Weekly Report for Week Ending February 17, 2005


 Exec. Comm. Agenda

Highlights

LSC

Administration

Hanford Observatory

Livingston Observatory

MIT

Caltech

Detector

40 Meter

TNI

LASTI

Data Analysis

Adv. LIGO Development

Past Weekly Reports


The LIGO Executive Committee meeting for February 21, 2005 is cancelled because of the Holiday.


Special Announcements:


Weekly Report Highlights:


LSC Issues (Saulson)


No report.


LIGO Laboratory Administration (Lindquist)


LIGO Laboratory Administration (Lindquist)

STATUS OF LSC MOUs (Petrac)

LSC MOUs and Research Plans and Progress Reports

For a web page summary showing the status of LSC MOUs and associated Attachment updates through August 15th and Progress Reports through February 12th see:

http://www.ligo.caltech.edu/~irena/Revstatus/Reviewstat.doc

Non-LSC MOUs

  • No report.

SITE TELECONFERENCE (Lindquist)

A site teleconference was held on Thursday, February 17, 2005. The following items were among those discussed:

·         Assigned Action Items: The action to establish a PMA account to be used for Web Site reservations for the LSC Meeting has been accomplished.  There seem to be learning curve issues related to getting the site up for people to begin registering for the March LSC meeting.  The current estimate is tomorrow (Friday, February 18, 2005).  E. Jasnow will monitor the situation with Livingston and with the Webmeister here at Caltech.

·         Conference Calling: Didn't work this week.  The numbers had expired.

·         P-Card Training:  P-card training for Livingston personnel is now scheduled for March 9th.

·         Livingston Electrical Maintenance Contract:  M. Zucker has read the draft RFQ and will return a couple of minor edits.

·         Replacement of Air Conditioning at Caltech:  Musical offices is in progress in Bridge at Caltech because of construction (replacement of the air conditioning system) and hazardous material remediation activities.  Everyone is asked to be patient if communications are occasionally disrupted.  The SCR will be used again next week for the site teleconference instead of the ECR.

·         Personnel Issues:  There was an editorial in the New York Times.  Apparently there has been a massive amount of pressure applied to the State Department from the scientific community to speed up the processing of VISAs.  New rules will make clearances valid for four years for students and for two years for working scientists.  E. Jasnow accepted an action (#130) to check with the International Scholars Office at Caltech to ascertain how this may affect students and scientists who are already here.

·         The list of assigned actions updated through February 17, 2005 will be found Here.

PROPERTY MANAGEMENT (Chargois)

>Ed Chargois <chargois_e@ligo.caltech.edu>

  • No report.

DOCUMENT CONTROL CENTER (Turner, Mak)

>Linda Turner - turner@ligo.caltech.edu>

  • Continued work on the processing and posting of remaining MOU's. Out of about 75 remaining, another 20+ have been handled. Continued to learn the process of web posting by adding new groups to the LSC that had not yet been part of the web postings.
  • Participated in the ongoing meetings of the DCC Steering Committee.
  • Received over 150 travel files from Irene.  All were numbered and added to the database.

>Cleveland Mak <mak_c@ligo.caltech.edu>

  • Processed MOU's.  A lot of time was spent on relocating office, mailroom, fax machine, etc...due to the HVAC project in the basement.

WE 2/17/2005

In

Out

Packages

22

4

Faxes

54

19

 

COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman, Salone)

>Esther Cunningham <esther@ligo.caltech.edu>

>"Brambila, Ruth" <Ruth.Brambila@caltech.edu>

  • Working on two change orders for Triad, and the change orders to LSU and U.S. DOE.
  • Closed out the blanket purchase order to AT & T (PO#1018727).
  • Assisted with goods being imported from our overseas supplier which is being held in Customs.
  • Completed change order #15 to US DOE and submitted the change to the vendor.

>Gina Salone <gsalone@ligo.caltech.edu>

  • No report.

>Florence Kaufman <fkaufman>

  • Attended a meeting to discuss accounting and tracking issues for Advanced LIGO phase.  Sent out samples of reports directly exportable from Oracle Discoverer so that the Project Controls personnel can look into how these reports can be used to extract information required for tracking performance in the construction phase of Advanced LIGO.
  • Working with Dot and Ruth about closing or transferring minor open encumbrance balances in the EPI accounts so that the fabrication accounts can be closed.
  • Prepared a Cost Transfer to transfer expenditure from LIGO.VINT to LIGO.LFNS account.
  • Financial reports can be found at: http://docuserv.ligo.caltech.edu/~fireport. (For passwords contact Florence)

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

>Irena@ligo.caltech.edu (Irena Petrac)

  • No report.

>Ed Jasnow <jasnow@ligo.caltech.edu>

  • The final draft of the RFQ for the electrical maintenance contract for LLO has been sent to Mike Zucker for review.  The RFQ is scheduled to be released next week.
  • The Caltech International Scholars Services Office is researching the question of whether the new extended validity of security clearances for foreign students and scientists applies to those individuals who are already here and have gone through the security clearance process already.
  • The amendment to the LSU/NSF lease to cover the building of the Science Education Center has not yet been signed due to the illness of the NSF lawyer assigned to review it.  Another lawyer has now been assigned, and signature is expected shortly.
  • Dennis Coyne, Peterre Shawhan, and Ed Jasnow will be testing a new teleconference carrier, CorporateConferenceCalls.com for the next month.  This carrier charges 5.9 cents per minute as opposed to 16 cents per minute from Raindance.  The results of this trial will be reviewed after one month.

SUPPORT (Baldon,  Lloyd)

>Irene Baldon

  • Processed the paper work for nine (9) new/revised trips.  There are three (3) trips to be completed and ticketed at this time.  Assisted several LIGO personnel with their travel arrangements using their P-Cards and made several reservations for outside visitors coming to LIGO/Caltech for meetings and/or workshops.
  • Completed eleven (11) Expense Reports and there are thirty-one (31) reports yet to be done.  I continue to contact travelers who have outstanding Expense Reports (more than one (1) month old) to ask for their cooperation in sending me their receipts so that these can be closed in a timely manner.  Presently there are two (2) reports more than 30 days old.  Travel Audit's new policy of accepting only original signatures seriously holds up the process of closing reports.
  • Reconciled thirty-eight (38) P-Card charges for the week which required telephoning hotels and car rental agencies to verify which traveler used my card for what amount.  There were a total of seventy-eight (78) items for the month ending February 15, 2005.

>Dorothy Lloyd

  • Processed the usual invoices for payment. Tracked and followed up on invoice problems. Reviewed and recorded payments processed by Esther the week of February 7.
  • Processed requisitions for standard purchases, payment requests and change orders. For more detail see Cost Schedule Control Systems report by Ruth Brambilla.
  • Jim continued with data entry in the LIGO database and helping out in the DCC.

PROPOSALS and REPORTS (Lindquist)

Nothing to report.

DCC Steering Committee (Lindquist)

The DCC Steering Committee met February 16, 2005.  Discussion continued on the requirements matrix currently under development.  The next meeting of the DCC steering committee is scheduled for Tuesday, February 22, 2005.  The location has been moved to the SCR while installation of the new air conditioning is in progress.

CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)

  • No new or open change requests.

>Cindy Akutagawa <cindy@ligo.caltech.edu>

  • A staffing meeting was held February 14, 2005.

Quality/Safety (Tyler)

>From: Bill Tyler <tyler@ligo.caltech.edu>

No report.


LIGO Hanford Observatory (LHO) and Interferometer Operations (Raab)



Summary of Commissioning Activities at LIGO Hanford Observatory (L. Matone)

This was a difficult week for H1, both in robustness and sensitivity. For the past couple of days, locking has been difficult -- investigations are in progress.

4km IFO

  • An updated noise budget can be found here.
  • Thermal Lensing
    • a series of g-factor measurements have been begun to pin-point the TMs involved in the 1064 laser induced thermal lensing (see this elog);
    • spot size measurements (baseline and preparation);
  • Thermal Compensation System:
    • questionable mount was replaced in the Xarm (elog) and the Yarm (elog) -- preliminary results show a reduction of both the bursty ~250Hz and 1s periodicity events;
    • problems with the TCS servo were encountered and addressed (see elog and elog);
    • the electrical noise floor for the TCS photodiodes (PD1 and PD2) was reduced (see elog ).
  • Calibration
    • the photon calibrator installed (elog);
    • DC calibrations in preparation for S4.
  • Noise issues
    • light onto ASPDs found misaligned: 
      • realignment method using injected acoustic peak increased Inspiral Range (see elog);

2km IFO

  • 60Hz reduced to pre-E12 level (elog);
  • Tuning of the optical lever servo notches started (elog);

DAQ

  • The DAQ has been reconfigured to add to the frames the heterodyned AS_Q channels (for both H1 and H2) at the free spectral range (elog).

LHO Outreach

  • LHO hosted Washington State Congressman Richard (Doc) Hastings and one of his staff members,  Joyce Olson,  for a visit on 2/4/05.  Topics of discussion included current interferometer performance, LIGO outreach programs and plans for Advanced LIGO.

LIGO Livingston Observatory (LLO) and Interferometer Operations (Zucker et al)


L1 Commissioning (Valera Frolov)

 

Interferometer stability improved significantly after additional sources of optical backscattering were identified and eliminated. The largest offender was the beam clipping on the optics on the X-arm transmitted light optical bench. During the last three days we had several long lock stretches with one lock lasting thirteen hours. The inspiral range during the long locks was around 6.5 Mpc and peak-to-peak variations of several percent on an hour time scale. The best inspiral range is now close to 7 Mpc.

 

The summary of commissioning activities this week:

 

·        mystery noise that appeared in the AS PD dark noise was removed by adding ferrite chokes on the cable going to the AS_I servo/test input. The dark noise was further improved by attenuating the RF drive of the AS_I servo.

·        dtt code was updated to allow fast DAQ data to be viewed in the control room. The up to date versions of SUN C and C++ compiler, and ROOT were installed on CDS machines.

·        WFS servos were retuned for more robust performance.

·        the UGF of the tidal was extended to 0.1Hz to suppress the HEPI gain peaking.

·        grounding of the electronics racks in the corner station was reworked.  Now all the racks are attached to a big lead by a short wire instead of being daisy-chained.

·        X end station seismic noise at 11Hz was identified to come from VEA HVAC air fans. The noise from 11Hz duct resonance was removed by changing the fan pitch.

·        frequency noise contribution to the ifo output was re-measured. It was found that the ifo noise improves with more light on the reflected port PD, but we are currently limited by saturations from the signal in the orthogonal phase.

·        accelerometers and magnetometer were re-connected. The 1 Hz sideband structure on 60Hz line from the end station heater still shows up on the end station magnetometers.

·        interferometer DC calibration was re-done and new LSC model was produced. The transfer functions of the anti-imaging boards at the end station were re-measured.

·        interferometer contrast defect was re-measured. The result is 10 times larger than was obtained in the last measurement a year ago.  Another independent measurement of the carrier to the sideband ratio gave a factor of 5 discrepancy with the old contrast defect number.

 

Education and Outreach (Thacker)

 

Sent out email LEPAC invitations for May meeting.

 

Prepared for two outreach visits 2/18:

  • HS Physics class (60 students);
  • Parish Librarians (25 people)

 

Attended LA GEAR UP Teacher Professional Development RFP review on 2/14

 

Safety and Security (MZ for Riesen)

 

Rich is at Rockwell in Cincinnati for an LSO training course this week.

Tom reports no safety issues worth noting, but does not enjoy carrying the cell phone.

 

Site Administration (B. Wooley)

 

·        Preparation for the March LSC Meeting in full swing.

·        Attended Dreamweaver training to support LLO web re-work.

 

L1 and AdL Mechanical Engineering (Spjeld)

 

AdL Quad SUS Installation Fixtures

  • Preliminary FEA on joint support beam completed & reviewed.
  • Redesign in progress; pneumatic lifting idea scrapped, trying to incorporate existing CAS linear lift (modified) instead.
  • Plan to utilize air bearing with translation step for fine alignment.

 

AdL SEI Engineering Effort

  • Mass and C.G. estimates for stage zero sub-system performed.
  • AdL ISI web-page completed; link given to Joe Giaime for posting.
  • Technical notes document from ASI meeting completed.
  • Status overview of manufacturing parts & drawings completed.
  • Will be posting updated AdL SEI models on PDMWorks vault at the end of February.

 

LLO Engineering

  • Redesigned GS13 sensor platforms for HAM crossbeam in production.
  • Redesign of new HAM door removal fixture in progress.

 

HEPI Valve Calibration

  • Calibration of new servo valves in progress.
  • Updated valve status page on HEPI web-site.

 

Upcoming Tasks

  • Look into shutter problem (decision made to wait till after S4).
  • Analyze replaced servo valves.

 

LLO General Computing and LIGO CyberSecurity (Roddy)

 

·        The new router locked up a couple days ago.  Tom had to power cycle and reboot it.  There was no indication of the reason for the lockup in logs, etc.  Might be nice to have a device to power cycle the router remotely.  Looking into this...

·        Still working with LSU on the bandwidth bottleneck.  It is somewhat of a mystery.  We have eliminated our bottleneck, now it is a matter of finding out where the remaining bottlenecks are.  My suspicions differ with LSU's.  It is not looking hopeful for S4 data transfers.

·        fixed (I think) a VPN issue with our firewall.  I still need to confirm that there are no other issues, but I believe that I found the bug.

·        Still working on putting together a new web server.

·        Working with the local Sun rep on covering our Suns whose warranties have expired.

·        Trying to track down a server that the shipping company lost.  Dell will replace it if the server cannot be found.  However, I am still behind since I have been delayed at least 3 weeks on receiving the server.

·        putting together an order for apple.  Two laptops and possibly a couple other machines.

·        working on some documentation and scheduling for security items as a result of the LHO meeting.

 

CDS Software Support (Khan)

 

·        Trying to bring the weather station data online. We have had no success, as we found out that there may be a problem with the cable runs between the EPICS controller and the outside weather station controller.

·        Preparing for S4 the run, including, the RoboScimon and the DMT channel configurations.

·        Writing a Linux device driver for a portable data logging system that may reduce the number of cables in the EPICS DAQ system.

 

High Power Laser Facility, Optics Modeling and L1 Commissioning (Franzen)

 

·        Finally received an update from IPG Photonics regarding the the status and repair of the broken 100 W laser. Unfortunately nothing but really bad news. The IPG engineers found that the fiber blocks and other components within the laser have burned. Furthermore, due to the extent of the damage they claim that it is difficult to determine the exact cause for the failure. The expected repair time is as long as 4-6 weeks, which they will expedite as much as possible.

·        David Reitze asked me to use the latest AdvLIGO mode cleaner Melody model to simulate the present LIGO-I mode cleaner at 0-30 W input power.  The reason for this exercise is to check that the reflected beam profile is consistent with the real data and also to predict how it would appear after an upgrade to 30 W input power after S5. My results so far can be inspected at http://www.ligo-la.caltech.edu/~franzen/melody/LIGO-I_MC.html

·        I used a microscope in order to study the coatings of the RTP crystals which was irradiated by a >85 W, <0.7 mm diameter beam for three weeks. After careful study I claim that no damage is detectable using this somewhat crude method.

 

LDAS/Condor Sysadmin and Burst Analysis (Yakushin)

 

Condor/LDAS admin

 

·        On Friday night tape robot got stuck while I was attending burst f2f meeting at CIT. I called the control room to ask Tom to power cycle the robot. Unfortunately, we misunderstood each other and a wrong button was pressed which resulted in power interruption in the LDAS room. After the power was restored, the system came up OK except that /samrds and /samraw were not mounted on gateway which was noticed and fixed on Monday. To prevent such cases of miscommunication in the future I suggest to have a cordless headset phone in the LDAS room so that it is easy to direct somebody remotely if I am not on site and something urgently needs to be done. Currently there is no phone in LDAS room at all.

·        During recent days tape robot misbehaved several times: it failed to initialized correctly on reboot, a tape got stuck in the hand, etc. It turned out that the robot's hand is worn out and had to be replaced.  After it was done the robot seems to be working OK. I am importing more tapes now in preparation for S4.

·        The file system was reconfigured: /samraw, /samrds, /cluster were merged into /archive (Dan).

·        For more convenient access to the archived data in the control room, ldas:/archive is NFS mounted on CDS machines river and london (there was a complaint that it is not that easy to access archived data in the control room). The long term solution for this problem would be to QFS mount /archive on some CDS machine, however, it cannot be implemented before S4.

·        3 disks failed in different T3s during this week.

 

Data analysis

 

·        Debugging and testing waveburst online scripts.

·        Generated several types of MDC frames for the whole S3 but since it was suggested at the burst f2f meeting that we might not have to do a complete burst analysis of S3, this activity is at the moment suspended until the final decision is made about S3 analysis.

·        Attended burst f2f meeting at CIT.

 


INITIAL LIGO DETECTOR SCIENCE & ENGINEERING (Coyne)


CDS

see also the CDS weekly meeting minutes in the commissioning archives:

CDS Software

no report

CDS Hardware

Jay Heefner reporting

Fiber Optic Timing Link (Sander)

  • The second set of electronics is almost complete.
  • 8 of the first 10 receivers are operational. 10 more receiver boards have been ordered.
  • Testing on the 40M will begin tomorrow.

LSC PD (Ben)

  • Waiting for prioritized list of PDs needed by sites.
  • Rana has requested 2 ea 24.5MHz PDs for LLO.

ISS (Flavio)

  • Completing the documentation
  • Finishing up testing of the additional boards.

LLO Mid Station Vacuum (Jay)

  • Building IOC for application.

Electrionics Shop (Todd)

  • Building timing link components.
  • Need to build more Rev B coil driver for the 40M.

DMT

no report

PSL

PeterKing

The transfer function of the NPRO power actuator was measured down to low frequencies (0.01 Hz) both with the noise eater on and off.  A LaserCheck power meter was compared with a Scientech calorimeter for consistency.  The power meter is used for random laser safety inspections.

Thermal Lensing

Bill Kells

I've been working with the COC people to plot the most efficient strategy for measuring/certifying the candidate replacement optics for H1. This puts heavy demands on the CIT facilities. To guide the emphasis of this, I have been also working on several new measurements of the H1 TL effects to better distinguish what optical properties (surface or bulk absorption? surface scatter?) they are due to. Several of these are being pursued and I'm following the data for interpretation.

Optical Contamination Cavities

Lee Cardenas, Liyuan Zhang

OTF Lab. (W. Bridge)   shut down due to the HVAC refurbishment & asbestos abatement

OTF Lab at Lauritsen ROOM 38 
Cavity #3 no change
The contamination test for (6) new disks of VAC SEAL Epoxy samples is in progress. Cavity is locked and we are taking measurements  for absorption and ring down for contamination loss every day.

Cavity #2  in progress
mode matching and optical set up is in progress New 51cm long contamination cavity is being disassembled, changing new mirrors and parts to be cleaned and baked.  We need some more optics (1/4waveplate, polarizer cube etc..) the alignment of the optics for the new 414 npro is underway.


40 Meter Interferometer (Weinstein)


·         This week we had a setback at the bond-noise experiment. Two of the RTV springs in our seismic stack ruptured, and we had to remove the plate, clean up the pieces, and install new springs. Many thanks to Steve Vass for donating extra springs!  IFO commissioning:

o        Rob and Rana tweaked up the filters for the LSC servos. They opened up the BW of all 3 loops (PRC, MICH, & SRC), bringing the UGFs to ~100-150 Hz. The changes seem to speed up the DRMI locking a lot, and seem to help it hold better against the arm resonances. Rana also added violin mode filters on the ETMY controller.

o        Rob and Rana's new auto-alignment script works pretty well. However, in their tests, they moved the BS, which messed up the Y arm completely. Osamu has put the BS P&Y back where it was, and he and Steve have completely realigned the entire interferometer, including all suspended optics, exit beam lines, oplevs, photodiodes.

o        Osamu tweaked the LSC demod phases to optimize the signals. However...

o        The MC length drift produces a phase shift on the transmitted RF sidebands; this wreaks havoc on all the LSC signals if the demod phases are kept fixed. The solution is to monitor the MC length (or equivalently, the RF frequency which is resonant in the MC) and change the RF frequency in response.

o        Osamu has set up a simple monitor, which dithers the MC_ERR signal at 30 kHz and then demods the demodulated MCR RFPD. He reports daily changes of 10 Hz out of 33 MHz (corresponding to ~4 microns in MC length); over months, the drift can be as large as 500 Hz or 200 microns!

o        He then feeds back to the RF signal generator. This works well, except that we need to simultaneously change the 33 MHz, 133, 166, and 199. The phase-locked signal generators can't respond to the feedback signal. We need to replace these additional signal generators with RF circuits that generate phase- and frequency-locked signals at 4x, 5x, and 6x. Osamu and Jay are working on the design of such circuits.

o        If we can servo the RF frequency to keep the transmitted sidebands on resonance, will the IFO servo demod phases stay stable? To determine this, Osamu measured the relationship between the demodulation phase delay on the MICH servo and the mismatch between the MC length and RF modulation frequency. He varied the RF modulation frequency from its perfectly resonant value by 1 Hz, 3Hz, 10Hz, ... 10kHz. His result agrees very well with the expectation assuming a simple MC cavity pole. From this, he accurately measure the MC finesse to be 970 (design is 1200).

o        Osamu found two problems with the optical spectrum analyzer at the SP: the driver was broken and the wrong cable was used. He swapped in the driver for the OSA at the MCT beam line, and replaced the cable. The broken driver will be shipped back to Coherent for repair.

o        Osamu found that the electro optic shutter (EOS) at the SP port varies in transmittance, and he suspects a thermal effect (crystal is heating up?). He plans to disable the EOS and replace it with a manual HWP/PBS (in addition to the mechanical shutter).

o        Virginio continues to optimize the performance of the MC2 optical lever, reducing the couplings between PIT, YAW and POS, in order to improve the diagonalization of the MC2 coil output matrix.

·         IFO modeling and DC detection development:

o        Ben has started testing the thermal handling capabilities of the new in-vac DC photodiode for our homodyne experiment. It has been heated inside a vacuum with 100mW for the past 24 hours, with a temperature increase of only around 4 Kelvin. He will continue the experiment for a few days until temperatures become stable.

o        Mike Smith made a revised layout of the output optics chamber to revise the steering mirrors and beam splitter for the output mode matching telescope, the output mode cleaner, and the in-vacuum DC photo detector.

o        Rob continues to use Finesse to search for more robust CARM and DARM signals for lock acquisition. Previously, we used XARM and YARM to acquire lock, then switched to CARM and DARM smoothly. But with dual recycling, the POX and POY signals are almost degenerate, and the CARM and DARM signals are very narrow and almost useless for lock acquisition.

o        Monica continues to develop her e2e 40m code. She is systematically measuring TFs and error signal sweeps from all degrees of freedom to all sensors.

·         PSL:

o        Ben and Rich will tune up the MINCO temperature to get rid of the large oscillation in the PSL reference cavity temperature. We are seeing the effect of this variation in the RF phase of the MC transmitted light.

·         Electronics and computing:

o        Ben has implemented all the new Rev.B coil driver functionality: changed all of the auxiliary databases; reworked an EPICS screens to employ the new coil offsets for all the core optics, and made the cables to connect the new 4116 cross connects to their modules when they are put in place. The revB coil drivers for ETMX and ETMY are in place and working. He will put in the ITMX and ITMY coil drivers in the next few days, and then the BS, PRM and SRM ones when they come in from the shop. We need to scrounge around for the required 4116s and re-arrange the crates to find room for them.

o        Rolf has completed the ASC code for the 40m, and Jay is ~90% done with testing it. Should be able to install next week.

o        Still no solution to the problem of glitches from the ISC110b ADC's reading out the suspension OSEMs. Jay and Ben are looking for similar glitches in the ICS110b's reading out the IO and PEM data. Rolf has a potential solution that was implemented in HEPI, but it probably would be a big effort to get it going at the 40m; so it's on the back burner.

o        Rana changed the fonts used in the MEDM screens. You can now read the numbers clearly! And the snapshots are easier to read, too.

o        We await some of Alex Ivanov's time to set up a new Linux disk server, network firewall, and fremebuilder. We hope that when S4 starts, he will become available.

·         Lab Infrastructure:

o        Virginio and Steve have written a first draft documenting the measurements, tuning up and resultant performance of the STACIS system.

o        Dan and Monica continue to survey all of our in-air optical beam lines, to document the as-built system and update the comprehensive optical layout AutoCad drawing maintained by Mike Smith.

o        Electricians are installing a new circuit and many new wall plugs in the 40m-control room. There is a circuit dedicated to our key control computers, which will also have a UPS backup system.

·         Bake oven Lab:

o        Bob is setting up for bake jobs for Dennis Coyne and for Janeen.

o        Bob continues to work with Calum, taking blade spring data.


Thermal Noise Interferometer (Libbrecht)


This week we had a setback at the bond-noise experiment. Two of the RTV springs in our seismic stack ruptured, and we had to remove the plate, clean up the pieces, and install new springs. Many thanks to Steve Vass for donating extra springs! The stack is now restored and back in operation.

 

Also, Akira has put together a frame and pulley system with counterweights for hoisting the glass bell jar in that experiment.

 

Jay continues to configure our new PC with Fedora 3 for epics control. Installation of Linux on that machine did not proceed smoothly at first, apparently due to a faulty CD-ROM drive. Jay replaced the drive and was able to install the operating system.

 


LASTI (Ottaway)


No report.


Data Analysis and Computing (Lazzarini)


Simulation and Modeling (Bhawal)

E2E Weekly Meeting

Mark Barton described his work on mechanical simulation for the Advanced LIGO that he started. Sany Yoshida and Dominic Dubois of Southern Louisianna University presented their work on simulation of the Input optics.

FFT runs

(Hiro) Various code modifications and runs have been done and will be done for the thermal effect study and the quantification of the effect of the mirror surface phase map. Physics results will be summarized next week.

Shift in Beam Centre

(Biplab) Using SimLIGO and a set-up for output optics that reduces the beam width to ~1 mm radius, studied how the motion of mirrors could induce the beam shift at a photodetector or a phasecamera. The estimate is : the beam could shift by about 3% of its width at the detector.

 

Related to this study: The large beamshifts (of the order of the beam width) observed in fitting data of phase camera images taken under same thermal states seem to be originating from correlation between beam  offsets and order 1 modal components, which creates degeneracy in fitted parameters.

Mechanical Simulation for Advanced LIGO

(Mark Barton) The e2e simulation of the AdvLIGO triple pendulum that I reported last week was quite slow to run, so I spent some time hacking at the Mathematica to improve it. The issue was that there was a high-frequency eigenmode of each blade-tip that required a very fine time-step to resolve. (This was after previously eliminating five other even higher frequency eigenmodes for each blade.) To fix this requires that the blade tip be eliminated from the model as a mass, but simply setting its mass to zero doesn't work because the eigenfrequency goes to infinity rather than disappearing. The coordinates of the blade-wire junction have to be considered for the purposes of analysing how the blade and wire behave as ideal elastic elements in series but must be suppressed from the normal mode analysis. This required some structural changes and new features in the modeling toolkit. It all seems to be working OK, and so a new v1.6 toolkit, a new "xtralite" triple model and an updated manual T020205-01 will be released in the next day or so.

Simulation of 40m interferometer

(Monica) New e2e simulations and comparison between e2e and Twiddle results: up to now the Differential Arm mode signals at 166 MHz and 33 MHz, the CARM signal at 33 Mhz match very well. Other signals at different frequencies will be compared soon. In the meanwhile, as crosscheck, I will try to simulate those outputs also with Finesse and with my analytical calculations.

Modeler code updates

(Hiro) Mark Barton started to build mechanical part of adv.LIGO simulation. He uses State Space code in e2e. The matrix is large, 45x45,

 and it runs pretty slow. Optimization of RungeKutta code is being attempted.

 

A new release, together with an updated manual, is scheduled soon. (The date got delayed because unexpected bugs surfaced.)

Alfi

(Bruce) - Completing Alfi documentation update.

  • Working on port reposition issues with the new JGo library release.

 

(Melody)  Performing regression testing using the new JGo library.

  • Notified Bruce of any problems found in the code. Creating a test document on how to reproduce the code exceptions. We anticipate distributing a new ALFI release soon with the new JGo library.

Data Analysis Activities (Lazzarini)

Chatterji:

  • Comparing Q Pipeline S2 H1-H2 double coincidence burst search results with 1997-2000 IGEC and the 2001 Explorer/Nautilus results.

Dupuis:

I spent some time installing LAL/LALApps and various applications I use  (like Supermongo:) on my new Apple laptop.  Then I checked some recent changes that Curt Cutler has made to LALBarycenter by comparing it to TEMPO.   By calculating the Einstein delay at the site as opposed to the center of the Earth, the agreement between the two codes has improved by 1-2 microsecs (~rejean/tempo_test).  I began preparing to write a methods paper for the pulsar search.

 

Mandic:

  • I worked on formulating ways of extracting information from time-shifted analysis in the stochastic search.
  • I also worked on the remaining details regarding hardware injections, which should be sorted out before S4.

 

Mendell:

The first version of the StackSlide binary search code (e.g., which will be used to search for GWs from Sco-X1, other LMXBs, and other neutron stars in binary systems) has been checked into LALapps by  Virginia Re.  Virginia is a postdoc visiting LHO from Birmingham.  She returns to the UK on Feb 20.  The code currently works for certain test cases. Virginia will be working on adding more routines to handle Monte Carlo software injections to map out the parameter space metric, so that the code can perform a real search in the near future.  Both she and I will be adding code in the next year to also StackSlide the F-statistic as part of a hierarchical search for continuous gravitational waves from isolated neutron stars and as well as those in binary systems.

 

Shawhan:

 

  • Hosted a face-to-face meeting of the LSC Burst Analysis Group on Friday and Saturday.  Topics included the S2 papers, the S3 untriggered searches, and plans for S4 analysis.
  • Following discussions within the Data Analysis Software Working Group, proposed a change to the interferometer state vector logic to make the treatment of data with burst and inspiral injections nearly the same as regular science-mode data and to minimize boundary effects when switching back and forth between the two states.
  • Belatedly created explicit E12 UDNs for DTT.  Also set up cron jobs to update S4 UDNs hourly once S4 begins.

 

Weinstein

  • Attended Burst F2F
  • Review telecom for LIGO-TAMA joint inspiral analysis

 

Yakushin:

  • Debugging and testing wave burst online scripts.
  • Generated several types of MDC frames for the whole S3 but since it was suggested at the burst f2f meeting that we might not have to do a complete burst analysis of S3, this activity is at the moment suspended until the final decision is made about S3 analysis.
  • Attended burst f2f meeting at CIT.

LIGO Data Analysis System

Software Systems (Blackburn)

LDAS

This week was focused on getting out a new release of LDAS for the S4 Science Run. This was needed to resolve a bug in the createRDS pipeline command discovered in the E12 Engineering Run. All system tests of the 1.5.0 release have passed.

 

A prerelease of the 1.5.0 release for the S4 run was installed at LHO on Monday to allow Greg Mendell to test against his createRDS driver script. Greg performed two days of testing and reran the E12 segments of data that had identified the bug. No problems were identified with the two-day run and all prior issues in LDAS and the createRDS script were shown to be fixed.

 

The LLO system was shutdown this week for hardware repairs and configuration issue. When the hardware was back online, we decided to install the prerelease of 1.5.0 there as well to provide more time for testing and evaluation. Only a documentation issue in the FAQ for the release was found to be in need of attention and now fixed in the official release.

 

The official release will be installed at LHO, LLO and CIT on Friday of this week. MIT is undergoing hardware maintenance and will not be upgraded to the official release until next week. LDAS-DEV and LDAS-TEST already have the official release running on them as of today.

 

S4 specific databases were generated at LHO and LLO on Wednesday of this week. They will be generated on CIT on Friday and MIT when it is available for upgrading to the new LDAS. The new S4 database will be made the default as each system is restarted with the 1.5.0 release.

 

The tandem systems are once again available to us after several months of waiting. We will begin upgrading these to LDAS 1.5.0 today.

 

TCLGLOBUS

Testing failed when using MyProxy delegated proxy certificate with the following error message:   globus_xio_gsi: gss_acquire_cred failed.   meaning there is no valid proxy certificate. We're still looking at the cause of the problem.

 

Fixed globus_io_read() and globus_io_register_read() issue on how to handle end-of-file flag at the SWIG layer.

 

Fixed globus_io_tcp_register_connect() issue on how to pass handle reference back at the Tcl layer.

 

Completed 2 Tcl scripts (asynchronous file copy and client/server) to exercise asynchronous functionalities of Globus I/O.

 

Two out of 96 SWIG-wrapped Globus I/O functions are still buggy. The functions are:

   globus_io_register_select()

   globus_io_secure_authorization_data_get_callback()

 

OSG

Naveen Palavalli is attending the OSG Integration Working Meeting in Chicago this week. The meeting intends to bring up the OSG Testbed at the 16 sites participating; LIGO Caltech is one of these sites. The LIGO-CIT-OSG site is now showing green afte a long week of preparation and installing software and properly configuring our OSG system from Chicago and here at home. The week got off to a slow start do to last minute availability of the hardware to be used for our OSG testbed. The hardware wasn't working at the time of Naveen's departure and a quick response by several members of the local LDAS software team got the system ready literally just in time for Naveens hands on training. The system currently has a gatekeeper and 3 nodes available.  Remaining work includes installing condor and syncronizing the worker nodes with the gatekeeper. We officially passed the site verification tests performed by the OSG integration team.

Hardware Systems (Anderson)

Caltech

 

(Dan Kozak)

  • Help rebuilding /archive file system at LLO.
  • Changed PFN's in LDR at LLO to reflect new /archive file system.

 

(Phil Ehrens)

  • Supported LDAS developers with a number of small tasks related to imminent release of LDAS.
  • Handled bulk RMA of 18 disk drives with Maxtor.
  • Investigated creation of conforming .rpm files for support of Fedora Core 3 based systems.

 

(Al Wilson)

  • Installed replacement memory into dev and test failed cluster nodes.
  • Took another golden image of the CIT system.

 

(Stuart Anderson)

  • Declared success on a Linux kernel patch to prevent a few crashes per day in the CIT cluster.
  • Getting ready for S4.

 

MIT

 

(Keith Bayer)

  • Upgrading cluster and intel boxes to FC3.
  • Updating passwords for boxes (along the way).
  • Building cluster image from scratch due to different architecture for MIT cluster.
  • Configuring systemimager.

 

Livingston

 

(Igor Yakushin)

  • On Friday night tape robot got stuck while I was attending burst f2f meeting at CIT. I called the control room to ask Tom to power cycle the robot. Unfortunately, we misunderstood each other and a wrong button was pressed which resulted in power interruption in the LDAS room.  After the power was restored, the system came up OK except that  /samrds and /samraw were not mounted on gateway which was noticed and fixed on Monday. To prevent such cases of miscommunication in the future I suggest having a cordless headset phone in the LDAS room so that it is easy to direct somebody remotely if I am not on site and something urgently needs to be done. Currently there is no phone in LDAS room at all.
  • During recent days tape robot misbehaved several times: it failed to initialize correctly on reboot, a tape got stuck in the hand, etc.  It turned out that the robot's hand is worn out and had to be replaced.  After it was done the robot seems to be working OK.  I am importing more tapes now in preparation for S4.
  • The file system was reconfigured: /samraw, /samrds, /cluster were merged into /archive (Dan).
  • For more convenient access to the archived data in the control room, ldas:/archive is NFS mounted on CDS machines river and london  (there was a complaint that it is not that easy to access archived data in the control room). The long-term solution for this problem would be to QFS mount /archive on some CDS machine, however, it cannot be implemented before S4.
  • 3 disks failed in different T3s during this week.

 

Hanford

 

(Greg Mendell)

  • RDS generation is ready for S4. Bugs that caused 4 createRDS jobs to fail during E12 (out of over 4000) have been fixed in LDAS 1.5.0 and in the scripts createrdsGUI.tcl v1.49 and createrds.tcl v1.13 (the scripts are available from CVS/Root=:pserver:USERNAME@gravity.phys.uwm.edu:2402/usr/local/cvs/lscsoft,   CVS/Repository=dsorun/contrib/createrds/scripts). Small gaps in the E12 Level 3 RDS frames due to these bugs have been filled in at LHO. A ~48 hr test, including simulations of the situation that triggered the bugs, has been run with no errors at LHO. Only the channel lists remain to be finalized before S4 begins.

 

(Ben Johnson)

  • L700 hand started losing its grip on tapes occasionally again (Feb. 11 2005). Wiping off the three rubber pads alleviated the problem.
  • Restarted syslogd on gateway. It apparently could not be restarted (part of a root cronjob) due to too many processes (too many ftp procs).
  • Copied and published E12 L1 LHO data to the cluster at LHO. Myungkee Sung requested this.
  • Continuing work on publishing script. As of Feb. 17 2005, I have gotten it to put data into the new LDR instance. I still need to de-hack it so that it more easily ported to the different sites.

General Computing (C. Barker for Wallace)

MIT:

(Keith)

 

  • Still dealing with R14 matlab...
  • Sent loaner laptop back to Caltech
  • Helping with user desktop issues
  • Upgraded GC sun desktop for new urop(s)
  • Added several GC machines to tripwire cron

Livingston:

(Shannon)

 

  • The new router locked up a couple days ago.  Tom had to power cycle and reboot it.  There was no indication of the reason for the lockup in logs, etc.  Might be nice to have a device to power cycle the router remotely.  Looking into this...
  • Still working with LSU on the bandwidth bottleneck.  It is somewhat of a mystery.  We have eliminated our bottleneck, now it is a matter of finding out where the remaining bottlenecks are.  My suspicions differ with LSU's.  It is not looking hopeful for S4 data transfers.
  • Fixed (I think) a VPN issue with our firewall.  I still need to confirm that there are no other issues, but I believe that I found the bug.
  • Still working on putting together a new web server.
  • Working with the local Sun rep on covering our Suns whose warranties have expired.
  • Trying to track down a server that the shipping company lost.  Dell will replace it if the server cannot be found.  However, I am still behind since I have been delayed at least 3 weeks on receiving the server.
  • Putting together an order for apple.  Two laptops and possibly a couple other machines.
  • Working on some documentation and scheduling for security items as a result of the LHO meeting.

Hanford:

(Christine)

 

  • Network usage can be seen athttp://www.ligo-wa.caltech.edu/~christin/mrtg/ 198.129.208.1_198.129.78.122.html
  • Still updating all Sun workstations to the latest open SSH.
  • Installed Norton Antivirus 9.0 on the guest PCs and loaner laptops. Advised all users to install on their PCs.  Made sure all users have updated to the latest virus definition files.
  • Spoke with PocketiNet, another local ISP, to get more information and prices on network connections.  PocketiNet does the local wireless broadband networking.  Also started looking into resurrecting our old ISDN line as a possible backup network.  Richard is again talking to the phone company, this time about the possibility of a DSL line.
  • Misc. user support for printer problems and new user accounts.

CIT:

(Mike)

 

  • Continuing to work on moving users from Bridge Annex to 2nd and 3rd floors of W/B.
  • Shourov Chatterji: Loading a new laptop with GC software and making this a dual boot to LINUX.
  • NTSRV's: Updated security and critical updates on Pictor, Antares, and Pherkab.
  • Jay Heefner: Working on transferring his data to a new hard disk. I have to ghost this drive and then dump to new drive and repartition this drive to make it dual bootable.
  • Moved the fax machine over to East Bridge and ran test to insure that everything is working. Cleveland gave me a hand with this.
  • Worked the Spam filters.
  • Recycling backup tapes.

 

(Veronica)

 

  • LSC:  Updates to the observational results pages.  Working on the website for the March meeting.  Updated contact information for the LA Tech MOU page.  Working with authorizenet.com on setting up an SSL interface for online payments.
  • LIGO:  Website updates (Visitors, conferences checklist, homepage).  Tracked a high-resolution image for Dave Beckett.  Prepared a high-resolution image for a publisher.  Security updates and audits of the Win servers and machines.  Miscellaneous user support.
  • CaJAGWR:  User support.

Advanced LIGO and Supporting R&D (Shoemaker)


Systems and Management

Adv. LIGO Systems

from Dennis Coyne

See also: AL Systems web page, AL Systems email archives

 

Planning

  • Worked on installation sequence and schedule planning. Discussions between Carol Wilkinson, Dwight Carter, Thomas Frey and Dennis Coyne to revise Primavera schedule.
  • Have done a first step labor resource allocation for each subsystem by phase as part of a scrub of the AL project costs.

 

Records Of Decision or Agreement (RODA)

See also the RODA status web page

  • no new RODAs

 

Requirements

  • nothing new.

 

Interface Issues

See the "Interfaces" section of the AL Systems web page

  • Continuing coupled SEI/Quad dynamics analysis in modal basis -- a report is being prepared. Have also started to integrate a more up-to-date SUS structure model.

Reviews and special meetings

  • Nothing new to report.

 

From: "Thomas Frey" tfrey@ligo.caltech.edu

 

Progress Period from 01.28 to 02.18

 

Out of the office on 01.24,26,26,02.08, 09, and 10

·         See http://www.ligo.caltech.edu/~tfrey/index.html for a complete listing of all project related cost and schedule data.

Accomplishments:

·         Sub-system PLANNING activities

§         Continued work on preparing web space for posting Adv. LIGO reports. ("The Whole Enchilada")

§         Continued work on the 40-Meter schedule changes.

§         Executed telecoms with Carol.

§         Finished work on AOS schedule changes.

§         Executed several meetings / telecoms regarding schedule and cost estimate topics.

§         Finished preparing the progress update with progress through 01.31.05 and posted data to web.

§         Started work preparing progress data requests for progress period ending 03.31.05.

 

·         ROSTER DATABASE:

§         Assisting Irena as needed on record changes.

§         Continue to assist Irena with setting up her web site to accommodate review of attachment As.

·         COST BOOK DATABASE:

§         Posted current version of the cost estimate inclusive of AOS and IO changes.

Seismic Isolation

From: Ken Mason <kmason@ligo.mit.edu>
 
Advanced LIGO Seismic Structure

SEI Structure:

86 0f 133 drawings have been completed and released by ASI. They are now posting all drawings to their project web site as they are being released.

ASI has sent to Ed Chargois hardware they purchased under the contract. This consists of nuts, bolts, and the spring calibration fixture.

The buy-off  meeting scheduled for 3/8  at ASI is still on schedule.

Actuators:

LBEC Technicians has finished termination and potting of the 6 Phase II large and small bobbins.

One small actuator has been integrated and tested.  One large actuator has been assembled and mounted to the test stand.  Testing of the large actuator was scheduled to be completed by monday

Integration and testing of the remaining 5 large and small actuators are occurring this week and they will be shipped to us next week.

Suspension

From: Janeen Romie <romie_j@ligo.caltech.edu>

AdLIGO Suspensions
Working with the SUS team on the full quad structure fea. Even with my new computer, Algor is troublesome. Algor support has been helpful and we continue to work this. Working with SUS team on welding issues.

Collecting hardware lists from sus team to purchase nuts, bolts and associated hardware. Tracking all this in PCard software.

Providing LIGO Lab SUS status/accomplishments and future plans to David.

Continuing to meet with Laurent every Tuesday at 8:30. This week we had a webcam at MIT and one on the MC in the Synchrotron to use to compare the suspensions. The webcams proved very useful.

Supporting Oddvar and Ken Mailand on their installation fixture designs.

Preparing for and meeting with Carol on SUS budgets and schedules.

Initial LIGO
Working with Doug, Betsy, Gari and Helena on the possibility of changing out a suspension at LHO. Met with Phil Willems this morning about possibly using an LOS structure prototype for a ring heater test.

Gin Gin
Researching availability of hardware for Stan and David.

From: Ken mailand <kmailand@ligo.caltech.edu>

I'm currently learning solidworks, and working on the lower suspension installation arm to move the lower suspension into the BSC chamber. Also Im designing a platform for the modules for the BSC chamber, to fit either the large or small port tube, and to allow positioning possibilities to clear obstructions that may be near the chamber.

I spoke to Riccardo re. his previous experience with the air bake ovens, for possible configurations and space requirements. This preliminary hardware design showing an oven with a integral wash cleaning platform was sent for quote, the hardware configuration was modified this week. The preliminary cost estimate for this bake oven/cleaning station should be at CIT in a week.

I have requested a ball park baking estimate from NTS based on our visit, not a quote, just an ROM for our budgeting use. We can use this with Astro-Pacs cleaning estimate and other shipping and handling costs estimates to compare with our in house estimate, for this task. I spoke to Michale Mize today and NTS expects to have the ROM finished and to us by 2-23.

Core Optics

From: Bill Kells <kells@ligo.caltech.edu>

Have now been spending focused time on the overview plan for AdL COC (ie the budget plan issue).  A big strategy in this is to learn as much as possible from our LIGO I experience and those interferometers as test beds (eg HR scatter and TL properties) to determine where the most effort is needed in further R&D.

Pre-Stabilized Laser

From: Peter King pking@ligo.caltech.edu

 

AdvLIGO PSL

An exposure test of a different high power photodiode has been underway for just over a week now without any detrimental effects.  Given that the device under test is the same as the one that failed earlier, my conclusion is that the voltage regulator that failed was just a bad regulator and that there is nothing basically wrong with design.  The photodetector under test has no heatsinking and is running at about 375 mA of photocurrent.


A newer version of the boards for the photodetector is being laid out.  This fixes the problems encountered in changing versions of Protel.

Auxiliary Optics

From: Michael Smith <smith@ligo.caltech.edu>

ZEMAX TRAINING COURSE

I attended a 5-day ZEMAX optical design training course: advanced optical design including birefringent media and physical optics propagation.

40 METER
Made a revised layout of the output optics chamber to revise the steering mirrors and beam splitter for the output mode matching telescope, the output mode cleaner, and the in-vacuum AS photodetector.

ADLIGO

STRAY LIGHT CONTROL
In the process of updating the scattered light budget for Adv LIGO, with emphasis on the recycing cavity scattering budget and the requirements for scattering by MMT2.

Other Laboratory R&D

From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>
 
We held a telecon with Alban and Jean Marie in Lyon.  The result is that the mirror prototype is quite satisfactory, except for the de-centering of the mexican head in the hat. Every other parameter is as good or better than needed for our tests. We are evaluating the effects of de-centering and proceeding with the main production trying to reduce the de-centering to a minimum.

Juri
Im still working on my (simplified) FFT program for studying the beam propagation in our Mexican Hat cavity; in particular I analyzed the problem of the fundamental limitations of discrete and finite grids in order to find the optimal choice for my simulation.
I sent an abstract for the conference Optics & Photonics 2005 which will be on 31 July - 4 August 2005 in San Diego, CA with the intention to present the status of our experiment on Flat-Top beam using the Mexican Hat mirrors that we will receive in the next weeks from LMA in Lyon.

Erika
Doing a simutaion of the effect of de-centering using the standard FFT program.

Marco (16 Feb)
OTF absestos removal works: for the next Tuesday an inspection is scheduled. The works on the roof and the floor will be performed the next week. The laboratory should be ready after my return from the Hanford shifts.
The PZTs driver is almost ready to be tested. The assembly will be completed before the end of this week.
Machine shop oven didnt cook our blades because a broken resistor which interrupted the cooking process.
The Rockwell hardness meter was re-calibrated and so we were able to measure the real hardness of our maraging blades.
The result was a difference of 10 points of the C-Rockwell scale of the new blades with respect with old blades (5 years old).
We are preparing to make comparative tests between ground surface and rolled surface blades. We started the hardness comparison between uncooked maraging grounded and grounded 20% oversize and then rolled to size samples. We are waiting for the oven repair for a further test on the maraging hardening and precipitation processes.
Creep experiment: today the temperature controller was turned to 190oC after a week at 40oC. During that period the data sample was quite stable around 7.34mm.


Riccardo
Final draft of conference contribution for the Long Beach ASME meeeting, available in http://www.ligo.caltech.edu/~desalvo/paper_asme-2005.doc

 


For additional information about this report, contact whitcomb_s@ligo.caltech.edu