|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday September 8, 2003 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
Special Items:
no report
LIGO Weekly Site Telecon (Lindquist)
A site teleconference was held on Thursday, September 4. The
following items were discussed:
A review of the Financial Tracking Report revealed that we have spent $27.3 million through the end of August. This is 3% more than the same period last year. Projecting expenditures through December to allow for the remainder of FY03 charges to come through, we should have about $6 million to carry over into FY04.
It was agreed to fund the MIT contract the amount of $600,000 to carry them through the first two months of FY04.
The glass vestibule for the LHO Laboratory has been completed and the final invoices will be paid for Chervenell.
The Office of Purchasing Services has issued a memorandum defining the schedule for the closing of the fiscal year. In order for charges to be counted in FY03, purchase requisitions must be processed by September 19, and P-card transactions must be submitted to the bank by the merchant by September 15.
Hanford reported that they had over 1200 visitors in 500 cars for "Mars Madness." Traffic was dense, parking was difficult, and three cars got stuck in the gravel. It was agreed that a contingency plan of action needs to be developed for those times when high volumes of traffic are anticipated on the site.
The list of current actions revised to reflect
the status of open actions assigned through September 4, 2003 may be found
at ACTION
LIST.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
ACTIVITY
One DCN processed and distributed..
| 09/04/03 | Packages | Faxes |
| In | 17 | 15 |
| Out | 4 | 15 |
Press here to access
the DOCUMENT CONTROL CENTER
WEB PAGE.
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA .
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>Completing orders placed previously and following up on acknowledgements and certifications. Updating Access files in Purchasing with LIGO subcontracts. Closing out subcontracts and transferring funds as requested.From: Gina Salone <gsalone@ligo.caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
SUPPORT (Baldon, Lloyd, Tischler)
>Irene Baldon
ADVANCED LIGO (Cost Schedule
Control Systems) T. Frey
From: Thomas Frey <tfrey@ligo.caltech.edu>
Out of the office on Friday the 29th and Monday
the 1st.
For list of documents that are being used to develop Adv. LIGO Cost and Schedule, see http://www.ligo.caltech.edu/~tfrey/Cost_MTG_082002/
Clink on links to view the Draft Work-plan and Estimate.
Continue testing of Primavera Enterprise version 3.5.1. See the links below for information / technology demonstrations:
Progress Reporter - http://www.projwebsite.com/GroupServerP3e/en/ Login using Username: admin and Password: admin.
Static HTML Example - http://ligo.caltech.edu/~tfrey/SUS_WebProj/ (AdL Suspensions Only) NOTE: This is after importing and before any data corrections.
Static HTML Example - http://ligo.caltech.edu/~tfrey/DAQ_WebProj/ (AdL DAQ Only) NOTE: This is after making adjustments to the WBS so that it displays as expected.
Prepared data in response to a NSF question regarding the FTE count of foreign institutions for LIGO1.
Prepared data in response to a David S. request regarding the FTE count at MIT..
PSL - No action items pending. Followed up with Peter and Benno has provided data. Peter has yet to review.
AOS - Still need completed WBS dictionary and BOE.
IO - Still need completed WBS dictionary and BOE.
SUS - No action items pending. I will make a first cut of schedule changes for Janeen to review.
ISC - Still need completed WBS dictionary and BOE.
LDAS - No action required at this point in time.
INSTALL - No action items pending.
DAQ - No action required at this point in time.
PM - No action required at this point in time.
FAC - No action required at this point in time.
SUP - No action required at this point in time.
Continued input of changes / corrections regarding supervisors and departments.
Project Web Site for posting schedule and progress related data continues to be updated with the latest and greatest.
We are working on two proposals and work plans:
As reported last week, we had a teleconference with a number of the
people involved in the Outreach Proposal on Monday, August 25, 2003.
Actions were assigned to review and adjust budgets and text. I have
incoporated top level suggestions into a rather simplistic budget model
and provided copies to M. Zucker last week. Mike is to meet with
LA SUBR to discuss their possible reductions. Nothing new to report
this week. The next teleconference is scheduled for Monday September
8.
The following change requests are open.
| CR-030015 | FY 2003 Livingston Observatory Detector Maintenance Expenses (Increment) | R. Wooley | July 14, 2003 |
| CR-030016 | Hanford Facilities 2.2--Divide the Large Equipment Access to Facilitate Movement of Large Items (currently assigned to FY 2004 liens list) | J. Worden | July 31, 2003 |
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
Summary of Commissioning Activities at LIGO Hanford Observatory
Friday night saw over 1000 visitors to the lab. In concert with the Tri-Cities Astronomy Club, LHO opened its grounds to visitors who toured the lab, listened to public lectures, and took in views of Mars' southern polar ice cap and basalt flood plains (yes, much like Hanford) through the some twenty optical telescopes.
Locking on both interferometers remains sporadic; some good days of rapid relocking, followed by a day of long mean-times-to-lock, or difficulties completing the common mode (full up) script. The commissioning emphasis remains on subsystems such as WFS, and not reliability, as we try to achieve invasive S3 goals prior to the Oct 1 freeze.
2K IFO
CM locking has been obtained, despite a ill-centered spot on the BS.
This has allowed more WFS work, including closing the loop on WFS3 and
4. Error signals are driven to zero, but this does not help arm powers
or spob, and even hurts them a little.
People are gearing up for more acoustic mitigation, as next week a second meat locker will be installed, this one over ISCT10, the 2k AS port.
4K IFO
A displacement spectrum was obtained for the 4k, now with acoustic mitigation in place. A description and sample plot is given here . Note the curve is about 20% too optimistic, owing to a SUS gain tweak that was unaccounted for. This same displacement curve is shown again , this time opposite the curve prior to installation of the meat locker and new periscope. Comparing the curves, we see a factor of ~7 reduction in noise between 70-100Hz, and a factor of a few reduction between 500-800Hz. Some novel features arise, however, including narrow and oddly-spaced peaks above 60Hz, the source of which is unkown at this time.
Microphone-based tests of the acoustic mitigation setup are shown and described here .
Lead filters added to the DARM and CARM paths haved added 15-20 degrees of phase at the unity gain frequency (the phase margin had been a lowly 30 degrees or less). This appears to have stabilized locks on the 4k out to 30m to a few hours.
DAQ
New
front end code (asc, lsc, dsc) was installed on 4k processors.
Enhancements include increased speed, and the production of overflow stats
for ADC and DAC channels.
no report
Jonathan Kern
Started work on a review of the EPI drawing package.
I made appropriate
red-lines of the PDF drawing set and worked with Oddvar
to amend the
drawings. Model deficiencies have necessitated considerable
dialog with
the machine shop in order to accommodate the plug
valves. Confirmed
with most major HEPI vendors that POs have been received
and that
appropriate type and quantities of purchased parts
are on order.
Working with Oddvar and Marcel to check the EPI drawing
package. Working
with Swagelok to modify a brazed bypass valve.
Ken Mailand
Cleaning up the design of the LLO Pump Stations, and
making a list of issues for the group that will need discussion and clarification.
Have received a third lab test of the LASTI fluid,
the original new fluid and two used fluid tests, from June and August.
The fluid biological growth test is showing nothing
after 37+2 weeks.[2 weeks dark environment]
I'm doing follow up work on the LASTI drawings and
purchase order paper work.
Last week I released a new revision of the DMT (v2.6.2)
that includes
among other things, the DMT data generation program
and a fix to correct
the sample order in those channels that were affected
by the byte swapping
error in S2.
- Completed and installed new software for LHO4k LVEA
systems, primarily
ADC/DAC overflow detectors/counters:
1) LSC: Added ADC/DAC overflows for the latest
set of photodiodes and
ASI servo outputs.
2) ASC: Added ADC overflows on all input signals.
A fix also went in
to get Epics updates on startup.
3) LOS controllers: ADC/DAC overflow counters.
Also, these no longer
poll the variable delay timing modules. Rather, they
use the same scheme
as the LSC (start a bus cycle and wait vs. polling).
4) SOS controller: ADC/DAC overflow counters.
Also, in an attempt to
stop channel hopping on ICS110Bs, the code now reads
these modules at an
effective rate of 16KHz (SOS controller algorithms
run at 2KHz). Channel
hopping has not been noted in end station controllers
which run at this
rate so hope is this will fix the problem.
We are now switching our development system over to
LHO2K to test
software differences between LHO2k and LHO4k. Plan
is to install latest
software on LHO2k next week.
- Trying to track down remaining HEPI control requirements
in hopes of
completing a design doc by next Friday. Along these
lines, we are
testing FIR filters in our control software in the
event these are
required in the HEPI seismic channels. (No firm req or details, as yet).
1. Most of my time has been devoted to solving
the power fluctuation issues with the laser and PMC system. I am
in the process of improving the monitoring capability of the laser output
power so a better diagnosis is possible.
2. I have most of the documentation done for
the ASI servo at LLO, but am not finished. I have not heard any details
from LHO, but I admit, I have not prompted them since the CDS meeting.
3. I have started, but not finished, the documentation for the EPI review. Rolf is waiting for information from me that I have not yet had time to give him. I understand the importance of this, and will do it ASAP.
Jay Heefner reporting
LOS Coil DAQ:
- Installation drawings were generated and sent to
LLO for both the end station and LVEA. Rus will check them out and send
back any corrections and/or changes.
- The LLO drawings were also sent to LHO so that they
could be marked up as per the current suspension system configuration.
Once the markups are returned new LHO drawings will be generated for installation.
40 Meter:
- Installation continues on the LSC and ASC systems.
- Continued support during installation of suspension
systems, optical levers, etc.
Direct Digital Down Conversion:
- Have restarted the modeling and testing of the direct
digital down conversion system that could be used to implement a fully
digital FSS on the 40 meter. If all goes well and there are no major interruptions
we should have a design in two weeks.
Frequency Devices DAC Module:
- We have received the DAC module back from FDI and are testing it for glitches. So far none have been observed.
Ben Abbott
I am in the process of testing some ISS PD boards that will accompany Flavio and me to Livingston on Monday.
I have been through the fundamental formalism beneath
light propagation, since
the question of whether the phase front of the optical
modes of a cavity must
match the mirror profiles has been raised during the
preparation of the paper
on the sideband balance and never resolved. My conclusions
are that in general
the eigenvalue problem may or may not have confined
modes as solutions of the
eigenvector equation and the case of spherical mirrors
is a special one, as it
corresponds to the harmonic oscillator problem in
quantum mechanics, which has
an infinite set of normalizable solutions that is
the Hermite-Gauss functions.
Actually the number of confined modes can be "finite"
for the same analogy
with quantum mechanics for a generic potential. Even
if solutions of the
eigenvalue problem are found, this does not imply
any equivalence between
the phase front at the mirror location and the and
mirror profile.
Only by requesting time reversal symmetry the above
condition on the
phase front is forced. There is a paper that helped
me a lot and that is
PRA 46, 7 which describes how designing custom made
mirrors in a similar way
non spherical mirrors have been designed to support
the flat top beam for
Advanced LIGO. The assumptions are strong and I relaxed
them one by one.
For example they start with real solutions but this is just an assumption.
The baffles are at the high temp furnace and will be returned to CIT for clean and vacuum bake in a few days.
OTF Lab. (W. Bridge)
Contamination Cavity # 1
The new sample "PEEK" wire spool four of them for
the OSEM is under test. Cavity is locked and we are
taking ring down and beat frequency measurements everyday.
Absorption Test Measurement prototypein
standby/ in progress
( New laser
coming the first week of September 2003)
Mr. Liyuan is going through the absorption set up
and updating all the optics to accommodate the new laser.
Scatterometer system
Re- arrangement of the lab and preparation of a new
optic table to house the new ND:YAG 30 watts laser
still inprogress.
OTF Lab at Lauritsen ROOM 38
Cavity #3
It is pumping with two new mirrors from REO .
We are stillhaving
a situation as far is concerned with power output and cavity visibility.
A new and complete system modematch from NPRO laser
to the EOM and to the cavity is underway.
This time we are using two lens mode match instead
of one.
Cavity #2 Test cavity in STANDBY.
Since our last report we have
1) redirected the output beams of both arm cavities, removing their
collimating lenses and installing ND 2.0 filters to suppress
backscattered light noise;
2)implemented a fast, frequency-correcting Pockels cell in the mode
cleaner servo to suppress laser frequency noise above 10 kHz;
3) increased the modulation depth on the arm-cavity sidebands to
suppress the relative contribution of the photodiode electronic noise.
Thanks to the new output-beam configuration, we can no longer detect
any coupling between motion of the output table and the error signal
due to backscattered light. Thanks to the new laser-frequency
stabilization servo, we have suppressed the noise floor above 10 kHz
by
up to a factor of ten. Increasing the modulation depth further reduced
the noise floor, but not by as much as we had expected.
In the sensitivity plot below, the dark blue line is our expected
coating thermal noise, red is the expected substrate thermal noise,
and
pale blue is our estimate of suspension thermal noise. Blue data is
SAC's sensitivity, green is NAC's, and red is the difference between
the two (common-mode rejection implemented).
Our current sensitivity is, with common-mode rejection active,
approximately 1e-18 m/rHz over two decades of frequency, from 1 kHz
up
to 100 kHz. We suspect that the limiting noise source is still
electronic noise in the photodiode, and we are currently measuring
that
noise level to see if it agrees with our current noise floor.
The
unusually high noise level in NAC below 100 Hz was temporary and did
not appear in SAC. We are also currently investigating the source
of
that. While the noise below 100 Hz seems to fluctuate, above
100 Hz it
appears quite stationary.
HEPI Pump Station (Mittleman, McInnes,Mason)
The resistors supplied by Ken Mailand at Caltech have been installed
into the pump room. Testing will begin next week. The supply and return
lines for adding hydraulic actuators to the two HAM's has also been
connected to the pump station. The pump station is back on line
supplying fluid to the BSC chamber.
The parts required to convert the MEPI pre-isolator to a HEPI
pre-isolator have been ordered. This changeover is expected to begin
on
9/15.
Simulation and Modeling (Bhawal)
E2E Weekly Physics Meeting
----------------------------
Matt presented the outline and objective of the ASC system as
implemented
in the new SimLIGO release 030902.
Summary of the new SimLIGO release, 030902
---------------------------------------------
(Matt)
#### LIGO ASC
Science Objective of the ASC
- reduce seismic/control induced alignment
motion to prevent
sideband (and carrier) power
fluctuation from deteriorating
sensitivity or altering DARM
-> AS_Q gain by more than 1%
- initial target, alignment fluctuations
< 50 urad and power
fluctuations < 10 %
Objective of my work on the SimLIGO ASC
- understand the alignment sensing system
- design a robust control system that
meets the science objective
- transfer that understanding and design
to the commissioning team
Challenges
- non-diagonal sensing matrix (worse than
anticipated with SB on SB)
- non-constant sensing matrix (mode overlap
and power fluctuations)
- significant and variable radiation pressure
effects
- IFO inertia
- simulation of burnt-out coils =)
#### SimLIGO ASC
Interferometer Simulation
- includes radiation pressure
- includes non-resonant sideband on resonant
sideband contribution
Overall Design
- Two forms of alignment control
- global:
{WFS, QPD} ->
input matrix -> servo filters -> mirrors
http://www.ligo-wa.caltech.edu/~sigg/power_angle/newASC.pdf
- local: optlevs -> mirrors
Input Matrix
- transforms sensor signals into angular
position estimates for
all mirrors (in micro-radians)
- a "selective" inverse of the sensing
matrix
- optimized for robustness against variations
in the sensing matrix
- current matrix:
WFS1 and dQPD -> dETM and
dITM
WFS3 and cQPD -> cETM and
cITM
WFS2a -> RM
WFS2b -> BS
Servo Filters
- compensate for mechanical system
- can be different each mirror (i.e.,
OL on or off?)
- current servos
dETM and dITM : UGF ~ 5 Hz,
disabled optical levers
cETM and cITM : UGF ~ 5 Hz,
disabled optical levers
RM : crosses optical lever
below 0.1 Hz
BS : crosses optical lever
below 0.1 Hz
Radiation Pressure (a.k.a., Optical Spring)
Compensations
- no explicit compensation
- robust servo design
- large gain margins
- UGF away from resonance
frequency
- will add explicit compensation soon
to allow for
more sophisticated servo design
(needed at the sites)
#### How SimLIGO ASC helps LIGO ASC
The LIGO ASC system is currently in a state
of flux. A
good deal of work is going into designing
and commissioning
a functional system, but there have been
a number of stumbling
blocks along the way. SimLIGO offers
a low cost and rapidly
changeable testbed for ASC systems.
The work on SimLIGO, if
performed in conjunction with the efforts
at the site, should
help to speed the development of a robust
ASC system which
will improve interferometer sensitivity
and duty cycle.
FFT
------
(Hiro)
In the last couple of months, there was a discrepancy regarding the
estimations of the shot noise limited sensitivity,
SRD (Kent's and Lyon/Regehr formula), e2e and FFT. Bill and Hiro
examined the formula and came to the following
conclusion. The formula in Brett Bachner's thesis is sqrt(2) off from
the one of Lyon/Regehr. With this taken into account,
SRD, e2e and FFT results agreed within a few 10%, mostly coming from
the values used for the recycling gain, the input
power and subtle differences of the transmittance.
The uncertainty of filling up the unmeasured region (outside of 15cm
diameter, it is impossible to predict reliably, the best
is an educated guess) and the tilt removal (FFT has LSC, but not ASC,
and pre-treatment is needed to mimic the ASC) is of the
order of 10% when estimating the effect of the actual phasemap.
The conclusion is, with the input power of 5W, recycling gain of 40-45,
and the phasemap with roughness around
lambda/1200, the shot noise estimation in the SRD curve is pretty much
the real as-built LIGO should expect to
have, within a few 10% uncertainty.
WFS loops
------------
(Biplab) Studied stability of the WFS loops that Luca has implemented
in H1.
At Unity Gain Frequency of 0.1 Hz for all loops, the WFS system
is
quite stable but instability increases in general, if gains
are
increased
in all or in a few of those loops.
Mechanical simulation
------------------------
(Virginio)
- Working on the translation of the old mse programs to work
with the
new
version of the mse library.
- LIGO1 suspension has been translated and is going under a deeper
debugging. Some objects necessary to complete the simulation
in the
frequency domain must to be implemented
(position actuator, and beam object).
- The quadruple pendulum model is under translation. The code
to
simulate
the triangular blades with internal modes is under debugging.
Code development and maintenance
---------------------------------
(Hiro) New packages released:
SimLIGO 030902 and e2e-1.8.1 have been released and are available
for
download from the e2e home page and via CVS update.
e2e-1.8.1 has been updated to support the new SimLIGO release,
including the radiation pressure. It also has several non-trivial
bug
fixes, and all e2e users need to update the simulation engine
to the
latest.
(Melody)
- Continuing e2e source
code modification to dynamically create
C++ source from FUNC_xxx
equation modules, which would be compiled,
combined to a shared library,
and used during runtime execution.
- Built a new release of
the e2e simulation software, version 1.8.1.
LIGO Data Analysis System
Software Systems (Blackburn)
None of the fixes last week eliminated the core dumps in the frameAPI.
It
has been shown that by reducing the job rate on the LDAS-TEST system
to
the
level that can be handled without optimization and inlining, that the
LDAS
system almost completely stops core dumping. This leads me to conclude
that
the bugs are not from the optimization and inlining levels. Rather,
the
current
code performance has exposed bugs in the LDAS code base that only start
to
become apparent at higher job concurrency rates
Began a rather involved task to evaluate (and possibly) migrate away
from
the standard template library supplied by GNU over to the SGI STL
library
in the public domain known as STLPort. The SGI library has been built
and
passes its unit tests. We are making the necessary changes to allow
LDCG/
C++ libraries to be rebuilt using this library. Once this is completed,
a
rebuild of LDAS will be tested against his library. This precipitated
out
of the continuing problems solving the core dumps in the frameAPI and
the
need to distinguish between bugs we wrote and bugs in other packages
under
LDAS which heavily use C++ code.
One thing the large number of core dumps generated each night (order
10
to
20) has revealed is a bug in our corewatch code used to detect core
dumps
and make these core files available for evaluation under debuggers.
This
bug has now been fixed.
We have migrated to the newest BWidget TCL/TK widget package (version
1.6)
exclusively for the next release of LDAS. This change only effects
the
client side of this API.
Continued to close out open problem reports as we prepare for next
month's
release of LDAS (version 0.8.0) just before the science run begins.
Added the ability for data products in a dataPipeline command to be
directed
to a user specified location on the file system. This was requested
to
allow
the SFT generated by the periodic group to become visible for later
post
analysis within LDAS as they are generated, without the need to move
them
first.
Completed most of our system level tests this week. This revealed a
new
bug
in the putStandAlone command which was isolated to the eventMonitorAPI's
TCL code. This is being fixed and tested this week.
Hardware Systems (Anderson is out this week. Provided by Wilson)
Shannon (LLO)
Most of this week has been spent working with Al Wilson on upgrading
the
VPN at CIT and LLO in an attempt to fix a bug that Igor discovered.
I
hope to have this finished and tested by the end of the week.
Keith (MIT)
received SATA pcraid units
mounted units into racks
repairing failed pcraid unit #3A
receiving cable tray pieces for ldas lab
measuring SATA pcraid power levels
Greg (LHO)
The generation of the intersite S2 PEM RDS has finished at Caltech.
The
data is located under /ide1/pemRDS/S2/ on ldas-archive at CIT. Dan
Kozak
is currently putting the data onto tape, and will send the tapes to
LHO
so that Robert Schofield can do the PEM S2 analysis.
Working with LDAS to identify bugs in RDS generation and test the latest
createRDS scripts. Currently the createRDS process leaves gaps in the
data when the input data crosses directories. LDAS will fix the problem
before S3.
Working with LDAS to plan for the upcoming mini-runs, E10, and S3.
Ben (LHO)
fb3 is being upgraded to Sol9/SAN4.2/QFS4.x this week (starting
September 3).
node46 has passed a 7 day burntest, I will incorporate it into LDAS
September 4.
Replaced drive 8 on the StorEdge 3510 here, September 3. It
reconstructed successfully (there were no global spares configured
at
the
time so it had to be performed manually).
Copied DMT trends from /frame11 to /frame10 September 3. Began
archiving trends September 4 (dual archive set "dmt_trends" HL005[0-7])
Firmware and pld code was updated on the 3510. FW Rev.=1000; pld
Rev.=1000
Hari (CIT)
Working on installing Condor on the remaining 208 nodes in the cluster.
Installed LDR on my PC so I can work on it and get familiar with the
LDR utility.
Installed gsi-opnssh on ldas-grid, so that users can use their DOE
certificates to log into it.
Dan (CIT)
Testing new (2.9a) version of hsi on ldas-archive to see if it's new
features will make retrieving LIGO data from HPSS more efficient.
Started retrieving E7 data from HPSS
Continuing to go thru and evaluate tapes that have failed to label
properly
Migration of data from 9940A to 9940B continues
Read test data from SAM-QFS tape written at LLO
Began copying S2 L1 RDS data into SAM-QFS (4 tape copies, so that the
data can be sent to the observatories)
Worked on planning and prep for new file system configurations at the
observatories
Got new QFS license for LHO frame builder
Had STK replace power supply on one of our 9940B drives
Got STK silo working again after it failed, possibly due to a
bad/misaligned slot
Helped Ben Johnson set up archiving of DMT trends at LHO
Al (CIT)
Setting up the first desktop machines with RH9.0
Added Grid mods to the CIT system. These included hosts table, password
, and user adds.
Working with Shannon on getting the VPN repairs made.
Contacted ASA about getting a new motherboard.
Replaced hard drive in m27 to a 40g drive
Disposed of the old beowulf cluster for test
Data Analysis Activities (Lazzarini)
Creighton:
This week I have been implementing in LAL certain Numerical Recipes
routines to invert matrices and compute eigenvalues and eigenvectors.
These are required in order to lay out a multidimensional template
bank with a flat (constant) parameter metric, as is the case for a
directed pulsar search with spindown.
Mendell:
1) Significant progress has been made in the stack-slide code; the
first
working versions of the code has been written (that just does stacking,
no sliding yet). As always, there are some bugs to sort out.
2) Members of the PULG group expressed interest in using my SURF
student's calculations on parameter estimation. I've been checking
those calculations for errors, and plan to extending the work to make
it
compatible for use with existing LAL code.
Reilly:
Most of my time has been spent debugging the stochastic
DSO. Now that the DSO is parallelized it runs 6.8 to several
hundred times faster than the original. This difference is dependent
upon how many computations are done in the wrapperAPI. In
the original DSO more computations cost equally more and now
more computations add almost insignificantly to the total analysis
time. I have also started working on adding the ability to do
50%
overlapping windows, frequency masking and high pass filtering.
Also, I am in the process of moving the stochastic web archive
cvs repository and email list over to Caltech.
Shawhan:
* Updated conlog to keep track of the names of all filters (previously
it had only kept track of filter names in the LSC servo). This
was in
response to the discovery by Rai that some SUS filter coefficients
had
been
changed during the S2 run, with unintended results.
* Coordinating efforts to fill in information currently missing from
the detector geometry structure in LIGO frame files, and discussing
whether to start using TWO structures for Hanford frames (differing
only in arm lengths).
Weinstein:
- working on burst s1 burst paper final(?) tweaks
- preparing document about burst waveforms to be considered for S2
General Computing (Wallace)
MIT:
(Keith)
-Troubleshot / swapped out drives from mailserver to another sunbox
-Ordering replacement nvram for 'ligo'
-Spec'd out / ordered desktop for postdoc
-Investigating bluetooth wireless
-Patched more Solaris gc machines
Livingston:
(Shannon)
-Working on setting up a SATA raid for storage on GC. This will
be a
small raid (~480 GB) and will serve as temporary and backup storage
as I
shuffle some files around.
-Still finding remnants of the welchia worm.
-Turned off the virus notification of the mail server since it was
sending out hundreds of complaints a day as Sobig.F makes it rounds
on
the internet still.
Hanford:
(Christine)
- Making arrangements for pcard training. Making sure I have
the latest
software, arranging a space, computers, network, etc.
- Continuing to work with Caltech ITS in order to get access to the
site
licensed software. Our computers can now get to the
software.caltech.edu web page, but when trying to actually download
and
install software, our IP addresses are blocked. Still waiting
for word
from Caltech on a resolution.
- Some user support and purchasing of supplies.
CIT:
(Mike)
-Setup the VRVS computer up in SCR and ran a few tests to insure that
the
VRVS system is working. This system is back up and ready for the next
LIGO
seminar via VRVS.
-Over at Wilson Back House, they were having printing problems that
I
took
care of. I also showed them how to troubleshoot their updated printer
and
not to hesitate to call me if they have problems.
-worked on the 3rd floor W/B 4500 printer that had a 49 error on the
control panel and it was also listing a fuser kit had to be replaced.
After
researching HP's tech support website I found that I had to reseat
the
jet
direct card plus reseat the formatter board then did a cold reboot
that
fix
the problem. I also had to swap out the fuser assembly.
-Load a newer computer for Ruth Brambila to swap out her
old computer. I had to get ATC involved with this, in order for Ruth
to
join the Business domain. I also loaded some additional peripherals
and
copied over her old data to her updated computer.
-Loaded three computers with General Computing Software. These computers
are to be used to swap out, some of our window users that have older
computers.
-Ran updated ghost images on all NTSRV's for end of the month
backups. I am now burning these images to DVD.
-Ran security and OS updates on all NTSRV's plus I looked through
security
logs looking for unknown intrusions and system errors, which came up
clean.
(Lisa)
- Fixed an automount problem in 40mars.
- Chased down an infected laptop.
- Looked into the problem of solaris 9 not being able to send e-mail
out via
cronjobs. Sol9 uses sendmail 8.12.x which uses a mail submission
agent
for this
type of task. The MSA gets its configuration from a file other
than the
sendmail.cf. I built new configuration files for use on the solaris
9
workstations.
- Upgraded the firmware on all of the printers.
- Did monthly backups. Wrote new backup scripts for that.
- Put together a list of the software packages that need to be
installed on the
sandboxes. This needs to be reviewed.
- Spent some more time looking into cups (printer service) but I have
not got it
going yet.
- Account maintenance and misc. user support.
(Veronica)
- LIGO website: Updates to various pages. A list of belated Amaldi
presentations was posted. Adding the talks to the LSC meeting database
as
they keep arriving. Updated the roster. Installing security patches
to
the
laptops that I currently have.
Making my way through a webbase tutorial.
- LSC website: An update of the talks to be presented as well as past
talks.
- Project Science: Generated a distribution list for mass mailing
announcements and helped Sydney install and use it. Provided other
user
support. Updated the webpage for the upcoming workshop.
- CaJAGWR website: Usual upkeep.
(Larry)
-Worked with DCC on a variety off issues. There have been some
discussions on
how making sure people are using the correct versions of s/w for
document
submissions. Linda is going to do more work on the issue.
-Placed a number of orders for new laptops, workstations, software
and
other
misc. items. In the process of updating the SUN maintenance contract.
We are
waiting for the new quote.
-Worked on the repair of the ligo web server. It has some disk
communication
problems but that should be resolved when the new server is installed.
-Worked on a number of PC's, updating s/w and related issues.
-Spent time with the ATC people on a couple of PC's that are not working
properly. The plan is now to move those units to another network which
will give
the ATC group more control over those units.
-Spending time with the exit interviews. A number of accounts are being
extended
so the students will be able to continue to work on their reports over
the next
month.
-Setup a couple of PC's.
-Working on a couple of documentation issues. We have a number of web
pages that
need to be updated and the security plan needs to be revised.
-Finished up a number of the regular types of requests concerning
accounts and
e-mail aliases.
-Working with Keith and Shannon on getting more information concerning
SATA raid
systems before we make another purchase of on for GC, next week.
Advanced LIGO Seismic Structure (Larry Jones)
Design/Fab Contract:
Phase I, Value Engineering, was completed with the Value Engineering Reviews held at the three contractors' sites. Some interesting ideas were presented, which will be incorporated into the Design Requirements for Phase II (design and fabricate prototypes for the BSC and HAM chambers). The contractors also submitted proposals for Phase II, along with estimates for Phase III (production). Evaluation of the proposals is scheduled for 9/9, with award of one or two parallel Phase II contracts following.
Actuator Testing and Redesign:
Kyle Ryan finished the second thermal vacuum test of the large actuator on 8/13, this time at 1.0 amp. This is being reviewed by Rich Abbott and Joe Giaime. The vendor Turbo-Jet has completed winding the bobbin from a small actuator with round wire, and has been given the refabricated bobbin without anodizing. We discovered that the purchased square wire had been made with paraffin added for smooth spooling, a common practice. The two spools of square wire purchased for winding will be precleaned to remove this. The "Kapton paint" (actually Cycom 3001 polyimide adhesive) has been received and is being held in cold storage (required to maintain a long shelf life) until Turbo-Jet has been given a purchase order to perform the winding (awaiting a quotation).
Gin Gin
Mark and I reviewed the ITM suspension optic balance. Mark fine-tuned
the pitch of the optic.
Helena and I assembled the structure for the ETM suspension. She'll
be gluing the wire standoff and magnets thru the end of this week. We'll
suspend it at the beginning of next week. I have an e-mail in to John Jacob
asking if they are ready for delivery of the suspensions.
Working with Coating vendors on contractural issues.
From: GariLynn
Billingsley <Billingsley_G@ligo.caltech.edu>
Laser delivery and services installation are on track for a mid-September
start for the absorption test set.
From: Bill Kells <kells@ligo.caltech.edu>
There is now a DCC document describing the transmission
polarization scatter measurements we finished. T030189-00-D.
PHOTON DRIVE R&D
The test of the photon actuation control of the mode cleaner is awaiting
the pump down and commissioning of the mode cleaner.
For additional information about this report, contact sanders@ligo.caltech.edu