Weekly Report for
Week Ending November 12, 2004
The LIGO Executive
Committee Agenda for
Monday, November 15, 2004 will be:
(Meeting time: 10:30 am Pacific Time)
- Announcements
- LSC
Issues (Saulson)
- Comments
on Weekly Report
- Field
Change Orders/Contingency Liens/Change Requests
- LIGO Lab Operations
- Administration
(Lindquist)
- Sites
(Raab, Zucker, Shoemaker)
- Commissioning
(Fritschel), Detector (Coyne)
- Campus
Research Facilities
- Weinstein
(40 Meter)
- Libbrecht
(TNI,
- Shoemaker(LASTI)
- Data
Analysis and Computing (Lazzarini)
- Advanced
R&D and LIGO II (Shoemaker)
- CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION AS
NEEDED
Special Items:
Special Announcements:
Weekly Report
Highlights
An NSF Review Panel conducted an annual review of the LIGO
Program November 8-10, 2004 at Caltech.
We want to thank everyone who helped the review go so smoothly. The panel was pleased with our progress,
and we should all be proud of accomplishments over the past year. Following is their draft summary
findings presented during the exit debriefing:
NSF
Annual Review Summary
The Panel is very pleased to see the significant improvement
in strain sensitivity for the H1 Interferometer at the Hanford Observatory since
the last review. The achieved
sensitivity is within a factor of two over nearly all of science bandwidth of
the design goal.
The Panel endorses the plans for achieving the remaining
factor of two on the H1 Interferometer and looks forward to the implementation
of these improvements on the other two interferometers.
The successful implementation of the active seismic isolation
system, HEPI, on the Livingston Interferometer is a major step. In addition to demonstrating the
effectiveness of one of the key elements of the Advanced LIGO design, it will
enable 24–7 operation of the interferometer and dramatically improve the duty
cycle of the observatory.
As LIGO approaches the S5 science run planned during 2005,
increased emphasis should be placed on improving the duty factors of all three
interferometers.
The prototype thermal compensation system on the H1
interferometer should be further refined and commissioned at all the
interferometers as soon as possible, with further research continuing to allow
the interferometers to reach their full laser power design goal by the end of
science run S5.
The transition from the leadership of Gary Sanders as Deputy
Director and co–PI to Stan Whitcomb as Deputy Director and co–PI has been very
smooth. The Panel wishes Stan well
in his new role.
The Panel wishes to thank Gary Sanders for the outstanding
leadership he has provided during the critical eight years of LIGO construction,
commissioning and early science running.
While both choices for the test mass substrates, fused silica
or sapphire, appear to satisfy the Advanced LIGO science requirements, it is
very important to make a decision soon so that other design efforts can go
forward. Better is always the enemy
of good enough.
The establishment of the new position of Visiting Associate
at Caltech is a welcome step forward.
It will enable non-Caltech members of the LSC to assume line management
roles in the operation of LIGO and in the construction and operation of Advanced
LIGO.
The mechanical properties of the optical coatings for the
optical elements in LIGO remain a concern for Advanced LIGO. The Panel is pleased with the strategy
that is being followed to resolve this issue.
The Panel encourages the continuation of the investigation of
the effects of electrostatic charging of the mirror surfaces and the mitigation
of these possible effects on the performance of the Advanced LIGO
interferometers.
The active participation of the foreign collaborators in
Advanced LIGO is an essential element of the Advanced LIGO construction
project. The Panel is pleased to
note that PPARC has already awarded the funds for the suspension system and some
optical elements and that the collaborators in Germany are well along in
securing the funding for the high power lasers.
The Panel endorses the proposed revision to the LIGO
organizational chart. The expansion
of the Directorate to include the Spokesperson of the LSC and the expansion of
the Oversight Committee are very positive steps. The inclusion of the LSC under the
LIGO Directorate will bring coherence to the overall LIGO program as the science
matures and the Advanced LIGO construction project gets underway.
The requested increase in the operating budget when the
construction of Advanced LIGO is complete will have to be justified in detail at
the time when the budget is submitted.
The projections will have to be accompanied by a detailed manpower
plan.
As a possible improvement to the performance of Advanced
LIGO, the Panel encourages the LIGO group to continue exploring noise-squeezing
techniques developed by outside groups and participating in the testing of these
techniques possibly at the 40 m.
The Panel endorses the plan to develop the specific security
policies for assuring the integrity of the LIGO computer systems. Patch management is an important
activity in the near term and deserves special attention.
Approval of the construction of Advanced LIGO by the National
Science Board is welcome news for the Panel. The Panel urges the LIGO collaboration
and the National Science Foundation to move forward as aggressively as possible
with the construction of this important project.
LSC Issues
(Saulson)
No report.
LIGO Laboratory
Administration (Lindquist)
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Petrac)
(LSC
Research Plans through Feb. 2005 and Progress Reports through Aug.
2004)
ACIGA
- Attach.
A / to PI for sign-off / McClelland
- Attach.
B / signed-off
- Attach.
C / signed-off
- Attach.
D / signed-off
- Attach.
Z / signed-off
CEGG
- Attach.
A / in sign-off by PI (reminder processed)
- Attach.
B / Rev. 1/ in sign-off by PI (reminder processed)
- Attach.
Z / in sign-off by PI (reminder processed)
EGO
- Attach.
3 (flat beam profile Fabry-Perot interferometer-concept) / to EGO for sign-off
/ DeSalvo
Florida
GEO
- Attach.
B / to PIs for sing-off / Danzmann
- Attach.
C / to PIs for sing-off / Danzmann
- Attach.
D / to PIs for sing-off / Danzmann
- Attach.
Z / to PIs for sing-off / Danzmann
MOU for Data Analysis
- Addendum
B / in LIGO review / Barish
Goddard
- Attach.
A / to PI for sign-off
- Attach.
C / signed-off
- Attach.
Z / signed-off
IAP
- Attach.
C / to PI for sign-off
- Attach.
Z / to PI for sign-off
Louisiana School of Math, Science, and Arts
(LSMSA)
- MOU
(LLO Outreach project) / in LIGO review / O. Reilly and Saulson
NAOC (Chinese Academy of Sciences)
- Draft-Attach.
1 (R&D in flat-top beam profile technology) / in NAOC review / DeSalvo
NAOJ-TAMA
- Attach.
D / signed-off
- Attach.
Z / signed-off
Orsay Group
- MOU
/ signed-off
- Attach.
No. 1 / signed-off
Rochester
- Attach.
A-draft / to PI for further inputs / Melissinos
SIOM
- Extension
of Attach. 2 / in LIGO review / Billingsley
Stanford
- Attach.
A / in LIGO review / Barish
- Attach.
B / in LIGO review / Barish
- Attach.
C / in LIGO review / Barish
- Attach.
D / in LIGO review / Barish
- Attach.
Z / to PI for sign-off / Byer
- Progress
Reports for Attach. A, B, C, and D / in process for web posting / Turner
UTBRG
- Attach.
A / in LIGO review / Barish
- Attach.
Z / in LIGO review / Barish
VIRGO
- MOU
Amendment No. 1 / in LIGO-LSC-VIRGO review / Barish, Saulson, and Giazotto
- Attach.
No. 4 / in LIGO-LSC-VIRGO review / Barish and Lazzarini, Saulson, and Giazotto
and Cavalier
- Attach.
No. 5 / in LIGO-LSC-VIRGO review / Barish and Lazzarini, Saulson, and Giazotto
and Cavalier
SITE TELECONFERENCE
(Jasnow)
A site teleconference was held on Thursday,
October 07, 2004. The following issues were among those discussed:
- Procedures:
(Action 124) Flowcharts for taxation need to be revised based on information
currently being provided.
- Funding:
Funding for the first half of FY 2005 for Operations has been received from
the NSF.
- Costs:
Tracking reports for the end of October have been issued.
- Contracts:
Still no contract from the Exploratorium. Caltech legal department has
approved the A&E Contract for the Outreach Building. Still waiting
for the final version from the contractor. Estimates for mitigation
efforts associated with building are sugnificantly reduced.
- Property:
Ed scheduled to be at Hanford next week.
- Audit:
A followup audit of the procedures for handling checking accounts at Hanford
was conducted. The report was relatively positive although there were a
few recommendations. To be addressed.
- Assigned
Action Items: The list of assigned actions updated through September 16,
2004 may be found Here.
PROPERTY MANAGEMENT
(Chargois)
>From: Ed Chargois
<chargois_e@ligo.caltech.edu>
- Provided
assistance to the Detector Group (H. Armandula) with packing and shipping four
(4) THI substrates and five (5) 3" diameter x1" Q-substrates to Research
Electro-Optics, Boulder CO. Attn: Dale Ness. Account Number P204296.
- Provided
assistance to Caltech's Property Services with the campus audit being
conducted by PWC.
- Provided
assistance to Caltech's Property Services with information concerning the
General Services Administration Vehicle Usage Report as required by the
National Science Foundation. This report was completed and forwarded to the
NSF. Attention: Mr. Kevin Rorer.
- Returned
several sets of Government Licenses Plates to the NSF. Account Number
P204254.
DOCUMENT CONTROL
CENTER (Turner, Mak)
>From: Linda Turner -
turner@ligo.caltech.edu>
- Attended
and supported the LSC Meeting at MIT.
- Supported
the NSF Review.
- Met
with Peter Saulson and discussed options for LSC meetings. He asked me
to work with a collaborator currently preparing for the March 2006 LSC and to
provide a budget analysis showing percentage of increase between the meeting
being held here in the States vs. in Europe. He also asked me to do
preliminary investigation into feasibility of holding LSC meetings in Atlanta
(rather than Livingston) and Salt Lake City (rather than Hanford). Work
has begun on the Atlanta portion.
- Finalizing
presentations from the LSC. These should be posted by this afternoon or
tomorrow morning.
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
COST SCHEDULE
CONTROL SYSTEMS (Cunningham, Brambila, Kaufman,
Salone)
>From: Esther Cunningham
<esther@ligo.caltech.edu>
>From: "Brambila, Ruth"
<Ruth.Brambila@caltech.edu>
- Working
on the two new change orders to Northrop Grumman.
- Completing
boxing the FY2003 and FY2004 closed purchase orders and set up the new files
for FY2005.
>From: Gina Salone <gsalone@ligo.caltech.edu>
>From: Florence Kaufman
<fkaufman@ligo.caltech.edu>
- Completed
and posted monthly reports as of the end of October for both fiscal year 2004
and fiscal year 2005. The reports were a little delayed this month
because the month end closing for Oracle ran into some problems, and data for
the end of October was not available until Monday November 8th.
- Submitted
a Cost Transfer to correct the allocation of ASI expenditures between the BSC
and HAM fabrication accounts. Unfortunately, I made an error on the Cost
Transfer and the adjustment was made to reduce the charges to the BSC
fabrication. I informed the Finance department of the
error and they are in the process of reversing the incorrect adjustment and
entering the proper adjustment.
Financial reports can be found at: http://docuserv.ligo.caltech.edu/~fireport. (For passwords
contact Florence)
SUBCONTRACTS
MANAGEMENT (Petrac, Jasnow)
>From:
irena@ligo.caltech.edu (Irena Petrac)
- MIT:
Change Order allocating first half of FY 2005 budget for the LIGO effort at
MIT is in preparation.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- We're
still awaiting the proposed contract documents from the Exploratorium for the
15 exhibits that we've ordered. These are 12 for LLO and 3 for
LHO. We expect the contract documents by tomorrow.
- The
draft report from the follow-up audit conducted at LHO has been issued for
review. LIGO is preparing its response to the findings set forth in the
report.
- The
final version of the architect/engineering contract with Eskew - Dumez -
Ripple is due today. It will include an appendix calling out unit prices
for construction management. LIGO will determine the amount of
construction management required at the time of selection of the construction
contractor.
- The
ASI contract will be modified to remove the prototype for the BSC
chamber. This will leave only the BSC design to be completed on the
contract.
SUPPORT (Baldon,
Kammerling, Lloyd)
>Irene Baldon
- Processed
the paper work for six (6) new/revised trips. There are six (6) trips to
be completed and ticketed at this time.
- Completed
thirty (30) Expense Reports and there are three (3) reports yet to be
done. I continue to contact travelers who have outstanding Expense
Reports (more than one (1) month old) to ask for their cooperation in sending
me their receipts so that these can be closed in a timely manner.
Presently there are ten (10) reports more than 30 days old. Travel
Audits new policy of accepting only original signatures seriously holds up the
process of closing reports. I have nine (9) Expenses Reports waiting for
original signatures to be sent/returned to me. [Please note that of the
ten (10) reports more than 30 days old (Travel Audit's Delinquent List) nine
have been completed and are awaiting original signatures to be sent to
me. Only one (1) traveler has not responded to my request for his/her
receipts.]
>Sharon Kammerling
- No
special projects to report.
>Dorothy Lloyd
- Processed
the usual invoices for payment. Tracked and followed up on invoice problems.
Reviewed and recorded payments processed by Esther the week of November 1.
- Initiated
electronic requisitions for change orders 36 and 37 to Northrop and change
order 18 to REO. Processed payment requests.
- Placed
P-card orders in Ruth's absence.
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
PROPOSALS and
REPORTS (Lindquist)
Schedule of proposals and
reports planned for the remainder of the calendar year.
- November
8-10 -- NSF Review
- December
31 -- FY 2007 - 2011 Operations Proposal including impact of Advanced LIGO
funding
- April
2005 -- NSF Review of Operations Proposal for FY 2007 - 2001
- April
2005 -- NSF Review of Advanced LIGO Proposal Revisions as required
CHANGE
CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
- D.
Coyne has submitted a change request for the ASI effort along with supporting
documentation. Modifications are proposed in response to ASI's latest
estimate increase. The change request will be distributed for discussion
during a future meeting of the Executive Committee..
HUMAN RESOURCES
(Akutagawa)
>From: Cindy Akutagawa
<cindy@ligo.caltech.edu>
- Various
personnel/payroll /HR related work.
Quality/Safety
(Tyler)
>From: Bill Tyler
<tyler@ligo.caltech.edu>
No report this
week.
LIGO Hanford Observatory (LHO)
and Interferometer Operations (Raab)
Summary of Commissioning
Activities at LIGO Hanford Observatory (Landry)
The weeklong
engineering run E11 begins next Wednesday, Nov 17th at LHO.
Commissioning
highlights from the past week are detailed below.
4K IFO
- force-to-pitch
(F2P) and torque-to-position (T2P) digital filters, recently found on the 4k
and the 2k IFOs to be incorrectly defined given the data acquisition rate,
have been redefined and corrected
- WFS2
behaviour as a function of laser power was characterized here
and here
- This
report
describes power levels during full lock. More IFO/Thermal compensation
system (TCS) studies are available here,
and here.
- thumbs
up for the new, quieter TCS chiller
- the
VCO was acting
up
- the
4k sideband analyzer was saturating;
ND filters added
- multiple
fixes
and improvements
were made to the 4k ISS hardware
- a
WFS spare was modified
to improve noise performance (by ~5dB)
2K IFO
- The
F2P filter investigations noted above led to the realization
that piston motion on the FMY mass results in excess yaw motion.
Checking for possible electronics mis-wiring.
- 2k
TCS chillers were tested. Problems
with the chiller were noted.
- New
F2Ps
were designed
- WFS
demod boards modified
to reduce noise
- The
2k has been steadily improving, running Wed eve on ASPD2 and ASPD3 with a
range of about 1Mpc. Next, input laser power will be ramped, and
auxillary loops will move to larger bandwidths, as was done on the 4k.
DAQ (some of the many items this week)
- Software
upgrades on both IFOs now allow the ramping of gains in filter modules
- For
some time it has been noted that requesting several (or more) test points of
the LSC front end adds noise to the gravity wave channel. Two responses
this week were to i) add a more representative CPU load monitor number (in
place and presumably reporting accurately), and ii) ensure that asking for
many test points does
not impact AS_Q
- fast
ADCU's installed
on 2k and 4k in place but not hooked up
- Dataviewer
was upgraded
- remote
reset capabilities
were added for various frontend CPUs
Outreach (D. Ingram)
We convened our Local
Educator Network (LEN) for a productive meeting at LHO on 11/4/2004.
The LEN provides input and advice for our outreach program. We
hosted students from two WSU Tri Cities education courses for class sessions on
the mornings of 11/3 and 11/4. The course instructor is Dr. Judy
Morrison. Fifty teachers-in-training (primarily grades 1-8) participated
in the 3-hour lessons.
LIGO Livingston Observatory
(LLO) and Interferometer Operations (Zucker)
Despite continued problems with ISC110B channel hopping,
HEPI commissioning is moving forward. The fourth test mass chamber (ITMY) is now
isolating with sensor correction in the most relevant 2 of 3 degrees of freedom,
and the beam splitter is 1 for 3.
IFO commissioning took further steps in preparation for high
power; high-speed shutters and new thermal compensator interface electronics
were installed.
We also exercised a new method for tuning optical lengths;
HEPI allowed us to move the MC length to smoothly "dial in" a new resonant
frequency to match our crystal oscillators.
Tom Lucas of Lucas Productions is filming at LLO tomorrow
(Friday) and next week. Special guest stars are flying in from LA and
Boston.
Livingston Outreach (Thacker)
LIGO SEC Education and Outreach Summary
- completed LIGO SEC
Project Execution Plan 1st Draft
- contacted vendor
about supplying gravity well exhibits; all looks good; awaiting invoice
- met w/ SUBR & LA
GEAR UP Tuesday afternoon to discuss Proj Exec Plan details;
- After discussions w/
Steve McGuire, have tentatively identified a final total of 5 exhibits, of
initial 12, to be installed at SUBR.
L1 Interferometer Commissioning
(Frolov)
- MC length was
changed by 0.7mm using HEPI HAM2 actuators. The required change is 1mm. To
make this change the position sensors will have to be repositioned to get more
range, MC length changed by full amount, and dial gauges installed.
- Found problems with
BS satellite amplifier box(had a short) and bad connection to MC1 satellite
amp box.
- ITMX optical lever
cable had to be reterminated.
- MC EO shutter
removed to accommodate the cross-connect change for the TSC installation. The
fast shutter was installed and tested. The optical table was realigned and
light levels were set for the new operation scheme. MC was locked after the
change.
- The electronics for
both TCS interfaces is installed and tested. The RS232-485 link for the
rotating polarizer has just been shown to work (communication established).
The test of the rotating polarizer will be completed when we are
allowed into LVEA later today (HEPI test is underway).
HEPI commissioning (O'Reilly)
There were no valve failures this week. We have not checked
accumulator pressures that may happen tomorrow during filming.
Work continues on HEPI. ITMY is now commissioned and has
working sensor correction in the Y and Z directions, although some further
investigation is needed for the X direction. The BS has sensor correction in the
Z direction and will hopefully have X and Y by tomorrow (which is Rich
Mittelman's last day).
The HAM3 blend filters had to be reworked due to a blend
frequency that was too low. We are now taking sensor correction data for this
tank.
We continue to have problems with channel hopping, which
necessitates frequent reboots of the l1hepi1 and l1hepi2 processors.
We removed two filters from PUMP1 and examined them for
contaminants. This was in an effort
to better understand our problems with valves. We found contamination in the 25 um
filter (metal debris and a spider), but the 3 um filter was very clean. PUMP1
will go back into service tomorrow.
Safety & Security (Riesen)
LASER SAFETY: Nothing to report
SITE SAFETY: Found no safety concerns during my weekly site
safety tour.
TRAINING: Continuing the training for control room operators
on the LSS and site security systems software and hardware.
AdL and LIGO 1 Mechanical Engineering
(Spjeld)
- received and
reviewed quotes, ordered safety screens and adapter plates for two hydraulic
actuators
- looking into history
of hydraulic servo valves; attempting to eliminate continuous troublesome
valves from the system
- dissection and
analysis of pump station filters for HEPI hydraulic system: no contaminations
found on “clean” side
- working on design
suggestions for HAM chamber door removal fixture: measured critical distances
in LVEA, clean room and fork lift
- preparing for quotes
evaluation meeting for the UHV Quad Bakeout oven
- working on assembly
and modification of hardware for the Photon Calibrator Support Shelves; aiming
to complete within early next week
- working on design
requirements report for Quad Suspension Installation Tooling
CDS Software (Parameswariah)
Mike Fyffe dressed up the timing cables in the High Bay. All
processors were restarted to get them resynced up.
Updated database/installed new database for Fast shutter
controls, TCS and MC Trasmitted QPD. all channels are now wired to first cards
on l1iool0 processors. Extra cards removed.
CDS's main disk containing all CDS user accounts and the main
/cvs/cds disk filled up. Last night fixed this and will have to move this to a
bigger disk. Conlog data is now at 15GB and occupies most of the disk space.
Frame Builder died and restarted itself again at 04:34 Hrs
this morning. Found the following
message logged in its log file: "Nov 11 04:34:25 fb1 daqd[2565]: Lost cycles:
-1056975780; shutdown". Traced this
to a spurious interrupt on the reflective memory.
LSC Aux processor - added new database records for ISCT1 Fast
Shutter controls and restarted it.
Working with Rus on getting the POX PD / REFL2 PD wired
up.
Working on HEPI Status screens. Fixing scripts/c
programs/medm screens/database that generate the status screens.
General Computing
(Roddy)
Finished setting up a central log host last week. This
machine is on an internal network and is not reachable from the outside. I
will be setting up firewall rules to restrict access to this machine from the
public subnet. Spent Monday-Wednesday at the NSF review. Discussed networking
issues with several people while in Pasadena since we could meet in person with
a whiteboard, etc. and hash out certain issues.
LDAS/Condor Sysadmin and Burst Analysis
(Yakushin)
LDAS/Condor admin:
Two extra tape drives were added to L700 robot. Firmware on
all the drives was upgraded to version 1.34.408, firmware on L700 itself was
upgraded to 3.06.00.
Data analysis:
1) Attended burst f2f and LSC meetings in Boston;
2) Submitted for LSC approval GWDAW-9 S3 burst search talk
abstract and preliminary version of slides;
3) Siong Heng from GEO is visiting me this week to learn how
to use waveburst for joint LIGO-GEO burst analysis;
4) Preparing plots of S2 double coincidence trigger rates
requested by the burst review committee.
HPLF, L1 Commissioning, and AdL Modeling
(Franzen)
1) Have been trying to communicate with the people at IPG,
who are supposed to fix the broken HPLF laser. Yesterday we got to know that the
problem have been identified to a burned fiber which will be replaced this
coming Friday. If everything works out during a 40 hours full power it will be
returned to LLO next week giving the IAP visitors a chance to finish their
experiment.
2) Have been working with Richard Mittleman on HEPI BS, MC1
and MC2 sys-id and control filter design.
CDS software (Khan)
1) Fixed the bug in the Beamcentering servo code that was
crashing the servo whenever a value of 0 was entered for the averaging factor,
also enhanced the medm screen as per request from Andre.
2) Helping John and Valera on the TCS wave plate controller
interface. Established
communication between the Newport Motion Controller unit and the vme162
processor.
Detector/Technical
Support (Coyne)
CDS
See also the CDS weekly meeting minutes in the commissioning
archives:
CDS Software
Rolf Bork reporting
- Alex was at LHO past
week and a half. Changes made at LHO during that time:
- Change ASC
front end for bulls eye detector. This involved removing FS5 from
overall ASC gain.
- Change to
LSC to support TCS.
- Installed
new 2.2GHz in LHO4k ITM controller.
- Installed
fast ADCU on both LHO IFO. Code still needs work to port to
Linux.
- New
dataviewer installed at LHO.
- Gain ramping
filter code installed on all systems.
- Continued work on
FPDP readout of ICS modules for HEPI. This software, along with new watchdogs,
will be installed next week during my visit to LLO.
- Some of the new
2.2GHz VME processors w/3 PMC slots should arrive by tomorrow. These units are to be used in ETM
controllers and LSC. I ported the LSC software to Linux yesterday, but have
not tested it yet.
CDS Hardware
Rich Abbott reporting
- Helping complete
needed calculations for tradeoffs of performance on new LSC RFPD
- Wrote procedure for
transferring an electronics design from one location to another with proper
supporting documentation
- Completed block
diagram explaining the HEPI system
Ben Abbott
RFPD Redesign:
- Testing of the
prototype continues. Attention is now being paid to the ASI servo
matching.
- The final gerber file
has gone out to PCB Pro for manufacture. It should be back next week
when we can begin stuffing and testing.
DMT
John Zweizig
This week I have been working with Tom Evans and Alex Ivanov
on trying to understand the loss of frame data to the DMT. Considerable progress
has been made, the DMT network configuration has been cleaned up, we found that
the broadcaster packet burst parameter has to be set to a higher value than
previously used, and the network interface card for delaronde was moved from a
slow (33MHz) PCI slot to a fast one. Each of these changes should have had a
significant effect on the ability to handle higher data rates, but at this point
the data losses persist. At this point the only known difference between the LLO
system and the LHO one (that successfully handles a higher data rate) is the
operating system (Solaris 9 at LLO, Solaris 8 at LHO). I don't think that this
is a problem, but this presents a good opportunity to upgrade the patch level of
the LLO DMT machines.
I have also been creating a utility program to generate the
xml calibration files used by SenseMonitor from the calibration group data
products.
PSL
PeterKing
The problem reported last week with my PSpice model of the
differential receiver on the intensity servo was fixed by the addition of a few
100MEG resistors. Probably for reasons owing to the model for the VAC
voltage source, this solution worked.
The power from the 10-W laser seems to have stabilised out at
just under 6 W after the latest re-alignment. Although the output power is
low, this is the most stable this particular laser has been since delivery.
TCS quiet Chiller
Ken Mailand
I’m working on 5 laser chiller assemblies to supply the LHO
and LLO sites. I have a corrosion
test in progress using the Chloramine-T, water mixture used for the PSL laser
and TCS laser, and also the LHO site house chiller fluid, and the CIT system
chiller fluid. Brass, Aluminum, plated steel and Copper are the test metals; to
accelerate the process the fluid temps are @~135F.
AS Port Astigmatic Beam
Mike Smith
I completed the write-up of the technical note, and will
submit it to the DCC, T040204-00.
Optical Contamination Cavities
Lee Cardenas, Liyuan Zhang
OTF Lab. (W. Bridge)
The chamber has two samples,
white Ceramabond, and disks of TRA-BOND #2254 color light brown epoxy.
Cavity is locked. We continue
taking measurements everyday. No Change
Absorption Test
Measurement prototype in standby
Scatterometer
system in standby
The Inner test mass 2ITM04 fused
silica mirror is in the scatterometer enclosure.
We are waiting on the
digital read out for the x-y motor travel bead.
Company contacted and they
are sending it back next week.
The Quantronix 60 watt laser
NO CHANGE
OTF Lab at Lauritsen ROOM 38 NO
CHANGE
Cavity #3
Chamber is pumping with (6) disks of TRA-BOND
#2151 color blue epoxy and (4) disks of TRA-BOND #2902 color silver
epoxy. The cavity is locked.
We'll continue taking daily
measurements.
Cavity #2 in standby
The assembly of the
new chamber is in progress.
40 Meter Interferometer
(Weinstein)
IFO commissioning:
- We've
achieved another important milestone in the path towards full ifo lock
acquisition. Osamu, Hartmut and Rob, working late nights, have acquired lock
of the dual-recycled Michelson (DRMI) with the 33 MHz sidebands resonant in
the PRC.
- Previously,
they locked the DRMI with the carrier resonant in the PRC, but the arms cannot
be added to this configuration; now, they can (when the carrier resonates in
the arms, the arm reflectivity flips sign, bringing the carrier into resonance
in the PRC as well). After some work, lock acquisition proceeded quickly, and
relatively long locks (~ 7 minutes) were achieved. Optical spectrum analyzers
(OSAs) at the SP, PO and AP confirmed that the RF structure was as expected
with the detuned configuration: the 166 MHz sidebands were unbalanced, with
one sideband reflected to the SP and the other transmitted to the AP. The
carrier was, of course, absent at the AP.
- Details:
lock MICH by dithering the BS at 1230 Hz and using digital-demod signals at
the PO and AP; lock PRC with 33 MHz at SP, with servo sign set to lock on
sidebands; lock SRC with (166-33) MHz signal at PO.
- Rob
wrote a script to (partially) automate the lock acquisition procedure.
Unfortunately, we don't yet have an easy way to automate the detection of
lock; we look at dataviewer traces, scope traces, and OSA displays. Soon, we
will implement the SPOB photodiode, which will help a lot.
- Lock
loss was associated with spikes at the dither signal, which appear to be due
to electronics couplings at the whitening boards. This was greatly reduced by
turning off the whitening; but the boards themselves can and will be fixed.
Also, digital notch filters were implemented and tuned to reduce the ringing
in the servos. The lock stability is strongly affected by the alignment of the
PRM and SRM (mode hopping?), so these were carefully realigned by maximizing
the peaks in the optical spectrum analyzers. After these mods, DRMI lock was
more robust, but problems remain.
- While
in lock, Osamu was able to measure OLTFs for all the servos. UGFs are 16 Hz
for MICH, 175 Hz for PRC, and 140 Hz for SRC, with 30-50 degrees of phase
margin in each loop.
- Rob
has been working with Hartmut to implement various "guided lock" schemes in
the LSC front-end code, to slow down the optics as they approach resonance.
This should make lock acquisition much faster. When used on the arms, it
should minimize the chance of sideband resonance in the arms disturbing the
lock of the central part. This will be tested with arm locking, and then
employed for the central part as well.
- Rob
has been tweaking the arm locking filters that were installed by Rana to
reduce the gain at high frequencies, which were causing ringing.
- Sasha
has been tuning up the mode cleaner WFS system, with help from Rob and Osamu.
At Rana's suggestion, he adgusted the gains on the WFS heads. Rob implemented
a digital filter to compensate for the phase delay in driving the coils on MC1
and MC3 (which use old SOS dewhitening boards with elliptical LPFs). Sasha
then re-aligned, re-diagonalized, re-adjusted the demod phases, and
re-diagonalized the servo matrix. He then was able to turn up the gains and
UGFs on the loops from ~2 Hz to ~4-5 Hz. Above the UGF, there is significant
excess noise, from 5-10 Hz. This is not understood, and work to eliminate it
is in progress.
- Bryan
continues to develop a FINESSE model of the 40m and AdvLIGO, which
incorporates TEM higher order modes, in order to develop an automated
alignment system and set tolerances on alignment in the main ifo.
Electronics and computing:
- The
length control front end CPU is nearly maxed out (59 usecs out of 61 for each
time step). Generating the dither signal and doing the dither demod is taking
up a lot of that time. Rob is exploring changes to speed up the computations.
- Bob,
Bryan, Ben and Jay completed the installation of the remaining cross connect
wiring for the aux controls of the additional LSC RFPDs (c1iscaux2). In the
process, they discovered the undocumented wiring of the in-vac PZT controls
(and whached the PZTs around for a while). This was discovered and fixed by
Jay & Ben, and the drawings were updated.
- Jay
worked on the EPICS database and screens for the c1iscaux1 and
c1iscaux2 systems, which monitor and control the LSC RFPD signals.
- Ben
swapped out the ADG333 on one of our LSC Whitening boards, and replaced it
with a MAX333A. Hopefully this will fix a problem with one of the channels
being noisier than the rest with specific gain settings.
- Two
LSC RFPDs remain to be installed: double-demod at the AP port and SPOB at the
POB port. Steve and Mike Smith ordered parts for the RFPD mount assemblies.
- Hartmut
has been tuning, and then commissioning, the remaining two LSC double-demod
RFPDs, to notch out the 33 and 166 MHz signals while maximizing response to
133 and 199 MHz. The DD RFPD at the PO is now in use (see above), and the one
at the AP will be fully commissioned soon.
- Hartmut
has been tracking down various noise sources, oscillations, offsets, and
signal degradation in the LSC electronics. Signals are now much cleaner, with
improved S/N and smaller offsets. He continues to work on reducing electronics
noise in the MICH dither signal.
- Bob
has finished looking for grounds in all of the elevated wiring trays in the
40m and will begin looking in all of the lower trays this week and next.
- Bob
wired up controls for three more mechanical shutters (POX, POY & POB) with
help from Ben.
- Jay
is working through a list of issues related to computing at the lab. He now
has saverestore working on the vacuum EPICS controls. He configured a
new linux desktop for EPICS monitoring of the vacuum system, and plans to
implement an EPICS IOC database on it for RGA monitoring/logging and other
misc tasks. He configured a linux wireless laptop for EPICS display, and is in
the process of diagnosing the long-standing problems we've been having with
our wireless reception in the lab. He's investigating the installation of a
proxy web server such as exists at the sites, to allow us to read and update
our ilog from within our martian cds network. He's planning to finally get an
ALH system working at the 40m.
- The
new MC2 oplev is very noisy, presumably due to scattered light and motion of
the distant optical table. The QPD has been moved to the nearby optical table,
and the beam will be focused to improve the resolution. Steve ordered a box to
cover the optical table to reduce stray light.
- A
TT FSS system is expected to arrive from LHO. We hope it comes with some
documentation, drawings, instructions... Rick Savage has offered to come help
install it. We are holding off on any major PSL mods (such as this) for a
while, to continue progress in lock acquisition and length control of the main
IFO.
- Never
enough scopes! We ordered two more, to keep a constant eye on the OSA's at the
SP and AP.
Lab Infrastructure and Bake oven Lab:
- Virginio
and Steve learned how to take open loop transfer functions of the STACIS
isolators, with help from the cognizant engineer Emil from TMC. They took
OLTFs for all 9 loops in the ETMY STACIS system. Only the x and z OLTFs from
the south isolator showed anomalous behavior, at 33 Hz. Work is in progress to
identify the cause of this problem and fix it. All the other STACIS systems
seems to work well, although the ITMX system can't get much more than 10 dB of
isolation.
- Rob
wrote a script to read out the Dycor RGA through a cute RS232-to-ethernet
adapter that Bob will use to put his bake oven temperature controllers on the
web. The script also checks tolerances and can set alarms. Rob and Jay will
integrate it with the EPICS system and automate it.
- Bob
has 20 Hybrid OSEMs ready for the air bake of the ceramabonded Diode boards.
- Bob
has completed the construction of a heated bell jar for Helena.
Thermal Noise Interferometer
(Libbrecht)
no report
LASTI (Ottaway)
no report
Data Analysis and Computing
(Lazzarini)
Simulation and Modeling (Bhawal)
Weekly Physics Meeting
Matt Evans gave an update of the
interferometer commissioning and operation at LLO. Hiro Yamamoto presented e2e
simulation results for signals measured before or after the Output Mode
Cleaner.
Commissioning Related
(Biplab) Prepared "summary
Statistics" files corresponding to various sets (Total no. 37) of measurements
that Luca & Keita made on Phase Camera: http://www.ligo.caltech.edu/~bbhawal/PC_modal_data/1Stat. Some of the files show that some modal
parameters for the beam-profiles varied significantly even under same "Thermal
Compensation" state on a specific date. For some sets of measurements, good
fitting could not be achieved even by considering upto 4th order
Hermite-Gaussian basis (15 modes) and it seems more modes are needed to describe
such images.
Effect of OMC on the AS signal
(Hiro) The effect of the Output
ModeCleaner (OMC) on the Antisymmetric (AS) port signal was studied by comparing
the Q-demod and I-demod signals measured before and after OMC (OMC just filters
all but 00 mode). The analysis is
still going on, but the signal after OMC seems to be preferable.
Simulation of 40m interferometer
Monica is calculating transfer
functions, L- to Power Recycling Mirror and Signal Recycling Mirror
outputs. Hiro helped her to set up
and use modeler freq.
Modeler code
Hiro modified modeler code to add
and improve a few modules for the study of OMC, and addressed an inconvenient
feature of modeler_freq.
Alfi
(Melody) Finished unit testing
and fixing bugs (found during testing) for the simpler view for FUNC_X
variables. Currently preparing the code for cvs checking and adding proper
comments for javadoc.
Data Analysis Activities (Lazzarini)
Brown:
- Attended inspiral
face to face and LSC meeting at MIT and presented final result of S2 MACHO
search.
- Continued working on
MACHO paper for review.
- Helped Scott Koranda
with final preparations for SC2004 demo.
Mendell:
Gave progress reports on the
StackSlide search for continuous gravitational waves, including comparisons with
the Hough and PowerFlux searches, and a first look at the analysis of the S3
hardware injected pulsar signals.
These reports will appear as DCC documents G040501-00.pdf and
G040502-00.pdf
Sutton:
This past week I attended the
Bursts and LSC meetings at MIT, where I presented the almost-final full-data-set
results of the LIGO-TAMA S2/DT8 bursts analysis. Since then I have been debugging the
coincidence codes and preparing the results for review and (hopefully) approval for presentation at
GWDAW. I'm also re-running the
coincidence incorporating additional TAMA data that was provided just before the
LSC meeting. The final coincidence
and efficiency numbers should be ready for review by this afternoon. Finally, I've circulated the LIGO-TAMA
GWDAW abstract for comment and approval.
Shawhan:
·
Attended the Burst Group face-to-face meeting and the
LSC Meeting at MIT
·
Read the LIGO-TAMA and LIGO-only paper drafts carefully
for comments
·
Gearing up to review Pulsar Group results to be
presented at GWDAW
Yakushin:
- Attended burst f2f
and LSC meetings in Boston;
- Submitted for LSC
approval GWDAW-9 S3 burst search talk abstract and preliminary version of
slides;
- Siong Heng from GEO
is visiting me this week to learn how to use waveburst for joint LIGO-GEO
burst analysis;
- Preparing plots of
S2 double coincidence trigger rates requested by the burst review committee.
Zanolin:
- Worked with Sergey
during the LSC to set up environment on my desktop to run single
interferometer Wave burst version 5.
- Worked on the stand
alone parameter estimation a) to verify robustness of analysis with respect to
error in signal duration, b) test the implementation of the errors.
LIGO Data Analysis System
Software Systems (Blackburn)
Pushed a pre-release version of
LDAS to LHO, LLO and TEST systems to allow further testing prior to the release
November 15. Greg Mendell has been testing the new features available for
creating RDS frames. A few minor issues have been identified and will be fixed
before the release. The pre-release also identified an issue with the email
notifications for files that are moved around frequently at LHO, which is not
seen at other sites. A quick fix to this was written up and tested here at
Caltech and then pushed to the sites for testing. The main task for us prior to
the release is to assure adequate testing of the new features associated with
generation of RDS frames.
A possible large memory leak may
be present in the new frameCPP/frameAPI code. More running will be
needed to determine the degree to which this is a memory leak versus a
tremendous startup cost for the new code. Close to a gigabyte is being used in
only a couple of hours. This is roughly an order of magnitude larger than in the
previous code base.
Wrote up documentation describing
usage and content of LDGC third party package environment.
Fixed the problem with
concatenation of AUX data within the FrAdcData structures identified when
first testing 40 meter code which makes use of this for storing data-valid array
data.
Updated ddd to version 3.3.10,
added rrdtool version 1.0.49, added ganglia version 2.5.7, updated
openssl to version 0.9.7e, and updated gnupg to version 1.2.6.
cmonClient - fixed PR 2734
by commenting out debug puts statement for diskcacheAPI directory
tree.
Documentation: updated
cmonClient client documentation and passed to librarian for cvs
inclusion.
Testing: ran ldas
System tests on version 1.2.63, updated results web page and cvs new results
html. Committed result updates to cvs.
Added options to new RDSVerify script to bypass verification, run
individual test, run as continuous loop and to dump RDS commands for
cmonClient test panel.
Updated cntlmon resource
files for test, lho and llo, created new databases and ran cmonClient
tests at lho and llo. Modify Makefiles to generate new RDS commands for
cmonClient test panel.
TCL/GLOBUS:
Completed SWIG wrapping of 2
asynchronous XIO read/write functions, globus_xio_register_read() &
globus_xio_register_write().
Working on Tcl test cases to
exercise asynchronous XIO client/server.
Four additional XIO functions are
just completed.
Globus XIO functionality summary
(latest):
- A
total of 31 functions.
- There are 12
functions not being used for our testing purposes.
- 17 functions are
completed.
- 2
asynchronous iovec functions are still buggy.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Set up GRID account
for Anand and helped to debug problem he was having logging in (lack of a FQDN
in NIS+).
- Did 4 tests of how
long it would take to stage all offline files to restore a bad disk in the
cluster. Answer: for just under
10,000 offline files (~60% full cluster filesystem) just under 5 hours, with
10 tape drives.
- Helped with
installation of new 9940B tape drives at LHO & LLO.
- Working on
rearchiving data and relabelling some poorly allocated tapes at LHO.
(Al Wilson)
- Setting up kickstart
to work with Fedora 3.
- Testing systemimager
for raid1 system setup.
- Continuing prepping
nodes for installation of second 200g disk.
(Stuart Anderson)
- Successfully
installed Fedora Core 3 on a laptop and desktop. The next step will be to try
a cluster server and node.
- Debugging hardware
issue with new large Ethernet switch at Caltech.
Livingston
(Igor Yakushin)
·
Two extra tape drives were added to L700 robot. Firmware
on all the drives was upgraded to version 1.34.408, firmware on L700 itself was
upgraded to 3.06.00.
Hanford
(Greg Mendell)
Preparing for E11, I have
incorporated new LDAS options to createRDS jobs into the createrds
drivers scripts. The options allow
the number of frames per file and the number of seconds per frame of the output
RDS frames to be specified. I am currently running tests of these options.
(Ben Johnson)
- The L700 was running
low on free tapes here, due to tape misallocation by samfs (caused by not
labelling them before restarting sam). They are presently being freed. Enough
tapes are available so that we can make it until the new tapes arrive next
week.
- I
have ordered 30, unlabeled, 9940B tapes. Greg has ordered 60. These are due
next Thursday or Friday.
- The two additional
tape drives have been added to samfs. Both appear to be working fine (in
addition to the previous four).
- Completed "burntest"
of 3511s. Had some benign scsi warnings, and one bad sector on a single 3511
disk drive. The bad sector was handled automatically by the 3511.
- node47 went offline
due to bad ram. New ram is being ordered today.
General Computing
(Wallace)
MIT:
(will report next week)
Livingston:
(Shannon)
- Finished setting up
a central log host last week.
This machine is on an internal network and is not reachable from the
outside. I will be setting up
firewall rules to restrict access to this machine from the public subnet.
- Spent
Monday-Wednesday at the NSF review.
- Discussed networking
issues with several people while in Pasadena since we could meet in person
with a whiteboard, etc. and hash out certain issues.
Hanford:
(Christine)
- Network usage can be
seen at http://www.ligo-wa.caltech.edu/~christin/mrtg/
198.129.208.1_198.129.78.122.html.
- Still contacting
network providers to see what network services are available. Nothing to report so far.
- The OS patches and
security hardening done on the main servers over the weekend has caused
problems with NIS+, e-mail and the elog mirror web site. I've had to remove most of the
security hardening in order to get services working again. I'm still fixing the elog mirror web
page.
- I'm still patching,
changing passwords and beefing up security on all the Sun workstations.
- The new Caltech ITS
VPN3000 software won't install properly on my Sys Admin laptop. I use this laptop and the VPN software
to connect to the Caltech Software site and download much of our PC
software. I've spent several
hours trying to get it working and have consulted ITS Support, but no
luck. The VPN software works fine
on other site computers.
- Modified the
firewall access list to block an IP address that was bombarding everyone with
virus email.
- At our weekly safety
meeting I reminded everyone of the rules for personal use of government
computing equipment and reminded everyone of the location of the Computer Use
Policy and other policy documentation.
- Misc. other user
support.
CIT:
(Mike)
- Control Room 3rd
floor W/B: Moved all computer equipment across the hallway into Phil Willems'
old office. This is now the new location for the control room.
- Jim Covington:
Workstation infected with a virus that required a complete rebuild. He is back
up and running.
- Phil Willems: I
loaded a new laptop for him with GC software and additional engineering
software.
- Started loading
laptop and PC workstation for loaner pool & Millikan.
- This week was mostly
dedicated to the NSF conference this included setting up the network,
printing, and user support.
(Veronica)
- LIGO: Last
minute updates/support for the NSF review. Updates to the PAC meeting
website. Working on a website for
Aspen Winter conference. Updates
to other LIGO webpages.
- LSC: Updates
to the website. Discussed with
Peter and Larry the proposed changes to the ligo.org
support/administration. A webpage
for the presentations from the last meeting.
- CaJAGWR:
Website updates/user support.
(Lisa)
- Lent a hand with the
NSF review.
- Spent quite a lot of
time working on the backup system.
Began using the new LTO drive.
- Did monthly backups.
Mail Stats 11/03 - 11/10/04
- Messages
Accepted:
34795
- Spam Rejected:
8996
- Viruses
Rejected:
1308
- False
Positives: 3
- Total Mail
Thru:
45099
(Larry)
- Working on new
maintenance contracts for Matlab. Still have a few items to get cleared
up but this should be wrapped up in the next few days. Resolved a couple of P-card issues.
Still waiting for receipts on a couple of items.
- Put in purchases for
a variety of items and working on a purchase of a new printer for the DCC.
- Assisted the DCC with
a number of different tasks. Most dealing with the documentation for the NSF.
- Worked a number of
logistical issues concerning the computer server room. Yes, the room is still
being worked on but we can see the light at the end of the tunnel. It should
be ready to test the new fire suppression system this next week.
- Resolved a cascading
problem with one of the servers. One of the E2E machines had a disk failure,
which caused a number of problems down the line causing one of the servers to
be flooded with requests (similar to a DOS attack). The E2E machine is taken off line and
all of the other offending units have been rebooted and tested. So far no
problems since the reboots.
- Resolved a couple of
minor issues with the LIGO web server. There was a naming conflict taking
place on the unit itself.
- Assisted in the setup
and takedown of items for the NSF review.
- Wrapped up some
documentation with the MIT audit. The summary should be in the DCC in next few
days.
- Resolved a couple of
printer problems and reset a number of workstations on the third floor of
Bridge.
Advanced LIGO and
Supporting R&D (Shoemaker)
Systems and Management
From: "Thomas Frey" <tfrey@ligo.caltech.edu>
Progress Period from 11.05 to
11.11
OUT
OF THE OFFICE Thursday the 11th.
·
See http://www.ligo.caltech.edu/~tfrey/index.htmlfor a complete
listing of all project related cost and schedule data.
Accomplishments:
·
Sub-system
PLANNING activities
§
Continued work on
preparing web space for posting Adv. LIGO reports. ("The Whole
Enchilada")
§
The 40-Meter
schedule remains to be completed with changes.
§
Finished work on
updated request curves inclusive of some schedule changes received on Tuesday
the 2nd.
§
Sent revised
curves to Carol for comment / distribution on Saturday the 6th.
§
Started work on
progress update with progress through October 31, 2004.
·
ROSTER
DATABASE:
§
Continued to work
with Irena to provide Barry with information regarding FTEs and
Institutions.
§
Assisting Irena
as needed on record changes.
·
COST BOOK
DATABASE:
§
Posted revised
cost data as a result of the latest revisions of last week.
Seismic Isolation
From:
Larry Jones <ljones@ligo.caltech.edu>
Advanced LIGO Seismic
Structure
SEI Structure:
I am awaiting cost and schedule
estimates from ASI in order to complete a draft rewrite of their contract.
Ken Mason has received quotes for fabricating the bulk of the parts (65%
of the total cost, by ASI's estimate) for the AdLIGO SEI BSC unit prototype,
from shops in MA. The level of these quotes confirm the August estimate by ASI,
which is considerably below ASI's latest estimate. This information is a
significant input to the study on how we should proceed.
Ken Mailand and
I talked with Brent Ekstrand of Astro Pak to get technical details of their
cleaning capabilities and recommendations. I'll be putting together a draft plan
for our cleaning pathfinder task, for the development of cleaning procedures and
quality evaluation methods to be used for parts too large to be cleaned and RGA
scanned at LIGO facilities.
Actuators:
We have told PSI
that the 12 actuator coils that failed the high-pot testing will need to be
reworked or replaced. Due to the severity of potential problems, we cannot stand
the risk of failure in service that may be caused by relaxing the
requirements.
Displacement Sensors:
ADE is proceeding with
fabricating and testing the 14 displacement sensors for the BSC prototype
structure. They have provided a quote for two calibration blocks.
Accu-Glass is proceeding with fabricating and testing the 3 feedthrough
flanges for the BSC chamber at LASTI, with 16 feedthrough fittings
each.
Seismometers:
Nothing new.
Galling/Dusting
Test:
Nothing new.
Suspension
From:
Janeen Romie <romie_j@ligo.caltech.edu>
Ian
Wilmut from RAL has joined us for 3 weeks, starting on Nov 8. We welcome him and
look forward to working with him on quad controls prototype design
issues.
Working on the quad tablecloth design.
Prepared for and
participated in the NSF Review.
Working on SUS Primavera
update.
Organizing the visit from Justin and Caroline at the end of
November. Getting travel arrangements in place for our visit to
Glasgow in January.
Created
the first draft of the Advanced LIGO safety stop design requirements document. I
have sent it to Mark for review.
From: ctorrie
<ctorrie@ligo.caltech.edu>
Advanced LIGO SUS
Weekly
report
1) Structures
Tim has been working on the lower structure
(containment truss) and is visiting Russell in Glasgow next week to discuss its
interface with the assembly rig (catcher).
We have a first resonance of the
overall structure of ~ 90 Hz in both ALGOR and ANSYS. The structure weighs ~
140kg and is lightweight around the lower three masses.
2)
Design Meeting
We have created an updated overall assembly with a drawing
tree and all of the various sections identified with LIGO numbers.
The task
summary (our schedule for the quad) was reviewed at the weekly meeting
http://www.ligo.caltech.edu/~ctorrie/QUAD_ETM/quad_etm_setup_page2.html
3)
Visits
Ian Wilmut is visiting us from RAL for 3 weeks. Mike Lloyd has
another week left of his visit from
Glasgow.
4) Design
Guidelines
To go along with the drawing guidelines by Dennis we are trying to
create a list of "rules" to ease the exchange between PRO-E and SolidWorks
files. A draft is available at http://www.ligo.caltech.edu/~ctorrie/SW/Hints.html.
From: Helena Armandula
<ahelena@ligo.caltech.edu>
Adv. LIGO "Q"
measurements
Silicate bonded a prism on a sapphire rod so "Q" measurements
can be taken.
Adv. LIGO SUS
Continued the development of indium cold
welding to attach magnets to holders and sensor flags.
Bob Taylor put
together a small vacuum to be used to melt indium on the aluminum parts to
enhance bonding.
Pre-Stabilized Laser
From:
Peter King <pking@ligo.caltech.edu>
AdvLIGO
PSL
As
Benno was here for the NSF Review, we had a discussion about some aspects of the
PSL. In particular some laser safety related concerns and the need for
having a clean room around the laser table enclosure. The latter is due to
the finding at LZH that some dust had stuck to one of the quartz rotators and
was promptly burnt by the laser. This in turn impacted the beam quality of
the laser along with the output power.
The pre-mode cleaner that was on
loan to Stanford was returned. The appearance of the packing material
caused some concern. The pre-mode cleaner will be checked
out.
Auxiliary Optics
From: Michael Smith
<smith@ligo.caltech.edu>
ADV LIGO
I am in the process
of "scrubbing" the AOS cost book with a fine, bristle brush.
Other Laboratory R&D
From: Riccardo
DeSalvo desalvo@ligo.caltech.edu
Juri
I made
the calculations for the thermal noises (coating and substrate / Brownian and
thermo elastic) for finite mirrors in the case of using a Mesa-Beam. I have only
preliminary results for the sapphire substrate because the calculations are
still running, however the results for coating and thermo elastic noises show a
noise reduction with respect to the Gaussian beam of a factor ~1.5 / ~1.7 for a
mirror radius of 16 cm. and diffraction losses of ~1ppm. I will check these
results with other calculations present in literature. I am taking measurements
for the “creep” experiment and I found a simple procedure to overcome the
strange behavior of the equilibrium position we observed sometimes (a
satisfactory explanation of this phenomenon is still
lacking).
I am
writing the short pre-thesis I have to present on December in Pisa
University.
Marco
The
final design of the “servo circuit” has been completed as the assembling of the
circuit on the board. I began to take the first measurements from the “creep
experiment”: on Saturday I and Juri have seen a second equilibrium point quite
far from the usual point.
The
creep is at 90 centigrades, it has something sticking inside generating a sort
of bistability.
Unfortunately
we cannot stop the measurement and check, we will have to proceed as
is.
For additional information about this report, contact whitcomb_s@ligo.caltech.edu