The LIGO Executive Committee Agenda for Monday September 14, 2004 will be:
(Meeting time: 10:30 am Pacific Time)
Special Items:
no report
STATUS OF LSC MOUs
(Petrac)
(LSC Research Plans through February 2005 and Progress Reports
through August 2004)
ACIGA
Balearic
Carleton
CaRT
Caltech-CEGG
Florida
GEO
IUCAA
LSU
Michigan
Moscow State
Northwestern
SLU
Syracuse
Trinity
Columbia
Vassar
Groupe Virgo
VIRGO
SITE TELECONFERENCE (Lindquist)
A site teleconference was scheduled for Thursday, September 9,
2004. The following issues were discussed:
The list of assigned actions updated through September 9,
2004 may be found Here.
PROPERTY MANAGEMENT (Chargois)
>From: Ed Chargois <chargois_e@ligo.caltech.edu>
DOCUMENT CONTROL CENTER (Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
COST SCHEDULE CONTROL SYSTEMS (Cunningham,
Brambila, Kaufman, Salone)
>From: Esther Cunningham <esther@ligo.caltech.edu>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
>From: Gina Salone <gsalone@ligo.caltech.edu>
>From: Florence Kaufman <fkaufman@ligo.caltech.edu>
Financial reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)
>From: irena@ligo.caltech.edu (Irena Petrac)
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
SUPPORT (Baldon, Kammerling, Lloyd)
>Irene Baldon
>Sharon Kammerling
>Dorothy Lloyd
PROPOSAL and REPORTS (Lindquist)
Schedule of proposals and reports planned for the remainder of the calendar
year.
CHANGE CONTROL/CONTINGENCY MANAGEMENT
(Lindquist)
There are no open change requests currently in the system.
The Advanced LIGO SEI group proposed to the LIGO Excomm on 23 August that the
budget be increased for the ASI contract, adding on the order of $750K in funds
to cover a growth in expected expenses with a slight decrease in contract
scope. This will be discussed again next week.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
Quality/Safety (Tyler)
>From: Bill Tyler <tyler@ligo.caltech.edu>
No report this week.
.
Summary of Commissioning Activities at
LIGO Hanford Observatory (Landry)
4K IFO
-----------
Current activities on the 4k IFO center on running with full power into the
interferometer, trying out the new coil driver circuit, and FSS modifications.
Some commissioning highlights of the past week include the following.
A 4k power budget
was worked out, and a lower-than-expected PMC transmission of .76 (possibly due
to higher order modes) was obtained.
Dewar accelerometer studies
continue to suggest that insulation has reduced the strength and number of
stick-slip events that may unlock an IFO. The question is, which is the next
noisiest dewar, and what should be done about it?
Resonant gain was added to suppress an optic roll
mode. Modifications
were made to WFS1 and WFS2 demod boards. Next, another attempt
at high power running of the 4k IFO was made.
Still another TCS leak
was observed. A temporary fix
is in place, to be followed up by a long term one.
The power-up script for the 4k typically took about 12 minutes to complete.
This has been significantly shortened
with the addition of gain ramping to LSC filter modules.
As noted above, at the end of the week, the 4k ETMX coil driver was out
for modification.
2K IFO
------------
Progress was made on the commissioning of the 2K TCS installation.
ISC10 cleaning
was underway; recall this was necessary in part due to visiting mice.
More nasty details are here,
followed on by a recent status
report.
New LSC
code that allows the gain ramping noted earlier was first installed on H2,
and then later on
H1.
no report.
see also the CDS weekly meeting minutes in the commissioning archives:
Rolf Bork reporting
- Upgrade of 40m lab to latest DAQ in progress. We ran into
some strange
problems, but the root cause seems to be trying to run the
latest framebuilder
on an Ultra60. We swapped it out, replacing it with the
SunBlade1000 from our
development system. Now, everything appears to be working.
Last piece is to
bring up AWG. We still need to do more tests and some
cleanup, but almost there.
- New LSC software delivered to LHO. Software has rampable
gains in filter
modules and photodiode matrices. Appears to be working fine.
Request now is to
also provide this ramping gain feature for MC2.
Jay Heefner reporting
AI Filters for Low Noise DACs:
Replacement capacitors have arrived and the remaining boards will be stuffed
and tested.
LLO EMI Upgrade: Continue to order cables, feedthroughs and
panels for the upgrade.
RF photodiode redesign
Ben Abbott
1) I received further comments from Daniel regarding some
component choices for the RFPD. I will finalize the schematic and PCB,
and the PCB will be sent to PCB express, and these boards will be stuffed
as soon as possible.
2) I continue to test and characterize the prototype board
that I have.
PeterKing
I have been helping Flavio out with testing of the table-top
intensity
stabilisation servo. The state code I wrote to control
the 10-W laser's AC
current adjust actuator was modified a number of times and
was tested out
at the 40m Lab. After resolving a user-problem
associated with invoking
more than one macro, the state code was run on a
processor. The behaviour
of the code has not been fully checked out.
Ken Mailand
The main cavity spacer and the PZT holder bracket drawing
are in process at the CES shop, along with the 'invar 36' material.
The mirror set-up location tools are also being made, Mike Gerfen estimated 10
more days until everything is completed.
Ken Mailand, Lee Cardenas
I have received several components for the laser chiller
task, and now completing the layout for the test assembly.
I have tested the acoustic levels and pumping properties on
4 pump set-ups; the gpm output is border line, with this style of pump, and the
set-up is sensitive laser cooling tube shape and id.
The flow restrictions in the actual laser coolant lines are
of some value not known to me, or anyone else at ligo. I have asked the laser
company to send me a standard set of coolant line assemblies for our laser,
[representing one laser], so I can work with the actual system, they should be
here tomorrow.
I haven’t received any answers yet from LHO re. the existing
plumbing terminations for their tubing connections, or if the chiller fluid is
a contamination problem issue if there is a leak. It seems there are more
unknowns and more development required in this task than as first described.
The test setup is in the west bridge OTF lab.
Simulation of the flow resistance for the Co2 laser cooling
is ongoing. We have all the components needed such as: main
reservoir(13gal), Two different types of copper lines (0.187 ID and 0.25
ID ), pumps: RIO 1100, RIO 600, VIA AQUA 1300 Models. and Aqua clear model.
Test performed for noise & flow rate for each pump(goal
is 1890ml / min.) Results for the 0.187" ID copper line(this ID is closer
to the laser line) are as follows:
RIO 1100 = 1000 ml / min.
RIO 600 = 900 ml / min.
VIA AQUA = 950 ml / min.
Mike Smith
AS PORT ASTIGMATIC BEAM
I received a list of documents from Keita regarding the
astigmatic AS port beam and am in the process of studying them. I discussed the
problem with Hiro. The first approach is to ascertain whether the beam is
already astigmatic when it exits the AS port. If so, the problem may be caused
by vignetting on the HAM table optics (Faraday isolator is a limiting aperture)
or thermal lensing in the beam splitter may produce astigmatism on the AS
beam. Is the astigmatism power dependent? I will create a model of the
recycling cavity using Zemax and attempt to determine the effect of thermal
lensing of the BS on the astigmatism of the AS beam.
Lee Cardenas, Liyuan Zhang
OTF Lab. (W. Bridge)
The chamber has two samples, white Ceramabond, and disks of TRA-BOND #2254
color light brown epoxy. Cavity is locked.
We continue taking measurements everyday. No Change
Absorption Test Measurement prototype in standby
Scatterometer system in progress!!
We have finished aligning and mode of the beam needed for scattering.
We have installed the Inner test mass 2ITM04 fused silica mirror in the
scatterometer
enclosure and aligned and found the scatter beam from the ITM using a
Photodiode.
We encounter with one situation, the background scatter beam is too high!!
meaning the mirror surface is dirty! We are going to have it cleaned this
mirror.
or We have to install the scatterometer head and proceed to see if there is any
change.
The Quantronix 60 watt laser No change
OTF Lab at Lauritsen ROOM 38
no change!
Cavity #3
Chamber is pumping with (6) disks of TRA-BOND #2151 color blue epoxy and
(4) disks of TRA-BOND #2902 color silver epoxy. The cavity is
locked.
We continue taking daily measurements.
Cavity #2
Taken to the shop to weld the leg support in place, still waiting in this
one.
new components have arrived and still gathering all the others.
PSL Laser lab Laser in standby
no report
HEPI Controls
We have the first results of the adaptive feed forward system in the X
direction posted on the Lasti ilog on August 7, 2004.http://emvogil-3.mit.edu/ilog
The optics table was installed into the y-end HAM chamber. The table was placed
on solid spools at the advanced ligo table height similar to our x-end HAM. All
three of our HAM chambers and the BSC chamber have optic tables installed.
Ken and Myron
LASTI TRIPLE PENDULUM INSTALLATION
We spent the last days checking and installing sensors electronics, We had to
change position sensors on 2 piers, there was one bad set of electronics and
one bad sensor. The sensor was bad due to a poor connection at the plug end. We
changed the gain of the new version of HEPI electronics for the geophones (we
reduced the gain to 2 instead of 100). We also finished the termination board
to merge the HEPI electronics with the triple system. Now the signals going out
the seismic interface are going to BNC and are added to the triple ADC with
Jay's cards. Today we have all the sensors running and added to the dSpace
acquisition so that we can see and analyze the 28 sensor's signals. We now need
to correct the alignment of the platform (it seems it moved when we installed
actuators or geophones on the optical table) and then we will be able to
install the valves on the 8 HEPI actuators.
Simulation and Modeling
(Bhawal)
Site related work
---------------------
(Matt) Continued work on ezsfft and related scripts.
(Biplab) Assisting Rick Savage (Hanford) to analyze modal content of light
coming out of Pre ModeCleaner(PMC) of H1 interferometer.
Sideband imbalance
------------------------------
(Hiro) FFT code and Mathematica are used to further investigate the imbalance
of upper and lower sidebands in the PRM. One possible explanation is as
follows. The propagator of a sideband is like 1 - r1 r2 exp( -i phi1 - i
phi2 ). phi1 = 2 * 2 * pi * L / lambda(SB) and this has opposite sign for upper
and lower sideband. phi2 is gouy phase for higher order mode, which has the
same sign for upper and lower side band. So the magnitude of the propagator of
higher order SBs are different. As the curvature mismatch becomes larger, more
higher order modes are excited, and the enhancement of the higher order modes
can be different for upper and lower bands. This can explain the imbalance of
the SB in PRM. This possibility is analyzed more carefully by comparing the FFT
and Mathematica analytic calculation.
Simulation work for 40m interferometer
-----------------------------------------
(Monica)
Mach-Zehnder : Comparison of e2e simulated curves and raw data from 40m
group (feedback filter transfer function, open and closed loop transfer
functions, power spectra density of the steering mirror displacement). Some
improvements have been added in the feedback filter (slighty lower DC gain, 3
additional poles at 300 kHz to compensate cable capacitance,lower Q for the
zeropair in the actuator) to match better the simulated curves and real ones.
40m/AdvLIGO configuration: New boxes have been implemented for the optical
configuration, the mirror positions, the signals extraction. Test of the static
configuration are in progress to validate field values expected.
FFT phasemap
---------------------
Xiao and Hiro are writing a LIGO document to summarize the creation of the
mirror phasemap for FFT. It was found that phase maps originally created was
wrong in scale (the mirror was effectively 15% larger), and Xiao has reproduced
all.
Phasemap and WFS
--------------------
(Biplab) After Xiao's correction of mirror phasemaps, repeated FFT calculations
for WFS signals. After pitch corrections last week, also finished correction of
yaw degrees of freedom and now an H1 interferometer with corrections of all
angular offsets (equivalent to asymmetries in mirror phasemaps) is ready.
Alfi
-------
(Bruce) Last Week:
- Parser implementation for reading
and writing box settings objects completed.
- Working on graphical interface for
manipulation of these objects.
(Bruce) This Week:
- Box setting dialog implementation
along with associated utility objects.
(Melody)
Continuing modifications to display the FUNC_X variables in a friendlier user
interface. Currently working on the simple view which parses the
C++ code in the MemberDecl primitive setting.
Data Analysis Activities (Lazzarini)
Mendell:
The emphasis for the past week has been on producing more plots showing the
loudest events (maxima of StackSlide Power) for each sky position, for
comparison with Hough and Power Flux, using S2 and fake data. The results
are shown under pgs. 14-16 on the pulgroup S2 StackSlide investigations page
(pulg password required):
http://www.lsc-group.phys.uwm.edu/pulgroup/investigations/
s2index.html#stackslide
Shawhan:
* Compiled a complete list of lock losses during the S3 run, many of which
occurred a second or two BEFORE the end of an official science-mode segment.
This is due to having based the segments on the Epics "state vector"
channel, which takes a second or two to respond and switch off the servo after
lock is lost. Defined an "UNLOCKED" data quality flag to mark
these times, plus a "PRELOCKLOSS_10" data quality flag to mark the
10-second interval before each lock loss, during which the interferometer might
start becoming unstable.
* Investigating periods during the S3 run when the light level in the arm
cavities dropped substantially but lock was not lost. In L1, these are
found to sometimes be associated with glitches in AS_Q.
Sutton:
With Lazzarini, I have continued to study how to perform a meaningful test of
the reported 2001 Explorer/Nautilus excess using LIGO. I think we have
answered the last major question about performing the comparison: how to select
signal amplitudes for the test (a simple Bayesian argument gives a well-defined
distribution). For LIGO-TAMA I have performed false rate and efficiency
measurements for the network over the full S2/DT8 data set; these are posted on
the joint working group web page. Finally, with Zweizig I have continued
work on the new easy calibration tool for the DMT.
LIGO Data Analysis System
Software Systems (Blackburn)
A minor bug in the diskCacheAPI was found to cause a performance issue at the
sites. This required a minor patch of the source code for the 1.2.0 release of
LDAS. Fortunately, CVS was still in its frozen state when the problem was
discovered. We were able to find a fix and test it in time to push the patched
LDAS 1.2.0 release to the sits last Friday.
We have now put the release behind us, opened up CVS for new code development
and have begun to tackle the major issues for the next release in preparation
for the S4 Science Run. Key among the changes for the next release is the more
flexible RDS creation code supporting multiple frames per file and the ability
to concatenate time series data.
The usage of the CIT, LHO, LLO, and MIT LDAS systems from March 1 through September
1 of this year was tallied up from the log files using the controlMonitorAPI's
GUI. Top level usage is...
CIT 197,995 jobs submitted
LHO 190,088 jobs submitted
LLO 152,705 jobs submitted
MIT 6,398 jobs submitted
There is a slight clustering of these jobs prior to the two LSC meetings
spanned by this time interval, indicating that LDAS is still being used
extensively to do science. It also indicates that LDAS at MIT is not seeing
much use.
Fixed the C++ code for the cacheCheck utility so that it now distinguishes
between different types of data. This has been tested on Tandem5 and LDAS-DEV
and will go into CVS today.
Reverted diskCacheAPI C++ code back to the second resolution algorithms for
file timestamps. The sub-second resolution is dependent on the file server
software, not on the operating system capabilities and hence can't be
implemented with complete confidence without standardizing file servers. This
has been tested on LDAS-DEV and the new(old) code should go into CVS today.
Worked on new directory creation routines to provide more explicit log
messages. This is a bit tricky to implement and needs more work within the
diskCacheAPI.
Continued working on the generalization of the time interval code associated
with PR 2392 in the diskCacheAPI. Incorporated the above mentioned changes into
this new branch of diskCache code development.
Fixed the confusion associated with missing .frame.cache2 files that was
appearing in the diskCacheAPI's log file. This was a change to the TCL layer.
Fixed the bug in the cacheDump Tcl code that was causing the -text option to be
incorrectly recognized.
Studied the complexities of the multiply connected API to resource file
dependencies associated with PR 2667.
Improved the documentation on the controlMonitorAPI's GUI. It was missing
references to many of the new features of the 1.2.0 release. This will be fixed
on LDAS-DEV and available in the next release.
Worked on the generic thread wakeup function to fix the thread wake up issue in
the lightWeightAPI. Needs more testing on the LDAS-Dev system to know status of
changes as this is a raw bug that is not readily reproducible.
Completed the LDAS-1.2.0 system testing webpage.
Began our TclGlobus activities with a new energy now that our ITR2003 hire is
on board. Tested out the Tcl wrappers with the new Globus 3.2 and discovered
that it lacks much of the thread support that was standard in the older Globus
2.4 package. This is a bit of a problem since the removal of the thread support
seems to be out of the Globus camp to make thier code work so we will need to
investigate possible workarounds. We are about to start tests of our code using
non-threaded builds of Globus 2.4 and with experimental partial threaded builds
of Globus 3.2 to learn more abou the source of the problem being encountered.
Hardware Systems (Anderson)
Caltech
-------
(Dan Kozak)
* Continued the transfer of non-run second trends for both LHO and LLO (about
1,000,000 files total) from HPSS to SAM-QFS (and their subsequent deletion from
HPSS).
* Still working on getting a quote from STK for silo maintenance.
* Still working with Sun on the problem where shared clients (in this
case
alterf) ask for files, but they never get staged.
* Got Sun to send out an engineer to replace the bottom controller in the
3510 in Millikan (3510-10). The amber light is out and it's not
beeping (both of which are improvements). We'll see how it behaves
now.
* Dealt with hung T3 at LLO as regards /samrds. Lesson learned
before now confirmed: don't reboot host in this situation.
* Ordered 9940 cleaning tapes (and retrieved cleaning tape stuck in drive).
* Have been working on problem with corrupt LLO second trend files in CIT
archive that Peter Shawhan reported. Files are good at LLO, so I'll
be copying them over, but I'm also trying to track down the likely source of
the problem.
(Hari Pulapaka)
* Helping Michael with some issues on setting up globus and getting some
tcl globus tests to run.
* Moved the condor setup on ldas-grid to use /grid.
* Working on moving ldas-pcdev2 to use gsi-ssh.
(Stuart Anderson)
* Collecting price quotes for additional disks, tape drives, servers,
network switches and cluster nodes.
* Wrote script to automate monitoring of stuck SAM-QFS files.
MIT
---
(Keith Bayer)
* Rebuilding both 3ware raids on pcraid1.
* Ordered pcraid#8 .
Hanford
-------
(Greg Mendell)
* Besides routine tasks, I've requested quotes from for media
racks/cabinets from three suppliers to store 9940B tapes.
(Ben Johnson)
* Assisted in debugging framebuilder issues last week. Initially, the problem
appeared to be with QFS, but eventually turned out to be
related to the installation of a Syskonnekt (sp) Optical Gig-E card.
* Grid account backups have now been moved from defiance, to
/samrds/backup/cluster (a corresponding archive set "backup"
was
created). Backups occur daily at 01:00 local time.
* Presently spraying L1 data across the cluster. I estimate spraying to take a
week for all S2/S3 LHO/LLO data. Publishing to start after the first S2/LHO set
is sprayed.
* Working on GRB/segment archiver GUI + aux archiving script. Coordinating with
Justin Garofoli to give the control room something that works for them.
* Concluded firmware tests on the test 3510-10. Despite problems inherent to
the test unit, the new firmware appears to work, and basically installs by the
book (minus a few syntax errors in the instructions).
General Computing (Wallace)
MIT:
(Keith)
-Working on FlexLM license server for Matlab 14
-R14 Matlab compiler does not work on Solaris apparently...
-Continuing to test RedHat WS Enterprise Edition on pc
-Experimented with TeamSpeak VOIP utility
Livingston:
(Shannon)
-Spent many hours working with Bell South on the phone and on site again this
week. They have:
1) replaced a card at LLO, then came back and changed it back to the old card.
2) fixed some issues with their SNMP alarming functions.
3) removed a piece of redundant hardware at the Denham Springs CO.
4) tested light levels
I now have an even better understanding of the equipment that lies between LLO
and LSU on the circuit. It turns out that we make many changes between
single and multi mode fiber. I am not sure that this is the best
available way of implementing this circuit, and in my opinion offers too many
points of failure. When Bell South removed the piece of redundant
hardware at DS, I asked why it was there in the first place. The answer I
got was that it was just engineered that way, and they were not sure as the
engineering group is totally separate from the support group. In Denham
we used to make a transition from single mode (SM) to multi mode (MM) several
times. This is what it looked like from Livingston:
MM -> SM -> MM -> SM -> MM -> SM -> MM -> SM -> MM
LLO
|
Denham
| Goodwood | LSU
Ihave asked about other hardware possibilities since the current hardware seems
overly complicated and introduces way too many failure points, etc. I
have been told that there is only one solution and that it is
non-managed. However, the person informed me that they are usually very
stable and he even complained about the fujitsu equipment being
unreliable. The non-managed portion really would not be that different
than what we have now, since when the connection goes down, my phone does not
ring like it should. Instead I have to call them and notify them that the
connection is down.
At this point we are in a "wait and see" mode to see if the circuit
goes down again. Bell has not had sufficient diagnostic capability in the
circuit for the last 10 months it turns out, but that is fixed now. If the
circuit does go down again, they should be able to more closely pinpoint the
location of the failure.
Hanford:
(Christine)
- Network usage can be seen at
http://www.ligo-wa.caltech.edu/~christin/mrtg/
198.129.208.1_198.129.78.122.html
- Continued to install Spyware Exterminator on PCs.
- Rebuilt a Win2k PC because it kept dumping memory and re-booting.
- Investigating an ssh problem on the mail server and LSC sandbox.
- Cleaning up the SURF student user and e-mail accounts.
- The usual user support.
CIT:
(Mike)
-Mohana Mageswaran: I had to reload her workstation due to a virus. This
computer had to be wiped cleaned and reloaded from scratch. Plus loaded various
engineering software and transferred over users data from backup.
-Linda Turner: I finished up loading an updated PC for Linda, but came across a
hardware issue that is going to require the motherboard to be replaced. I
called Dell to get the motherboard replaced, that should arrive today.
-Control Room W/B: I finished up reloading and setting up a PC rack mount unit
back up in the control room 352.
-Loaner Pool: I started reloading a laptop for the loaner pool. I have four
laptops that were turned in, these will require complete rebuilds.
-Much other misc. onsite/phone user support
(Veronica)
- LSC website: Updated the author list posting. Other updates to the website.
Updated the roster database to reflect changes in LSC memberships and status of
some members.
- LIGO website: Updates to various pages. Worked on an overview of a web
security class that I recently attended.
- Project Science website: Updates and user support.
(Lisa)
- Vacation
- Working out some video problems on hadar.
- Discussed with Larry options regarding the spam filters.
Mail Stats 9/2 - 9/8/04
Messages Accepted:
Spam Rejected:
Viruses Rejected:
False Positives:
Total Mail Thru:
% spam blocked:
(Larry)
-Still doing a lot of work with different procurements. Trying to get some more
disk space and upgrade the backup system to handle the increase in data we are
now handling. Purchased new machines for different people. It looks like we
need a few more laptops to replace some of the old ones that are not
functioning correctly and can no longer handle the applications being loaded on
them.
-The computer room is still being worked on. We have some cleanup to do before
the testing of the fire suppression system.
-Added a number of new users and cleaned up a few more old accounts. Still a
lot of work to do there.
-Tested a number of web conference items. Things are improving but we still
have a number of items to work out.
-Spent a couple of hours on the new sandbox unit. The NIS+ installation is
still being worked on and a number of applications still need to be loaded.
-Worked a number of e-mail issues covering logs to aliases. Thanks to Albert,
David S., and Stan a number of aliases have been cleaned up but still more to
go.
-Worked on some backup items and a few licensing issues.
From: "Thomas Frey"
<tfrey@ligo.caltech.edu>
Progress Period from 09.03 to
09.09
Out of the Office on
vacation 09.03 and 09.06.
·
·
See http://www.ligo.caltech.edu/~tfrey/index.html for a
complete listing of all project related cost and schedule data.
Accomplishments:
·
·
Sub-system
PLANNING activities
§
§
Continued work on preparing web space for posting Adv. LIGO reports.
("The Whole Enchilada")
§
§
Continued the input of changes / preparing RFIs / responding to RFIs, as
a result of the meetings with Carol and the Subsystem Teams.
§
§
Executed a telecom with Carol W, Benno W., and Peter King. regarding PSL
progress.
§
§
Executed a telecom with Carol W., Phil W., and Mike Smith regarding AOS
progress and schedule / cost changes.
§
§
Executed a telecom with Carol W., and Janeen R. regarding SUS progress
and schedule changes.
§
§
Executed a telecom with Carol W., and Larry Jones regarding SEI progress
and schedule changes.
§
§
Started work on the progress schedule update with progress through
§
§
Started work on 40-Meter schedule changes for remaining work.
§
§
Corresponded with Benno regarding a challenge with the PostOffice
application.
·
·
ROSTER DATABASE:
§
§
Continued to work with Irena to provide Barry with information regarding
FTEs and Institutions.
§
§
Will update and post a revision to the approved version of the LSC S2
Authorship List
§
§
http://www.ligo.caltech.edu/~tfrey/authorship/compare.htm
·
·
COST BOOK DATABASE:
§
§
Nothing new to report.
§
§
http://www.ligo.caltech.edu/~tfrey/rd2005/Acct_Stats.htm
From: Larry Jones <ljones@ligo.caltech.edu>
Advanced LIGO Seismic Structure
SEI Structure:
ASI continues to work on tuning their estimate for the cost of HAM unit
design; it's now expected on 17 September.
A meeting between Stan Whitcomb and Rene Fraudet, president of ASI is scheduled
for 10 September, to discuss cost issues.
Stage 0 detailed drawings, expected last week, are yet to be released.
Budgetary needs are being developed for FY05.
Actuators:
Weather problems associated with Hurricane
Displacement Sensors:
ADE is proceeding with fabricating and testing the 14 displacement sensors
for the BSC prototype structure.
Accu-Glass is proceeding with fabricating and testing the 3 feedthrough flanges
for the BSC chamber at LASTI, with 16 feedthrough fittings each.
Seismometers:
Nothing new
Galling/Dusting Test:
Nothing new.
From: Janeen Romie <romie_j@ligo.caltech.edu>
AdLIGO Suspension
Continuing to work with Caroline Cantley, Sheila Rowan, Helena
Armandula and Thomas Frey about the ribbon process design and the optic ribbon
attachment design. We had a meeting on Friday. Will review responsibilities for
these items in final design and fabrication phase with Thomas tomorrow for
review with Helena and Caroline after that.
Working with Norna and Calum on flexibility study for suspension design for
sapphire and fused silica. Calum distributed a preliminary
flexibility study. We will discuss this on Tuesday.
Worked on a magnet holder for an eddy current damper design.
Provided Primavera updates to Thomas. Participated in a meeting with Carol and
Thomas on suspension progress.
Finished the RODA M040283 on the sapphire and fused silica baseline sizes for
ETMs and ITMs. Forwarded to Gari.
Gin Gin
Sent the blades and clamps to Conor at AMU. He should receive them
next week.
From: ctorrie <ctorrie@ligo.caltech.edu>
1. QUAD Update
The drawings for the lower masses that we will use in the controls
prototype, that is to say the test mass and penultimate mass in both the main
and reaction have been completed. they are on the PDMWorks vault. I hope to
have the completed drawings in the shop by the end of the week.
The next set to be done are for the penultimate test and reaction mass.
Russell Jones and I have worked through the detail of switching to a
"3&1" assembly technique rather than a "2&2". We
are confident that the "3&1' approach makes it easier to assemble and
install the suspension. It should also simplify the interface with the fibres /
ribbons. The approach involves the Upper Intermediate mass becoming part of the
lower half of the structure thus leaving only the top stage and the top masses
to be installed with the seismic system (at LASTI). The larger
"lower-half" can fit through the BSC chamber door and works in
conjunction with Ken Mailand's and Ken Mason's installation approaches. http://www.ligo.caltech.edu/~ctorrie/QUAD_ETM/RdeJ/lowerhalf%20plus%20UImass_in%20BSCdoor1.jpg
More to follow.
2. Flexible ETM
The suspension team (Norna, Janeen and I) have been looking at what would
be involved in keeping the ETM, both controls and noise, flexible for either
silica or sapphire. This will discussed in more detail at next weeks SUS and
design meetings.
3. Blades
Both Valley Precision and CES have started manufacturing the controls
prototype blades.
4. Design Meeting
For a review of this week's design meeting please refer to the following
link: -
http://www.ligo.caltech.edu/~ctorrie/QUAD_ETM/quad_etm%2520setup%20page2.html
5. Visits
Tim Hayler October 3rd to
Mike Perreur-Lloyd October 18th to
Ian Wilmut Nov 8th to Nov 25th - JG to confirn!
Russell Jones Nov 29th - Dec 4th TBC
Caroline Cantley, Justin Greenhalgh & Norna Robertson (TBC)
Janeen Romie and I are visiting Stanford next week.
From: Helena
Armandula <ahelena@ligo.caltech.edu>
Adv. LIGO SUS
The mask to be used for the gold evaporation on Pyrex plates to make the
electrostatic drive will be delivered this Friday. The Pyrex plates attach to
the metal masses used on the quad controls prototype.
Next Monday I will visit Navitar Coating Labs to confirm that the mask is
acceptable; they will deposit a very thin layer of inconel and 10,000 angstroms
of gold on the Pyrex plates to manufacture the electrostatic drive.
From: Helena Armandula <ahelena@ligo.caltech.edu>
From: Peter King
<pking@ligo.caltech.edu>
AdvLIGO PSL
===========
A progress meeting was held with Carol, Thomas and Benno to
report for the month of August.
The high power stage has been injection-locked to the front end and the output
power was 170 W.
From: Michael Smith <smith@ligo.caltech.edu>
AOS
I am in the process of updating the development schedule and cost for the AOS
subsystem.
I received a list of documents from Keita regarding the astigmatic AS port beam
and am in the process of studying them. I discussed the problem with Hiro. The
first approach is to ascertain whether the beam is already astigmatic when it
exits the AS port. If so, the problem may be caused by vignetting on the HAM
table optics (Faraday isolator is a limiting aperture) or thermal lensing
in the beam splitter may produce astigmatism on the AS beam. Is the astigmatism
power dependent? I will create a model of the recycling cavity using Zemax and
attempt to determine the effect of thermal lensing of the BS on the astigmatism
of the AS beam.
From: Riccardo
DeSalvo <desalvo@ligo.caltech.edu>
Barbara
Finished the thesis work and
left for
Anamaria:
I am still gathering as much
data as I can and am beginning to trace the Q-factor dependence on frequency
for Maraging. It is a pretty slow proccess, and there is a lot of noise that
has to be taken into account. By next week I should move on to the
Copper-Berrylium blade.
Nicky
Started the school, her
Maraging blade creep measurement setup was finally started and it is taking
data. She will continue to come
over occasionally to look at the growing data.
Maddalena
The anomaly in the frequency
behavior as a function of the vertical position (which we thought caused by the
appearence of higher order corrections) is, in the new, faster measurements,
disappeared. The effect that we measured could be due to temperature drifts
because the old measurements were in the frequency domain (that meant 2 days of
integration for each measure). Now with the faster time domain analysis (several
measurements per day) the effect disappeared.
We are also studying again
the slope behavior for different resonant frequency values (by separating the
slope from the resonant frequency meqasurements we now can measure 4-5
slopes/day instead of one every two days). We confirmed the unusual behavior
the transfer function slope decreasing from slope 2 to slope 1.5 below 100 mHz.
If we extrapolate the
behavior of the slope and considering a ideal system (without saturation) we
obtained that all transfer functions corresponding to resonant frequencies
below 100 mHz have an intersection point at ~3Hz.
We still do not understand
this behavior.
I have also been helping
Barbara with her thesis work.
Justin
Gianni has completed the
final designs for the new Ultra sound transducer. We are now planning a meeting
in
Simone
Working on my final report,
prepared the massholder
for the Q-machine and done
some pictures with the exercise flexjoint

Juri
I helped Barbara for the
alignment of our cavity and finally it was locked quite easily. I learned from Maddalena
how to take measurements with the apparatus in the Synchroton for studying the
properties of the blades for the vertical attenuation system when she will be
gone.
I found a problem with the
simulation program for the dynamics of the Mexican-hat cavity and is now under
investigation. I am sending the summaries for the GR17 proceedings. I am
working on the calculation of coating thermal noise for finite mirrors.
Francesco
The flex joint fixture
presently available present resonant frequency close to the silicon
thermoelastic dissipation peak. In
order to generate an oscillator with resonant frequency far from the
thermoelastic peak, I simulated a new design of joint with an 8g iron mass in
the middle instead of the thin silicon mass (few milligram inertial mass). The
resulting resonant frequency for the high frequency mode ranges from 1 to 1.2
KHz for loads from 1 to 10 Kg. These frequencies, lower than the previous
design, should avoid the thermoelastic region, giving more space to detect the Q
due to the internal dissipation, up to 106.
I assembled an high-freq
transformer with a gain of 100 times to provide an excitation electrostatic
force to excite the rets mass in the Q-machine and now I am trying to connect
it to a power amplifier. Within next week we should be able to mount the laser
and the photodiode to the machine and try a first measurement.
For additional information about this report, contact whitcomb_s@ligo.caltech.edu