The LIGO Executive Committee Agenda for Monday July 26, 2004 will be:
(Meeting time: 10:30 am Pacific Time)
Special Items:
no report
STATUS OF LSC MOUs
(Petrac)
(LSC Research Updates through August 2004, and Progress Reports
through February 2004)
AURIGA:
Balearic:
IAP:
National Astronomical Observatory-China (NAO-C):
Orsay Group (aka Groupe Virgo):
Penn State:
VIRGO:
Wisconsin:
SITE TELECONFERENCE (Lindquist)
A site teleconference was scheduled for Thursday, July 22,
2004. The following items were among those discussed:
The list of assigned actions updated through July 22, 2004
may be found Here.
PROPERTY MANAGEMENT (Chargois)
>From: Ed Chargois <chargois_e@ligo.caltech.edu>
DOCUMENT CONTROL CENTER (Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
> From: Cleveland Mak <mak_c@ligo.caltech.edu>
|
July 22, 2004 |
Packages |
Faxes |
|
In |
13 |
34 |
|
Out |
9 |
23 |
COST SCHEDULE CONTROL SYSTEMS (Cunningham,
Brambila, Kaufman, Salone)
>From: Esther Cunningham <esther@ligo.caltech.edu>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
>From: Gina Salone <gsalone@ligo.caltech.edu>
>From: Florence Kaufman <fkaufman@ligo.caltech.edu>
Financial reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)
>From: irena@ligo.caltech.edu (Irena Petrac)
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
SUPPORT (Kammerling, Baldon, Lloyd)
>Irene Baldon
>Dorothy Lloyd
ADVANCED LIGO (Cost Schedule Control
Systems) T. Frey
>From: Thomas Frey <tfrey@ligo.caltech.edu>
See Advanced R&D Section.
REPORTS (Lindquist)
CHANGE CONTROL/CONTINGENCY MANAGEMENT
(Lindquist)
There are no open change requests currently in the system.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
Quality/Safety (Tyler)
>From: Bill Tyler <tyler@ligo.caltech.edu>
No report this week.
.
Summary of Commissioning Activities at LIGO Hanford Observatory (Landry)
The full 2K IFO remains down, with arms valved off after the
June 30th vent. The 4K is locking in common mode with inspiral ranges of
~5Mpc.
Backscatter studies: black holes are no
better than foolscap.
N.B. Owing to mechanical failure, LHO's vacuum bake ovens are out of
service until further notice. (Kyle Ryan)
4K IFO
A model for the modal decomposition of the bright Michelson in the basis of the
output mode cleaner compares
favourably to measurement.
Following up from observations during S3 PEM injections, the 4K was made to be
more robust against impulses and acoustic noise in the end-Y station: an
optical lever interface board was swapped
out.
A (followup) 4k shot noise study
employed a different RF source a modulation frequencies than the original
measurement.
2K IFO
Mice temporarily mistook ISCT10 for a water
closet. The visitor has fouled the table, necessitating cleanup of
not only the table surface, but many optic faces as well.
2K PSL (Justin Garofoli for Team PSL):
We've been struggling with the lasers deceptive beam quality: to the eye it
looks pretty bad, but to the PMC it is pretty good, 91% visibility. We may be
able to eak a bit more out of the mode matching and improve the visibility a
bit more. Some trouble also may have been coming from the EOM, a swap of
EOM's changed the visibility from 76% to 91%. The PMC's transmission
efficiency is 87%: 6.09 watts out, 7.03 W in.
LHO Outreach Activities (Dale Ingram)
We are pleased to welcome Greg Baker to LHO for a summer research internship.
Greg is a high school physics teacher from Geneva, New York who is developing a
research course for Geneva High School physics students that will focus on
LIGO-related projects. Greg majored in physics at Hobart and William
Smith Colleges, also in Geneva. Steve Penn of the LSC is now a professor at HWS
and will be the LIGO mentor for the Geneva High endeavor. The high school
students will be hunting for bicoherences in LIGO interferometer data using
Steve's DMT bicoherence monitor. Greg is already busy learning the ins
and outs of LIGO data collection and analysis, and he has developed a very
talented group of young physicists who are eager to get started on the project
once the school year begins. We wish him the best.
Friday, July 23 will be the final day of the Washington State University course
for school teachers that has unfolded at LHO over the last two weeks.
Titled "The Nature of Scientific Inquiry", the course brings teachers
face-to-face with the challenge of creating science activities that require
students to personally navigate through the scientific method. Dr. Judy
Morrison, Assistant Professor of Education at WSU Tri-Cities, has taught the
course with assistance from Fred Raab and Dale Ingram of LHO. Nine local
teachers, ranging from elementary through high school, are now completing the
major course assignment of designing several inquiry-based science activities
for use in their own classrooms. These activities will help the teachers
meet state and national education standards for science inquiry. The
participants have also engaged in several LIGO-related activities to learn how
the methods of science play out in a major international science project.
In addition to touring the site and listening to presentations about
gravitational-wave astronomy, the teachers have shadowed and interviewed LHO
personnel to get an up-close look at how the work here gets accomplished.
LHO has enjoyed hosting the course and we look forward to future collaborations
with WSU and Professor Morrison.
LHO staff member Corey Gray recently presented a summary of LIGO at the Salish
Kootenai College Summer Astronomy Camp for students in grades 8-12 on the
Flathead Reservation in western Montana. LSC member and SKC professor Tim
Olsen obtained grant funds to sponsor the camp (and fund other activities as
well), which is a collaboration between SKC, Montana State University and NASA.
Corey also set up several very nice demos of optical and signal equipment; the
students enjoyed investigating these devices after his talk. You can see
a more complete description of Corey's trip (along with some great photos) at http://www.ligo-wa.caltech.edu/~cgray/SKC_summer_camp_04.html.
HEPI (Abbott, Giaime, ...)
---------------------------------------------------------------------
Work continues on the corner station HEPI task. This week, the chambers
retrofitted with HEPI were freed
their caging stops and the hydraulic flow was turned on and off. This
process searches for unusual
hydraulic offsets that may indicate a problem with an actuator or hydraulic
control valve.
System ID data is being collected in the corner station on ITMX as a first step
towards turning on HEPI
control for this chamber. Earlier on this week, the HEPI system was used
to adjust the beam alignment on
HAM-4. This adjustment worked remarkably well.
Refinements were made in the HEPI control code to permit verification of the
correct loading of filter coefficients.
L1 PSL and EMC Retrofit (Peter King)
---------------------------------------------------------------------
I mapped out the cables going into (and out of) 1X4 and 1X5 in preparation for
moving the racks into the new CDs rack area.
The PSL wiring harness and excitation engine connection was checked out in
preparation for the new intensity stabilisation. In particular the
connections for the VMIVME-4116 DAC and laser system interface was mapped out
and compared with the EPICS records database.
L1 Commissioning and HPLF (Amin)
---------------------------------------------------------------------
HPLF: We still have no report from IPG Photonics. We await information
regarding the failure mode of the 100 W laser.
Commissioning: I finally measured the phase noise of the Wenzel crystal
oscillators. Their noise level is better than the Wenzel specification at
> 100 Hz. With Rai's help, we obtained similar numbers in a second
data run using power supplies instead of automobile batteries. WFS
detection heads are being returned to their sensing tables, and I have started
basic checkouts of the WFS chains.
LLO Seismic retrofit (Rich Abbott)
---------------------------------------------------------------------
LLO Facilities and Infrastructure (Allen Sibley)
---------------------------------------------------------------------
The building monitoring, security and fire alarm computers have been removed
from the control room. The monitors for these machines remain in the control
room.
Current transducers have been installed at the chill water circulation pumps to
replace the differential pressure switches that have been giving more and more
trouble lately. The new sensors are working well but we need to have Siemens
modify the software alarms.
General computing (Roddy)
--------------------------------------------------------------------
* Current bandwidth usage can be seen at http://teche.ligo-la.caltech.edu/mrtg/LLO-Router/130.39.245.1_1.html
* Archived bandwidth usage can be seen at http://teche.ligo-la.caltech.edu/mrtg/archive/
under the dated folder for the week of interest.
* Made a couple of firewall changes for some UDP ports.
* looking into an issue on a Linux box where it runs out of memory every two
weeks or so. This is the machine that handles DHCP, mrtg, BigBrother,
etc. When the box runs out of memory, it locks up solidly and the only
way to reboot it is to hit the reset switch. The main problem is that
when this happens, no one can get DHCP addresses.
* Still working on rebuilding the applications share. I have added things
like Matlab, gcc-3.4.1, gnu ld (binutils), Mozilla, etc. We are still not
back to the point we were before the disk crash, but it is getting there.
I have spent many hours in the last week compiling software. So far, I am
pleased with the disk array that I purchased to replace the Linux box that was
sharing out the applications.
* working with a Sun rep to find out if a couple of SAN ideas I have will
work. This is an idea that I have on how to handle the user web pages and
server if we move all of the Sun boxes to an internal network with only the web
and mail boxes on the DMZ.
* ordered a license for F-Secure anti virus for us to use when Norton decides
to die because of a virus or other problem. There have been several
instances when a machine becomes infected with a virus and Norton will not
work, so we cannot clean it. We just had an instance like that this week
when Tom was trying to clean Bagle.AG@mm off of a machine.
CDS (Parameswariah)
--------------------------------------------------------------------
Installed a new PC on the CDS Network for Beam Centering system for Andri.
Installed the latest Windows XP, Matlab and Spiricon software. This computer is
being setup to the be accessed via the Spiricon computer's monitor with a
switch.
Moved the hepi watchdogs to baja processors after compiling it at hanford.
Worked with Peter King, Rich Abbott and Danny Sellers to get the hepi vmecrates
up and running. Had to figure out the right jumper settings and the location of
the cards in the crate.
Troubleshooted the problems with HEPI input/output channels at the corner
station. The following problems fixed:
Problem: -1.000 seen on odd position sensor input channels (V1, V3, H1, H3) on
hepi2 for RM and OUT channels. Traced it to 110B ADC Card. Swapped it with a
card from the cabinet and set the right jumpers.
Problem: RM and OUT inputs signals look swapped on the medm screens Traced it
to the cables plugged in to the 110B. Swapped the input ADC cables and this
fixed it.
Problem: STS sensor signals read hard zero The problem goes away if I unplug
the MC1 input cable to the 110B. STS signals are on channels 11 through 13 on
this cable. Rich A. and I traced it to railed outputs from the STS electronics
Worked with Rolf and Alex to install the fix for filter module coefficient loading
problems.
As of today this is now propagated to all the systems - suspensions, lsc, asc.
Also the overflow bug in suspension controllers found and fixed at hanford was
also propagated to llo with this change. Hepi output (Actuator drive fast channels)
to DAQ were fixed to have the right order. Earlier we found the channel names
on Dataviewer did not match the actual outputs. Added fast outputs to DAQ for
the corner station hepi. Also added the flag to trend all corner hepi channels.
Burst Analysis, AdL IO Modeling, and HPLF (Franzen)
--------------------------------------------------------------------
1) Have been trying to help Alessandra Di Credico to run glitchMon on alvar at
LLO. There were many problems, but now it seems like Masahiro Ito has sorted
things out.
2) Have run a few tests on ldas-grid in order to familiarize myself with this
new Condor system at LLO.
3) Helped Marc Cenac, the LLO SURF student, to solve a few programming problems
related to his project.
Data analysis (Yakushin)
---------------------------------------------------------------------
LDAS admin:
1) There was a double disk failure in t3-4: u1d8 and u1d9. The disks are
replaced, no data lost.
2) Installed matlab and matlab compiler on ldas-grid.
3) Helping Ken Franzen to get started with Condor.
4) Helping Shyang Wen to learn how to get data he needs into matlab.
LDAS data analysis:
Condorizing DMT version of waveburst: tested that ROOT can be used under
Condor, writing a function for getting frames into waveburst.
John Zweizig
This week I upgraded the glitch finder in PSLmon to fill in
some of the new trigger table fields and to allow it to generate multiple triggers
in a single time stride. It also now histograms glitch parameters to allow the
user to tuned the glitch finder more easily. I also moved the program that matches triggers to
simulated events to the gds cvs repository.
see also the CDS weekly meeting minutes in the commissioning archives:
Rolf Bork reporting
- Modified the CDS filter modules to perform CRC check sum
tests when new coefficients are downloaded. This has been incorporated in the
HEPI software and installed at LLO. Modifications are in progress to
incorporate this change in other CDS systems.
- In process of adding down sampling filters for DAQ.
Testing is underway now, with first release to sites end of next week.
- Sigg has noted that some suspension controllers are
running near and, at times, beyond max of 61usec. I'm not sure we can play any
more software tricks to improve this. I compiled the latest software to run on
our new 2.2GHz VME Pentium
processors under Linux for testing and got times around 30usec. We presently
only have a few of these available, so this is not an option unless we purchase
more.
- A couple of Hepi changes are going out today. First is the
addition of the corner station actuator output DAQ channels. Second is a fix
for Hepi2 test points.
- I'm still trying to work a day or so a week on code
documentation. Presently I'm working on a doc which describes the code common
to all realtime front ends, such as DAQ/GDS routines, VME hardware drivers,
etc. This should then make it easier to document the individual front end code
by heavily referencing this document.
Jay Heefner reporting
Fiber Optic Timing Link (Sander)
=======================
- The fibers for the 40 meter test have been received.
Sander will work with Bob to install them this week.
- Testing will be coordinated with 40 meter operations.
Timing System Redesign (Flavio)
=======================
- On hold for ISS work. Will be restarted after ISS pcb is
complete.
- Review scheduled for mid-Aug.
Anti-Image for Low Noise DACs (Jay)
===========================
- The first board was shipped to LHO last week. The other 9
are 90% stuffed and awaiting some back ordered caps. They should be here this
week.
- Don is writing a test procedure.
40 Meter (Ben, Jay)
============================
- Mach-Zehnder changes and upgrades.
- MC2 Univ Dewhite board has been changed to a rev B7, but
there seems to be some confusion as to whether the schematic actually reflects
what is installed at LLO. Jay has contacted Rana and Rus.
- DAQ channels for PSL and MC are being fixed.
LSC PD Redesign (Ben)
===========================
- Schematic has been finalized. PCB layout will be started
tomorrow.
EMI Upgrade (Mohana, Jay)
===========================
- LLO LSC drawings have been started and should be ready for
review by next week.
- Lots of parts are on order. There is a potential problem
with the 64 conductor cable. It is a long lead from AMP. Rus is checking to see
if he can find any.
TNI Arm Cavity Servo (Jay)
===========================
- Preliminary schematic is complete and being reviewed.
- EPICS control software is being tested.
AdL SEI (Jay)
==========================
- Nothing new
AdL SUS (Jay)
==========================
- BNC to DSpace ADC modules shipped to LASTI
- The satellite amps received back from LASTI have been
upgraded to Rev B1 and the termminator boards installed. They will be installed
in the CIT test stand.
PeterKing
I went over the state code to control the power amplifier
pump diode current in order to fix bugs with the event handling. The
problem (I think) was with the ordering of the when() statements and the order
of execution and evaluation. Hopefully that has been sorted out
now. The code will be tested later this week when I get back on campus.
Ken Mailand
I contacted Keita Kawabe @LHO 7-21 re. the 4 element mode
cleaner cavity, and I am waiting for further information to begin a detail shop
drawing.
Lee Cardenas, Liyuan Zhang
OTF Lab. (W. Bridge)
The white Ceramabond, and disks of TRA-BOND #2254 color light brown epoxy
are IN.
Cavity is locked and we are taking measurements everyday. these epoxy samples
appear clean and there is no evidence of contamination
as yet. We'll continue taking measurements.
Absorption Test Measurement prototype in progress
New sapphire mirror already annealed are the one that it is going to
be tested for absorption. We are preparing the set-up of the optics. and
new alignment for the 30 watt laser, as well as mode match.
Scatterometer system in progress!
We have installed the scatterometer head after a severe modification.
We took new measurements as to find exactly how much more space is needed
between the scatterometer base and the top of the mirror. The space needed is
exactly as calculated to be 1.125" inches. Therefore, we need new
shorter post for the mirror holder.
The Quantronix 60 watt laser is in progress.
OTF Lab at Lauritsen ROOM 38
Cavity #3
The cavity is locked with (6) disks of TRA-BOND #2151 color blue epoxy and (4)
disks of TRA-BOND #2902 color silver epoxy. Both are in.
No evidence of contamination as yet
we are continuing taking daily measurements.
Cavity #2 Test cavity optical set up is still in standby
PSL Laser lab Laser in standby
no report
no report
Simulation and Modeling
(Bhawal)
Weekly Physics Meeting
------------------------
Luca Matone presented the analysis the 25MHz phase camera image taken on
transmission of the Output Mode-Cleaner with H1 locked on a Michelson bright
fringe. Good agreement between the fit and the model was found indicating that
with the current setup the beam is astigmatic and made up of a significant
amount of higher order modes. Monica Varvella described her e2e-simulation work
on 29 MHz control of Mach-Zehnder interferometer.
LLO WFS meeting
----------------
Attendees: Andri, Gaby, Valera (LLO), Matt, Hiro, Biplab(Caltech) In the
meeting a number of problems that need proper understanding of the system were
described by people at Site. One of the strange problems is that the
demodulation angle of the WFS1 signal changes, in some cases by almost 90
degree, after the "Q-phase" is fixed using Michelson configuration.
We discussed how modeling could help in understanding and operation of the WFS
system at LLO especially after the interferometer comes back into operation.
Mirror phase map
--------------------------------------
(Xiao, Hiro) Xiao is trying to extrapolate the mirror phase map to cover all
the mirror surface (measured within 15cm diameter, actual coating covering up to
24 cm diameter).
The covered region is fit using Zernike Polynomial using up to 36 Wyko
terms and calculate the noise RMS. Add a control band between 25 cm to 30 cm of
diameter with a value of the average. Then do the Zernike polynomial fit using
the measured data (weight of 1) and the control band with varying weight
(changing 0 to 1), which is used to regulate the outside behavior. Different
weight in the control band is used to generate a few sets of extrapolation for
systematic study. These fit curves with noise is used to smoothly extrapolate
the data to outer side are. The algorithm development is almost done, and a
fine tuning (although cosmetic) is being done to make the connection region
(real data and smooth fit) smooth.
FFT-e2e and Thermal lensing and BS curvature
--------------------------------------------------------
(Hiro) The work was continued using FFT and e2e to analyze the effect of the
thermal lensing and BS curvature.
As to the thermal lensing, based on the suggestion of Phil Willems, a new
map was made which has the distribution of the thermal model except for the
central region within 4.5 cm where the shape is a simple lens ( a + b*(x^2+y^2)
). The sideband gain with this thermal lens shows the almost same result as the
thermal lens which represent a pure lens. This means, by correcting the thermal
deformation in the central region, the thermal compensation can be improved. As
a possible explanation of the necessity of the excess heating, Phil suggested a
residual lens due to the AR side curvature and the substrate inhomogeneity.
Based on the FFT run, it was found that, in order to account for the amount of
excess power, a very strong lens is needed. Phil learned from Gari that the
residual lens is pretty small, and this possibility is not likely the
explanation.
Validation of the FFT code and modification of e2e code are going on to
validate the BS effect predicted by the modified FFT code and to lock LIGO like
LSC.
Alignment Control of LIGO and mirror phase maps
----------------------------------------------------
(Biplab) Mirror phasemaps introduce asymmetry in beam profiles which affect WFS
signals. Work on neutralizing this effect by calculating equivalent angles of
mirrors and correcting that by proper tilt-offsets is going on. Once this
correction is made, a proper estimation of the actual effect of mirror maps on
LIGO performance will be possible.
Mach-Zehnder Interferometer
-----------------------------------
(Monica) The e2e Mach-Zehnder design changed in order to move the control on
the mirror where there is the PZT; the feedback filter has been designed as in
the real Mach-Zehnder (1 pole at 22O Hz at the moment). Tests about error and
control signal have been done. 40m/AdvLIGO e2e optical configuration is ready
and has been tested with a single EOM at 33MHz. The others EOMs will be insert
soon: tests using the previous EOMs configuration (in series) and then the new
one (with Mach-Zehnder) are foreseen.
Code development and maintenance
-----------------------------------
(Melody) Worked on revamping the modeler's parser to make it more
efficient and maintainable.
Alfi
---------
(Melody) Finished fixing PR 468.
Modifying the Primitive Settings dialog to display the FUNC_X data
variables in a friendlier user interface. The dialog will show the member
variables in the table instead of having to look at C++ code.
Data Analysis Activities (Lazzarini)
Creighton:
Modified the pulsar Condor python script to use the new FrComputeFStatistic,
and to store input data and results in an indexable, easily-retrievable manner.
Mendell:
Ihave finished the first version of a new LAL function,
LALFastGeneratePulsarSFTs, that will speed up the Monte Carlo simulations
performed by the CW group. I am in the process of debugging and documenting
the function, and will submit it to LAL by the end of this week.
Shawhan:
* Set up to run the inspiral search code on S3 data on the Caltech LDAS cluster
using Condor. Had to get help from various people to resolve problems
with certificate authentication and data cataloging.
* Continuing to work with SURF student Matt Wroten on inspiral filtering and
waveform consistency test studies. LIGO Data Analysis Software/Hardware
Activities
Yakushin:
Condorizing DMT version of waveburst: tested that ROOT can be used under
Condor, writing a function for getting frames into waveburst.
Software Systems (Blackburn)
Anew sanity check on frames has been added to the createRDS user command to
check that the dataValid flag in the FrADCData structure of frame files is set
to zero indicating a "good" dataset. This flag has been tested this
week and uncovered a non trivial amount of data which doesn't satisfy the
"good" condition from the S2 and S3 science runs. There are channels
that do not have the value of zero or the CDS standard value of 0xbad
indicating an issue with the data acquisition. This has been reported to John
Zweizig. Some of the channels that have been found to have an issue with the
dataValid flag from the science runs thus far are
For S2 Run:
H2:IFO-ACTIVITY_STATE
H2:IFO-ACTIVITY_INDEX
H1:IFO-ACTIVITY_STATE
H1:IFO-ACTIVITY_INDEX
L1:LSC-ETMY_EXC_DAQ
L1:IFO-ACTIVITY_STATE
L1:IFO-ACTIVITY_INDEX
For S3 Run:
L1:LSC-REFL_Q
L1:LSC-DARM_CTRL_EXC_DAQ
L1:LSC-ETMX_EXC_DAQ
This is not an exhaustive search, nor is it known if these issues are present
during the entirety of the run or only found in the small snippets of data we
looked at. It does indicate that a more careful look into what the framebuilder
is writing into the dataValid field of the FrADCData is needed.
New code is nearing completion to allow different I/O characteristics of
different devices (file systems) to be optimally tuned on a per device basis to
improve overall I/O performance in LDAS. This will not result in a major
improvement (order few percent to roughly 10 percent will be typical), but it
does give us greater flexibility to explore new file systems without impacting
currently optimized technologies.
The issues with generating the time intervals of frame data available under the
diskCacheAPI have now been resolved. A single threaded call is now made by the
TCL layer per job to generate the list of time intervals for display in the
controlMonitorAPI's client window. All problem reports associated with this
process are now ready to be closed out.
Began making enhancements and working on open problem reports associated with
the CGI script used to apply and process requests for LDAS accounts. This
includes inproved formating and colorization on the existing pages.
Worked on makefile changes necessary to support the newer Operating Systems
that have subsecond mtime resolution.
Completed all system and integration tests without issue. New results are
posted on the web and checked into CVS.
The managerAPI no longer reports duplicate frame file names in the resultant
from diskCacheAPI queries in the email returned to the user. This fix addressed
problem report 2527.
The gps time conversion algorithm is not detecting entry of negative GPS times.
A new problem report has been opened on this and code to fix the issue is
currently being tested on the Tandem-V LDAS system.
The issue of the mpiAPI starting multiple wrapperAPI masters on the same node
is still open and work continues to identify the solution.
A meeting was held with technical representation from all software applications
that perform I/O on frames to determine the impact of changes to make RDS
frames longer and reduce the number of files that are stored on our file
systems. The meeting was very productive and everyone was in favor of
lengthening the RDS frames via changes to LDAS, though a determination of the
structure of this data within the frame file itself is still under evaluation.
In addition, the possibility of lengthening the raw frames was discuss, but the
current hardware technology used by the framebuilder limits making frame much
longer that a factor of two over the current size and time length. A second
meeting is scheduled for next week with the summary and recommendations to be
presented to the LSC Computer Committee (originators of the request to lengthen
RDS frames).
Hardware Systems (Anderson)
Caltech
-------
(Dan Kozak)
* Continued the transfer of files from HPSS to SAM-QFS. Also continuted
deleting files in HPSS after confirmation that they were successfully
transferred. Did a full listing of the remaining files in HPSS and
determined that we should be completely done in less than 1 month.
*Restarted various parts of HPSS that crashed so that the above could continue.
* Set up ldas-suntest5 to have read-only access to /archive via the SAM-QFS
shared filesystem.
* Moved two 9940B drives from the production system (ldas-archive) to samtest
for continued testing of SAM-QFS 4.1 and relabeled more tapes for samtest to
use.
* Tried to figure out why m26 doesn't masquerade as ligo.caltech.edu in
email. Now this has been narrowed down to why doesn't the MH comp command
get it right when /bin/mail does...
(Hari Pulapaka)
* Added some documentation on ldas-gridmon on using the cluster effectively.
* Working on setting up grid cvs on ldas-sw.
* Wrote the storage module for 1% data transfer testing from the sites using
LDR.
* Setup the Matlab frame channel software on the cluster.
(Al Wilson)
*Finished test, and put back on-line node7 in the test system Replacing MB in node8.
Should be ready for testing by Friday.
* New software and firmware for the 3ware card is out. Installing on our test
unit for evaluation.
(Stuart Anderson)
* Ran fibers and connected ldas-suntest5 to the LDAS SAN so it can run SAM-QFS.
* Continued testing SAM-QFS 4.1.2. Sun has opened an internal bug id for the
one observed kernel crash when doing a large recursive release (bug id5074546).
* Enhancing the SAM prestage tool to keep data flowing from tape to disk ahead
of user requests.
* Worked with Larry to resolve an NIS+ hostname resolution problem with the new
Grid software.
* Updated LDAS web servers to the latest Apache release.
MIT
---
(Keith Bayer)
* Working on dataserver crashes.
* Continue to work on LDR transfer of S2 L1 RDS data.
* Purchasing another pcraid.
* Replacing failed drives in pcraid#3.
* Patched GSI-SSH on ldas-jobs, ldas-pcdev1, ldas-grid.
* Restarted mit ldas with new credentials.
Livingston
----------
(Igor Yakushin)
* There was a double disk failure in t3-4: u1d8 and u1d9. The disks are
replaced, no data lost.
* Installed matlab and matlab compiler on ldas-grid.
* Helping Ken Franzen to get started with Condor.
* Helping Shyang Wen to learn how to get data he needs into matlab.
Hanford
-------
(Greg Mendell)
* The full raw frame files from fb1 at LHO are unreadable from July 20 and 21
2004 for this GPS interval: [774379744-16 774482192). They fail make
check with this error:
Sequentiel file reading. Please wait....
Read Error. Last errors are:
*** FrError: in FrError FrRead error:Error 0
*** FrError: in FrReadVL error reading bank
*** FrError: in FrVectRead : Record length error: nBytes=123157225
nBytesR=122496976 length=65644
The reason for this is that channels with complex heterodyned data were
added to the raw frames for the first time. Dave Barker was informed of
the problem and the channels have been removed until the framebuilder code can
be updated to fix the problem.
(Ben Johnson)
* Performed a 12 hour fully-loaded cluster, humidifiers on etc., test of
the the new air chiller on Wednesday. The modifications to the water bypass
valve on the air handler appear to have worked, as there absolutely no problems
with the new chiller turning off due to water flow problems.
* Researching 3510 disk->FC port mapping. Port 5 of fb0's 3510 has been
connected to LDAS's FC switch. A test to see if the units disks can be seen on
the LDAS fabric will occur on Thursday afternoon, 7/22/2004. fb0 will be
brought down to perform these tests.
* Fixed bad disk on defiance IDE RAID.
* Published L1 and L3 RDS one-percent/postS3 RDS data to gateway's LDR
instance. No word if CIT can see the metadata yet.
* Received 2 new DIMMs for node109. It has been repaired and is now a fully
functioning node; for now.
* spare parts T3 (t3-25) on oldgateway setup with new UFS filesystem. approx.
400 GB of raw frames files are now on it for testing.
* fb1 was producing bad frame files for Tuesday and Wednesday. CDS put the new
heterodyned complex channels into the stream, causing framebuilder bugs to be
revealed. The channels have been removed and the framebuilder code is being
debugged presently.
* Working on small presentation for the ligo-dc telecon on Friday, July 23.
This will regard an examination of S2 data corruption; in short, S2 data was
also affected.
General Computing (Wallace)
MIT:
(Keith)
-Windows desktop troubleshooting
-Windows laptop troubleshooting
-Continuing to test licenses for MIT matlab installs (I think they've got ones
that work now)
Livingston:
(Shannon)
* Current bandwidth usage can be seen at
http://teche.ligo-la.caltech.edu/mrtg/LLO-Router/130.39.245.1_1.html
* Archived bandwidth usage can be seen at
http://teche.ligo-la.caltech.edu/mrtg/archive/
under the dated folder
for the week of interest.
* Made a couple of firewall changes for some UDP ports.
* looking into an issue on a Linux box where it runs out of memory every two
weeks or so. This is the machine that handles DHCP, mrtg, BigBrother,
etc. When the box runs out of memory, it locks up solidly and the only
way to reboot it is to hit the reset switch. The main problem is that
when this happens, no one can get DHCP addresses.
* Still working on rebuilding the applications share. I have added things
like Matlab, gcc-3.4.1, gnu ld (binutils), Mozilla, etc. We are still not
back to the point we were before the disk crash, but it is getting there.
I have spent many hours in the last week compiling software. So far, I am
pleased with the disk array that I purchased to replace the Linux box that was
sharing out the applications.
* working with a Sun rep to find out if a couple of SAN ideas I have will
work. This is an idea that I have on how to handle the user web pages and
server if we move all of the Sun boxes to an internal network with only the web
and mail boxes on the DMZ.
* ordered a license for F-Secure anti virus for us to use when Norton decides
to die because of a virus or other problem. There have been several
instances when a machine becomes infected with a virus and Norton will not
work, so we cannot clean it. We just had an instance like that this week
when Tom was trying to clean Bagle.AG@mm off of a machine.
Hanford:
(Christine)
- Network usage can be seen at
http://www.ligo-wa.caltech.edu/~christin/mrtg/
198.129.208.1_198.129.78.122.html
- Started planning and purchasing of equipment for the F2F, LSC and Summer Camp
meetings coming up in Aug. I will be installing wireless radio boosters
and NAT routers.
- Working on setting up one of the new SunBlade 1500 computers to be the DHCP
server.
- Continue to setup the rest of the new SunBlade 1500 computers.
- The usual user support for email problems, setting up new user accounts, SURF
computing problems, and etc.
CIT:
(Mike)
-NTSRV: Updated OS security/critical patches and Anti virus software.
-Synchrotron: Worked on a surf student's workstation, behind a dead monitor. I
replaced this monitor and updated security patches and anti virus software on
this computer.
-Wilson House Front & Back: Updated OS security/critical patches and office
settings on multiple workstations.
-Don Webber: I swapped outhis CTR monitor with a flat-screen. I have surplus
this CTR monitor, due to popping sounds coming from inside the monitor.
-Sander Liu: Worked on a software installation (MathCAD) very time consuming.
This is an older version of MathCAD that I could not get to installed on win
2000 pro. He is going to have to purchase an updated version of this software.
-Larry Wallace and I worked on Irene Baldon's workstation due to a virus. Her
computer was definitely infected with the
<mailto:W32.Beagle.AG@MM>W32.Beagle.AG@MM
virus. I was able to clean this workstation up; user is back up and running.
-I setup two workstations for a surf student/visitor for Wilson House Front. I
also installed additional software for the surf student and setup e-mail
settings plus showed user how to run updates on windows and anti virus
software.
-I am working on upgrading all our Solid Works users to 2004. This upgrade is
taking me quite awhile per workstation.
-Other Misc. onsite/phone user support.
(Veronica)
- LSC website: Posting updates to the August meeting website as they arrive.
Updates to other parts of the LSC website. Working on the automation of the S1
author list. Working on posting a [big] new batch of MOUs/progress reports.
- LIGO website: Updates to various pages and usual upkeep. Tutored Sharon on
basics of html and web updates and provided user support. Worked with JoAnn
Boyd helping her on DVD authoring using iDVD. Prepared a high-resolution image
for Scientific American.
(Lisa)
- Spent quite a lot of time responding to the latest virus that was going
around.
- Working with Larry to determine which applications need to be installed on
the new application server.
- Began demo'ing mozillato see if it should be rolled out with the new
application server. I'm not at a point with this where I have anything
concrete to report.
- Have done a number of file restores this last week.
- Looked briefly at what it would take to setup an acrobat 6 interactive pdf
form.
Mail Stats 07/15 - 07/21/04
Messages Accepted:
Spam Rejected:
Viruses Rejected:
False Positives:
Total Mail Thru:
(Larry)
-Assisted in taking care of machines that had been infected with a virus. One
of the machines started sending out e-mail which was easy to track down the
other two machines had viruses that were probing other networks they were a
little more difficult to track down since they were using DHCP, we used the MAC
addresses and were able to track down the units and get them repaired.
-Assisted in some of the logistics for the upcoming LSC meeting at LHO.
-Spent a deal of time working with purchases and reconciling. The new printer
is at the CIT loading doc. No time estimate on when shipping and receiving will
be delivering the unit. The Spyware detection software and licenses should
arrive this Friday and then we will start distributing it. The quad CPU is on
order and should arrive next week.
-It appears the electricians are finished with the computer room and we are now
waiting for the fire suppression unit to be installed.
-Assisted a number of new SURF students with various items. Another day or two
and they should be settled in.
-Assisted/assisting Dave Barker on some network issues on the network swapout
being planned. Just as an interesting side-note the ATM system that was
installed has been working for about 6 years. Not too bad.
-Working on a number of configuration changes for user accounts. This project
will take some time and should cover a number of months.
-Regular user support and assistance in moving equipment and office items for
different people on the project.
From: "Thomas Frey"
<tfrey@ligo.caltech.edu>
Progress Period from 07.09 to 07.22
Out of the office sick on July 12, 13, and 14.
·
·
See http://www.ligo.caltech.edu/~tfrey/index.html
for a complete listing of all project related cost and schedule data.
Accomplishments:
·
·
Sub-system
PLANNING activities
§
§
ISC - Finished data
input / changes. Posted data for review.
§
§
Finished working on AOS
and IO. All relevant scope has been moved to ISC.
§
§
Split all
"Sub-System Management" tasks into two phases. One task for
development and one for production.
§
§
Input all task changes
and cost changes into the cost book database, as a result of the
"Sub-System Management" task split.
§
§
Started the input of
all progress data, and reflecting changes above into the current progress
schedule.
§
§
Prepared for, and
executed, meeting with Phil and Stan, as schedule by Albert, to discuss how to
improve the author ship list development process.
§
§
Prepared report showing
milestones for COC, SUS, LASTI, Install, and PM, as requested by Carol.
§
§
Started work on
preparing web space for posting Adv. LIGO reports. ("The Whole
Enchilada")
§
§
Continue to evaluate
the effect of hammocks on percent complete calculations, and limitations of
resource / cost loading exports.
·
·
ROSTER DATABASE:
§
§
Input additional author
ship list corrections and changes provided by Peter Saulson.
§
§
Posted updated source
files for Albert's use in generating the authorship list.
§
§
Started work with Irena
to provide Barry with information regarding FTEs and Institutions.
·
·
COST BOOK DATABASE:
§
§
Re-evaluating the cost
code structure, in anticipation of funding that crosses WBS phases.
From: Larry Jones <ljones@ligo.caltech.edu>
Advanced LIGO Seismic Structure
SEI Structure:
ASI has completed the drawings for the seismometer pods. ASI plans to
release drawings for fabrication in packages, serially, by structure stage.
LIGO's approval for the start of fabrication is awaiting review of expected
costs. Drawing production is slower than expected.
ASI's "bottom-up" cost estimate for fabricating the BSC structure
prototype is expected at LIGO yet this week, and the cost estimate to complete
the contract is expected next week. An updated schedule is also expected.
Progress is continuing on closing out action items generated at the Design
Review.
The pod feedthrough flanges have been ordered within LIGO.
The HAM structure Design Review is scheduled for
Actuators:
Vacuum bake and RGA scanning were completed on the small prototype actuator on
July 21, with good results. Mechanical inspection was performed on the large
prototype actuator, with no significant problems found. The large actuator was
recleaned to correct problems with the initial cleaning, and the vacuum bake
was restarted.
Formal acceptance of the prototype actuators was given to the contractor, PSI,
initiating Phase 2 of the contract. This involves the production of 6 each of
the actuators, small and large. Delivery is expected by
A sample of the cleaning solution (APCA 265, sodium tri-basic phosphate) used
by Branford Wire, a possible contractor for precleaning the mag wire, was
received and will be tested for effectiveness in removing paraffin and checked
for potential damage to the HML polyimide wire insulation.
Optical contamination cavity testing of the potting compound (epoxy) Tra-Bond
2254 and the adhesive Ceramabond 835M continues to look good.
Displacement Sensors:
Optical contamination cavity testing of Tra-Bond 2902 (silver) coupons and
Tra-Bond 2151 (blue) coupons continues to look good. Additional coupons have been
made of Aremco epoxies as possible replacements for the Tra-Bond materials;
these will be vacuum baked and RGA scanned prior to placing into the optical
contamination test.
Seismometers:
Nothing new
Galling/Dusting Test:
Nothing new.
Other:
Planning is proceeding on the design and sourcing of a larger vacuum bake
oven for the quad structure.
From: Janeen Romie <romie_j@ligo.caltech.edu>
AdLIGO Suspensions
Updating the ETM Upper Structure Product Design Specification,
T040141, with comments received. Also, the failure and repair paper is
generating good communication.
Held an installation fixture design meeting this morning and got a lot
accomplished. We will be coordinating this work at the monday morning design
meetings. We are thankful that Ken Mason, Ken Mailand and Doug Cook will be
able to support this effort.
Working with procurement on the quad blade RFQ. We must start the process
again. We have streamlined the notes on the blade drawings to avoid confusion
and forced vendors to consider bending only, as opposed to EDMing. Procurement
will be sending out RFIs today and will hopefully be sending out a second round
of RFQs next week. It is still out hope to have a
Worked with Calum and Mike P-L on releasing all of the mode cleaner drawings.
Met with Dennis last week on the DCN process and on mechanical drawing
guidelines.
Attended the output mode cleaner meeting last thursday to get a heads up on the
design development.
Received training on the pendant crane in the Synchrotron.
Coordinating with Justin on a noise prototype design kick-off in August.
From: Helena Armandula <ahelena@ligo.caltech.edu>
Advanced LIGO Coatings Development
LMA
Gregg was able to trace the thin missing substrate coated with Formula #3. It
is once again on its way to MIT.
The next coating run with Formula #4 will take place on the large VIRGO coater.
This run will test the ability to deposit doped materials on this chamber.
Several parts will be coated: One 3"dia. x 1" thick sapphire; a
similar size fused silica substrate, a 3'' dia. x 0.100" thick fused
silica part and several 1"dia. test plates (sapphire and fused silica).
CSIRO
Coating Kenji's substrates.
From: "Mark Barton"
<mbarton@ligo.caltech.edu>
This week I worked on the forthcoming 02 rev of the ALIGO
SUS DRD, T010007. I also computed several more asymmetrical quad pendulum
models for Carolyn Cantley, to explore different ways of hanging an optic to have
its HR face at a prescribed angle.
From: Peter King <pking@ligo.caltech.edu>
From: Bill Kells <kells@ligo.caltech.edu>
Pertaining to AdL R&D I've been contributing to:
1. Issues on the FS/ Sapph. choice. In particular discussions with P. Willems
on the distortion effects on signal SBs. Also following the
"in progress" study
of smoothing of sapph. absorption inhomogeneities via high T
annealing.
2. Setting up for detailed (lab) examination of large area HR coating point
defect [scattering].
We are planning , in near term, to convert the OTF scanner
over to this task.
3. Ongoing study of interferometer noise at the AdL level. The leakage of
radiation noise back into
the interferometer via TM mirror scattering. This is the one
I hope to present at the August LSC.
From: <felfre@caltech.edu>
Barbara:
This week i retuned the blade reach resonant frequency to approximately 0.5 Hz.
About the circuit for the piezo: there are some weird problems with
channel 1 and 4. So now I'm reassembling these two channels. Also I'm starting
to assemble the driver for the stepping motor as soon as the machine shop
gives me the vacuum connector.
Anamaria:
I've taken more data and analyzed it. I was out on Monday for the SURF Goldstone
tour. I will leave at the end of this week for 5 weeks and will be back August
30th to continue my SURF.
Nicky:
I was ill, but now I'm back. I've been working on the setup for my experiment
and doing some drawings.
For additional information about this report, contact whitcomb_s@ligo.caltech.edu