|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday October 13, 2003 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
Special Items: BARRY AND PHIL WILL CHAIR THIS MEETING
no report
LIGO Weekly Site Telecon (Lindquist)
A site teleconference was held on Thursday, October 9, 2003. The following were among the issues discussed:
Action List - Ed Jasnow is ready to implement the convenience checks for Livingston..
Budgets - A FY 2004 budget model has been distributed. I have received some comments from Florence and from Alan Weinstein. There is no overt management reserve in the model. We estimate $6 million of carry forward, and all $6 million has been allocated to tasks remaining from FY 2003. However, delaying HAM Seismic Isolation work into FY 2005 will defer approximately $1 million.
EPI - The last of the EPI contracts that required NSF review and approval are out to the vendors.
Property - The trailers (plus some miscellaneous other equipment),
will be posted for sale this week. If they are not sold in two weeks
the will be "abandoned," which means that the government will have to haul
them away.
The list of current actions revised to reflect
the status of open actions assigned through August 28, 2003 may be found
at ACTION
LIST.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
ACTIVITY
| 10/09/03 | Packages | Faxes |
| In | 19 | 36 |
| Out | 12 | 43 |
Press here to access
the DOCUMENT CONTROL CENTER
WEB PAGE.
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA .
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
SUPPORT (Baldon, Lloyd, Tischler)
>Irene Baldon
ADVANCED LIGO (Cost Schedule
Control Systems) T. Frey
From: Thomas Frey <tfrey@ligo.caltech.edu>
Out
of the office on Friday the 3rd.
For list of documents that
are being used to develop Adv. LIGO Cost and Schedule, see http://www.ligo.caltech.edu/~tfrey/Cost_MTG_082002/
Continued development of a proposal for implementing Primavera Project Planner Enterprise.
Static HTML Example - http://ligo.caltech.edu/~tfrey/SUS_WebProj/ (AdL Suspensions Only) NOTE: This is after importing and before any data corrections.
Static HTML Example - http://ligo.caltech.edu/~tfrey/DAQ_WebProj/(AdL DAQ Only) NOTE: This is after making adjustments to the WBS so that it displays as expected.
Continue to prepare meeting minutes regarding the tracking of action items discussed with Carol.
AOS - Still need completed WBS dictionary and BOE.
IO - Still need completed WBS dictionary and BOE.
SUS - No action items pending.
SEI - No action items pending. Working with Larry to update SEI with progress through 09.26.02.
ISC - Still need completed WBS dictionary and BOE.
LDAS - No action required at this point in time.
INSTALL - No action items pending.
DAQ - No action required at this point in time.
PM - No action required at this point in time.
FAC - No action required at this point in time.
SUP - No action required at this point in time.
Followed up with Irena Petrac regarding the status of LSC MOUs.
A budget model has been submitted to Florence to be used in the FY 2004
reports. We will continue to iterate over the next month or so.
The following change requests are open.
| CR-030015 | FY 2003 Livingston Observatory Detector Maintenance Expenses (Increment) | R. Wooley | July 14, 2003 |
| CR-030016 | Hanford Facilities 2.2--Divide the Large Equipment Access to Facilitate Movement of Large Items (currently assigned to FY 2004 liens list) | J. Worden | July 31, 2003 |
Additionally we have received a request to add budget to the Louisiana
Facilities account to cover items moved there when the Construction Project
was closed. We will do this, but we are waiting for the final numbers
for FY 2003 so that we can address all of the Louisiana accounts.
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
Summary of Commissioning Activities at LIGO Hanford Observatory (compiled by L.Matone)
H1
In the past week, H1 has been running in high sensitivity mode with
all of the angular
DOF locked. However, the lock stretches have been observed to be only
4-6 hours long and
we are currently investigating the reason for these short stretches.
The inspiral range has been observed to vary from 1.7Mpc to 1.2Mpc (see
elog).
This was
due to non-stationary peaks around 100Hz coming from the ITMY (and
X) bounce
modes (the "3-fingers" problem, see log).
Despite the non-stationarity, signs of improvement
in acoustic coupling were seen due to the table work on the reflection
port from last week (see elog).
The "3-fingers" problem was then resolved by adjusting the power recycling
loop gain (see elog)
which
eliminated the non-stationary behavior. Our current displacement
sensitivity is shown in this elog
which
also compares the sensitivity from a few months ago (note that the
vertical scale is in m/rHz).
Measurements on frequency and intensity noise were also made (freq
noise, intensity
noise)
and they were found not to limit our sensitivity.
H2
Just like H1, we replaced the EO shutter on table ISCT7 with a rotable
half-wave plate (see elog).
The Guoy phase telescopes were adjusted for WFS2 (on reflection), WFS3
and WFS4 (see elog.).
The Guoy phase telescope for WFS2 on POY was designed (see elog).
All of the WFS loops were
successfully closed (see elog).
LLO (Zucker et al)
---------------------------------------------------------------------
(some contributions missing due to LLO disk crash and GC net outage)
Interferometer commissioning:
--------------------------------------------------------------------
Tough week on L1. We now have robust locking during nighttime hours,
but
have an excess noise problem which is proving difficult to track down.
It seems to originate somewhere in the common mode frequency control
system and only manifests itself when the interferometer is in
operation; off line, every component checks out fine. We have tested
numerous theories and are currently probing for a subtle nonlinearity
that could be associated with some recent electronics mods; in theory
this looks like a good candidate and could be easy to fix, but at this
writing it's too soon to tell. Rana, Pradeep, Valera and Andri
are on
the problem for tonight.
In the meantime we've made significant progress on many other fronts
(check the ilog for many more):
o Stefan Ballmer, Brian O'Reilly and others calibrated and tested shot
noise sensitivity for our new dark port "running" photodiodes; Rana
and
Stefan were able to successfully hand off from the acquisition diode
to
these as required for our eventual power up.
o Brian and Rus installed the new ETM Dewhitening filters and
characterized them. These should allow a bigger noise margin than S2-era
dewhiteners at high frequencies.
o Matt Evans, Rana Adhikari, Rupal Amin and Gaby Gonzalez have made
significant progress on the WFS control matrix. Due to the above problem
we didn't get to try full WFS control out properly before Matt took
off.
o Matt also wrote an automatic lock-in servo script which processes
the
alignment dither (a method borrowed from LHO last week) to automatically
converge arm alignment at the push of a button. Still in "beta test"
but
the demo was slick.
o Pradeep Sarin, Rupal Amin and Valera Frolov tuned up the mode cleaner
wavefront sensors (MCWFS) and built new digital control filters. The
mode cleaner holds alignment like a rock now, doesn't even notice the
nightly trains.
o Rich Abbott and Flavio Nocera (by phone) diagnosed an oscillation
problem with our new intensity stabilizer (ISS).
o Rolf Bork flew out to help Chethan Paramesewariah debug a nasty timing
bug in the end test mass EPICS processors. After exhaustive round-robin
component, code and location swaps it was traced to an apparent bug
in
the MVME162 microprocessors themselves (probably only certain vintages,
as the problem was never seen at LHO). Today they recompiled the code
for MIPS CPU's and substituted these for the 162's, solving the problem.
o Rai has done significant work to modify and characterize the new Coil
Readout filter boards. These allow high-SNR readback of the actual
forces applied to the test masses during low noise operation. In the
process Rai also fully characterized all the new ETM electronics and
blessed their quietness.
o Harry O and Gary T have installed the LHO damping kits on all of our
periscopes and installed the new super-rigid periscope shipped from
MIT
onto our dark port. A second unit slated for the REFL port turned
out
not to fit without modification, so we backtracked to the original.
Safety and security (Riesen)
--------------------------------------------------------------------
Completed weekly IR scans on PSL and IO/ISC tables, found zero
errant beams.
Weekly site tour gave no concerns or reports.
Continuing work on the revised LLO Laser SOP.
CDS Software (Khan)
--------------------------------------------------------------------
1) Developed and tested the Mode Cleaner Autolocker perl script.
2) Developing a method for monitoring the UPS
3) Developing scripts for XArm and YArm autolocking
Commissioning (Traylor)
--------------------------------------------------------------------
Installed constrained layer dampers on all of the ISC and IOT periscopes.
Completed the installation of the new and improved AS periscope on
ISCT4
after modifying the mirror mounts and machining new shims for the mirror
mounts.
Commissioning (Peter King)
--------------------------------------------------------------------
I have been trying to diagnose the optically contacted pre-modecleaner.
After sorting out a few minor problems associated with running an NPRO
laser at low power, I managed to align the pre-modecleaner. I
did not
see any of the errant beams that were reported last month; either with
an IR viewer, IR flashcard or both. It also checked out with
the green
HeNe laser. In short I think the cavity is okay but cannot explain
what
was observed previously.
I tried to find out where New Focus get the cases for the photodetectors
in the hope of being able to use a similar package but apparently they
are custom made. Whilst the prototype is packaged and heatsinked,
assembly and disassembly is not very convenient. It may require
a
designed housing.
Shally Saraf is coming down next week to fabricate the approx. 100 mm
round-trip length ring cavity. All items are expected to be in
hand by
tomorrow.
Commissioining and HEPI electronics (Abbott)
--------------------------------------------------------------------
1. Finished all electronics for valve calibration stand.
7 units are
to be produced per Jonathan Kern. All metal work, parts ordering,
and
PCB ordering has been completed. Units to arrive soon, and be
sent to
stuffing house. I opted to see the units first instead of sending
them
directly to the stuffing house. In the future, I will send them
directly to the stuffing house along with the necessary parts.
2. Design is underway for the seismic interface chassis.
Received
prototype chassis for use in the design, and it looks good. I
will be
sending around the schematics as they are completed.
3. Modified the ISS board to cure a crossover related instability.
System performing well.
4. Tested a prototype FSS card with enhanced high speed HV amp.
Achieved ~500 kHz UGF, but design is far too prototypical to install
this close to a run.
Commissioning (Gretarsson)
--------------------------------------------------------------------
Made a simplified interface for getting RDS and NDS data to a Matlab
workspace including the workspace of functions (not possible e.g. with
DataLoad). The GUI is called "datapuppy" and the idea is basically
to
make getting small amounts of data (be it live or from a previous run)
into Matlab totally trivial, even for a complete newbie.
Should be
available on from the Matlab command line on GC at LLO by S3.
LLO Seismic retrofit (Kern)
--------------------------------------------------------------------
All of the drawings for manufactured and machined parts have now been
released for production. Working with Linda T. to complete the
last
large contract, however the shop has been given the go-ahead.
The
machine shop manufacturing complete sets of parts for 12 actuators
by
November 14 still seems to be on schedule, have had a few conversations
with the manufacturing engineers at JPL and should have a milestone
spreadsheet completed this week. Sent the parker valve test manifold
back to the shop for manufacture and installation of sleeve bushings
in
the plug valve bores. Ordered misc VCO fittings from Whitey valve.
I've reported the difficulties we've experienced using SolidWorks,
managing the integrated models of the HEPI/HAM and HEPI/BSC. I have
installed PDMWorks on a local server. PDMWorks is a digital analog
of
old fashioned 'flat files' in drafting rooms, keeping track of who
is
working on what part of the model as well as revision history. We've
archived the LLO Seismic retrofit to a PDMWorks vault. Ken Mason
is
here to go over the integrated model with us, and we've arranged for
a
tutorial on S
Interferometer commissioning, AdLIGO simulation, and data analysis (Franzen)
--------------------------------------------------------------------
1) Weili Ke and myself finished installing the f2p filters. See our
entry in the e-log on Oct.2 for a summary. We would still like to fine
tune the actuator coil gains a little if given a window of opportunity
and if it is judged to be worthwhile to do it.
2) I have prepared and tested scripts for running a WaveMon LLO S2 veto
analysis on alvar. However, some S2 data is still not available on
this
machine. Igor is now fixing this.
3) I resumed my AdLIGO MC simulation work using MELODY.
Jonathan Kern
Contamination Cavity # 1
The contamination test for the sample "PEEK" wire
spool for the OSEM it has been completed. The result does not show signs
of contamination. plots will be released by Dr. Zhang.
Absorption Test Measurement prototypein
standby. We have received the new 30 watts laser and took it down to OTF
Lab. New bench for the new laser has been designed and parts ordered and
drawings taken to the Physics shop for fabrication.It
will take ~ two weeks.This new bench
will match the same height as the Scatterometer breadboard.
Scatterometer system: A new and complete scan for
the HR and AR surface Reflectance and transmission for the 2ITM04-C (Inner
test mass mirror) has been completed.The
results are the same as before.The
contaminated film of Gaussian shape is still there. We have tested the
mirror surfaces at different incoming laser beam angles, flipped mirror
surface, changed polarization etc.. and measured it but the result is the
same.the
reflectance is~ 4% and transmission
~ 2000 ppm. The question to understand is, Why Does the transmission increase
as the beam goes through the contaminated film ??Mr.
Zhang and I, will set up a new scanning test through the mirror surfaces
and be able to measure at different rotated mirror angle and so on. Complete
plot and results will be released by Dr. Zhang.
OTF Lab at Lauritsen ROOM 38
Cavity #3: We have recovered the old results and the
chamber is pumping now with the old, cleaned and original mirrors of ~70ppm
and the ring down was recovered back to 23.5 microsec. as compared to the
18.0 microsec from the new REO mirrors (too much scattering). We are taking
New RGA measurements and recording it as a chamber without test sample.We
will introduce a new test simple of solder joints.Kester
SN63Pb37 solder vacuum cleaned with RGA results.
Cavity #2 Test cavity in STANDBY.
no report
HEPI Progress (McInnes, Mittleman)
The hydraulic plumbing has been completed and leak check by the
installers. We are in the process of transferring the 8 hydraulic
actuators from the BSC to the HAM and hope to have fluid flowing by
early
next week.
LASTI Planning
A LASTI reveiw will be held at the LSC meeting, hopefully the issues
such
as weigh budgets and cavity configurations can be settled there.
---------------------------------------------------------
LIGO Data Analysis and Computing (Anderson for Lazzarini)
---------------------------------------------------------
-----------------------------
LDAS Software Team (Blackburn)
------------------------------
Focused on closing out critical and important problem report over the
past week. More than 50 problem reports were closed out. There still
remain 2 critical and 20+ important to be addressed before the release
next week.
The Standard Template Library's string class has been identified as
one
of the major contributors to core dumps in the frameAPI. We have written
our own substitute string class which is thread save. It has partially
been integrated into the frameCPP code as of this week and has greatly
reduced the rate of core dumps on the LDAS TEST system where it is
primarily being tested. We will continue to advance the integration
of
this new string class for the release, but have not committed yet to
using the optimized level of inlining that this is intended to fix
in
the science run. Without the optimization, we are seeing only about
40% of the performance in the frameAPI.
A bug was discovered in the LDAS user account cgi script which caused
it to report to the database that new user account were created when
in fact they were not. This has been fixed and the user accounts at
the sites and in the database synchronized.
Developed a new test to validate that the frameAPI does not corrupt
data. This test will be run tens of thousands of times before the LDAS
release to verify that no data corruptions is taking place.
On Monday we commenced the mock data challenge for S3 data reduction.
Three levels of data were being produced at LHO and LLO on Mon-Wed
(LLO
has stopped producing reduced data at the moment because of problems
with GC
servers. It should be back online today). Level 1 reduced data is being
produced at a rate about 1.7 times faster than real-time while it is
catching up to the current time. Level 2 (AS_Q, DARM_CTRL and EXC channels)
and Level 3 (AS_Q only) data are being produced several times faster
than
real-time. The server outage at Livingston and the harddisk failure
in the
CIT archive have caused testing to temporarily pause at these two sites.
After some initial problems with installation, the new LDR has now been
successfully installed on all machines (cit, lho, llo, mit) by Hari
this
morning and we will be publishing data to LDR today.
-----------------
E2E team (Bhawal)
-----------------
E2E Weekly Physics Meeting
----------------------------
Luca and Matt described current status and problems at sites.
Matt explained his ezlockin script.
At LLO
-----------
(Matt) Worked on ASC system at LLO. Also developed generic script
for system
diagonalization (ezlockin). ezlockin can be used to diagonalize
drives,
align cavities, and generally decouple bilinear degrees of freedom.
WFS
--------
(Biplab) Large changes in demodulation angle for differential heating
in two
arms have been observed in simulation. For example, for change
in temperature
only in Y-arm from a state half-way between "cold" and "Final
hot" state,
while keeping X-arm in "Final-hot" state, the demodulation angle
for WFS2 signals
for rotations in the recycling mirror changed by about 0.4*pi=72
degrees, while
the maximum value of the signal increased by about 33%.
Code development and maintenance
---------------------------------
(Melody) Performing code cleanup for the framework to do the on-the-fly
compiling & dynamic linking.
Extending the code base for a 1x1, 2x2, VxV, and 2VxV new FUNC
primitives.
Alfi
--------------
(Bruce) Attempting to track down a difficult edit-window initialization
problem.
-----------------------------------
Data Analysis Activities (Anderson)
-----------------------------------
Shawhan:
* Looked at loud inspiral event candidates found in the H2 S2 playground
data, and tried to find veto conditions which could eliminate
them.
I found that a veto condition using LSC-POB_I with a certain
band-pass
filter was very effective for some of the event candidates,
but there
were others for which I could not find any good veto condition.
* Went through the LHO trend data from S2, checking the Epics channels
which indicate timing problems in the front end. There
seem to have
been some problems. Waiting for advice from Dave Barker
and/or Rolf
Bork to see whether any data should be excluded from analysis
because
of these problems.
Reilly:
* In preparation for running the sgwb DSO on the recently released ldas,
I recompiled lal and lalwrapper under RH9 on ldas-pcdev1.
I also
compiled the standalone wrapper there. After some debugging
of
the DSO (removing printf statements) I was able to get it to
run on the new system and I was able to test the frequency masking.
All necessary preparations were made to *finally* get through
the S2 data
set but the ldas system seems to have a bug which cause the
frameAPI
to shutdown during my jobs. The cause of this problem is still
unknown.
Further delays are expected because the file system used by
ldas-cit
has crashed.
Yakushin:
* Finished working on using the calibration data in the waveburst.
-------------------------------------
LDAS System Administration (Anderson)
-------------------------------------
Caltech
-------
(Dan Kozak)
* Encountered "stuck" file in archive (ls -l of it would hang), rebooted
ldas-archive, ran samfsck, got it working again.
* Got QFS licenses for new gateway boxes at LLO/LHO (waiting on a permanent
one for MIT)
* Relabeled tapes in archive to make obsolete (9940A format) tapes
available again.
* Migration from 9940A to 9940B format tapes continues. We've
got 6%
left to go as of this writing.
* Continued to copy E7 data from HPSS.
* Finished copying all S2 L1 RDS files from IDE-RAID into SAM-QFS.
Am now
doing some housekeeping work in order to ship tapes to the observatories.
* Recovered from failure when a 3510 disappeared from the FC fabric
and
the FC switch reset it's port (i.e. a piece of the filesystem
disappeared). This involved finding the data that had
been corrupted
and ensuring that a good copy went into the archive.
* Fixed stuck silo robot.
* Started copying RDS from IDE-RAID into SAM-QFS at LLO.
* Tracked "stale inode" message at LLO--a benign message as best I can
tell.
* Assisted with exporting tapes from silos at the observatories for
the MDC.
(Hari Pulapaka)
* Installed the old LDR on test machine and tested the RDS publish
script. Ironed out a few bugs in it.
* Requested certificates for all the hosts in the MDC run and installed
them.
* Installed LDR on the hosts in the MDC run.
* Publishing data as a part of the MDC run.
(Al Wilson)
* Installed RH9 on ldas-pcdev1 and m26 .
* Replaced motherboard in 3 pc's: datacachetest1, ldasbox4,5.
The new board
so far is working just fine.
* Rack mounted pc's and cleaned up cables in 215 Synchrotron.
(Stuart Anderson)
* Upgraded several LDAS servers (hardware and software) in preparation
for S3.
* Upgraded all the Lab LDAS systems to a pre-release version for the
currently ongoing Reduced Data Set (RDS) Mock Data Challenge
(MDC)
which is testing our ability to generated reduced frame files
and distribute them throughout the collaboration.
* Testing replacement motherboards for IDE-RAID and stand-a-lone
Linux LDAS development machines. The initial results are very
positive. If no errors are found during weekend testing all
~20 of these systems will be upgraded.
MIT
---
(Keith Bayer)
* Installed SSH patch on gateway machine.
* Installing cable trays when possible.
* Installing 280R new gateway server.
* Moving cables into existing trays in ceiling when possible
enoki / lancelot back in production DMT mode .
Livingston
----------
(Igor Yakushin)
* This week we are running MDC to test the raw data
archival and RDS generation.
Several problems have been uncovered as a result.
a) dd that is used in Ben's script to copy raw data
from /frames to /samrds worked extremely slow
at LLO
(but not LHO) unless one changes the default
block
size. Currently I am using bs=128k.
b) The current version of diskcacheAPI has trouble learning
about new directories added to MOUNT_PT. To
fix this problem
Phil had to increase the number of threads
from 2 to 8.
c) Ben's script copying raw data crashed. Ben has
fixed the bug.
d) Yesterday the whole GC system went down and as a
result we can no longer run createrds script
on
ldas-jobs since it uses NIS and mounts user
accounts
from GC. It is down until GC problem is fixed.
* I tried running DB2 administration server under RH9
and so far was unable to do so. Without it we cannot
use replication.
Hanford
-------
(Ben Johnson)
* The new 280R gateway server has been installed and has been working
as the ldas/gateway box during the MDC this week.
* I have now been set up as part of the GC dsorun group. I can now
administer and run createRDS jobs on the ldas-jobs box at LHO.
* The disk2disk copy script (/frames -> /samraw) has been copying data
for the MDC this week at both LLO and LHO. I have been working
with Igor
on getting rid of bugs in the script.
* I have also been working on scripts to allow for easy monitoring of
the archiving processes; disk2disk copying and archiving+staging
in samfs.
---------------------------
General Computing (Wallace)
---------------------------
MIT:
(Keith)
-Troubleshooting XP laptop with registry problems
-Working on laptop with sporadic system crashes
-Working on desktop PC that no longer boots
-Ordered software / spare computer parts
Livingston:
(Larry for Shannon and Tom)
-Shannon has been spending time setting up the PDMworks to run locally.
-Major portion of time spent repairing their main server.
Hanford:
(Christine)
- It's been a very busy week. Our network has been bombarded
with
pings followed by short bursts of TCP packets originating from about
100
different IP addresses. Most of the ip addresses were dhcp addresses
from Stanford University. I sent an e-mail to ITS Security at
Stanford,
but just received an automated e-mail back saying they were so
overwhelmed with computer security issues they would try to get to
my
problem. There were also ip addresses from Germany, Japan, Mexico,
and
several USA ISP companies. I started blocking the ip addresses
at the
router firewall, but it was just too many. As soon as I would
block one
batch of addresses another batch of new addresses would show up.
At
first it looked like they were just targeting my dhcp server, so I
got
dhcp running on another computer, took my original dhcp server off
the
network, reinstalled the Solaris OS, took this opportunity to upgrade
from Solaris 8 to Solaris 9, installed all of the Solaris 9 patches,
and
finally got dhcp running again on the re-built server. This is
when the
pings started going to all the computers on site and not just the dhcp
server. As a last resort to stop the hacking I blocked ping to
all of
our computers. Blocking ping stopped all the hacking packets
at the
router firewall, they are no longer getting into our network.
The
hacker traffic to the router is slowing down our legitimate WAN traffic
and now that the access list on the router is much longer this also
slows down legitimate network traffic which has to be compared to the
access list.
- I ran into the same problem that Shannon experienced back in April
or
May. I used the new Solaris Management software to add a user
to a
group in the NIS+ tables and it messed up the NIS+ tables and the
ownership of all the files in the home directories for every user.
It
took me three days to correct everything in the NIS+ tables and the
files.
- Last Friday night the network to Caltech went down causing us to
loose
our DNS servers. I modified all our local DNS tables to use the
DNS
servers at MIT. At Larry's suggestion I'm looking into building
our own
secondary DNS server.
CIT:
(Mike)
-Ghosted Cindy Akutagawa and Calum Torrie's computer.
-Updated all NTSRV's this week with windows update and Norton anti-virus.
I
also check the security logs for intrusions.
-Setup a user account for a visitor that is working with Hiro.
-Worked on a hardware problem for Mike Smith. This PC was having a
problem
with the CDROM I was able to correct this problem. He is back up and
running.
-Reloaded Calum Torrie's engineering workstation. This computer had
a
bad
hard disk. I tried to perform a mirror image of the damaged drive to
a new
hard disk, by using multiple restore utilities that were suppose to
handle
these types of problems. This got me know where, but I was able to
get most
of this users data off the old drive and transfer over to the new drive.
This is a big project due to reloading OS, GC software and multiple
engineering software packages that needed to be loaded. There was a
problem
logging into solid works to download the latest service packs, due
to some
licensing issues that required many phone calls to solid works tech
support. This issue is now resolve!
-Worked with Cindy Akutagawa showing her how to work with and get the
best
performance out of her new scanner.
-Worked on a virus problem that was on Gina Salone's computer. I ended
up
having to download and run a removal tool for this virus, cleanup registry,
update windows and virus scan software. Plus I loaded zone alarm to
prevent
this from happening again. This bug also corrupted her e-mail, which
needed
to be un-installed and re-installed. It is possible that this computer
might have to be reloaded from scratch, due to this computer having
a few
more glitches that are still present.
-Burned end of the month NTSRV's ghost images to DVD.
-Started going through and updating some of our loaner laptops, that
were brought back from travel. This includes updating installed software,
and most installed virus scan software and windows updates and cleaning
up
the users old data that was left on these computers.
-Called in Linda Turner's old Dell laptop. The LCD went out on this
laptop
and had to go through multiple diagnostic tests with Dell's tech support
people. After being on the phone with these for a few hours they decided
to
send me out a tech to replace the LCD.
(Lisa)
- Updated the mail code on acrux. Spent some time talking to the developer
of
the pop code we use regarding a problem with webmail and pop.
I know why there
was a problem but have not yet recompiled the code.
- Reconfigured the web server on lsc1 to accommodate the stochastic
website.
- Installed castor in the server room. It is a special use web
server.
- Spent many hours demo'ing the next generation of wireless access
points.
There are some management issues with the new models that will take
me some time
to resolve.
- Got a quote for the update the webmail software.
(Veronica)
- LSC website: Finished scripting and images for the upcoming meeting
website. After some troubleshooting, installed the website at the LSC
webserver. Posting updates as they arrive almost hourly.
Worked with Kaice Reilly on migrating the website for the stochastic
group
to the LSC webserver. This involved working out some server configuration
issues.
- LIGO website: Set up and monitored the VRVS videoconferencing for
the
last seminar. Working with Larry and Mike on bulletproofing the system;
we were testing a combined VNC-VRVS setting to allow more detailed
view of
the viewgraphs, which is sometimes difficult with the current setup.
So
far, the desktop sharing system that VRVS offers seems to be an
alternative.
Briefly worked with George Stokes regarding updates of the DCC
architecture. We need to meet and discuss his proposed changes in more
detail.
Posted various updates to the LIGO website, doing several document
transfers and conversions in the process. Provided user support.
- CaJAGWR: Videotaped the opening talk by Massimo Tinto; captured and
compressed the video, which is ready to be transferred to the streaming
media server and posted online. Provided user support.
- Project Science website: Posted the bulk of the presentations from
the
last workshop. Converted them to pdf. Updating the database of attendees
and generating an e-mail distribution list.
(Larry)
-Worked a number s/w licensing issues. The Ansys pkg has been renewed
for
another year. We still have a few pkgs. that need to get the new licensing
worked out.
Purchased a number of supply items for different people.
-Assisted the DCC with a number of document issues. Most just getting
files
put into the correct locations.
-Worked with the Observatories on a variety of items. The majority
of the time
was spent with the Livingston site. The WAN has been a hot topic and
then
assistance with their recovery from a major server crash.
-Spent time working on PC's. All were minor issues with one exception
where
reloading a couple of pkgs. from scratch was needed.
-Worked a number of user and account issues.
-Continue rewriting a number of documents.
(Sears)
* (BS) Systems Work:
(1.0 days)
- Ilog upgrade to disable some
link features which affect privacy.
- Created new Caltech site Ilog
group and added users.
http://www.ligo.caltech.edu/docs/T/T030197-02.pdf
From: Sander Liu <syliu@ligo.caltech.edu>
Completed installation of the electronics for GEO suspension controller
test set.
We are currently working on the as built documentations
for the unit.
Shally Saraf is coming down next week to fabricate
the approx. 100 mm
round-trip length ring cavity. All items are expected to be in
hand by
tomorrow.
Cc: Gregg Harry <gharry@ligo.mit.edu>
Summary of discussion with Jean-Marie Mackowski
The dopant used in the doped tantala/silica coating that showed a reduction
in mechanical loss was
titania. This dopant also reduces the thermal expansion
of the tantala.
He feels a factor of 2 improvement in loss can be obtained beyond which
that which
has been optained.
A seven micron thick monolayer of hafnia was attempted in the small
coater, but was deemed a failure. It
had a milky look to it, indicating crystallization occuring in places.
Hafnia coatings are capable of
having absorption in the ppm range. Hafnia gets deposited only
about 1/3 as fast as tantala,
0.5 angstrom/sec compared to 0.16 angstrom/sec.
JMM was very concerned about how the coated mirrors are handled beween
the coating chamber and
their fully installed state. His experience in Virgo, which seems
to be born out in initial LIGO, is
that the absorption gets much higher due to contamination during installation.
This does seem to be a big
problem. JMM had some ideas about how to put a clean room around chambers
to avoid this problem.
A new idea for improving mechanical loss is to use many nanolayers of
the two coating materials, rather
than the normal quarter wave. Very small layers are denser than
micron scale layers, and this compactness
may translate into lower mechanical loss. Optical loss will probably
be higher in this case, though,
because of transission region effects. The coating will have
to be thicker overall, though, and this will
mitigate some of the thermal noise benefits of lower mechanical loss.
A nano layer coating would probably
take about twice as long to put down as a conventional coating made
from quarter wave thick layers.
The so called "magic" or "mystery" material was revealed to be made
from silicon, oxygen, and nitrogen.
Laurent's thesis at SMA was on investigating this material, although
not for our purposes.
The index of refraction of this material is between 1.9 and 1.95.
It would be used as the high index material in a
coating.
Sapphire is very difficult to clean compared to silica, and this depends
on which axis the sapphire is cut to. He
seemed to remember that c-axis is the easiest to clean, but he was
going to check into the axis dependance of this.
A good tantala layer should crystalize at 900 C. Lower crystalization
means too much gas was trapped in the layer
during coating.
Made 8 decisions that JMM wrote down and will work on in the next few months.
1 - First deliverable will be small coater run of 30 layers of 1/4 wave
hafnia and silica. There will be 1 thick Q
sample, 1 one inch sample, and 2 half inch samples.
2 - We tentatively agreed that he will provide two small coater runs
of monolayer coatings, one each of silica and
tantala. We agreed on a canonical thickness of 2 microns.
He felt any thicker would seriously distort the properties of the layer.
We will check to see if this thickness will work
for Q, absorption etc measurments.
3 - The failed 7 micron hafnia coating will be provied to Eric Black for photothermal experiments.
4 - The first official coating in the big coater will be a doped tantala sample.
5 - He will look into cleaning an AR coated sample with liquinox to
see if it effects the reflectivity the way it seems to on LIGO
optics.
6 - He will provide information about what temperature depositions are typically made at. He thinks it is about 300 C.
7 - He will look into whether a lab he knows in
was removed from the
8 - He will provide us with the data on the cleanliness of the Virgo
mirrors.
Stefano Tirelli
finished his last year report, now in the shape of a third year thesis.
Available in
ligo.caltech.edu/~desalvo/S.Tirelli.Final.pdf
Riccardo
Helped Stefano.
Studied more hysteresis of MGASF, a first draft report available in
ligo.caltech.edu/~desalvo/maraging-hysteresis.doc
Virginio and Giancarlo
Produced draft of the MGAS spring theory paper,
ligo.caltech.edu/~desalvo/MGASFTheory.pdf
Alessandro
Cut some sapphire samples for Maddalena, received fused silica samples
for cantilever coating Q-factor jigs.
For additional information about this report, contact sanders@ligo.caltech.edu