Weekly Report for Week
Ending April 15, 2004
The LIGO Executive
Committee Agenda for Monday April 19, 2004
will be:
(Meeting time: 10:30 am Pacific Time)
- Announcements
- LSC Issues
(Saulson)
- Comments on Weekly
Report
- WBS 1 LIGO I
Construction (Lindquist)
- Field Change Orders/Contingency Liens/Change Requests
- WBS 2 LIGO Lab
Operations
- Administration (Lindquist)
- Sites (Raab, Zucker, Shoemaker)
- Detector (Whitcomb, Coyne)
- Campus Research Facilities (Weinstein (40 Meter), Libbrecht
(TNI), Ottoway (LASTI))
- Data Analysis and Computing (Lazzarini)
- WBS 3 and 4 Advanced R&D and LIGO II
(Shoemaker)
- CHANGE
CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION AS NEEDED
Special Announcements:
Weekly
Report Highlights
LSC Issues (Saulson)
No report this week.
LIGO I
Construction/LIGO Laboratory Administration (Lindquist)
Status of LSC/MOU Research
Updates and Program Reports (Petrac)
(LSC Research Updates through Aug. 2004,and Prog. Report through
Feb. 2004)
Dom. Hills:
- Attach. A and Z / signed-off
Univ. of Oregon:
- Attach. A and Z / signed-off
Goddard:
- Attach. A, D and Z / to PI for sign-off
LaTech:
- Attach. A and Z / to PI for sign-off
Univ. of Texas at Brownsville:
- Attach. A and Z / to PI for sign-off
Trinity Univ.
- Attach. A and Z / to PI for sign-off
Nat. Observatory of Japan-TAMA
- Attach. D ad Z / to PI for sign-off
Univ. of Washington:
- MOU, and Attach. D and Z / to PI for sign-off
Univ. of Syracuse:
- Attach. A and Z / signed-off
- Attach. B and Z / to PI for sign-off
Southeastern Louisiana Univ.:
- Attach. A and Z / to PI for sign-off
Univ. Of Rochester:
- Attach. A through Feb. 2004 / to PI for sign-off
GEO600:
- Attach. Z / in LIGO review / Barish
AURIGA / proposed
collaboration:
- MOU and Attach. 1 / in progress / Saulson and Cadonati
National Astronomical
Observatory, Chinese Academy of Sciences (NAOC) / proposed
collaboration:
- MOU for collaboration in setting up a LIGO-type interferometer in
China / to NAOC for sign-off
LIGO Weekly Site Telecon
(Lindquist)
There was a site teleconference Thursday, April 15,
2004. The following issues were among those discussed:
- Procedure Manual:
still not done, hopefully (again) will be by next week for distribution
to
sites and campuses.
- Budgets:
travel costs are exceeding budgets. Areas overrun include the
Director's Office, the Business Office, Hanford and Livingston
Commissioning accounts, and MIT. Examples of causes include
support
for science runs and LSC
meetings where attendance is important for many people.
- Cost Transfers:
A number of cost transfers have been requested. This is being
resisted
unless there is a significant mistake or significant potential cost
savings. A large number of cost transfers attract attention
during
audits and if it is necessary to go back over 90 days, the bureaucratic
hurdles are daunting. We can move the costs, but the preferred
approach is to get it right the first time (we are providing tracking
reports now and greater attention is being paid, hence the requests for
transfers) and to adjust budgets if needed. The procedure manual
is
expected to help.
- Teleconferencing:
Raindance has been selected as our new provider of teleconferencing
services. Calls will, as previously done, be charged against the
Director's Office, the Business Office, and the Site Commissioning
accounts. Charges for extraordinary calls (e.g., international
LSC
working group meetings lasting eight hours on a Saturday) will be
considered on an individual basis.
The list of current actions revised
to reflect
the status of open actions assigned through the last update (March 4,
2004) may be
found at ACTION
LIST.
PROPERTY
MANAGEMENT (Chargois)
From: Ed Chargois
<chargois_e@ligo.caltech.edu>
- Nothing Significant to report.
DOCUMENT
CONTROL CENTER (Turner, Mak)
>From:
Linda
Turner - turner@ligo.caltech.edu>
Web pages
for the DCC give simple how-to's for document numbering, easy access to
the latest on-line documents, and search capabilities for the DCC
database. Take a look.
. .
ACCOMPLISHMENTS
- Completed checking all of the 1997 Account Charges .pdf
files. Will burn CDs and then shred the documents.
- Helped Ed Jasnow generate several letters for NSF reflecting
management change.
- New high-density file modules were installed and will provide
much needed additional space.
- Per Barry's request, began writing a new procedure for the
handling of confidential documents between LIGO's executive management.
- Started sifting through piles of documents left by Gary.
Found
numerous documents that hadn't come into the DCC. These are being
numbered and processed.
- Handled several remaining Aspen presentations.
> From: Cleveland Mak <mak_c@ligo.caltech.edu>
ACTIVITY
04/15/04
|
Packages
|
Faxes
|
In
|
27
|
32
|
Out
|
9
|
23
|
Press here to access
the DOCUMENT CONTROL
CENTER WEB PAGE.
COST
SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman, Salone)
From: Esther Cunningham
<esther@ligo.caltech.edu>
Press here for
ACCOUNTS
PAYABLE HISTORY DATA.
From: "Brambila, Ruth"
<Ruth.Brambila@caltech.edu>
No report (vacation).
From: Gina
Salone
<gsalone@ligo.caltech.edu>
- Preparing purchase
orders (Due to Ruth being on vacation)
- Set up a Contract
for Planning System Inc (PSI); working closely with Larry Jones, Ed
Jasnow and Paul Banas (PSI) to finalize a Contract.
- Modified Excel
Contract per Florence
- Continue to assist
Recardo De Salvo Group
- Working on getting
and Invoice paid from Veeco awaiting approval from Garylynn.
From:
Florence Kaufman
<fkaufman@ligo.caltech.edu>
- Prepared Cost Transfers to transfer costs from the Low Frequency
Noise Suppression account (task 5.11) to the fabrication account
LIGO.VINT/5.11 at Riccardo's request.
- Prepared Cost Transfers to transfer travel expenditures for the
Thermal Compensation fabrication from Task 2.8.1.
- Worked with Cindy to transfer portion of Ed Maros payroll from
Task 1.5.1 to Albert's AJL.GRID/1 MIT.GRID account.
- Provided information to Carol Wilkinson regarding University of
Florida invoices being held for payment.
- Provided status of Visitor accounts.
- Requested that the fabrication account for Reflective Memory
upgrade at Hanford LIGO.HANCA/2.8.11 be closed.
- Provided schedules to David Shoemaker indicating status of MIT
accounts after payment of March invoice.
- Updated Operations report for April, including making budget
realignments based on approved Change Requests.
Financial reports can be
found at:
http://docuserv.ligo.caltech.edu/~fireport.
SUBCONTRACTS
MANAGEMENT (Petrac, Jasnow)
From: irena@ligo.caltech.edu (Irena Petrac)
Goodrich: Final
invoice was approved for payment.
From: Ed Jasnow <jasnow@ligo.caltech.edu>
We are waiting for a proposal from ASI to cover the removal of the
Advanced LIGO seismic isolation system for the HAM chamber. That
decision was made by the CCB to defer that task until next fiscal
year. ASI will produce a set of full design and manufacturing
drawings for the HAM system, but will not fabricate. This will result
in a reduction of the target cost.
SUPPORT (Baldon, Lloyd,
Tischler)
>Irene Baldon
- A great portion of my time has been tied-up with testing out a
new P-Card Program which after at least an entire day attempting to
make it work it still appears, at least to me, seriously needs
reworking.
- Also at least two (2) full days of my time has been taken up with
working with Raindance Reservationless Conferencing, selected as the
new replacement for AT&T Teleconferencing, adapting it LIGO's
needs, setting up cards and pins for frequent users, distributing
these, and cancelling AT&T standing calls as users become
comfortable with Raindance. Raindance will be charging LIGO
$0.24/minute/caller as opposed to AT&T charging LIGO
$1.00/minute/caller. As significant savings to LIGO.
- Processed the paper work eleven (11) new/revised trip.
There are eleven (11) trips in various stages of completion before
ticketing can be done and/or paper work completed. PLEASE
NOTE: That 2004 SURF travel has started and this year I'm
currently working twenty-five (25) travel arrangements, including
domestic and foreign. I continue to work closely with Terry
Gunter and LIGO/Hanford personnel in acquainting them with travel
procedures, etc.
- Completed nine (9) Expense Reports and there are thirty-four (34)
reports yet to be done. I continue to contact travelers who have
outstanding Expense Reports (more than one (1) month old) to ask for
their cooperation in sending me their receipts so that these can be
closed in a timely manner. Presently is are seven (7) reports
more than 30 days old.
- Reconciled ten (10) P-Card items which required numerous phone
calls to hotels, car rentals, etc., in order to track down which
traveler incurred which charge; and the pulling of each traveler's file
to assure that charges are correct for each fee incurred.
- Continued to cover the Project Office, Barry Barish's and Donna
Tomlinson's Office when called upon. Worked on the preparation
and distribution of the Travel/Vacation Itinerary for April 12,
2004. Arranged twelve (12) new or revised AT&T
teleconferences and two (2) new reservation on the LIGO Calendar.
>Dorothy Lloyd
- Processed the usual invoices for payment. Tracked and followed up
on invoice problems.
- Processed the usual requisitions, change orders and payment
requests.
- Continue to monitor contract and blanket order encumbrance and
notify task managers when supplements are needed.
- Jim continued with data entry in the LIGO database and helping
out in the DCC.
>From: Ryan Tischler <rtischle@ligo.caltech.edu>
-
PAC16 details, Travel issues, Matriculation of New LIGOites
-Mark Turner, Photo site.
ADVANCED LIGO (Cost
Schedule
Control Systems) T. Frey
From: Thomas Frey <tfrey@ligo.caltech.edu>
For list of documents
that are being used to develop Adv.
LIGO Cost and Schedule, see
http://www.ligo.caltech.edu/~tfrey/Cost_MTG_082002/
Assisted Carol with
ACIGA cost and schedule data.
http://ligo.caltech.edu/~tfrey/ACIGA/
-
ROSTER DATABASE:
-
Continued
input of changes / corrections regarding supervisors and departments.
-
Continued
correspondence regarding the future implementation of start and finish
dates for LSC members for maintenance of the authorship list.
Project Web Site for
posting schedule and progress related data continues to be updated with
the latest and greatest.
Reports
(Lindquist)
LIGO Video--Tom
Lucas (Lucas Productions) will be visiting Caltech April 21 through 23
to
interview people. Tom is building the "plot line" for a 20-25
minute NOVA type video on LIGO under a Grant from the NSF. I will
be arranging interviews with Caltech personnel for Tom. Tom will
be traveling from Caltech to the Hanford site to participate in the
"star party" scheduled for April 24.
Change
Control/Contingency (Lindquist)
There are no open change requests. The minutes for the meeting
of the LIGO Change Control Board held on April 5 and April 8 have
been
published (LIGO-M04-107-00-P). An electronic version is being
circulated for electronic concurrence signatures.
Human
Resources (Akutagawa)
From: Cindy Akutagawa
<cindy@ligo.caltech.edu>
- Various personnel/payroll /HR related work.
Quality/Safety (Tyler)
>From: Bill Tyler <tyler@ligo.caltech.edu>
No report.
LIGO Hanford
Observatory (LHO) and Interferometer Operations
(Raab)
Summary of
Commissioning Activities at LIGO Hanford
Observatory (Sigg)
H1 activities
A new laser is being installed. This one giving up to 7.5W at the input
to the mode cleaner. Details here,
here.
and here.
and here.
An equalizer filter was tried in the LO path of the AS port
photodetector,
but strangely enough no effect could be observed. Details see here
and here.
The mode cleaner board has yet another modification that prevents
the
signal from being attenuated first only to be amplified again. Details
see here.
An additonal photodetector in the REFL path using the non-resonant
sidebands
has been installed and checked out. Details here,
here,
here,
here,
here
and here.
Currently trying to use the new diode in common mode.
Mode measurements of the RIN of the TCS have been performed. Details
here
and here.
Measurements of the beam profile on the AS table have been done in
preperation
of the installation of the OMC. Details here.
and here.
H2 activities
An attempt was made to stabilize the beam jitter on WFS1 using a PZT
controlled
mirror. However, its range was not large enough.
Site activities
No increase in LVEA temperature fluctuations noted after pulsed heating
was shut off. Details here.
Dust not producing glitches at tables other than dark port. Details
here.
Various problems with the new DAQ setup have been fixed.
LIGO Livingston
Observatory (LLO) and Interferometer Operations
(Zucker)
Announcement
Tomorrow is Jonathan Kern's last day at LLO. Jonathan was a founding
member of the Livingston staff and played key roles in designing and
commissioning the interferometers as a lead optical engineer and as our
Laser Safety Officer. Most recently we were fortunate to have Jonathan
leading our HEPI seismic retrofit effort, managing the design and
continuing through much of the fabrication.
Jonathan now moves on to the Magdalena Ridge Observatory in New
Mexico, where he will lead a design team to build a novel optical
interferometer for astronomy. We at LIGO thank him, and wish him the
best of luck in this exciting new endeavor.
Public Outreach (MZ)
Tom Lucas of Lucas Productions is here with a film crew to tape a
HEPI actuator installation for an upcoming LIGO video. Gary and HarryO
have been spotted on site wearing cool sunglasses.
L1 Commissioning
The move of the electronics at the X end station was accomplished
successfully. It is too early to do a complete EMC evaluation,
but preliminary checks indicate dramatic reductions in local VME bus
interference as well as 60 Hz hum. We have more cleanup to do, but are
extremely pleased with the
way things look so far.
The timely completion of the X end electronics swap allowed us to
run the interferometer over the weekend; this verifies that the
electronics transplant was functionally successful. It also allowed
resumption of ongoing commissioning.
The most interesting result was a probe of the sideband field
amplitude and optical gain as a function of induced offsets in the PRC
control path. This showed a clear peak well away from the nominal null;
phase camera pictures also show the appearance of a ring structure in
the sideband field. This behavior is qualitatively very similar to
model predictions by E. D'Ambrosio. Follow up measurements are planned
to make the comparison quantitative.
After this experiment the corner station gate valves were sealed
to prepare for HEPI actuator installation in the LVEA. We expect
to be closed off for about 5-6 weeks to do this installation, finish
hydraulic piping, install the TCS viewports, regenerate the cryos, and
fix some IP valves. Rolf has also installed the latest version of the
ASC code this week (along with the HEPI code) and is testing it with
Chethan and Ash. Meanwhile HEPI commissioning is in full swing at
the end stations (see below).
LLO Seismic retrofit (MZ for Rich Abbott)
The X end HEPI electronics are now installed and wired. All
the pier modules are checked out and powered up, and we expect to
bring signals into the ADC's tomorrow. Meanwhile Pradeep, Brian and
Rich Mittleman are testing the I/O and software. The system is wet and
purged, and the pump speed control is now fully operational with
closed-loop pressure regulation.
At the Y end we expect the last hoses to come in tomorrow so we
can wet and purge the Y actuators over the weekend.
In the corner station, the acoustic enclosure was craned off ISCT4
and the table pivoted out of the way for installation of actuators on
HAM4. The special lifting fixtures for gently lifting each leg of the
HAM were load-tested. The first two actuators and piers have been
staged to the LVEA airlock. The HAM4 crossbeams have been
instrumented with dial indicators to monitor the lifts. We expect
to begin HAM4 actuator installation tomorrow morning.
Meanwhile the LVEA hydraulic piping continues to progress rapidly;
the HAM supply lines are almost complete, as well as one of the BSC
sets.
Oddvar Spjeld adds:
- received quote and ordered all flex hoses for vertex
- completed HAM Lifting Procedure (reviewed and approved)
- completed assembly of two HAM HEPI housings (left and right)
- fit check of holes pattern on HAM lifting plate against crossbeam
- fit check of HAM piers, indicated left and right on each pier
- mounting holes for 4-way valve plate have been added to the piers
- remaining shims have been shipped back to Lavallee for correction
- checked status of hardware before installation start
- completed update of HAM Top Level Assembly drawings
Safety and security (Rich Riesen)
- The last of the GSA "turn back in" items have been removed from
site.
- items: 2 forklifts w/battery chargers, flatbed truck, 4
projectors, and 2computer consoles.
- Found no safety concerns during weekly site tour.
- Continuing work on SOP procedures for both site and laser
safety.
- The HEPI installation crew are continuing excellent safety work
habits.
- Working with trucking company for lower shipping rates.
(completed).
General Computing (Roddy)
- Current bandwidth usage can be seen at http://teche.ligo-la.caltech.edu/mrtg/LLO-Router/130.39.245.1_1.html
- Archived bandwidth usage can be seen at http://teche.ligo-la.caltech.edu/mrtg/archive/
under the dated folder for the week of interest.
- Actually making progress with LSU on the network issues we have
been having. I need to contact them next time it happens so that
they can contact Bellsouth within 48 hours since that is how long their
logs last.
- Having file system corruption on the Linux file server. I
am still working on this issue, and I am a bit nervous about the state
that it is in. We are working on a solution but the next 48 hours
will be critical.
- Moved a lot of equipment into the two new racks including two new
UPSs, 3 solaris servers, 5 PC servers, etc.
- As usual, some firewall updates.
- looking into some strange log entries from my firewall.
Haven't had time to determine the problem yet, but this will have to be
looked into next week if the file server issues are taken care of by
then.
- Replaced two failed hard drives on one of the RAIDs on Decatur.
- Ordered some software for Katrina and Rich Abbot to use for web
development for HEPI stuff.
- Ordered several pieces of hardware to replace failed items,
including our server KVM. Warranty was expired on it and it will
cost about $2k to replace.
- Discussed several billing items with LSU over the internet bill.
- Looking into archiving/deleting several locked accounts at
LLO. They have been locked for about 18 months and no one has
complained, so it is time to remove them from the system.
Need to decide how I am going to archive these files. I think I
will start burning them to DVD and storing somewhere.
- Several miscellaneous user support issues.
Data Analysis (Yakushin)
LDAS admin:
- crossmounted nodes' disk to ldas-pcdev1
- configuring NIS+ client on ldas-pcdev1
- 2 T3 disks crashed today in t3-13 and t3-3.
Data analysis:
- Generated low frequency MDC frames for the whole S2 and tested
them with waveburst. Still more testing is needed.
- Working on generating high frequency MDC frames for LIGO-TAMA
analysis.
CDS Controls (Chethan Parameswariah)
Rolf visiting LLO this week. Working with him on installing the
new ASC Code, Hepi code and the frame builder upgrade.
CDS support (Ash Khan)
- Helped Russ and Jay in the X-End systems relocation.
- Worked with Rolf in the installation of the new ASC and HEPI
system.
- Brought new Channels from PSL in to our DAQ system, upon request
from Valera.
E2E Suspension Modeling (T. Findley and S. Yoshida)
We investigated the effect of asymmetric coil force on small
optic's pitch and yaw motion using an e2e SOS box with a realistic
table top motion given to its suspension point. To consider the coil
force asymmetry, we gave different coil efficiencies (coil force per
unit coil current) to the four OSEM actuators. The four coil
efficiencies were randomly varied from the nominal value by 1% (i.e.,
two of the four coil have efficiencies higher than the nominal value
and the other two coils have efficiencies lower than the nominal
value). The SOS was facing normal to the beam direction (U-direction),
and we looked at the height of the peak at 1.45 Hz in the pitch and yaw
spectra of the optic's motion. Here 1.45 Hz is the HAM stack's U-U
transfer resonance frequency. When the two top coil efficiencies were
lower than the nominal value and the bottom two coil efficiencies were
higher than the nominal value, the 1.45 Hz peak in the pitch spectrum
increased by 18% and the 1.45 Hz peak in the yaw spectrum decreased by
9%. This can be interpreted as follows: When the HAM table moves, the
OSEM actuators attached to the suspension tower pushes/pulls the optic
via the magnetic force synchronously with the table motion. Under the
given coil force asymmetry, horizontal HAM table motion in the
U-direction results in a pitch motion of the optic because the
difference between the top coil efficiency and the bottom coil
efficiency is greater than the difference between the right coil
efficiency and the left coil efficiency. Therefore, the pitch
motion of the optic tends to be enhanced, and consequently, less energy
goes into the yaw motion of the optic. When the right two coil
efficiencies were higher than the nominal value and the left two coil
efficiencies were lower than the nominal value, the 1.45 peak in the
pitch spectrum decreased by 11% and the 1.45 peak in the yaw spectrum
increased by 10%. This effect can be explained in the same way as
above. With this second coil force asymmetry, we examined the
effect on an LOS. When the coil force asymmetry is 1%, there was no
substantial difference in either the pitch or yaw spectrum. When the
coil asymmetry was increased to 10%, a similar effect as the SOS case
(with 1% asymmetry) was observed.
Detector/Technical
Support (Coyne)
Seismic Upgrade Project
see also:
- the LASTI report for
experimental
progress in controls
- the CDS report for electronics and
software developments
- the LLO report for
installation
Ken Mailand
Working on the task of organizing the HEPI
materials and
documentation, and sending drawing files to the DCC. The
development area in the CES building has been cleaned up and returned
to
its original condition (I thanked Mike Gerfen for letting us use the
space.
CDS
see also CDS meeting minutes in the commissioning
archives:
CDS Software
Rolf Bork reporting
At LLO this week:
- Updated all front end code to latest rev. as loaded
at LHO.
- Loaded new ASC code which supports new IO WFS
configuration; hardware still needs to be installed.
- Modified and loaded new HEPI code to match latest
hardware I/O connections. Testing will start tomorrow.
- Installed a third linux PC to match configuration
at LHO; new PC runs lsc and asc epics software.
All of our EPICS code which runs on Linux PCs and
all
2KHz/16KHz front end software has been put in a new CVS branch
(cds/rts). This
new branch allows for high level Makefiles and perl scripts to create
all of
the epics databases and sequencers and load them into target
directories, which
include the startup scripts and autoburt files. All of the front end
code now resides
in cds/rts/src/fe, with a single Makefile.
CDS Hardware
Jay Heefner reporting
Fiber Optic Timing Signal Link (Sander)
The oscillation problems reported on last meeting
turned
out to be a problem with the receiver itself. It appears as though the
low
frequency response of the receiver is limited to freq>100KHz. While
this is
fine for the 4MHz clock it is not OK for the 1pps signal. Sander is
looking for
different transmitters and receivers to use. He will have suggestions
by next
week's meeting.
Timing System Redesign (Flavio)
- Talking to Sazabi about the atomic clock.
- Flavio and Jay are working on a schedule to present to the
commissioning team.
Anti-Image Filter (Mohana)
- The 3rd order cheby prototype is working and appears to
perform as predicted by the simulation.
- Discussions on the type of filter that we need and the
requirements for the final design continue amongst the commissioning
team. We
should have a better idea by next week.
ISS (Flavio)
- The offset that was observed on the whitened version of
the PD monitor signal was due to the large bias currents of the AD827
amp. It
was swapped for an OP270 and now the offsets are <1mV.
- Flavio and Peter K are looking into the 1-2MHz resonant
feature in the current shunt response.
LSC PD Redesign (Ben)
- Ben has an updated schematic that he sent to Vern for
comments. Vern has a few additions. They will be incorporated and the
design
presented to the commissioning team for review.
EMI Upgrade (Jay)
- X end at LLO done last week and is being tested.
- We need to order the 50 pin cables needed for the Y end,
etc.
Output Mode Cleaner (Jay)
- Rounding up equipment for tests.H
HEPI (Ben)
- Sent 4 new pier interface modules to LLO for installation.
- The drawing for the system schematics for the corner
station is currently on hold. I have 26 pages with the parts in
place,
but I need to find out what the racks will look like before I can label
any of
the cables, modules, and feedthroughs.
Elect Shop (Todd)
- 2 ea 166MHz PDs for the 40M are complete except for final
tuning.
- Addtional pier interface modules in test.
- Dave is assembling QPDs for 40M.
PSL
PeterKing
Flavio and I have been working on the both the current shunt
and the
intensity stabilization board. The electronics noise
was measured in a
number of places. We believe we have a small
improvement for the DAQ channel readouts.
OMC
PeterKing
Still more delays are being encountered with the machining
of the
vacuum chamber. At last inspection, around 15:00
Wednesday, the only
machining operations for the vacuum chamber were to tap two
pipe threads,
cut three access notches and drill four clearance
holes. Other
miscellaneous hardware items have been cleaned and are ready
for baking over
the weekend.
Thermal Compensation System (TCS)
Mike Smith
Price and delivery quotations for 4 TCS installations plus
spares are complete, pending a decision about the CO2 laser power.
A tentative installation and commissioning schedule for TCS
systems at H2 and L1 was completed. Installation and commissioning
would be
occur during the months of July and August.
Baffles
Ken Mailand, Mike Smith
I'm working with Mike Smith on the Baffle project layouts
for the next few days to complete and check the work before Mikes
vacation.
COS Papers
Mike Smith
An abstract was submitted for a talk to be given at the GR17
conference in Dublin on 4-18.
Revising the scattered light calculations and editing the
paper to be submitted on "Direct Measurement of Scattered Light Effect
on
the Sensitivity in TAMA300", by Takahashi, Arai, Kawamura, and Smith.
Optical Contamination Cavities
Lee Cardenas, Liyuan Zhang
OTF Lab. (W. Bridge)
The (21) pieces of the new twisted, shielded, teflon cables are under
test. We are taking ring down and beat frequency measurements
as well as the RGA of the chamber every day. NO CHANGE
Absorption Test Measurement prototype in
progress
The sapphire substrate PINK color from Lyon, France. (314 mm Dia. X
131mm
thick.) still inside the enclosure and it is in standby for further
measurements. The 80mm sapphire cube is waiting for
cleaning. The aluminum support for this cube has been fabricated
and tested to hold the
cube in place. We'll scan this cube for absorption test and
compared with the sapphire
rod (~50ppm/cm in loss). This cube will be our STANDARD for
measuring absorption. The fabrication of the rods for the
enclosure still in progress.
Scatterometer system in standby
OTF Lab at Lauritsen ROOM 38 NO CHANGE.
Cavity #3
The cavity is locked and we are taking ring down and beat frequency
measurements every day as well as the RGA for the chamber.
Cavity #2 Test cavity optical set up in
standby.
We need to mount back the NPRO and re-align it on the loop.
PSL LAB.
The 10 watt ND:YAG laser is undergoing for a complete and new
alignment
which is in progress. We are waiting on the OMC parts from the
shop. We made a ring adapter to align the PZT and the mirror in
place to glue it
together. We are baking the OMC body and mirror support.
Misc... tasks
Spacer to increase the height of the
mirror holder at the imaging lab has been
completed. Ken Mailand and I, have disassembled the wooden frame
for the HEPI assembly and
cleaned the area from the shop.
40 Meter
Interferometer (Weinstein)
Commissioning (Miyakawa, Vass,
Ward, Kawamura):
- Osamu is preparing
to lock the PRC with double-demodulation (DD) at the SP. A DD RFPD is
in place, the DD will be done with a pair of IQ Demod boards, and the
LO RF signals are in place (at 166+33 and 166-33 MHz). We need to do
some wiring of the LSC rack to get the signals into the LSC system, and
are now looking into the needed software changes, if any.
- Jay, Osamu, and Rob
are going over the requirements for LSC hardware and software for the
full dual-recycling lock acquisition, and Rolf knows that we're
thinking about it.
- Rolf and Alex are
thinking about implementing a general-purpose "math block" in the
digital controls software, which we could use for dither-locking the
PRC.
- Locking of the
Fabry-Perot-Michelson (FPMI) is currently hampered by a (new) problem
with the PSL (see below). It can be done, but there is apparently a
problem making the transition between locking of XARM/YARM and
CARM/DARM that is not understood and is under investigation.
PSL (Miyakawa, Vass, Ward):
- The PSL is starting
to misbehave again, in a new way. The frequency reference cavity (FRC)
error signal is oscillating in a funny way, suggesting saturation.
Osamu suspects the FSS fast (PZT) loop. Under investigation.
- Steve & Osamu
decreased the PSL NPRO #238 power output from 712mW to 504mW by
adjusting the doide current potentiometer from 2A to 1.7A. DTEC fell
from 1.7 v to 1.25 v (that was the point; the PSL trips off when DTEC
exceeds 2 v), and the MOPA power fell from 12.1 W to 11.0 W. The PSL
has been performing stably since then. We think we're out of the woods
with regard to heating, but we still await an NPRO heat sink from the
shop. That will hopefully arrive and be installed next week, at which
time we will fully close the MOPA cover and hope that the heat (DTEC
voltage) doesn't rise unacceptably.
- We intend to adjust
the PSL slow loop temperature change in the EPICS state code.
Optical sensing (Kawazoe, Sakata,
Ward):
- Fumiko has tried to
implement an oplev servo filter based on what she found at the sites
(modified with FOTON to be more appropriate for our 5" optics). She was
unable to see a reduction in P/Y noise (as measured by the OSEMs). She
will pursue this work systematically.
- Rob has finished
laying out the POB beamline, and is hooking up the electro-optics: a
ccd camera, an RFPD, and a QPD.
- We now have 12 QPDs
installed and being read out: IPPOS, IPANG, IOPOS, IOANG, MCR, MCT,
TRX, TRY, POX, POY, AP, SP. We need one more, POB, and an additional
readout channel. Ben has delivered the QPD itself; we have to either
instrument a new readout channel or borrow POY's.
- Shihori has aligned
all the QPDs except for POB, and TRX and TRY. She will do those next.
- We now have 3
electro-optic shutters (EOS): at MCR, SP, AP. The MCR one has been
working for many months. Shihori and Osamu got the SP one working, and
Shihori measured the transmittance vs HV; a nice cosine curve. She will
document it. There are problems with the one at the AP, which may be
due to bugs in the controller. Under investigation.
- We now have 4
mechanical shutters under EPICS control (PSL, MCR, AP, SP) and 4 under
manual control (MCT, POB, POX, POY). One shutter is not functioning and
has been returned for repair/replacement.
- EPICS code to
shutter the PSL during vacuum transitions will be implemented soon.
- Osamu, Steve, Rob
and Shihori have cleaned up all the optical tables, removing all excess
optical components for storage, and ensuring that all beamlines are
fully instrumented and laid out as in the drawings.
- The PSL table is
now grounded to the vacuum enclosure, as are all other optical tables.
Electronics (B. Abbott, Heefner,
Taylor, Mageswaran):
- We now have Marconi
signal generators for all required frequencies (29.5 MHz for MCR, and
33, 166, 133, and 199 for the main interferometer, all phase-locked to
multiples of 33 MHz).
- Ben brought over
LSC RF distribution boxes for the 133, and 199; not needed for 166,
only one IQ demod board needs it. There are heliac cables for the 33
and 166 to the LSC rack, and Bob ran some temporary RG405 for the 133
and 199; more heliac cable is on order.
- At Osamu's request,
Ben removed (and jumpered across) the output attentuators at the end of
the RF AM stabilizers that go to the EOMs. Osamu measured the maximum
modulation depth for 166 MHz to be 0.3; more than enough, and easily
turned down to 0.1 with the EPICS slider. The 33 MHz is probably much
deeper, but will also be turned down to 0.1.
- The 166 MHz and
133,199 MHz RFPDs show oscillation at 500 kHz. This is a known problem
for RFPDs with low light level, with a known fix, and Ben will
implement it.
- Ben cured the
long-standing problem of the varying monitoring readout of a couple of
Thorlabs photodiodes on the PSL (PMC transmitted DCPD and FSS
transmitted DCPD), by tying the "Guard" pin to the signal "Lo" pin
(discovered after reading the 96 page manual for the 3123 ADC). He will
now investigate the PSL DAQ channels, some of which have been railed
forever.
- Ben continues to
work on the redesign of the RFPD board, with Vern Sandberg. They are
working to incorporate a few new features that would be nice to have.
Ben plan to give Dennis a schedule of development by the end of this
week.
- Ben is updating the
system wiring schematics for the 40m Auxiliary rack, in order to
reflect the as-built condition.
- We plan to do a
careful search for 60 Hz pickup in our LSC crate, which is anomalously
large.
- Mohana and Shihori
continue to work on setting alarm limits on all EPICS channels in the
EPICS alarm handler.
- Ben Olson continues
to diagnose problems with the STACIS seismic isolators. Two of the 3
isolators in the south end are working well, the NE isolator is
behaving badly. Under investigation. Steve will locate the STACIS servo
extender board or order a new one.
Dual-recycling lock acquisition
(Kawamura, Miyakawa): Seiji and Osamu have settled on two lock
acquisition sequences (using double demod) that they think will work
robustly. Seiji's involves dither-locking MICH then locking the PRC and
then SRC with double demodulation at the SP and PO, respectively.
Osamu's replaces the first step with an alternative scheme for MICH. We
will work towards implementing these schemes. This is a perfect thing
to test with e2e... new visitors are arriving in May who may want to
work on this.
Facility (Vass) and South Annex
Bake Ovens (Taylor):
- Steve is cleaning
up the 40m lab, moving excess optics and equipment to cabinets in the
east arm, and getting rid of surplus equipment such as old 40m racks
full of obsolete electronics.
- Bob tied down the
monitors in the control room for earthquake safety.
- Bob is plumbing up
new "clean" oven C.
- Bob will
decommission "dirty" oven D, will surplus it, and will recommission old
oven C as a new "dirty" oven D.
- Bob is exploring
building a new very large bake oven for AdvLIGO.
- Bob is building
OSEM diodes for Janeen (AdvLIGO MC triple) and for the 40m.
Thermal Noise
Interferometer (Libbrecht)
No report.
LASTI (Ottoway)
LASTI Weekly (Allen, McInnes, Mason, Mittleman, Ottaway, Sarin,
Smith)
No report.
Data Analysis and
Computing (Lazzarini)
Simulation and Modeling (Yamamoto)
Weekly Physics meeting
We discussed current status of H1 and H2 and problems of WFS,
especially noise in WFS1 and low bandwidth in WFS2b loop, with Luca (at
LHO). Matt (at MIT) described plans to improve lock acquisition
procedure for LIGO I and developing this procedure for Advanced LIGO.
Dual Recycling Cavity
(Hiro) finished the calculation of the scalar case field evolution
in a Dual Recycling Cavity. The LIGO document (T040062), matlab
code, validation note and e2e box files using primitive modules are
placed in
www.ligo.caltech.edu/~e2e/drm. Next is to
extend this to include the modal model.
Note on Thermal effect on WFS
Code development and
maintenance
(Hiro) Getting ready for the release of e2e-2.0.0: Melody and Hiro
have been working to finish the simulation engine code release for the
next release of e2e, version 2.0.0. This will be released by next
Monday. Big thing is the FUNC_X, replacement of FUNC, which uses c++
compiler and dynamic linking.
(Melody)
Modeler:
Modified the build scripts to change some default options and
provide more user feedback.
Alfi
(Bruce)
- More implementation of connection and parser objects for use with
new bundle/bundler objects.
(Melody)
- Fixed a bug in the new version of JGo (the third party software
used in alfi). Performing more regression testing.
LIGO Data Analysis System
Software Systems (Blackburn)
The weekend tests of LDAS revealed memory leaks in the frameAPI
and the metaDataAPI. Both of these have had recent code changes and the
authors of these code changes are reviewing their code in an effort to
track down the source of the memory leaks. The standing memory leak in
the dataConditionAPI is still there, but we now have an idea where to
look to fix these.
The DASWG group has requested that LDAS delay its release until
final decisions can be made regarding database table changes. The
inspiral group has finalized its table changes and the GDS group will
be making a proposal for a change early next week. We will probably
have a one week delay to accommodate these changes.
Several issues within the controlMonitorAPI regarding backwards
compatibility and standardization of the widgets between releases have
been resolved this week.
The decision was made this week to upgrade to the IBM DB2 version
8.1 with fixpac level 5 after two weeks of testing revealed no
incompatibilities with Redhat 9 and showed performance boosts as much
as 5.5x. This decision was also facilitated by the delay in the release
proposed by the DASWG. It will also set the stage for bringing online
the federated/replicated database services.
Much of the documentation has now been cleaned up in preparation
for the next release of LDAS. New versions of dependencies on tools and
added functionality has been the focus.
We have a new programmer on staff; Mark Turner will be taking on
half of the C++ development associated with LDAS in conjunction with Ed
Maros. Mark spent the week reviewing the LDAS architecture and learning
how to build LDAS and maintain the nightly builds on the LDAS-Dev
system. He has also spent some time studying the diskCacheAPI
interfaces with TCL code.
A set of temporary patches have been made to the lightWeightAPI
and the eventMonitorAPI to address thread wake-up issues seen under RH
Linux (note: these issues have also been seen by the Globus
Project). Eventually, we would like to implement a common
solution for all APIs that can reside in the genericAPI instead of
patching each API for which the problem is seen.
Several problem reports for the frameAPI, eventMonitorAPI,
lightWeightAPI and controlMonitorAPI were closed out this week also.
Another 4 seconds of delay were shaved off of jobs that use cURL to
move data via URL addresses. This was accomplished with a few lines of
code changes in the managerAPI.
The full suite of system and integration tests were completed this
week and results were posted on the web. This pass through validated
the use of the GCC 3.3.3 CC compiler on our tools sets. We are also
verifying that the DB2 7.2 -> 8.1 upgrade will be database
compatible and that backup restore functionality translates across
version.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Continued testing the latest SAM-QFS patch using samtest with
9940A drives and T3 disks. Some bad behaviors kept us from
installing the patch on the ldas-archive system this week. I am
continuing to investigate.
- Continued deleting files in HPSS.
- Changed IP numbers of 3510s to make the ldas-archive private
(admin) network consistent (FC switch, 3510s and T3s are now all on the
same subnet).
- Worked on SAM problem where releaser log got near 2Gb and
releasing quit working correctly resulting in /archive filling
up. Archived outstanding files to tape and ran samfsck,
recovering disk space.
- Got Arlo Ruiz at Sun to ship 4 T3 disks to CIT (should be
arriving today).
(Al Wilson)
- Setting up Tripwire for ldas system. Configuring rules for
tripwire. Compiling TW for Solaris 9 machines.
- Rebuild array for datacache3.
- Installed memory for ldas-cit 880.
- Still working on tw_cli for datacache, I am not happy yet with
the reporting to the system logs.
(Stuart Anderson)
- Worked on V880 memory problem.
- Generating S1 L3 frames for Stochastic group.
- Finished loading S2 and S3 L1 frames into LDAS-CIT cluser for use
by Condor jobs.
- Renewed the T3 maintenance contract with Sun for another year.
- Renewed the LHO, LLO, and CIT Copper GigE switch maintenance
contract with Foundry for another year.
MIT
(Keith Bayer)
- Troubleshot and reinstalled firmware on dmt raid array after
power outage.
- Built condor on cluster and ldas-grid.
- Rebuild NIS on cluster and ldas-grid.
- Configured and started LDR for transfer of new data sets.
Livingston
(Igor Yakushin)
- Crossmounted nodes' disk to ldas-pcdev1.
- Configuring NIS+ client on ldas-pcdev1.
- 2 T3 disks crashed today in t3-13 and t3-3.
Hanford
(Greg Mendell)
- Level 1, 2, and 3 createrds jobs are running at LHO and LLO every
100,000 seconds on 1000 s of raw frame data. This is monitored
daily from http://ldas-jobs.ligo-wa.caltech.edu/dsorun/cgi-bin/index.cgi
to make sure our systems are working and ready to archive and reduce
data between runs, for example in the event of an external trigger such
as a gamma ray burst. (Automated archiving and reductions of data
associated with an external trigger, initiated by an operator, is still
under construction.) The LSC should note that raw frame data is
not archived or reduced between runs except upon requests to LDAS.
Please email Greg Mendell <gmendell@ligo-wa.caltech.edu> or Ben
Johnson <johnson_b@ligo-wa.caltech.edu> if you need raw frame
data archived or reduced at LHO. We will consult with LDAS and get back
to you. At LHO the framebuilder disk cache currently holds 92 hrs (3.83
days) of raw frame data, so request need to be within that time frame
before the data is deleted by the framebuilder.
(Ben Johnson)
- ldas-pcdev1 has been set up on LDAS and GC networks. Working with
Christine Barker on setting up GC user accounts (NIS+, autofs etc.) for
the machine.
- Installed host certificate and requested 'datarobot' certificate
for ldas-grid. Initial tests on gsi-ssh into the box have been
unsuccessful.
- Working with Dave Barker to set up the Framebuilder <->
LDAS connection again.
- Continuing work with Vern Sandberg on Data Valid problems.
Presently writing up a final report.
Data Analysis Activities (Lazzarini)
Creighton:
This has been a week of cross-checking: I have been looking at the
precision of radio pulsar timing data for the known pulsar analysis,
examining changes between old and ``official'' versions of the
F-statistic code for the GriPhyN pulsar area search, and checking some
calculations for seismic noise reduction in subterranean
interferometers.
Mendell:
The StackSlide code now has the option to use LALSRunningMedian to
normalized the power in the SFTs using the running median estimate of
the power spectral density. We continue to work on comparisons of
our code with the Hough code, and improve our estimated upper
limits. We will soon start working on the code needed to run the
Monte Carlo simulations needed to get the final results.
Shawhan:
- Revised and submitted paper about inspiral waveform consistency
tests to Classical and Quantum Gravity for the GWDAW-8 proceedings
- Spent time reviewing the S2 known-pulsar analysis, which is to be
presented at the APS Meeting in a few weeks
- Updated ivana to fix a minor bug and to add some features for
special veto studies for the inspiral search
Sutton:
I divided my time this week between working on the new DMT code
for calibrations, processing TFClusters events for the LIGO-TAMA
analydid, and editing the LIGO-TAMA paper for the GWDAW proceedings.
Sylvestre:
- Worked on simulations for measuring the TFClusters efficiency on
S2 data.
- Started work on modifying TFClusters to run in stand-alone mode.
Weinstein:
- Working on inspiral s2 analysis review.
- Working on burst waveform catalog for DASWG.
Yakushin:
- Generated low frequency MDC frames for the whole S2 and tested
them with waveburst. Still more testing is needed.
- Working on generating high frequency MDC frames for LIGO-TAMA
analysis.
Lazzarini:
- Revised/edited/resubmitted the H1+H2 optimal signal estimation
paper to PRD.
- Working on verifying the new S2 matlab pipeline, when run against
S1 data gives same results we obtained during S1 analysis.
- Completed the DASWG report on data formats.
General Computing (Wallace)
MIT:
(Keith)
- Installing Solaris9 on several machines
- Built desktop system for postdoc
Livingston:
(Shannon)
- Current bandwidth usage can be seen at http://teche.ligo-la.caltech.edu/mrtg/LLO-Router/130.39.245.1_1.html
- Archived bandwidth usage can be seen at http://teche.ligo-la.caltech.edu/mrtg/archive/
under the dated folder for the week of interest.
- Actually making progress with LSU on the network issues we have
been having. I need to contact them next time it happens so that
they can contact Bellsouth within 48 hours since that is how long their
logs last.
- Having file system corruption on the Linux file server. I
am still working on this issue, and I am a bit nervous about the state
that it is in. We are working on a solution but the next 48 hours
will be critical.
- Moved a lot of equipment into the two new racks including two new
UPSs, 3 Solaris servers, 5 PC servers, etc.
- As usual, some firewall updates.
- Looking into some strange log entries from my firewall.
Haven't had time to determine the problem yet, but this will have to be
looked into next week if the file server issues are taken care of by
then.
- Replaced two failed hard drives on one of the RAIDs on Decatur.
- Ordered some software for Katrina and Rich Abbot to use for web
development for HEPI stuff.
- Ordered several pieces of hardware to replace failed items,
including our server KVM. Warranty was expired on it and it will
cost about $2k to replace.
- Discussed several billing items with LSU over the Internet bill.
- Looking into archiving/deleting several locked accounts at
LLO. They have been locked for about 18 months and no one has
complained, so it is time to remove them from the system.
Need to decide how I am going to archive these files. I think I
will start burning them to DVD and storing somewhere.
- Several miscellaneous user support issues.
Hanford:
(Christine)
- Network usage can be seen at http://www.ligo-wa.caltech.edu/~christin/mrtg/
198.129.208.1_198.129.78.122.html
- New staff member orientation and setup of accounts and office
space.
- Working with Mike Pedraza on PC audits and upgrades. Thanks
so much to Mike for all his help! He has upgraded several
computers to Win2k as well as securing and updating many other
PCs. He also reinstalled Win2k server and I now have a working
Windows server! Some changes that will take place because of his
visit are that the Administrator user account will have the user name
changed, the password changed and lengthened and the password will not
be given to the users. I will also have to start a regular
program for updating every computer.
- Still finishing up the software install and license upgrades for
the new application license server.
- Spoke with the PNNL/ESnet representative. They are planning
on changing our connection from OC3 to GigE and are currently looking
at what hardware changes will be needed. Presently they are
researching media converters.
- Put the latest Solaris patches on all my Sun boxes in response to
the hack at ITS at Caltech.
- Misc. user support.
CIT:
(Bruce Sears)
Ilog/Enote: (3.0
days)
- Working on a port of the entry data from Ilog to Enote for the
Stochastic group.
(Mike)
- Working at LHO this week:
- I have been going through PC's and Laptops, checking
network/registry settings and making some changes to enhance the
network. Patching up security holes by stopping services that are not
being used, but allow hackers to use these types of services as
backdoors. Running windows updates installing critical/security updates
and service packs. Going through event viewer looking for system &
application errors. Correcting all errors that I find. Defragmenting
hard disk. Removing adware & spyware. Keeping Christine
updated on all my findings. Making a few suggestions to Christine on
ways to better secure the network, referring to the windows side of
things.
- Reloaded two visitor workstation's. These were win98 installs
that I wiped clean and loaded win 2000 pro. I also loaded all GC
software and a few engineering packages that were loaded from the
previous load.
- Loaded a NTSRV for Christine. This sever is going to be used for
backup purposes.
- Attended Microsoft security meeting,(San Diego) that was very
informative, in regards to security.
(Lisa)
- Finished the tcl/expect script to program the ap2000's.
- Began replacing the rest of the ap1000 AP with ap2000's.
- Worked on some misc. user problems with wireless access.
- Set up a new account and gave the nickle tour to Mark Turner.
- Many more hours of work on e-mail and spam.
Mail Stats 4/1/04 - 4/7/04
Messages Accepted: 18188
Spam Rejected: 10044
Viruses Rejected: 1131
False Positives: 12
Total Mail Thru: 29363
Mail Stats 4/8/04 - 4/14/04
Messages Accepted: 18043
Spam Rejected: 9448
Viruses Rejected: 1130
False Positives: 24
Total Mail Thru: 28645
(Veronica)
- CaJAGWR website: Videotaped the last talk, captured and
compressed it for web posting. Posting updates to the website.
- LSC website: Working on the website for the upcoming June
meeting. Incorporating an ecommerce interface into the website.
Posted updates to documents at the general LSC website.
- LIGO website: Updates to various pages and usual upkeep.
Addressed a DCC issue. User support at Project Science.
(Larry)
- A number of items to address this week. The wireless access
points are being swapped out with updated units. Just as a note, we
need at least 72 hours notice before adding a MAC address. Adding a MAC
address requires the units to be rebooted and takes some time to get
all of the config files propagated to the different units. So, people
arriving and expecting immediate wireless access without sending the
needed information before hand, will be disappointed. Also, as a
reminder, do not use the e-mail aliases used for general broadcasts
without permission from LIGO management. These aliases are for LIGO
related business only. Any exceptions must be signed off on by someone
in LIGO management.
- Spent time assisting Lisa with the e-mail spam filtering. This is
another area of concern. When someone is notified of a questionable
message, they need to respond ASAP. The message stays in the queue for
only a few days before it is automatically discarded. As can be
seen from the e-mail statistics there is a lot to go through. The
quicker the response the lesser the chance of a legitimate message
being lost. I have received a number of messages from people noticing
that the amount of spam has diminished. It will probably never be
completely eliminated but with the present tools it should be somewhat
manageable.
- Purchased a new lens for one of the Webcams. So far it is looking
pretty good for use in one of the conference rooms. A few minor
modifications are needed before I start testing in the SCR.
- Worked on a number of PC's. Most were reinstallations of s/w and
upgrading the patches.
- Helped Irene with her connection to the new version of the P-Card
s/w. From the short period I spent getting things to work for
Irene, I would say the pkg. is not ready for prime-time yet.
- Made a number of updates on the DNS, host server, account server
and web servers. All were requests but we are working on changes to
accommodate the patches needed on a number of machines.
- Added and removed a number of accounts. The accounts removed also
had their files/data removed from the system. If needed they can be
restored from backup tapes. This process will continue as we are
getting ready for more SURF students and visitors.
- There are a number of matlab fonts that have to be installed in
order for remote usage to work correctly. Albert has supplied the font
listings and instructions for the unix side. The instructions for the
exceed font problem were pretty explicit and do work in resolving the
problem on the PC side of the house.
- Assisted Ed C. with a number of equipment items.
- Started work with Albert and Stuart on some LDAS/GC logistical
issues, as it appears the support from GC for LDAS related issues is
going to increase.
- No major procurement issues this week which is a nice surprise.
Advanced LIGO and
Supporting R&D (Shoemaker)
Seismic Isolation
From: Larry Jones <ljones@ligo.caltech.edu>
Advanced LIGO Seismic
Structure
SEI Structure:
ASI has completed a NASTRAN finite element
model of what they call Stage -1:
the BSC crossbeams, clamps and support tubes. The first resonant mode
is at 21
Hz, with 7 modes below 100 Hz. They are performing analyses to
determine the
phase of the stage-to-stage transfer function. The BSC configuration
development is on plan.
LIGO has directed that the BSC optical table be lowered in elevation by
10 cm,
to accommodate an overall quad height of 200.5 cm.
LIGO has directed that both optical tables have nitronic-60 Heli-Coil
inserts installed in all of the 1/4-20 tapped holes, to greatly reduce
the
amount of particles generated by fasteners.
ASI has released a process specification for fabrication of the SEI
structure,
and issued a draft process specification for precision packaging of the
SEI
structure and pods.
We have requested copies of drawings and fabrication quotations as
structure
design progresses, and have enlisted Mike Gerfens
and
Rick Paniagua, supervisors of Caltech
machine shops,
to assist in making independent estimates of fabrication costs.
Quotations and
estimates will be tracked and compared in an effort to understand and
control
costs.
The Design Review meeting for the BSC structure is now scheduled for May 18, 2004. The HAM
structure
Design Review is scheduled for July
30, 2004. Delivery at LASTI of the BSC prototype is expected
to be
in November, 2004.
Actuators:
A contract was signed with Planning Systems Inc.
(PSI) for the design and
fabrication of voice coil actuators for the SEI prototype BSC structure
for
LASTI. Planned deliveries are as follows:
29 April 2004: interface drawings, small and large actuators
24 June 2004: production drawings and prototype units, one each, small
and
large actuators
30 September 2004: production units, 6 each, small and large actuators
Having production drawings will permit LIGO to competitively bid the
production
quantities of the actuators, likely to be over one million dollars.
A teleconference was held between PSI and ASI (SEI structure
contractor) to
clarify design requirements and to make sure that all known design
issues were
understood. PSI's thermal analysis had
assumed a four
point mounting at the bobbin instead of our planned two point mounting.
The
four point mounting provides higher heat transfer, for lower outgassing; this has now been incorporated in
the SEI structure
design plans. It will likely be implemented by two mounting points and
two
copper cold straps. Bobbin wall thickness and top and bottom flange
thickness
are increased (compared with the actuators previously used) which will
also
result in a cooler bobbin coil. Lateral coil gap has been increased
slightly to
allow for more convenient assembly. The capability of having the
actuators
custom designed is a big benefit to LIGO.
Position Sensors:
Refinements were made in the design requirements
for the position sensors. Jay Heefner will
be directing the procurement of the sensor
probes and modules.
Seismometers:
Nothing new.
Galling/Dusting Test:
Nothing new.
Suspension
From: Janeen Romie
<romie_j@ligo.caltech.edu>
AdLIGO Suspensions
Quad FEA
Working with Dennis and Calum on
Quad/SEI fea. I'm currently working on the
heavy mass/high first
mode model to remove enough mass to meet the mass budget Dennis has
provided.
I've gone from 214 kg to 189kg with a goal of 175kg. I hope to get that
done this
afternoon. I'll run an analysis to make sure that the changes have not
drastically changed the 1st mode.
MC to LASTI in June
Coordinating with many key folks on preparing for the mode cleaner
triple
suspension to go to LASTI in June. The long poles are osems, so far, along with working around
personnel travel
schedules. We will discuss this in more detail at the Tuesday SUS telecon.
Hybrid Osems
I've requested a quote and delivery schedule from a coil winding
house in
Corona - Corona Magnetics - which may be
do the coil
winding for the hybrid osems. Russell
reports that 20
hybrid osem heads/formers should make it
to Caltech
(barring Customs problems) by April 30. We have the Kapton
magnet wire ready to go.
Suspension Gazebo
Minitec in
New
York
has provided us a faxed drawing of the suspension gazebo. We chose a
rectangular structure, made of 90mm x 90mm Bosch-like aluminum
extrusions. I've
asked
Minitec to quote for a kit, so that
we can
assemble the structure here in the Synchrotron. Hopefully, they will
provide
answers to some more questions in the next day, along with providing us
a firm
price and delivery schedule.
Suspensions Controls Prototype Testing Plan
I've received input and comments from almost everyone on the
Suspensions
Controls Prototype Testing Plan. I've
incorporate
all
changes and am just waiting for clarification on a few issues from Mark
Barton
and Caroline
Cantley. As soon as that is
done, I'll
make any more changes necessary and send it around to the
aligo_sus
mailing list.
Primavera
I've been working on assigning Primavera task numbers to the Quad
task list
such that Primavera updates and task scheduling/priorities may be done
more
easily. I will try to get this done as soon as possible as Primavera %
completes are due to Thomas. I'll schedule a meeting with the Primavera
reporting personnel to make the appropriate updates as soon as Thomas,
Calum and I have checked the interfaces.
Core Optics
From: Bill Kells
<kells@ligo.caltech.edu>
As the
downselect issue heats up now, I've
been spending more time re-considering the entire situation and doing
some related studies. What more can we conclude
, near
term about sapphire? How much better will it indeed be functionally? A
lot is related to the thermal issues, and so this has been in close
contact with P.
Willems. Also
whetehr some further OTF measurements on the
samples we have can give some further clues. An immediate need I'm
pursuing
are the
outstanding DRR "action
items" in this regard.
Auxiliary Optics
From: "Mark Barton" mbarton@ligo.caltech.edu
This week Bram Slagmolen
of the AIGO facility at Gingin and I
reached a major milestone in the work that I had come to Australia
to help with. We had prepared and suspended two BK7 test optics, an ETM
and an ITM, and in the last few days we finished installing them in the
vacuum system and aligning them. (See attached photos.) Thanks to Janeen
and Helena for all the prep work that made it possible. The whole
process went without major incident except that we had to do a number
of workarounds because the practice optics weren't quite the same size
as the sapphire optics that the fixtures had been designed for. In the
remaining week and a half of my time here we'll see how far we get
towards locking an 80 m cavity.
Other Laboratory R&D
From: Riccardo DeSalvo
<desalvo@ligo.caltech.edu>
Simoni
We have cleaned and reorganized the OTF laboratory to begin the
constuction of the cavity. Probably lost five ponds in the
process.
We received the suspension maraging components and we built a
support to constrain the shape of the maraging blades and wires during
the bake. Yesterday we started the bake, at the beginning of the
next week we will have the blade and the suspending wire ready to use.
We also received and are preparing most components of the cavity
structures, in the next week we will probably be able to finish the
assembling of the internal part of the cavity mechanics . We
received the initial optics but we forgot ordering the mirror
micrometric screws. As soon as we get the screws we will start to
mount the optics in the cavity. The delayed vacuum tanks should be done
in 10 days.
Mantovani
I almost finished the modifications of the control circuit,
adding the thermal compensation part. In the next week I'm going to
take transfer function measurements to reach lower resonance
frequencies (so far stoppped at 60 mHz vertical frequency due to
thermal instabilities. I have also calibrated the magnetic actuator and
modified the magnetic circuit to improve its performance increasing the
flatness of the working region.
Agresti, D'Ambrosio
Considering the possibility of converting the MHM interferometer from
co-palnar to confocal, like the new baseline Adv-LIGO. We
calculated the corrective coating profile needed to produce M-H mirror
for this confocal configuration starting from spherical mirrors of
different focal lengths. The best starting mirror seems to be a
8500 mm focal length mirror.
For additional information about this report, contact lindquist_p@ligo.caltech.edu