Weekly Report for Week Ending November 12, 2004


 Exec. Comm. Agenda

Highlights

LSC

Administration

Hanford Observatory

Livingston Observatory

MIT

Caltech

Detector

40 Meter

TNI

LASTI

Data Analysis

Adv. LIGO Development

Past Weekly Reports


The LIGO Executive Committee Agenda for Monday, November 15, 2004 will be:

 (Meeting time: 10:30 am Pacific Time)  

  1. Announcements
  2. LSC Issues (Saulson)
  3. Comments on Weekly Report
  4. Field Change Orders/Contingency Liens/Change Requests
  5.  LIGO Lab Operations
      • Administration (Lindquist)
      • Sites (Raab, Zucker, Shoemaker)
      • Commissioning (Fritschel), Detector (Coyne)
      • Campus Research Facilities
        1. Weinstein (40 Meter)
        2. Libbrecht (TNI,
        3. Shoemaker(LASTI)
      • Data Analysis and Computing (Lazzarini)
  6. Advanced R&D and LIGO II (Shoemaker)
  7. CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION AS NEEDED


Special Items:


Special Announcements:


Weekly Report Highlights

An NSF Review Panel conducted an annual review of the LIGO Program November 8-10, 2004 at Caltech.  We want to thank everyone who helped the review go so smoothly.  The panel was pleased with our progress, and we should all be proud of accomplishments over the past year.  Following is their draft summary findings presented during the exit debriefing:

 

NSF Annual Review Summary

 

The Panel is very pleased to see the significant improvement in strain sensitivity for the H1 Interferometer at the Hanford Observatory since the last review.   The achieved sensitivity is within a factor of two over nearly all of science bandwidth of the design goal.

 

The Panel endorses the plans for achieving the remaining factor of two on the H1 Interferometer and looks forward to the implementation of these improvements on the other two interferometers.

 

The successful implementation of the active seismic isolation system, HEPI, on the Livingston Interferometer is a major step.  In addition to demonstrating the effectiveness of one of the key elements of the Advanced LIGO design, it will enable 24–7 operation of the interferometer and dramatically improve the duty cycle of the observatory.

 

As LIGO approaches the S5 science run planned during 2005, increased emphasis should be placed on improving the duty factors of all three interferometers.

 

The prototype thermal compensation system on the H1 interferometer should be further refined and commissioned at all the interferometers as soon as possible, with further research continuing to allow the interferometers to reach their full laser power design goal by the end of science run S5.

 

The transition from the leadership of Gary Sanders as Deputy Director and co–PI to Stan Whitcomb as Deputy Director and co–PI has been very smooth.  The Panel wishes Stan well in his new role.

 

The Panel wishes to thank Gary Sanders for the outstanding leadership he has provided during the critical eight years of LIGO construction, commissioning and early science running. 

 

While both choices for the test mass substrates, fused silica or sapphire, appear to satisfy the Advanced LIGO science requirements, it is very important to make a decision soon so that other design efforts can go forward.  Better is always the enemy of good enough.

 

The establishment of the new position of Visiting Associate at Caltech is a welcome step forward.  It will enable non-Caltech members of the LSC to assume line management roles in the operation of LIGO and in the construction and operation of Advanced LIGO.

 

The mechanical properties of the optical coatings for the optical elements in LIGO remain a concern for Advanced LIGO.  The Panel is pleased with the strategy that is being followed to resolve this issue.

 

The Panel encourages the continuation of the investigation of the effects of electrostatic charging of the mirror surfaces and the mitigation of these possible effects on the performance of the Advanced LIGO interferometers.

 

The active participation of the foreign collaborators in Advanced LIGO is an essential element of the Advanced LIGO construction project.  The Panel is pleased to note that PPARC has already awarded the funds for the suspension system and some optical elements and that the collaborators in Germany are well along in securing the funding for the high power lasers.

 

The Panel endorses the proposed revision to the LIGO organizational chart.  The expansion of the Directorate to include the Spokesperson of the LSC and the expansion of the Oversight Committee are very positive steps.   The inclusion of the LSC under the LIGO Directorate will bring coherence to the overall LIGO program as the science matures and the Advanced LIGO construction project gets underway.

 

The requested increase in the operating budget when the construction of Advanced LIGO is complete will have to be justified in detail at the time when the budget is submitted.  The projections will have to be accompanied by a detailed manpower plan.

 

As a possible improvement to the performance of Advanced LIGO, the Panel encourages the LIGO group to continue exploring noise-squeezing techniques developed by outside groups and participating in the testing of these techniques possibly at the 40 m.

 

The Panel endorses the plan to develop the specific security policies for assuring the integrity of the LIGO computer systems.  Patch management is an important activity in the near term and deserves special attention.

 

Approval of the construction of Advanced LIGO by the National Science Board is welcome news for the Panel.  The Panel urges the LIGO collaboration and the National Science Foundation to move forward as aggressively as possible with the construction of this important project.


LSC Issues (Saulson)


No report.


LIGO Laboratory Administration (Lindquist)


LIGO Laboratory Administration (Lindquist)

STATUS OF LSC MOUs (Petrac)

(LSC Research Plans through Feb. 2005 and Progress Reports through Aug. 2004)

ACIGA


CEGG


EGO


Florida


GEO


 MOU for Data Analysis


Goddard


IAP


Louisiana School of Math, Science, and Arts (LSMSA)


NAOC (Chinese Academy of Sciences)


NAOJ-TAMA


Orsay Group


Rochester


SIOM


Stanford


UTBRG


VIRGO



SITE TELECONFERENCE (Jasnow)

A site teleconference was held on Thursday, October 07, 2004.  The following issues were among those discussed:


PROPERTY MANAGEMENT (Chargois)

>From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>


>From: Cleveland Mak <mak_c@ligo.caltech.edu>


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman, Salone)

>From: Esther Cunningham <esther@ligo.caltech.edu>


>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>


>From: Gina Salone <gsalone@ligo.caltech.edu>


>From: Florence Kaufman <fkaufman@ligo.caltech.edu>


Financial reports can be found at: http://docuserv.ligo.caltech.edu/~fireport. (For passwords contact Florence)

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

>From: irena@ligo.caltech.edu (Irena Petrac)


>From: Ed Jasnow <jasnow@ligo.caltech.edu>


SUPPORT (Baldon, Kammerling, Lloyd)

>Irene Baldon


>Sharon Kammerling


>Dorothy Lloyd


PROPOSALS and REPORTS (Lindquist)

Schedule of proposals and reports planned for the remainder of the calendar year.


CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)


HUMAN RESOURCES (Akutagawa)

>From: Cindy Akutagawa <cindy@ligo.caltech.edu>

 


Quality/Safety (Tyler)

>From: Bill Tyler <tyler@ligo.caltech.edu>

No report this week.

 


LIGO Hanford Observatory (LHO) and Interferometer Operations (Raab)


Summary of Commissioning Activities at LIGO Hanford Observatory (Landry)

The weeklong engineering run E11 begins next Wednesday, Nov 17th at LHO.

Commissioning highlights from the past week are detailed below.

4K IFO


2K IFO


DAQ (some of the many items this week)


Outreach (D. Ingram)

We convened our Local Educator Network (LEN) for a productive meeting at LHO on 11/4/2004.  The LEN provides input and advice for our outreach program.   We hosted students from two WSU Tri Cities education courses for class sessions on the mornings of 11/3 and 11/4.  The course instructor is Dr. Judy Morrison.  Fifty teachers-in-training (primarily grades 1-8) participated in the 3-hour lessons.

 


LIGO Livingston Observatory (LLO) and Interferometer Operations (Zucker)



Despite continued problems with ISC110B channel hopping, HEPI commissioning is moving forward. The fourth test mass chamber (ITMY) is now isolating with sensor correction in the most relevant 2 of 3 degrees of freedom, and the beam splitter is 1 for 3.

 

IFO commissioning took further steps in preparation for high power; high-speed shutters and new thermal compensator interface electronics were installed.

 

We also exercised a new method for tuning optical lengths; HEPI allowed us to move the MC length to smoothly "dial in" a new resonant frequency to match our crystal oscillators.

 

Tom Lucas of Lucas Productions is filming at LLO tomorrow (Friday) and next week. Special guest stars are flying in from LA and Boston.

 

Livingston Outreach (Thacker)

 

LIGO SEC Education and Outreach Summary

 

 

L1 Interferometer Commissioning (Frolov)

 

 

HEPI commissioning (O'Reilly)

 

There were no valve failures this week. We have not checked accumulator pressures that may happen tomorrow during filming.

 

Work continues on HEPI. ITMY is now commissioned and has working sensor correction in the Y and Z directions, although some further investigation is needed for the X direction. The BS has sensor correction in the Z direction and will hopefully have X and Y by tomorrow (which is Rich Mittelman's last day).

 

The HAM3 blend filters had to be reworked due to a blend frequency that was too low. We are now taking sensor correction data for this tank.

 

We continue to have problems with channel hopping, which necessitates frequent reboots of the l1hepi1 and l1hepi2 processors.

 

We removed two filters from PUMP1 and examined them for contaminants.  This was in an effort to better understand our problems with valves.  We found contamination in the 25 um filter (metal debris and a spider), but the 3 um filter was very clean. PUMP1 will go back into service tomorrow.

 

Safety & Security (Riesen)

 

LASER SAFETY: Nothing to report

 

SITE SAFETY: Found no safety concerns during my weekly site safety tour.

 

TRAINING: Continuing the training for control room operators on the LSS and site security systems software and hardware.

 

AdL and LIGO 1 Mechanical Engineering (Spjeld)

 

 

CDS Software (Parameswariah)

 

Mike Fyffe dressed up the timing cables in the High Bay. All processors were restarted to get them resynced up.

 

Updated database/installed new database for Fast shutter controls, TCS and MC Trasmitted QPD. all channels are now wired to first cards on l1iool0 processors. Extra cards removed.

 

CDS's main disk containing all CDS user accounts and the main /cvs/cds disk filled up. Last night fixed this and will have to move this to a bigger disk. Conlog data is now at 15GB and occupies most of the disk space.

 

Frame Builder died and restarted itself again at 04:34 Hrs this morning.  Found the following message logged in its log file: "Nov 11 04:34:25 fb1 daqd[2565]: Lost cycles: -1056975780; shutdown".  Traced this to a spurious interrupt on the reflective memory.

 

LSC Aux processor - added new database records for ISCT1 Fast Shutter controls and restarted it.

 

Working with Rus on getting the POX PD / REFL2 PD wired up.

 

Working on HEPI Status screens. Fixing scripts/c programs/medm screens/database that generate the status screens.


General Computing (Roddy)

Finished setting up a central log host last week.  This machine is on an internal network and is not reachable from the outside.  I will be setting up firewall rules to restrict access to this machine from the public subnet. Spent Monday-Wednesday at the NSF review. Discussed networking issues with several people while in Pasadena since we could meet in person with a whiteboard, etc. and hash out certain issues.

LDAS/Condor Sysadmin and Burst Analysis (Yakushin)

 

LDAS/Condor admin:

 

Two extra tape drives were added to L700 robot. Firmware on all the drives was upgraded to version 1.34.408, firmware on L700 itself was upgraded to 3.06.00.

 

Data analysis:

 

1) Attended burst f2f and LSC meetings in Boston;

2) Submitted for LSC approval GWDAW-9 S3 burst search talk abstract and preliminary version of slides;

3) Siong Heng from GEO is visiting me this week to learn how to use waveburst for joint LIGO-GEO burst analysis;

4) Preparing plots of S2 double coincidence trigger rates requested by the burst review committee.

 

HPLF, L1 Commissioning, and AdL Modeling (Franzen)

 

1) Have been trying to communicate with the people at IPG, who are supposed to fix the broken HPLF laser. Yesterday we got to know that the problem have been identified to a burned fiber which will be replaced this coming Friday. If everything works out during a 40 hours full power it will be returned to LLO next week giving the IAP visitors a chance to finish their experiment.

 

2) Have been working with Richard Mittleman on HEPI BS, MC1 and MC2 sys-id and control filter design.

 

CDS software (Khan)

 

1) Fixed the bug in the Beamcentering servo code that was crashing the servo whenever a value of 0 was entered for the averaging factor, also enhanced the medm screen as per request from Andre.

 

2) Helping John and Valera on the TCS wave plate controller interface.  Established communication between the Newport Motion Controller unit and the vme162 processor.

 


Detector/Technical Support (Coyne)


CDS

See also the CDS weekly meeting minutes in the commissioning archives:

CDS Software

Rolf Bork reporting

CDS Hardware

Rich Abbott reporting

 

Ben Abbott

RFPD Redesign:

DMT

John Zweizig

This week I have been working with Tom Evans and Alex Ivanov on trying to understand the loss of frame data to the DMT. Considerable progress has been made, the DMT network configuration has been cleaned up, we found that the broadcaster packet burst parameter has to be set to a higher value than previously used, and the network interface card for delaronde was moved from a slow (33MHz) PCI slot to a fast one. Each of these changes should have had a significant effect on the ability to handle higher data rates, but at this point the data losses persist. At this point the only known difference between the LLO system and the LHO one (that successfully handles a higher data rate) is the operating system (Solaris 9 at LLO, Solaris 8 at LHO). I don't think that this is a problem, but this presents a good opportunity to upgrade the patch level of the LLO DMT machines.

 

I have also been creating a utility program to generate the xml calibration files used by SenseMonitor from the calibration group data products.

PSL

PeterKing

The problem reported last week with my PSpice model of the differential receiver on the intensity servo was fixed by the addition of a few 100MEG resistors.  Probably for reasons owing to the model for the VAC voltage source, this solution worked.

 

The power from the 10-W laser seems to have stabilised out at just under 6 W after the latest re-alignment.  Although the output power is low, this is the most stable this particular laser has been since delivery.

TCS quiet Chiller

Ken Mailand

I’m working on 5 laser chiller assemblies to supply the LHO and LLO sites.  I have a corrosion test in progress using the Chloramine-T, water mixture used for the PSL laser and TCS laser, and also the LHO site house chiller fluid, and the CIT system chiller fluid. Brass, Aluminum, plated steel and Copper are the test metals; to accelerate the process the fluid temps are @~135F.

AS Port Astigmatic Beam

Mike Smith

I completed the write-up of the technical note, and will submit it to the DCC, T040204-00.

Optical Contamination Cavities

Lee Cardenas, Liyuan Zhang

OTF Lab. (W. Bridge)
The chamber has two samples, white Ceramabond, and disks of TRA-BOND #2254 color light brown epoxy.  Cavity is locked.  We continue taking measurements everyday.  No Change

Absorption Test Measurement prototype   in standby

Scatterometer system  in standby
The Inner test mass 2ITM04 fused silica mirror is in the scatterometer enclosure.
We are waiting on the digital read out for the x-y motor travel bead.
Company contacted and they are sending it back next week.

The Quantronix 60 watt laser  NO CHANGE

OTF Lab at Lauritsen ROOM 38   NO CHANGE
Cavity #3
Chamber is pumping with (6) disks of TRA-BOND #2151 color blue epoxy and  (4) disks of TRA-BOND #2902 color silver epoxy.  The cavity is locked.
We'll continue taking daily measurements.

Cavity #2  in standby
The assembly of the new chamber is in progress.

 


40 Meter Interferometer (Weinstein)


IFO commissioning:

Electronics and computing:

Lab Infrastructure and Bake oven Lab:


Thermal Noise Interferometer (Libbrecht)


no report


LASTI (Ottaway)


no report


Data Analysis and Computing (Lazzarini)


Simulation and Modeling (Bhawal)

Weekly Physics Meeting

Matt Evans gave an update of the interferometer commissioning and operation at LLO.  Hiro Yamamoto presented e2e simulation results for signals measured before or after the Output Mode Cleaner.

Commissioning Related

(Biplab) Prepared "summary Statistics" files corresponding to various sets (Total no. 37) of measurements that Luca & Keita made on Phase Camera: http://www.ligo.caltech.edu/~bbhawal/PC_modal_data/1Stat.  Some of the files show that some modal parameters for the beam-profiles varied significantly even under same "Thermal Compensation" state on a specific date. For some sets of measurements, good fitting could not be achieved even by considering upto 4th order Hermite-Gaussian basis (15 modes) and it seems more modes are needed to describe such images.

Effect of OMC on the AS signal

(Hiro) The effect of the Output ModeCleaner (OMC) on the Antisymmetric (AS) port signal was studied by comparing the Q-demod and I-demod signals measured before and after OMC (OMC just filters all but 00 mode).  The analysis is still going on, but the signal after OMC seems to be preferable.

Simulation of 40m interferometer

Monica is calculating transfer functions, L- to Power Recycling Mirror and Signal Recycling Mirror outputs.  Hiro helped her to set up and use modeler freq.

Modeler code

Hiro modified modeler code to add and improve a few modules for the study of OMC, and addressed an inconvenient feature of modeler_freq.

Alfi

(Melody) Finished unit testing and fixing bugs (found during testing) for the simpler view for FUNC_X variables. Currently preparing the code for cvs checking and adding proper comments for javadoc.

Data Analysis Activities (Lazzarini)

Brown:

Mendell:

Gave progress reports on the StackSlide search for continuous gravitational waves, including comparisons with the Hough and PowerFlux searches, and a first look at the analysis of the S3 hardware injected pulsar signals.  These reports will appear as DCC documents G040501-00.pdf and G040502-00.pdf

Sutton:

This past week I attended the Bursts and LSC meetings at MIT, where I presented the almost-final full-data-set results of the LIGO-TAMA S2/DT8 bursts analysis.  Since then I have been debugging the coincidence codes and preparing the results for review and  (hopefully) approval for presentation at GWDAW.  I'm also re-running the coincidence incorporating additional TAMA data that was provided just before the LSC meeting.  The final coincidence and efficiency numbers should be ready for review by this afternoon.  Finally, I've circulated the LIGO-TAMA GWDAW abstract for comment and approval.

Shawhan:

·         Attended the Burst Group face-to-face meeting and the LSC Meeting at MIT

·         Read the LIGO-TAMA and LIGO-only paper drafts carefully for comments

·         Gearing up to review Pulsar Group results to be presented at GWDAW

Yakushin:

 

Zanolin:

LIGO Data Analysis System

Software Systems (Blackburn)

Pushed a pre-release version of LDAS to LHO, LLO and TEST systems to allow further testing prior to the release November 15. Greg Mendell has been testing the new features available for creating RDS frames. A few minor issues have been identified and will be fixed before the release. The pre-release also identified an issue with the email notifications for files that are moved around frequently at LHO, which is not seen at other sites. A quick fix to this was written up and tested here at Caltech and then pushed to the sites for testing. The main task for us prior to the release is to assure adequate testing of the new features associated with generation of RDS frames.

A possible large memory leak may be present in the new frameCPP/frameAPI code. More running will be needed to determine the degree to which this is a memory leak versus a tremendous startup cost for the new code. Close to a gigabyte is being used in only a couple of hours. This is roughly an order of magnitude larger than in the previous code base.

Wrote up documentation describing usage and content of LDGC third party package environment.

Fixed the problem with concatenation of AUX data within the FrAdcData structures identified when first testing 40 meter code which makes use of this for storing data-valid array data.

Updated ddd to version 3.3.10, added rrdtool version 1.0.49, added ganglia version 2.5.7, updated openssl to version 0.9.7e, and updated gnupg to version 1.2.6.

cmonClient - fixed PR 2734 by commenting out debug puts statement for diskcacheAPI directory tree.

Documentation: updated cmonClient client documentation and passed to librarian for cvs inclusion.

Testing: ran ldas System tests on version 1.2.63, updated results web page and cvs new results html. Committed result updates to cvs.  Added options to new RDSVerify script to bypass verification, run individual test, run as continuous loop and to dump RDS commands for cmonClient test panel.

Updated cntlmon resource files for test, lho and llo, created new databases and ran cmonClient tests at lho and llo. Modify Makefiles to generate new RDS commands for cmonClient test panel.

TCL/GLOBUS:

Completed SWIG wrapping of 2 asynchronous XIO read/write functions, globus_xio_register_read() & globus_xio_register_write().

Working on Tcl test cases to exercise asynchronous XIO client/server.

Four additional XIO functions are just completed.

Globus XIO functionality summary (latest):

Hardware Systems (Anderson)

Caltech

(Dan Kozak)

(Al Wilson)

(Stuart Anderson)

 

Livingston

(Igor Yakushin)

·         Two extra tape drives were added to L700 robot. Firmware on all the drives was upgraded to version 1.34.408, firmware on L700 itself was upgraded to 3.06.00.

Hanford

(Greg Mendell)

Preparing for E11, I have incorporated new LDAS options to createRDS jobs into the createrds drivers scripts.  The options allow the number of frames per file and the number of seconds per frame of the output RDS frames to be specified. I am currently running tests of these options.

(Ben Johnson)

 

General Computing (Wallace)

MIT:

(will report next week)

Livingston:

(Shannon)

Hanford:

(Christine)

CIT:

(Mike)

(Veronica)

(Lisa)

Mail Stats 11/03 - 11/10/04

(Larry)

 


Advanced LIGO and Supporting R&D (Shoemaker)


Systems and Management

From: "Thomas Frey" <tfrey@ligo.caltech.edu>

Progress Period from 11.05 to 11.11

OUT OF THE OFFICE Thursday the 11th.

·         See http://www.ligo.caltech.edu/~tfrey/index.htmlfor a complete listing of all project related cost and schedule data.

Accomplishments:

·         Sub-system PLANNING activities

§         Continued work on preparing web space for posting Adv. LIGO reports. ("The Whole Enchilada")

§         The 40-Meter schedule remains to be completed with changes.

§         Finished work on updated request curves inclusive of some schedule changes received on Tuesday the 2nd.

§         Sent revised curves to Carol for comment / distribution on Saturday the 6th.

§         Started work on progress update with progress through October 31, 2004.

·         ROSTER DATABASE:

§         Continued to work with Irena to provide Barry with information regarding FTEs and Institutions.

§         Assisting Irena as needed on record changes.

·         COST BOOK DATABASE:

§         Posted revised cost data as a result of the latest revisions of last week.

Seismic Isolation

From: Larry Jones <ljones@ligo.caltech.edu>
 
Advanced LIGO Seismic Structure

SEI Structure:

I am awaiting cost and schedule estimates from ASI in order to complete a draft rewrite of their contract.

Ken Mason has received quotes for fabricating the bulk of the parts (65% of the total cost, by ASI's estimate) for the AdLIGO SEI BSC unit prototype, from shops in MA. The level of these quotes confirm the August estimate by ASI, which is considerably below ASI's latest estimate. This information is a significant input to the study on how we should proceed.

Ken Mailand and I talked with Brent Ekstrand of Astro Pak to get technical details of their cleaning capabilities and recommendations. I'll be putting together a draft plan for our cleaning pathfinder task, for the development of cleaning procedures and quality evaluation methods to be used for parts too large to be cleaned and RGA scanned at LIGO facilities.

Actuators:

We have told PSI that the 12 actuator coils that failed the high-pot testing will need to be reworked or replaced. Due to the severity of potential problems, we cannot stand the risk of failure in service that may be caused by relaxing the requirements.

Displacement Sensors:

ADE is proceeding with fabricating and testing the 14 displacement sensors for the BSC prototype structure. They have provided a quote for two calibration blocks.

Accu-Glass is proceeding with fabricating and testing the 3 feedthrough flanges for the BSC chamber at LASTI, with 16 feedthrough fittings each.

Seismometers:

Nothing new.

Galling/Dusting Test:

Nothing new.

Suspension

From: Janeen Romie <romie_j@ligo.caltech.edu>

Ian Wilmut from RAL has joined us for 3 weeks, starting on Nov 8. We welcome him and look forward to working with him on quad controls prototype design issues.

Working on the quad tablecloth design.

Prepared for and participated in the NSF Review.

Working on SUS Primavera update.

Organizing the visit from Justin and Caroline at the end of November. Getting travel arrangements in place for our visit to Glasgow in January.

Created the first draft of the Advanced LIGO safety stop design requirements document. I have sent it to Mark for review.

From: ctorrie <ctorrie@ligo.caltech.edu>
 
Advanced LIGO SUS

Weekly report

1) Structures

Tim has been working on the lower structure (containment truss) and is visiting Russell in Glasgow next week to discuss its interface with the assembly rig (catcher).
We have a first resonance of the overall structure of ~ 90 Hz in both ALGOR and ANSYS. The structure weighs ~ 140kg and is lightweight around the lower three masses.

2) Design Meeting

We have created an updated overall assembly with a drawing tree and all of the various sections identified with LIGO numbers.
The task summary (our schedule for the quad) was reviewed at the weekly meeting
http://www.ligo.caltech.edu/~ctorrie/QUAD_ETM/quad_etm_setup_page2.html

3) Visits

Ian Wilmut is visiting us from RAL for 3 weeks. Mike Lloyd has another week left of his visit from Glasgow.

4) Design Guidelines
To go along with the drawing guidelines by Dennis we are trying to create a list of "rules" to ease the exchange between PRO-E and SolidWorks files. A draft is available at http://www.ligo.caltech.edu/~ctorrie/SW/Hints.html.
 
From: Helena Armandula <ahelena@ligo.caltech.edu>
 
Adv. LIGO "Q" measurements
Silicate bonded a prism on a sapphire rod so "Q" measurements can be taken.

Adv. LIGO SUS
Continued the development of indium cold welding to attach magnets to holders and sensor flags.
Bob Taylor put together a small vacuum to be used to melt indium on the aluminum parts to enhance bonding.

Pre-Stabilized Laser

From: Peter King <pking@ligo.caltech.edu>

AdvLIGO PSL

As Benno was here for the NSF Review, we had a discussion about some aspects of the PSL.  In particular some laser safety related concerns and the need for having a clean room around the laser table enclosure.  The latter is due to the finding at LZH that some dust had stuck to one of the quartz rotators and was promptly burnt by the laser.  This in turn impacted the beam quality of the laser along with the output power.

The pre-mode cleaner that was on loan to Stanford was returned.  The appearance of the packing material caused some concern.  The pre-mode cleaner will be checked out.

Auxiliary Optics

From: Michael Smith <smith@ligo.caltech.edu>

ADV LIGO
I am in the process of "scrubbing" the AOS cost book with a fine, bristle brush.

Other Laboratory R&D

From: Riccardo DeSalvo desalvo@ligo.caltech.edu

Juri

I made the calculations for the thermal noises (coating and substrate / Brownian and thermo elastic) for finite mirrors in the case of using a Mesa-Beam. I have only preliminary results for the sapphire substrate because the calculations are still running, however the results for coating and thermo elastic noises show a noise reduction with respect to the Gaussian beam of a factor ~1.5 / ~1.7 for a mirror radius of 16 cm. and diffraction losses of ~1ppm. I will check these results with other calculations present in literature. I am taking measurements for the “creep” experiment and I found a simple procedure to overcome the strange behavior of the equilibrium position we observed sometimes (a satisfactory explanation of this phenomenon is still lacking).

I am writing the short pre-thesis I have to present on December in Pisa University.

Marco

The final design of the “servo circuit” has been completed as the assembling of the circuit on the board. I began to take the first measurements from the “creep experiment”: on Saturday I and Juri have seen a second equilibrium point quite far from the usual point.

The creep is at 90 centigrades, it has something sticking inside generating a sort of bistability.

Unfortunately we cannot stop the measurement and check, we will have to proceed as is.


For additional information about this report, contact whitcomb_s@ligo.caltech.edu