Weekly Report for
Week Ending March 17, 2005
The LIGO Executive Committee meeting for March 21, 2005 is
cancelled due to the LIGO Scientific Collaboration Committee (LSC) meeting.
Special Announcements:
Weekly
Report Highlights
Duty cycles for the week at Hanford were high, H1 (83.3%) and H2
(87.0). The cumulative duty factor
thus far at Livingston is 71% with an Inspiral Range of between 6 and 7 Mpc.
LSC Issues (Saulson)
No report.
LIGO Laboratory Administration (Lindquist)
STATUS OF LSC MOUs (Petrac)
LSC MOUs and Research Plans and Progress Reports
- Nothing
significant to report.
For a web page summary showing the status of LSC MOUs and associated
Attachment updates see: http://www.ligo.caltech.edu/~irena/Revstatus/Reviewstat.doc
Non-LSC MOUs
SITE TELECONFERENCE (Lindquist)
A site teleconference was held on Thursday, March 17, 2005. The following
items were among those discussed:
- Budgetary Issues--How are the sites doing relative to budgets?
As of end of February Hanford was at 86 percent relative to straight line
budget. Livingston is at 75 percent, lower partially because they
are not fully staffed. Also there will be some charges hitting
towards the end of the fiscal year in support of the Outreach Center (site
preparation, etc.)
- Conference
Call Carrier--a few questions have been raised about sound quality,
but overall seems to be working well. Still need input from D.
Coyne.
- The list
of assigned actions updated through March 10, 2005 will be found Here.
PROPERTY MANAGEMENT (Chargois)
>From: Ed Chargois <chargois_e@ligo.caltech.edu>
- Nothing
significant to report. Assisting with Campus Inventory.
DOCUMENT CONTROL CENTER (Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- packages:
in - 251, out - 5
- faxes:
in - 25, out - 13
- Processed
a set of HAM drawings from Promec.
- Processed
a set of Adv. LIGO SEI Structure Development drawings.
COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman, Salone)
>From: Esther Cunningham <esther@ligo.caltech.edu>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Working
on change order #159 to Triad for one renewal.
- Followed
up on a pending credit from Bell Pipe and Supply which the vendor will
applying to my credit card for reconciliation on April's report. They have
provided me with a copy of the corresponding credit memo.
- Completed
the two no-cost extensions to Hereaus Optics and Taylor Porter.
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Florence Kaufman <fkaufman>
- Worked
on updating monthly financial reports.
- Prepared
four Cost Transfers last week to correct minor misclassifications of
expenditures.
- Prepared
an analysis of expenditures to date and projected expenditures for labor
and related costs for the LFNS/5.11 and VINT/5.11 accounts, at the request
of Riccardo De Salvo.
- Responded
to a request from Project Accounting to do a funding realignment, which is
required whenever expenditures in a project exceed the budget in Oracle
for that project.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence).
SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)
>From: irena@ligo.caltech.edu (Irena Petrac)
- Nothing
significant to report.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- The
last workshop with the LLO SEC architect, EDR produced a reduction in
scope that preserved much of the original functionality while getting the
cost estimate back within the budgeted amount. The next workshop is scheduled for April 20.
- The
NSF has executed the lease amendment for the LLO SEC, and is now in the
hands of the LSU attorney, who will have it signed there. We are now in compliance with the
requirements of the LSU/NSF lease for the LLO land.
SUPPORT (Baldon, Lloyd)
>Irene Baldon
- Processed
the paper work for eight (8) new/revised trips. There are three (3) trips that need to be completed and
ticketed at this time.
Assisted several LIGO personnel with their travel arrangements
using their P-Cards and made several reservations for outside visitors
coming to LIGO/Caltech for meetings and/or workshops.
- Completed
twenty-three (23) Expense Reports and there are thirteen (13) reports yet
to be done. I continue to
contact travelers who have outstanding Expense Reports (more than one (1)
month old) to ask for their cooperation in sending me their receipts so
that these can be closed in a timely manner. Presently there are two (2) reports more than 30 days
old.
>Dorothy Lloyd
- Processed
the usual invoices for payment. Tracked and followed up on invoice
problems. Reviewed and recorded payments processed by Esther the week of
March 7.
- Processed
requisitions for standard purchases, payment requests and change orders.
For more detail see Cost Schedule Control Systems report by Ruth
Brambilla.
- Jim continued
with data entry in the LIGO database and helping out in the DCC.
PROPOSALS and REPORTS (Lindquist)
The NSF has indicated that we should have our funding for the second half of
the fiscal year very soon.
DCC Steering Committee (Lindquist)
The DCC Steering Committee met March 16, 2005. Linda Turner has contacted or is in process of contacting
several possible vendors and summarized information gleaned to date. Potential vendors include OpenEDMS, by
Altima a Canadian firm, Tower Software, OnBase (four vendors contacted partner
with OnBase),. DocStar, Liberty Net, Liberty Information Management Systems,
CDG, a customized program from an extension of The Boeing Corp, and CERN EDMS.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- A
staffing meeting was held March 14, 2005.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
No report.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of Commissioning Activities at LIGO Hanford Observatory (Landry)
- Despite
losing most of Wednesday due to wind
gusts (at times in excess of 60mph), duty cycles for the week were
high, H1 (83.3%) and H2 (87.0). Nearby road construction on highway
240 yielded impulse
events in both interferometers.
- Another
type of airplane veto: a fighter jet intercepted
a prop plane that strayed too near NP2 reactor's airspace.
- While
fully expected, it is good to see gamma
ray bursts occurring while in triple coincidence.
- Under
very windy conditions such as those of Wednesday 16th, enhanced dust
levels are seen on IFO dark ports. From these plots it is not clear
if this dust is shaken off the table housing or is brought in from outside
despite building overpressure.
4K IFO
- TCS servo mods continued to
be suggested.
- EX
seismic noise that has been in the past casually attributed to the
vitrification plant on the Hanford site, may be self-induced.
As Hanford VIT plant people know of no seismic drivers in the middle of
the night, attention has turned to the LN2
system.
- The
TCS laser power on the y-arm (only) shows large variability.
- TCS
intensity noise was assessed,
and a 4k noise budget produced.
2K IFO
- After floundering a bit
last week in range (straying below 3Mpc), a piecewise alignment
was done, including restoring FMY back to biases similar to early in
S4. The result was a restored range of 3.3-3.5Mpc.
- a
PRM 24V power supply current-limited,
preventing acuire++ operation.
- 16.5Hz
noise made a reappearance
in MX.
Outreach (D. Ingram)
- Vern
Sandberg hosted a showing of the film "Death Star" to an
audience of roughly 150 visitors on 3/5. Next on LHO's World Year
agenda is National
Astronomy Day.
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
S4 Report (Brian O'Reilly)
We had a somewhat rocky week with high winds early on, and high micro-seism
towards the end. As evidence of how high our standards have become our duty
factor for the last 7 days beginning on March 10th was 76%, 83%, 85%, 88%, 81%,
88% and 47.5%. The last (and lowest) number came from a period of very high
microseism and increased activity near the Y-end. One problem noticed during
the period of high winds was a saturation of the Streckheisen seismometer DAQ
for the transverse directions at the end stations. Turning off sensor
correction in these directions seems to have helped our stability.
We briefly interrupted science mode on 3/16 during a period of locking
difficulty at LHO (high winds up there). At this time a new PEM channel was
added L0:PEM-RADIO_ROOF, which should monitor the external RF bursts that we
have seen in the L0:PEM-RADIO_LVEA channel. The antenna is tunedto 24.483 MHz.
For the remainder of the run we plan to take some time to perform PEM
injections, and some miscellaneous hardware injections. The plan is to have a
post-S4 freeze of the configuration to last until Monday the 28th.
Our cumulative duty factor thus far is 71% with an Inspiral Range of between
6 and 7 Mpc.
Education and Outreach (Thacker)
- completed
NSF grant Annual Report
- continued
Local Educator's Network definition/refinement
Safety and Security (Riesen)
Nothing of substance to report this week.
L1 and AdL Mechanical Engineering (Spjeld)
AdL Quad SUS Installation
Fixtures
- Design
review of fixtures in weekly SUS teleconference 3/15
- Table
height requirement and removal of top cross-braces looked into
- Quote
request for IDC linear drives in progress
- Additional
FEA on lift assembly in progress
AdL SEI Engineering Effort
- Reviewed
additional released assembly drawings
- Uploading
release drawings and models to PDWorks vault in progress
- Create
drawings from existing tooling in progress
LLO Outreach Facility - Pendulum Exhibit Wall
- Met
with exhibit designers on 3/16; design details clarified
- Redesign
of preliminary wall assembly in progress
- Looking
into possible ball bearing fatigue issues
General Engineering
- Still
awaiting new GS13 sensor platforms from shop
- Purchased
3D file conversion software in order to provide correct format for NSF
animation film producers
LLO General Computing and LIGO Computing Security (Roddy)
no report
CDS Software Support (Khan)
no report
HPLF, Optics Modeling, Data Analysis and L1 Commissioning (Franzen)
- IPG
Photonics reported that they have almost completed the assembly of the
broken laser and that they have tested it at +100 W. They will go ahead
with a 7 days burn test starting tomorrow Friday March 17.
- Completed
a first draft of a technical note reporting our Melody AdvLIGO mode
cleaner simulation results.
- Have
been asked by Sergey Klimenko (UF) to run burstMon off-line on S4 and S3
data using the CIT cluster. Preparing this.
LDAS/Condor Sysadmin and Burst Analysis (Yakushin)
Data archiving/Condor/LDAS admin:
- Tape
drive 2 had a stuck tape in it. It turned out to be the same tape that got
stuck in tape drive 5 a few days earlier. StorageTek engineer got it out,
tested that the drive is OK and there were no more problems with the tape
robot after that. The bad tape LLO346 has been removed from the robot.
- RDS
creating and data archiving are running fine.
- It
was decided to let the grid school users submit their jobs from the same
ldas-grid box as other users rather than to configure a separate Condor
head node on ldas-pcdev1.
Data analysis:
- Waveburst
online analysis is running fine without a single crash doing trigger
production, triple coincidence, web page generation, matching loud events
with hardware injections automatically.
- I
have added online software injections of optimal orientation SG235Q8.9
waveform to the online infrastructure. The corresponding web page
generation is not quite automated yet. A plot of the efficiency for the
high threshold waveburst analysis is posted.
- Added
r-statistics values to the loud trigger table.
- Added
start time column to the loud trigger table.
- Working
on calculating the rate vs geometric significance threshold and the rate
vs time shift plots.
- Working
on generating ROC (hrss50 vs rate) plot.
- My
first choice summer SURF student has accepted an offer from another
institution so I am considering now other students.
INITIAL LIGO DETECTOR SCIENCE & ENGINEERING
(Coyne)
CDS
see also the CDS weekly meeting minutes in the commissioning archives
CDS Software
Rolf Bork
- Alex
has built and installed two linux PCs at the 40m lab. One is setup to be
the NFS server, which used to be handled by a Sun450. The second is being
used as an operator console. He is now starting work on putting CDS filter
modules into EPICS.
- I
have continued work on front end code generation from a GUI. I have had to
add some generic routines to our code library to handle front end to EPICS
communications and a few other pieces. These are useful for both this auto
code generator and hand writing front end code. I am adding a few things
to the GUI and script such that the code generator knows what order the
front end code is to execute the described tasks. Once this is done
(probably today), I should be able to reproduce the 40m ASC code, both
front end and EPICS, from a GUI. Since there seems to be interest in being
able to use Simulink as the GUI, I will start to look into that next week.
CDS Hardware
Jay Heefner reporting
Fiber Optic Timing Link (Sander)
- 4
transmitters, 3 fanouts and 19 receivers are fabbed and in test.
- LeCroy
will be here Friday at 10:00 to demo the SDA6000A serial data analyzer.
- Sander
will generate installation and test plans for LLO.
LLO Midstation Vac Control (Jay)
- 2
IOCs running. Linux and EPICS are installed on IDE flash drive..
- Received
the signal list from Rus.
- Should
be ready to install by next week.
ISS (Flavio)
- Continued
fab and documentation completion
EE Shop (Todd)
- Building
SOS coil drivers.
- Building
LSC PDs.
DMT
no report
PSL
PeterKing
Nothing significant to report. I was looking into hot-swap controllers
for suitability, especially as this might be a concern for the AdvLIGO PSL.
Optical Contamination Cavities
Lee Cardenas, Liyuan Zhang
OTF Lab. (W. Bridge)
Ready
This chamber still locked with two samples, white Ceramabond, and disks of
TRA-BOND #2254 color light brown epoxy. Cavity is clean and we are waiting on
the new mirrors to be tested for contamination.
Absorption Test Measurement prototype
in standby
Scatterometer system
in progress
We have leveled the optical table and do the scanning again for the
mirrors. We have finished the
scattering measurements for the two fused silica 4ITM05, and 4ITM 08 after cleaning
the surface. The data results are being treated. We have installed back the 4ITM08 for reference and scanning
is in progress. We need to make a
better calibration, for that we have cleaned a 1.00" mirror (50ppm
mirror) and the scattering is much lower(~22uv as compare of 350uv of the big
mirrors). Definitely, the big
mirrors such as 4ITM08 has to be cooked!! cleaned. Since the small mirrors
prove that the scattering level is much lower after the mirror being cooked
cleaned.
The acquisition of a new HEPA unit for the scatterometer enclosure has been
decided as we found a new vendor and the unit price is ~$600. This will take at least 2to 3 weeks
before it can be delivered.
The Quantronix 60 watt laser
shut down
OTF Lab at Lauritsen ROOM 38
Cavity #3
The contamination test for (20) pieces of Glenair Micro-D-connectors still
in progress and so far it has been (3/2-3/16/05 about 15 days). Cavity is locked and we are taking
measurements for absorption and ring down for contamination loss every day.
So far so good. By this time we
can say by our previous experience that these elements appear to be clean and
acceptable. How clean? That can be
assured with time, it usually needs to be at least 1000 hours before we can
fully determined. (for advance
ligo is <= 0.1ppm/yr for absorption loss and <10ppm/yr scattering loss)
Cavity #2 in progress
40 Meter Interferometer (Weinstein)
IFO commissioning:
- Osamu
has been working on improving the quality of the DDM signal at SP. He
installed an RF amp (+20db) on SP DDM PD, because the dark noise was
limited by ADC noise at all frequencies. Now the noise appears to be
limited by PD noise (or RF amp noise).
- As a
result of the amplifier, the SP DDM signal is much improved, and the big
fluctuation of the DRMI with DDM is gone. However, this good performance
does not last so long. After 30 minutes the noise creeps up by a factor
10; but it is still better than before. Could be drifting alignment, demod
phases, etc.
- Osamu
has been trying to track down the source of the large drifts in the demod
phases required for optimal DDM signals for the DRMI. He found leakage of
the POB 199MHz local oscillator into 133MHz PD path, presumably through
the RF dividers. He changed the RF divider to one with more isolation. It
didn't make a big difference; still investigating demod phase changes.
- Dan
and Rana have sketched out a new layout of the AP table with shorter runs
and fewer mirrors, for both the AP and SP beamlines. Dan is calculating
beam diameters everywhere, and the required lenses. Steve is ordering the
required new optics.
- Virginio
has completed work on the diagonalization of the MC2 output matrix, and
measured the resulting couplings. The coupling from POS to pitch & yaw
are now much reduced at frequencies below and above the pendulum freq,
more in line with the performance of the core optics. This should help in
reducing beam jitter in the MC transmitted beam. He also improved the
diagonalization scripts in various ways, and will pass the improvements on
to Vuk or whoever keeps them.
- Osamu
is preparing a talk on the progress towards lock acquisition of the full
DRFPMI configuration for the 40m Technical Advisory Committee meeting at
the LSC meeting at LHO next week.
IFO modeling and DC detection development:
- Rob
is preparing a talk on our DC detection experiment for the LSC meeting.
Rana is planning a talk about DC detection at the sites.
- Monica
is taking a break from trying to track down discrepancies between transfer
functions of small signals calculated with her e2e model and with Twiddle.
She's back to modifying her e2e code to add control loops around the
plant, and building filter banks. She's also preparing summary slides on
the status of her simulation for Osamu's report to the 40m Technical
Advisory Committee at next week's LSC meeting.
Electronics, controls, and computing:
- Dan,
Rana and Ben are assembling the new RF frequency multiplier circuit
(input: 33 MHz; output: 133, 166, 199 MHz). Rich A. suggested baluns on
the input to isolate grounds; Ben is acquiring them.
- Osamu
found that the ITMX suspension is much noisier than the others; the
pendulum frequencies are not as well damped. He was not able to improve
the damping by adjusting gains or filters. We have long suspected that the
side damping is not working, perhaps because of a weak magnet, and Osamu
thinks that this can explain the problem. By adjusting the side damping
filtering, he improved the pendulum damping significantly.
- Ben
modified the Rev.B coil driver Bias Screen to incorporate a few new
features that were desired.
- Three
more SOS coil driver Rev B boards (for the remaining core optics: BS, PRM,
SRM) are almost finished at Wilson House. Ben redrew the front panels for
them because the original CAD files couldn't be found. They have arrived
from Front Panel Express, and Ben will test them for size.
- Ben
ordered a fiber optic to replace a reflective memory cable that had
broken.
- The
QPDs on the PSL table track the humidity strongly. Rana suggested that the
Pds weren't being properly biased. Ben check; they are biased at +24v
straight from the sorensen power supply.
- Our
digital suspension controller (DSC) at ETMX hung, requiring reboot, three
times since the fiber timing system was installed and then uninstalled.
The entire DSC system went down once. We suspect timing errors, causing
channel hopping or other pathologies.
- Virginio
swapped the ETMY STACIS controller with a spare, and it now communicates
reliably with the EPICS controls. We now do not have a working spare. Virginio
and Ben will look at it to see if it can be fixed easily.
- Alex
built us a new linux-based NFS server (called linux1) for our online
software (/cvs/cds/), with 276G mirrored (RAID1) filesystem on two Serial
ATA hard drives. He and Jay have switched all (?) of the online computers
(EPICS linux boxes, EPICS VME cpus, front end controls, operator
workstations) to point to this new machine. All were rebooted and work.
- Alex
set up a web server on linux1 and the conlog web interface, and a samba
server so that our windows laptops can mount /cvs/cds and run EPICS.
- Alex
and Jay set up NIS YP services on op140m. All user workstations are NIS
clients now, so all CDS network hosts should resolve properly (at long
last).
- Alex
and Jay set up two new linux boxes (linux2 and linux3) as operator
workstations. They run medm, dataviewer and dtt. They don't yet run ezca
stuff. We're checking them out, finding small problems.
- Steve
and Alex tested the new UPS backup system; it does indeed cause the
computers to power down gracefully in the event of a protracted power
outage.
- When
the PSL and vacuum system EPICS controls are rebooted, certain EPICS
channels (toggles) are not being restored correctly. This is apparently a
known problem with BURT restore that Rolf is working on.
Bake oven Lab:
- Bob
is working with the electricians to do safety upgrades to the electrical
circuits in the Bake oven lab (installing new circuits and power strips).
All circuits have been locked out and tagged. The bake oven lab will be
down this week for this upgrade.
- Bob is taking advantage of
the down time in the Bake oven lab to connect the temperature controllers
to the network, make repairs and do preventative maintenance on the pumps.
Thermal Noise Interferometer (Libbrecht)
Nothing significant to report this week.
LASTI (Ottaway)
No report.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
FFT Study: From Output Port to the Bench
(Biplab) Studied with 'FFTprop' tool how sideband beam properties change as
it goes from Beam-Splitter to output optics bench through some optics set-up
which reduces its overall width. This study shows that the difference of the
width of a cold state beam from that of a hot state beam is about 7% at the
beam splitter (where beam size is ~35 mm). However, this difference increases to about 50% at a
position (say of WFS1 or the phase camera) where the beam size is of the order
of 1 mm. This fact is mainly related
to the increased level of higher order spatial modes in cold state, which
accumulate Gouy phases different from the zeroth order mode (the main content
in hot state).
Simulation of 40m advanced interferometer
(Monica) E2E set-up for 40m Interferometer has been modified: the control
feedback on the mirror positions has been added and tests to implement a bank
of filters have just started. In the meanwhile I'm continuing analytical
calculations with Mathematica for a Dual-Recycled Fabry-Perot Michelson cavity.
Alfi
(Bruce)
- Finishing
geometry special case connection mechanics: Problem Report (PR) 355
- Continuing
work on recursive bundle content tracing.
(Melody) Working on fixing existing Problem Reports. Currently working on PR 449 (a cleanup utility to delete
ALFI backup files after a certain amount of time has passed) and PR 471.
Data Analysis Activities (Lazzarini)
Charlton:
This week I've been getting
myself set up to start GRID-ifying the stochastic background pipeline:
- obtained
DOE grid certificate and grid account(s)
- installed
LSC datagrid tools, matlab etc on my desktop machine
- reading
through current stochastic pipeline scripts
Mandic:
- I
estimated the S3 H1L1 upper bound on Omega_gw using the Feldman-Cousins
method.
- I
worked on the code for implementing time-shifts in the stochastic
analysis.
- With
Peter Shawhan, we continued performing hardware injections for the S4 run.
In addition to the daily inspiral and burst injections, and the background
pulsar injections, we performed triple-coincident stochastic injections,
as well as the LLO-ALLEGRO coincident stochastic injections.
Mendell:
Progress on the StackSlide search will be presented at the upcoming PULG F2F
and LSC meetings.
Shawhan:
- With
Erik Katsavounidis, revised the S2 LIGO-only untriggered burst search
paper and sent it out to the LSC for comment.
- With
Vuk Mandic, did hardware injections.
Also tracked down the origin of the glitches which have been seen
to occur when a hardware injection stream is closed.
- Preparations
for the upcoming LSC Meeting and Burst Group face-to-face meeting.
Yakushin:
- Waveburst
online analysis is running fine without a single crash doing trigger
production, triple coincidence, web page generation, matching loud events
with hardware injections automatically.
- I
have added online software injections of optimal orientation SG235Q8.9
waveform to the online infrastructure. The corresponding web page
generation is not quite automated yet. A plot of the efficiency for the
high threshold waveburst analysis is posted.
- Added
r-statistics values to the loud trigger table.
- Added
start time column to the loud trigger table.
- Working
on calculating the rate vs geometric significance threshold and the rate
vs time shift plots.
- Working
on generating ROC (hrss50 vs rate) plot.
- My
first choice summer SURF student has accepted an offer from another
institution so I am considering now other students.
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS:
Focused on migrating LDAS and LDCG over to the new GCC 3.4.3 compiler
technologies. This included a removal of the STLPort standard C++ libraries,
which we had been using in place of the standard C++ library from GNU.
Unfortunately, this compiler has exposed a new problem that we have spent
several days trying to understand a new error condition that has entered into
LDAS. When stating a file that has been copied via CURl, their is a 5% chance
the stat function will report success and the inode number to be zero. The
inode number should never be zero.
Plan to next revert to the old tool set and seeing if the problem
continues.
Fixed an error in LDAS that caused the token_math_vector unit test to fail.
Removed building of documentation as to allow the nightly builds of LDAS to
succeed.
Fixed several issues with sinstall to get packages built properly.
Still working on PR 2336 resource update page for putting in headers and
support of sorting; use BLT treeview widget for this. No progress this week
since I have to spend time with ldas testing.
Fixed cleanup_ldas_output.tcl to skip if there are no archive logs for the
wrapperAPI.
Testing: ran system test on ldas 1.5.7. Working on getting test scripts
running from quark to use persistent sockets to retrieve reply back from
tandems and other systems blocked by firewall. Got dataStandAlone scripts to
run on tandem-iii without running out of disk space. Created putStandAlone cmds
from standalone test results to be included in loops with dataStandAlone.
Working on putStandAlone loop tests.
TCLGLOBUS:
Finished testing Globus FTP client functions to move data from tclglobus box
to GSIFTP server. The functions are:
- globus_ftp_client_put()
- globus_ftp_client_get()
- globus_ftp_client_register_read()
- globus_ftp_client_register_write()
- globus_ftp_client_mkdir()
- globus_ftp_client_rmdir()
- globus_ftp_client_delete()
- globus_ftp_client_list()
- globus_ftp_client_verbose_list()
Working on test cases to transfer very large files using different
attributes used to control the security and performance of an FTP operation provided
by Globus FTP client and control packages.
Still working on Perl script to publish the result of each test case on the
web.
Five out of 89 SWIG-wrapped Globus FTP Client functions are still buggy:
- globus_ftp_client_operationattr_get_layout()
- globus_ftp_client_operationattr_get_tcp_buffer()
- globus_ftp_client_operationattr_get_dcau()
- globus_ftp_client_operationattr_get_read_all()
- globus_ftp_client_exists()
Attended first monthly meeting of the ITR2003 recipients (CIT, MIT, PSU,
UWM) to discuss progress on the individual projects that are under the ITR2003
(TclGlobus, DMT, LDR). Also discussed planning for a meeting with our reviews
sometime between now and the OSG meeting in Milwaukee in July.
OSG AND GRID COMPUTING:
Succeeded in configuring Condor on our OSG testbed this week. Our use of a
non-standard Condor user on the system revealed several bugs in the integration
test scripts being used by the OSG integration group to validate OSG sites that
are participating in the integration testbed activities. With the Condor now
properly configured, our LIGO-CIT-OSG site map on the OSG Grid map is now
showing Green.
Kent and Albert have been developing the LSC Computing Plan Model for the
LSC Computing Committee. Inputs for the plan have been provided by representatives
of each search group. The purpose is to have information based on actual S2/S3
experience and projecting to S4/S5 in order to identify CPU resource shortfalls
in the near and longer term future.
THe ultimate usefulness of this plan/model is to develop a needs
justification for gaining access to or acquiring new LSC computing resources in
the future. At first blush, not surprisingly, CW searches are starting to
"flex their muscle". This underscores the need to properly factor in
beneficial access to einstein@home cycles as part of any comprehensive LSC-wide
plan.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Fixed
lag plot problem caused by bad data points, still no good data on why this happens.
- Monitored
LDR status and transfer rates.
- Continued
end-to-end md5sum checks on L0 data.
At the current time, all files that have transferred and been
checked have passed.
- Got
cleaning tapes in L700 at LLO imported into SAM-QFS's catalog. While it sill doesn't clean drives
automatically, it can now be done with the cleandrive command rather than
requiring physical access to the silo.
- Reorganized
all trend frames at CIT into /archive/frames/trend. Discovered a very peculiar
file
(/archive/LHO/minute-trend/archive/H-M-72/H-M-723560400-3600.gwf) that had a duplicate that didn't
compare the same (cmp) but showed the same computed checksum
(FrCheck). Discovered some
overlapping (but not identical) files from the ancient past...working on
cleaning this up.
- Repurposed
some L0 copy 2 tapes at LHO, working on getting more tape slots available
for blank tapes.
- Received
two 3510 disks and put them in the spares unit in Booth.
- Added
grid accounts.
- Refiled
or deleted hundreds of pieces of email...ongoing.
(Stuart Anderson)
- Working
on getting several of the LDAS-TEST cluster nodes back on-line, currently
at 6 out of 8 with the last 2 running a final memory check.
- Monitoring
S4 data and metadata activities.
- Signed
up for a 10GigE evaluation test.
- Inventoried
the remaining available electrical power in 215 Synchrotron and 605
Millikan to find a place to put a new OSG cluster.
MIT
(Keith Bayer)
- Rebuilt
my script that adds users to our cluster.
- Added
several more users to cluster.
- Tested
and sent back 5 defective drives to Maxtor.
- Throughout
several that were beyond warranty.
Livingston
(Igor Yakushin)
- Tape
drive 2 had a stuck tape in it. It turned out to be the same tape that got stuck in tape
drive 5 a few days earlier. StorageTek engineer got it out, tested that
the drive is OK and there were no more problems with the tape robot after
that. The bad tape LLO346 has been removed from the robot.
- RDS
creating and data archiving are running fine.
- It
was decided to let the grid school users submit their jobs from the same
ldas-grid box as other users rather than to configure a separate Condor
head node on ldas-pcdev1.
Hanford
(Greg Mendell)
- S4 data archiving and RDS generation continues to run
smoothly at LHO and LLO.
There are no gaps in the archived raw or RDS data at LHO. The only gaps in the LLO data due
to the power failure and times when both framebuilders have been down or
rebooted.
(Ben Johnson)
- Started
publishing minute trend data for S4 and beyond (LHO and LLO). Added URLs to caltech's
RLS/LRC/RLI/etc. catalog.
- Shipped
63 postS3 L0 second copy data tapes to Caltech.
- Called
Sun about L700/Samfs CAP problem. They recommended patch 118526. As the
patch requires a reboot (so says Sun), it will not be applied, as we'll be
upgrading to 4.3.x after S4 anyway.
- Working
on polishing up publishing code (making it easier for me to add code to
reliably publish different data sets). Also working on a '-c' option to
megamd5.
General Computing (Wallace)
MIT:
(Keith)
- Setting
up collab machine
- Trying
to get rid of old hardware through MIT property office
- Spec'd
and purchased new pc for high bay DSpace/Matlab work
- Put
NW17 wireless onto backup router while I'm building the new router with authpf
- Still
investigating Eudora SSL issues with new release 6.2
Livingston:
Hanford:
(Christine)
- Network
usage can be seen at http://www.ligo-wa.caltech.edu/~christin/mrtg/
198.129.208.1_198.129.78.122.html
- Attended
a phone conference with Amerion, PNNL, and ESnet to discuss possible
options for a backup network service in the event the new PNNL network
were to go down. Nothing much
new out of the meeting except that the time for swap over to the new PNNL
network keeps moving farther away.
They are still hoping for a June time swap, but are not terminating
their existing network contract until Oct.
- Followed
up with NoaNet on another possible networking option. Still waiting for a quote on this
option.
- Investigated
why the mail server attaches the name of the mail server to the return
address of the users when sending off-site email. The result is that I either need
to upgrade and re-build the sendmail software or it is possibly due to the
way the mail host is defined in the Caltech DNS tables.
- Created
more user accounts for people serving SciMon shifts.
- Served
3, 1/2 day shifts as an operator in the Control Room.
- Other
misc. user support.
CIT:
(Mike)
- NTSRV:
Loaded a 2003 Server that is being setup to run as a VPN server. This is still in testing mode.
This VPN service is to run the PRISM Project Management software only.
- Did
a lot of calling around to get information on Citrix MetaFrame Access
server. This is our second option if the VPN server does not work to serve
the PRISM software.
- Modem
Pool: Larry W. and I worked on trouble shooting the 1-800 number hunt
sequence. This now looks like the problem we are having is on the phone
company's end.
- Robert
Ward: Loaded a new laptop for him with General Computing software and
other engineering packages.
- Calum
Torrie: Worked on a visitor's workstation; updating an expired FlexLM
license server for Pro Engineering. This was a project due to the server
caching the old expired license. After going into the registry, and
removing all keys that pointed to the old license, I was able to get this
software back up, and running.
- I loaded
a laptop for the loaner pool to turn into Ed Chargois for travel.
- Worked
the spam filters with Larry W.
- Other
misc. onsite/phone user support.
(Veronica)
- LIGO:
Updates / usual upkeep.
Working on a website for the upcoming PAC meeting. Updates to the last NSF Review
pages. Working on online
submit forms for the 40m website per a request from Robert Taylor.
- Roster
database updates.
- LSC: Updates to the March meeting
website. Updates to document
pages of the LSC website.
(Larry)
- Working
on a number of procurements. We may purchase a new blade for the Foundry
system which will allow copper GigE GBIC. This will help eliminate the
need for some of the converter boxes. Purchased a number of computer related items for
different people. Working on
a couple of h/w maintenance contracts. Discovered that the p-card reconciliation is not too
bad when you have just a few items. Reconciliation only took about 20
minutes this time, normally I wind up spending 4-8 hours trying to get
everything corrected and getting the correct paperwork from the different
companies, this is after having put the orders in the computer
system. Finished up the CIT
campus maintenance contract for the SUN systems.
- Resolved
a performance issue with the main web server. The main problem was a bad
network switch. Unfortunately, there were no error messages on any of the
pieces of equipment involved and I had difficulty duplicating the problem,
so it took a little bit of time to track down.
- Hopefully,
the modem pool problem has been resolved. It appears the provider had mad
some configuration changes which caused the auto hunting feature to work
incorrectly in our environment. This problem should be resolved by the end
of this week.
- Worked
a couple of printer issues.
- Worked
a number of user issues. Started getting Julie setup with ownership of
different accounts, calendars and related items. Assisted in a couple of different CAD related issues.
From one item it appears we will be moving or adding a CAD/FEA workstation
to a location where more people can access it. Still a few logistical
issues to workout. Modified a
number of user accounts.
Cleaned up a couple of the LSC e-mail issues.
- Assisted
the DCC with a couple of items, including getting things ready for the
LSC.
- Moved
the new tape backup system into the computer room and upgraded its network
connection to GigE. The system still needs some monitoring, the automatic
tagging of tapes for recycling is not working properly.
- Continual
work on the mail server. At least one hour/day is spent on checking for
false positives and clearing out different tables.
- Mail
Statistics March 10-16, 05
Accepted
Mail 33,635
Virus
420
Rejected
Mail 13,096
False Positives 245
Total Mail 46,731
Advanced LIGO and Supporting R&D (Shoemaker)
Systems and Management
From: "Thomas Frey" <tfrey@ligo.caltech.edu>
Progress Period from 03.04 to 03.17
Out of the office from 03.09 through 03.15 -
Conference at Monterey, CA
Accomplishments:
- Sub-system
PLANNING activities
- Finished
work on the 40-Meter schedule changes.
- Executed
telecoms with Carol and Dwight.
- Started
preparing information regarding the application of indirect costs within
the detailed estimate.
- ROSTER
DATABASE:
- Assisting
Irena as needed on record changes.
- COST
BOOK DATABASE:
- Working
with Carol and Dwight regarding structure of the cost book database and,
pending changes
Seismic Isolation
From: Ken Mason kmason@ligo.mit.edu
Advanced LIGO Seismic Structure
SEI Structure:
ASI delivered all missing drawings and responded to questions submitted to
them after we reviewed the documentation package.
ASI is submitting their final invoice, probably this week, and Ed Jasnow
will be conducting an audit of the contract beginning Tuesday of next
week. The contract will then be amended to add a fixed price for
consulting of 25K if needed during assembly and test.
We have purchased a version of Nastran to allow us to check finite element
models created by ASI and make changes if necessary.
Actuators:
We have not recieved any actuators from PSI.
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
Advanced LIGO Suspensions
Tim Hayler and Ian Wilmut from RAL arrived here on Monday to support quad work.
Ian is staying for one week. Tim is here for 3 weeks and will join Calum, Mark,
Helena and I at the LSC next week. We thank them both for coming and appreciate
their participation.
Solidworks, PDMWorks, Symantec and Algor all seem to work on my desktop now.
Thanks Mike Pedraza.
Worked some more on the modeling wanted by the LIGO movie folks.
Primarily working on preparing for the LSC next week.
Submitted a first draft of the ear positioning and alignment document to Helena
for comments
From: Ken mailand kmailand@ligo.caltech.edu
I'm currently learning solidworks, and working on the lower suspension
installation arm to move the lower suspension into the BSC chamber. I’m doing a
more detailed design of the arms, and pivot pin bearing housing. The first
algor stress analysis indicates no problem stresses or deflection issues on the
preliminary design. I’m selecting a tapered roller bearing common for all the
pivot shafts.
One of the module shelf brackets for the BSC chamber has been completed.
Further work on the attachment of the chassis box will be done when the chassis
box component part has been selected by Todd.
The preliminary cost estimate for this bake oven/cleaning station is
~$45,000 +shipping.
Two other quotes are expected from other vendors.
Core Optics
No report this week.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
- Testing
of the high power photodetector continues. So far so good.
- I
have been working on sorting out some preliminary laser safety related
issues for the Conceptual Design Review. Benno circulated some
concerns that the pre-review committee had about the conceptual design.
Auxiliary Optics
From: Michael Smith smith@ligo.caltech.edu
ZEMAX COURSE
I attended an optical design course for the use of ZEMAX to do
non-sequential ray tracing. This will be useful in modeling the full ADVLIGO
IFO, and for making scattered light calculations.
ADV LIGO
OPTICAL LEVER
I am in the process of modeling and analyzing an optical lever receiver lens
with effective focal length variable between 3 to 22 meters. The receiver will
be used to make an optical lever system that is sensitive only to angular
deviations of the COC mirrors.
I have established a SURF project to develop and characterize an optical
lever receiver for ADVLIGO.
BRDF MEASUREMENT
I have established a SURF project to develop a BRDF measuring apparatus and
to characterize suitable materials for use as beam dumps and baffles for
ADVLIGO.
Other Laboratory R&D
From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>
Maddalena
- Paper
on low frequency GAS filters accepted for publication on NIM after
modifications.
Juri
- I upgraded
my simulation program in order to include 2D mirror maps, and I made a
first run with the Mexican Hat mirror shape obtained in the LMA
laboratory. The results qualitatively agree with those obtained by Erika
with the standard FFT program. A quantitative comparative analysis and the
study of the tilt optimization is the next step.
- I
spent some hours learning the basics of the LIGO control room for my
shifts for S4 in Hanford
next week.
Alban (LMA)
- Solved
problem with corrective coating alignment, finalizing the production of MH
mirrors. The first mirror should be ready within 10 days.
Marco (16 Mar)
- PZTs
driver debugging: finally identified a problem into the -120V power
supply. Adjusting its two current/voltage rating potentiometers the
voltage fall disappeared only with one board as load. With both the boards
as power supply load the fall comes back, even if now the oscillation is
weaker and just for little bias inputs. Buying a new PS!
- The
OTF lab should be be ready on Monday 28th of this month. At this moment
roof and floor re-building is performed for the first half of the lab. The
next Monday I will move all the stuff in the rehabilitated side to
complete the works.
- Maraging
measurements: hardness measurements showed that Mesa Beam Cavity blades material
was good chemically good but in a poor re-solubilization state and did not
precipitate properly. Re-solubilizing in air the bent blades, and then
undergoing a precipitation process, their hardness was restored to the
value of 51 C-Rockwell scale, close to the typical hardness value for the
martensitic arrangement of the maraging lattice (about 52).
- Creep
experiment: we switched blades temperature from 40 to 200oC for the last
heating run.
Justin
- Measuring
other resonances.
Riccardo
- Designed
glassy metal GAS blades test setup for Anamaria/David.
- Studying
alternative coating strategies with Pinto’s group in Salerno.
For additional information about this report, contact S. Whitcomb or P. Lindquist