Weekly Report for Week Ending December
11, 2003
The LIGO Executive Committee
Agenda for Monday December 15, 2003 will be:
(Meeting time: 10:30 am Pacific Time)
The meeting Monday, December 15,
2003 will be a Staffing Committee meeting. There will be no Executive
Committee meeting scheduled.
Special Announcements:
Weekly
Report Highlights
LSC Issues (Saulson)
No report.
LIGO I Construction/LIGO Laboratory
Administration (Lindquist)
LIGO Weekly Site Telecon (Lindquist)
There was no site teleconference scheduled on Thursday, December 11,
2003.
The list of current actions revised to reflect
the status of open actions assigned through December 4, 2003 may be found
at ACTION
LIST.
PROPERTY
MANAGEMENT (Chargois)
From: Ed Chargois <chargois_e@ligo.caltech.edu>
-
Provided assistance to General Computing (L. Wallace) with the disposal
of twelve (12) assorted Computers, four (4) Monitors, one (1) Tape
Library, and one (1) Electronic Cabinet. These items were declared
not economically repairable.
-
Provided assistance to the DCC (L. Turner) with the disposal of a copier
MITA DC 3060, Serial Number NM37052880. This machine was stripped of usable
parts to repair the third floor copier.
-
Providing assistance to Caltech Property by assisting with the PMA
Property Audit.
DOCUMENT
CONTROL CENTER (Turner, Mak)
>From: Linda Turner
- turner@ligo.caltech.edu>
Web pages for
the DCC give simple how-to's for document numbering, easy access to the
latest on-line documents, and search capabilities for the DCC database.
Take
a look. . .
ACCOMPLISHMENTS
-
Continued
to work with George. The new version of the DCC database program
has been installed on all DCC machines after thorough testing. We
now have the capaibility to enter, transfer, and update--both internally
and publically--each document in real time. This has enabled a labor
intensive procedure, especially for transferring electronic documents,
to be greatly consolidated and automated. George has created some
remarkable user-intuitive features that will be a pleasure to use.
-
Met with Norm Franks from AFS to consider the DCC's storage needs.
His company manufactures high density file systems, similar to what is
currently installed in the DCC. I showed him a couple of proposed
floorplans where additional shelving might be added. Working with
these plans, we configured shelving that would add 50% more to what we
currently have. The accordion shelving units that we've used for
the past 8 years provides 600 lateral feet of filing space. The proposed
new units would add another 340 linear feet. A formal quotation is
expected from AFS this morning, but rough estimates placed the cost at
about $11,000 including shipping, delivery, and installation.
-
Several MOU's were processed and posted.
-
The electronic documents are completely processed and current to date.
-
Worked on the upcoming LIGO holiday party. We have over 70 people
signed up as of this morning.
>
From: Cleveland Mak <mak_c@ligo.caltech.edu>
ACTIVITY
Packaged and shipped PAC 15 binders to Hanford for Meeting
| 12/11/03 |
Packages |
Faxes |
| In |
22 |
38 |
| Out |
19 |
28 |
Press here to access
the DOCUMENT CONTROL CENTER
WEB PAGE.
COST SCHEDULE
CONTROL SYSTEMS (Cunningham, Brambila, Kaufman, Salone)
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS
PAYABLE HISTORY DATA .
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
-
Completed change order # 2 to George Stokes. Completed change order
# 17 to MCI. Completed change order # 1 to Southbridge Sheet Metal.
Completed change order # 4 to the LaCour blanket order 1053188. Completed
change order # 3 to Southern Enterprises. Completed and routed change
order # 142 to Triad for signatures.
-
Placed and reconciled pcard orders. Followed up on delivery schedules
for the 10 rush orders shipping to MIT for Mike Smith. Followed up
on credit card orders placed for Ken Mailand.
-
Obtained data and prepared spreadsheet for Ed Jasnow pertaining to contracted
personnel.
-
Resolved issues on one time standard purchase orders.
From: Gina Salone <gsalone@ligo.caltech.edu>
-
Continuing to manage and update contracts
-
Generating requisitions to extend maintenance agreements on copiers
-
Ordering toner cartridges for copiers and fax machines
-
Assisting accounts payable with invoice corrections
-
Working with Florence on possible correction to Northrop Grumman invoices
From: Florence Kaufman <fkaufman@ligo.caltech.edu>
-
Completed report for the Visitor Account as of November 2003. All
funds from the award for the period from July 15, 2000 through June 30,
2003, which was on a No Cost Extension through June 30, 2004, have been
spent. New charges for visitors should be made to the new account
LIGO.VISIT/1 NSFLIGO.VISITO.
-
Attended a workshop on Discoverer on Monday afternoon from 1:00 to 5:00
p.m.
-
Submitted 2 Cost Transfers to correct misclassifications of expenditures
within the FY04 Award.
-
Requested Expenditure Type correction for travel expenditure in the Visitor
Program which was charged to Travel-Domestic Allocable rather than Travel-Participant
Support, thereby resulting in unwarranted Indirect Cost charges.
-
Provided requested information to Garilynn Billingsley.
-
Provided analysis of the FY03 expenditures for Livingston Facilities and
met with Ed Jasnow and Allen Sibley to review amounts for FY04 budget.
-
Financial reports can be found at: http://docuserv.ligo.caltech.edu/~fireport
SUBCONTRACTS
MANAGEMENT (Petrac, Jasnow)
From: irena@ligo.caltech.edu (Irena Petrac)
LSC MOUs / Attachment Updates and Program Reports
ACIGA:
Draft-Attach. B for 08-15-03 to 02-15-04
/ in LIGO review / Shoemaker
Draft-Attach. B for 08-15-03 to 02-15-04
/ in process for web posting
Attach. C for 08-15-03 to 02-15-04 / in
LIGO review / Barish
Draft-Attach. C for 08-15-03 to 02-15-04
/ in process for web posting
Attach. D for 08-15-03 to 02-15-04 / in
LIGO review / Barish
Draft-Attach. D for 08-15-03 to 02-15-04
/ in process for web posting
Prog. report against Attach. B / in process
for web posting
Prog. report against Attach. C / in process
for web posting
Balearic:
Attach. A for 02-15-03 to 08-15-03 / to
Prof. Sintes for signature
Attach. A for 08-15-03 to 02-15-04 / in
LIGO review / Lazzarini
Draft-Attach. A for 08-15-03 to 02-15-04
/ in process for web posting
Attach. Z for 08-15-03 to 02-15-04 / to
Prof. Sintes for signature
Carleton:
Attach. A for 02-15-03 to 08-15-03 / in
process for web posting
Attach. Z for 02-15-03 to 08-15-03 / in
process for web posting
Attach. A for 08-15-03 to 02-15-04 / in
LIGO review / Barish
Attach. Z for 02-15-03 to 08-15-03 / in
process for web posting
Attach. Z for 08-15-03 to 02-15-04 / in
process for web posting
Caltech Experimental Gravitational-Physics
Group:
Attach. A for 02-15-03 to 02-15-04 / to
Prof. Drever for sign-off
Attach. B for 02-15-03 to 02-15-04 / to
Prof. Drever for sign-offf
Attach. Z for 02-15-03 to 02-15-04 / to
Prof. Drever for sign-off
Institute of Applied Physics (IAP):
Attach. C for 08-15-03 to 02-15-04 / to
Dr. Sergeev for sign-off
Attach. Z for 08-15-03 to 02-15-04 / to
Dr. Sergeev for sign-off
Inter-University Centre for Astronomy
and Astrophysics (IUCAA):
Attach. A for 02-15-03 to 08-15-03 / to
Prof. Dhurandhar for sign-off
Attach. A for 08-15-03 to 02-15-04 / to
Prof. Dhurandhar for sign-off
Attach. Z for 02-15-03 to 08-15-03 / to
Prof. Dhurandhar for sign-off
Attach. Z for 08-15-03 to 02-15-04 / to
Prof. Dhurandhar for sign-off
Loyola:
Attach. A for 02-15-03 to 08-15-03 / to
Prof. McHugh for sign-off
Attach. A for 08-15-03 to 02-15-04 / in
LIGO review / Lazzarini
Attach. Z for 08-15-03 to 02-15-04 / to
Prof. McHugh for sign-off
Northwestern:
Draft-Attach. A for 02-15-03 to 08-15-03
/ in process for web posting
Draft-Attach. A for 02-15-03 to 08-15-03 / in LIGO review / Lazzarini
Draft-Attach. A for 08-15-03 to 02-15-04 / in process for web posting
Draft-Attach. A for 08-15-03 to 02-15-04 / in LIGO review / Lazzarini
and Riles
Draft-Attach. Z for 02-15-03 to 08-15-03 / in process for web posting
Draft-Attach. Z for 08-15-03 to 02-15-04 / in process for web posting
Prog. Report against Attach. A of February 15, 2003 / in process for
web posting
Prog. Report against Attach. A of August 15, 2003 / / in process for
web posting
Southeastern Louisiana Univ.:
Attach. A for 02-15-03 to 08-15-03 / to
Prof. Yoshida for sign-off
Attach. A for 08-15-03 to 02-15-04 / to
Prof. Yoshida for sign-off
Univ. of Florida:
Attach. A for 08-15-03 to 02-15-04 / in
LIGO review / Lazzarini
Attach. C for 08-15-03 to 02-15-04 / to
Prof. Mitselmakher for sign-off
Attach. D for 08-15-03 to 02-15-04 / to
Prof. Mitselmakher for sign-off
Attach. Z for 08-15-03 to 02-15-04 / to
Prof. Mitselmakher for sign-off
Subcontracts:
-
Lightwave: Released a no-cost
contract modification to extend the performance period through Sept. 30,
2004 to Purchasing. The continued level of technical servicing of the LIGO
high-power lasers is under discussion.
-
Univ. of Oregon: The proposal for
FY'04 funding, in support of Univ. of Oregon's continuing on-site support
activity at Hanford, has been under consideration by LIGO for some time
now. Note: Univ. of Oregon's FY'04 effort is under way since August 30,
2003.
From: Ed Jasnow <jasnow@ligo.caltech.edu>
No report this week (became a grandad again).
SUPPORT (Baldon, Lloyd, Tischler)
>Irene Baldon
PLEASE NOTE: This report covers a
two (2) week period and includes a three (3) day trip to LHO to work with
Terry Gunter and the Thanksgiving Holiday.
Processed the paper work for seven (7) new/revised trips. Additionally,
there are nine (9) trips completed and waiting the necessary paper work
to be completed; and there are nine (9) trips in various stages of completion
before ticketing can be done and/or paper work completed. I continue
to work closely with Terry Gunter and LIGO/Hanford personnel in acquainting
them with travel procedures, etc. I will continued to close out existing
LHO trips and/or assisting where necessary. I continue to process
and reconcile travel started on Ryan Tischler's P-Card while I was on vacation.Completed
twenty-six (26) Expense Reports and there are thirty-two (32) reports yet
to be done. I continue to contact travelers who have outstanding
Expense Reports (more than one (1) month old) to ask for their cooperation
in sending me their receipts so that these can be closed in a timely manner.
Presently there are five (5) reports more than 30 days old.Reconciled one-hundred-three
(103) P-Card items which required numerous phone calls to hotels, car rentals,
etc., in order to track down which traveler incurred which charge; and
the pulling of each traveler's file to assure that charges are correct
for each fee incurred.I continued to cover the Project Office, Barry Barish's
and Donna Tomlinson's Office when called upon.Worked on the preparation
and distribution of the Travel/Vacation Itinerary for December 8, 2003.
Arranged seventeen (17) new or revised teleconferences and four (4) new
reservation on the LIGO Calendar.
>Dorothy Lloyd
Processed the usual invoices for payment. Tracked and followed up on
invoice problems. Reviewed and recorded payments processed by Esther the
week of December 1.Processed the usual requisitions, change orders and
payment requests.Continue to monitor contract and blanket order encumbrance
and notify task managers when supplements are needed.Jim continued with
data entry in the LIGO database and helping out in the DCC.
>From: Ryan Tischler <rtischle@ligo.caltech.edu>
PAC15 detailsPreparation for submission of Final Report for award PHY-980158
(Advanced R&D)LIGO space renovation report to PMA. Submit requests
now!!!
ADVANCED LIGO (Cost Schedule
Control Systems) T. Frey
From: Thomas Frey <tfrey@ligo.caltech.edu>
Out of the office on 12/5 and 12/8.
For list of documents that
are being used to develop Adv. LIGO Cost and Schedule, see
http://www.ligo.caltech.edu/~tfrey/Cost_MTG_082002/
Continued development of
a proposal for implementing Primavera Project Planner Enterprise.
Phone conference with
Carol regarding status of SUS schedule changes and input. Also discussed
IO, PSL, SEI, and COC.
Advanced LIGO Request
The following is a summary
of status by sub system:
COC - Still need completed
WBS dictionary and BOE. Followed-up with Garilyn Billingsley regarding
changes to the schedule.
PSL - No action
items pending. Comments pending per changes made to schedule by
Carol.
AOS - Still need completed
WBS dictionary and BOE.
IO - Still need completed
WBS dictionary and BOE. Corresponded with David Reitze regarding
changes and progress data.
SUS - No action items
pending. Attended meeting on Tuesday with SUS group to discuss
data input. Executed meeting with Janeen, Dennis and Carol to go
through the SUS cost estimate and adjust for current scope considerations.
SEI - Schedule changes
are pending per our meeting of November 12. Followed-up with Larry
Jones regarding changes to the schedule.
ISC - Still need completed
WBS dictionary and BOE.
LDAS - No action required
at this point in time.
INSTALL - No action items
pending.
DAQ - No action required
at this point in time.
PM - No action required
at this point in time.
FAC - No action required
at this point in time.
SUP - No action required
at this point in time.
Cost Book Tool.
ROSTER DATABASE:
Continued input of
changes / corrections regarding supervisors and departments.
Issued two new revisions
to the Authorship list. Made database structure changes to accommodate
the some new requirements.
Development of the Advanced
LIGO Project Controls Guidebook continues.
Project Web Site for posting
schedule and progress related data continues to be updated with the latest
and greatest.
Reports
(Lindquist)
The NSF caught up with the fact that we have yet to submit a final report
for the Advanced R&D Grant (PHY-980158) when FastLane pointed the Knarly
finger at LIGO and held up our FY 2004 funding. We are working on
it. We may request some additional information from selected R&D
task managers.
Reviews of the FY 2004 Operating budgets continue.
Change
Control/Contingency (Lindquist)
The following change requests are open.
| CR-030015 |
FY 2003 Livingston Observatory Detector Maintenance Expenses
(Increment) |
R. Wooley |
July 14, 2003 |
| CR-030016 |
Hanford Facilities 2.2--Divide the Large Equipment Access
to Facilitate Movement of Large Items (currently assigned to FY 2004 liens
list) |
J. Worden |
July 31, 2003 |
Human
Resources (Akutagawa)
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
-
Various personnel/payroll /HR related work.
Quality/Safety (Tyler)
>From: Bill Tyler <tyler@ligo.caltech.edu>
-
Safety audits of LIGO on-campus labs have been started by an audit team
comprised of the LIGO Laser Safety Officer (campus), LIGO QA and Safety
representative and the Associate Director, Radiation Safety Officer and
Health Physicist of the Caltech Safety Office.
-
With the exception of the 40M lab, the lab audits should be completed during
the next week.
-
The audit of the 40M is anticipated for early next year.
LIGO Hanford Observatory (LHO)
and Interferometer Operations (Raab)
Summary of S3 Activities at LIGO
Hanford Observatory (compiled by M. Landry)
More conjecture about the microseism as an impediment to locking is
given here.
Also in the same entry, a description is given of the clear correlation
of lock losses and trucks passing on the bumpy route 10. A follow-up
report notes that, even if such truck passings don't unlock an ifo, up-conversion
into the gw band is observed. Seismic and wind impacts on locking
are shown here.
After a testing phase, a GRB alarm is now running in the control room.
The diamond-shaped GRB widget now goes red on the site overview screen
when notification of a GRB event is received. The idea is to ensure
that the IFOs remain in science mode if possible (e.g. no breaks for calibrations
or injections, etc) for at least the hour following a GRB, in case there
is some long-term GW activity associated with the burst.
Roughly 290 burst and inspiral waveforms were injected
into H1 and H2.
The two day PAC15 meeting is underway at Hanford, 11-12 Dec.
DAQ
DAQ mysteries
such as fb3 restarts and h1adcuex problems were observed. Investigations
into the low-bit flips (seen in data such as the 2k state vector and the
4k MC sensor channels) are ongoing: the DAQ controller cpu was vindicated.
LIGO Livingston Observatory (LLO)
and Interferometer Operations (Zucker)
S3 (or "What
doesn't kill you, makes you stronger..." )
Logging activity close to LLO continues to prevent useful locking
during daylight hours. We also lost about 3 full nights of the last week
to high microseismic activity from storm-related wave action in the Gulf
of Mexico. Equipment troubles of various kinds are credited with further
reducing the L1 duty factor.We have redoubled efforts to debug the equipment
problems, with a view toward recovering duty factor (weather permitting)
and stabilizing noise for the remaining few weeks of the run. So far this
push has flushed but some nasty bugs:
-
The extreme low-frequency noise (below 60 Hz) was found to be dominated
by angle-->length coupling from the ITM alignment controls. Fine-balancing
the ITM coil output matrices to remove this coupling gave a factor of three
reduction in strain noise from 20 to 60 Hz.
-
An anomalous result, stumbled across in the process of balancing the ITMx
coils, eventually unraveled a much deeper standing mystery. We have been
plagued by a stationary 1/f2 noise floor around 100 Hz since
(at least) the beginning of summer. It turns out three of four relays on
the ITMX driver nominally charged with selecting the low-noise "RUN" mode
were not responding to their command. Those three noisy ITMx coils accounted
for most of the strain noise between 70 and 150 Hz. A strain improvement
of about a factor of two at 100 Hz was achieved by goosing the relay drive.
-
A frustrating push to rework the WFS3/WFS4 control allocation using new
model results eventually uncovered a partially blown Pentek ADC, which
may have been wreaking all kinds of havoc for some time. It's been replaced;
we now expect better luck applying WFS3 and WFS4 to control the recycling
cavity, as originally envisioned.
-
We have tracked intermittent bursts of 10-30 Hz seismic activity at both
end stations to malfunctions or tolerance issues in HVAC fans and chiller
cycling. Although we can see the signatures of these vibrations in the
low-frequency strain noise, we have yet to establish a positive link between
these events and lock loss (mainly because so many other things also cause
lock loss...)
-
Due to parameter drifts we don't yet understand, the microseismic feedforward
has apparently on occasion introduced spurious motion of several fringes
amplitude at frequencies above its intended active band. In retrospect,
we're pretty sure this buzz brought the interferometer down at least three
nights when we could find no other problem. We added margin so it's less
likely to happen again (plus, we know what to look for now).
-
Continued investigation of sudden lock-losses NOT attributable to seismic
or alignment issues remains inconclusive. Mode cleaner dropouts recently
have become highly variable in rate, ranging from a few per hour to none
in 7 hours.
-
An unplanned interaction between the QPD beam centering and WFS1 may have
contributed to much of the alignment instability observed over recent weeks.
The problem has been temporarily resolved by just letting WFS1 "win."
-
These efforts and a microseism window finally permitted enough locking
to get some of our PEM injections done. A quick analysis of the results
may uncover other glaring interactions, and maybe some can be fixed quickly.
Safety/security
(Rich Riesen) Replaced faulty proximity detector on machine
shop exterior door. No more false alarms.Eliminated minor safety hazards.
1) trip hazard. 2) electrical concern. Site tour found
no other safety concerns.Pre HEPI installation work: Getting the
Toyota forklift, Genie lift and class 100 trailer ready for the end station.
Scheduled annual crane inspections for units that did not get inspected
last go around. Ensuring that "in chamber" and "class 100 area" apparel
is ready on demand.Finishing up with the GSA sale equipment.Installed computer
and printer in shipping & receiving to better facilitate contacting
recipients of received packages, scheduling pick-ups, printing UPS and
Fedex shipping labels.
S3 and detector
optimization (V. Frolov)
I worked on diagonalization of the test mass coil actuators. The
coil drives were tuned to minimize the contribution of the angular drives
to the ifo darm response. In the process of doing the tunning I found that
three coils on the ITMX were not switched from the acquire state(high noise
high dynamic range) to the run state(low noise) due to the undervoltage
of the switching circuit.
HPLF, S3 Detector
Studies, IO Faraday Upgrade (R. Amin)
HPLF: No outstanding reports, except. Three weeks ago, US Laser misplaced
our purchase order for a high power laser shutter ordered earlier in November.
Two weeks ago LLO contacted them to both remind them of our purchase and
reorder the product (thank you Bonnie!). The shutter is due to arrive
this week or early next week.Lock Loss: With respect to the growing interest
in lock losses of the L1 detector, I have been compiling lock loss time
series data for lock breaks that occur for both known and unknown reasons.
Last week I sorted through several lock loss data in hopes to find error
signals that herald the onset of detector failure or mode cleaner failure.
So far data collected has been pointing towards the PSL and mode cleaner.
However, enticing artifacts of data have generated inadequate evidence
due to nonuniform sampling rates in the PSL.Faraday Isolator Upgrade: The
proposal to replace the current Faraday isolator is nearing completion.
Basic designs, cost analysis, vacuum incursion plans, and a second draft
proposal are complete. Stray field analysis models have been constructed
based on LIGO tech document LIGO_T970149-00-D by Sanichiro Yoshida et al
and are being debugged. A final proposal is expected to be
delivered by early next week.
CDS software
(C. Parameswariah)
Documenting the software robots
-
ROBO-SCIMON - Locked statistics automation and elogger,
-
ROBO-PLOTTER - Daily Summary plot automation,
-
ROBO-SCIFOM - Figure of merit and seismic noise capture and elogger,
-
ROBO-BOOTLOGGER - Reboot logger
Investigated the causes of the Y End seismic noise cycling in the 10 -
30 Hz band. Traced it to the chiller.Found the ascaux processor was/got
rebooted last night. Burt restore was missing. Fixed the channel values
with a burt restore.
LDAS (Yakushin)
LDAS admin:
1) Disabled 'Fast Load' option for the
tape robot.
LDAS data analysis:
1) Working on line removal algorithm in
waveburst.
2) Produced and tested sine-gaussian burst
MDC frames.
General Computing
(Roddy)
The latest news on the Gigabit connection to the observatory is that Bell
South will be ready by Dec 18th. LSU will be ready by Dec 22nd.
This means that the Gigabit will not happen till I return from vacation
on Jan 7th. At some point after that we should be ready to go live.
LSU is going to provide us with the new router and also the interface cards
for our firewall.Did a fresh windows install on a machine to put in the
shipping and receiving area. The usual windows/office/norton/etc.
Beware of Service Pack 4. After a fresh install of Windows, SP4 crashed
the OS. Had to start over again.Have unplugged a machine on the network
which I believe is infected with a virus. Have not had a chance to
check and see which one yet, but I was getting alerts from one of the IDSs.Coordinated
with Rich to send our old E3000 to sun to receive a trade in credit towards
a 280R purchase. The "machine formerly known as Sirius" is no longer
with us. It was basically unused for the last year anyway.
The machine is terribly slow now and I am surprised Sun was willing to
give us any kind of trade in value.Trying to work with the software.caltech.edu
folks and improve the reliability of the software downloads. They
seem to not be very interested in the fact that it is nearly impossible
for us to download site licensed software at the observatory.Patched several
linux boxes with the kernel/rsync/etc. security patches.Once again I had
to track down some invoices from Dell. This is always a headache.Mounted
the LDAS shares on touro at Igor's request. People are complaining
that decatur is too slow. However, touro is not necessarily supposed
to be used for analysis work in this manner. This is something that
should be looked at in the future. Decatur desperately needs to be
upgraded to Solaris 9 after the run, but more importantly, the hardware
is showing its age. Ideally decatur needs to be upgraded to an SF880,
but that is around $40k if I remember correctly. I do not like the
idea of hard mounting the LDAS nfs shares to multiple GC machines and some
sort of better solution needs to be found.
Burst analysis
& S3 detector support (K. Franzen)
-
One SciMon shift since last week.
-
Continued the veto study of S2 WaveBurst events. I am now also trying to
include L1 glitchMon triggers in addition to L1 WaveMon triggers in order
to further increase the veto efficiency.
-
Continued to produce H1 S2 WaveMon triggers.
S3 Data Quality
(Wang)
I checked the S3 data segments every day. The lock loss for
segment L1:239 ( 754356088-754356736 ) was caused by a large seismic bump
in the X end.
LLO Seismic
Retrofit (Rich Abbott)
Working exclusively on HEPI. Ben has largely finished the assessment
of the cabling and RFI feed through issues. He anticipates being
ready for the next task early next week. I have sent out the first
boards to the board house and ordered a bunch of parts. I am working
full bore on finishing more of the circuit boards. Things are going
well in general. Flavio is working on the pump speed controller to repackage
it and incorporate a new isolation amplifier.Tasks completed so far include:
Ordered all chassis parts and have started to receive them Ordered front
panels for seismic interface chassis Ordered differential receiver boards
for seismic interface chassis Am about 75% complete on the AA/Whitening
board for the seismic interface chassis Ordered all parts for differential
receiver board in seismic interface chassis Rear panel for VME crate RFI
feed through has been designed and is ready to go to the panel house Excel
has progressed well in completing the pump controller boxes and is almost
complete.Much of the legwork to date allows rapid conclusion of the remaining
tasks. It takes a lot of time to research the proper parts, but once
they are found and available the designs can progress much faster.
LLO Seismic
retrofit (J. Kern)
The shop manufacturing the machined parts for the hydraulic actuator
ison target to deliver the balance of sets for 84 actuators this week.
Four actuators have been assembled and leak checked and 4 more are in assembly.
These will be delivered to LLO next week for final assembly and shipment
to MIT for installation on the BSC. HAM piers are completed and 4 will
be shipped to MIT next week as well. Springs are on track and 8 will
be shipped to MIT before the 19th. 2 shops, manufacturing the HEPI housing
and boot have fallen behind on production and it appears that the earliest
we'll have parts to assemble for fit-check will be early January. A vendor
has been selected to fabricate the pump station carts and assemble them.
Ken Mailand released drawings this afternoon and we'll begin fabrication
immediately. Ordered computer, daq cards and cables for the valve
calibration pump cart. Working on directing long-distance the assembly
of the cart in Lafayette. Completed the mechanical Installation RFQ and
statement of work. Ed Jasnow is reviewing it. Marcel gave a familiarization
to a few LLO staff members who will be involved in assembling and installing
HEPI.
Detector/Technical Support (Coyne)
see also the Revision Technical Review Board (RTRB) status
here
Seismic Upgrade Project
see also the LASTI report for HEPI experimental
progress
Jonathan Kern reporting
-
The shop manufacturing the machined parts for the hydraulic actuator is
on target
to deliver the balance of sets for 84 actuators this week. 4 actuators
have been assembled and leak checked and 4 more are in assembly. These
will be delivered to LLO next week for final assembly and shipment to MIT
for installation on the BSC. Images of the first new welded actuator can
be found here: http://www.ligo-la.caltech.edu/~jkern/Actuator_progress_20031201/
-
Working on completing the final bill of materials for HEPI, and ordering
much miscellaneous hardware and minor purchased parts. Ordered thru-hole
load cells and displays for the springs. Ordered our custom 4-way valve
for the bypass tree.
-
Mike, Rus, Allen, Rich A and Dennis began a critical look at
the installation schedule and staffing requirements.
-
HAM piers are completed and 4 will be shipped to MIT next week as well.
-
Springs are on track and 8 will be shipped to MIT before the 19th.
-
The two shops, manufacturing the HEPI housing and boot have fallen behind
on production and it appears that the earliest we'll have parts to assemble
for fit-check will be early January.
-
A vendor has been selected to fabricate the pump station carts and assemble
them. Ken Mailand released drawings this afternoon and we'll begin
fabrication immediately.
-
Ordered computer, daq cards and cables for the valve calibration pump cart.
Working on directing long-distance the assembly of the cart in Lafayette.
-
Completed the piping Installation RFQ and statement of work. Ed Jasnow
is reviewing it.
-
Marcel gave a familiarization to a few LLO staff members who will be involved
in assembling and installing HEPI.
Ken Mailand
-
The pump station manifold welding / machining operations are in progress
may be completed by 12-16.. The motor mount plate and the manifold mounting
brackets are in the shop and should be complete by 12-17.
-
The main frame and valve mounting plates and bracket drawings are complete
and at LLO for fabrication.
-
The 7 granite bases have been ordered and will be delivered to LLO in two
weeks.
-
The accumulators have been ordered and should be delivered to LLO the week
of 12-8.
-
The pumps are complete and in shipment to CIT for inspection and a modification
to mount a 3 axis accelerometer bracket.
-
An approach to the reservoir design making it a small <5 gal. capacity
and possibly mounting to the distribution manifold will be complete 12-12,
and fabricated at LLO.
-
The fluid biological growth test is showing nothing after 37+12+4 weeks.
[12 weeks dark environment] [4 weeks with the following materials added
and placed in light] I have added aluminum, copper, brass, and iron to
the fluid to represent the materials in the system, and moved it to the
light.
CDS
DMT
John Zweizig
With much invaluable assistance from Dan Kozak, Stuart
Anderson and Al Wilson, I was able to bring up a cluster of 4 Linux nodes
for use in offline detector characterization using the DMT. The cluster
has access to the Caltech data archive and has all the necessary software
for running DMT applications and monitors.
Several modifications to the DMT software were necessary
to allow coexistence of the Linux code with the Solaris code in the same
directory tree. I have also been making changes to the DMT software to
facilitate its use in offline batch environment for e.g. trigger generation.
CDS Software
Rolf Bork reporting
12/4 report:
-
Continued work on HEPI software. All EPICS and front end software functional
for corner station. Testing in progress. Code written such that it will
work for end stations and MIT as well. Latest work has been installing
the GDS modules. Test points are working and ready to test excitations.
Final piece to be done is FIR filtering. Still do not have specs for this,
which is becoming very worrisome ie could blow away the present code design.
Really need this info ASAP.
-
Also, spoke with Rich this week, and we will change the corner station
design slightly. Instead of a split backplane VME crate, we will go with
two separate VME crates. The number of cables coming into the crate was
overloading the available space for feedthrus on the new RFI crates, plus
the number of cables in the VME crate air plenum would reduce our airflow
to below minimum requirements for the VME modules. This has no effect on
the software or number of VME modules required.
-
Alex
continues work on the new DAQ/GDS code for LLO, which provides space for
HEPI on the new network. Framebuilders and TP manager are operational.
AWG still needs work.
-
Hongyu has made a couple of minor requested changes to dataviewer. She
is now working on some DAQ diagnostics software.
-
Still
need to get with M. Evans on some details on the new ASC software. This
code development has not yet begun.
12/11 report:
-
Continued work on HEPI software. After discussions with Joe Giame (LSU)
and Heisheng Hua and Brian Lantz (Stanford), now have specs for the FIR
filtering section. This has been installed in the software and seems to
be working fine. Stanford is rerunning their models and will get FIR filter
coefficients to me soon. Last pieces of code are to read in pump station
status and output settings to the STS2 units. We may want to test the new
software on the MIT system in early January prior to installation at LLO.
As for VME hardware, the ICS110B ADC modules arrived this week. Delivery
of VME processors has been delayed until early January.
-
Software updates for the DAQ network upgrade after S3 continues. Framebuilder,
DAQ controller, TP manager and AWG are all running. Update of the ADCU
software is in progress. After that, LSC and suspension control software
will need to be modified.
CDS Hardware
Rich Abbott reporting
Working exclusively on HEPI. Ben has largely
finished the assessment of the cabling and RFI feed through issues.
He anticipates being ready for the next task early next week. I have
sent out the first boards to the board house and ordered a bunch of parts.
I am working full bore on finishing more of the circuit boards. Things
are going well in general. Flavio is working on the pump speed controller
to repackage it and incorporate a new isolation amplifier.
Tasks completed so far include:
-
Ordered all chassis parts and have started to receive them
-
Ordered front panels for seismic interface chassis
-
Ordered differential receiver boards for seismic interface chassis
-
Am about 75% complete on the AA/Whitening board for the seismic interface
chassis
-
Ordered all parts for differential receiver board in seismic interface
chassis
-
Rear panel for VME crate RFI feed through has been designed and is ready
to go to the panel house
-
Excel has progressed well in completing the pump controller boxes and is
almost complete
Much of the legwork to date allows rapid conclusion
of the remaining tasks. It takes a lot of time to research the proper
parts, but once they are found and available the designs can progress much
faster.
Jay Heefner reporting
Suspension: Week before last, discovered an oscillation
in the bypass path for the sus pd whitening interface board. It is caused
by the choice of resistor values in the circuit. It is cured by putting
a 10pF cap in the feedback path of the circuit, per the datasheet. A DCN
will be issued to upgrade all boards in the system.
RFI Upgrade: Week before last, received a quote for
the EMI racks that we recently tested. It is significantly lower than any
quote received to date. Since the performance is essentially the same as
the best rack tested, we (Rusyl Wooley) will order Knurr racks. A request
for a revised quote (with relatively minor changes) has been made.
Thermal Compensation: Alex and I succeeded in getting
EPICS to run on a linux pc with a Measurement Computing PCI-DAS-1002 IO
card. The card has 8 differential analog inputs, 2 analog outputs, 16 binary
inputs and 8 binary outputs. One card should support the controls required
for each of the systems to installed at LHO.
Lower Noise Anti-Image Boards: Looking at design alternatives
for an anti-image board to be used with our new low noise DACs.
Sander Liu
Working on the optical link for the GPS clock distribution
system. (Note this will be needed for HEPI since we are imposing the new
RFI standards and we need a different means of connection of the clock
signal than the current 4-oin lemo connector.)
PSL
PeterKing
Week before last: I have been troubleshooting my high
voltage amplifier that is to beused
in the beam pointing control experiment. A number of things were
tested out on the circuit. The monitor port is truly a monitor port
now, without some excess noise that was experienced with the previous version.
A broadband peak around 85 kHz was traced to a faulty regulator.
The high voltage offset was trimmed down to 100 uV and it was found that
the offset trimming circuit added some noise to the output of the high
voltage stage. This was remedied. The output voltage noise is less
than a factor of 2 off from a noise model.
Further to last weeks' high voltage amplifier troubleshooting,
theamplifier
was tested with a dummy load of 0.7 uF. This mimics a PZT in the
steering mirror mount. The output current limit had to be increased
in order to maintain a bandwidth of 500 Hz but the limitation seems to
be the slew rate of the amplifier. The output voltage noise of the
amplifier remained the same. Initially part of the problems were
due ringing in the output of the function generator used in testing.
Full power testing also revealed a slew rate problem with the OP-37 based
monitor.
A relatively minor change will be made to the laser
enclosure in the PSL Lab to activate the panic button. This is one
of the outcomes of the recent lab safety inspection.
Active Thermal Compensation
see also report from Dave Ottaway (MIT)
Mike Smith
CO2 Telescope Projector:
Several re-designs of the thermal compensation optical
bench were made to accommodate the availability of vendor components.
Parts are arriving at MIT for two thermal compensation optical bench assemblies.
The parabolic mirrors from Edmund are delayed until 1/9/04. The CO2 laser
periscope from Thorlabs will not arrive until 12/18/03. Most of the mechanical
parts being made by CIT will arrive on 12/15; one bracket may be delayed
until 12/16. Phone and e-mail discussions are being held with Daniel
S., Doug C., Ken M., Dave O., and Mike S. to finalize the installation
configuration of the thermal compensation bench and periscope steering
mirror at LHO 4K. Mike Smith has made travel arrangements to be at MIT
during the week of 12/15 to assemble the CO2 laser mask projector. He will
return to MIT the week of 1/12/04 for alignment and testing of the projector.
Optical Contamination Cavities
Lee Cardenas, Liyuan Zhang
OTF Lab. (W. Bridge)
Contamination Cavity # 1
-
The new sample still under test, the solder for the OSEM assembly.
RGA, Ring down(RD) and beat frequency(BF) measurements are being taken
everyday. This sample is "clean" because the ring down as well as
the beat frequency have not changed. No mirror absorption has been detected
from these samples.
-
Absorption Test Measurement prototype in progress. The new 30 watts laser
from Quantronix. is finally ready. The mode is OK and power desired is
on. We'll start laser alignment into the scatterometer enclosure.
-
Scatterometer system in progress. We have the new base to house the larger
Sapphire mirror in placed. New base plate to hold the original Fused Silica
ITM is in place.
-
Complete scanning of the HR surface of a new 3" FS mirror coated by CSIRO
has been completed. The transmission indicates that the coating is not
very uniform – shows a low spatial frequency variation across the diameter.
Results have been reported to CSIRO so that they can think about how to
correct (e.g. go to planetary stage).
OTF Lab at Lauritsen ROOM 38
Cavity #3
-
We have changed a new set of mirrors that have been cleaned [72 ppm mirrors
from ATF(AdvancedThin Films)}. The cavity is locked. We are taking ring
down, beat frequency and RGA measurement everyday. This chamber is ready
for the next sample( cabling) from Larry Jones.
Cavity #2
-
Test cavity optical set up in progress
40 Meter Interferometer (Weinstein)
Commissioning
(Miyakawa, Kawamura, Sakura):
-
Osamu, Seiji, and Shihori have been working on tuning the filters for length
control of the Fabry-Perot-Michelson to achieve low-noise operation.
-
They did a careful calibration (documentation in progress) and a displacement
noise spectrum. To reduce the noise, they are working on implementing whitening
and dewhitening filters in hardware, with appropriate software compensation.
-
They succeeded in reducing the noise above 2KHz (to around 1e-16 m/rtHz)
using the hardware LSC whitening filter, after adjusting offsets and gains.
-
They had trouble employing the dewhitening to the coil drivers; there was
a large 100 Hz oscillation. They traced it to the MC servo cross-over (between
MCL and VCO). They reduced the MCL gain, but MC locking became less stable;
they suspect VCO saturation.
-
But, with the modified MCL/VCO gains, the noise in the 30-300 Hz region
is now 2x better than before.
-
Another problem with the hardware dewhiting filter is that the board is
RevB2; should be B5. This has been fixed; now, the dewhitening filter transfer
function is according to design.
-
There's also some 4kHz oscillation in the coil driver. All under investigation.
-
The symmetric port beam seems to be clipping at an in-vac Brewster prism
mirror. This might improve once we properly mode-match into the IFO (not
yet done).
-
IFO auto-locking scripts have been developed and tested.
-
QPDs and cameras have been installed and aligned at the ends (TRX and TRY).
Still need to install the remaining optics in POX and POY, and complete
the sym port (SP) beamline, including electro-optic shutter.
-
Next big step is to implement 166 MHz RF sidebands and demod boards at
166, 133, and 199 MHz.
-
And, tune mode-matching into the main IFO.
-
Osamu is documenting all the IFO locking, tuning, and calibration procedures
that he and Seiji are developing.
Computing:
-
Our main "online" computer, op140m, crashed last week, bringing all commissioning
to a halt.
-
Lisa Bogue came to our rescue, and with Jay, they took the opportunity
to finally bring up our Sun E450's and completely re-arrange the computers
in our control room. Bob, Steve, and Osamu all helped rearrange and recable
all the computers there.
-
One E450 is now the new op140m, and has all the controls software (targets,
dataviewer, dtt, etc). One of the old Blade 100's now has 2 screens in
"cinematic" mode.
-
Finally, dataviewer and dtt now seem to run reliably on the E450. These
essential commissioning tools were all but useless when running on our
Blade 100's; they now seem to work!
-
Lisa is rearranging all the data and accounts in our martian network, cleaning
up a very sloppy and barely functional system.
-
Many thanks to Lisa and Jay for getting our control room back in shape!!
Electronics (B. Abbott, Heefner, Taylor,
Nocera, Mageswaran)
-
From Jay: ASC aux crate testing is ~90% complete.
-
Ben has installed balancing pots on the last three Universal Dewhitening
boards needed for the IFO. These and others that he had done previously,
are now installed on: ITMX, ITMY, BS, PRM, SRM, ETMX, ETMY, and MC2. These
optics are now finished on this issue except the four newly installed ones
(ITMX, ITMY, PRM and SRM) which need to have their digital gains balanced
by Osamu.
-
Jay continues to develop plans to form double demod signals (at the sum
and difference of 33 and 166 MHz) for LSC. He suggests first using the
sums and differences, then move to genuine double demod in a second step.
-
So, we'll form 133 MHz and 199 MHz by phase-locking the signal generators,
then bring those signals over to the LSC crate demod boards.
-
Bob is running RF heliac cables for these new RF signals.
-
Osamu is preparing to install the 166 MHz EOM on the PSL table.
-
The STACIS system still is down, awaiting some attention.
PSL (Miyakawa, Kawamura, Abbott, Nocera):
-
The PSL ISS system is disabled until Flavio investigates the dynamic range
problem.
-
Osamu is working on completing technical notes on the performance of the
PSL post-re-layout.
Digital suspension controllers (Sakata,
Goggin, B. Abbott, Heefner)
-
Shihori continues to work on improving the input matrix for ITMY and the
remaining suspended optics.
Optical sensing (Smith, Kawazoe):
-
Fumiko continues to work on understanding the oplev signals, to establish
the calibrated rms motion of the sensed optics and distinguish it from
oplev sensing noise.
South Annex Bake Ovens (Taylor):
-
A mistake in the bake oven RGA calibration was found, and it is now realized
that some of Bob's bake ovens are dirtier than was thought. Bob is working
with Larry Jones and Steve to diagnose and correct the problem.
-
He is in the process of rebuilding bake oven C, and has found a large deposity
of gunk close to the turbopump manifold. Under investigation.
-
He's also been baking the other ovens to recondition them.
AJW
compiled an equipment budget for the 40m for FY04, with input from Jay,
Steve, and Bob. There has been some re-alignment of the budget in order
to relieve the pressure on the overall LIGO budget.
Thermal Noise Interferometer (Libbrecht)
This week we shipped the Sapphire masses back to REO for
recoating, and we finished re-installing the fused-silica masses.
We are now in the process of aligning the South Arm Cavity (SAC). NAC was
not removed and does not need realignment.
In other news, Dave Crooks has been helping us analyze
our data on thermal noise in silica-tantala coatings on the fused-silica
mirrors. Based on the most recent estimates of coating loss angle from
ringdown measurements, our observed thermal noise falls below the minimum
predicted noise level by about 30%. This difference is greater than the
uncertainties in both the prediction and the measurement. Many thanks to
Gregg Harry for pointing out that the initially-reported coating phi of
10-4, the initial reported result from the ringdown experiments
and the one we used in our initial analysis, was in error. The corrected
value, as reported in Penn, et al., Class. Quantum Grav. 20, 2917 (2003),
is 5.2x10-4.
LASTI (Ottoway)
No report
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
Nothing to report.
LIGO Data Analysis System
Software Systems (Blackburn)
-
Updated the LDAS database tables to support an internal column which captures
the insertion time of all rows. This is handled strickly byDB2 and required
no modifications to the metaDataAPI. This new columnwill allow generation
of time series and histograms of numerical datastored in any table between
any user specified time range.
-
Demonstrated that the a Beowulf cluster can have multiple LDAS systemrunning
in front of it, sharing the nodes in a none interfering way. This opens
up a new way of using LDAS when the search codes tend to be minimally MPI
based and use very few nodes per job, but need the I/O, signal conditioning
and database features of LDAS, but not bigparallel computing. Repeated
the full suite of LDAS system tests early this week. The webpage has been
updated with resent results based on the version of LDAS under development.
-
Demonstrated that LDAS can use ip numbered addresses as well as thepreferred
hostname configuration of ip address without any
-
modifications.
-
Developed new testing scripts to exercise the different complex frame query
options.
-
Continued rework on frame query option clean up. Most of the issues were
resolved by unification of all frame queries for a single jobinto a single
thread. However, a new format which is not correctlyhandled has been revealed
by system testing and requires more work.
-
Implemented thread-safe recursive class that collects metadata onframe
files and subdirectories. The same class will update a globalhash map with
new data in the diskCacheAPI. This is part of the performance migration
of TCL functionality into C++.
-
Contacted the LAM (MPI library) development team concerning a verystrange
bug we have seen. They agree with us that it is a strangebug, but don't
understand it any better than us. We will try totrap around this bug to
better understand it and hopefully get apatch in for it.
-
Tracked down the reasons behind the performance differences betweenthe
VIRGO frcheck utility and the LDAS frverify utility when performingframe
file checksums. The VIRGO utility was roughly twice as fast asthe LDAS
version. The main reasons for this were
a) a buffering issue in C++ that doesn't
exist in C which can easily be coded around
b) the LDAS version was doing a deeper checksum, evaluating both the
individual frame structure and the entire file; the VIRGO version only
evaluated the file checksum
c) the LDAS version read the bytes twice when it is only needed to
read once.
After correcting these three differences (evening the playing field),the
two version are within 10% of each other.
(Peter Shawhan)A web page is being set up to provide information about
database tables, such as the current table definitions and procedures for
modifying themor adding new tables. For now, at least, the URL is:
http://www.ligo.caltech.edu/~pshawhan/dbwg/
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
-
Continued pulling LHO E1-6 data into SAM-QFS from HPSS. We're on
E6 now.
-
Started untarring and renaming E1/E2 data and archiving it to tape in SAM.
LHO-E1 is done.
-
Wrote first version of "prestage", a script that tries to identify patterns
in the staging of data from tape to disk in SAM-QFS and then stages the
next data that the user is likely to need.
-
Got /archive mounted as shared QFS disk on saiph, replacing NFS mount.
-
Called in broken 2Gb FC HBA (no resolution on that yet).
-
Exported L1 RDS tapes at observatories for mailing to the other observatory.
(Hari Pulapaka)
-
Working towards installing NIS on the CIT cluster.
-
Finished the publishing of S2 L3 data here at CIT.
-
Created the file /var/adm/wtmp on ldas-cit, and this stopped the flood
of Globus ftpd messages in /var/adm/messages. Will replicate this across
the sites.
(Al Wilson)
-
Setup dmt0-3 machines. These are ldasbox type of machines that John Z.
will manage for use by DMT.
-
Found a problem with badblocks running on the datacache's as a cron job.
Besides taking forever to complete a scan it seems to end its life as a
zombie.
-
Sun called regarding the memory that the shipped to us for dataserver in
the dev system. It seems that it was shipped in two boxes. And I shipped
it back in only one. This caused much confusion for Sun.
(Stuart Anderson)
-
Reconfigured 2 old LDAS E450 machines from being DB2 servers to being test/development
machines (ldas-suntest4 and ldas-suntest5) with a stand-a-lone installation
of LDAS.
-
Backed up /dso-test directory at Caltech to SAM-QFS.
-
Updated a few packages in the Solaris version of /ldcg: ddd, cvs, and coreutils.
-
Help configure new 4 node Linux DMT cluster at Caltech to have access to
the main data archive and pre-built binary packages from ldas-sw.
MIT(Keith Bayer)
-
ide-raid #6 ordered.
-
Reviewed power requirements for lab.
Hanford(Ben Johnson)
-
Archiving DMT Sepctrum Archiver trends at both sites in tarball format
at both sites. This is done daily at 11:30 local time to archive the previous
day's trends.
-
Raw data tapes for 12/1 -> 12/8 sent to Caltech. S3 RDS data tapes sent
to LLO on 12/10.
-
Top drive in L700 got stuck in "Cartridge In" state on the evening of 12/9.
This was fixed on the morning of 12/10 by following the usual recipe. This
required taking the library offline for 30 minutes. I also took this time
to clean all 4 tape drives.
-
I have been working with Dave Barker and Vern Sandberg to analyze/solve
the data corruption problem at LHO. Most of my effort has been in learning
the Frame Library (the Benoit Mours version) and making custom utilities
to search though our data.
Data Analysis Activities (Lazzarini)
(Greg Mendell)The first version of the StackSlide driver code to run
under Condor and the Grid has been completed. The code currently
has been run on test data only. Our next step is get set up to run
the code on a Condor cluster. The stackslide algorithm (which will
be the same LAL code for the Condor/Grid and LDAS versions) needs to be
refined and debugged, using test data and the injections into the S2/E10/S3
data. This of course, will be an ongoing process over the next few
weeks.(Peter Shawhan)
-
More veto studies for the S2 inspiral analysis
-
Worked on software to get higher access speed when reading from the /archive
filesystem on saiph
-
Hardware signal injections
-
Reviewed pulsar group GWDAW presentations
-
Preparing talks for GWDAW
(Patrick Sutton)
Lazzarini and Sutton travelled to Osaka and had extensive discussions
with Nobuyuki Kanda of TAMA regarding the LIGO-TAMA joint burst search
for S2. Sutton is currently in Tokyo meeting with Masaki Ando, the
TAMA leader for burst investigations. They are planning the simulations
and coincidence procedures necessary for combining LIGO and TAMA data.(Igor
Yakushin)
-
Working on line removal algorithm in waveburst.
-
Produced and tested sine-gaussian burst MDC frames.
(Alan Weinstein)
General Computing (Wallace)
MIT:(Keith)
-
Worked on repairing old Ultra10 hardware
-
Spec'd out new thinkpad for scientist
-
Looked into lab pc problems
-
Trying to get users to clear junk off the file-system
-
Ordered replacement computer parts
-
Requested more IP addresses for lab
Livingston:(Shannon)
-
The latest news on the Gigabit connection to the observatory is that Bell
South will be ready by Dec 18th. LSU will be ready by Dec 22nd. This
means that the Gigabit will not happen till I return from vacation on Jan
7th. At some point after that we should be ready to go live.
LSU is going to provide us with the new router and also the interface cards
for our firewall.
-
Did a fresh windows install on a machine to put in the shipping and receiving
area. The usual windows/office/norton/etc. Beware of
Service Pack 4. After a fresh install of Windows, SP4 crashed the
OS. Had to start over again.
-
Have unplugged a machine on the network which I believe is infected with
a virus. Have not had a chance to check and see which one yet, but
I was getting alerts from one of the IDSs.
-
Coordinated with Rich to send our old E3000 to sun to receive a trade in
credit towards a 280R purchase. The "machine formerly known as Sirius"
is no longer with us. It was basically unused for the last year anyway.
The machine is terribly slow now and I am surprised Sun was willing to
give us any kind of trade in value.
-
Trying to work with the software.caltech.edu folks and improve the reliability
of the software downloads. They seem to not be very interested in
the fact that it is nearly impossible for us to download site licensed
software at the observatory.
-
Patched several linux boxes with the kernel/rsync/etc. security patches.
-
Once again I had to track down some invoices from Dell. This is always
a headache.
-
Mounted the LDAS shares on touro at Igor's request. People are complaining
that decatur is too slow. However, touro is not necessarily supposed
to be used for analysis work in this manner. This is something that
should be looked at in the future. Decatur desperately needs to be
upgraded to Solaris 9 after the run, but more importantly, the hardware
is showing its age. Ideally decatur needs to be upgraded to an SF880,
but that is around $40k if I remember correctly. I do not like the
idea of hard mounting the LDAS nfs shares to multiple GC machines and some
sort of better solution needs to be found.
(Yakushin)
-
Disabled "Fast Load" option for the tape robot.
Hanford:(Christine)
-
Working evening operator shifts this week, so less time spent on system
administration.
-
Upgraded the standard software on a couple of shared PCs.
-
Purchased some software and more AP-2000 wireless access points.
-
Set up a break out room for the PAC meeting and added 35 more IP addresses
to my DHCP server.
-
Typical user support.
CIT:(Mike)
-
Loaded a PC for DCC. I had to do a major hardware upgrade to this computer,
that I used to swap out with. This included swapping over the most of the
hardware from their old computer to the new PC which is a much faster computer.
This required me loading additional software besides General Computing
Software.
-
Network switch went down up on the third floor of West Bridge. I ended
up having to pull that switch out and swap over users ethernet connections
to additional switches/hubs until I had enough active ports to get everyone
backup and running.
-
Upgraded all our Solid Works users from 2001+ to 2003 with pdmworks client
installed.
-
I finished up loading all DCC computers with updated software. All these
computers are now running 2000 pro and have office xp loaded with all service
packs installed.
-
Loaded a dual bootable laptop for the loaner pool.
-
Loaded a laptop for Mike Smith, with GC software & autocad to take
on travel.
-
Burned all NTSRV end of month ghost backups to DVD.
-
Worked on all NTSRV's upgrading firewall software and windows updates.
-
This week I had a lot of user support that included printing, networking
and software issues.
(Veronica)
-
LIGO website: Finished and, after
some troubleshooting, installed the Aspen 2004 website. Posting updates
for the Aspen as they arrive. Updated several other webpages throughout
the LIGO website. Updated the roster. Updated the page for the upcoming
LIGO seminars. Addressed a DCC-related issue.
-
LSC website: Posting MOUs as they
are being supplied by the DCC. Looking into a database of the progress
reports and the scripts for their submission. It needs some further troubeshooting.
Updating other LSC-related webpages.
(Lisa)
-
Worked on spam, sp@m and more S.P.A.M
-
Did some small cleanup work in the 40m.
-
Did a couple of file restores.
-
Did root backups on the servers.
-
Updated the mathematica license on sirius.
(Bruce)
-
(BS) Systems Work:
(5.0 days)
-
Ilog upgrade to implement new search features.
(Larry)
-
Worked a number of issues with the DCC group. Everything from assisting
in testing the s/w changes to cleaning out and moving documents.
-
Worked out a couple of procurement issues. We have a number of laptops
to purchase as replacements in the loaner pool and upgrades for users with
existing laptops. Each new procurement and upgrade is being looked at on
a case by case basis in order to keep costs in-line.
-
Spent time working on equipment and space issues. This is an ever going
process but this last week and it looks like over the next few weeks we
will be spending more time on these issues.
-
Worked on a couple of E2E projects. One of the new servers has a bad disk
drive and the mouse connection on the video switch has gone bad. Both will
be getting replaced in the near future. Presently, installing a new version
of the OS on one of the servers and will be upgrading a couple of the workstations.
-
Installed another video card in a SUN box in the remote control room. We
will be setting the second machine up again. The room has been getting
quite a bit of use as of late.
-
Worked on a couple of network problems. Setup a new edge switch to replace
the bad one on the third floor. So far the new switch has passed all of
the testing and should be installed soon.
-
Assisted a number of users with various PC problems. One problem is that
when people are patching their Windows OS they notice the driver listed
on the same page and are installing them also. So far we have not had anything
but problems with the updated drivers and have had to replace them. So
please, avoid changing your working drivers if possible.
-
Worked with Mike on cleaning up a couple of areas.
-
\Modified a number of user accounts, DNS table changes, e-mail filtering,
file restorations ... and the rest of the normal daily activities.
Advanced
LIGO and Supporting R&D (Shoemaker)
Seismic Isolation
From: Larry Jones <ljones@ligo.caltech.edu>
Advanced LIGO Seismic Structure (Larry Jones
)
Actuator Testing and Redesign:
I met with BEI/Kimco representatives on
12/4 and showed them the reworked small actuator and told them of the thermal
vacuum testing of the large actuator. We discussed each of the changes
desired by LIGO to meet UHV requirements. They offered to supply anodized
coupons and neodimium-iron magnets for
RGA and contamination testing. They are working on a quote to provide design
and prototyping of one unit each, which they feel will take 12 weeks. With
LIGO testing required after that and 8-10 weeks estimated for producing
units for the LIGO prototypes, we will be hard pressed to have units ready
for the start of ASI's assembly phase. ASI's
design review is currently scheduled for 3/16/04,
and the BSC assembly fit check is scheduled to be complete on 6/9/04.
Position Sensor Probe Testing:
Cabling, connectors, epoxy and solder were received from ADE Technologies
and the cabling has been cleaned to prepare it for a vacuum bake/RGA scan,
which is scheduled for next week at the 40M lab. After that is complete,
the cabling will be tested in the optical contamination cavity.
Suspension
From:
JaneenRomie
<romie_j@ligo.caltech.edu>
Continuing
to work with CalumTorrie
on getting more data points for the MC modal testing. This work
will provide confidence in future fea
work. Mike in the machine shop machined a set of stiffening plates that
we bolted to the structure but there were not enough attachment points
to provide enough stiffening. I'm sending new prints to Mike this week.
He'll make up new plates and rework the structure. This stiffening approach
may be used for the RM also.
Worked on some Solidworks/PDMWorks
issues.Ongoing.
Working on schedule and labor estimates for the
next few months.Reviewed Thomas's updated cost
and labor data.
From: ctorrie <ctorrie@ligo.caltech.edu>
1) Eddy Current Dampers
Mark Barton and I are working with Mike Plissi,
Caroline and Norna on a paper summarizing
the recent work on eddy current dampers at both Glasgow and Caltech. We
have a setup that includes a 2x2 array at Caltech on a single pendulum.
2) Galling and Dust
Larry Jones and I have been working with Mike Gerfin
to come up with a plan for testing galling and the production of dust particles
for fasteners and tapped holes. Work should start on this in the new
year. See report from Larry Jones for more detail.
3) PDMWorks and SolidWorks
Caltech now has PDMWorks 2004 and a
sever that acts as our vault. Tests are
ongoing and are about to be expanded to include hopefully MIT and the UK.
The suspension team has now updated to SolidWorks
2003 service Pack 4.0. We also have a copy of SolidWorks
2004 on the visitor machine to allow communication with the Seismic team.
4) RM Suspension
MPL and I are continuing to tie up various aspects of the RM suspension
including a +/- 500 g mass adjuster for
the intermediate stage and a pitch adjuster that better meets the requirements
from Betsy Blade.
5) Structure analysis
JaneenRomie,
Russell and I are gathering together al of the data we have collected both
experimentally and through FEA. This is divided into 2 sections. Section
1 includes several data points such that we are able to compare FEA directly
to experiment. This has proved fairly successful so far. Section 2 includes
various conceits for stiffening the structure and highlights the importance
of the non-suspended components in the analysis. Ideas are being gathered
from various people and these include increasing the footprint for the
RM as well as several stiffening concepts. All of which we hope to test
on the existing MC structure.
6) MATLAB
Norna Robertson and I have been looking
at the prospect of increasing the separation of the ribbons in the ETM.
This is ongoing but looks promising.
Other updates to the existing quad model are ongoing and it is hoped
a version of the MC< RM and ETM can be sent to the DCC before Christmas.
7) VISIT
I plan to visit the IGR at Glasgow
for 1/2 a day during my vacation in Scotland,
probably the morning of the 23rd. I have a small experiment to carry out
and a meeting with Jim, Harry and Caroline.
8) Mode Cleaner Suspension
Both Mode Cleaner suspensions have been prepared and stored again in
the containers as they were for the Caltech Workshop in October. New parts
for the local control osems, all made
from 6061-T6-Al, are due from Glasgow
in the new year. At present Russell Jones
is ordering 80 to cover the 1 RM, 2 ETM and 2 MC. Perhaps this needs to
be reviewed?
CalumTorrie
(with input from Norna
Robertson)
Core Optics
From:
Helena Armandula <ahelena@ligo.caltech.edu>
Advanced LIGO Coatings -
CSIRO
Received a 3"dia. fused silica substrate
with a 30 layer (Ta2O5/SiO2) coating.
This was a trial run to allow them to tune their coating parameters
and measurement techniques.
By their calculations, a (HL)^15 coating design should have a transmittance
of 75ppm, we measured ~162 ppm on the delivered parts; this means that
they need to revise their calculations to incorporate the refractive indexes
they are actually getting on the materials.
Coating thickness uniformity was not very good, CSIRO knew there was
a problem with the uniformity on the SiO2 layers, they calculated it to
be ~1% on a single layer, we see ~10% on
the 3" dia. sample. It is assumed that,
as the layer count increases, so does the thickness non-uniformity.
CSIRO also coated four 1"dia. fused silica substrates that were sent
toRoger Route for absorption
measurements. Roger received the parts and he expects Vlad
to measure them after some problems with their laser are solved.
MLD
The coating on the 3" dia. sapphire
substrates blistered after annealing them at 350 degrees C.
On a previous occasion MLD had tried to anneal 1" dia.
witness pieces at 450 and then 400 deg. C and
they had all blistered.
For the 350 deg anneal test they had none of the 1" pieces that we
supplied, so they used sapphire witnesses that MLD supplied and coated
with our parts.
The test anneal at 350 degrees was successful, so, our 3" diameter
pieces were loaded and annealed using the same protocol that had been tested.
For some reason that they do not understand, both 3"dia. pieces blistered
in the 350 deg C anneal process. They suggest that it may be that our substrates
were polished using a different process than the 1" sapphire witnesses
that MLD had provided and the difference in the surfaces was the reason
that the coating adherence to our parts failed.
I suspect that contamination on the surface may be the cause; those
parts were originally coated more than 7 mo. ago. I suggested to
clean the parts before annealing, however, I do not know if the
suggestion was followed.
After they make some interferograms,
they expect to ship the parts next week.
Auxiliary Optics
From:
Michael Smith
<smith@ligo.caltech.edu>
PHOTON DRIVE
R&D
Awaiting replacement
of the 500 mW
laser.
For additional information about this report, contact sanders@ligo.caltech.edu