Weekly Report for Week Ending November 4, 2004


 Exec. Comm. Agenda

Highlights

LSC

Administration

Hanford Observatory

Livingston Observatory

MIT

Caltech

Detector

40 Meter

TNI

LASTI

Data Analysis

Adv. LIGO Development

Past Weekly Reports


The LIGO Executive Committee is cancelled because of the NSF Review.


Special Announcements:

 


Weekly Report Highlights
 


LSC Issues (Saulson)


no report


LIGO Laboratory Administration (Lindquist)


STATUS OF LSC MOUs (Petrac)

(LSC Research Plans through February 2005 and Progress Reports through August 2004)

CEGG

EGO

Florida

GEO

MOU for Data Analysis

Goddard

IAP

Louisiana School of Math, Science, and Arts (LSMSA)

NAOC (Chinese Academy of Sciences)

NAOJ-TAMA

Rochester

SIOM

UTBRG

Orsay Group

VIRGO



SITE TELECONFERENCE (Jasnow)

A site teleconference was held on Thursday, November 4, 2004.  The following issues were among those discussed:


PROPERTY MANAGEMENT (Chargois)

>From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

>From: Cleveland Mak <mak_c@ligo.caltech.edu>


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman, Salone)

>From: Esther Cunningham <esther@ligo.caltech.edu>

>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

>From: Gina Salone <gsalone@ligo.caltech.edu>

>From: Florence Kaufman <fkaufman@ligo.caltech.edu>


Financial reports can be found at: http://docuserv.ligo.caltech.edu/~fireport. (For passwords contact Florence)

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

>From: irena@ligo.caltech.edu (Irena Petrac)

>From: Ed Jasnow <jasnow@ligo.caltech.edu>


SUPPORT (Baldon, Kammerling, Lloyd)

>Irene Baldon

>Sharon Kammerling

>Dorothy Lloyd


PROPOSALS and REPORTS (Lindquist)

Schedule of proposals and reports planned for the remainder of the calendar year.

CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)

HUMAN RESOURCES (Akutagawa)

>From: Cindy Akutagawa <cindy@ligo.caltech.edu>

Quality/Safety (Tyler)

>From: Bill Tyler <tyler@ligo.caltech.edu>

Nothing significant to report for QA and Safety this week.

 

.


LIGO Hanford Observatory (LHO) and Interferometer Operations (Raab)



 Summary of Commissioning Activities at LIGO Hanford Observatory  (compiled by L.Matone)

These have been the highlights of the week:

H2

During the mini-run of last weekend, the AS2_Q channel was found to be contaminated by a 10Hz oscillation that would come and go. This was traced to a faulty whitening board which was replaced here.

The new quieter TCS chillers have been installed (see elog) and the new TCS interface board was installed on the X-arm (see elog).

The digital filters (F2Ps) that decouple the force-to-pitch coupling of the large optics were found to be incorrectly installed (on H1 as well). This seems to be a remnant of the switchover from the 2kHz system to the 16kHz one. At the same time, if these filters are turned off on H2's BS, the stability of the arm powers is enhanced (see elog).

H2 is currently undergoing LSC/ASC code upgrades, features like gain ramping and a common TCS servo replacing WFS5's  filter bank are being added.

H1

The ISS photodiodes and servo have been installed, testing is underway (see elog)

There was an attempt to run H1 at 4W but problems using the Bulls eye to feedback differential TCS heating were found (see elog). At the same time, WFS2's response to the angular degrees of freedom needs to be re-visited (see elog).

Commissioning of the u-seismic feedback system has begun (see elog). And the new OMC has been installed and more observations have been made (see elog).

The new F2Ps and T2Ps have been generated and have been installed on ITMx. An automated script has been created to minimize the Pos-to-Angle coupling.

 


LIGO Livingston Observatory (LLO) and Interferometer Operations (Zucker)


Big news this week; fixing that errant filter on the beamsplitter optical lever has indeed restored L1 to about the S3 noise level (Hooray!). We're now concentrating on the backlog of sensing and control upgrades to permit higher-power operation, on improving the SNR and bandwidth of auxiliary length controls, and tweaking up the WFS system. We are also continuing to knock off remaining punchlist items from the EMC retrofit and HEPI installation.

HEPI commissioning is progressing steadily. Servo valve and accumulator problems have thankfully tapered off, but the ADC "channel hopping" issue remains a plague. Rolf Bork has developed a possible workaround which should be ready to try week of the 15th; in the meantime, the bootfest never stops.

This week Rich Mittleman is down from MIT helping out on HEPI, and Vuk Mandic is out from Caltech working on LOS filter updates. Next week we will host Rana Adhikari and Matt Evans from CIT and Jon Allen from MIT.

Livingston Outreach (MZ and John Thacker)
---------------------------------------------------------------------
Wednesday we had a full-day workshop to kick off the  design of the LIGO Science Education Center at LLO with our architects Eskew+Dumez+Ripple. We covered a lot of ground and agreed to a very aggressive design schedule.

John adds:
11/02/04 Presented LIGO science material and discussed Science Education Center at regional GEAR UP conference in Biloxi, MS;

11/03/04 participated in discussions with A&E contractor;

11/04/04 Conducted site visit by Baton Rouge Lutheran school. 21 students participated in hands-on science activities related to resonance and EM waves.

Currently developing 1st draft of LIGO SEC Project Execution Plan.


L1 Interferometer Commissioning (Frolov)
----------------------------------------------------------------------
- BS oplev filtering improved the noise to the S3 level.
- installed the POX PD. The PD was tested using the POB read out path.
-  measured the couplings and noise contribution from optical lever to the asq.
- setting up for the MC length change to switch to the low noise oscillator.

L1 Commissioning (Gretarsson)
---------------------------------------------------------------------
The Beam Centering (BC) servo has been exercised.  The /Spiricon/Labview/ActiveX/Epics software works reliably and the WFS4, QPD's, WFS2 and WFS3 do their job of moving the interferometer in response to the servo'd input beam.  We haven't yet set the gains correctly so the servo still wanders and breaks the lock eventually. Ash has written a upgrade to the Epics code that allows the servo to act on more than one optic at a time. This makes it a bit more flexible, for example it can be used to get pure translation by feeding back to both MMT1 and MMT3 or the servo could be used for alignment of other cavities.


HEPI commissioning (O'Reilly)
---------------------------------------------------------------------
Work continues on HEPI commissioning. We continue to have problems with channel hopping in the 110b's. This led us to believe we had failed valves on the BS chamber when we probably did not. It also occasionally trips off a working chamber. There is no good diagnostic, but one is promised soon.

On the 28th we moved ETMY in an effort to remove an rZ offset of ~312K counts. The move was partially successful in that the offset required to align the tank, with zero bias on the suspension sliders is now -100K counts. More importantly the drive being sent to the actuators is only a couple of thousand counts, so there should be no danger of using dynamic range due to the offset. After the ETMY move there was a strong resonance in the vertical (Z) mode at 52 Hz. This appears to be a 50Hz resonance which moved. The notch frequency and depth were changed.

We are slowly removing offsets that make no physical sense (basically everything except rZ), from all chambers.

ITMY now has a blended controller thanks to Shyang Wen and Rich Mittelman. We have also taken new data both to fill in gaps in the BS and ITMY and to account for the fact that we found two bad geophones on these chambers.

The GS13 witness sensors were removed from ETMY and are now installed on ITMY for the purposes of obtaining sensor correction data.

There are now blended controllers on HAM1, HAM2 and HAM3. Sensor correction data is being taken for HAM3.

We continue to monitor accumulator pressures on a weekly basis. This week for the first time there seemed to have been no significant loss of pressure.

A new oil-free compressor has been ordered by Allen Sibley. This is to allow us to move the valve test stand out of the machine shop. We are concerned that metallic debris is contaminating the valves.


Safety & security (Riesen)
---------------------------------------------------------------------

LASER SAFETY

Completed logic software fix for the functional inconsistency between laser tables in the LVEA. Replaced a defective LSS controller relay board. Activated the 4 LVEA laser tables for closing the PSL internal shutter if a table has a forced door condition (non-swipe entrance).

##MZ NOTE: Re-enabling the PSL shutter requires LSO or management authorization. REMEMBER TO SWIPE IN BEFORE YOU OPEN THAT DOOR!##

Submitted scope-of-work instructions and request for price quote to Excel for laser safety system upgrades concerning the transmission monitors and the photon calibration systems for both end stations. The 4 LVEA laser tables are now unlocked.  If locking a table door is deemed necessary, the keys are in the control room key locker.

SITE SAFETY

Found no safety concerns during my weekly site safety tour. Sightings of rodent and reptile pests have increased in the LVEA and the end station buildings.  I have increased rodent traps 3 fold in the LVEA and end station buildings. This appears to be paying off.

TRAINING

Started training control room operators on the LSS software and hardware, plus a refresher course on the site security system.

AdL and LIGO 1 Mechanical Engineering (Spjeld)
---------------------------------------------------------------------
- received hardware for Photon Calibrator shelf, working on assembly

- received last quotes for UHV Quad Cleaning Oven, working on review report

- brief meeting with Mike Zucker and Rusyl Wooley on HAM door remove fixture

- working on design requirement report for the Quad Suspension install. fixtures

CDS Software (Parameswariah)
---------------------------------------------------------------------
Chethan is away on travel.  See reports by Khan and Yakushin.

General Computing (Roddy)
---------------------------------------------------------------------
In the process of setting up 3 new computers and 1 existing computer for various network functions.  These machines will replace services that some machines are currently offering (DHCP, DNS, etc.) in order to upgrade some services and fix stability problems with others (DHCP). Also, one of these machines will be a dedicated IDS and netflow collector.

Working with Andri on some workstation issues.

Troubleshooting one machine which I think has a failing hard drive. SuSE Linux definitely seems to be a stable and complete linux distribution. I am setting up the above computers with SuSE 9.2 in both 32 and 64 bit flavors.  So far it is working well for general tasks.  I will be standardizing the LLO GC linux computers to run SuSE in the future barring some technical problem yet to be discovered.

Ordered a laptop to replace a dying laptop.  Stay away from Sony Vaios. They have not been very reliable at all and tend to fall apart after a year or so of use.

Various other items, such as planning for the NSF review, Pcard paperwork, etc.

Data analysis (Yakushin)
---------------------------------------------------------------------
LDAS/Condor admin:

1) The file system is upgraded both at LDAS and CDS side. Together with Chethan we applied SAN, SAM-QFS and Solaris patches to our systems.
2) Controllers in 3510 were replaced.
3) The new servers are mounted by Excel.
4) The fiber between FC switch and L700 is put in place by Excel.

Data analysis:

1) Generated and processed LIGO-GEO triggers. The standard set of plots
can be found here:
http://www.ligo-la.caltech.edu/~igor/MDC/waveburst_on_S3_playground.html
(the new burst group password should be used).
2) Participated in S2 paper review telecon on Tuesday and Wednesday.
3) Redrawing injected vs detected hrss plot for S2 paper.
4) Processing S3 hardware injections with waveburst.


HPLF, L1 Commissioning, and AdL Modeling (Franzen)
---------------------------------------------------------------------
1) Unfortunately the IPG laser broke down again during last week. It has been returned to the manufactorer for inspection and repair. The IAP visitors are waiting for a diagnosis in order to decide on staying at LLO or to go home and come back at a later date.

2) Have been working with Rich Mittleman with HEPI ITMY and BS SYS-ID. This had to be redone since two geophones had problems and where exchanged. The data quality is now more or less OK and we can go on to the next step.


CDS software (Khan)
---------------------------------------------------------------------
1) Implemented the Beam centering servo with additions that let you position any of the large optics besides MMT1 and also allow you to bring beam from any camera.

2) Fixing the medm status screens and database for the IOO WFS status monitoring.

3) General CDS maintenance.


Detector/Technical Support (Coyne)



 CDS

see also the CDS weekly meeting minutes in the commissioning archives:

CDS Software

Rolf Bork reporting

- Had a failure of a Pentek module in the ETMX controller at the 40m lab (all channels read over 2000 counts with no input). I swapped this out with a Pentek from my development system.

 

- Alex at LHO this week installing latest software, along with software for useismic control. We are encountering some problems with the small optics controller software on the 2K system, though it works fine on the 4k at LHO and LLO. We are continuing to investigate this.

 

- I have software running which reads data from ICS110B ADC modules over its Front Panel Data Port (FPDP) instead of the VME bus. I am waiting for another module to arrive from LHO to test this with 2 ICS modules. If this works out, I would like to travel back to LLO the week of Nov. 15 and install it into HEPI. At the same time, I would install the new Hepi watchdog software and software to handle a second STS-2 at the corner station.

 

- Just received a new software request from S. Ballmer to handle a bull's eye detector. Alex will code this up at LHO and test it there with Stefan.

CDS Hardware

Rich Abbott reporting

1.  Did measurements on the diodes used in the RFPD for series resistance and capacitance.  6 units were tested.

2.  Helped understand some of the remaining tradeoffs on the RFPD design

3.  Began writing documents on common LIGO procedures such as, transferring a piece of electrical hardware from a remote design facility to the sites

 

Jay Heefner reporting

 

Fiber Optic Timing Link (Sander)

=============================

- More phase noise measurements are in progress

 

Anti-Image Filters for Low Noise DACs (Todd)

=================================

- 12 more are being fab'd.

 

40 Meter (Jay, Ben)

===================================

- LSC drawings have been updated to show the new PD numbering that matches the software.

- A laptop has been converted to Linux and loaded with linux epics tools.

 

LSC PD Redesign (Ben)

==================================

- Prototype testing continues. The layout of the production board will be changed due to things learned in testing. Tests should be completed this week.

 

TCS Chiller (Mohana)

===================================

- There will be a discussion at today's CDS meeting to answer some questions before a new interface board is completed.

- Right now the plan is to only have one system operational for the engineering run. The other systems will be operational for the science run.

 

ISS (Flavio)

==================================

- 2 more boards are stuffed. Dave is assembling the boxes.

 

Elect Shop (Todd)

=====================================

- 4 Bull's eye PDs shipped. 1 more being tuned. Another board has been stuffed minus the tuning components and will be held in reserve.

-GPS clock driver test stand is being reassembled.

- A list of parts for common stock has been compiled and approved for purchase. The parts will be ordered soon.

TCS quiet chiller

Ken Mailand, Phil Willems

Phil Willems, approved the LHO site laser chiller performance. Ken is gathering parts for assembly at CIT of 5 more mechanical units.

PSL

PeterKing

The fabricated high power photodetectors needed to be disassembled as I had forgotten to install an insulator between the voltage regulators and a mounting nut.  Otherwise the mechanical assembly went well.  Now the 10-W laser is undergoing some tweaking.

 

    During testing of the production intensity stabilisation servo, there was some concern about the discrepancy between the "theoretical" step response and the measured step response of two low-pass filters used.  The "theoretical" data suggested a rise time of approximately 5 seconds whereas I had measured about one-tenth that value.  I modelled the section in PSpice and obtained a value consistent the experimental value, although the agreement is still not great (505 ms vs. 535 ms).

 

I also tried to model the differential input stage that accepts the output of the photodetector.  This required adapting the vendor-supplied Spice model for the THS4151.  The input stage was then modeled but the model prediction differed from the measured result which I think is due to a problem with the Spice model of the AD829J.

AS Port Astigmatic Beam

Mike Smith

I have completed the calculation of the recycling cavity eigenmodes using actual installed radii of curvatures for the ITMx, ITMy, RM, and BS. I analyzed two cases: 1) equal heating of both ITMs: the in-line ITM is heated until the stable cavity eigenmode matches the IFO carrier beam size; with this same heating of the reflected ITM, the reflected cavity is unstable, and supports a mode that is a replica of the carrier beam. Minimum ellipticities at the BS of around 20% are obtained for all three IFOs under these conditions, 2) optimium differential heating of both ITMs; the transmitted and reflected cavities are stable with their eigenmodes matched to the IFO carrier spot size. Minimum ellipticities at the BS of around 20% are also obtained for all three IFOs under these conditions. The 30-70 mW absorbed power by the ITM to create the conditions in the analysis are quantitatively similar to the observed data with the recent TCS experiments at LHO.

 

There is still unexplained evidence that the output beam exhibits ellipticity and axis rotation in the absence of the recycling cavity being locked.

 

A discussion with Garilynn and Hiro revealed that the two different published radii of curvature of the BS HR resulted from a different interpretation of the phase map data taken with the BS at 45 deg and at normal incidence. Hiro is reviewing the procedure.

Optical Contamination Cavities

Lee Cardenas, Liyuan Zhang

OTF Lab. (W. Bridge)
The chamber has two samples, white Ceramabond, and disks of TRA-BOND #2254
color light brown epoxy.  Cavity is locked.
We continue taking measurements everyday.  No Change


Absorption Test Measurement prototype   in standby

Scatterometer system  in standby
The Inner test mass 2ITM04 fused silica mirror is in the scatterometer enclosure.
We had an incident with our digital read out for the x-y motor travel bead.
The digital unit memory went out and all our previous information got lost.
I sent the unit to Sony manufacturing to be checked and it has a bad CPU board.
The board has to be replaced.  It will take a week before the unit will comeback.

The Quantronix 60 watt laser  No change

OTF Lab at Lauritsen ROOM 38   No Change
Cavity #3
Chamber is pumping with (6) disks of TRA-BOND #2151 color blue epoxy and
 (4) disks of TRA-BOND #2902 color silver epoxy.  The cavity is locked.
it has been already 17 weeks of testing and we'll continue taking daily measurements.

Cavity #2  in standby
Mounting all the components and preparing the new chamber is still in progress.

 


 

40 Meter Interferometer (Weinstein)



Thermal Noise Interferometer (Libbrecht)


no report


LASTI (Ottaway)


no report


Data Analysis and Computing (Lazzarini)


 Simulation and Modeling (Bhawal)
Weekly Physics Meeting
--------------------------------
Matt Evans described the procedure adopted for successful locking of Virgo and its advantages and disadvantages and implication on adopting a good procedure of locking for Advanced LIGO.

Commissioning Related
--------------------------
(Biplab) Started posting data for mode-decomposition of the phase camera images taken at the dark port of H1 interferometer by Luca and Keita. Analysis-Files corresponding to various sets of measurements are available here:
      http://www.ligo.caltech.edu/~bbhawal/PC_modal_data/
 [Mode decomposition is performed up to both 3rd and 4th order of Hermite- Gauss modes (astigmatic basis). So, the images are fitted with 33 parameters (for 4th order). Please read the '1README' file first.]

(Matt) Worked on scripting tools (ezsine, ezsfft, ezrms, ezwait, ...) for use in IFO automation, diagnosis and commissioning.

Beam splitter phasemap
-----------------------------------------
(Hiro) There was a meeting on Nov.1st afternoon, discussing the phasemap data of LIGO beam splitter mirror. GariLynn, Mike Smith, Bill Kells and Hiro attended. Gari explained how measurements were done, and why there are two ROC numbers in Gari's as-built mirror home page. One is based on the 0 angle incident measurements and the other is 45 degree incident measurements. Both have issues to be considered, and Gari quoted an analysis done by a SURF student. Hiro is looking into the analysis to obtain a more reliable phasemaps and curvatures.

Simulation of 40m interferometer
------------------------------------------------
(Monica) Implementation of all degrees of freedom in the 40m/advLIGO package. Tests of transfer functions with both the configuration with EOMs in series and in parallel: in particular, simulation of the transfer function between L_ (differential signal) and the dark port signal demodulated at 166 MHz to compare it to the same transfer function simulated with Twiddle.

Hardware 128 bit floating on SUN machine
--------------------------------------------------
(Hiro) Stuart forwarded a mail from a SUN engineer who is interested in knowing why LIGO simulation needs quad precision float. I replied to him outlining the demand of huge dynamic range of mass motion (using layman's words). The team was interested in seeing the code, and the location of the modeler source code and how to install were explained to him. If the quad precision float is supported by hardware, that simplifies the modeling of adv.LIGO.

Alfi
--------------
(Melody) Continuing modifications to display the FUNC_X variables in a friendlier user interface. Currently working on the simple view which parses the C++ code in the MemberDecl primitive setting.  Working on assigning default values for inherited nodes and functional consistency. Currently unit testing the code.

Data Analysis Activities (Lazzarini)

Creighton:
Helped Naoki Seto (tapir) develop a technique for measuring distances to gravitational pulsars through ``timing paralax''.

Shawhan:
I have been studying the H2 veto being proposed for the S3 burst search, in particular to properly calculate the effective deadtime for different choices of veto threshold and simulated signals with different durations. I also have been working with Erik Katsavounidis to organize the Burst Group face-to-face meeting this Friday and preparing for the LSC Meeting.

Yakushin:
1) Generated and processed LIGO-GEO triggers. The standard set of plots 
 can be found here:
http://www.ligo-la.caltech.edu/~igor/MDC/waveburst_on_S3_playground.html
(the new burst group password should be used).
2) Participated in S2 paper review telecon on Tuesday and Wednesday.
3) Redrawing injected vs detected hrss plot for S2 paper.
4) Processing S3 hardware injections with waveburst.

Lazzarini;
Over time I had amassed a body of Mathematica code used to perform post-processing of the stochastic search measurements. I invested the time to completely port the analysis into matlab so others in the stochastic group can use the tool and maybe improve on it.

LIGO Data Analysis System

Software Systems (Maros for Blackburn)
[LDAS]:
The focus for this week has been on stabilizing code in preparation for the code freeze this Friday. The list of open problem reports scheduled for closure for ldas-1.3.0 was reviewed and several of the problem reports have been scheduled for the ldas-1.4.0 release.

The cmonClient has been modified to display a directory tree of the diskcache mount points.

The diskcacheAPI has been modified to detect 'lost' threads (PR#2730). Although this does not provide a solution to the problem, it does provide an audit trail. Also, several members are working with UWM to understand the slow loop time observed at UWM using lsync (a standalone application based on the diskcacheAPI). Several discoveries were made. The LD_ASSUME_KERNEL=2.2.5 is needed and a custom version of tcl which has threads enabled must be used. Work is now being done at CIT to try and reproduce the large number of directories to determine if this is the cause of the slowing.

Work to support searching for and reading of FrStatData structures from a frame file via frameCPP is nearly complete.

Testing continues as the system tests were run against ldas-1.2.55. This revealed one error in the frameAPI library which was fixed early in the week. The new RDSVerify script can now be executed as part of a 'make system-check' directive. It is currently being modified to also run as a loop test.

The performance of the LDAS on ldas-dev was observed to be slower than usual. After the dmt tables and indexes were reorganized via db2 utilities, the normal performance returned.

Documentation is being reviewed and updated.

[Tcl/Globus]:

Work continues on the globus_xio_register_read() and globus_xio_register_write() functions. These two calls are more complex than any others that have been SWIG wrapped to date. This is due to the asynchronous nature of the calls. Work is estimated to be completed by the end of next week on these two calls.

ROBOdoc has been chosen as the documentation tool to use. It will be installed on the system late this week or early next.

Hardware Systems (Anderson)
Caltech
-------
(Dan Kozak)
* Spent time with Hari learning about Grid/Condor/LDR/etc. stuff.  As a test that I'd learned something, republished some files that had had their containing directory renamed and added 2 grid users to the cluster.
* Worked with Sun on the problem (at CIT) with SCSI timeouts and retryable errors on two of our 3510s.  Sun engineer Jeff Reed suggested setting ssd_max_throttle lower than the default 256 (we finally settled on 32) and this seems to have addressed the problem.  The line,
        set ssd:ssd_max_throttle = 32
  was added to /etc/system onldas-archive and LLO's gateway & dataserver (since they were being rebooted anyway).
* Assisted in the big LLO Sol/SAN/SAM-QFS upgrade.
* Worked with Stuart to fix the incorrect cache mode (writethrough rather than writebehind) on 3 T3s at LLO.
* Gave some assistance to Ben at LHO in setting up his new /archive and new tape drives.

(Al Wilson)
* Replaced disk drives in datacache 2,7.
* Doing prep work for the second 200g hard drive installed in the nodes
* working on modifying HTML code in BB for a more covenant display.

(Stuart Anderson)
* Installed and tested new CISCO switch which came with the wrong version of the software pre-installed.
* Helped with LLO Solaris/SAN/SAM/QFS upgrade.
* Installed Ganglia on LDAS-TEST cluster and worked with Brian Moe at UWM to get all the Lab clusters to appear on the LSC Data Grid page as separate clusters.
* Worked with Dan to solve a SCSI timeout problem after our recent Solaris/SAN/SAM upgrade.
* Picked up a few GRID related tasks.

MIT
---
(Keith Bayer)
* Installing 1U servers into racks.

Livingston
----------
(Igor Yakushin)
* The file system is upgradedboth at LDAS and CDS side. Together with Chethan we applied SAN, SAM-QFS and Solaris patches to our systems.
* Controllers in 3510 were replaced.
* The new servers are mounted by Excel.
* The fiber between FC switch and L700 is put in place by Excel.

Hanford
-------
(Ben Johnson)
* Most of my time has been spent working on the LSCfileAdd utility this past week. 90% of the work involves checking of command line parameters in various combinations to make sure the metadata entries are kosher.
* Created the /archive filesystem on the 5 3511's at LHO. I can copy and read files to/from gateway and dataserver via /archive, and said files can pass FrCheck.
* 15 nodes how have an additional hard drive. The larger part of the cluster will have to wait until after the LSC meeting, in case folks want to perform last minute analyses at LHO.
* All tape drives are are rev. 1.34.408 and the additional two are recognized by Solaris (cfgadm -c configure cX:WWN).

General Computing (Wallace)
MIT:
(Keith)
-Prep work for LSC conference
-Getting visitors internet access
-Testing out new Dell projector
-Investigating dataviewer problems to LHO
-Investigating new wireless access method via 'authpf'

Livingston:
(Shannon)
-In the process of settingup 3 new computers and 1 existing computer for various network functions.  These machines will replace services that some machines are currently offering (DHCP, DNS, etc.) in order to upgrade some services and fix stability problems with others (DHCP). Also, one of these machines will be a dedicated IDS and netflow collector.
-Working with Andri on some workstation issues.
-Troubleshooting onemachine which I think has a failing hard drive. SuSE Linux definitely seems to be a stable and complete linux distribution.  I am setting up the above computers with SuSE 9.2 in both 32 and 64 bit flavors.  So far it is working well for general tasks.  I will be standardizing the LLO GC linux computers to run SuSE in the future barring some technical problem as yet to be discovered. Ordered a laptop to replace a dying laptop.  Stay away from Sony Vaios. They have not been very reliable at all and tend to fall apart after a year or so of use.
-Various other items, such as planning for the NSF review, Pcard paperwork, etc.

Hanford:
(Christine)
- Network usage can be seen at
http://www.ligo-wa.caltech.edu/~christin/mrtg/ 198.129.208.1_198.129.78.122.html
- Contacted a couple other networkproviders for quotes on network service.  Our current network provider will be changing their service next year, so it is a good time to look again at other services.
- Received a quote to buy our own site licenses for AutoCAD as opposed to buying licenses from Caltech ITS.  It's too expensive to buy our own, Caltech says they are re-negotiating their contract and will be upgrading to the latest version inthe next few weeks.
- The file and e-mail servers wereshutdown over the weekend to install patches and security hardening measures.  All of the Sun computers are being patched, security hardened, root passwords changed then I'm running scans and password cracking software to check the security measures.  The Windows computers will be next.
- Other misc. user support.

CIT:
(Veronica)
- LIGO website:Most time spent redoing the old PAC website and testing it on various platforms/browsers.  Updates to the meeting website. Updates to the NSF Review webpages. Working on a new website for NSF reviews per Stan's request, and on a website for the Aspen05 Winter Conference.  Updates to the LIGO webpages.  Updatesto the roster database.
- LSC website:  Updates tothe November meeting website and usual upkeep.
- Project Science:  Updates to the past workshop webpages.
- CaJAGWR:  Updates/support.

(Hiro)
Macintosh support
Installed OSX and severalsoftwares ( Caltech has site license of these softwares ) on Syd Mechkov's iBook, and configured for ease of use. Helped Riccardo DeSalvo to diagnose and backup his powerbook so that he can replace the internal harddisk, which exhibited erratic performance.

(Mike)
-Ran end of the month ghost backups on all NTSRV's.
-Sharon Kammerling: Workstation infected with a virus. This required a complete rebuild.
-NTSRV: Problems with the LLPDMWORKS server. This turned out to be a hard disk issue that I am watching closely. This server is backup and running.
-MarcoTarallo: I am currently loading a PC for him.
-Other onsite user support.

(Larry)
-Resolved a number of procurement issues. The SUN maint. contract has been renewed. Presently, going through the Matlab license contract. Working with Foundry to get all of the equipment put on the same contract and set to expire at the same time. The new tape library has arrived. Specialty items for different people have arrived and most have been delivered. Working on a new printer for the DCC.
-Worked on a number of PC's. Most were having spyware issues. We are putting on adware/spyware detection programs on more of the machines. This is starting to be a problem with performance of the units and allowing viruses to gain access.
-Assisted the DCC with a number of issues. Location of files. Downloading and conversion of files and printing.
-Assisted Sharon and Cindy with a couple of PC and printing issues.
-Still cleaning up old accounts and clearing off files off the systems. This project is going to take some time to wrap up.
-Installed another server system for the admin group to use for testing out different items.
-Worked/working on a number of different document related items. Most dealing with my trip to MIT aswell as the NSF review.
-Worked with the mail services but Lisa will have that in her report for next week.
-Assisting with the setup for the NSF review.
-The regular assistance for user accounts.


Advanced LIGO and Supporting R&D (Shoemaker)


Systems and Management

From: "Thomas Frey" <tfrey@ligo.caltech.edu>

 

Progress Period from 10.29 to 11.04

 

·         ·         See http://www.ligo.caltech.edu/~tfrey/index.htmlfor a complete listing of all project related cost and schedule data.

Accomplishments:

·         ·         Sub-system PLANNING activities

§         §         Continued work on preparing web space for posting Adv. LIGO reports. ("The Whole Enchilada")

§         §         Finished the input of changes / preparing RFIs / responding to RFIs, as a result of the meetings with Carol and the Subsystem Teams.

§         §         The 40-Meter schedule remains to be completed with changes.

§         §         Finished work on updating database coding to account for scope being added to the request amount.

§         §         Issued preliminary cost integrated schedule curve data to Carol for review and comment on Friday the 29th.

§         §         Started and continue to work on updated request curves inclusive of some schedule changes received on Tuesday the 2nd.

·         ·         ROSTER DATABASE:

§         §         Continued to work with Irena to provide Barry with information regarding FTEs and Institutions.

§         §         Assisting Irena as needed on record changes.

·         ·         COST BOOK DATABASE:

§         §         Posted revised cost data as a result of the meetings with Carol and the Subsystem Teams.

Seismic Isolation

From: Larry Jones <ljones@ligo.caltech.edu>
 
Advanced LIGO Seismic Structure

SEI Structure:

A change request is being submitted to the Change Board, proposing to limit the ASI contract activities to the completion of the SEI structure Design Package. Further studies will be performed to help determine future actions, involving performance, cost and other options. ASI has been given authorization to proceed with completing the Design Package.

Rai Weiss is providing consultation on determining the best means of evaluating the outgassing levels of large parts that cannot be RGA scanned.

Actuators:

PSI traced the high-pot test failures to a breakdown of the Ceramabond 835M adhesive used as a potting compound. An attempt to remove the potting compound from one of the bobbins resulted in damaging the coil wire, which will require rewinding. I've asked Jay if we can provide any relief in PSI's 100 MOhm at 500VDC high-pot requirement, which may save substantial rework and potential damage. PSI is checking to locate the availability of high-pot testors with adjustable resistance levels.

Displacement Sensors:

ADE is proceeding with fabricating and testing the 14 displacement sensors for the BSC prototype structure. They have provided a quote for two calibration blocks.

Accu-Glass is proceeding with fabricating and testing the 3 feedthrough flanges for the BSC chamber at LASTI, with 16 feedthrough fittings each.

Seismometers:

Nothing new.

Galling/Dusting Test:

Nothing new.

Suspension

From: Janeen Romie romie_j@ligo.caltech.edu

 


Advanced LIGO Suspensions
Working on quad structure design and analysis with the design team.

Met with Ken Mason and Oddvar Spjeld at LLO about the quad installation fixture design. Oddvar, Gary Traylor and Joe Hansen are considering designs for an air lift for vertical translation and tilt and using the air bearings for translations and rotations.

Met with Ken Mason and Mike Zucker and toured the LLO Staging Building discussing areas for storage and assembly of the advanced LIGO SUSs, COC, IO and SEI assemblies. I took many pictures and will go over them with Helena, who has created a brief summary of the clean areas required for the optic processing.

Preparing for NSF Review.

Working on Primavera update for the end of October.

Coordinating with Justin and Caroline for their visits here the week of Nov 29th. Coordinating travel plans for the Glasgow monolithic suspension workshop.

Initial LIGO Suspensions
Ordered the spare quartz wire standoffs yesterday. They have an 8 week lead time but due to a facility move, may be delivered in 12 weeks.

Gin Gin
Working with Ed Chargois on customs issue.

 

From: Helena Armandula <ahelena@ligo.caltech.edu>
 
Indium Cold Welding
I was able to join a large nickel plated magnet to an aluminum flag with indium.
The bond , obtained by using a very rudimentary process, seems to be fairly strong. These parts do not hold any weight and are only exposed to accidental knocks.
The surfaces were processed to remove the top oxide layer, the bond was made by applying pressure.

 From: ctorrie <ctorrie@ligo.caltech.edu>


Advanced LIGO SUS

1. QUAD Update

Helena and I have been testing the ergonomic arm with the controls prototype test mass. Aluminium main section with glass face plates that are held in place with 4 screws and VITON washers.
A view of the Quad as it is being built is available at http://131.215.114.242/view/index.shtml
Tests on "GEO-style" wire clamps with 1mm wire (the size of the wire in the top stage of a quad) lead us to believe that we should adopt an approach similar to that used in VIRGO and in the seismic system. Virginio and Ricardo have donated some "dumbbell" steel wires for us to test in our set up.

2. Visits

Ian Wilmut arrives from RAL on Monday for 3 weeks.

3. FEA of Structure

Analysis continues on the structure of the QUAD ETM. At the time of writing we have a 1st resonance of 75 Hz for the overall structure with non-suspended mass and are well on the way to meeting our goal of >100 Hz for this first resonance.
We have already met our goal of > 200 Hz for the 1st resonance of the upper section of the structure with non-suspended mass on its own. And with RAL are working on the lower section having a 1st resonance of > 100 Hz. The next stages wrt to the upper structure is to consider the use of U section instead of box extrusion and to incorporate the table cloth fixtures and the mounting of the top stage. RAL and in particular Tim Hayler are supporting our existing effort.

4. E -Drawing

We have built an e-drawing of the overall Quad ETM suspension in a tank. it is available at: -
http://www.ligo.caltech.edu/~ctorrie/ETM/
D040400_Assembly_ETM_Suspension_Structure_&_Assembly_Fixtures_02NOV04.EASM

5. Design Meeting

For a review of this week's design meeting please refer to the following link: -
http://www.ligo.caltech.edu/~ctorrie/QUAD_ETM/quad_etm_setup_page2.html

6. NSF Review

We have prepared several jpg's of the current suspension effort. These are available at: -
http://www.ligo.caltech.edu/~ctorrie/ETM/
 

Other Laboratory R&D

From: Riccardo DeSalvo desalvo@ligo.caltech.edu


Marco (3nov)

I began my work on Monday (1 November) with Phil Willems: for the moment we have tested the alignment of the laser beam first in the optical bench and then in the cavity.

 I’m studying also the PZT driver circuit for a new design by DXP software which I’m beginning to learn.

For the next week I will work improving the output layout in the output bench, draw a servo circuit scheme whit Phil for the cavity signal feedback and, if I can, continue the work on the new PZT circuit board.

 

Juri

I am working on the problem of thermal noise for finite mirrors in the case of Mesa Beam in order to have a better estimation of the improvements in the sensitivity of the interferometer. I am writing a Mathematica notebook for the thermoelastic noise for finite mirrors. Moreover I am taking measurements for the “creep” experiment.

 

Nicki

Creep measurement now at 40 degrees, next step 90 degrees

 


 

For additional information about this report, contact whitcomb_s@ligo.caltech.edu