used a phone dialup for the last seminar, I ran a test cam setup in case
we are asked to provide a webcast.
Updated the roster database. Helped Julie in working on web
updates.
- LSC:
Website updates. Posted the last presentations from the March meeting
and a batch of GWDAW papers for review.
(Larry)
- Purchased
a number of misc. computer items for the users. Ordered a couple of disk drives to get a couple of
workstations back on-line. Working
on another maintenance contract with SUN. Received the Foundry equipment which was ordered last
week. This should allow a few copper GigE connections to the core switch. Worked a number of P-card issues.
- Worked
a little with Mike on the PRISM software installation. Mike has a few more
configurations to test out before going prime-time with it.
- Added
a few new accounts. Removed a couple of accounts. Made another quick review
of the system and we should be able to remove another 10-15 accounts next week.
Trying to get as much cleaned up as possible before the SURF program starts
up.
- Modified
the contact information for the LIGO.ORG domain name. Working on a few more
modifications to make the domain a little more useful to the LSC.
- Resolved
a number of printer issues. Covered cartridge replacement to repairing configuration
files.
- Spent
some time going over DCC items. Includes looking at new packages and trying
to accommodate requests from George Stokes to update the existing system.
- Worked
a number of web related issues. Setting up new web directories, cleaning up
and modification of files.
- Assisted
Julie H. with a number of issues. Most dealing with getting files transferred
to her control.
- Assisted
Ed on tracking down a few property items. Just as a note the webcam has been checked out for use,
finally. It appears there is now more interest in its use. We are working
on getting another one with better resolution.
- Worked
a couple of backup and file restoration issues. Monthly backups will start
tonight.
- Continue
working with the spam filters on the e-mail system. We are averaging over
an hour a day keeping an eye out for false positives. We are now in the process
of seeing what changes can be made to the system/procedure to cut down on
this time sink.
- Mail
Statistics for March 24-30, 05
Accepted messages 15,297
Virus messages 1,491
False Positives 226
Rejected Messages 12,049
Total messages 27,346
Advanced LIGO and Supporting R&D (Shoemaker)
Systems and Management
Adv. LIGO Systems
from Dennis Coyne
See also:
AL Systems web page
AL Systems email archives
Planning
- Worked
on revisions to the FAC (facilities) cost estimate and planning with Carol
Wilkinson and Dwight Carter. SUP (support equipment) has been subsumed
into the FAC work breakdown structure.
- Working
with Carol Wilkinson to revise the SEI (seismic isolation) cost estimate
basis of estimate (BOE) to be consistent with the latest estimate from the
SEI critical design review and re-mapped to a better WBS structure.
Records Of Decision or Agreement (RODA)
See also the RODA status web page
Requirements
Interface Issues
See the "Interfaces" section of the AL Systems web page
- Continuing
coupled SEI/Quad dynamics analysis in modal basis -- a report is being
prepared. Have developed and integrated a finite element model of the
current quad SUS structure with ASI's model of the inner stage of the SEI
system. Have obtained modal based transfer functions.
- Working
to establish proper system design sensitivity for use in setting technical
noise source limits. Will revise the FS sensitivity plot in the current
version of the system design document
- May
need new HAM crossbeams due to the increased overall load. These
crossbeams are also far more compliant than we would like anyway. (New
cost item.)
- OSEM
emitters and photodiodes (80 units each) have been ordered for vacuum
compatibility testing.
- A
small, vacuum compatible stepper motor manufactured by AML and used in
Virgo is being tested for compatibility with LIGO vacuum requirements.
This unit (model C17.2) or a similar one may serve to move a mass on the
SUS quad to enable pitch bias adjustment (though this is not part of the
current design as yet). This stepper motor might also serve for other
future LIGO needs (e.g. in-vacuum mirror adjustment).
- Vacuum
Preparation Oven Plans: We need the capability to qualify large parts for
LIGO vacuum service. (see the UHV page for background).
o
In the
near term (2 months) we need to process the quad SUS prototype for vacuum
service in LASTI. Late this year we'll need to process BSC SEI parts. Ken
Mailand and Helena Armandula have identified some commercial ovens which can
serve our near-term quad prototype needs and arrive in time. The plan is to
place this oven in the 40m vacuum bake lab.
o
Riccardo
DeSalvo and Ken Mailand are working on a proposal and cost estimate for a large
(BSC-sized) cleaning station and dry N2 bake oven. The proposal (to the VRB and
excomm) is to place this system at LLO in the staging building. The alternative
of outsourcing the "precision cleaning" is also being investigated,
but we prefer the in-house approach because we can control costs and cleanliness
better. The proposal should be ready soon.
Reviews and special meetings
- Held
informal SUS Electronics meeting with the Univ.
of Birmingham (Stuart
Aston, Dave Hoyland, Alberto Vecchio) group and the US SUS electronics
people (Jay Heefner, Mohana Mageswaran). Useful meeting with regard to
establishing interface requirements and expectations for the preliminary
design review (PDR).
- The
SUS/UK Electronics PDR has been set for Tuesday 7/12, 8-~11am PT
- Held
a maraging steel "round table" discussion as part of the LSC isolation
working group meeting. Good information exchange, but no conclusions as
yet.
Seismic Isolation
From: Ken Mason kmason@ligo.mit.edu
No report
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
Advanced LIGO Suspensions
Tim Hayler is here from RAL to support quad work. He joined us at the LSC
last week. We have a meeting this morning about the upper structure
design status and the upper structure to tablecloth interface.
Participated in the SUS electronics discussion at LLO last week. Participated
in the LSC before that.
Enjoyed vacation on Friday and Monday.
From: Ken mailand kmailand@ligo.caltech.edu
Adv. LIGO
I’m working on a lower suspension installation fixture arm, attaching to the
flange of the BSC chamber. I’m
doing a detailed design of the arms, minus the interface with the suspension
frame. I will get with Russell
when the framework closer to final design. The Algor stress analysis indicates no problem stresses or
deflection issues on the preliminary design. I have selected a common tapered roller bearing for all the
pivot shafts.
One of the module shelf brackets for the BSC chamber has been completed.
Further work on the attachment of the chassis box will be done when the chassis
box component part has been selected by Todd.
From: ctorrie <ctorrie@ligo.caltech.edu>
ADVANCED LIGO SUSPENSIONS - 2 weeks again!
LIGO Movie
Oddvar, Ken Mason and I have been working with William Maher to create CAD
files of the seismic and suspension system for the LIGO movie.
Quad build
For the LSC meeting last week we had built a triple pendulum. This week we
hope to have a quad suspended from a fixed support.
http://www.ligo.caltech.edu/~ctorrie/pictures/
With respect to tooling Ian Wilmut finished a week at Caltech. With veronica we
gathered a couple of hours of video footage of Ian assembling and using the
tooling he had designed.
Drum Ended Wires
Ricardo and I spoke with Mr. Galli, the producer of the drum ended wires,
and discussed a series of 10x and 60x magnified photographs of the prototype
wires. further wires are planned for the controls prototype to cover the top
and UI stages.
FEA
Tim and I worked on the FEa of the interface ring between the upper and
lower structures, results to follow.
Janeen and I worked on the FEA of the tablecloth. The requirement of the 1st
mode > 20 Hz was easily met.
Drawings for the Controls Prototype
The four main items left for the controls prototype are as follows: -
"3and1" assembly tooling, table cloth and the upper and lower
structures
All are in hand.
LSC Talk
I gave a talk at the LSC which is now on the DCC, LIGO-G050175
Upper structure
Tim Hayler has been visiting form Rutherford Appleton Laboratory for the
last 3 weeks. Yesterday we received 21 drawings and CAD files, including an
assembly, of the upper structure for advanced LIGO. All of the piece parts have
been completed by Caltech Engineering services (CES) and as of yesterday work
can now start on the welding.
Core Optics
From: Helena Armandula <ahelena@ligo.caltech.edu>
Advanced LIGO Coating - Cleaning tests
Document T050055-00-D has been placed in the DCC OUT folder. It shows the
effect of several cleaning methods in optical absorption.
The tests were performed at Stanford
University last March
17th.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
AdvLIGO PSL
The conceptual design review was held last Thursday. There were no big
surprises. Benno (as I recall) will circulate notes about any outstanding
issues that we need to resolve.
The campus safety office confirmed that I did not miss any fine print as far
as laser safety goggles is concerned. The minimum optical density for laser
safety goggles for the 200-W laser is 5.5. So our existing glasses are
sufficient.
Auxiliary Optics
From: Michael Smith smith@ligo.caltech.edu
ADV LIGO
OPTICAL LEVER
I completed a tolerance analysis of a candidate optical receiver lens system
using ZEMAX. The receiver lens has an effective focal length of 13 meters. The
angular/displacement sensitivity on the quad photodetector at the focal plane
is approximately 0.013 mm/microradian; with the QPD's used for the current LIGO
optlev sensors; we should be able to detect a 1 microradian angular beam
deviation. ZEMAX assembled a random assortment of lens systems with typical
tolerance values; the internal beam shifts due to the non-ideal properties
of the real lens elements and the assembly tolerances could be compensated for
by tilting the lens barrel and by focusing of the input objective lens
assembly, so it appears that the lens system can be assembled in a lens barrel
with fixed spacers without the need for individual decentering adjustments of
each lens element. I am in the process of evaluating the coupling between the
displacement and angle of the input beam.
Other Laboratory R&D
From: Riccardo DeSalvo desalvo@ligo.caltech.edu
Juri
I’ve been in Hanford
for the S4 shifts. The abstract “Flat top beam profile cavity prototype” was
accepted for an oral presentation in the conference on “Laser Beam Shaping VI,”
part of the SPIE Optics & Photonics 2005 Symposium which will be held 31
July-4 August 2005 in San Diego,
CA.
I’m working on my simulation program in order to obtain Erika’s results for
the first Mexican Hat mirror prototype and to make further analysis on
misalignment and control of the cavity with Mexican Hat mirrors.
Anamaria:
I have restarted working for LIGO this term. I will be seting up a similar
experiment to the one I did last summer, but more ample. I will try to compare
Maraging, Copper-Berylium, and two types of glassy metal for the MGAS blades.
Right now I am trying to get the blades manufactured. Also I will have to start
training David Koenitz, who will be working with me on the same project.
Marco (29 Mar)
OTF lab: asbestos removal and roof clearing works are finished. We are going
to restart the lab.
PZT driver: PS problem was fixed by putting an anti-latch up filter on the
LN723C voltage regulator into the control circuit of both the high voltage PSs.
Now all OK.
Innocenzo
Pinto &C. Universita del Sannio & Salerno
working on a Genetic Algorithm version implantable in Caltech, and on various
Darwinian evolutions of mirrors.
Maddalena:
Replying to required revisions of LF GAS paper.
Justin:
Playing with different modes of flex joints.
For additional information about this report, contact Stan Whitcomb or Phil Lindquist