Weekly Report for
Week Ending November 12, 2004
The LIGO Executive
Committee Agenda for Monday, November
15, 2004 will be:
(Meeting time: 10:30 am Pacific Time)
- Announcements
- LSC Issues (Saulson)
- Comments on Weekly Report
- Field Change
Orders/Contingency Liens/Change Requests
- LIGO Lab Operations
- Administration
(Lindquist)
- Sites (Raab,
Zucker, Shoemaker)
- Commissioning
(Fritschel), Detector (Coyne)
- Campus Research
Facilities
- Weinstein (40 Meter)
- Libbrecht (TNI,
- Shoemaker(LASTI)
- Data Analysis and
Computing (Lazzarini)
- Advanced R&D and LIGO
II (Shoemaker)
- CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION AS NEEDED
Special Items:
Special Announcements:
Weekly Report Highlights
An NSF Review Panel conducted an annual review of the LIGO
Program November 8-10, 2004 at Caltech.
We want to thank everyone who helped the review go so smoothly. The panel was pleased with our
progress, and we should all be proud of accomplishments over the past
year. Following is their draft
summary findings presented during the exit debriefing:
NSF
Annual Review Summary
The Panel is very pleased to see the significant improvement
in strain sensitivity for the H1 Interferometer at the Hanford Observatory
since the last review. The
achieved sensitivity is within a factor of two over nearly all of science
bandwidth of the design goal.
The Panel endorses the plans for achieving the remaining
factor of two on the H1 Interferometer and looks forward to the implementation
of these improvements on the other two interferometers.
The successful implementation of the active seismic
isolation system, HEPI, on the Livingston Interferometer is a major step. In addition to demonstrating the
effectiveness of one of the key elements of the Advanced LIGO design, it will
enable 24–7 operation of the interferometer and dramatically improve the duty
cycle of the observatory.
As LIGO approaches the S5 science run planned during 2005, increased
emphasis should be placed on improving the duty factors of all three
interferometers.
The prototype thermal compensation system on the H1
interferometer should be further refined and commissioned at all the
interferometers as soon as possible, with further research continuing to allow
the interferometers to reach their full laser power design goal by the end of
science run S5.
The transition from the leadership of Gary Sanders as Deputy
Director and co–PI to Stan Whitcomb as Deputy Director and co–PI has been very
smooth. The Panel wishes Stan well
in his new role.
The Panel wishes to thank Gary Sanders for the outstanding
leadership he has provided during the critical eight years of LIGO
construction, commissioning and early science running.
While both choices for the test mass substrates, fused
silica or sapphire, appear to satisfy the Advanced LIGO science requirements,
it is very important to make a decision soon so that other design efforts can
go forward. Better is always the
enemy of good enough.
The establishment of the new position of Visiting Associate
at Caltech is a welcome step forward.
It will enable non-Caltech members of the LSC to assume line management
roles in the operation of LIGO and in the construction and operation of
Advanced LIGO.
The mechanical properties of the optical coatings for the
optical elements in LIGO remain a concern for Advanced LIGO. The Panel is pleased with the strategy
that is being followed to resolve this issue.
The Panel encourages the continuation of the investigation
of the effects of electrostatic charging of the mirror surfaces and the
mitigation of these possible effects on the performance of the Advanced LIGO
interferometers.
The active participation of the foreign collaborators in
Advanced LIGO is an essential element of the Advanced LIGO construction
project. The Panel is pleased to
note that PPARC has already awarded the funds for the suspension system and
some optical elements and that the collaborators in Germany are well along in
securing the funding for the high power lasers.
The Panel endorses the proposed revision to the LIGO
organizational chart. The
expansion of the Directorate to include the Spokesperson of the LSC and the
expansion of the Oversight Committee are very positive steps. The inclusion of the LSC under
the LIGO Directorate will bring coherence to the overall LIGO program as the
science matures and the Advanced LIGO construction project gets underway.
The requested increase in the operating budget when the
construction of Advanced LIGO is complete will have to be justified in detail
at the time when the budget is submitted.
The projections will have to be accompanied by a detailed manpower plan.
As a possible improvement to the performance of Advanced
LIGO, the Panel encourages the LIGO group to continue exploring noise-squeezing
techniques developed by outside groups and participating in the testing of
these techniques possibly at the 40 m.
The Panel endorses the plan to develop the specific security
policies for assuring the integrity of the LIGO computer systems. Patch management is an important
activity in the near term and deserves special attention.
Approval of the construction of Advanced LIGO by the
National Science Board is welcome news for the Panel. The Panel urges the LIGO collaboration
and the National Science Foundation to move forward as aggressively as possible
with the construction of this important project.
LSC Issues (Saulson)
No report.
LIGO Laboratory
Administration (Lindquist)
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Petrac)
(LSC Research Plans through Feb. 2005 and Progress Reports
through Aug. 2004)
ACIGA
- Attach. A / to PI for
sign-off / McClelland
- Attach. B / signed-off
- Attach. C / signed-off
- Attach. D / signed-off
- Attach. Z / signed-off
CEGG
- Attach. A / in sign-off by
PI (reminder processed)
- Attach. B / Rev. 1/ in
sign-off by PI (reminder processed)
- Attach. Z / in sign-off by
PI (reminder processed)
EGO
- Attach. 3 (flat beam
profile Fabry-Perot interferometer-concept) / to EGO for sign-off /
DeSalvo
Florida
GEO
- Attach. B / to PIs for
sing-off / Danzmann
- Attach. C / to PIs for
sing-off / Danzmann
- Attach. D / to PIs for
sing-off / Danzmann
- Attach. Z / to PIs for sing-off
/ Danzmann
MOU for Data Analysis
- Addendum B / in LIGO
review / Barish
Goddard
- Attach. A / to PI for
sign-off
- Attach. C / signed-off
- Attach. Z / signed-off
IAP
- Attach. C / to PI for
sign-off
- Attach. Z / to PI for
sign-off
Louisiana School of Math, Science, and Arts (LSMSA)
- MOU (LLO Outreach project)
/ in LIGO review / O. Reilly and Saulson
NAOC (Chinese Academy of Sciences)
- Draft-Attach. 1 (R&D in
flat-top beam profile technology) / in NAOC review / DeSalvo
NAOJ-TAMA
- Attach. D / signed-off
- Attach. Z / signed-off
Orsay Group
- MOU / signed-off
- Attach. No. 1 / signed-off
Rochester
- Attach. A-draft / to PI for
further inputs / Melissinos
SIOM
- Extension of Attach. 2 / in
LIGO review / Billingsley
Stanford
- Attach. A / in LIGO review
/ Barish
- Attach. B / in LIGO review
/ Barish
- Attach. C / in LIGO review
/ Barish
- Attach. D / in LIGO review
/ Barish
- Attach. Z / to PI for
sign-off / Byer
- Progress Reports for
Attach. A, B, C, and D / in process for web posting / Turner
UTBRG
- Attach. A / in LIGO review
/ Barish
- Attach. Z / in LIGO
review / Barish
VIRGO
- MOU Amendment No. 1 / in
LIGO-LSC-VIRGO review / Barish, Saulson, and Giazotto
- Attach. No. 4 / in LIGO-LSC-VIRGO
review / Barish and Lazzarini, Saulson, and Giazotto and Cavalier
- Attach. No. 5 / in
LIGO-LSC-VIRGO review / Barish and Lazzarini, Saulson, and Giazotto and
Cavalier
SITE TELECONFERENCE (Jasnow)
A site teleconference was held on Thursday, October 07,
2004. The following issues were among those discussed:
- Procedures:
(Action 124) Flowcharts for taxation need to be revised based on
information currently being provided.
- Funding:
Funding for the first half of FY 2005 for Operations has been received
from the NSF.
- Costs:
Tracking reports for the end of October have been issued.
- Contracts:
Still no contract from the Exploratorium. Caltech legal department
has approved the A&E Contract for the Outreach Building. Still
waiting for the final version from the contractor. Estimates for
mitigation efforts associated with building are sugnificantly reduced.
- Property: Ed
scheduled to be at Hanford next week.
- Audit: A
followup audit of the procedures for handling checking accounts at Hanford
was conducted. The report was relatively positive although there
were a few recommendations. To be addressed.
- Assigned Action Items:
The list of assigned actions updated through September 16, 2004 may be
found Here.
PROPERTY MANAGEMENT (Chargois)
>From: Ed Chargois <chargois_e@ligo.caltech.edu>
- Provided assistance to the
Detector Group (H. Armandula) with packing and shipping four (4) THI
substrates and five (5) 3" diameter x1" Q-substrates to Research
Electro-Optics, Boulder CO. Attn: Dale Ness. Account Number P204296.
- Provided assistance to
Caltech's Property Services with the campus audit being conducted by PWC.
- Provided assistance to
Caltech's Property Services with information concerning the General
Services Administration Vehicle Usage Report as required by the National
Science Foundation. This report was completed and forwarded to the NSF.
Attention: Mr. Kevin Rorer.
- Returned several sets
of Government Licenses Plates to the NSF. Account Number P204254.
DOCUMENT CONTROL CENTER (Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
- Attended and supported the
LSC Meeting at MIT.
- Supported the NSF Review.
- Met with Peter Saulson and
discussed options for LSC meetings. He asked me to work with a
collaborator currently preparing for the March 2006 LSC and to provide a
budget analysis showing percentage of increase between the meeting being
held here in the States vs. in Europe. He also asked me to do preliminary
investigation into feasibility of holding LSC meetings in Atlanta (rather
than Livingston) and Salt Lake City (rather than Hanford). Work has
begun on the Atlanta portion.
- Finalizing presentations
from the LSC. These should be posted by this afternoon or tomorrow
morning.
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
COST SCHEDULE CONTROL SYSTEMS (Cunningham,
Brambila, Kaufman, Salone)
>From: Esther Cunningham <esther@ligo.caltech.edu>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Working on the two new
change orders to Northrop Grumman.
- Completing boxing the
FY2003 and FY2004 closed purchase orders and set up the new files for
FY2005.
>From: Gina Salone <gsalone@ligo.caltech.edu>
>From: Florence Kaufman <fkaufman@ligo.caltech.edu>
- Completed and posted
monthly reports as of the end of October for both fiscal year 2004 and
fiscal year 2005. The reports were a little delayed this month
because the month end closing for Oracle ran into some problems, and data
for the end of October was not available until Monday November 8th.
- Submitted a Cost Transfer
to correct the allocation of ASI expenditures between the BSC and HAM
fabrication accounts. Unfortunately, I made an error on the Cost
Transfer and the adjustment was made to reduce the charges to the
BSC fabrication. I informed the Finance department
of the error and they are in the process of reversing the incorrect
adjustment and entering the proper adjustment.
Financial reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)
>From: irena@ligo.caltech.edu (Irena Petrac)
- MIT: Change Order
allocating first half of FY 2005 budget for the LIGO effort at MIT is in
preparation.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- We're still awaiting the
proposed contract documents from the Exploratorium for the 15 exhibits
that we've ordered. These are 12 for LLO and 3 for LHO. We
expect the contract documents by tomorrow.
- The draft report from the
follow-up audit conducted at LHO has been issued for review. LIGO is
preparing its response to the findings set forth in the report.
- The final version of the
architect/engineering contract with Eskew - Dumez - Ripple is due
today. It will include an appendix calling out unit prices for
construction management. LIGO will determine the amount of
construction management required at the time of selection of the
construction contractor.
- The ASI contract will be
modified to remove the prototype for the BSC chamber. This will
leave only the BSC design to be completed on the contract.
SUPPORT (Baldon, Kammerling, Lloyd)
>Irene Baldon
- Processed the paper work
for six (6) new/revised trips. There are six (6) trips to be
completed and ticketed at this time.
- Completed thirty (30) Expense
Reports and there are three (3) reports yet to be done. I continue
to contact travelers who have outstanding Expense Reports (more than one
(1) month old) to ask for their cooperation in sending me their receipts
so that these can be closed in a timely manner. Presently there are
ten (10) reports more than 30 days old. Travel Audits new policy of
accepting only original signatures seriously holds up the process of
closing reports. I have nine (9) Expenses Reports waiting for original
signatures to be sent/returned to me. [Please note that of the ten
(10) reports more than 30 days old (Travel Audit's Delinquent List) nine
have been completed and are awaiting original signatures to be sent to
me. Only one (1) traveler has not responded to my request for
his/her receipts.]
>Sharon Kammerling
- No special projects to
report.
>Dorothy Lloyd
- Processed the usual
invoices for payment. Tracked and followed up on invoice problems.
Reviewed and recorded payments processed by Esther the week of November 1.
- Initiated electronic
requisitions for change orders 36 and 37 to Northrop and change order 18
to REO. Processed payment requests.
- Placed P-card orders in
Ruth's absence.
- Jim continued with data
entry in the LIGO database and helping out in the DCC.
PROPOSALS and REPORTS (Lindquist)
Schedule of proposals and reports planned for the remainder of the calendar
year.
- November 8-10 -- NSF
Review
- December 31 -- FY 2007 -
2011 Operations Proposal including impact of Advanced LIGO funding
- April 2005 -- NSF Review of
Operations Proposal for FY 2007 - 2001
- April 2005 -- NSF Review of
Advanced LIGO Proposal Revisions as required
CHANGE CONTROL/CONTINGENCY MANAGEMENT
(Lindquist)
- D. Coyne has submitted a
change request for the ASI effort along with supporting
documentation. Modifications are proposed in response to ASI's
latest estimate increase. The change request will be distributed for
discussion during a future meeting of the Executive Committee..
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- Various personnel/payroll
/HR related work.
Quality/Safety (Tyler)
>From: Bill Tyler <tyler@ligo.caltech.edu>
No report this week.
LIGO Hanford Observatory
(LHO) and Interferometer Operations (Raab)
Summary of Commissioning
Activities at LIGO Hanford Observatory (Landry)
The weeklong engineering run E11 begins next Wednesday, Nov 17th at LHO.
Commissioning highlights from the past week are detailed below.
4K IFO
- force-to-pitch (F2P) and
torque-to-position (T2P) digital filters, recently found on the 4k and the
2k IFOs to be incorrectly defined given the data acquisition rate, have
been redefined and corrected
- WFS2 behaviour as a
function of laser power was characterized here
and here
- This report
describes power levels during full lock. More IFO/Thermal
compensation system (TCS) studies are available here,
and here.
- thumbs
up for the new, quieter TCS chiller
- the VCO was acting
up
- the 4k sideband analyzer
was saturating;
ND filters added
- multiple fixes
and improvements
were made to the 4k ISS hardware
- a WFS spare was modified
to improve noise performance (by ~5dB)
2K IFO
- The F2P filter
investigations noted above led to the realization
that piston motion on the FMY mass results in excess yaw motion.
Checking for possible electronics mis-wiring.
- 2k TCS chillers were tested. Problems
with the chiller were noted.
- New F2Ps
were designed
- WFS demod boards modified
to reduce noise
- The 2k has been steadily
improving, running Wed eve on ASPD2 and ASPD3 with a range of about
1Mpc. Next, input laser power will be ramped, and auxillary loops
will move to larger bandwidths, as was done on the 4k.
DAQ (some of the many items this week)
- Software upgrades on both
IFOs now allow the ramping of gains in filter modules
- For some time it has been
noted that requesting several (or more) test points of the LSC front end
adds noise to the gravity wave channel. Two responses this week were
to i) add a more representative CPU load monitor number (in place and
presumably reporting accurately), and ii) ensure that asking for many test
points does
not impact AS_Q
- fast ADCU's installed
on 2k and 4k in place but not hooked up
- Dataviewer was upgraded
- remote reset capabilities
were added for various frontend CPUs
Outreach (D. Ingram)
We convened our Local
Educator Network (LEN) for a productive meeting at LHO on 11/4/2004.
The LEN provides input and advice for our outreach program. We
hosted students from two WSU Tri Cities education courses for class sessions on
the mornings of 11/3 and 11/4. The course instructor is Dr. Judy
Morrison. Fifty teachers-in-training (primarily grades 1-8) participated
in the 3-hour lessons.
LIGO Livingston Observatory
(LLO) and Interferometer Operations (Zucker)
Despite continued problems with ISC110B channel hopping, HEPI commissioning is
moving forward. The fourth test mass chamber (ITMY) is now isolating with
sensor correction in the most relevant 2 of 3 degrees of freedom, and the beam
splitter is 1 for 3.
IFO commissioning took further steps in preparation for high
power; high-speed shutters and new thermal compensator interface electronics
were installed.
We also exercised a new method for tuning optical lengths;
HEPI allowed us to move the MC length to smoothly "dial in" a new
resonant frequency to match our crystal oscillators.
Tom Lucas of Lucas Productions is filming at LLO tomorrow
(Friday) and next week. Special guest stars are flying in from LA and Boston.
Livingston Outreach (Thacker)
LIGO SEC Education and Outreach Summary
- completed
LIGO SEC Project Execution Plan 1st Draft
- contacted
vendor about supplying gravity well exhibits; all looks good; awaiting
invoice
- met
w/ SUBR & LA GEAR UP Tuesday afternoon to discuss Proj Exec Plan
details;
- After
discussions w/ Steve McGuire, have tentatively identified a final total of
5 exhibits, of initial 12, to be installed at SUBR.
L1 Interferometer Commissioning (Frolov)
- MC
length was changed by 0.7mm using HEPI HAM2 actuators. The required change
is 1mm. To make this change the position sensors will have to be
repositioned to get more range, MC length changed by full amount, and dial
gauges installed.
- Found
problems with BS satellite amplifier box(had a short) and bad connection
to MC1 satellite amp box.
- ITMX
optical lever cable had to be reterminated.
- MC
EO shutter removed to accommodate the cross-connect change for the TSC
installation. The fast shutter was installed and tested. The optical table
was realigned and light levels were set for the new operation scheme. MC
was locked after the change.
- The
electronics for both TCS interfaces is installed and tested. The RS232-485
link for the rotating polarizer has just been shown to work (communication
established). The test of the rotating polarizer will be completed when we
are allowed into LVEA later today (HEPI test is underway).
HEPI commissioning (O'Reilly)
There were no valve failures this week. We have not checked
accumulator pressures that may happen tomorrow during filming.
Work continues on HEPI. ITMY is now commissioned and has
working sensor correction in the Y and Z directions, although some further
investigation is needed for the X direction. The BS has sensor correction in
the Z direction and will hopefully have X and Y by tomorrow (which is Rich
Mittelman's last day).
The HAM3 blend filters had to be reworked due to a blend
frequency that was too low. We are now taking sensor correction data for this
tank.
We continue to have problems with channel hopping, which
necessitates frequent reboots of the l1hepi1 and l1hepi2 processors.
We removed two filters from PUMP1 and examined them for
contaminants. This was in an
effort to better understand our problems with valves. We found contamination in the 25 um filter (metal debris and
a spider), but the 3 um filter was very clean. PUMP1 will go back into service
tomorrow.
Safety & Security (Riesen)
LASER SAFETY: Nothing to report
SITE SAFETY: Found no safety concerns during my weekly site
safety tour.
TRAINING: Continuing the training for control room operators
on the LSS and site security systems software and hardware.
AdL and LIGO 1 Mechanical Engineering (Spjeld)
- received
and reviewed quotes, ordered safety screens and adapter plates for two
hydraulic actuators
- looking
into history of hydraulic servo valves; attempting to eliminate continuous
troublesome valves from the system
- dissection
and analysis of pump station filters for HEPI hydraulic system: no
contaminations found on “clean” side
- working
on design suggestions for HAM chamber door removal fixture: measured
critical distances in LVEA, clean room and fork lift
- preparing
for quotes evaluation meeting for the UHV Quad Bakeout oven
- working
on assembly and modification of hardware for the Photon Calibrator Support
Shelves; aiming to complete within early next week
- working
on design requirements report for Quad Suspension Installation Tooling
CDS Software (Parameswariah)
Mike Fyffe dressed up the timing cables in the High Bay. All
processors were restarted to get them resynced up.
Updated database/installed new database for Fast shutter
controls, TCS and MC Trasmitted QPD. all channels are now wired to first cards
on l1iool0 processors. Extra cards removed.
CDS's main disk containing all CDS user accounts and the
main /cvs/cds disk filled up. Last night fixed this and will have to move this
to a bigger disk. Conlog data is now at 15GB and occupies most of the disk
space.
Frame Builder died and restarted itself again at 04:34 Hrs
this morning. Found the following
message logged in its log file: "Nov 11 04:34:25 fb1 daqd[2565]: Lost
cycles: -1056975780; shutdown".
Traced this to a spurious interrupt on the reflective memory.
LSC Aux processor - added new database records for ISCT1
Fast Shutter controls and restarted it.
Working with Rus on getting the POX PD / REFL2 PD wired up.
Working on HEPI Status screens. Fixing scripts/c
programs/medm screens/database that generate the status screens.
General Computing (Roddy)
Finished setting up a central log host last week. This
machine is on an internal network and is not reachable from the outside.
I will be setting up firewall rules to restrict access to this machine from the
public subnet. Spent Monday-Wednesday at the NSF review. Discussed networking
issues with several people while in Pasadena since we could meet in person with
a whiteboard, etc. and hash out certain issues.
LDAS/Condor Sysadmin and Burst Analysis (Yakushin)
LDAS/Condor admin:
Two extra tape drives were added to L700 robot. Firmware on
all the drives was upgraded to version 1.34.408, firmware on L700 itself was
upgraded to 3.06.00.
Data analysis:
1) Attended burst f2f and LSC meetings in Boston;
2) Submitted for LSC approval GWDAW-9 S3 burst search talk
abstract and preliminary version of slides;
3) Siong Heng from GEO is visiting me this week to learn how
to use waveburst for joint LIGO-GEO burst analysis;
4) Preparing plots of S2 double coincidence trigger rates
requested by the burst review committee.
HPLF, L1 Commissioning, and AdL Modeling (Franzen)
1) Have been trying to communicate with the people at IPG,
who are supposed to fix the broken HPLF laser. Yesterday we got to know that
the problem have been identified to a burned fiber which will be replaced this
coming Friday. If everything works out during a 40 hours full power it will be
returned to LLO next week giving the IAP visitors a chance to finish their
experiment.
2) Have been working with Richard Mittleman on HEPI BS, MC1
and MC2 sys-id and control filter design.
CDS software (Khan)
1) Fixed the bug in the Beamcentering servo code that was
crashing the servo whenever a value of 0 was entered for the averaging factor,
also enhanced the medm screen as per request from Andre.
2) Helping John and Valera on the TCS wave plate controller
interface. Established
communication between the Newport Motion Controller unit and the vme162 processor.
Detector/Technical
Support (Coyne)
CDS
See also the CDS weekly meeting minutes in the commissioning archives:
CDS Software
Rolf Bork reporting
- Alex
was at LHO past week and a half. Changes made at LHO during that time:
- Change
ASC front end for bulls eye detector. This involved removing FS5
from overall ASC gain.
- Change
to LSC to support TCS.
- Installed
new 2.2GHz in LHO4k ITM controller.
- Installed
fast ADCU on both LHO IFO. Code still needs work to port to Linux.
- New
dataviewer installed at LHO.
- Gain
ramping filter code installed on all systems.
- Continued
work on FPDP readout of ICS modules for HEPI. This software, along with
new watchdogs, will be installed next week during my visit to LLO.
- Some
of the new 2.2GHz VME processors w/3 PMC slots should arrive by tomorrow. These units are to be used in ETM
controllers and LSC. I ported the LSC software to Linux yesterday, but
have not tested it yet.
CDS Hardware
Rich Abbott reporting
- Helping
complete needed calculations for tradeoffs of performance on new LSC RFPD
- Wrote
procedure for transferring an electronics design from one location to
another with proper supporting documentation
- Completed
block diagram explaining the HEPI system
Ben Abbott
RFPD Redesign:
- Testing
of the prototype continues. Attention is now being paid to the ASI
servo matching.
- The
final gerber file has gone out to PCB Pro for manufacture. It should
be back next week when we can begin stuffing and testing.
DMT
John Zweizig
This week I have been working with Tom Evans and Alex Ivanov
on trying to understand the loss of frame data to the DMT. Considerable
progress has been made, the DMT network configuration has been cleaned up, we
found that the broadcaster packet burst parameter has to be set to a higher
value than previously used, and the network interface card for delaronde was moved
from a slow (33MHz) PCI slot to a fast one. Each of these changes should have
had a significant effect on the ability to handle higher data rates, but at
this point the data losses persist. At this point the only known difference
between the LLO system and the LHO one (that successfully handles a higher data
rate) is the operating system (Solaris 9 at LLO, Solaris 8 at LHO). I don't
think that this is a problem, but this presents a good opportunity to upgrade
the patch level of the LLO DMT machines.
I have also been creating a utility program to generate the
xml calibration files used by SenseMonitor from the calibration group data
products.
PSL
PeterKing
The problem reported last week with my PSpice model of the differential
receiver on the intensity servo was fixed by the addition of a few 100MEG resistors.
Probably for reasons owing to the model for the VAC voltage source, this
solution worked.
The power from the 10-W laser seems to have stabilised out
at just under 6 W after the latest re-alignment. Although the output
power is low, this is the most stable this particular laser has been since
delivery.
TCS quiet Chiller
Ken Mailand
I’m working on 5 laser chiller assemblies to supply the LHO
and LLO sites. I have a corrosion
test in progress using the Chloramine-T, water mixture used for the PSL laser
and TCS laser, and also the LHO site house chiller fluid, and the CIT system
chiller fluid. Brass, Aluminum, plated steel and Copper are the test metals; to
accelerate the process the fluid temps are @~135F.
AS Port Astigmatic Beam
Mike Smith
I completed the write-up of the technical note, and will
submit it to the DCC, T040204-00.
Optical Contamination Cavities
Lee Cardenas, Liyuan Zhang
OTF Lab. (W. Bridge)
The chamber has two samples, white Ceramabond, and disks of TRA-BOND #2254 color
light brown epoxy. Cavity is locked. We continue taking measurements everyday. No Change
Absorption Test Measurement prototype in standby
Scatterometer system in standby
The Inner test mass 2ITM04 fused silica mirror is in the scatterometer
enclosure.
We are waiting on the digital read out for the x-y motor travel bead.
Company contacted and they are sending it back next week.
The Quantronix 60 watt laser NO CHANGE
OTF Lab at Lauritsen ROOM 38 NO CHANGE
Cavity #3
Chamber is pumping with (6) disks of TRA-BOND #2151 color blue epoxy and (4)
disks of TRA-BOND #2902 color silver epoxy. The cavity is locked.
We'll continue taking daily measurements.
Cavity #2 in standby
The assembly of the new chamber is in progress.
40 Meter Interferometer
(Weinstein)
IFO commissioning:
- We've achieved another
important milestone in the path towards full ifo lock acquisition. Osamu, Hartmut
and Rob, working late nights, have acquired lock of the dual-recycled
Michelson (DRMI) with the 33 MHz sidebands resonant in the PRC.
- Previously, they locked
the DRMI with the carrier resonant in the PRC, but the arms cannot be
added to this configuration; now, they can (when the carrier resonates in
the arms, the arm reflectivity flips sign, bringing the carrier into
resonance in the PRC as well). After some work, lock acquisition proceeded
quickly, and relatively long locks (~ 7 minutes) were achieved. Optical
spectrum analyzers (OSAs) at the SP, PO and AP confirmed that the RF
structure was as expected with the detuned configuration: the 166 MHz
sidebands were unbalanced, with one sideband reflected to the SP and the
other transmitted to the AP. The carrier was, of course, absent at the AP.
- Details: lock MICH by
dithering the BS at 1230 Hz and using digital-demod signals at the PO and
AP; lock PRC with 33 MHz at SP, with servo sign set to lock on sidebands;
lock SRC with (166-33) MHz signal at PO.
- Rob wrote a script to
(partially) automate the lock acquisition procedure. Unfortunately, we
don't yet have an easy way to automate the detection of lock; we look at
dataviewer traces, scope traces, and OSA displays. Soon, we will implement
the SPOB photodiode, which will help a lot.
- Lock loss was associated
with spikes at the dither signal, which appear to be due to electronics
couplings at the whitening boards. This was greatly reduced by turning off
the whitening; but the boards themselves can and will be fixed. Also,
digital notch filters were implemented and tuned to reduce the ringing in
the servos. The lock stability is strongly affected by the alignment of
the PRM and SRM (mode hopping?), so these were carefully realigned by
maximizing the peaks in the optical spectrum analyzers. After these mods,
DRMI lock was more robust, but problems remain.
- While in lock, Osamu was
able to measure OLTFs for all the servos. UGFs are 16 Hz for MICH, 175 Hz
for PRC, and 140 Hz for SRC, with 30-50 degrees of phase margin in each
loop.
- Rob has been working with
Hartmut to implement various "guided lock" schemes in the LSC front-end
code, to slow down the optics as they approach resonance. This should make
lock acquisition much faster. When used on the arms, it should minimize
the chance of sideband resonance in the arms disturbing the lock of the
central part. This will be tested with arm locking, and then employed for
the central part as well.
- Rob has been tweaking the
arm locking filters that were installed by Rana to reduce the gain at high
frequencies, which were causing ringing.
- Sasha has been tuning up
the mode cleaner WFS system, with help from Rob and Osamu. At Rana's
suggestion, he adgusted the gains on the WFS heads. Rob implemented a
digital filter to compensate for the phase delay in driving the coils on
MC1 and MC3 (which use old SOS dewhitening boards with elliptical LPFs).
Sasha then re-aligned, re-diagonalized, re-adjusted the demod phases, and
re-diagonalized the servo matrix. He then was able to turn up the gains
and UGFs on the loops from ~2 Hz to ~4-5 Hz. Above the UGF, there is
significant excess noise, from 5-10 Hz. This is not understood, and work
to eliminate it is in progress.
- Bryan continues to develop
a FINESSE model of the 40m and AdvLIGO, which incorporates TEM higher
order modes, in order to develop an automated alignment system and set
tolerances on alignment in the main ifo.
Electronics and computing:
- The length control front
end CPU is nearly maxed out (59 usecs out of 61 for each time step).
Generating the dither signal and doing the dither demod is taking up a lot
of that time. Rob is exploring changes to speed up the computations.
- Bob, Bryan, Ben and Jay
completed the installation of the remaining cross connect wiring for the
aux controls of the additional LSC RFPDs (c1iscaux2). In the process, they
discovered the undocumented wiring of the in-vac PZT controls (and whached
the PZTs around for a while). This was discovered and fixed by Jay &
Ben, and the drawings were updated.
- Jay worked on the EPICS
database and screens for the c1iscaux1 and c1iscaux2 systems,
which monitor and control the LSC RFPD signals.
- Ben swapped out the ADG333
on one of our LSC Whitening boards, and replaced it with a MAX333A.
Hopefully this will fix a problem with one of the channels being noisier
than the rest with specific gain settings.
- Two LSC RFPDs remain to be
installed: double-demod at the AP port and SPOB at the POB port. Steve and
Mike Smith ordered parts for the RFPD mount assemblies.
- Hartmut has been tuning,
and then commissioning, the remaining two LSC double-demod RFPDs, to notch
out the 33 and 166 MHz signals while maximizing response to 133 and 199
MHz. The DD RFPD at the PO is now in use (see above), and the one at the
AP will be fully commissioned soon.
- Hartmut has been tracking
down various noise sources, oscillations, offsets, and signal degradation
in the LSC electronics. Signals are now much cleaner, with improved S/N
and smaller offsets. He continues to work on reducing electronics noise in
the MICH dither signal.
- Bob has finished looking
for grounds in all of the elevated wiring trays in the 40m and will begin
looking in all of the lower trays this week and next.
- Bob wired up controls for
three more mechanical shutters (POX, POY & POB) with help from Ben.
- Jay is working through a
list of issues related to computing at the lab. He now has saverestore
working on the vacuum EPICS controls. He configured a new linux desktop
for EPICS monitoring of the vacuum system, and plans to implement an EPICS
IOC database on it for RGA monitoring/logging and other misc tasks. He
configured a linux wireless laptop for EPICS display, and is in the
process of diagnosing the long-standing problems we've been having with
our wireless reception in the lab. He's investigating the installation of
a proxy web server such as exists at the sites, to allow us to read and
update our ilog from within our martian cds network. He's planning to
finally get an ALH system working at the 40m.
- The new MC2 oplev is very
noisy, presumably due to scattered light and motion of the distant optical
table. The QPD has been moved to the nearby optical table, and the beam
will be focused to improve the resolution. Steve ordered a box to cover
the optical table to reduce stray light.
- A TT FSS system is expected
to arrive from LHO. We hope it comes with some documentation, drawings,
instructions... Rick Savage has offered to come help install it. We are
holding off on any major PSL mods (such as this) for a while, to continue
progress in lock acquisition and length control of the main IFO.
- Never enough scopes! We
ordered two more, to keep a constant eye on the OSA's at the SP and AP.
Lab Infrastructure and Bake oven Lab:
- Virginio and Steve learned
how to take open loop transfer functions of the STACIS isolators, with
help from the cognizant engineer Emil from TMC. They took OLTFs for all 9
loops in the ETMY STACIS system. Only the x and z OLTFs from the south
isolator showed anomalous behavior, at 33 Hz. Work is in progress to identify
the cause of this problem and fix it. All the other STACIS systems seems
to work well, although the ITMX system can't get much more than 10 dB of
isolation.
- Rob wrote a script to read
out the Dycor RGA through a cute RS232-to-ethernet adapter that Bob will
use to put his bake oven temperature controllers on the web. The script
also checks tolerances and can set alarms. Rob and Jay will integrate it
with the EPICS system and automate it.
- Bob has 20 Hybrid OSEMs
ready for the air bake of the ceramabonded Diode boards.
- Bob has completed the
construction of a heated bell jar for Helena.
Thermal Noise Interferometer
(Libbrecht)
no report
LASTI (Ottaway)
no report
Data
Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
Weekly Physics Meeting
Matt Evans gave an update of
the interferometer commissioning and operation at LLO. Hiro Yamamoto presented e2e
simulation results for signals measured before or after the Output Mode
Cleaner.
Commissioning Related
(Biplab) Prepared "summary
Statistics" files corresponding to various sets (Total no. 37) of
measurements that Luca & Keita made on Phase Camera: http://www.ligo.caltech.edu/~bbhawal/PC_modal_data/1Stat. Some of the files show that some modal
parameters for the beam-profiles varied significantly even under same
"Thermal Compensation" state on a specific date. For some sets of
measurements, good fitting could not be achieved even by considering upto 4th
order Hermite-Gaussian basis (15 modes) and it seems more modes are needed to
describe such images.
Effect of OMC on the AS signal
(Hiro) The effect of the Output
ModeCleaner (OMC) on the Antisymmetric (AS) port signal was studied by
comparing the Q-demod and I-demod signals measured before and after OMC (OMC
just filters all but 00 mode). The
analysis is still going on, but the signal after OMC seems to be preferable.
Simulation of 40m interferometer
Monica is calculating transfer
functions, L- to Power Recycling Mirror and Signal Recycling Mirror
outputs. Hiro helped her to set up
and use modeler freq.
Modeler code
Hiro modified modeler code to
add and improve a few modules for the study of OMC, and addressed an
inconvenient feature of modeler_freq.
Alfi
(Melody) Finished unit testing
and fixing bugs (found during testing) for the simpler view for FUNC_X
variables. Currently preparing the code for cvs checking and adding proper
comments for javadoc.
Data Analysis Activities (Lazzarini)
Brown:
- Attended
inspiral face to face and LSC meeting at MIT and presented final result of
S2 MACHO search.
- Continued
working on MACHO paper for review.
- Helped
Scott Koranda with final preparations for SC2004 demo.
Mendell:
Gave progress reports on the
StackSlide search for continuous gravitational waves, including comparisons
with the Hough and PowerFlux searches, and a first look at the analysis of the
S3 hardware injected pulsar signals.
These reports will appear as DCC documents G040501-00.pdf and
G040502-00.pdf
Sutton:
This past week I attended the
Bursts and LSC meetings at MIT, where I presented the almost-final
full-data-set results of the LIGO-TAMA S2/DT8 bursts analysis. Since then I have been debugging the
coincidence codes and preparing the results for review and (hopefully) approval for presentation
at GWDAW. I'm also re-running the
coincidence incorporating additional TAMA data that was provided just before
the LSC meeting. The final
coincidence and efficiency numbers should be ready for review by this
afternoon. Finally, I've
circulated the LIGO-TAMA GWDAW abstract for comment and approval.
Shawhan:
·
Attended the Burst Group face-to-face meeting and the
LSC Meeting at MIT
·
Read the LIGO-TAMA and LIGO-only paper drafts carefully
for comments
·
Gearing up to review Pulsar Group results to be
presented at GWDAW
Yakushin:
- Attended
burst f2f and LSC meetings in Boston;
- Submitted
for LSC approval GWDAW-9 S3 burst search talk abstract and preliminary
version of slides;
- Siong
Heng from GEO is visiting me this week to learn how to use waveburst for
joint LIGO-GEO burst analysis;
- Preparing
plots of S2 double coincidence trigger rates requested by the burst review
committee.
Zanolin:
- Worked
with Sergey during the LSC to set up environment on my desktop to run
single interferometer Wave burst version 5.
- Worked
on the stand alone parameter estimation a) to verify robustness of
analysis with respect to error in signal duration, b) test the
implementation of the errors.
LIGO Data Analysis System
Software Systems (Blackburn)
Pushed a pre-release version of
LDAS to LHO, LLO and TEST systems to allow further testing prior to the release
November 15. Greg Mendell has been testing the new features available for
creating RDS frames. A few minor issues have been identified and will be fixed
before the release. The pre-release also identified an issue with the email
notifications for files that are moved around frequently at LHO, which is not
seen at other sites. A quick fix to this was written up and tested here at
Caltech and then pushed to the sites for testing. The main task for us prior to
the release is to assure adequate testing of the new features associated with
generation of RDS frames.
A possible large memory leak
may be present in the new frameCPP/frameAPI code. More running
will be needed to determine the degree to which this is a memory leak versus a
tremendous startup cost for the new code. Close to a gigabyte is being used in
only a couple of hours. This is roughly an order of magnitude larger than in
the previous code base.
Wrote up documentation
describing usage and content of LDGC third party package environment.
Fixed the problem with
concatenation of AUX data within the FrAdcData structures identified
when first testing 40 meter code which makes use of this for storing data-valid
array data.
Updated ddd to version 3.3.10,
added rrdtool version 1.0.49, added ganglia version 2.5.7, updated openssl
to version 0.9.7e, and updated gnupg to version 1.2.6.
cmonClient - fixed PR
2734 by commenting out debug puts statement for diskcacheAPI directory
tree.
Documentation: updated cmonClient
client documentation and passed to librarian for cvs inclusion.
Testing: ran ldas
System tests on version 1.2.63, updated results web page and cvs new results
html. Committed result updates to cvs.
Added options to new RDSVerify script to bypass verification, run
individual test, run as continuous loop and to dump RDS commands for cmonClient
test panel.
Updated cntlmon resource
files for test, lho and llo, created new databases and ran cmonClient
tests at lho and llo. Modify Makefiles to generate new RDS commands for cmonClient
test panel.
TCL/GLOBUS:
Completed SWIG wrapping of 2
asynchronous XIO read/write functions, globus_xio_register_read() &
globus_xio_register_write().
Working on Tcl test cases to
exercise asynchronous XIO client/server.
Four additional XIO functions
are just completed.
Globus XIO functionality
summary (latest):
- A
total of 31 functions.
- There
are 12 functions not being used for our testing purposes.
- 17
functions are completed.
- 2
asynchronous iovec functions are still buggy.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Set
up GRID account for Anand and helped to debug problem he was having
logging in (lack of a FQDN in NIS+).
- Did
4 tests of how long it would take to stage all offline files to restore a
bad disk in the cluster.
Answer: for just under 10,000 offline files (~60% full cluster
filesystem) just under 5 hours, with 10 tape drives.
- Helped
with installation of new 9940B tape drives at LHO & LLO.
- Working
on rearchiving data and relabelling some poorly allocated tapes at LHO.
(Al Wilson)
- Setting
up kickstart to work with Fedora 3.
- Testing
systemimager for raid1 system setup.
- Continuing
prepping nodes for installation of second 200g disk.
(Stuart Anderson)
- Successfully
installed Fedora Core 3 on a laptop and desktop. The next step will be to
try a cluster server and node.
- Debugging
hardware issue with new large Ethernet switch at Caltech.
Livingston
(Igor Yakushin)
·
Two extra tape drives were added to L700 robot.
Firmware on all the drives was upgraded to version 1.34.408, firmware on L700
itself was upgraded to 3.06.00.
Hanford
(Greg Mendell)
Preparing for E11, I have
incorporated new LDAS options to createRDS jobs into the createrds
drivers scripts. The options allow
the number of frames per file and the number of seconds per frame of the output
RDS frames to be specified. I am currently running tests of these options.
(Ben Johnson)
- The
L700 was running low on free tapes here, due to tape misallocation by
samfs (caused by not labelling them before restarting sam). They are
presently being freed. Enough tapes are available so that we can make it
until the new tapes arrive next week.
- I
have ordered 30, unlabeled, 9940B tapes. Greg has ordered 60. These are
due next Thursday or Friday.
- The
two additional tape drives have been added to samfs. Both appear to be
working fine (in addition to the previous four).
- Completed
"burntest" of 3511s. Had some benign scsi warnings, and one bad
sector on a single 3511 disk drive. The bad sector was handled
automatically by the 3511.
- node47
went offline due to bad ram. New ram is being ordered today.
General Computing (Wallace)
MIT:
(will report next week)
Livingston:
(Shannon)
- Finished
setting up a central log host last week. This machine is on an internal network and is not
reachable from the outside. I
will be setting up firewall rules to restrict access to this machine from
the public subnet.
- Spent
Monday-Wednesday at the NSF review.
- Discussed
networking issues with several people while in Pasadena since we could
meet in person with a whiteboard, etc. and hash out certain issues.
Hanford:
(Christine)
- Network
usage can be seen at http://www.ligo-wa.caltech.edu/~christin/mrtg/
198.129.208.1_198.129.78.122.html.
- Still
contacting network providers to see what network services are
available. Nothing to report
so far.
- The
OS patches and security hardening done on the main servers over the
weekend has caused problems with NIS+, e-mail and the elog mirror web
site. I've had to remove most
of the security hardening in order to get services working again. I'm still fixing the elog mirror
web page.
- I'm
still patching, changing passwords and beefing up security on all the Sun
workstations.
- The
new Caltech ITS VPN3000 software won't install properly on my Sys Admin
laptop. I use this laptop and
the VPN software to connect to the Caltech Software site and download much
of our PC software. I've
spent several hours trying to get it working and have consulted ITS Support,
but no luck. The VPN software
works fine on other site computers.
- Modified
the firewall access list to block an IP address that was bombarding
everyone with virus email.
- At
our weekly safety meeting I reminded everyone of the rules for personal use
of government computing equipment and reminded everyone of the location of
the Computer Use Policy and other policy documentation.
- Misc.
other user support.
CIT:
(Mike)
- Control
Room 3rd floor W/B: Moved all computer equipment across the hallway into
Phil Willems' old office. This is now the new location for the control
room.
- Jim
Covington: Workstation infected with a virus that required a complete
rebuild. He is back up and running.
- Phil
Willems: I loaded a new laptop for him with GC software and additional
engineering software.
- Started
loading laptop and PC workstation for loaner pool & Millikan.
- This
week was mostly dedicated to the NSF conference this included setting up
the network, printing, and user support.
(Veronica)
- LIGO:
Last minute updates/support for the NSF review. Updates to the PAC meeting website. Working on a website for Aspen
Winter conference. Updates to
other LIGO webpages.
- LSC:
Updates to the website.
Discussed with Peter and Larry the proposed changes to the ligo.org
support/administration. A
webpage for the presentations from the last meeting.
- CaJAGWR:
Website updates/user support.
(Lisa)
- Lent
a hand with the NSF review.
- Spent
quite a lot of time working on the backup system. Began using the new LTO drive.
- Did
monthly backups.
Mail Stats 11/03 - 11/10/04
- Messages
Accepted:
34795
- Spam
Rejected: 8996
- Viruses
Rejected: 1308
- False
Positives: 3
- Total
Mail Thru: 45099
(Larry)
- Working
on new maintenance contracts for Matlab. Still have a few items to
get cleared up but this should be wrapped up in the next few days. Resolved a couple of P-card
issues. Still waiting for receipts on a couple of items.
- Put
in purchases for a variety of items and working on a purchase of a new
printer for the DCC.
- Assisted
the DCC with a number of different tasks. Most dealing with the
documentation for the NSF.
- Worked
a number of logistical issues concerning the computer server room. Yes,
the room is still being worked on but we can see the light at the end of
the tunnel. It should be ready to test the new fire suppression system
this next week.
- Resolved
a cascading problem with one of the servers. One of the E2E machines had a
disk failure, which caused a number of problems down the line causing one
of the servers to be flooded with requests (similar to a DOS attack). The E2E machine is taken off line
and all of the other offending units have been rebooted and tested. So far
no problems since the reboots.
- Resolved
a couple of minor issues with the LIGO web server. There was a naming
conflict taking place on the unit itself.
- Assisted
in the setup and takedown of items for the NSF review.
- Wrapped
up some documentation with the MIT audit. The summary should be in the DCC
in next few days.
- Resolved
a couple of printer problems and reset a number of workstations on the
third floor of Bridge.
Advanced LIGO and
Supporting R&D (Shoemaker)
Systems and Management
From: "Thomas Frey" <tfrey@ligo.caltech.edu>
Progress Period from 11.05 to
11.11
OUT OF THE OFFICE Thursday the
11th.
o See http://www.ligo.caltech.edu/~tfrey/index.htmlfor
a complete listing of all project related cost and schedule data.
Accomplishments:
o Sub-system PLANNING
activities
o Continued work on
preparing web space for posting Adv. LIGO reports. ("The Whole
Enchilada")
o The 40-Meter
schedule remains to be completed with changes.
o Finished work on
updated request curves inclusive of some schedule changes received on Tuesday
the 2nd.
o Sent revised curves
to Carol for comment / distribution on Saturday the 6th.
o Started work on
progress update with progress through October
31, 2004.
o ROSTER DATABASE:
o Continued to work
with Irena to provide Barry with information regarding FTEs and Institutions.
o Assisting Irena as
needed on record changes.
o COST BOOK DATABASE:
o Posted revised cost
data as a result of the latest revisions of last week.
Seismic Isolation
From: Larry Jones
<ljones@ligo.caltech.edu>
Advanced LIGO Seismic Structure
SEI Structure:
I am awaiting cost and schedule estimates from ASI in order to complete a
draft rewrite of their contract.
Ken Mason has received quotes for fabricating the bulk of the parts (65% of the
total cost, by ASI's estimate) for the AdLIGO SEI BSC unit prototype, from
shops in MA. The level of these quotes confirm the August estimate by ASI, which
is considerably below ASI's latest estimate. This information is a significant
input to the study on how we should proceed.
Ken Mailand and I talked with Brent Ekstrand of Astro Pak to get technical
details of their cleaning capabilities and recommendations. I'll be putting
together a draft plan for our cleaning pathfinder task, for the development of
cleaning procedures and quality evaluation methods to be used for parts too
large to be cleaned and RGA scanned at LIGO facilities.
Actuators:
We have told PSI that the 12 actuator coils that failed the high-pot
testing will need to be reworked or replaced. Due to the severity of potential
problems, we cannot stand the risk of failure in service that may be caused by
relaxing the requirements.
Displacement Sensors:
ADE is proceeding with fabricating and testing the 14 displacement sensors
for the BSC prototype structure. They have provided a quote for two calibration
blocks.
Accu-Glass is proceeding with fabricating and testing the 3 feedthrough flanges
for the BSC chamber at LASTI, with 16 feedthrough fittings each.
Seismometers:
Nothing new.
Galling/Dusting Test:
Nothing new.
Suspension
From: Janeen Romie
<romie_j@ligo.caltech.edu>
Ian Wilmut from RAL has joined us for 3 weeks, starting on Nov 8. We welcome
him and look forward to working with him on quad controls prototype design
issues.
Working on the quad tablecloth design.
Prepared for and participated in the NSF Review.
Working on SUS Primavera update.
Organizing the visit from Justin and Caroline at the end of November. Getting
travel arrangements in place for our visit to Glasgow
in January.
Created the first draft of the Advanced LIGO safety stop design requirements
document. I have sent it to Mark for review.
From: ctorrie <ctorrie@ligo.caltech.edu>
Advanced LIGO SUS
Weekly report
1) Structures
Tim has been working on the lower structure (containment truss) and is visiting
Russell in Glasgow next week to discuss its interface with the assembly rig
(catcher).
We have a first resonance of the overall structure of ~ 90 Hz in both ALGOR and
ANSYS. The structure weighs ~ 140kg and is lightweight around the lower three
masses.
2)
Design Meeting
We have created an updated overall assembly with a drawing tree and all of the
various sections identified with LIGO numbers.
The task summary (our schedule for the quad) was reviewed at the weekly meeting
http://www.ligo.caltech.edu/~ctorrie/QUAD_ETM/quad_etm_setup_page2.html
3) Visits
Ian Wilmut is visiting us from RAL for 3 weeks. Mike Lloyd has another week
left of his visit from Glasgow.
4) Design Guidelines
To go along with the drawing guidelines by Dennis we are trying to create a
list of "rules" to ease the exchange between PRO-E and SolidWorks
files. A draft is available at http://www.ligo.caltech.edu/~ctorrie/SW/Hints.html.
From: Helena Armandula
<ahelena@ligo.caltech.edu>
Adv. LIGO "Q" measurements
Silicate bonded a prism on a sapphire rod so "Q" measurements can be
taken.
Adv. LIGO SUS
Continued the development of indium cold welding to attach magnets to holders
and sensor flags.
Bob Taylor put together a small vacuum to be used to melt indium on the
aluminum parts to enhance bonding.
Pre-Stabilized Laser
From:
Peter King <pking@ligo.caltech.edu>
AdvLIGO PSL
As Benno was here for the NSF Review, we had a discussion about some aspects of
the PSL. In particular some laser safety related concerns and the need
for having a clean room around the laser table enclosure. The latter is
due to the finding at LZH that some dust had stuck to one of the quartz
rotators and was promptly burnt by the laser. This in turn impacted the
beam quality of the laser along with the output power.
The pre-mode cleaner that was on loan to Stanford was returned. The
appearance of the packing material caused some concern. The pre-mode
cleaner will be checked out.
Auxiliary Optics
From: Michael Smith
<smith@ligo.caltech.edu>
ADV LIGO
I am in the process of "scrubbing" the AOS cost book with a fine,
bristle brush.
Other Laboratory R&D
From:
Riccardo DeSalvo desalvo@ligo.caltech.edu
Juri
I
made the calculations for the thermal noises (coating and substrate / Brownian
and thermo elastic) for finite mirrors in the case of using a Mesa-Beam. I have
only preliminary results for the sapphire substrate because the calculations
are still running, however the results for coating and thermo elastic noises
show a noise reduction with respect to the Gaussian beam of a factor ~1.5 /
~1.7 for a mirror radius of 16 cm. and diffraction losses of ~1ppm. I will
check these results with other calculations present in literature. I am taking
measurements for the “creep” experiment and I found a simple procedure to
overcome the strange behavior of the equilibrium position we observed sometimes
(a satisfactory explanation of this phenomenon is still lacking).
I
am writing the short pre-thesis I have to present on December in Pisa
University.
Marco
The
final design of the “servo circuit” has been completed as the assembling of the
circuit on the board. I began to take the first measurements from the “creep
experiment”: on Saturday I and Juri have seen a second equilibrium point quite
far from the usual point.
The
creep is at 90 centigrades, it has something sticking inside generating a sort
of bistability.
Unfortunately
we cannot stop the measurement and check, we will have to proceed as is.
For additional information about this report, contact whitcomb_s@ligo.caltech.edu