Weekly Report for Week Ending March 10, 2005


 Exec. Comm. Agenda

Highlights

LSC

Administration

Hanford Observatory

Livingston Observatory

MIT

Caltech

Detector

40 Meter

TNI

LASTI

Data Analysis

Adv. LIGO Development

Past Weekly Reports


The LIGO Executive Committee meeting for March 14, 2005 is cancelled because of the Staffing Committee meeting.


Special Announcements:


Weekly Report Highlights:

S4 continues, with good duty cycles over the last week - H1 (84.3%), and H2 (75.1%), L1 achieved a very high duty factor over the weekend, including one day where science mode fraction was 98%, L1 currently running at ~7 Mpc inspiral range


LSC Issues (Saulson)


No report.


LIGO Laboratory Administration (Lindquist)


STATUS OF LSC MOUs (Petrac)

LSC MOUs and Research Plans and Progress Reports

  • Updates for all outside LIGO LSC groups have been endorsed by the LSC MOU Review Committee for sign-off by the LIGO/LSC leadership.
  • Progress Reports for all outside LIGO LSC groups have been submitted.
  • The sign-off process was initiated.

For a web page summary showing the status of LSC MOUs and associated Attachment updates see:

http://www.ligo.caltech.edu/~irena/Revstatus/Reviewstat.doc

Non-LSC MOUs

  • No report.

SITE TELECONFERENCE (Lindquist)

A site teleconference was held on Thursday, March 3, 2005. The following items were among those discussed:

  • Web Site Registration for LSC Meeting:  Web site up and working.  Action #129 is closed..
  • Financial:  A mischarge of $88K for "Livingston Atomic Clock" has been residing on the books for some time.  E. Jasnow will contact Caltech Finance to encourage resolution.
  • Livingston Electrical Maintenance Contract:  Issue closed.  There no longer appears any advantage to soliciting an umbrella contractor.
  • Livingston Science Education Center:  NSF has approved the lease amendment.
  • The list of assigned actions updated through March 10, 2005 will be found Here.

PROPERTY MANAGEMENT (Chargois)

>From: Ed Chargois <chargois_e@ligo.caltech.edu>

  • Nothing significant to report.

DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

  • Compiled and drafted a DCC Design and System Requirements document for the DCC Steering Committee.
  • Researched and began putting together a list of potential vendors that have products which match our requirements.  Also compiled a list of questions to ask vendors.  Will create a list and comments/review for the Steering committee by next Wednesday's meeting..

>From: Cleveland Mak <mak_c@ligo.caltech.edu>

  • packages: in - 21, out - 11
  • faxes: in - 35, out - 15
  • No special projects to report.

COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman, Salone)

>From: Esther Cunningham <esther@ligo.caltech.edu>

>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

  • Extended the AT & T blanket purchase order through the end of the current fiscal year. Closed out the old JPL blanket purchase order for the work order and removed the active encumbrances. Checked the expiration date of the LIGO blanket purchase orders to make sure they are current. All of the open blanket purchase orders are now current.
  • Working on the new purchase order for the boards for Livingston.
  • Updated the Purchasing database on the subcontracts and requested extensions or close outs of expired contracts.  Sent out Release of Claims to various vendors for close out.  There are currently 10 subcontracts pending close outs.
  • Completed the Corning change order for the purchase of the blank. Awaiting for the vendor's order acknowledgement.
  • Completed the no-cost extension for Southbridge Sheet Metal and faxed the change to the vendor. Completed the no-cost extension to LaCour dba Kineoptics and faxed the change to the vendor.
  • Placed credit card orders as requested. Following up on missing packing slips and invoices for billed transactions.

>From: Gina Salone <gsalone@ligo.caltech.edu>

  • Nothing significant to report.

>From: Florence Kaufman <fkaufman>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

>From: irena@ligo.caltech.edu (Irena Petrac)

  • MIT has requested allocation of funds in support of their LIGO program beyond March.  [We are proceeding with the change order. --pel]

>From: Ed Jasnow <jasnow@ligo.caltech.edu>

  • Ed Jasnow and Jennifer Mertz were at LLO on Wednesday, March 9, to conduct P-Card training for six staff members who are receiving new P-Cards.  The training included both commodity purchasing and travel.
  • While at LLO, Ed Jasnow worked with Allen Sibley to review the current contracts in existence to maintain various aspects of the site.  This involves sixteen separate contracts to cover everything from the fire suppression systems, to waste removal, to HVAC, well water, etc.
  • Also reviewed were the latest Excel invoices, which have been so low that the proposed procurement for an electrical maintenance contract for LO is being re-considered.

SUPPORT (Baldon,  Lloyd)

>Irene Baldon

  • Processed the paper work for eleven (11) new/revised trips.  There are seven (7) trips to be completed and ticketed at this time.  Assisted several LIGO personnel with their travel arrangements using their P-Cards and made several reservations for outside visitors coming to LIGO/Caltech for meetings and/or workshops.
  • Completed twenty-nine (29) Expense Reports and there are eighteen (18) reports yet to be done.  I continue to contact travelers who have outstanding Expense Reports (more than one (1) month old) to ask for their cooperation in sending me their receipts so that these can be closed in a timely manner.  Presently there are eight (8) reports more than 30 days old. 

>Dorothy Lloyd

  • No report.
  • Jim continued with data entry in the LIGO database and helping out in the DCC.

PROPOSALS and REPORTS (Lindquist)

Nothing new to report.

DCC Steering Committee (Lindquist)

The DCC Steering Committee met the morning of March 9, 2005 pacific time.  Discussion centered on the recently released DRAFT requirements document and potential vendors.  A pointer to the requirements document has been provided to members of the Executive Committee.  Several interesting vendors are being explored.

CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)

No open change requests.

HUMAN RESOURCES (Akutagawa)

>From: Cindy Akutagawa <cindy@ligo.caltech.edu>

  • A staffing meeting has been scheduled for March 14, 2005.  A draft agenda has been posted.

Quality/Safety (Tyler)

>From: Bill Tyler tyler@ligo.caltech.edu

No report.


LIGO Hanford Observatory (LHO) and Interferometer Operations (Raab)


Summary of Commissioning Activities at LIGO Hanford Observatory (Landry)

S4 continues apace, with a higher H1 duty cycles over the last week - H1 (84.3%), and H2 (75.1%). H2's was impacted by an FMY optical lever problem (see below). As usual, some lock losses correlate with earthquake activity.  A typical suite of injections was introduced on the interferometers; burst injections are here reviewed. Injections of fake pulsars injections were started (continuously).  This elog underscores however that the injection process is not yet bulletproof. Fast channel calibration was investigated.

Some IFO-specific elog entries are bulleted below:

4K IFO

  • The thermal compensation system (TCS) has oscillations that remain problematic. More on potential solutions and modifications, below.
  • Fast port shutters replaced last week appear to have fixed our problems.
  • TCS servo changes were considered, leading to a somewhat scrappy elog exchange. More TCS musings were followed by suggested  changes here, and here .  Finally, modifications to the TCS servo were approved.

2K IFO

  • FMY optical levers have been glitching at some level for months to years
  • recall last week we were chasing a mobile line above a kHz; more on our mobile 1200Hz line
  • Ultimately, the FMY optical lever problem took the 2k down for approximately a day .  It was fixed here.

Outreach (D. Ingram)

Roughly 50 Pasco High Geometry students visited on 3/2 under the auspices of MESA.  Mike Landry presented a World Year Public Lecture at Triumf in Vancouver on 2/26.  Fred Raab spoke to ~90 members of the Richland Rotary on 3/3 and to a meeting of the Majorana Collaboration on 2/26


LIGO Livingston Observatory (LLO) and Interferometer Operations (Zucker)


S4 Report (Brian O'Reilly)

We achieved a very high duty factor over the weekend, including one day where our science mode fraction was 98%. The only interruptions were due to large earthquakes and planned commissioning activities.

On the evening of Wed. 9th we finally got back to high power running.  Diagnostic measurements  seemed to indicate that the problem was in the common mode board. A switch to a spare showed this not to be the case. The problem was eventually traced to a bad slider on the MC board (#MZ note: a subtle fault which did not appear in standalone testing, but only manifested itself in the fully integrated interferometer!). This was fixed by inserting a voltage divider and using a different slider setting.

On Thur. 9th we had a downtime to install a new Wenzel crystal oscillator. This had a dramatic effect on our phase noise bump at ~ 2 kHz. We also replaced ASPD2 with a modified version, the old  photodiode was twice as susceptible to AS_I saturation.

From Fri. 4th until Wed. 9th we had a wandering line feature in our noise spectrum. This was traced to the lsc front-end crate. Swapping the pentek ADC did not fix the problem, which turned out to also be visible in the dark noise. We noticed that it was acoustically sensitive, and sensitive to blocking fans at the back of the crate. The problem disappeared while we were diagnosing it, apparently due to cleaning the crate fans of lint buildup (or perhaps because our activities fixed some other intermittent acoustic coupling).

Currently we are running at ~7 Mpc inspiral range and we anticipate no further interruptions for commissioning activities.

#MZ Note: This recovery was technically challenging (you have to admit, those hardware problems turned out to be pretty obscure!!), but the method also presents a good model for performing measured and coordinated repairs during science operations. Each step was thoroughly prepared in advance by the team and downtime was coordinated with LHO, giving a minimal sacrifice of triple coincidence... and substantially improved performance for the remainder of the run.  Great team effort!

Education and Outreach (Thacker)

  • arranged exhibit delivery schedule with Exploratorium
  • began developing exhibit post-delivery training schedule
  • organized SURF resource requirements for summer 2005
  • arranged details for 3 tours
  • organized summer RET response
  • collected anecdotal info on solar telescope exhibits

Safety and Security (MZ for Riesen)

  • I found no site safety concerns during my weekly rounds. (limited to the corner station areas).
  • An accident report was completed Monday 3-7-05 which involved the main security gate being hit and thrown out of alignment by an incoming delivery truck on Friday 3-4-05. The gate has been re-aligned and appears to be functioning normally.
  • Works continues on the inputting of LLO's lasers "beam characteristics" into the Laser Hazard Analysis software data base.

L1 and AdL Mechanical Engineering (Spjeld)

AdL Quad SUS Installation Fixtures

  • New design utilizing electric IDC lead-screw drives for lift in progress.
  • FEA of redesigned transport-table, lift-table and support arms completed.
  • Mass estimate of total redesigned fixtures completed.
  • Contacted local IDC sales rep for application and quotes.

AdL SEI Engineering Effort

  • Review of ASI Engineering Hand-off documents completed.
  • Uploading of release drawings and models to PDMWorks vault in progress.

General Engineering

  • New GS13 sensor platforms production issues resolved.
  • Created and converted LIGO1 BSC assembly for NSF movie makers.
  • Preliminary modeling and analysis of planned pendulum exhibit wall.

LLO General Computing and LIGO Computing Security (Roddy)

In the process of digging through logs and connection status of the firewall I found a windows machine that was infected with some form of windows virus or worm.  This machine does not belong to LIGO.  The owner of the machine has been notified and is taking care of the situation.  The Norton install was expired and had not been updated in a while.  It was scanning the net for port 445 and had > 1700 open connections when I found it.

Working with Syskonnect on a PCI express card that is not working.  The engineers in Germany were able to duplicate the problem and are working on it.

Made several more changes to the firewall.  It has turned out to be quite useful to have a linux firewall instead of Cisco.  I have been able to do many things with it that I was unable to do with the Cisco hardware.  Performance is also better.

Still trying to find a pgp/gpg package for windows that will work reasonably well for "non-technically inclined" users.  I have evaluated several and have not found one that works easily and is compatible with existing tools in use yet.

Purchased the media kit from Sun for the EduSoft packages.  It comes with Sun Studio 9.  Unfortunately, Daniel Sigg needs Sun Studio 10.  I am working with Sun on licensing for it.  A site license is only $100.

Looking into several Sun software packages that may be useful.

Started working on a way of scripting Solaris patch checks under Solaris 9.

CDS Software Support (Khan)

no report

High Power Laser Facility, Optics Modeling and L1 Commissioning (Franzen)

1) Last week we had a telecon with IPG. They reported that the system is cleaned up, new diodes are installed and a fiber block has been installed. The system now gives 80 W. They still need some time to install new and hopefully better diodes and making some other optimizations before going up to 100 W. We requested that they test the system for seven days instead of only 24 hours before shipping which they agreed to do. They again mentioned that if we change wavelength from 1064 nm to 1070 nm or even better 1075 nm the system would be much more robust. We asked them to give the 1064 nm another shot since it is much better for our purpose and what we have paid for. They will keep us updated on the progress. We are expecting to get news tomorrow Friday March 11.

2) The Melody Advanced LIGO mode cleaner model with beam injection through the curved mirror clearly exhibit a great deal less of thermal distortion in the reflected beam even at high power. I need to verify the validity of this before going on but it looks very promising. Please find some results at http://www.ligo-la.caltech.edu/~franzen/melody/AdvLIGO_MC_m3_injection.html.  The UF group is discussing if and how we would change the current MC design in accordance with these results.

LDAS/Condor Sysadmin and Burst Analysis (Yakushin)

Data archiving/Condor/LDAS admin:

  • Tape drive 5 failed and had to be replaced;
  • Couple nodes somehow got unmounted from ldas-grid and I had to remount them back;
  • gridmap-file was synced between ldas-grid, ldas-gridmon and ldas machines;
  • createRDS scripts are running fine, RDS data appears at CIT with the delay of 0.5-1.0 hour, copying of raw data from LLO to CIT is catching up as well (currently it is 69 hours behind).

Data analysis:

1) Waveburst online pipeline including trigger production with 100+1 time shifts, triple coincidence, plotting figures of merit, publishing triggers in ROOT and ASCII formats (ROOT files are made browsable under Carrot so that one can quickly plot various pictures using the web browser) and comparing loud events with hardware injections is fully automated and running great at CIT: http://ldas-pcdev1.ligo.caltech.edu/~igor

Two styles of analysis are performed online:

a) High threshold analysis in which the threshold on geometric significance is set so high that only a handful of the most loud triple coincidence events survive (half of S4 generated only 110 such events so far and most of them have already been explained out by hardware injections). For such an analysis we look both at zero lag and time shifted triggers.

b) Low threshold analysis in which we do not look at zero time lag but only use time shifted events to study the properties of the background. Made a presentation about the waveburst online status at the burst group telecon this week.

2) Finished production of S3 triggers to be used for the final analysis (contrary to the ones with the different time shifts used for tuning the thresholds);

3) Working on incorporating software simulations into the online waveburst infrastructure;

4) Communicating with the potential SURF student concerning the possible research projects for summer;

5) Redoing 'time between consecutive events' picture for S2 paper in black and white on Erik's request.

6) Currently online waveburst infrastructure provides triggers and plots either per job or for the whole run up to now (actually waveburst is configured to keep about 6-8 hours behind the real time). Working on providing daily figures of merit and statistics.


INITIAL LIGO DETECTOR SCIENCE & ENGINEERING (Coyne)


CDS

see also the CDS weekly meeting minutes in the commissioning archives

CDS Software (Rolf Bork)

Alex is working on the PC104-based epics system for monitoring the vacuum signals from LLO mid-stations. This should be done in the next couple of days.

I've somewhat strayed from my post S4 list for the past couple of days. Since our real-time front end code is pretty modular now, I wanted to see if I could write a perl scipt to generate it. We already do this for generating most of the EPICS code, which communicates with the front ends. As a test, I am trying to generate the asc code for the 40m lab. So far, I am able to:

  • Draw the filters and layout using the EPICS MEDM. (Would use a better drawing tool if this finds an application, but it was quick for a test.)
  • A perl script then reads the file generated by MEDM and writes the text file necessary for our present EPICS generation perl script, with extensions for the front-end code generator.
  • Another perl script generates front-end C code based on this file, which includes reading/writing I/O, performing matrix operations, filter calculations, writing to DAQ and reading/writing GDS TP.
  • A Makefile generates the front-end object code.

In this fashion, I have been able to generate and run a basic front end system.  Something like this could be useful for building LIGO-like test stands. It could also be packaged into a PC running Linux, with some PCI I/O cards, for an inexpensive front end for test systems with LIGO-like capabilities and connections to LIGO Framebuilders, etc. Unless there is some interest in this, I only plan to work on this for another day or two to see if I can fully replicate the 40m ASC code using this method. If nothing else, this exercise has shown where a few more generic code modules would be useful in our front end code.

Along these lines, Alex put together what I call "DAQ in a box" for use at the TNI. This is a Linux PC with an ADC module installed. The PC has a Linux version of Framebuilder installed and code to read out the ADC module. The ADC module is triggered by an external clock. So, it kind of combines our ADCU and Framebuilder into one unit. It has full Framebuilder functionality, so it saves data as frames and provides connections to the standard LIGO tool set, such as DTT. So, again, it could provide a LIGO-like environment for test stands without the expense of VME and high end workstations.

CDS Hardware (Jay Heefner reporting)

Fiber Optic Timing Link (Sander)

  • 4 transmitters built and tested.
  • 2 fanouts built, 1 tested
  • 10 receiver built, 9 working
  • 6 more reciever being stuffed.
  • Looking into renting test equipment. Test plan for system needed prior to LLO installation.

ISS (Flavio)

  • Completing documentation and implementing changes on the boards that we have in-house.

LSC PD (Ben)

  • Todd is working on five PDs that will be tuned to 24.5 MHz.  A final consideration of PD numbers and frequencies is expected to emerge from the LSC meeting.

LLO Mid-Station Vacuum (Jay/Alex)

  • Three CPUs with ADCs received and are working. Once the signal list is received from LLO we will generate the databases.

DMT

no report

PSL (PeterKing)

After the recent power outage at LLO, there was a small suspicion that the high voltage power supply for the reference cavity ion pump might be faulty.  A check with the new manufacturer suggested that the LED display was faulty but that the power supply itself was okay.  During the process I learnt that Physical Electronics sold off their vacuum equipment lines and that Gamma Vacuum now sells them.

Optical Contamination Cavities (Lee Cardenas, Liyuan Zhang)

OTF Lab. (W. Bridge)  Ready

This chamber still has two samples, white Ceramabond, and disks of TRA-BOND #2254 color light brown epoxy.  Waiting on the new mirrors to be tested for contamination.

Absorption Test Measurement prototype  in standby

Scatterometer system  in progress

  • The fused silica 2ITM05 is  in the scatterometer   We were scanning for beam scattering. Long term scanning.
  • We have encountered a situation with the base optical table.  It needs to be level more accurately.  We'll do this as soon as finish the scanning.
  • The acquisition of a new HEPA for the scatterometer enclosure is underway.  We have contacted a few vendors and we are waiting on their quote.  So far, we found one that it is suitable and the HEPA wanted it is just the right size and most likely this will be the one.  The cost (~$1200 ).

The Quantronix 60 watt laser shut down

OTF Lab at Lauritsen ROOM 38 

Cavity #3

  • The contamination tests for (20) pieces of Glenair Micro-D-connectors are underway.  Cavity is locked and we are taking measurements  for absorption and ring down for contamination loss every day. So far so good.  By the next week we'll be able to tell how clean they are.

Cavity #2  in progress

  • The assembly is underway.

40 Meter Interferometer (Weinstein)


IFO commissioning:

  • Osamu continues to tune up all aspects of the dual-recycled-michelson (DRMI) signals, discovering and fixing problems as he goes:
  • He found a coupling between the PD DC signals and the double-demod (DDM) signals from the RFPDs at the AP and POB ports. Hartmut Grote saw this problem on the SP port when he was here some months ago, and traced it to an unregulated +15v power line from the back panel on the IQ-Demod board. An easy fix was to use regulated power instead; he implemented this on the SP demod boards. Osamu has now done the same, for the AP and POB DDM boards. He also found and eliminated some ground loops. Now, the cross-coupling noise is much less. He will work with Ben to update the traveller documents for these boards.
  • Osamu sees cross talk between AP, SP, POB demodulated dark signals (offsets) with shutters closed. This is probably due to coupling in the demod board electronics, but to minimize the offsets, he rewrote his offset-measuring script to leave appropriate shutters open when measuring offsets in demodulated signals. Now the offsets are gone.
  • Osamu installed an installed RF amp on the POB RFPD output, to boost the signal. Rana put in caps to reduce ripple in the power supply of the amp. The amplified signal is 25 dB higher. But then Osamu found a ground loop in the amp power supply that made many 60 Hz harmonics, so he cut the ground; now the amp is floating and the 60 Hz harmonics are gone.
  • Ben got the new RevB coil drivers going for the ITMs, and Osamu switched the pitch & yaw bias voltages for ITMX and ITMY to the analog bias on the new drivers. Also, the resistors on the coil drive path have changed. These changes give much more drive to the ITMs for dithering and lock acquisition (but ITMY pitch is still saturated).
  • Dither locking of MICH, now using ITMs instead of BS, with more light on POB, less noise, and less offset, is now much more stable. The dithering of the BS used to make a DC misalignment, so you couldn't turn off the dither without changing alignment. But now with new coil drivers and ITMs this is not a problem.
  • Finding optimal demod phases for the differential-demod signals takes a long time. For the SRC, Osamu now finds that the POB 199 MHz signal is much less noisy than before, while the POB 133 is saturating; he will fix it.
  • Osamu continues to investigate the extreme dependence of the optimal demod phases for the DRMI control signals on the RF frequency: 24 Hz out of 33 MHz introduced 100 degrees of demod phase change in some signals. Under investigation, but it's NOT the MC. The MC has the expected effect on 166 phase, but there's some other effect when changing 33 MHz. He suspects the RF signal generator itself.
  • The signal from the SP DDM is smaller than expected; it should be 10x larger than PO, but it is same size. Osamu suspects a bad cable. Under investigation.
  • The SPOB and POB DD RFPDs were on temporary bases. Osamu and Steve installed the right ones.
  • Rana suggests moving the SP RFPD much closer, to the AP table. He also suggests completely rearranging that table to minimize the path lengths to the critical photodiodes and to use 2" optics were necessary to minimize clipping, scatter and beam loss. He and Dan will work on this. Steve says there's no room for 2" optics on the POB table, and the AP table will be very tight; they'll need to be clever.

IFO modeling and DC detection development:

  • Monica continues to debug her e2e code to find the cause of the disagreement between e2e and twiddle results on transfer functions. The signals obtained at 33 Mhz agree well but 166 does not. She's also trying to do longer simulations to get down to lower frequencies.
  • Monica is comparing analytical and numerical calculations on DR summation cavity.
  • Rob is continuing to explore issues related to control of the DRFPMI, especially how to acquire lock in the arms while the DRMI is locked. He's also continuing his study of noise in the proposed DC readout and homodyne detection, for both initial LIGO and 40m/AdvLIGO.

PSL:

Electronics, controls, and computing:

  • Steve obtained a frequency counter to monitor the 33 MHz output of the RF signal generator. It differs from the front panel of the signal generator by 70 Hz, and drifts by ~2 Hz over 6 hours. We are looking at ways to get it into the control system.
  • Dan, with help from Rana and Ben, is assembling a frequency multiplier circuit with minicircuits components that will generate, from 33 MHz RF, amplified signals at 4*33, 5*33, and 6*33. This will allow us to implement a servo on the 33 MHz to keep it and all its multiples fully resonant in the mode cleaner. Steve ordered the minicircuits parts, and Bob ordered a chassis, connectors and other misc parts.
  • Many of the QPDs on our PSL table have strong dependence on temperature and humidity. Rana wonders if they are being properly biased. Ben will follow up.
  • Ben got all four Rev.B coil drivers installed and functioning properly in ETMX, ETMY, ITMX, and ITMY. The databases needed debugging, and modification, but they are now all correct.
  • Three more SOS coil driver Rev B boards are being made at Wilson House, for the BS, PRM, and SRM. Ben has all of the infrastructure (4116s, cross-connects, databases and screens) needed for this installation in place.
  • Ben remade the new suspension pitch/yaw bias screen to show sliders for the new analog bias controls and lights to show that the old digital bias controls are turned off.
  • Virginio reports that ETMY stacis works well but the controller doesn't communicate with medm or even with its front panel. He will try to swap with spare. He verifies with DTT that the OSEM readings show significant attentuation compared with STACIS off, so it works.
  • Virginio is working on improving the coil output matrix (diagonalization to minimize coupling of POS to pitch or yaw) for MC2, using the new oplev. He has now minimized the POS-to-PIT coupling in the oplevs, so coil diagonalizing should work better. He's also making improvements to the diagonalization scripts that he inherited from Vuk. Hope to finish today.
  • The MC2 oplev signal is smaller than the other oplevs. Virginio and Ben will check why (oplev PD resistors?)
  • Jay, Ben and Monica are debugging and commissioning the new alignment control (ASC) system. They will look into implementing initial pointing servos for PSL -> MC and for MC -> IFO.
  • Rolf is writing a perl scipt to generate the ASC code for the 40m lab (!)
  • Alex is building two new linux boxes for us: one with a small RAID array as an NFS server for our controls directories, as well as a samba server, Apache web server, and YP server. Another will be an operator console, running medm, dataviewer, dtt.

Lab Infrastructure:

Bake oven Lab:

  • Bob is improving his bake oven lab web site. He has a problem with putting pirani gauge readout on the site, and is working on making his iservers talk to them. He's adding more forms to the site.
  • Bob is beginning work on some cleaning & baking for quad suspensions requested by Janeen, more OSEMs for Gingin and hybrid osems for quads.

Thermal Noise Interferometer (Libbrecht)


No report.


LASTI (Ottaway)


Ken reports:

A design has been completed and all parts ordered for a structure to support the BSC down tube. This will be used to isolate the down tube from the support table during pier amplification and other dynamic testing of the BSC structure.

I am currently working on the design of the solid stack for the BSC chamber for testing the quad prototype at the advanced ligo height.  The aim is produce a structure with a resonance above 50 Hz.

Myron has been Cleaning and staging of equipment (walk platforms, chamber floor, optic table support, cartridge clean room, etc.) for the BSC chamber work coming up.

Rich reports:

The BSC is now under HEPI control (again) and is currently taking data to be used in the design of sensor correction filters. We had more than the usual amount of cross coupling, also during the day the ground noise at MIT is high enough that the valves on the actuators are operating at or in their non-linear range, I don't know how these two things couple.

Using the geophones on the BSC optics table we measured the transfer function from the support table (HEPI geophones) to the optics table. This should be useful in the design of HEPI resonant gain.

Laurent is visiting his home institution in France to develop the necessary modeling tools for the upcoming LASTI work.

Jon is repairing our SOS controllers and SR560s


Data Analysis and Computing (Lazzarini)


Simulation and Modeling (Bhawal)

Weekly E2E Physics Meeting

Mark Barton talked about "Suspension Modeling in Mathematica". The physics behind various tools and two major families of models were discussed. Those are: GEO-style triple pendulum and AdvLIGO's quad pendulum. These models are used to generate some numeric state-space matrices which are efficient for time-domain simulation. These matrices are then exported to modules in e2e simulation set-up. Viewgraphs available at: http://www.ligo.caltech/~e2e/ME2ET/Minutes05/050310/.

Modes and Phase camera

(Biplab) Worked on analysis of the limitation of phase-camera set-up  with its pixels distributed on a spiral coordinate and how that  affects the determination of modes in a beam.

Simulation of 40meter advanced interferometer

(Monica) I validate my analytical calculations with Mathematica and  compared them with those done by Hiro and Osamu for the Dual Recycled  Michelson Cavity. The comparison looked satisfactory. I'm still debugging  the e2e code for only Signal recycled interferometer with Fabry-Perot cavities in arms:  Numerical values of the fields at the symmetric and asymmetric ports  for minor signals will be checked.

Modeler

(Hiro) Worked on modeler programming issues.

Alfi

(Bruce)

  • Completed initial bundler rework to accommodate unresolved data channels.
  • Implemented box file finding menu item. (PR 297)
  • Fixing dogleg connection mechanics. (PR 355)
  • Starting work on recursive bundle content tracing.

(Melody) Working on fixing existing Problem reports.

  • Finished working on disabling/enabling appropriate menu items
  • (PR 371).
  • Currently working on PR 449 (a cleanup utility to delete ALFI backup files after a certain amount of time has passed).

Data Analysis Activities (Lazzarini)

Charlton: (A.L. NOTE: Philip Charlton has returned from his teaching stint in Australia; he will be with us for a quarter, then moves on to the Cardiff GEO group to work on stochastic background searches with Joe) - started looking at how to modify the stochastic data analysis pipeline to work on the GRID

Mandic:

I performed several calculations needed for the S3 paper on stochastic analysis. In particular, I combined the H1L1 and H2L1 results, and I determined the frequency range containing most of the signal-to-noise for this analysis.

I worked on the code for studying time-shift effects in the stochastic analysis.

With Peter Shawhan, we worked on the hardware injection code, and have successfully injected a number of different waveforms.

Mendell:

Work continues on making further comparisons between the Hough,  StackSlide and PowerFlux codes and preparing the StackSlide code to generate example preliminary S3 results for the March LSC meeting.

Shawhan:

  • Took SciMon shifts at Hanford.
  • Got the pulsar hardware signal injections going (with Mandic, Landry, and Prix).
  • Did other hardware signal injections.
  • Generated data quality flags for first half of S4 run.

Sutton;

This week I finished the LIGO-TAMA untriggered bursts paper, P040050-02, which has since been distributed to the full LSC for comments.

Weinstein:

  • Reviewing S2 BNS paper.
  • Reviewing S2 BBH paper.
  • Awaiting S2 MACHO final draft.

Yakushin:

1) Waveburst online pipeline including trigger production with 100+1 time shifts, triple coincidence, plotting figures of merit, publishing triggers in ROOT and ASCII formats (ROOT files are made browsable under Carrot so that one can quickly plot various pictures using the web browser) and comparing loud events with hardware injections is fully automated and running great at CIT: http://ldas-pcdev1.ligo.caltech.edu/~igor.

Two styles of analysis are performed online:

a) High threshold analysis in which the threshold on geometric significance is set so high that only a handful of the most loud triple coincidence events survive (half of S4 generated only 110 such events so far and most of them have already been explained out by hardware injections). For such an analysis we look both at zero lag and time shifted triggers.

b) Low threshold analysis in which we do not look at zero time lag but only use time shifted events to study the properties of the background.  Made a presentation about the waveburst online status at the burst group telecon this week.

2) Finished production of S3 triggers to be used for the final analysis (contrary to the ones with the different time shifts used for tuning the thresholds);

3) Working on incorporating software simulations into the online waveburst infrastructure;

4) Communicating with the potential SURF student concerning the possible research projects for summer;

5) Redoing 'time between consecutive events' picture for S2 paper in black and white on Erik's request.

6) Currently online waveburst infrastructure provides triggers and plots either per job or for the whole run up to now (actually waveburst is configured to keep about 6-8 hours behind the real time). Working on providing daily figures of merit and statistics.

LIGO Data Analysis System

Software Systems (Blackburn)

LDAS;

The 1.5.1 release of LDAS went out this week. It has a fix to allow merging non-aligned LLO and LHO frames into a single RDS frame in the createRDS code. This came about from the expanded feather in the 1.5.0 release of allowing shorter frames to be automatically generated when data dropouts in the instruments occur. The 1.5.1 release is now running at MIT, CIT and TEST. LLO and LHO are free to upgrade when it doesn't interfere with the science run. But since LLO and LHO do not have each other's datasets at this time, the upgrade is not significant to their sites. NOTE: LDAS is now running again at MIT.

The stalled LDAS-MIT user accounts that collected during the MIT down time were updated on the LDAS-MIT system.

Successfully advanced the LDCG and LDAS code to run with the new GCC 3.4.3 compilers on the Tandem 2 LDAS system. Preliminary testing indicated that this compiler is about 10% better for the overall performance of LDAS on Linux systems. Don't have a comparison yet for Solaris hardware improvements and expect this will have to wait until the migration of the code base onto the LDAS-DEV system in a few days. Also, with this new compiler, we are attempting to go back to the STL library provide by GCC instead of having to use the STLPORT version of the STL libraries due to better thread support in STLPORT. Conclusive results with the GCC STL libraries will have to wait until the code has been challenge tested on the LDAS-DEV system.

Added the fix to CVS to all creation of 100% of the raw frame channel lists in RDS frames.  The 20,000 or so channels were causing an FrHistory overflow when this operation was attempted in the 1.5.0 and 1.5.1 code base. The fix is running on the LDAS-DEV system and will be in the 1.6.0 release.

Upgraded the LDAS-DEV and LDAS Tandem systems to the new DB2 8.2.1 release. In our unit tests, this release of DB2 demonstated nearly a 50% improvement in performance. NOTE:  Also upgraded MIT to the required 8.1.5 release of DB2 since they had not upgraded LDAS since the 1.3.0 release.

With the LDAS CVS repository reopenning this week, several watershed fixes to the control-MonitorAPI and the genericAPI were checked in and have now been tested on the LDAS-DEV system.

TCL-GLOBUS:

Development has progressed in the last week to the point that only 4 out of 89 Globus FTP Client functions are remain buggy:

  • globus_ftp_client_operationattr_get_layout()
  • globus_ftp_client_operationattr_get_tcp_buffer()
  • globus_ftp_client_operationattr_get_dcau()
  • globus_ftp_client_operationattr_get_read_all()

Currently have developed tests for the following six Globus FTP Client functions to emulate FTP client/server data movements.

  • globus_ftp_client_put()
  • globus_ftp_client_get()
  • globus_ftp_client_register_read()
  • globus_ftp_client_register_write()
  • globus_ftp_client_list()
  • globus_ftp_client_size()

Began working on Perl scripts to automate publication of the results of individual test cases on the web from nightly build.

OSG:

Now have Ganglia configured and running on the three OSG worker nodes. There was an issue that was discovered due to the LDAS-CIT and LDAS-TEST cluster being networked across the switch which was causing the LSC Data Grid to report OSG worker nodes in its private ganglia. This was resolved by changing the default broadcast to a specific multicast on the OSG nodes.

Have successfully configured MonALISA on the OSG gatekeeper. Our OSG site now has a green dot on the MonALISA homepage.

Presently working on bringing up the condor batch system on the three OSG nodes. There have been several issues associated with sharing these nodes with LSC Data Grid which are slowing down the completion. Learning how to install and run condor on the non-standard "condor" unix account being chief among these.

Hardware Systems (Anderson)

Caltech

(Dan Kozak)

  • Restarted LDR a few times because of LDRTransfer memory leak and LDRqueue table leak (both now fixed).
  • Fixed LDR lag plot problem caused by two bad data points.
  • Generally monitored LDR status and transfer rates.
  • Continued end-to-end md5sum checks on L0 data.  6 files from LLO were continually transferring, failing md5sum check and being requeued, but in the last 48 hours 3 of them eventually made it through successfully.  I've handed this off to the LDR team.  Other than that, all L0 data has been transferring successfully.
  • Synchronized grip-mapfiles at CIT.
  • Worked with Igor to diagnose a failed 9940 tape drive at LLO and then debug why it's replacement didn't work.  Kicked SAM-QFS to get it past the problem and staging data (for LDR) again.
  • Re-filed or deleted hundreds of pieces of S4 email...ongoing.

(Phil Ehrens)

  • Worked with Mary Lei and Keith Bayer to get the MIT LDAS system up and running LDAS-1.5.1.
  • Ported LDAS generic API smtp.tcl module to a completely generic mailing module for Tcl which supports attachments and use of .signature file.
  • Wrote a script for producing automated reports of ide raid system status by retrieving and parsing the pages produced by the ide raid webserver.
  • Ongoing work to produce easily installable and maintainable Linux system images.
  • Collected some data which will be useful for developing a beowulf configuration diagnostic script. This in response to the relative difficulty of starting the LDAS mpi API at MIT (due to ssh/rsh and lam configuration issues).

(Stuart Anderson)

  • Various LDR tasks related to S4 data movement.
  • Helped with MIT Fedora Core 3 upgrade.
  • Working with Sun to solve transition problem in re-tuning our large QFS filesystems to better support small files associated with grid computing.
  • Split cluster users from 1 to 4 separate 1TB file servers.
  • Isolated and reported one Condor configuration management bug.

MIT

(Keith Bayer)

  • Troubleshooting condor job failures.
  • Changed cluster over to static mounts.
  • pcraid8 stability problems cured after cdrom drive disconnected from board.

Livingston

(Igor Yakushin)

  • Tape drive 5 failed and had to be replaced;
  • Couple nodes somehow got unmounted from ldas-grid and I had to remount them back;
  • gridmap-file was synced between ldas-grid, ldas-gridmon and ldas machines;
  • createRDS scripts are running fine, RDS data appears at CIT with the delay of 0.5-1.0 hour, copying of raw data from LLO to CIT is catching up as well (currently it is 69 hours behind).

Hanford

(Greg Mendell)

  • S4 data archiving and RDS generation continues to run smoothly at LHO and LLO.  There are not gaps in the archived raw or RDS data at LHO.  The only gaps in the raw and RDS data at LLO are associated with the power failure and a reboot of both framebuilders on Mar 03, 2005 at 19:48:35 UTC.

(Ben Johnson)

  • Created a script status page, and added it to the "Useful Admin Links" page.
  • Added lfn_exists() method to publishing script and restarted all publishing scripts with the new code. Scripts have been running fine for 7 days.
  • Assisting some local users with Matlab <- archived data interface.
  • Preparing talk for local linux users group. I was recruited for the local outreach effort this upcoming weekend.

General Computing (Wallace)

MIT:

(Keith)

  • -Investigating mail trouble with eudora 6.2
  • -Building collab machine for postdoc
  • -Building einstein@home mirror machine
  • -Rebuilt old Dell laptop w/ XP (as spare)

Livingston:

(Shannon)

  • In the process of digging through logs and connection status of the firewall I found a windows machine that was infected with some form of windows virus or worm.  This machine does not belong to LIGO.  The owner of the machine has been notified and is taking care of the situation.  The Norton install was expired and had not been updated in a while.  It was scanning the net for port 445 and had > 1700 open connections when I found it.  Working with Syskonnect on a PCI express card that is not working.  The engineers in Germany were able to duplicate the problem and are working on it.
  • Made several more changes to the firewall.  It has turned out to be quite useful to have a linux firewall instead of Cisco.  I have been able to do many things with it that I was unable to do with the Cisco hardware.  Performance is also better.
  • Still trying to find a pgp/gpg package for windows that will work reasonably well for "non-technically inclined" users.  I have evaluated several and have not found one that works easily and is compatible with existing tools in use yet.
  • Purchased the media kit from Sun for the EduSoft packages.  It comes with Sun Studio 9.  Unfortunately, Daniel Sigg needs Sun Studio 10.  I am working with Sun on licensing for it.  A site license is only $100.  Looking into several Sun software packages that may be useful.  Started working on a way of scripting Solaris patch checks under Solaris 9.

Hanford:

(Christine)

  • Network usage can be seen at network usage.
  • Working with Amerion, PNNL and ESnet to determine the needs of a backup network system should the PNNL network go down.  We have been talking about exactly how the backup would work and I requested a quote from Amerion who may provide the backup service.  I'm also looking into ISDN and possibly DSL services.  No DSL to our site, but maybe there is a method to bring it out from Richland.
  • Created more new user accounts for LSC members serving S4 shifts.
  • Discovered in the authlogs, an attempted break in on all of our Sun computers back on Jan. 10th.  An IP address originating in Amsterdam was trying to SSH in to every one of the Sun computers using many different user names and port numbers.  I'm guessing it was a script because it attempted all the same logins at the same time on all the Sun computers.  Thankfully none of the Sun computers were cracked and there is no evidence of the intruder getting in.
  • Mounted more disks from ldas on to GC computers for analysis of the data.
  • Installed the new printer in the reception office.
  • Other misc. user support.

CIT:

(Mike)

  • Setup all visitor workstations that were used for temporary offices for Bridge Annex users.
  • Ran monthly ghost backups on all NTSRV's.
  • Ed Jasnow: Made multiple copies of CD's & DVD's from ASI, to send out to various users.
  • Janeen Romie: Worked on a Solid Works issue she was having, when opening certain drawings. This turned out to be an incompatible video card. I was able to find and download an additional driver that seems to have corrected this issue.
  • Search for Remote Access Server to replace our current modem pool that is having some hardware issues. It looks like I found one, and have forwarded to Larry Wallace to work the cost and purchasing of this unit.
  • Finished up loading a laptop for Shourov Chatterji.
  • Started loading server 2003, to setup and use as a VPN server.
  • Other misc. user support.

(Veronica)

  • LSC:  Finished the installation of an application for the online credit card submission for the March meeting.  The application is now fully functional.  Updates to the LSC website and to the March meeting webpages.
  • LIGO:  Started working on a website for the next PAC meeting.  Updates to the websites of the past NSF reviews.  Prepared high-resolution photos for a publisher.  Set up and test-ran an application for online request submittals for the 40m website per a request from Robert Taylor, troubleshooting and support on how to add it to the website.  Support and website updates for the LIGO seminars, updates to other LIGO webpages.
  • CaJAGWR:  Captured and compressed the video of the last seminar, posted website updates.

(Larry)

  • Finished making changes for the ligo.org mail services. Jeff M. at PSU ran a few tests and things are working to where they can start setting things up at PSU.
  • Handling different logistical issues with the computer room. The air-conditioning change to the building has created some issues. The testing of the fire suppression system still needs to take place and people have been looking at that system.  Moving equipment around to handle more equipment installations.
  • Worked a security incident. It appears to have been a ssh exploit on one of the users accounts and their desktop unit. The unit has been removed and the user has made the appropriate changes.
  • Worked with Mike on a DVD problem. After a number of tests and attempts to copy the DVD, Mike had a new copy of the DVD from the company made and delivered. The files on the first DVD were definitely corrupted.
  • Cleaned up a few accounts. Restored an old account that is being used again.  Setup a new account for Julie H..
  • Rviewed some more material on the Weblink Conversion Guide. The workaround, supplied by Campus, Veronica setup for the LSC meeting is definitely the way to go for the short run. The Weblink conversion supplied by the company requires a great deal of work and setup, more than could have been done in the time we had.
  • Spent a great deal of time going through mail logs and filters. Added a number of items to the whitelist.  Mail Statistics March 03 - March 09, 05

Advanced LIGO and Supporting R&D (Shoemaker)


Systems and Management

From: "Thomas Frey" <tfrey@ligo.caltech.edu>

No report this week.

Seismic Isolation

From: Ken Mason <kmason@ligo.mit.edu>

SEI Structure:

We have received a final DVD containing the final released documentation from ASI.

Oddvar Spjeld, Dennis Coyne and I have been reviewing the documentation. We expect to close out the purchase contract with ASI next week.

The BSC seismic isolation design package is complete. All models and analysis files have been opened and checked. The fabrication and assembly drawings are ready to send to suppliers for quoting and fabrication.

The tooling and fixturing required to assemble the BSC seismic isolation system is approximately 60% complete. LIGO engineers will complete this design.

The HAM seismic isolation design is approximately 30% complete. Models and analysis exist for the stage 1 and stage 2 subassemblies. The pods, actuator assemblies and spring assemblies are mostly finished. Stage 0 and all fabrication and assembly drawings have not been started.

Actuators:

All actuators are scheduled to be shipped from PSI today.

Suspension

From: Janeen Romie <romie_j@ligo.caltech.edu>

Advanced LIGO Suspensions

Russell Jones joined us for the last 2 weeks to work on the quad. His participation was greatly appreciated. We look forward to Tim Hayler and Ian Wilmut from RAL next monday.

I submitted an updated SUS budget to Carol and Dennis.

Got the tablecloth modeled and, with Calum's help, meshed. Worked with Calum and Russell on the earthquake stop design concept for the quad.

Mike Pedraza had to do lots of work on my desktop but hopes he's found a solution to the problems I was experiencing with Solidworks, PDMWorks, Symantec and Algor.

Worked some on the modeling wanted by the LIGO movie folks.

Sent around a preliminary schedule for the SUS breakout session on Monday, March 21 st at the LSC.

From: ctorrie <ctorrie@ligo.caltech.edu>

VISITS

Russell Jones and Norna Robertson visited Caltech last week. As part of their visit we, along with Janeen, went through the steps involved with the "3and1" assembly technique. This involved the upper intermediate, penultimate and test mass in a mock up of the lower structure. This proved extremely useful and allow us to test a whole series of assumptions. At the end of this build we suspended, admittedly briefly, a triple pendulum from a fixed top mass.

These photos and more are available on my webpage at:  photos

QUAD ETM DESIGN and DESIGN WORK

Janeen (with some support from me) have been looking at the resonances for the tablecloth, more to follow.

I have been looking at, with Mike Perreur-Lloyd, extending the use of drum-ended wires to the upper intermediate and penultimate stages in the suspension.

Ian Wilmut and I have been looking at the blade data and have now selected blades and associated clamps for the controls prototype.

WORKSHOPS

Valley Precision, a local machine shop, delivered a set of fixtures that will be used to aid in the assembly of the cantilever blades in their suspended stages.

CES has now finished all of the suspended parts, we received the penultimate reaction mass this week, and will now move on to making us 2 upper structures. One for the controls prototype and the other for coupled tests at Stanford.

The Physics shop are working on the housing for the drum ended wires, clamp wire clamp assembly jigs and the top stage that interfaces between the suspension and the structure. This will all be competed in time for next weeks visitors.

UPCOMING VISITS

Tim Hayler and Ian Wilmut are visiting next week from Rutherford Appleton Laboratory.

LIGO MOVIE

Oddvar, Janeen, Ken Mason and I are working on preparing files from both initial and advanced LIGO for Tom Lucas who is making the LIGO movie. As part of this we should get some very useful free renderings.

From: Ken mailand <kmailand@ligo.caltech.edu>

Adv. LIGO

I'm currently learning solidworks, and working on the lower suspension installation arm to move the lower suspension into the BSC chamber. I’m doing a more detailed design of the arms, and pivot pin bearing housing. The first algor stress analysis indicates no problem stresses or deflection issues on the preliminary design.

Also I have finished designing a platform for the modules for the BSC chamber, one assembly is in process at the CIT shop, and should be finished by Friday.

I sent 3D views of the 10x10x3 capacitive position sensor chassis to people at LHO, and Oddvar at LLO for comment on the clearance to the top flange that John Worden was concerned about.

The preliminary cost estimate for this bake oven/cleaning station is ~$45,000 +shipping.  I will try to get two other vendor quotes for comparison.

Core Optics

From: Helena Armandula <ahelena@ligo.caltech.edu>

Advanced LIGO Coatings

Developing and characterizing a new mirror cleaning process.

Advanced LIGO SUS

Assembling magnets, holders and flags by cold indium welding. Testing and modifying process.

From: Bill Kells <kells@ligo.caltech.edu>  

MOstly ill this period, but we are anticipating a meeting on the AdL beamsplitter geometry next week, so I am working on considerations for that. So far I am working through the scaling of what diffractive scatter loss might be considered acceptable from naïve scaling from LIGO I (where the amount we do have is presumably now known to be acceptable).

Pre-Stabilized Laser

From: Peter King pking@ligo.caltech.edu

The high power photodetector is still going strong after about a month now.  No noticeable damage so far, although the unit is warm.

A board for the next revision of this design was laid out.

Auxiliary Optics

From: Michael Smith <smith@ligo.caltech.edu>

No report this week.

Other Laboratory R&D

From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>

Marco

Mesa Beam Cavity blades were cooked at 480oC with the fixed oven. The previously tested maraging samples, from Janeen stock, non A&D, now are cooking at 435oC. The hardening process studies and maraging treatments should be finished before the LSC meeting.

Creep experiment: we are taking measurements at 40oC. Observed a “fall” of 0.18 mm for the equilibrium point, probably due to the mechanical set up of the experiment

Debugging piezo driver circuits.

Lab cleared of asbestos, but still to be rehabilitated.

Juri

I found a problem in my simulation routine: the automatic length control intended to achieve the resonance condition in the cavity wasn’t working as expected (my results of the previous week were not correct…). I fixed this problem and now it is working well, I am debugging further and making more investigations before going to the 2D mirror case and especially to Mexican Hat mirror shape.

Justin

Measuring modes in the Q setup.


For additional information about this report, contact S. Whitcomb or P. Lindquist