|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday August 25, 2003 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
Special Items:
no report
LIGO Weekly Site Telecon (Lindquist)
There was no site teleconference held on Thursday, August 21, 2003.
The list of current actions revised to reflect
the status of open actions assigned through August 7, 2003 may be found
at ACTION
LIST.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
ACTIVITY
Electronic document activity has been busy. Processing of LSC
documents for the LSC Meeting this week in Germany.
| 08/21/03 | Packages | Faxes |
| In | 26 | 25 |
| Out | 12 | 30 |
Press here to access
the DOCUMENT CONTROL CENTER
WEB PAGE.
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA .
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
SUPPORT (Baldon, Lloyd, Tischler)
>Irene Baldon
ADVANCED LIGO (Cost Schedule
Control Systems) T. Frey
From: Thomas Frey <tfrey@ligo.caltech.edu>
Accomplishments:
For list of documents that are being used to develop Adv. LIGO Cost and Schedule, see http://www.ligo.caltech.edu/~tfrey/Cost_MTG_082002/
Project Web Site for posting schedule and progress related data continues to be updated with the latest and greatest.
We are working on three proposals and work plans:
The following change requests are open.
| CR-030015 | FY 2003 Livingston Observatory Detector Maintenance Expenses (Increment) | R. Wooley | July 14, 2003 |
| CR-030016 | Hanford Facilities 2.2--Divide the Large Equipment Access | J. Worden | July 31, 2003 |
Change Request CR-030016 was discussed during the Executive Committee Meeting on August 4, 2003. Three questions were raised:
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
------------------------- H1 -----------------------------
o S2-like angular control of Test Masses restored. The WFS engagement
has been reliable and robust. Main difference is that
all WFSs loops are now closed. The loops are still DC
controlling the
angles and at the S2 laser power level (800mW going into
MC);
o The DC angular control of the Test Masses has proved to be not enough
to handle the laser power increase. For this reason we
began to focus
on increasing the WFS bandwidth. We succeeded to go from
DC control
to 100mHz-1Hz angular control (depending on the WFS) with
no signs
of instabilities or oscillations. Although promising,
we need to test
this new setup at the 2.3W laser power level. 25% decrease
in the
AS_I rms was observed from the S2-like configuration to
the new gain
setup (elog luca 8/18/2003);
o The ISCT4 meat locker is in place and we have enough pass through
clearance between BSC3 and the meat locker to squeeze
through. The
optics table is in place using the damped tripod (24.5")
legs and
spacers. The optic table position was adjusted 2" to the
right from
the drawing layout to accommodate the new periscope. The
periscope
top mirror was raised 2 3/4 inches to make up for the
lack of height
and beam running up hill. The light pipes are installed
and fastened
to the meat locker wall and coupled to the view ports.
The end of
the light pipes have a short bellows connecting them to
the table
enclosure. The PO beams are well center within the light
pipes. The
light pipes have acoustic damping material wrapped around
them. The
table enclosure back panels will need to be modified for
the new
light pipe and wiring perforations The wiring will come
through the
back now. The re-cabling will start today. The rack that
was under
the table now resides out side of the meat locker. I have
received
some of the new 2" Newport and CVI optics to allow us
to start
aligning beam paths. The other Newport 2" mounts ship
Friday (will
not be a show stopper). We can start cleaning all of the
existing
optics and installing the new optics and mounts today.
The periscopes
are installed to a rough position as well. Akiteru made
some new
measurements on the periscopes and the table mounted on
the new legs
prior to us putting the meat locker in place (for comparison).
I am
installing the access card reader on the meat locker tomorrow
as
well. I made up some grouting 'dams' and installed them
around the
tripod feet so we can grout the legs later on. I had the
electrician
hook up the fans and lights with a 30ft extension cord
to give us
access to power. The acoustic materials from E.A.R arrived
yesterday.
I used the 2" wide by 1/2" thick strip foam the seal the
bottom of
the meat locker to the floor. I' still need to call Acoustic
Solutions for the fix instructions on the air intake (they
sent the
insulation materials less the adhesive and no instructions).
We hope
to finish up late Friday. -- D.Cook
--------------------------- H2 --------------------------------
o WFS sensing matrix measured in pitch and yaw; WFS4 is the less
sensitive of all the WFSs, RF gain was increased. For
this reason,
the AM laser characterization of WFS4 may need to be re-visited
(see details vsanni elog 8/20/2003);
o 3 WFS loops closed (pitch only) -- WFS1>dETM, WFS2A>cITM and
WFS3>RM -- in a 'H1 S2-like' configuration (see vsanni
elog
8/21/2003);
no report
Completed dip brazing a first-article of Amit's valve
calibrationfixture
and the work looks fine. Gave the OK to braze the remaining 6.
Have had several meetings with Southern Enterprises of Ponchatoula, Louisiana. This is shop that has received the contract to machine the parts for our hydraulic actuators.
We're hashing out the fine details of production sequence and delivery, using as our target January 9, 2004 to begin HEPI installation in ETM-y. Ed Jasnow is working with us. With our contracts awarded, we're finally able to use hard dates from the various vendors and shops and in spite of the late start a January installation look possible. The long pole in the tent remains machining and assembly of the actuators. Marcel is at MIT and working to complete and check the integration of the actuator with the EPI housing and geophones.
Note from D. Coyne: Although an early Jan start of EPI installation is possible, this schedule has absolutely no margin for problems that are likely to occur. LIGO management and the commissioning directors are aware of the possibility of a somewhat later start of the installation, though early Jan remains the teams goal.
Sander Liu
Finished writing the draft for HEPI electronic design
requirement. Will send it out for peer review before finalizing document.
Ken Mailand
The fluid biological growth test is showing nothing
after 37 weeks.
The assembly of the dummy load network is complete
at CIT, the final design has been coordinated with MIT, to mate-up with
their plumbing.
Waiting on confirmation re. LASTI plumbing.
MIT will modify the pump station base, and install
the part of the plumbing that will mate to the dummy load sub-assembly.
The distribution manifolds [6] are in process all
the longer lead parts have been ordered. The design is for a simplified
single manifold ea.for supply and return.
The manifolds begin welding assembly tomorrow and
will be complete wed. 8-27, the arrival date of the accumulators.
Minutes from previous meetings are available in the commissioning archives
- Updated the end station software for the LHO4k.
This is the faster version of
code developed a few weeks ago. In the process of
installation, it was also
noted that one reason the LHO4k end stations ran slower
(max out at 60usec) was
that the processors were still the older version pentiums.
These were replaced
with new units. With the combination of new software
and CPU, the end station
software is now running at ~45usec.
- Started work on putting ADC/DAC channel overflow
monitors in all control
signals, as requested by Peter, Daniel, and others
a few months ago. This is
similar as to what the LSC ADCs have had for awhile.
The new end station code
installed in the LHO4k yesterday now has this feature.
For each ADC/DAC channel,
there is a counter which reports the number of overflows/sec.
There is then an
accumulator for each optic, which sums all the ADC/DAC
overflows. This
accumulator is only reset manually or automatically
if it rolls over 1 million.
We are now in the process of adding this to the LVEA
suspension controllers.
- MIT had a clock driver module failure in the new
HEPI system. A replacement is
on its way.
- Some more work was done with EPICS on a Linux box.
As a test, a driver for a 8
channel ADC / 7 binary I/O module was added and EPICS
device support written to
allow EPICS records to directly address this board.
This turned out to be fairly
simple and quick to do. What this type of thing would
allow is a complete EPICS
system on a PC (no requirement for VME) making an
inexpensive system for such
things as test systems or replacing some of our auxillary
control VME systems
with PCs.
- In this same vein, an EPICS device support routine
was added to allow EPICS
records to directly connect to the reflected memory
(RFM) network used in CDS
systems. This could allow us to remove some of the
extra software that we have
installed in systems which basically only interfaces
EPICS to the RFM network
data. Since we have limited (1) VME systems in our
development system, this
feature will also allow us to better test RFM connections
prior to installing
new software at the sites.
1. Putting together the equipment and methods
to do a baseline survey of the RFI background. I have ordered parts
to facilitate data taking using our HP spectrum analyzer, and plan on using
a broad band antenna that we have here. The test will take data at
various locations morning and night and repeat all data at least twice
for consistency.
2. Did some research into the type of motor
controller we might order for the pump station. So far, although
I have found some interesting units, they all fall short for one reason
or another. I am starting to feel like the one we have might be the
way to go even in the future.
3. Went over data for implementing the tidal
servo with Brian O'Reilly and am making plans to help him once he returns
from the LSC meeting.
The high power photodetector boards were stuffed and
the photodetector
assembled. Apart from an oscillation out at
about 16 MHz the photodetector
performed pretty much as expected. The photodetector
was operated for a
sustained period of time at approximately 350 mA.
When the light level was
increased beyond about 400 mA, the photodiode substrate
was damaged. A
circular burn mark on the substrate is easily identifiable
along with a
crack in the substrate. The bonding wire was
intact however. Another
interesting observation is that it appears that there
was some vapour
inside the photodiode, as there is evidence of condensation on the window.
The MC1 and MC3 baffles are being re made to eliminate any possibility of the beam striking a wire when the baffle is rotated at a high angle to the SOS. The baffles will go into the high temp bake this week, the final outside service.
I put in words some results I obtained by simulations,
that are related to the
"multi-modal" nature of the electromagnetic fields
and more specifically to
the different composition of carrier and sideband
light. The conclusions have
been included in the proceeding regarding the presented
poster at the Fifth
Amaldi Conference. Although I have been doing simulations
for both H1 and L1
with all the as built parameters, I reported and commented
the results for H1
which can be summarized as follows:
|
Physical mechanism
|
Effect in the SB resonant curves
|
Possible cure
|
|
Different optical gain
|
Different maximum SB amplitude
|
ASI Servo (DS)
|
|
wrong "effective" l+
|
The peaks are split but SB are h.c.
|
Demod. phase
|
|
Different Gouy phase
|
"Common" off set for the two SB
|
No cure
|
Of course all the above are not independent. As far
as the two output channels
are *perfectly* separated, the fact that the SB experience
different losses
does not have an influence on the signal demodulated
in quadrature, since the
phase difference between the carrier beams coming
from the two Fabry-Perot
combines with the average SB amplitude. If the carrier
contrast is not ideal
the signal demodulated in phase is non zero when the
SB amplitude is
different. There can be many causes for the SB having
different maximum peaks
but basically we can adjust l- to make their losses
equivalent and restore
balance ... BUT this has an effect on the carrier.
In principle there is no problem if l+ is not exactly
3/4*lambda_mod. Actually
even using this ideal value the SB are still complex
conjugate because of the
Schnupp asymmetry: in the symmetric combination of
l1 and l2 the amplitude of
the SB beams travelling along the two branches also
counts. All the mechanisms
work exactly the same other than the SB are not at
their maximum power and the
phase between ASI and ASQ must be appropriately adjusted
to maximize ASQ.
When the interferometer is cold the mismatch between
the carrier and the
sidebands is significant enough they really experience
a different round-trip
phase w.r.t. CR. Since this entails a common phase,
the real and imaginary
part are mixed and part of the carrier light
due to a bad contrast
contributes to ASQ.
In this case ASI=0 and in order to check my calculations
I ran
a few simulations, with increasing differential losses
in the two arms.
As a result ASI was zero and ASQ was not but unfortunately
I was not able
to squeeze those data in the proceeding. This problem
seems to me the most
important one as the interferometers behave like they are always cold.
The WYKO 6000 surface measurement interferometer shipped
to Tucson for upgrade and repair.
Lee Cardenas, Liyuan Zhang
OTF Lab. (W. Bridge)
Contamination Cavity # 1
We took out the Aluminum wire spool for the OSEM.
Results from the plots for absorption, ring down and
thermal lensing will be released (Dr.Zhang)
Cleaned mirrors installed, alignment, mode match done
and cavity is locked.
took ring down and beat frequency measurements for
base line.
We introduced a new sample "PEEK" wire spool four
of them.Cavity is locked again and
took our first
ring down measurement which it shows no change so
far.
· Another sample collected. Solder joints for
the OSEM assembly is in preparation as more samples needed.
Absorption Test Measurement prototype in standby (
New laser coming soon?)
We completed the measurements for the surface birefringence
(polarization rotation) of the sapphire- B crystal
substrate.Full
scan result of the sapphire-B shows to be very consistent with our previous
result.
Please seeDr.
Zhangsset-up, calibration, and full
scan results plots.
It is pumping with two new mirrors from REO . The
most recent ones.These mirrors were
cleaned (Helena)
The previous two had higher beam scattering so we
could not use them.
All these efforts
are in progress.
Cavity #2 Test cavity in STANDBY.
We will be installing a new cavity with cleaned mirrors
as soon as we learn from the other cavities.
no report
no report
Simulation and Modeling (Bhawal)
--------------------------------
Wave Front sensor
-------------------
(Biplab)
Working with Luca to understand the behavior of WFS loops
especially if the gains are increased. It was observed that H1
(real IFO)
goes out of lock if the power is increased without increasing
the gain.
Code development and maintenance
---------------------------------
(Melody)
- Continuing e2e source code modification to dynamically create
C++ source from FUNC_xxx equation modules, which would
be compiled,
combined to a shared library, and used during runtime
execution.
Alfi
-----
(Bruce)
Continuing work on bundles and bundlers in Alfi (PR 272.)
LIGO Data Analysis System
-------------------------
LDAS Software Systems
---------------------
(Blackburn)
The LIGO Data Computing Group Toolset (LDCG) was upgraded on several
of
the standalone LDAS systems and on the tandem (dual server) system
with
the GCC 3.3.1 compilers. Once this was accomplished, the version of
LDAS
on these systems was rebuilt to also be based on GCC 3.3.1. Only a
few
files had to be modified to be compliant with the stricter ANSI/ISO
standards imposed with this compiler. LDAS was then tested on these
systems and found to run as reliable and slightly faster than with
the
previous GCC 3.3.0 compilers. The LDAS-DEV system will be upgraded
by
the end of this week to be based on this GCC 3.3.1 compiler set.
A performance comparison of three candidate platforms used to run the
LDAS metaServerAPI and the DB2 database server was carried out this
week in order to pick the best hardware platform for the next science
run. The comparison was between the old Sun 4 CPU server, a new faster
2 CPU server from Sun, and a dual CPU Intel server. Two different classes
of tests were performed. The first suite of tests challenged only the
metaDataAPI and the database server. The second test suite was our
"real
world" nightly dataPipeline/metadata access and insertion tests. The
dual Intel server won in all categories by a factor of 3 to 4 over
the
original four CPU Sun server. The newer dual Sun server came in second
place being about 1.5 times faster than the original 4 CPU Sun server.
We are now performing longer term tests of the dual Intel server under
heavier loads to get a better understanding of the issues associated
with running our database server under Linux.
We have upgraded our MPI distribution to the newest LAM version 7.0.
Testing has been carried out on the same set of servers that the new
GCC 3.3.1 compiler was tested on and will be migrated onto the LDAS-DEV
system later this week. Preliminary tests indicate that this version
of
LAM is more stable and reliable than the previous release, resulting
in significantly fewer jobs failing in the MPI layer of LDAS.
It does
continue to have a memory leak issue under single server configurations.
It has not yet been tested to determine if it generates the network
packet storms seen on large clusters.
An issue was discovered (or probably rediscovered) involving blocking
sends of data between the frameAPI and the dataConditionAPI in a bi-
directional mode this week. Code is being developed and tested to
attempt to handle this condition.
Continued to improve documentation for various LDAS webpages.
Continued to read C++ code in search of poorly implimented use of
container methods.
Began development of an interface in the controlMonitorAPI and functionality
in the managerAPI to allow any LDAS user to have their account temporarily
blocked with unattended open loop scripts are causing distructive behavior
on an LDAS system. This is based on experiences during the previous
science
runs and originated with a request from Greg Mendell.
The process coredump monitoring software (corewatch) was modified to
allow
it to correctly monitor and manage coredumps that are very close together
in the LDAS system.
Began evaluating the new BWidget TCL/TK package version 1.6 for inclusion
in the next release of LDAS. This package is used by the controlMonitorAPI
and has several nice bug fixes in it for us, but also has changes to
its
interfaces which will require code changes in our code to make compatible.
(Charlton)
This week I have continued to work on the software for creating reduced
data in S3 and the future. It should be ready for initial release at
the
end of the week. Things added since last time were:
- ability to handle errors in LDAS jobs
- ability to handle LDAS outages
- status information that can be monitored via the dsorun web
page (used
in the control room)
- extended logging information
- graphical representation of raw and reduced data
LDAS Hardware Systems
---------------------
Caltech
-------
(Dan Kozak)
Trip to LLO:
* Put 2Gb FC HBAs in metaserver and dataserver.
* Installed SAN 4.2 on gateway, metaserver & dataserver.
* Hooked up 2Gb FC switch to hosts, STK 9940Bs, L700, T3s, 3510,
framebuilder.
* Configured SAM-QFS on dataserver to use 9940Bs/L700.
* Set up new framebuilder (SunBlade2000) with SAN4.2, standalone
QFS 4.0.
* Installed new firmware on 3510.
(Hari Pulapaka)
* Installing of Condor: Setting up condor took quite a bit of time,
I had to
spend a lot of time debugging condor. The main head node had
2 interfaces
and somehow the nodes were not able to connect to the head node,
so I had
to setup a private domain group for the private subnet. So,
now the nodes
in the pool can connect to the head node but job submission
is still
creating problems.
* I was also looking after the transfer of files from UWM using LDR.
The
transfer was completed today, but it crashed many times earlier
and I had
to debug and restart it many times.
* I was also getting myself familiar with the LDR code in python.
(Al Wilson)
* Setting up RH9 for kickstart installation.
Have a core set of rpm's and working directory. Testing is going
well.
Should be ready for beta by weeks end.
* Sent files to MIT for the beowulf nodes. Will help Keith with the
installation.
(Stuart Anderson)
* Solved problem with incompatible firmware inside one of the 3510
RAID
units and as a result upgraded all 10 units at Caltech.
* Successfully created a single 10TByte file on the new SAM-QFS disk
cache (built out of 8 3510 units).
* Helped Paul Armor at UWM to get LDAS-0.7.0 running on the Medusa
cluster.
* Started testing Solaris9 Maintenance Update 4 with its support for
larger than 1TB storage devices.
* Started testing motherboard BIOS upgrade for P4DL6 systems used for
the 5 standalone software development machines and the IDE-RAID
servers.
MIT
---
(Keith Bayer)
* Installed LHO foundry switch at MIT.
* Set IP addresses on foundry switch's to 10.11.254.252 and 253.
* Installed SysKonnect cards into new datacon/beowulf nodes.
* Received gigabit cards and fiber patch cords from Caltech.
* Troubleshooting failing raid drive on pcraid#3.
* Monitored cluster node with watt measuring tool.
Livingston
----------
(Igor Yakushin)
* Two T3 disks failed and have been replaced.
* Dan Kozak is visiting LLO to configure the tape robot, fiber channel
switch, 3510, fb2. Tape robot is configured, however, one of
the drives
seems to have some problems: it writes data 200 times slower
than other
drives. I called StorageTek: a technician should come this Friday.
fb3
is configured to use LDAS' T3s, however, it is running Solaris
9 (to
work with T3s correctly, the current fb2 is running Solaris
8) which has
not been proved yet to work with CDS software and hardware;
once it is
proved that it works, fb3 will replace fb2. 3510 firmware upgrade
is in
progress. Servers, T3s, taperobot, fb3, 3510 are using now the
new fiber
channel switch.
* Upgraded firmware on the new gige switch.
* Tested VPN connectivity from MIT to other sites. It works fine to
LLO
and LHO but I observed the same problems from MIT to CIT as
from all the
other sites to CIT. With the existing network problems it is
impossible
to use the central metaserver (as well as ldas-cit's metaserver)
at CIT
through VPN. We are going to take another look at this tonight
with
Shannon.
* The new AC has been installed in LDAS room last week and seems to
work fine so far: I have been running very heavy load on LDAS
during the
weekend to test how AC can handle it. Some time next week the
remnants
of the old AC will be removed and hopefully LDAS room would
get back
into an ordered state.
Hanford
-------
(Ben Johnson)
* Reconnected the LDAS room temp monitor computer to the CDS network.
The box is a standalone SparcStation 5 which sends the LDAS
room
temperature into the CDS EPICS system.
* Working with Dave Barker on how to allow CDS-side NDS users to have
longer and efficent data lookback during S3 (lookback longer
than 6-12
days).
* Set IPaddr for the one 3510 at LHO to 10.10.35.10 . It is on
the
same network as the T3's and 64-port FC switch (storage network).
* Begun process of moving the 10.10.x.y network over to dataserver.
I
can now telnet from dataserver to any device on the storage
network. I
still need to install the SUNWesm (Enterprise Storage Manager
software)
to capture the T3 logs on a regular basis.
* Continuing work on data archiving scripts for S3.
Data Analysis Activities
------------------------
(Creighton)
Finally managed to generate good all-sky pulsar search template meshes
for short (day-long) integrations, and started checking the code on
longer (month- or year-long) integrations.
(Yakushin)
Debugging parallelized version of waveburst.
General Computing (Wallace)
---------------------------
MIT:
(Keith)
- Troubleshot / reinstalled windows pc
- Working on wireless channel interference with PSFC
Filesystem backups migrated to new SCSI drive
-Patching Sun machines
Livingston:
(Shannon)
- This week can be summed up as spending all of my time on windows
worms and viruses. Blaster, Welchia and SoBig.f@mm
Hanford:
(Christine)
- On vacation and out sick most of last week and Monday of this
week.
- Came in off my vacation for a short time to work with Ed Chargois
who
was on site to dispose of all of our broken or excess
computer
equipment.
- Continuing to work with Larry to get access to the Caltech
ITS
software site. Our IP addresses are blocked by Caltech.
I am not able
to get access to any of the site license software.
- Working with Larry and Carol Wilkinson to get software from
Caltech
that Carol needs in order to do her job.
- Helped Carol set up her modem to use her account on the 800
line at
Caltech.
- Helped a few users clean up their PCs after the worm and virus
attacks. One user had several trojan software programs
running on his
PC.
- Working on Otto's computer to resolve a problem where some
programs
are unable to run properly. At this time it appears
the problem is due
to some accessibility settings that Otto needs.
- Resumed work on the network upgrade problem. I've contacted
PNNL
again with the status of my most recent testing.
Last I heard from them
someone was trying to come up with some e2e performance
testing tools as
they have nothing at this time to test with.
- Continued working with Larry on whether he bought tech support
for my
Cisco router and if so what is the support contract number.
Larry is
sure he bought the tech support, but can't find the contract
number. He
will continue to investigate and get back to me.
As soon as I have a
contract number from Larry I can open a case with Cisco
tech support for
help on the router.
- I have opened a case with Cisco tech support for help configuring
my
internal switches. I have 8 a.m. to 5 p.m. next
business day telephone
support for my switches.
- Installed some software required by Biplab for e2e.
- Will be installing a gige interface card on the cisco router.
- Resuming the install of the Calcium calendar on our web server.
CIT:
(Lisa)
- Spent a large chunk of time working on windows security issues
and viruses.
The mail server has been blocking most of the latest virus
attack from the
end user. Still, there are a lot of error messages
to read through.
- Working in the 40m. Started a todo list with Lisa Goggin
of what we will
need to get accomplished in the next few weeks.
I think I finally have
the ntp issue resolved, but this doesn't get tested often,
so the feedback
is minimal.
- Still working on a problem from last week. ITS blocked
port 135 at our
router but some of the purchasing people need that port
to get their e-mail
from the ATC server. This is still unresolved.
- Reprogrammed the wireless access points many times. When
submitting mac
address, please be careful to get the correct address
for the wireless card.
Folks have been sending in lan addresses by mistake.
- Installed quite a few software packages on the server that
will replace
canopus.
- Began working on a new template to make the GC internal web
pages pretty.
(Mike)
- Setup and installed an HP5000n printer in the 40M and removed
their old
printer that was giving them a lot of problems.
- Worked on a PC that was having problems with the Operating
System. It
turned out that this computer had multiple viruses that
I was able to clean.
This computer is back up and running.
- Moved and setup in Wilson House the new HP5500dn color printer
from the
40M; this included programming and loading printer drivers
on existing
workstations to connect to this printer.
- Went all over to update all computers with OS & Security
Patches.
- Worked on updating a few laptops software & OS/Security
for the loaner pool.
- Started loading a new IBM laptop with General Computing software
and
setting up security settings. This has a built in wireless
card that is
giving me some problems that will require me to contact
IBM tech support on
this.
- Finishing up loading a new Dell workstation to replace the
VRVS system
up on the third floor of W/B. This includes loading all
General Computing
Software plus VRVS. I am also testing & optimizing
VRVS settings.
- Worked on a scanner for DCC. I swapped out the Automatic Document
Feeder
that had been not working. I had another scanner that
was not functioning
correctly but ADF seemed to be working just fine. I swapped
this out but
hardware still needs to be tested.
- This week I had a lot of software, e-mail, viruses and networking
issues
that kept me real busy this week.
(Veronica)
- LIGO website: Posted the latest newsletter. Posted updates to various
pages. Installed a webpage for the LSC August meeting's transparencies;
posting them as they arrive. Posted a local copy with all supporting
files
of a press release for MIT per David Shoemaker's request.
Installed and updated a webpage for S1 papers.
Tracked down what appeared to be a glitch with the roster database.
What
seemed like a loss of data turned out to be due to an inadvertent
switch
to an earlier copy. I restored the data so that it is now up-to-date.
Assisted Ed Chargois in recovering data for one of his databases.
This
included installing a copy of data recovery software and repopulating
a
new database with data from another application. It appears
to be working
now.
Thomas Frey has requested that I take over management of the
roster and
costbook databases. This will include maintenance, updates,
and occasional
design tuneups. Since I am already familiar with the roster
db's
architecture and front ends, I am looking into the costbook
database
layout.
Minor assistance to Cleveland in setting permissions for some
docs in
/docspublic/.
Videotaped the last seminar. Set up and monitored the VRVS webcast.
Captured the video, encoded, and posted for streaming. Made
a CD for the
Moscow U. group with the downloadable copies of the video in
various
formats. Assisted Sergei Vyatchanin and Farid Khalili in transferring
and
converting their files. While at it, updated virus software
on the laptop
that I loaned for them.
Addressing an issue of posting an update to the LLO website.
Looked up
animations for Tom Lucatorto. Preparing a high-resolution copy
of a
Hanford aerial.
M82 seemed to had been hit with a virus again. I 'cleaned' it
about 2
weeks ago and keep checking it almost daily.
- LSC website: Posted various updates (most notably, S1 Author List
and
Acknowledgment of Support).
- Project Science: user support.
(Larry)
- Wrapped up a number of procurement items. This included making
new purchases
for various people. Started working on the SUN maintenance
contract renewal.
We will be including some LDAS equipment but with the
new person we are
working with at SUN we should have everything worked out
in about a week.
- Supporting DCC on different fronts. It appears that Linda Turners
computer
had some major problems, so we will be doing a little
more on this end in
trying to get the LSC items posted.
- Spent some time going over things Christine needs for the Hanford
site. They
still are not on the list to access s/w at Caltech. The
software people were
not aware the problem had not been resolved some weeks
ago but assured me
they would make sure it would be done today.
Started contact with Cisco to find out the contract number
on Christine's
router. The contract was to be mailed to Christine since
she was put down
as the contact. We now have a new sales rep. so I am going
through the hoops
again to get the information we need.
- This latest round of viruses is hitting everyone pretty hard.
Keeping the
machines up to date with patches and antivirus definitions
is really taking
up a lot of time. So far we have been fortunate and not
had any major
problems here at LIGO CIT.
- Working on a number of document issues.
- Setup a number of accounts and checked out a couple of SURF
students that
are returning home. Regular user support has also been
a time consuming
activity this week as well as trying to catch up on things
left over from
last week while on vacation.
From: Catharine Stebbins <stebbins@caltech.edu>
Observatory website redesign:
1. Have contacted Shannon Roddy about transferring Livingston site
files.
2. Development of logos/graphic design for both observatories progresses.
Expect to have working examples for review in early September.
We are setting up a meeting with Physical plant to plan installation of water and power service for the 30W laser which will be installed at the scanner. Shipment of the laser is promised September 4th.
Downselect
Sapphire homogeneity was measured along the
a and m-axis of a single material sample. A-axis material
was found to be significantly more homogeneous than m-axis material. LIGO-T030177-00.
PHOTON DRIVE R&D
Tom Essinger-Hileman has aligned an
optical system with 4 bounces from the MC2 mirror. He presented his SURF
talk, and has completed his SURF program.
Aidan Crook is staying an extra week and will
test the photon actuation control of the mode cleaner after it is locked.
Simone:
Ive completed the XRD scan of the MoRuB
just splatted. Some samples [b=15,16,18]
present an unidentified small crystalline peak around 25 deg in 2theta
scale. Bill told measures on samples could be done for it should be less
than 1% crystalline. Spent the rest of the week
visiting LIGO site in
Hareem:
Consulted Numata-san about the Borlan
builder issue and am waiting. Also preparing to
leave.
Allyson:
Final week. Finishing hardness measurements.
Charles:
Very short week because of the
Francesco:
Me and Charles worked on the stress-strain machine, mainly to understand
how we can use the PID to control the heating of the central rod.
The first simulation from ANSYS for the strain energy of the joint reveals
that the analytical formula is correct for the joint at rest, but not for
the bending. The simulation shows that the strain energy for the ending
is linear with mass, my my formula is mass
independent, so I have to understand what's wrong. I borrowed from the
library two books on elasticity for this purpose. That's all, on thursday
I went to
Greg:
Continuing to prepare samples to test mechanical properties (Youngs
modulus, stress-strain). Beginning work on report.
Xavier:
Finished simulations. Starting to work on my
report.
For additional information about this report, contact sanders@ligo.caltech.edu