|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday April 5, 2004 will be:
(Meeting time: 10:30 am Pacific Time)
Special Items:
no report
Status of LSC/MOU Research Updates
and Program Reports (Petrac)
(LSC / Status of Research Updates through Aug. 2004 and Prog. Reports
through Feb. 2004)
LIGO Weekly Site Telecon (Lindquist)
There was a site teleconference Thursday, April, 2004. Cost reports
through March, which represents fifty percent of the fiscal year, have
been prepared and are posted on the
network. The rest of the meeting
was dedicated to a continuation of the Change Control Board. See
below for status.
The list of current actions revised to reflect
the status of open actions assigned through the last update (March 4, 2004)
may be found at ACTION
LIST.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
Nothing Significant to report.
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
ACTIVITY
| 04/01/04 | Packages | Faxes |
| In | 28 | 27 |
| Out | 5 | 37 |
Press here to access the DOCUMENT
CONTROL CENTER WEB PAGE.
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA.
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
SUPPORT (Baldon, Lloyd, Tischler)
>Irene Baldon
ADVANCED LIGO (Cost Schedule
Control Systems) T. Frey
From: Thomas Frey <tfrey@ligo.caltech.edu>
For list of documents that
are being used to develop Adv. LIGO Cost and Schedule, see
http://www.ligo.caltech.edu/~tfrey/Cost_MTG_082002/
Working on the integration of project summary data created by Carol. Due to Carol on Friday.
IO - Still need completed WBS dictionary and BOE. Starting to prepare current progress update and EV reports.
Will send update request for progress through 4/2/04.
LDAS - No action required at this point in time.
INSTALL - No action items pending.
DAQ - No action required at this point in time.
PM - No action required at this point in time.
FAC - No action required at this point in time.
SUP - No action required at this point in time.
LASTI - Sent the revised progress data collection spreadsheet to David O. David provided his progress data on Tuesday
Working with Irena regarding the bounced email addresses reported by use of the LSC mail list(s).
Continue to work with Carol and Florence starting work setting up "crosswalk" between accounting and progress reporting.
Project Web Site for posting schedule and progress related data continues to be updated with the latest and greatest.
LIGO Video--Tom Lucas
(Lucas Productions) will be visiting Caltech April 22 and 23 to interview
people. Tom is building the "plot line" for a 20-25 minute NOVA type
video on LIGO under a Grant from the NSF. I will be arranging interviews
with Caltech personnel for Tom. Tom will be traveling from Caltech
to the Hanford site to participate in the "star party" currently scheduled
for April 24.
A LIGO Change Control Board (CCB) meeting was scheduled for Monday,
March 29, 2004 as part of the normally scheduled Executive Committee meeting
and was continued on April 1, 2004 during the Site Teleconference.
The following Change Requests were discussed:
| CR Number | Description | Submitted By | Date |
| CR-040003 Rev B | Sensors & Actuators for the Advanced LIGO Seismic Isolation System (SEI) Prototypes | L. Jones | March 18, 2004 |
| CR-040004 | Budget
to cover New Projectors in Livingston Auditorium
|
P. Lindquist | March 19, 2004 |
| CR-040005 | Sensors & Actuators for the Advanced LIGO Seismic Isolation System (SEI) Prototypes | L. Jones | March 23, 2004 |
| CR-040006 | Scope Reduction and Cost Increase for the HEPI Effort. | D. Coyne | March 26, 2004 |
| CR-040007 Rev A | Thermal
Compensation System (TCS)
|
D. Coyne | March 31, 2004 |
| CR-040008 Rev A | Budget Adjustments for Post Doc Salaries based on Actual Costs | P. LIndquist | March 31, 2004 |
| CR-040009 | Budget Adjustment Mechanical Engineering Position at Livingston | M. Zucker | March 26, 2004 |
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
Summary of Commissioning Activities at LIGO Hanford Observatory (compiled by M. Landry)
Major work this week has been on the 4K laser, as it is swapped out
for another
unit (the Livingston spare), and the PSL table was reconfigured.
We had trouble with an inadvertent partial vent in the vertex, resulting
in a spike
up to 9e-6torr. While repositioning plumbing associated with
a roughing pump,
a small amount of air was introduced into the vertex (vacuum seals
may have
been compromised by pump hardware placed after meatlocker installation)
.
Beam tube gate valves autoclosed, and later the 2K and 4K vertices
were manually
isolated. Once vertex pressures returned to standard operating
points (~hours), gate
valves were reopened. The port is blanked off and will not be
worked on until the next
scheduled vent in ~June. Plots are available in the elog,
and a DCC document
will be submitted in the coming days, describing the event and future
safeguards.
4K IFO
More sophistication was built into the 4k ASC system, as off-diagonal
elements
were employed in the QPDs, and a new un-OPLEV filter bank was added.
The IFO was offline for the majority of the week due to the PSL swap.
The
laser team noted today that 70% transmission had been achieved in the
PMC,
elogs forthcoming.
2K IFO
We chased alignment drifts for much of the week optics (examples here,
and here),
often flying blind without trends or test points. Suspicion has
been cast on the input
pointing servo but drifts are evident when it is off. The 4K
is offline so we don't have
a second machine to compare. Recall (Mar 11 weekly) we replaced
pulsed heating
in the LVEA for staged heating, to mitigate 60Hz sidebands in ASQ;
temp control
was another suspect but LVEA trends do not bear this hypothesis out.
A lens was swapped
out on the 2k output port ISCT10, to reduce the beamspot
size on the WFS1 photodiode.
DAQ
The state of the DAQ at the outset of the week, after major upgrades,
is elogged here.
no report
Rich Abbott
1. All hydraulic work is complete in the X end
station with the exception of wetting the control valve portion of the
system. The procedure for completing this was reviewed Wednesday
by Joe G, Brian L. and myself, now a DCN must be prepared and submitted
for final approval.
2. All electronics is on site now for completion
of the X end station installation. Much paperwork is needed to conform
to our installation criteria for new electronics. This is a work
in progress and must be completed by next week.
3. The pump servo has been running in the X
end station for most of the last week. The system seems to be responding
well so far as air removal is concerned up to the plane of the 4 way isolation
valves on the piers.
4. As of now, the status of the hydraulic control
valve commissioning leaves something to be desired. Out of a total
of 92 valves:
8 were shipped calibrated to MIT
22 were discovered to leak in one way or another.
This requires more definition
7 were rejected based on aspects of their performance
(hysteresis etc.)
The final leak test is revealing additional leaky
valves from among the remaining 55 units. This really needs additional
scrutiny and cross checking before conclusions can be reached and that
is ongoing. The plan now is to get as many flawless valves in a heap
and analyze the remainder once the "good" valves are weeded out.
5. Installation of actuators is proceeding well.
We are on to the third pier in the Y end station without major issues.
The experience in the X end station served well to improve the process.
6. The piping installation is well underway in the corner station. About 70% of the main 1.5 inch piping runs are complete. The installation of manifolds and running of the 1/2 inch lines will take the bulk of the time and is now about 15% complete.
a. The Pier Interface box PCBs have come back, and
they seem O.K. They will be stuffed this week, and sent to Livingston
to replace the 4 that I sent with jumpers in them.
b. I have finished the system schematic for the HEPI
system End Stations. The Vertex schematic is underway, and will be
finished in the next few weeks.
c. I have started getting ISS PDs together for Hanford.
d. I am working to get QPDs for the 40m lab, and am
going to order the 2 new IFR signal generators that are needed.
e. The 3123 oscillations are still under study.
Jay Heefner reporting
EMI Upgrade
- Cables and components continue to arrive for EMI
upgrade at LLO.
Installation of the Y end will begin next week.
Output Mode Cleaner
- Putting together and testing electronics components
tobe used in output mode cleaner.
Low Noise DACs
- Continued discussions with Vern and FDI about possible
sources for the excess noise measured during some of the tests here at
CIT.
- Shipped 7 more DACs to LHO for installation and
testing. They now have 8 units.
- 5 modules will be shipped to LLO today.
Sander Liu
In the process of testing both the transmitter and receiver board (optical coupling for HEPI compliance with RFI requirements). The transmitter board seems to work OK but the receiver board run into oscillation problem. Initial inspection reveal that tracing on board might be too long and looped around the wrong place by Protel's autorouting process.
The NPRO that was recently removed
from the 40m Lab 10-W laser was
turned on using a standalone NPRO power supply.
Apart from the drop in
output power, which is not too surprising given the
number of hours
accumulated, the other difference was the default
crystal temperature. As
far as I know this cannot be set from the 10-W laser
power supply so I do
not know how this would have altered without accessing
the potentiometer on
the back of the laser. It just might be that
there is some voltage offset
in the 10-W laser power supply that triggered this
off.
The default crystal temperature was restored and the
diode current was
increased to bring the power level up to the shipped
value of 550 mW.
After a week of running no obvious problems have been
observed. At least
not with the output power or various temperatures.
I have been going through the 10-W
laser power supply PCB as the
designators on the schematic differ from those actually
on the board. The
diode drive electronics section has been completed.
The machined pieces for the output
modecleaner vacuum chamber are
taking longer than expected. Partly due to the
relative size of the vacuum
chamber and locally available EDM machines.
The high-voltage instrumentation
vacuum feedthrough is a longer than expected lead
item. Although the
promised delivery is consistent our other time constraints.
The machine
shop on campus does realise that I would like the
parts as soon as
possible.
A cost analysis of the installed 4K TC system and
an estimated cost for 4 additional TC systems was completed.
A technical note describing the design calculations for determining the mask sizes and the heating patterns projected onto the ITM is in progress.
A CCB request for the funds required for the additional systems was submitted, reviewed and approved.
OTF Lab. (W. Bridge)
The (21) pieces of the new twisted, shielded, teflon
cables are under test.
We are taking ring down and beat frequency measurements
as well as the RGA of the chamber every day.
Absorption Test Measurement prototype in progress
We have received the other sapphire substrate PINK
color from Lyon, France. (314 mm Dia. X 131mm thick.)
We have scan the mirror for absorption measurement
and it has been completed.
later we'll test this mirror for absorption at different
depths and noise sensitivity.Other
priority came up.
We borrowed a small sapphire substrate rod 10mm in
Dia.x 20mm long from Standford to calibrate a standard at CIT.
this sapphire rod is an undoped rod, it is uniform
and ~ 50-55 ppm/cm in loss at 1064nm. with this
we are going to calibrate a sapphire sample which
is a 80mm cube.
we just completed a scan for absorption for this sapphire
rod.data
treatment is in progress.
We are still improving the absorption and detection
sensitivity by testing different samples
and improving the optical set up as well as the quality
of the different optics.
Scatterometer system in standby
OTF Lab at Lauritsen ROOM 38 NO CHANGE.
Cavity #3
The cavity is locked and we are taking ring down and
beat frequency measurements every
day as well as the RGA for the chamber.
Cavity #2 Test cavity optical set up in standby(
NPRO s/n 414 was given to the 40m lab.)
Misc... tasks
I made a special holder for the borrowed sapphire
rod.
I just finished making the groove on the 8-32 SHCS
for the OMC suspension.
The design of a new mount for the 80mm cube sapphire
sample is in progress.
no report
LASTI Weekly Report (Allen,MacInnes,Mason,Ottaway,Ruet,Sarin)
Pradeep worked on characterizing the noise from Position Sensors
and Geophones and readout electronics in the LASTI HEPI setup, in
preparation for doing the same at the LLO setup starting next week.
Rich and Laurent have analyzed the BSC platform position vs spring tension
data and posted it on the LASTI ilog (3/31/04).
The BSC now has fluid running though all of the actuators, it only need
some cables in order to start running it again.
Myron and Ken have been finalizing the components for the vacuum
compatible geophones that will be sent to Livingston.
Dave measured the power saturation properties of the Lightwave 10 Watt
laser to compare with his model.
The LASTI vacuum system has been sealed and is now under vacuum (~1E-5
torr as of thursday morning). As this system has been up at air for
nearly
a year it will take an appreciable amount of time get the water out
that
has been aborbed in the viton.
Simulation and Modeling (Bhawal)
Weekly Physics Meeting
-------------------------
Luca from LHO described current status of interferometers and current
issues related to Wave Front Sensors. The problem related to extracting
input mirrors' differential alignment signals was discussed. Matt
described his work on LinLIGO. Virginio talked about improvements in
the
code for Violin modes. Biplab from LHO described phase camera that
Joe
Betwiezer has set up at LHO and related problems on FFT modeling of
lensing and propagation effects.
More e2e examples
-------------------------
(Hiro) A few interests are expressed from overseas, one from Australia
(Mark Barton), one from UK (Sabina H. Huttner), for use of e2e
to
study the
high finesse Fabry-Perot locking and the effect of radiation
pressure
in
Mode-cleaner.
Two new example modules are being written so that they can start
from a
working model, instead of starting from scratch, which may be
tough.
From LHO
-------------------
(Biplab)
Phasemap: Received various parameters for the phase camera setup
from Joe
Betzwiezer and interacted with him about the set up
and his
data and phasemaps he captured so far.
Introduced
lens phasemap in Matlab interface for FFT but
faced
the problem of reduction in the number of pixel for
a focussed
beam.
WFS: Interacted with Luca on FFT results
and current problems of
extracting
differential Input mirror (DITM) misalignments.
Generated
signals for WFS 2a and 2b for excitation of common
and differential
ITM misalignments respectively under various
heated
conditions and calculated demodulation angles.
Dual Recycling Michelson Cavity
------------------------------------
(Hiro) A document, written using Mathematica, is being revised, and
the
matlab
code is cleaned up so that it is easier to define the configuration
and
running condition.
One scenario after this is completed is that Biplab writes an
e2e
primitive and Hiro develops the formula with modal model included.
LAL/Orsay group is interested in participating in the model
development.
LinLIGO
------------
(Matt) Worked on integrating sophisticated noise plotting into the
existing
LinLIGO transfer function model.
FFT runs with all phase maps
-------------------------------
Xiao and Hiro have started to study the effect of the phase map on
sidebands.
Now with the thermal compensation working well, it is interesting
to
know
the effects of actual phase maps on various aspects.
Last year, a SURF student, Raghu of SLU, developed a code to
convert
the measured phase map data for use in the FFT program.
Raghu used it and placed the phase maps in the FP arms to find
that the
performance degradation is not larger. This was mainly focused
on the
Carrier. Also, the existence of the thermal effect was not taken
into
account.
Xiao is using this software to convert more phase maps and running
the
FFT program with the thermal effect taken into account.
There is not all data available, but this study will give
semi-quantitative
results if the surface aberration can have observable effects
on the
performance.
More sophisticated study will follow if this study indicates
positive
results.
Code development and maintenance
----------------------------------
Preparation for new e2e package release:
Hiro and Melody are working together toward the release of the
next e2e
package, 2.0.0.
The big thing is the dynamic linking at run time which makes
e2e much
more flexible.
Also an effort is devoted to make the installation cleaner and
robust.
(Melody) Modeler:
Resolved some building and threading issues with a 64 bit Linux
system.
Committed FUNC_X changes into CVS and resolving some build issues.
Worked on some documentation for the release of FUNC_X.
(Ed Maros) Added option to build e2e without generating documentation
(--disable-documentation).
Alfi
-----------
(Melody) Working on using the client system's default editor to edit
the
primitive settings.
LIGO Data Analysis System
Software Systems (Blackburn)
Modified the frameAPI and the createRDS user command such that it
no longer uses a resource variable to determine whether or not to
perform checksums on input frame data. This functionality has now
been migrated into the user command as a flag with a default to
not checksum.
Added a new flag to user commands that read input data from frame
data to perform a sanity check on the start time of data inside a
frame against the start time of the frame filename. Performance
tests are currently being performed to determine the appropriate
default for this flag.
Work continues on TCL/Globus callbacks needed to adopt the same
paradigm as the PyGlobus package. Discovered that a separate
package was needed to suppliment TCL with thread support. This
TCL thread extension library has been added to the tclglobus
development server and development is now underway to utilize
this package in the callback solution.
Proposed an upgrade to the automake 1.8.3, and libtool 1.5.2
packages to the DASWG. No comments have been received from that
group on whether or not this is a recommended change for all
the different projects.
Rebuild all CC applications on tandem-ii environment. Discovered
an issue with emacs with this newer gcc compiler. Will be doing
further investigations on this problem prior to recompiling all
the CC applications on the LDAS-DEV system.
Made very good progress on open problem reports this week. Worked
on 15 problem reports this week, closing out 11 of these, all
under software.
Completed the system level test suite and posted the results.
Ran database performance benchmarks to compare speed of DB2 8.1
against the currently supported DB2 7.2 in preparation for the
upgrade of LDAS to DB2 8.1.
Hardware Systems (Anderson)
Caltech
-------
(Dan Kozak)
* Did T3 firmware (pSOS and disk) upgrades to all T3s at LLO.
* Continued emptying HPSS of LIGO data. Have had to fix HPSS
a number of times. Am also saving md5sums for data in
SAM-QFS after comparing to HPSS md5sums.
(Hari Pulapaka)
* Working on setting up LDR Datafindserver on ldas-gridmon.
* Added mounts for users home directories on ldas-grid.
* Working on adding new documentation for job submission on
ldas-grid.
* Added a new metric to ganglia with output similar to iostat.
* Working with Keith and Igor by giving inputs and generally
helping out with installing grid-related software.
(Al Wilson)
* Testing ldas-pcdev1 - Still having problems with this machine.
Passes memtest. But fails burn test, and to stay running the
OS for overnight. The last test is to load the OS and burntest
again. All complaints have been reseated.
* Test-gridmon - System has been put online. When the grid
machine arrives (new MB) the grid system on the test system
will be setup and ready to go.
* BB is still giving false possessives. Datacache1 for some
reason is still sending messages regarding disk scans. Will
perform a reload of the BB program to see if this helps.
(Stuart Anderson)
* Removed the SRL sub-net from the 6th floor of Millikan.
* Worked on data distribution script to interleave data
files from the central archive to the LDAS-CIT cluster
internal node disk space.
* Installed Fedora Core 2 Test 2 release on test IDE-RAID
server. This worked much better than the Test 1 release
but still needs work before it can be used. Currently,
the keyboard, mouse and RAID units do not fully work.
* Switched ftp mirroring tools from an old unsupported
program named fmirror to the newer actively maintained
and fuller-featured lftp.
MIT
---
(Keith Bayer)
* Installed NIS on cluster (ypserv -d is useful).
* Continuing work setting up cluster for condor.
* Helped with setup of 10 node DMT cluster.
* Specing out GE-fiber cards for dataserver/pcraid6/pcraid7.
Livingston
----------
(Igor Yakushin)
* Working with Patrick Sutton on preparation of the final set
of MDC frames for LIGO and LIGO-TAMA S2 analysis.
Hanford
-------
(Greg Mendell)
* In the current raw frames a File Checksum exists, but FrCheck
fails with a Frame Checksum error. Previously there were
no
Frame Checksums in the raw frames. I am working with
Ben Johnson and CDS to sort this out. It seems that the
files are OK, but the Frame Checksum is not being set
correctly or should be left out of the raw frames. (The Frame
Checksum is perhaps redundant with the File Checksum for
files with 1 frame).
* Worked with Ben Johnson and the commissioners at LHO to
temporarily archive and reduce data from studies performed
last week. The final reduced data from the studies should
be ~30 GBs, which we can permanently archive.
* I'm also working to set up another test of how LDAS handles
the data valid flag in the frames, and will put a PR on this
into the LDAS gnats system if the tests indicate this is
necessary.
(Ben Johnson)
* The DOE Cert for ldas-grid.ligo-wa has been requested. Just
waiting for approval/receipt.
* Linux kernels on ldas-grid and ldas-gridmon are now at
2.4.20-30.9smp.
* Frame files being generated by the new DAQ system have
contained bad "frame" and "file" checksums. Greg and I are
working with CDS to make sure that the checksums from the new
DAQ system are valid, useful, and to the frame specification.
CDS has already modified framebuilder code to produce useful
file checksums.
* Used "lokkit" to configure the iptables firewall on ldas-grid.
Now it only allows incoming ssh connections. Working with Hari
to see what the appropriate iptables settings are for Ganglia
on ldas-gridmon.
* Working with Vern Sandberg on writing up a short report on
the "dataValid" problem. A preliminary draft of the dataValid
problem report with input from Stan should be enterted into
the E-Log at LHO on Friday April 2.
Data Analysis Activities (Lazzarini)
Mendell:
Mike Landry and I wrote matlab code that compares the expected results
from the StackSlide and Hough code. We hope to report on this
at the
next PULG telecon.
Shawhan:
* Gave a talk at the Pacific Coast Gravity Meeting on the status of
LIGO searches for binary inspirals
* Finished revising inspiral veto study paper (with Nelson Christensen
and Gaby Gonzalez), and submitted it to Classical and
Quantum Gravity
for the GWDAW-8 proceedings special issue
* Working to finish paper about a new inspiral waveform consistency
test
(work done with Evan Ochsner last summer) for the GWDAW-8
proceedings
* Modified guild to add some new functionality when retrieving frame
data.
* Added information about LIGO database tables to DASWG web pages.
Sutton;
I drafted and presented a talk titled "Status of LIGO" at
the 20th Pacific Coast Gravity Meeting, here at Caltech.
It was well received.
With Igor Yakushin I've been coordinating the simulations
which will be used to characterize the efficiency of the
S2 bursts search. They will be based on MDC frames containing
simulated signals without noise, generated by Yakushin. I've
also proposed this to TAMA as the mechanism for joint LIGO-TAMA
simulations.
Finally, I've been drafting a note for the GWDAW proceedings
on our plans for the LIGO-TAMA untriggered bursts analysis.
Weinstein;
- Working on Inspiral review.
- Working on modeling galactic SN sources for burst search.
Yakushin:
Working with Patrick Sutton on preparation of the final set of MDC
frames for LIGO and LIGO-TAMA S2 analysis.
General Computing (Wallace)
MIT:
(Keith)
-Ordered Solaris 9 for gc (and SB1500's)
-Arranging meeting with Tufts for June LSC
-Manufacturer testing SCSI/IDE raid array
-Found trouble on new SB1500 (automount of non-existent dir)
-Replaced backup SCSI hdd for gc filesystem (with duplicate)
-Investigated booting off of LSI SCSI card on SB1500's (works)
Livingston:
(Shannon)
-Current bandwidth usage can be seen at
http://teche.ligo-la.caltech.edu/mrtg/LLO-Router/130.39.245.1_1.html
-Archived bandwidth usage can be seen at
http://teche.ligo-la.caltech.edu/mrtg/archive/ under the dated folder
for the week of interest.
-Looking into some network problems at LSU (again!) that seem to stem
from their intrusion prevention system.
-Added an additional subnet and set up IPs to the PIX firewall.
Also
added the associated firewall rules for this subnet. This will
be used
exclusively for DHCP hosts.
-Moving the software archives off of the "softwareserver" AKA
annette.ligo-la.caltech.edu and moving them to a suitable location
on
the RAID server. The applications will only be available via
NFS
capable systems for now. This means that a windows user will
have to
use SCP to copy installation files for software packages.
-Reinstalled the helpdesk software that we used a while back.
All
support requests for LLO GC should come through here now.
-Ordered two new UPSs for the racks that we will be installing in the
coming weeks.
-Ordered a couple of servers for the Intellution software which will
be installed on the building controls system.
-Ordered a laptop from Dell for Bonnie to use.
-Added a "network management" subnet to the PIX. This will make
it
much easier to administer the network switches around LLO.
-Working with Solsoft on an apparent bug that I have found in their
software. The gateway selection for one of my networks is not
persistent between saves.
Hanford:
(Christine)
- Network bandwidth usage can be seen at
http://www.ligo-wa.caltech.edu/~christin/mrtg/ 198.129.208.1_198.129.78.122.html
- Most of this week has been spent building disk systems and installing
application software on the new license server. I had to transfer
licenses for some software and have purchased some additional licenses
and renewed maintenance support for others.
- I'm also setting up and installing Win2k on a Dell server for a CDS
project.
- I'm preparing for Mike Pedraza's visit on Apr. 12.
- Misc. user support for; ssh tunneling problems from a home computer,
web page editing how to, questions about how Norton handles virus files
and notified Ben Johnson one of his LDAS/GC gateway computers was having
problems resolving host names and couldn't send out e-mail.
- Richard McCarthy is making arrangements to have a spare fiber pair
connected through to PNNL. This would be used for testing the
new
network connection.
CIT:
(Mike)
-Updated the Ansys license server, with a renewed research license.
-I swapped out John Zweizig, with a more updated laptop. His old laptop
would not run on battery. It would only run on AC. I have surplus his
old
laptop and pulled the old parts that were good and added them to the
updated laptop. These laptops are out of warrantee. (This is a
motherboard
problem on the old laptop)
-Work on Barry's laptop. There were multiple software issues that I
corrected for him. I also came across a backup issue that took up a
lot
of
time. This was due to a hardware error that had our backup sequence
fouled
up. Everything seems to be back on track with his laptop.
-Reloaded 2 loaner laptops that came in from travel. These laptops
had
OS
errors and software issues. I have these laptops back into our loaner
pool.
-Swapped out Ed Chargois's with an updated laptop that was turned in
by
one
of our users. This laptop was turned in with a hardware issue. I fixed
this
with parts from a surplus laptop.
-Ghosted the following user's workstations, Irena Petrac, Ken Mailand
and
Paul Russell.
-I received a new laptop & workstation that I am currently loading
GC
software, and configuring network/security settings.
-I also had the usual onsite/phone support, which included printing,
e-mail,
software, and some networking issues.
(Lisa)
- On Sunday I put in a new primary mailserver. The swap went
very
well. There
were a couple of small glitches with the mailman mailing lists due
to a
version
change with python. As part of the upgrade, I now have CanIt
running
on acrux.
I am in the process of training the spam filters and have set up a
mailbox for
people to forward their spam to. It turns out that some of the
forwarded spam
is being caught in the spam trap. It's interesting that it didn't
get
caught
the first time. There is a bug fix version of the spam filters
that was
released yesterday that might fix this problem.
For those corresponding with international groups you need to get the
addresses
put on a white list. The spam trap has a tendency to capture
non-English e-mail
and having people on a white list will cut down on the false positives.
Avoiding the use of html is also a plus. The e-mail filters prefer
plain text.
- As part of the switch to the new mailserver, I needed to make changes
to
sadal, the mailman server. This resulted in a couple of glitches
for
the
calendars that should now be resolved.
- Went to the ITS monthly security discussion. That included
an
interesting
presentation from someone at IPAC who went to the RSA security
conference.
Individual user passwords are still the number biggest problem in
securing a
network.
- Mail Statistics from 3/28 - 3/31
Total Messages Accepted: 10969
Total Spam Rejected: 4427
Total Viruses Rejected: 777
(Veronica)
- LIGO website: Installed the March newsletter. Prepared high-resolution
LIGO images for a publication by British Science Council. Updated pages
throughout the website. Updated the roster database.
Provided assistance to Donna on webpage setting. Addressed an issue
with
maillists.
- LSC website: Discussed with Irena and Linda the logistics and workflow
of the MOU submission. We need to meet with all interested parties
to go
through the process again before we can start working on the makeover
of
the automated submittal system.
Posted late-arrival presentations from the last meeting.
- CaJAGWR website: Assisted Paula Lonergan in setup for videotaping
of a
talk. I need to get the videotape from her and compress the footage
for
streaming. Posted updates to the website and provided user support.
(Larry)
-This has been an interesting time as far as procurements go. I spent
a
great
deal of time with CISCO trying to get things sorted out on their
contract.
Someone on their end just loaded a number of items on to our contract
because
the Caltech name was associated with the other equipment. It is getting
sorted
out but there is still some work to do.
Received a couple of SUN and Dell boxes.
Worked on a couple of orders for other groups.
-Continue working on the computer room expansion. PMA is now having
the
power
usage from existing supplies to see if they can find enough power to
put in the
room without running a new source line.
I have started setting up the racks and populating one with test
equipment.
-We did some more testing with the WEBcams and have found that they
do
work well
in a presentation type situation. Still working on getting some zoom
lenses for
the units.
Also, spent some time looking for better webcams. The industry is always
changing.
-Working a some disk cleanup. Generating a list of old accounts that
we
will
pass around before removing the accounts and associated files.
-Assisted a number of users with different e-mail issues. So far they
all turned
out to be a bad configuration on the local computer or a typo on the
users part.
-No new news from ESnet on the h/w swap.
-Assisted a number of people with different web related issues. Most
just
needing to have their pages testes.
-Assisted DCC with a couple of document issues.
-The regular user support but was surprised that I did not have to
restore any
files for anyone this week.
Advanced LIGO Seismic Structure
SEI Structure Design/Fab contract:
ASI is applying fewer hours than expected. A re-plan has been completed, resulting in schedule delays and considerable increase in expected cost from a bottoms-up analysis. ASI has instituted a new policy to decouple the HAM and BSC design efforts from parallel to series, with no sacrifice in commonality. The re-plan has shifted the BSC design review by 8 weeks and the HAM design review by 19+ weeks; prototype delivery is shifted by 12 weeks. We are considering various options to deal with the expected cost increase.
A first-order configuration design (hexagonal beam) has been completed on the BSC Stage 0 structure. A coarse finite element model (FEM) of Stage 0 with external support members was completed to assess resonant frequencies, and a technical memorandum covering the findings of the Stage 0 FEM assessment was compiled. ASI has run into some issues in sizing the BSC Stage 0 configuration: the external structure is not stiff enough to keep Stage 0 modes above 100 Hz. This was discussed with Giaime. A detailed finite element model of the BSC support structure was started.
The Design Review meeting for the BSC structure is now scheduled for
Actuator Testing and Redesign:
Procurement of the actuators is awaiting a budget decision by the Change
Board.
Position Sensor Probe Development:
RGA scans were made of the LHO empty vacuum oven at elevated temperatures and of the single position sensor probe assembly at 100C and at ambient. Although our RGA sensitivity is insufficient for full confidence, outgassing results appear favorable.
Procurement of the position sensors is awaiting a budget decision by
the Change Board.
Seismometer Procurement:
This task is on hold pending management approval for SEI structure prototype
fabrication.
Galling/Dusting Test:
All testing is now complete. Data evaluation is in process.
Working with Dennis and Calum on Quad/SEI fea.
Bill Grady delivered the wooden quad structure to the Synchrotron and
its very cool. I will make mock-ups of the
masses and upper blades to
use as aids in determining the best assembly approach.
Working with
Suspension
http://www.ligo.caltech.edu/~ctorrie/SUS_MEETING/SUS_MEETING.html,
at a
link on the left side of the page titled Suspension Workshops, LLO
March
2004.
Working with Calum
on design details for the double pendulum. Had a
discussion with Russell, Caroline and Calum
about how best to approach
the catcher design in the near term.
From: ctorrie <ctorrie@ligo.caltech.edu>
Probably a monthly report, as I have not sent
one recently
Weekly Report
Advanced LIGO Suspensions
1) FEA
Working with Dennis and Janeen with
input from Larry. We have modeled many configurations of the ETM quad structure
and non-associated mass in both ALGOR and ANSYS Workbench. This work will
be added to a new revision of T030044-03, by Dennis Coyne
2) Layout
I have been working on the layout of the beam splitter suspension and
ETM / ITM suspensions with Norna Robertson.
3) Controls Prototype Quad
Working is ongoing for the controls prototype suspension for LASTI.
This involves Caltech, RAL and Glasgow. Several avenues have been advancing
recently including the requirements for the final 2 stages, a blade testing
unit in RAL, blade design, top mass requirements and laying out several
possibly catcher / assembly designs for the final stages.
4) Prototype Single Pendulum
Working with Helena Armandula we have
successfully suspended a 40kg single pendulum in the lab with the aid of
the ergonomic arm.
Photographs can be found at : -
http://www.ligo.caltech.edu/~ctorrie/SUMMITSUSmar2004/singlependulum40kg.jpg
The next plan involved suspended the 2 final stages of an ETM quad from
a support structure: -
http://www.ligo.caltech.edu/~ctorrie/QUAD_ETM/single%20and%20double%20pend%20tests-01.jpg
5) Design Meeting
We now have a weekly design meeting with the suspenders from Stanford,
Glasgow, Caltech and RAL. It is held Mondays at
The focus is the ETM / ITM controls prototype for LASTI.
The notes and actions are updated on: -
http://www.ligo.caltech.edu/~ctorrie/QUAD_ETM/quad_etm%2520setup%20page2.html
6) SUS Summit
A web page that collects the
talks and notes from the SUSPENSIONS SUMMIT MEETING at LLO from the 18th-19th
March 2004 can be found at: -
http://www.ligo.caltech.edu/~ctorrie/SUMMITSUSmar2004/summitsusMar2004.html
(several talks / links have still to be added)
7) Link to my talk from the LSC
On the DCC search for G040095-01
On Thursday, March 25th we had a teleconference with CSIRO.
In attendance from CSIRO: Roger Netterfield,
Mark Gross, Bob Oreb
From Glasgow University: Sheila Rowan and Jim Hough
From MIT: Gregg Harry
From Stanford: Martin Fejer and
From Caltech: Helena Armandula
The telecon was set up to discuss with
CSIRO a series of coatings suggested by Jim Hough.
The goal of these coatings, oxygen rich and oxygen deficient films
of Ta2O5, aim to see if the film's stoichiometry
affects coating loss.
As result of the discussions, CSIRO
will fabricate Ta2O5 coatings which are (i) oxygen
deficient, (ii) 'standard' and (iii) oxygen rich, characterizing the stoichiometry.
CSIRO will make Young's Modulus measurements, stress measurements,
perform XRD and XPS on these films first deposited on 1" samples, and,
he will report on the results before coating the "deliverable parts".
Annealing processes were discussed for these initial samples; the annealing parameters will be chosen to emphasize the stoichiometry.
It was also decided to test commercially polished substrates in an effort
to reduce cost.
A few coating runs failed (at CSIRO and LMA) diminishing the stock
of substrates.
Relevant test are underway to confirm that changing to commercially
polished substrates will not impact the current research plan.
AdvLIGO SUS
Bonded ten 1/2"dia. SF2 substrates to fused
silica. No problems encountered.
From: "Erika D'Ambrosio"
<ambrosio@ligo.caltech.edu>
I am working on the concentric configuration for flat top beams: the
problem
can be studied by exploiting the formal symmetry with the flat case.
The instability due to radiation pressure induced torque has also
been theoretically analysed. I will
ask Kip how to proceed, since
the quantitative assessments are based on the first article on non gaussian
beams to reduce thermoelastic noise,
which has not been published yet.
My approach is completely analytical and I have tested it in a well-known
case
to check that the obtained set of eigenvalues
is the expected one. A note on
the formalism I am using and the results I am getting is going to be
written
by JuriAgresti
and me. Further analyses are going on for our project on flat
top beams, regarding some fabrication issues for the mirror profile
that
corresponds to the nearly concentric case. The flat configuration will
be
tested first and then we will switch to the concentric one. I am giving
all
the support I can to Barbara anJuri,
both in terms of educational training
and mathematical tools I had developped.
For additional information about this report, contact sanders@ligo.caltech.edu