Weekly Report for Week Ending May 27, 2004


 Exec. Comm. Agenda

Highlights

LSC

Administration

Hanford Observatory

Livingston Observatory

MIT

Caltech

Detector

40 Meter

TNI

LASTI

Data Analysis

Adv. LIGO Development

Past Weekly Reports


The LIGO Executive Committee Agenda:

 No Meeting because of Holiday


Special Items:


Special Announcements:

 


Weekly Report Highlights
 


LSC Issues (Saulson)


no report


LIGO Laboratory Administration (Lindquist)


 

 

.


LIGO Hanford Observatory (LHO) and Interferometer Operations (Raab)



 Summary of Commissioning Activities at LIGO Hanford Observatory  (compiled by M. Landry)

Livingston-like weather resulted in some unexpected sparking in the mass storage room on Friday night.  No long term problems were noted but investigation is underway to see if we are susceptible to future strikes.

First-time heavy use (i.e. all 200 nodes) of the LDAS Beowolf cluster loaded AC units and tripped power to cluster racks.

Thankfully, elog file are no longer editable!

4K IFO
The 4k digital IO WFS system was installed, necessitating a ASC front end and EPICS interface upgrade.  AM laser diagnostics were performed and repeated.  The IO WFS2 loop was closed, but WFS1 needs more work.

The optical layout for the output mode-cleaner is summarized here.  The mode structure of the AS port and OMC was analyzed.

2K IFO
The 2k was brought to better locking performance throught the weekend, described in elogs and briefly summarized here, and with links, here. The effect of IO WFS on the MC_F spectrum was detailed.


LIGO Livingston Observatory (LLO) and Interferometer Operations (Zucker)


L1 Commissioning highlights (Zucker)
---------------------------------------------------------------------

Main thrust continues to be HEPI installation and commissioning. The HAM actuator installation in the corner station is now complete, and the crew has moved on to BSC2. Oddvar has designed an adaptation so IOT1 can roll back in close to HAM1; we anticipate doing this and getting the mode cleaner back on line by end of next week. Piping is continuing on schedule.

At the X end BSC, two GS-13 seismometers were installed on the crossbeam as extra-loop witness sensors. An exercise to rezero the position dial indicators using DC commands to the actuators succeeded, although it absorbed more of the DC range than wanted. Another iteration may be indicated to parallel translate to the best collective average "mid-range".

Rupal did some realignment of the PSL EO modulators to achieve a significant reduction in residual RFAM. He also is nearly done updating the PSL table layout to  be consistent with H1 and H2 (FSS pickoff before the PMC).

In other developments, Rolf installed and successfully tested the latest version of the LSC and ASC, EPICS (for Linux), framebuilders, IO WFS, AWG and ADCU code.

At the Y end, relocation of interferometer electronics to the new rack system was completed, along with the HEPI electronics installation. Testing is also concurrent. The corner station EMC-shielded rack and power installation is nearing completion in the CDS High Bay (formerly known as Clean Storage). The current plan is to cut over the corner station in two stages this summer, first moving IO and SUS crates and cables and then, after testing, moving LSC and ASC.


L1 Commissioning (Frolov)
---------------------------------------------------------------------
I wrote the draft of the technical note on intensity noise coupling measurement. I also started setting up the TCS optical benches in the optics lab.

Safety (Rich Riesen)
---------------------------------------------------------------------
Continuing work on Safety Procedures.
Found no site safety concerns during my weekly site tour.
HEPI installation crew continuing excellent safety practices.
Shipped scissor table to Janeen at CIT.  It has arrived.


LLO Seismic retrofit (Rich Abbott)
---------------------------------------------------------------------
1.  Actuator installation is now taking place on BSC2.  All HAMs are complete with the exception of bolting actuators on HAM3

2.  Electronics installation in the Y-end station is essentially complete.  We are in the process of powering things up and checking connections

3.  The piping contractor is still on track for completion during the week of 7 June

4.  Inventory is under way on materials for the LASTI but not complete as of writing



LLO Seismic retrofit (Oddvar Spjeld)
---------------------------------------------------------------------
Completed
- received the remaining HEPI boots for LLO (10 total, 2 spares)
- completed assembly of (4) HEPI BSC actuator housings for LVEA BSC #2
- re-designed mounting bracket for HEPI housing circuit box, quote requested
- follow-up of IOT1 Leg Modification fabrication, delivery LLO Tuesday 6/1

Ongoing
- assembly of hydraulic actuators for HEPI housings
- started assembly of HEPI housings for the next LVEA BSC chamber
- updating HEPI drawings and models on the PDM Server


General computing (Roddy)
--------------------------------------------------------------------
* Current bandwidth usage can be seen at http://teche.ligo-la.caltech.edu/mrtg/LLO-Router/130.39.245.1_1.html

* Archived bandwidth usage can be seen at http://teche.ligo-la.caltech.edu/mrtg/archive/ under the dated folder for the week of interest.

* The Bell South circuit has been stable for the last 9 days.  I have seen no interface resets.  This is much better than what we have seen almost since the circuit went live.  I will continue to keep a close eye on it over the next month.

* Added several user accounts on GC.  SMC is still not working perfectly, but several problems have been solved by moving to the new server.

* The new web server is mostly set up.  GCC, associated gnu tools, Apache 2.0.49 are all installed.

* I have been going through the web pages and archiving obsolete pages. I have also been going through the existing pages that will remain and editing where necessary.  Currently there is about 11 GB of files.  Some of this will be archived, but much of it will have to stay.  Most of the files are pictures, etc.


CDS (Parameswariah)
--------------------------------------------------------------------
Rolf and Alex visiting LLO over the weekend. Changes made to epics systems, hepi ey installed, frame builders upgraded.

fb1 upgraded to solaris 9 and running with the new code.

fb0 upgraded to solaris 9. Have got the A1000, D1000 and the 20 internal disks configured and mounted. StorEdge 3510 is still being configured. LDAS pointed me to software I need to get it up and running. Syskonnect Gigabit Ethernet Card which I installed was found to be bad. Ordered a new card.

Working on autogeneration of HEPI status screens. Testing some code to do this. This will help to generate status screens for all the nine HEPI systems.

Setting uptest point name resolver to resolv selected test point names from numbers.

CDS gateway2 - river upgraded to Solaris 9. User accounts and directories put back in. River back online. Didnt run into any problems while I was watching it over the past few days.

CDS gateway - london will also be upgraded to Solaris 9.



CDS software support (Khan)
--------------------------------------------------------------------
1) Helping Sany in his analysis of BSC Seismic coupling to the yaw motion of the optics.

2) Developing test software for ICS110B ADC board.


Data analysis (Yakushin)
---------------------------------------------------------------------
LDAS admin:

1) Configuring LDR on gridmon. Waiting for host/datarobot certificates to be approved to be able to complete the installation.

2) Configured a new T3 for dmt data. Now it needs to be mounted on the framebuilder.

3) Got two Fujitsu (instead of requested SEAGATE) replacement disks from SUN.

Data analysis:

1) Studied how waveburst event detection and reconstruction depend on the way the triple coincidence science time segments are divided into 120 second intervals used by the ETG: http://www.ligo-la.caltech.edu/~igor/TIMESHIFT. Presented the results at the burst telecon.

2) During the last week face to face waveburst code review meeting at LLO we found a minor bug/feature in the waveburst that caused event reconstruction to be done slightly differently than originally intended and described in the documentation (although quite legitimate as well). I compared the waveburst performance on the SG5 MDC frames for the current and corrected versions and showed that the difference is not significant: http://www.ligo-la.caltech.edu/~igor/BUGEFFECT. Presented the results at the burst telecon.

3) Helping Michele to learn how run waveburst production and postproduction scripts for waveburst review.

4) Together with Patrick Sutton trying to figure out what's wrong with SG13 LIGO-TAMA MDC frames (apparently the amplitudes of the injected signals are wrong while timing and and frequency seem to be OK).

5) Tested the effect of usize bug (now fixed) in the postproduction scripts: http://www.ligo-la.caltech.edu/~igor/USIZE


E2E analysis of suspensions (Yoshida et al)
---------------------------------------------------------------------
Under collaboration with Caltech e2e group, we investigated the coupling between translational floor motion and rotational/translational BSC1 table motions. We obtained the table's translational (in Y direction)/rational motions by dividing recorded ITMY's position/yaw motions by theoretical table-to-optic position/yaw transfer functions. We then computed the coherence between Accelerometer X/Y (ACCX/ACCY) signals and table's translational/yaw motions. ACCY and table's translational (in Y direction) motion show high coherence (>0.98) around 6 Hz, 10.5 Hz, 13.5 Hz, and 16 Hz. ACCX and table's yaw motion show fairly high coherence (>0.85) around 6 Hz and 13.5 Hz, indicating translation-rotational coupling via BSC stacks. ACCY and table's yaw motion also shows high coherence (~0.9) around 17.5 Hz. ACCX and table's translational (in Y direction) does not show clear coherence in the investigated frequency range of 0 - 20 Hz.


Detector/Technical Support (Coyne)



 CDS

see also the CDS weekly meeting minutes in the commissioning archives

CDS Software

Rolf Bork reporting

- Alex and I spent last four or five days at LLO. Main purpose was to update the systems to latest code versions, same as running at LHO. See elog entries for details.

 

- Ran into some problems at LLO running DTT. This turned out to be a problem with the Network Time Server (NTS) not seeing satellites. We had to "jump start" the NTS by connecting the antenna going to the DAQ controller. Russ is planning on moving some antennas and will make a new connection to NTS at that time.

 

- Got the software part of the DAQ going to acquire the HEPI spare channels. However, the cables necessary to connect Spare 2 channels are not in (waiting for cables from manufacturer). I still need to get the latest wiring diagrams for the corner station from Ben Abbott to get the spare channel readouts into the corner station HEPI software.

 

- Installed the HEPI EY VME modules and got that software up and running.

 

- Received an email from M. Landry that we need to start working microseismic feedforward for LHO. However, that system will be different than what was previously installed at LLO, so we need to work out the details.

 

- Still working the new LSC software for the 40m lab. We will schedule an installation/test time, probably next week, depending on their run schedule.

CDS Hardware

Jay Heefner reporting

 

Fiber Optic Timing Link (for HEPI compliance with RFI requirements) (Sander)

===============================

- Jitter measurements show ~10psec jitter on the 4MHz signal. This needs to be compared to the jitter on the 4MHz coming directly out of the GPS receiver.

 

Timing System Redesign (Flavio)

================================

- A draft block diagram has been sent to Daniel for comment.

- A draft requirements document should be available for comment next week.

 

Anti-Image Filter for Low Noise DACs (Mohana)

===================================

- Tests of the single op amp prototype should be complete by Friday.

 

40 M (Jay, Ben)

===================================

- Ben is working on the RF Distribution Drawings

- Ben is checking the PSL and ISS DAQ signals to make sure the gains on the whitening board are appropriate.

- LSC cross connect wiring is complete. Jay will modify the databases next week to add signals.

 

HEPI (Ben)

=================================

- ordered some 7-foot, 50 pin D-sub, Female - Female connectored  cables from Wilco Wire today.  This solves a connector problem for the HEPI Analog rack.

- The reworked 44-pin cables are shipping this Friday and should be in hand in Livingston on Monday.

- I have shipped 28 of the Pier Interface modules to Livingston.  They have all been tested by Don, and passed with no problems.

- There was a change in the rack location numbering for HEPI.  This change has now been reflected on my system schematics for both the Y-end, and the Vertex.

 

LSC PD Redesign (Ben)

====================================

- got the go-ahead from the commissioning group/RTRB to begin the process of making 10 new RFPDs.  The first step will be to gather all of the existing rework ideas together, and circulate it for comments.  I will do this later this week, and will go from there.

 

ISS (Flavio)

=====================================

- A modified version of the original servo has been installed on the 40 meter. Initial test results are very encouraging.

- Rana is working on a revision of the ISS requirements (originally written by Mike Z.)

- Flavio issued a block diagram of the revised ISS for review. Revised schematics to be issued soon for review.

 

EMI Upgrade (Jay, Mohana)

=====================================

- LLO LVEA SUS drawings are 90% complete.

- Feedthroughs and cables will be ordered next week.

 

Elect Shop (Todd)

======================================

- Continued stuffing and testing of Pier Interface Boards

- Cross connect upgrades for 40M complete.

- Inventoried PDs for the commissioning group.

DMT

John Zweizig

This week I modified the Data Quality monitor to allow exclusion of line features in from the Figure-of-merit bands. During S3 the power in the figures of merit bands was dominated by the narrow line features notably calibration, violin/internal mode and power lines. The figures of  merit effectively followed these line features and were correspondingly less sensitive to the overall IFO noise level that they were supposed to monitor.

 

I have also modified the DMT data accessor class so that it can be used to get frequency series data from frames. This has become necessary for the implementation of a frequency-domain calibration class.

PSL

PeterKing

I found some problems with the master oscillator monitoring circuit which I suspect is due to a grounding problem.  Each time either the master oscillator power monitor, or the amplifier power monitor, was connected the crystal temperature appeared to change by as much as 4 degrees.  The 10-W laser output power fluctuates by about 20-25%.

 

    I tried out a new photodetector circuit.  Unfortunately the bandwidth was woefully short of the design value, for reasons I have not figured out yet.  But I might have to check the photodiode capacitance to see if this is the limiting factor.

OMC

PeterKing

Quotations from the three coating vendors (ATF, MLD and REO) have now been received.  Delivery for all are 8 weeks ARO.

TCS

Mike Smith, Ken Mailand

Sent the uncoated parabolic mirrors to Cascade Optical for gold-coating. A revised schedule for assembly, installation, and commissioning of the LHO and LLO TC systems is awaiting approval. The schedule added an extra week of assembly to allow for  late delivery of the housing assembly. Installation will begin on 6/28, and commissioning will begin on 7/12.

Errant Beam Baffles

Mike Smith, Ken Mailand

Have been working with Ken Mailand to clean up the documentation for the errant beam baffles before submission to the DCC. LHO 4K and 2K are ready for submission.

Optical Contamination Cavities

Lee Cardenas, Liyuan Zhang

OTF Lab. (W. Bridge)
The test for contamination of (21) pieces of the twisted, shielded, teflon cables are completed.
 We are still taking ring down and beat frequency measurements
as well as the RGA of the chamber every other day. NO CHANGE

Absorption Test Measurement prototype in progress
The scanning for absorption of the15 cm dia. sapphire substrate is in progress.
the scanning are done at Z= 10, 15, 20, 25, 30 & 35 mm in depth.
We'll continue scanning at other depths in order to have better understanding
of the sapphire absorption.

The fabrication of the rods for the laser enclosure have been completed and
installed in place. We have found the need of three more rods and the modification
of the two rods of 27" inches. The plates being cut to size still in PROGRESS! as
the modification have changed the plates dimensions in lenght.

Scatterometer system in standby

OTF Lab at Lauritsen ROOM 38  NO CHANGE.

Cavity #3
The cavity is locked and we are taking ring down and beat frequency measurements every
day as well as the RGA for the chamber.

Cavity #2 Test cavity optical set up in standby for further samples. NO CHANGE

PSL.
The 10 watt laser alignment and mode match has been completed.
We (Peter and I) still have the power output not being stable as power degrades with time.
and the laser is temperature independent as we have change the temperature without noticing a significant change.  So far, we can conclude the power change it has to do with the power amplifier.
Next option will be to remove the Pockell cell(EOM) from the optical train and make a new alignment.

 


 

40 Meter Interferometer (Weinstein)



Thermal Noise Interferometer (Libbrecht)


no report


LASTI (Ottaway)


HEPI Installation and MC Triple Installation

Myron has installed the four piers on the the Xend HAM and the piers are now floating on springs. Preparation has begun for the preparation for the upcoming vent to install the mode cleaner triple pendulum. Laurent has been visiting Caltech to learn the fine details of the MC triple system.

LASTI Vacuum
We have installed a scroll pump to back the main LASTI turbo pump when we get to low vacuums (~1e-5 torr). This is to both save continued wear on the expensive high volume capacity backing pumps and to make the highbay significantly quieter. We had a diaphram pump fail, that was backing one of the small annulus turbo pumps. With this experience in mind Jon is pursuing a pressure guage interlock for the forline of the main LASTI turbo pump.

Controls for HEPI
Lei and Dave have been investigating the implementation of an adaptive feed forward system for isolation on the HEPI HAM system. This technique was developed by the Mech Eng department at MIT. Preliminary results are encouraging with a factor of at least 20 isolation at the Stack Mode peaks.

Ken Mason reports:
Laser Thermal Compensation
Several minor changes were made to the Camera box allowing easier access to the mirror mount adjustment screws and adding lateral adjustment to the camera. The drawings have been completed and supplied to the fabrication shops.

Triple Suspension Installation
Viewports and vacuum feedthrus have been ordered and shipped directly to Bob Taylor at Caltech for vacuum baking. In addition The stack spacers for the y-end HAM have been shipped to Caltech for clean and bake.


Data Analysis and Computing (Lazzarini)


 Simulation and Modeling (Bhawal)
--------------------------------
Collaboration with LAL / Orsay
--------------------------------
Hello and Barsuglia from Virgo LAL/Orsay visited Caltech to discuss the collaboration between Caltech and Orsay on advanced interferometer configurations. Alan suggested once again to pursue the 40 modeling using e2e as an important learning step, and it was agreed that Monica Varvella will work to develop a 40 m model based on Han2k and SimLIGO, existing LIGO I model. Hiro, Biplab, Bruce and Melody provided Monica with necessary software, tools and technical assistance. Monica is going to come back in July for one month, and for a longer period sometime after. Possibilities to have regular meetings between Caltech and Orsay have been discussed. Han2k model uses old LSC algorithm and it did not work as is, and Hiro is working to fix it.

Mirror phase map and FFT study
---------------------------------------------------
Hiro wrote a code to fit the mirror phase map using Zernike polynomial. One major use of this work is to extract phase map of BS by subtracting the power, the major aberration, and to see the source of asymmetry. LLO 4K BS has a small ROC, but the remaining aberration after subtracting tilt and power is worse than that of LHO4k BS. The image can be viewed at
http://www.ligo.caltech.edu/~e2e/images/LLOBSMap.jpg

Biplab produced field intensity profiles with raw mirror map data and also data with tilt removed. An example POY intensity profile in hot state of H1 can be viewed at
http://www.ligo.caltech.edu/~e2e/images/WA4KPOY.jpg

The study of the contribution of these mirror maps on WFS signals and changes in field profiles after the alignment correction is brought in is now going on. Note that FFT code does not have any control system in it so the correction is done manually after calculating WFS signals.

Code development and maintenance
----------------------------------------
Macro in e2e:
Hiro and Bruce worked together about the macro implementation. It is still a most complicated issue. Bruce is working to fix an inconsistency between Alfi and modeler and associated tweaks. Hiro is working to make sure that the macro is implemented as is documented.

Examples and documentation:
Hiro is working to update the e2e document to reflect the latest change in the e2e 2.0.1 release. He is also fixing some examples which need fixes associated with this update.

Alfi
----------
(Bruce)
    - Finished macro parsing (to not parse them.) (PR 457)
    - Working om port movement problems in external view. (PR 391)
    - Working on helping modeler in situations where Alfi
      has implicitly removed a connection. (PR 444)

(Melody) Fixing several problem reports.

LIGO Data Analysis System

Software Systems (Blackburn)

On Monday and Tuesday we met with Scott Koranda and Patrick Brady of UWM to discuss and plan out a new deliverable from the LDAS software group. The deliverable involves extracting the functionality in the diskCacheAPI for discovering frame files on a file system and making it into a standalone library that can be used outside of LDAS. In addition, we have been asked to deliver a testbed TCL driver script that supervises the library in a standalone process. Also, we've been asked to provide a Python shared object that allows the C++ diskCache library to be called from a Python script to be developed by CIT/UWM and possibly other LSC institutions. We have postponed work on LDAS tasks, making this our highest priority until delivered (hopefully in under 3 weeks). In addition, we have asked and been granted an extension on the next LDAS release as a result of this high priority critical path task. We now expect to have the next LDAS release at the end of August.

As of today, we have been able to construct the tarball of the source code for the standalone diskCache library using LDAS's build rules environment. This work has only been attempted on a test system and not migrated into CVS yet. There, the C++ library has been separated from the TCL SWIG shared object and a new Python SWIG shared object has been created. One of the standard LDAS unit tests fails as a result of the gross extraction process to remove dependencys on LDAS from this new deliverable. This will be resolved in short order.

On the LDAS side, work was carried out to clean up several open issues involving ldcg packages and thier associated SINSTALL rules in the build-package script.

Effort to port LDAS to the Solaris Compiler Suite continued up until the definition of the new task to deliver a diskCache Library was put on the table.

Also started working on supporting different I/O characteristics based on different file system types up until the new task was defined and given highest priority.

An issue with LDAS system emails was discovered at LHO and demonstrated on other LDAS systems. The problem has never shown up on any of the CIT LDAS systems but is thought at this time to be a race condition at the socket level when connecting with the mail server at LHO. This effort has also been placed on hold as we work on the diskCache Library task. However, a PR does capture what has been learned and proposed as a solution.

In the controlMonitorAPI's client graphs additional time standard information has been aadded to the windows and printouts.

Work has started on providing a GUI to graphically view what frame data is available under the diskCacheAPI's hash table.

Fine tuning of a timeout parameter for the metaDataAPI was iterated over the weekend run. A second iteration will be needed this weekend to determine if doubleing the timeout period is acceptable before commiting changes to CVS.

Worked on PR 2474 associated with the insertion rate variable in the eventMonitorAPI. C++ changes will now be needed to resolve this open PR.

Carried out integration and system testing on the following: compression test, createRDS, RDS verification, NDAS verification, datacond MDC, non-standard DSO, DC to frame, FrProc Read/Write tests and updated results; monitor dev test results. Also ran frame tests and added new exception tests to the metadataAPI testsuite to verifying fixes in metadataAPI for DB2 messages, including deadlock messages.

The diskCacheAPI PR 2455 is ready for CVS. It required changes to both C++ and TCL code as the getHashNumbers() interface had to be changed. Started working on PR 2526 also. Code for PR 2407 is now being tested on tandem-5 and LDAS-DEV.

New code is now being tested to throttle the number of jobs in any LDAS API, as well as, code to throttle number of jobs in the data- ConditionAPI based on current memory usage.

The LDAS Project webpages on the DASWG website have now been updated to reflect information that is current as of the LDAS 1.1.0 release. This includes new pointers to the FAQ, major changes, problem reports closed with that release, and links to the new dataCondition library used external to LDAS.

Hardware Systems (Anderson)

Caltech
-------
(Dan Kozak)
* Continued retrieving and deleting data from HPSS.
* Unwedged ldas-archive staging a couple of times.
* Imported and FrCheck'd E10 at CIT (the tapes had been shipped but the
  metadata never incorporated into the /archive filesystem).  LLO done,
  LHO still being FrCheck'd.
* Exported tapes of post S3 data at LHO/LLO for shipping to CIT.
* Made some refinements to the scripts for moving SAM-QFS metadata  between
  sites in preparation for firing up the tape shipment pipeline again.

(Al Wilson)
* Replaced memory in dataserver in the dev system.
* Another disk failure in the IDE raid test unit. Replaced and rebuilt  the  array.
* Set up a test bb system for using Ben monitoring software. Still  testing the  reporting to BB.

(Stuart Anderson)
* Installed and started tested Fedora Core 2 on: laptop, desktop, and  server.
* Verified LDAS passes all expected unit tests on Fedora Core 2.
* Finished publishing old S1 L0 data to LDR (several LDR restarts).
* Ran some createRDS jobs to fill a small hole in S2 RDS data for   Condor users.
* Discussed plans to integrate the LDAS diskcacheAPI and LDR for S4 to
  provide automated data discovery.

MIT
---
(Keith Bayer)
* Finished downloading the S2 MDC frames using LDR.
* Restarted LDR on S2 L1 RDS frames.
* Successfully had Laura test the condor installation   and run jobs on the cluster.

Livingston
----------
(Igor Yakushin)
* Configuring LDR on gridmon. Waiting for host/datarobot certificates
  to be approved to be able to complete the installation.
* Configured a new T3 for dmt data. Now it needs to be mounted on the   framebuilder.
* Got two Fujitsu (instead of requested SEAGATE) replacement disks from 
SUN.

Hanford
-------
(Greg Mendell)
* LLO S3 Level 3 RDS data (i.e., L1:LSC-AS_Q only) is now available at LHO under /samrds/S3/L3/LLO and from the LHO cluster.  (Thus, all of S2 and S3 Level 1 and Level 3 data for LHO and LLO is available at LHO under /samrds/S[2|3]/L[1|3]/LLO; the Level 3 data is available from the cluster.)
* Added these options to createrds.tcl and creatrdsGUI.tcl scripts: -filechecksum (validate file checksums), -frametimecheck (validate frame time), and -framedatavalid (check datavalid flags).  These new options work with LDAS v1.1.0 createRDS jobs.  If these flags are set to 1 in the .rsc file for the scripts then the input frames are checked as indicated and the jobs returns an error if any check fails.  (For example, see the documentation at
  http://www.ldas-cit.ligo.caltech.edu/doc/userAPI/html/createRDS.html.)

(Ben Johnson)
* S3 L3 LLO data has been sprayed across the cluster and published into
  the local LDR database at LHO.
* Dealt with power outage in LDAS room on 5/22/2004. All filesystems recovered successfully after running samfsck several times on each filesystem. Tape archive also appears to be OK.
* Tweaking AC in LDAS room. On Sunday, 5/23/2004 the temperature in the LDAS room was creeping up (76F on 10 ton unit) due to positive feedback loop between the 5ton humidifier and 10ton dehumidifier. Problem has been "fixed" by increasing the humidity tolerance to 10% on the 5ton.
* Despite electrical power difficulties and issues with the globus-rls-server in LDR, the cluster has been tested with a 4+ day 100CPU condor job by Xavier Siemens. The Condor+LDR setup appears to be in basic working condition.
* Replaced disk in t3-15.
* The 5kVA UPS's at Hanford are now on the blue T3 network. Working on a way to use the 2.2kVA serial-port-only UPS's to perform the auto-poweroff of servers when the batteries are low.

Data Analysis Activities (Lazzarini)
Creighton:
This week I fixed several bugs in LAL: fixed skewed Galactic population of inspirals for MC simulations, removed a (rare) infinite recursion in template placement code for pulsars, and made the root finder to compute start time of inspirals more robust (needed for low-mass halo objects).

Mendell:
The StackSlide Monte Carlo simulations code is nearly complete, with the goal of having some preliminary results for the June 5-6 LSC meeting in about 1 week.

Sylvestre:
o I have been working on finishing the S2 analysis by processing the last MDC frames.

o I have also been working on organizing the documentation for TFClusters in preparation for its review by the burst group.

Weinstein:
- working on inspiral S2 BNS review
- working on burst astrophysical interpretation section of paper

Yakushin:
1) Studied how waveburst event detection and reconstruction depend on the way the triple coincidence science time segments are divided into 120 second intervals used by the ETG:
http://www.ligo-la.caltech.edu/~igor/TIMESHIFT. Presented the results  at the burst telecon.
2) During the last week face to face waveburst code review meeting at LLO we found a minor bug/feature in the waveburst that caused event reconstruction to be done slightly differently than originally intended and described in the documentation (although quite legitimate as well). I compared the waveburst performance on the SG5 MDC frames for the current and corrected versions and showed that the difference is not significant: http://www.ligo-la.caltech.edu/~igor/BUGEFFECT. Presented the results at the burst telecon.
3) Helping Michele to learn how run waveburst production and  postproduction scripts for waveburst review.
4) Together with Patrick Sutton trying to figure out what's wrong with SG13 LIGO-TAMA MDC frames (apparently the amplitudes of the injected signals are wrong while timing and and frequency seem to be OK).
5) Tested the effect of usize bug (now fixed) in the postproduction 
scripts: http://www.ligo-la.caltech.edu/~igor/USIZE

Lazzarini:
Completed a time-series analysis of the point estimates of Omega_GW from the H1L1 S2 analysis (23200 data points). The purpose was to make sure there were no discernible fluctuations in the estimates that were generated over the course of the 2 months of S2. A harmonic analysis was performed using the Lomb-Scargle algorithm (cf: Numerical Recipes). A search for secular variations (e.g., linear drift over 2 months) was performed by regressing a line against the ~23200 data points. Results indicate that nothing is obviously present in the time evolution of our results. This allowed us to set up a formalism to use in S3. Interested people are referred to the stochastic elog, URL: http://www.ldas-sw.ligo.caltech.edu/ilog/pub/ilog.cgi? group=stochastic&date_to_view=05/25/2004&anchor_to_scroll_to=2004:05: 27:12:21:50-lazz and the assoicated sub-entry.

Continued work on implementing a targeted stochastic search formalism based on published techniques. In the course of validating the matlab model I built, I generated several movies (.MOV Quicktime objects) showing the temporal and frequency-dependent evolution of the H-L antenna pattern. See

http://www.ligo.caltech.edu/~lazz/distribution/LSC_DataDir1/SGWB/ LHOLLOAntennaPattern_0-500Hz.mov and http://www.ligo.caltech.edu/~lazz/distribution/LSC_DataDir1/SGWB/ LHOLLOAntennaPattern_0Hz.mov

Last, I generated the f-t map of the geomtric overlap reduction factor for a targeted stochastic search for a 5x5 deg^2 patch centered on Virgo cluster. See
http://www.ligo.caltech.edu/~lazz/distribution/LSC_DataDir1/SGWB/ Gamma_ft_Virgo.pdf

General Computing (Wallace)
MIT:
(Keith)
-Finishing the new mailserver build
-Installed ideas package on straw
-Continuing to help with LSC conf
-Moved emvogil-2 & emvogil-3 onto ups power
-Moved emvogil-3 over to visitor office for urop
-Registered for Usenix conference (Boston)
-Setup first group of urops on gc

Livingston:
(Shannon)
* Current bandwidth usage can be seen at
http://teche.ligo-la.caltech.edu/mrtg/LLO-Router/130.39.245.1_1.html
* Archived bandwidth usage can be seen at
http://teche.ligo-la.caltech.edu/mrtg/archive/ under the dated folder
for the week of interest.
*The Bell South circuit has been stable for the last 9 days.  I have seen no interface resets.  This is much better than what we have seen almost since the circuit went live.  I will continue to keep a close eye on it over the next month.
* Added several user accounts on GC.  SMC is still not working perfectly, but several problems have been solved by moving to the new server.
* The new web server is mostly set up.  GCC, associated gnu tools, Apache 2.0.49 are all installed.
* I have been going through the web pages and archiving obsolete pages. I have also been going through the existing pages that will remain and editing where necessary.  Currently there is about 11 GB of files. Some of this will be archived, but much of it will have to stay.  Most of the files are pictures, etc.

Hanford:
(Christine)
- Network usage can be seen at
http://www.ligo-wa.caltech.edu/~christin/mrtg/ 198.129.208.1_198.129.78.122.html
- Installing and testing more new software on the new application license server.
- Helped with trying to figure out why the dataviewer and dtt data
analysis tools are not working from the GC network.
- Started following cables to determine best way to get GC network back
into the LVEA for commissioning work for the next month.
- Doing more testing trying figure out why the range and signal strength
of the new AP2000 wireless access points is so poor.
- Preparing disk space and computers for the Surf students.  Responding
to requests for accounts and additional software for the students.
- Did some more searching of mail logs and configuration trying to help
Greg and Ben determine why their ldas e-mail messages are causing errors
on the mail server.
- The new fiber line between LHO and PNNL has been established.  Light
will be shown down the line to determine losses.  The job should be
completed this week.

CIT:
(Mike)

-Worked on Seiji Kawamura's laptop. After he finished reloading his  laptop
due to a hard disk failure, I installed additional software and work on
network configuration, security settings and office updates.
-Finished up loading and ghosting GariLynn Billingsley's new laptop and have given this to her.
-Running a diagnostic on multiple hard disks that were given to me by Al
Wilson I have more drives that need to be shipped out for RMA  replacements.
-Loaded a loaner laptop from scratch; this was turned in from one of our
users. I came across some hardware errors that I fixed from surplus  laptops.
-Ran an additional network cable over in 40 meter. This is setup in the
clean room to give users Internet/Network connectivity, while working  from
this room.
-I cleaned up the ghost backup server by burning ghost images to DVD. I  am
getting ready to update many ghost images that are out of date.
-Worked on Cleveland's workstation trying to resolve a database issue. I
have more work/research on this. (Request by George Stokes)
-Ran security updates on the following user workstations: Irene Baldon,
Millikan conference room M50, 40 Meter: M18-visitor, M3-visitor,
M17-visitor, M25-visitor, Bob Taylor, and Steve Vass.
-Ghosted the following user workstations: Irene Baldon, Cindy Akutagawa
laptop/workstation and GariLynn Billingsley.
-Other misc. onsite/phone user support.

(Lisa)
- Spam
- Working on the new application server
- Looked into a mailman problem for Dennis Coyne
- Looked into an e-mail problem on Albert's laptop

Mail Stats 5/20 - 5/26/04
Messages Accepted:      17876
Spam Rejected:          8092
Viruses Rejected:       1154
False Positives:        10
Total Mail Thru:        27122

(Veronica)

- LSC website: Posting updates to the June meeting as they arrive. 
Working with the MIT ecommerce dept. on backend modifications for our 
application.
Working with Marie on last-minute website additions, and providing
information to Keith for his visitor accounts setup.
Updates to the Observational Results webpage and other parts of the LSC website.
- LIGO website: Updates/upkeep of the PAC meeting website. Updates to  the
SURF programs webpages. User support in transfer and posting a
presentation online. Updates to various other pages throughout the
website.
- Project Science: Working on the website for the October workshop.
- CaJAGWR: Website updates and user support.

(Larry)
-Finished up the print-server replacement. It is now on-line. Overall  it is working the way it should. I'm sure there will need to be some 
adjustments but they should be minor.
-Started a new server installation for the E2E group. Virginio is going  to do some testing on it for the next few days and then we will work on the  build next week.
-Some assistance on the logistics of the PAC and LSC meetings that are  coming up.
-Purchased a number of supply items and equipment for other groups.
-Some minor work with Lisa on the spam filters.
-A number of account modifications. Disk cleanup and related work.
-Working on a new SDRC license and upgrade.
-Working on the updating of a couple of contracts. One with Caltech and  one with ESnet.

(Bruce Sears)
-Ilog (Electronic Log) Development:                     (1.0 days)
        - Ongoing minor works on Ilog interface.


Advanced LIGO and Supporting R&D (Shoemaker)


Seismic Isolation

From: Larry Jones <ljones@ligo.caltech.edu>
 
Advanced LIGO Seismic Structure

SEI Structure:

Revision A of the E030179 Design Requirements document for the BSC structure was released on 5/21 and given to ASI. We discussed ASI's responses to this on 5/25, involving clarification on a few remaining issues. ASI has slipped the Design Review for the BSC structure by 2 weeks to allow all significant issues to be included in the review.

The Design Review meeting for the BSC structure is now scheduled for June 18, 2004. Delivery at LASTI of the BSC prototype is expected to be in November, 2004.


Actuators:

The wire manufacturer that we'd hoped to use for precleaning the actuator mag wires prior to winding has backed out of quoting, likely due to the small amount of wire involved. We're purchasing respooling equipment and will ultrasonically clean the wire as a batch process in the 40 m lab; the wire and equipment should arrive this week.

The candidate epoxy potting material outgassing coupons were made and shipped to LHO for RGA testing.

PSI, the actuator developer, is shipping plated magnets (unmagnetized), bobbins, mag-iron frame pieces and fasteners to Caltech for precleaning.

Actuator bobbin winding is scheduled to start 14 June.

Displacement Sensors:

Jay has the updated quote from ADE, and is ready to order the BSC SEI sensors.

Seismometers:

Nothing new.

Galling/Dusting Test:

Further progress was made in writing the report.


Suspension

From: Janeen Romie <romie_j@ligo.caltech.edu>
 
AdLIGO Suspensions
MC to LASTI in June
Continuing to coordinate with folks on tasks associated with sending the mode cleaner triple suspension to LASTI in June for installation in a HAM chamber. Laurent has been updating the assembly specification, while he works with Helena, Calum, Mark and I. Work is on schedule.

Jay Heefner will install the mode cleaner electronics at LASTI on June 9 & 10. The suspension and it's accompanying hardware should arrive at MIT by June 10th. Mark Barton and Luke Williams from the Univ. of Florida will work with LASTI personnel supporting the re-assembly and installation work at MIT the week of June 14-18.

I've created a bake oven schedule for Bob Taylor's small and large ovens at the 40m to facilitate the processing of parts that are needed for this assembly and installation work. Dennis, Larry Jones and, especially, Bob, have signed off on the schedule. If needed, Bob will receive support from Helena and I in the next few weeks to help meet this tight schedule. Ken Mason has sent components that require cleaning and baking for this installation. They have been incorporated into the schedule.

Last Friday, Doug Cook, Dave Ottaway, Ken Mason and I had a telecon about the mode cleaner installation/alignment tasks still left to work out. A list of actions were generated and folks are working on them now.  Work is on schedule.

Working with Dennis, Jay, Dave O. and Laurent on dSPACE system capabilities and testing requirements at LASTI.

Quad Work
Rich Reisen from LLO sent us a scissors table to use for small range, heavy load vertical translation. We hope to use it when installing a quad in a BSC.

Initial LIGO
Output Mode Cleaner
Calum and Mark have modeled a double pendulum suspension for the Initial LIGO output mode cleaner. Peter Fritschel will decide next week if we will go forward with the mechancal design of this concept.
 


Pre-stabilized Laser

From: Peter King <pking@ligo.caltech.edu>
 


 

Core Optics


From: Helena Armandula <ahelena@ligo.caltech.edu>
 
Advanced LIGO Coating Development

LMA

The last doped Ta2O5 coating (Formula 2) received from LMA showed improved "Q" measurements as reported from MIT and Glasgow.
This coating material had about double TiO2 concentration than the first doped Ta2O5.
Coating absorption and expansion coefficient of the doped material improved as the dopant concentration increased. Refractive index was also higher, resulting in thinner layers.
The dopant seems to be uniformly distributed.
Formula 2 coating, compared with un-doped Ta2O5 resulted in ~50% "Q" improvement.

In coating Formula 3, for the next run, the concentration of TiO2 will increase to ~50%.
Jean-Marie estimates the maximum TiO2 doping concentration at ~80%. Also expressed the importance of adding TiO2 to Ta2O5 (and not vice versa) to obtain a more stable film.



Other Laboratory R&D

From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>
 
 
Maddalena

I have finished re-building the mechanics to make a more symmetric filter in order to reduce the noise due to the umbalance
at ~1Hz. I have finished to mount and calibrate the actuator(magnet and coil) and the movement reading system (LVDT), repairing some defects in the LVDT coils. In the end of the week I'll be able to start to take some frequency response measurements with the new system, more symetric and with a more thermal stabilization due to the thermic isolation box.
Moreover, in order to measure the behavior of the working point position in function of the temperature, I have to finish the Lab View program to aquire the temperature and the position changes at high acquisition frequency and making an average on the data to improve the precision of the measurement.

Barbara

this week we have tested the thermal expansion  of the invar rods and we found a thermal expansion coefficient on the order of 1.7*10^-6 as expected  from the specs. After the testing of the invar we started to mount the cavity and the suspension system and now I'm ready to start the calibration of the suspension
blades. Also, we have finally received the the vacuum tanks and in these days we are building wood protections to cover the flanges of the vacuum pipe and riggings to transfer the vacuum pipe down the elevator shaft from the synchrotron to the Wilson sub-basement lab.  For themechanics, the only missing parts are the LVDT and control coils, expected anytime now.
We expect to spend about two weeks intuning and assemblying the mechanics.

Juri

More toiling and calculations, more details next week.

 


 

For additional information about this report, contact whitcomb_s@ligo.caltech.edu