|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday November 3, 2003 will be:
(Meeting time: 10:30 am Pacific Time)
Special Items:
CHECK THE LLO COMMISSIONING DISCUSSION FOR A MUCH EARNED BREAKTHROUGH.
AND THE TNI
MAY BE SHOWING US A CLEAR THERMAL NOISE SIGNAL. SEE THE TNI REPORT BELOW
no report
LIGO Weekly Site Telecon (Lindquist)
A site teleconference was held on Thursday, October 30, 2003. The following were among the issues discussed:
Hanford LSC Meeting - The Weber Bar is mounted. Plaques still to be hung.
S3 - We discussed readiness at the sites for the S3 run. An electrical problem has been discovered and repaired. Livingston is still scrambling, but back on the road to S2 sensitivity.
Convenience Checks - Ed Jasnow and the P-Card folks will be at Livingston the first week in December to set up Convenience Checking.
Budgets - FY 2003 costs are coming in at a higher rate than last year. We cannot tell whether this means that the same costs are coming in faster, or the total will be higher. Therefore, our estimate of $6 million for the carry-forward may be too optimistic. A budget surplus does not appear to exist. David and Dennis have an action to review R&D scope.
Statements of Work have been prepared and are to be mailed to potential bidders for time and material contracts. Given the evidence that it is going to be difficult to fit inside the budget constraints, all time and material contracts must include a ceiling price and a commitment to manage with careful control of scope changes.
Property - Ed Chargois and Livingston sold all of the excess
property.
The list of current actions revised to reflect
the status of open actions assigned through October 30, 2003 may be found
at ACTION
LIST.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
ACCOMPLISHMENTS
(This report
reflects activity for the past month.)
ACTIVITY
| 10/30/03 | Packages | Faxes |
| In | 18 | 33 |
| Out | 13 | 34 |
Press here to access
the DOCUMENT CONTROL CENTER
WEB PAGE.
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA .
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
SUPPORT (Baldon, Lloyd, Tischler)
>Irene Baldon
ADVANCED LIGO (Cost Schedule
Control Systems) T. Frey
From: Thomas Frey <tfrey@ligo.caltech.edu>
For list of documents that
are being used to develop Adv. LIGO Cost and Schedule, see http://www.ligo.caltech.edu/~tfrey/Cost_MTG_082002/
Continued development of a proposal for implementing Primavera Project Planner Enterprise.
Static HTML Example - http://ligo.caltech.edu/~tfrey/DAQ_WebProj/(AdL DAQ Only) NOTE: This is after making adjustments to the WBS so that it displays as expected.
SUS - No action items pending. Worked with Janeen and Calum preparing revised progress data / ETCs.
SEI - No action items pending. Working with Larry to update SEI with progress through 09.26.02.
ISC - Still need completed WBS dictionary and BOE.
LDAS - No action required at this point in time.
INSTALL - No action items pending.
DAQ - No action required at this point in time.
PM - No action required at this point in time.
FAC - No action required at this point in time.
SUP - No action required at this point in time.
A draft Final Report for Cooperative Agreement NSF PHY-9210038, the
cooperative agreement that covered construction, installation and commissioning,
and initial operations of the sites, has been distributed for internal
review.
The following change requests are open.
| CR-030015 | FY 2003 Livingston Observatory Detector Maintenance Expenses (Increment) | R. Wooley | July 14, 2003 |
| CR-030016 | Hanford Facilities 2.2--Divide the Large Equipment Access to Facilitate Movement of Large Items (currently assigned to FY 2004 liens list) | J. Worden | July 31, 2003 |
| CR-030017 | Livingston Computing (WBS 3.5) WAN Upgrade | A. Lazzarini | October 17, 2003 |
CR-030017 proposes to upgrade the LIGO Laboratory Wide Area Network
(WAN) at Livingston from 2xT1 (3.088 Mbps) to Gigbit Ethernet (1000
Mbps) at a cost of approximately $217K through 2006. This change
request was discussed and approved during the Executive Committee Meeting
on Monday, October 27, 2003. Minutes have been prepared for distribution
(LIGO-M030197-00-P).
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
no report
---------------------------------------------------------------------
Interferometer commissioning and S3 preparation
--------------------------------------------------------------------
After an exhausting and nerve wracking three
weeks we finally isolated
the source of the excess interferometer noise
during the wee hours of
Wednesday morning. A connector accepting our
main RF feed coaxial cable
had apparently suffered a freak accident some
time back.
This somehow left it just making sufficient
contact to keep the interferometer working
"normally" on the
face of it, but caused nonlinear generation
of excess noise in the sensing chain.
Because of the nonlinearity, this noise only
manifested itself when the
full interferometer was running, rendering
it invisible to normal
troubleshooting protocols. The bizarre confluence
of improbable
events needed to produce this fault and then
to have it
evade us for so long in this way truly boggles
the imagination.
See http://www.ligo-la.caltech.edu/ilog/pub/ilog.cgi?group=detector&date_to_view=10/28/2003&anchor_to_scroll_to=2003:10:28:04:24:08-rana
for details.
After fixing the RF feed (a fairly trivial
operation) the L1 sensitivity
improved markedly for the first time since
16 October. It
is not yet quite up to the (spectacular) H1
or
H2 standard, but it's in the ballpark and
getting better.
Among the other big successes of the hours-old
"post-fubar era", the WFS system
is now operating with most degrees of freedom
under control (WFS1, 3, and 4 plus
the ETM quadrant sensors) and markedly improves
the stability of
the interferometer alignment. Tonight it is
hoped WFS2a will also
get a check. Nighttime locking and duty cycle
look good. A horrendous
60 Hz line interference problem was traced
to an overstressed
power supply and fixed.
In addition to continued debugging and tuning
to exploit the
new noise floor and added interferometer features,
we are finallly
getting into our daunting pre-run punchlist,
only hours before S3 (a
process originally planned for the whole month
of October). We hope
to have enough of it done by the official
starting gun that finishing
up during the run will not be too disruptive.
CONGRATULATIONS TO ALL FOR A TENACIOUS EFFORT!
ALL'S WELL THAT END'S WELL! - GHS
Safety/security (Riesen)
---------------------------------------------------------------------
Completed weekly IR scan on the PSL and the 4 IOT/ISC tables, Found
no
errant beams.
All IOT/ISC table enclosures are properly locked and the auto laser
warning light system is fully operational.
Found no safety concerns on the weekly site tour.
All non controlled doors on site are closed and locked.
The site entrance side gate will be closed 24/7 starting tomorrow at
noon (during S3) and will be opened only upon request and authorization
from the control room.
Working daily with Ed Chargois on GSA equipment that has been bought
and
will be removed from the off site warehouse hopefully by the end of
next
week.
Continuing work on LLO SOPs.
L1 PSL (King)
---------------------------------------------------------------------
The power amplifier diode temperature was abnormally high at about
30.0
degrees C, this was reduced to 28.3 degrees by dropping the setpoint
of the
chiller from 20 to 18 degrees C. After running for a period of
time the
temperature suddenly increased back to 30 degrees. Examining
the water
revealed bits of what looked like copper sulphate. The cooling
hoses and
chiller was subsequently flushed and the amplifier cooling tubes cleaned.
The chiller setpoint was then restored back to 20 degrees and the laser
temperature seems to have stabilized out to within 0.2 degrees over
a day.
The power monitor, L1:PSL-126MOPA_AMPMON, was re-calibrated against
a power
meter. By the end of the same morning the calibration had drifted
even
though the laser power had not. Although the output of the photodiode
within the laser did not change (approximately -280 mV), the signal
as
measured in the wiring harness did (from approximately 220 mV to 60
mV).
I suspect the problem lies with the 8-bit ADC within the laser power
supply but am not certain.
General Computing (Roddy)
---------------------------------------------------------------------
After spending several days working the bugs out of the new file server
provided by ASA, I have begun setting up the directory structure and
shares on it. I have decided to go with ReiserFS on the file
systems
since it gives more useable space as compared to ext3. Also,
in some
benchmarks it performed better than ext3. I have not benchmarked
NFS
speeds yet. Now that I have all of the bugs worked out, I will
continue
to test it for a couple of days before I put it in service.
Still had some email server troubles until Sunday. I checked the
mail
server over the weekend before leaving home at 10:30 am and when I
returned at 2:30 it had stopped accepting messages. I have been
able to
clear up most of the error messages that I believe were contributing
to
the problems. Also, it appears that a change in the firewal
configuration helped. It is still not exaclty clear what is causing
the
mail server to start rejecting messages even though several people
have
looked into it. However, it has not happened again since Sunday
after
the additional firewall change.
Received a quote from Sun for another 280R to replace our exisiting
web
server. This includes trading in the tired E3000 that was a
hand-me-down from CIT. It saves an additional 12% off the list
price of
the 280R due to the trade in.
Received a quote from Sun for a calendar server and an email server.
Will look into this when I am done with LDAP.
Set up a couple of workstations in the new building.
Installed an atomic clock client on the laser safety computer to stop
the time from bcoming skewed and locking doors at inappropriate times.
Setting up a mirror of both the SunFreeware site and gnu.org.
I will be
rebuilding the GC apps when the file server is complete, so I will
need
many of these items in the process.
LLO Seismic retrofit (Kern)
---------------------------------------------------------------------
Submitted the last of the DCNs for manufacture of fabricated components
(23 parts drawings) this week. Proper generation of a final bill of
materials is still in the works but we've completed 'by the book'
documentation of all build to print components. Updated the retrofit
schedule based upon latest communications with the shops. Things are
still nip-n-tuck, but I'm increasingly confident that all of the parts
will be on hand for a January start date. HEPI is making just-in-time
deliveries a fine art. Reworking a Request for Quotation for the piping
contract. A small misunderstanding about schedule occurred with the
machine shop machining the parts for the actuators, a few e-mails and
phone calls resolved the issue. Received a replacement power
supply
(#3) for our new PDMWorks server. Successfully installed the new power
supply and got PDMWorks server up and running on the new machine.
I
copied the vault from the old machine to the server, renamed it and
installed PDMWorks server. I substituted our vault for the default
installed one and the jobs, and users all appear normal. Received the
brazed valves for the bypass tree from Swagelok and they are up to
Swagelok standards, beautifully done. I will send one to Dennis
and Ken
for approval.
CDS software (Khan)
---------------------------------------------------------------------
Developing the PSL-ISS Autotracker software, it would track the low
frequency fluctuations on the ISS photodiode through a PID controller,
using
an error signal from the LF Actdrive and the set point from the INPDMon
of
the ISS system
LDAS (Yakushin)
---------------------------------------------------------------------
1) Configured and ran burntest on the new dataserver;
2) Migrating old databases from Solaris to RH9 Linux. Currently all
but
one LLO databases are migrated to the new metaserver. LLO_2 would
require some extra manual work because of blobs. Working on LHO, MIT,
CIT systems now.
3) Sent E10 raw data to CIT.
LDAS data analysis
1) Studying waveburst sensitivity using software injections of
sine-gaussians.
have taken transfer function for the HEPI/HAM system and have closed 5 of the 8 loops
Jonathan Kern
Ken Mailand
I’m finishing up the detail design of the LLO pump station manifold, and ordering parts for assembly.
Rolf Bork
- HEPI
- Continuing to order parts
- Alex has started on LLO Hepi software.
- Hongyu has begun to look at end station ADCU code changes necessary to connect end station Hepi controls to DAQ system.
- Working at LLO to prepare for S3 run
- New ASC software loaded (just a fix
of Pitch/Yaw DAQ channels to floats instead of shorts, same as LHO)
- Checking final DAQ configuration
I am still working on the high voltage amplifier for
the PZT mirror
mount used for driving the beam position in the intensity
stabilization
experiment.
Since returning from LHO last week, I've been
mainly working on interpretation of the various
observations on LHO optic imperfections, scattering
and associated loss. See, eg, the video clips of the
2k ifo optic beam spots, now streaming on our web
site
(thanks to Garilynn and Veronika). We are concocting
experiments we can do in the lab to corroborate these
in
situ studies (with Liyuan). Interest in this has also
slopped over
to the 40m where they are coincidentally just getting
arm
locks, and concomitant high intensities on TMs. I'm
condensing
the results for a talk at the LSC.
Helena Armandula, GariLynn Billingsley
In an effort to correlate what is seen in some of
the of mirror's pictures that B. Kells took at LHO, Gari and I, run some
tests by looking at different mirror surfaces under the dark field microscope
(without much success)
1.
2.
3.
4.
5.
6.
7.
8.
9.
Next, during my trip to Livingston for the NSF review,
I will try to get some pictures of the mirrors at LLO, similar to the ones
that B. Kells took at LHO.
I am coordinating with M.Zucker to get assistance from a colleague at Livingston to accomplish this.
Links to video of scatter on H2 mirrors.
http://www.ligo.caltech.edu/~coreopt/Scatter/
CO2 Telescope projector: Have modeled a parabolic mirror astronomical telescope with ZnSe objective and eyepiece design in ASAP; have evaluated the model with a grid of rays, which verify the mapping of an annular input mask onto the 4K ITM mirror. An on-axis red pointing beam is incorporated into the projected annular pattern. A preliminary optical layout of the projector has been drawn in ACAD. An annular illuminator is being designed for illuminating the annular mask. The annular illuminator may replace the mask.
I will review with Bob Taylor the complete list of cleaned baffles, mounts, and hardware, sort, and prepare for shipping to LLO and LHO.
Veeco expects to have completed repair of the WYKO 6000 interferometer by 5 November. We will then need some time to re-qualify the instrument.
OTF Lab. (W. Bridge)
Contamination Cavity # 1
This cavity is locked finally but we couldn't recover
its full output power as before.
Absorption Test Measurement prototype in standby
The new 30
watts laser from Quantronix. is ON !
We have been checking its power at various current
and beam waist measurement set up
is underway.
The new bench
for thisnew laser is still under
fabrication.
Scatterometer systeminSTANDBY
The new base to house the larger Sapphire mirror has
been completed finally and
It will be installed this week as modifications to
it has been done.
The new optical plate that holds the RTS head is still
under fabrication.
OTF Lab at Lauritsen ROOM 38
Cavity #3
This chamber is pumping now and we are taking ring
down and beat
frequency measurements every day as well as new RGA
measurements .
Cavity #2 Test cavity in STANDBY.
This week the TNI lived up to its name and
gave us our first look at
thermal noise. The plot above shows
the measured total displacement
noise (differential between the two cavities)
along with a sum of the
expected coating thermal noise plus a constant
electronic noise. As it
turns out, the TNI schedule was forecasting
that we would achieve this
milestone this very week!
VERY IMPRESSIVE AND ENCOURAGING. CHECKING THIS
RESULT IS NEXT. CONGRATULATIONS TO THE TNI TEAM! - GHS
We spent some time examining the calibration of the instrument and
determined that the electronic noise that currently limits us is at
4.7e-19 m/rHz, with some structure above 20 kHz. Shot noise is
well
below this level.
We also took a careful look at the thermal noise theory, accounting
for
all the various factors of root-2 that appear in a differential
measurement. Our new noise curve is fairly clean between 500
Hz and 20
kHz and is well accounted for by a combination of coating thermal noise
and the measured electronic noise. Bulk thermal noise is lower.
To
draw the coating thermal noise curve on our data, we used the measured
value of phi_{parallel} = 1e-4 (obtained from ringdown measurements)
for
both phi_{parallel} and phi_{perpendicular}.
HEPI Design and Installation (McInnes, Mason)
The first in vacuum geophone has been completed. Myron assembled the
L4C
geophone into a vacuum nipple inside of an argon filled glove box.
The
unit successfully passed an RGA scan.
Southbridge Sheet Metal and Arland Tool are on schedule to deliver the
housings and boots by 1/5/03. Lavallee Machine who is fabricating
smaller componants has not recieved final drawings.
HEPI Ham Control (Ottaway, Mittleman)
The x,y,z,ry,rz loops have been simultaneously locked with a noticeable
reduction of the error point signals. At present we are do not have
the
top of the table instrumented as we are waiting fof the vacuum compatible
geophones (see above).
LASTI Design (Ottaway)
Have nearly completed a complete comparison of the two cavity vs single
cavity LASTI design. This should be available on Monday so that we
can get
feedback at LSC meeting.
Simulation and Modeling (Bhawal)
Weekly Physics meeting
-------------------------
Matt was at LLOand called in to describe work on WFS there. The current
WFS loop configuration
at LLO is same as what he developed in SimLIGO and is different from
the H1
implementation. Virginio showed mechanical simulation of "blade" and
its
transfer functions. Hiro, Matt, Biplab discussed modifications in FFT
and E2E code that may be necessary especially for Advanced LIGO studies.
FFT program
-------------
(Hiro) The original FFT program developed by B.Bochner (then) at MIT
has been
improved in several ways:
(1) Mirrors can have different refractive indices to mimic different
thermal lensing status (say, ITMx and
ITMy are different)
(2) pox, poy and pob are calculated and stored in output files
as well
as in the summary file.
(3) The code can be compiled using g77 and produces correct
results on
linux.
(4) Code was optimized, and it runs 5 times faster on linux
box (3GHx
Xeon) compared with SUN box (800M SPARC).
( SUN's fortran compiler, f77, is smarter
than g77).
(5) Output codes have been modified so that summary report can
be
modified easily to include more modes
or fields.
(6) The FFT source code is now maintained in LDAS CVS, FFTSim.
Future plan is to adopt fftw, and to port to c++. This is a step
toward
implementing fft-ish field calculation in e2e.
(Biplab)
- Wrote Matlab code that can take FFT outputs of beam profiles
and
calculate LSC and ASC signals at near and far fields.
- Testing the newly modified FFT code and the matlab code with
e2e results.
Linear Noise Model
--------------------------------
(Matt) Continued work on linear noise model. Worked on LLO ASC
system.
Wrote/updated scripting
tools (ezlockin, ezgain).
Code development and maintenance
------------------------------------
(Melody)
- Dynamically compiled and
linked FUNC capabilities: Working
on creating only one source
code for each equation and passing in
the macro definition (database)
into the object.
Alfi
--------
(Bruce)
- Fixed more window resize
issues.
- Remerged bundler code
back into Alfi.
- New bundler code testing.
LIGO Data Analysis System
Software Systems (Blackburn)
The new software release of LDAS for the science run was fully tested
and pushed onto the central LDAS software server on Tuesday of this
week. It fixed all known issues with the diskCacheAPI from the prior
release of LDAS and had a last minute fix for an issue discovered at
LHO which could not be simulated here at Caltech. A couple of other
APIs had minor fixed as well. This 0.9.0 release looks pretty good.
This software has been moved to the sites and awaits hardware changes
before being started there. We expect to having it running everywhere
today (Thurday). This release also demonstrated the ability to create
the S3 Reduced Data Set (RDS Frames) at faster that 2X realtime.
There was an issue discovered with the FrDump6 utility shipped with
LDAS on Tuesday this week. It was core dumping on current frames. A
last minute fix prevents the coredumping so it made it into the release,
but there are a few other issues associated with it that will be worked
on this week. If necessary we will provide a patched version of this
utility next week. It is not used in a running LDAS system so it
will not impact the science run.
We are currently busy migrating the DB2 databases and servers over to
Linux platforms on all the non-Caltech LDAS systems. This has been
a
difficult challenge, but the procedures for accomplishing this were
developed and tested only mid week. This is expected to complete in
time for the start of the science run tomorrow morning. We are also
working closely with the DMT developers to assure that the DMT is in
lock-step with the migration over to the new databases specifically
for this science run.
We have discovered a new issue with the threaded metaDataAPI pushing
data into the DB2 database faster than its services can handle. A few
days of testing DB2 configuration parameters has identified a set of
parameter values that resolve this in our test example. However, the
challenges of the science run may require us to re-tune the database.
The upshot of this is that the metaDataAPI is nolonger the primary
bottleneck in insertion under heavy load now that we have the new
threading implemented!
A new release of LAL and LALwrapper are expected to come out today -
just in time for the science run. We will probably have to shorten
our nominal 24 hour test requirement prior to pushing a LAL/LALwrapper
release to the sites in order to make the start of the science run.
It unfortunately cannot be avoided given the late hour of the release.
(Not available as of the time of this writing).
We have made a startling discovery while using the new STLPort Standard
Template Library. Using it instead of the standard template library
provided by GCC, we see about 20X improvement in the performance of
the FrameAPI under Linux and a 3-5X improvement under Solaris. We have
just today begun testing this Library under a heavily threaded LDAS
enviroment so these improvements are preliminary, but if this holds
up we could be looking at nearly an order of magnitude improvement
in the performance of LDAS in the next release!
Guild, and the LIGOtools 'dataflow' package, had to be modified slightly
to handle changes in the frame cache and LIGO_LW formatting in the
new
release of LDAS.
Hardware Systems (Anderson)
Caltech
-------
(Dan Kozak)
* Exported tapes with E10 full frames at observatories for shipping
to CIT,
and with RDS to other observatory. LLO full frames received
and staged
at CIT with no problems.
* Fixed badly broken HPSS.
* Continued HPSS migration to SAM-QFS.
* Exported tapes with S2 L1/3 RDS at CIT and shipped to observatories.
* Worked on getting SAM-FS licenses for new dataserver boxes at CIT/LHO/LLO,
with partial success (got temp licenses, still working on getting
permanent licenses.
* Got new dataservers configured and operational at CIT/LHO/LLO.
(Hari Pulapaka)
* Worked only getting data transferred for E10 using LDR.
* Published data at LLO and LHO into LDR. All the data generated at
the
sites was published into the LDR on friday night.
* Pulled data into ldas-cit-g using LDR. The last of the L3 rds data
generated at the sites arrived at ldas-cit on Monday after a
weekend
without any of transfer owing to the shutdown of the machines
at LHO.
* Wrote a new storage module for LDR to be used at ldas-cit with
improvements in the way the files are stored.
* Had to re-configure LDR at LLO as the gateway box had changed. Spent
quite some time debugging the problems that aroused because
of it.
Including adding the changes to firewall policy, modifying inetd.conf
and /etc/services.
(Al Wilson)
* Installing new motherboards in the ldas datacache systems.
(Stuart Anderson)
* Worked on getting LDAS-0.9.0 installed and running on all of the Lab
LDAS
systems for S3 analysis. It is now operational at all locations
and ready
for S3.
* Finished Solaris installation and configuration on new V880 SAM-QFS
server at Caltech--now in production use.
* Helped configure and install the new Solaris LDAS gateway machine
at MIT.
* Switched all the production Lab LDAS systems over to use Linux database.
* Applied OpenSSH security patches on Solaris LDAS computers at CIT.
MIT
---
(Keith Bayer)
* Received both motherboards for pc raid units.
* Ran sendmail updates on E450 (prior to swap).
* Patches all solaris machines with OpenSSH patch.
* Setup 22 more cluster nodes for use with the MIT LDAS cluster.
* Put 280R and metaserver on-line.
* Swapping motherboards on pcraid3.
* Tweaked script to run commands on cluster nodes.
Livingston
----------
(Igor Yakushin)
* Configured and ran burntest on the new dataserver;
* Migrating old databases from Solaris to RH9 Linux. Currently all
but
one LLO databases are migrated to the new metaserver. LLO_2
would
require some extra manual work because of blobs. Working on
LHO, MIT,
CIT systems now.
* Sent E10 raw data to CIT.
Hanford
-------
(Greg Mendell)
* Sent tapes with E10 full frame data to CIT. Sent tapes with
E10 L1
rds data to LLO. This data is on disk and tape at LHO
under
/samraw/LHO/full/E10 and /samrds/LHO/rds/E10/L1. (Leve 2 and
3 rds
frames are under /samrds/LHO/rds/E10/L2 and /samrds/LHO/rds/E10/L3.)
* Assisted ldas in debugging the diskcacheAPI.
* Set up final configuration of LDAS servers for S3.
* LDAS is now ready for S3 at LHO.
Data Analysis Activities (Lazzarini)
Creighton:
* Tracked down a glitch in signal simulation routines that was causing
low-level harmonic structure in pulsar injections: the
(double-precision) signal phase model was only being interpolated
at
single-precision to find the phase at any time sample.
Lazzarini:
Worked with Kaice during and after the MIT stochastic face to face
meeting to
generate first-pass preliminary S2 results for the 3 interferometer
pairs.
These have been posted to the stochastic e-log notebook.
No surprises.
Mendell:
The week has mostly been spent getting LDAS ready for S3 at LHO. I
have
also started generating SFTs for E10 and investigating the injected
pulsar signals; the hope is to do some sort of online investigation
of
the injected signals during S3, but scripts need to be written. Also,
Mike Landry and I plan to spend much more time on stack slide between
now and the LSC meeting, now that S3 preparations are finished.
Reilly:
Thursday and Friday were the days of the Stochastic F2F.
At the f2f we computed the "final" answer for the first 10000
values of the ccstatistic. Later after over coming copious database
issues with the help of Peter Shawhan, I was finally able to extract
all
data points and eventually get them almost time ordered. Albert used
excel for the final time ordering based on segment number. I have been
working on further implementation and testing of the new DSO. At the
f2f we
discussed a plan for testing both the dso and the data analysis pipeline.
I also spent a lot of time configuring my laptop so that I will be
able to
use it for analysis while I am in Taiwan. Also I was able to run some
matlab scripts Tania prepared which created the E10 coherence plots
for H1H2.
Shawhan:
* More signal injection studies. Took a close look at the output
from
the pulsar simulation code, and discovered significant structure in
the
amplitude spectral density at frequencies other than the pulsar frequency.
This may point to a numerical precision problem in the simulation.
* Working on finalizing the veto conditions for the S2 inspiral analysis.
* Helped Kaice extract stochastic analysis results from the LDAS database.
Yakushin:
1) Studying waveburst sensitivity using software injections of
sine-gaussians.
General Computing (Wallace)
MIT:
(Keith)
-Troubleshooting sporadic lock-ups on webserver / printserver
(no messages, no panics, no cores, hw seems to check out fine)
(connections lost (serial, console, network) - can't get to OK
prompt)
-Patched several windows machines
-Trying to free disk space on main fileserver
-Installing Cisco wireless access point to see if it handles non-orinoco
mini-pci cards (Phillips / Intel etc) without rebooting the AP
-Setup PC so visiting postdoc could swap files from laptop
Hanford:
(Larry for Christine)
-Purchased a number of items for wireless expansion.
-Working a number of logistical issues for the LSC mtg. coming up.
Livingston:
(Shannon)
-After spending several days working the bugs out of the new file server
provided by ASA, I have begun setting up the directory structure and
shares on it. I have decided to go with ReiserFS on the file
systems
since it gives more useable space as compared to ext3. Also,
in some
benchmarks it performed better than ext3. I have not benchmarked
NFS
speeds yet. Now that I have all of the bugs worked out, I will
continue
to test it for a couple of days before I put it in service.
-Still had some e-mail server troubles until Sunday. I checked
the mail
server over the weekend before leaving home at 10:30 am and when I
returned at 2:30 it had stopped accepting messages. I have been
able to
clear up most of the error messages that I believe were contributing
to
the problems. Also, it appears that a change in the firewall
configuration helped. It is still not exactly clear what is causing
the
mail server to start rejecting messages even though several people
have
looked into it. However, it has not happened again since Sunday
after
the additional firewall change.
-Received a quote from Sun for another 280R to replace our existing
web
server. This includes trading in the tired E3000 that was a
hand-me-down from CIT. It saves an additional 12% off the list
price of
the 280R due to the trade in.
-Received a quote from Sun for a calendar server and an e-mail server.
-Will look into this when I am done with LDAP.
-Set up a couple of workstations in the new building.
-Installed an atomic clock client on the laser safety computer to stop
the time from becoming skewed and locking doors at inappropriate times.
-Setting up a mirror of both the SunFreeware site and gnu.org.
I will be
rebuilding the GC apps when the file server is complete, so I will
need
many of these items in the process.
(Mike)
-Worked with Cindy Akutagawa, showing her how to work with her new
assigned laptop.
-Worked with Angelo Gladding showing him how to load a GC workstation;
plus showing him how to get updated ghost images through the network
to
our ghost backup server.
-Ghosted Cindy Akutagawa, Fumiko Kawazoe, and three visitors
workstations this week.
-Work on loading a workstation for Fumiko Kawazoe; she is on a win98
workstation. I am loading a 2000 pro computer with updated software
for
her.
-Installed additional hardware on Calum Torrie & Ken Mailands computers.
This included installing additional monitors & video cards, to
give them a
panoramic view.
I am having a problem running solid works running this new video card;
it
seems that there is an incompatibility issue with this new video card.
I
will have to do some more research on this.
-Worked on Janeen, Calum, and visitors workstations fixing an ANSYS
problem. After going to ANSYS website I found that Microsoft's service
pack 4 for 2000 pro, is not compatible with ANSYS. Recommendation is
to
uninstall service pack 4, which I did. ANSYS is up and running again.
-This week there was a lot of user support that I took care of, that
included networking, e-mail, software and many printing problems etc.
etc.
(Veronica)
- LIGO website: Captured/digitized analog video footage provided by
Bill
Kells. The footage is a series of 9 clips. I captured it as separate
clips, as requested by GariLynn, and as a single clip for archiving.
Compressed them for streaming for 2 bandwidths and installed at the
media
server. Burned the raw source files onto a DVD for Bill. Compressed
a 2nd
batch for downloading and burned onto CDs for Bill and GariLynn to
distribute. Wrote the scripts for web sharing of the videos and helped
GariLynn install them at the Core Optics webpage. Working on editing
the
clips for Bill's upcoming presentations.
Posted various updates at the LIGO website. Updated the roster database.
Working with Karl Gebhardt on the VRVS setup for his Friday LIGO seminar.
I will also videotape it per Riccardo's request.
Looking into the configuration of castor. Tried to install password
protection files for Ryan but it seems the server configuration needs
to
be checked.
- LSC website: Posting daily updates to the upcoming meeting website.
- CaJAGWR website: Posted updates to the roster. User support.
(Lisa)
-Testing out new mail filtering program.
-Modified LSC web services.
-Attending LISA (computer) conference.
(Larry)
-Made a number of purchases for different groups. Reviewing the contract
with
Matlab.
-Built a number of PC's and started setting up the sandbox units for
the E2E
group.
-Began a build of a new server for the 40M.
-Reworked a couple of accounts and cleaned up a couple of old accounts.
Started
moving old dead accounts to another location to free up space for the
active
accounts.
-Worked a couple of small e-mail issues.
-Spent a little more time on VRVS but this has been put on the back
burner for a
few days. It still needs some work to get the quality we want/need.
-The work to get the WAN for Livingston continues. Mike Z. and others
are
getting paperwork through the system.
-Worked a number of logistical issues for the upcoming meetings.
-Attending the LISA conference.
Working with various suspension team members on a top-down progress report for the preliminary design phase and, in conjunction with that, working on an understanding of the tasks left to complete the RM and ETM controls prototypes designs and fabrication. Worked on refining the FY04 suspension budget along with various descoping scenarios.Preparing for the NSF review.
From: ctorrie <ctorrie@ligo.caltech.edu>
Recycling Mirror suspension
The masses and moments of inertia of the three
suspended masses have now been checked with Norna
and the MATLAB model. The info has been checked against the blade drawings.
No request for RFQ will be made at his point in time. We have one question
to finalize before this section of work is complete.
MPL, Alastair Grant and I met on 2 occasions
this week to discuss aspects of the Recycling Mirror including an improved
pitch adjuster and a method for adding an
removing mass to the intermediate mass. We also discussed what sections
of work will be done over the next few weeks for the RM.
Layout of the ETM
At present the ETM suspension is 210.5 cm in length. For advanced LIGO
this will allow for the possibility of either cartridge installation where
everything goes into the tank together or allowing you to add everything
except the final 2 stages of the suspension, which would then be added
later. However for LASTI there could be an interface
problem doing an all together installation with a 210.5 cm quad,
for full description see Janeen's notes
from SUS telecon this week.
Over the next few months Norna and I
will model the quad in more detail and investigate amoung
other things the lengths of the individual stages. At the same time
progress will be made on the design for the ETM and in fact we should hopefully
have a detailed design and therefore a more definite overall length around
March 2004.
I believe the plan is to use 210.5cm as an upper limit for this work,
but if it is found it can be done for less without affecting performance
then we will consider giving back
~ cm.
Coils
A full set of drawings for RM, ETM and MC
coil head and associated parts have now been reviewed by Larry Jones and
updated by Russell Jones and I. We hope to summarise
what we have and what we believe we should order for the Controls Prototype
at next weeks SUS telecon.
Eddy Current Damper
Mark Barton and I worked in the laboratory testing several eddy current
damper designs on a suspended 6kg mass. full
report to follow.
Man Power
Janeen had several meetings this week with
the suspension team to try and understand better the sections in Thomass'
Status Report and to update the estimates in % complete and time left to
complete.
Visits
Russell Jones will visit Caltech from the 11th to the 25th of October.
Mike Lloyd is planning to visit from the 18th Jan to
From: "Mark Barton" <mbarton@ligo.caltech.edu>
This week I worked on updating the Adv LIGO
SUS DRDs. I also did some
measurements with Calum on the effectiveness
of a light-weight eddy-
current damper design, and worked with Janeen
on a LASTI controls
prototype test plan.
From: GariLynn Billingsley
<Billingsley_G@ligo.caltech.edu>
The scatter/absorption test stand now has an operational 30 watt TEMoo laser. The baseplate and beam delivery system are both in the final stage of alteration.
We have not yet received a quote from Makowski
for absorption measurement of the
A discussion with Chandra Khattak of
Insaco is still working on a more conventional method for getting a good polish on the barrel edge of a large substrate.
We have placed an order with CSI for a 43mm diameter x 300mm long sapphire rod for use in measuring the Q of sapphire at low frequency. Delivery is promised in February '04.
CSI has updated delivery of the 16 3" x 1" sapphire Q substrates from Late September to early December '03.
MaddalenaMantovani
and Barbara Simoni arrived from Pisa for
a 9 month 5th year thesis work.
Maddalena will work on sapphire thermal conductivity,
wrapping up Mike Hall's work, and issues connected with Hysteresis
in Maraging and advanced passive seismic
isolation.
Barbara will work on mexican
hat interferometer with Erika and Phil.
Maddalena
checked up the cryo lab and found the
cryostat broken, contacting the manufacturer for repairs.
Barbara
being introduced into the formalism by Erika.
Riccardo, Hareem
working on paper, draft in /~desalvo/maraging-hysteresis.doc, waiting
for comments from other authors
For additional information about this report, contact sanders@ligo.caltech.edu