Weekly Report for Week Ending August 14, 2003


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
Adv. LIGO Development
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  August 18, 2003 will be:
 

  •  CANCELLED DUE TO LSC MEETING


  • Special Announcements:


    Weekly Report Highlights
     


    LSC Issues (Saulson)


    August 15, 2003

      I am pleased to be able to inform you that two papers related to the LIGO S1 run are now posted on the gr-qc archive.

      The paper describing the LIGO and GEO detectors during S1 can be found at

    http://www.arxiv.org/abs/gr-qc/0308043  .

      The paper describing the LIGO/GEO upper limit work on periodic signals can be found at the same site, with number 0308050.

      Please make this information available widely. ...

      We will inform you when the other S1 papers are posted. ...
     

    Best regards,
    Peter Saulson
    Spokesperson, LIGO Scientific Collaboration
     


    LIGO I Construction/LIGO Laboratory Administration (Lindquist)


    LIGO Weekly Site Telecon (Lindquist)

    A site teleconference was held on on Thursday, August 14, 2003.  The following issues were discussed:

    Budgets--Projections indicate that the Project will spend about $31.4 million this year, leaving a carry over for FY04 of about $7 million on a cash flow basis.

    The FY04 budgets for the sites have not yet been set.  Both Fred Raab and Mike Zucker are reviewing the site budgets to definitize them.  The Work Plan is due to the NSF August 31, and the current fiscal year ends September 30.

    Civil Construction--There is an indication of activity on the glass vestibule for the LHO Laboratory, but no visible signs of progress. Ed Jasnow indicated that the final invoice, which is construction dollars, will not be paid until the vestibule is complete.  John Worden indicated that he will contact Chervenell Construction.

    Personnel (Visas)--Ed Jasnow will distribute his e-mail on the new interview process for visas to the sites.  Foreign nationals on the LIGO staff are urged to allow sufficient time for the interview when they arrive at the airport to return to the U.S.

    Hanford Facilities--The issue regarding the assumption of Otto Matherny's duties was discussed.  Otto is on a permanent leave of absence until May 2005, at which time he will retire.  Although John Worden will assume most of Otto's duties, Fred Raab brought up the issue of having to provide a licensed water purveyor to satisfy the requirements of the Washington State Department of Health.  Otto had been grandfathered in when the new rules went into effect two years ago, but planned on taking the required courses and test by February 2004.  Since he is now on a leave of absence, the question was raised regarding filling the role.  It was suggested that Fred and John contact the Department, explain the situation, and follow their advice.  In the meantime, Fred should designate two people to take the required five courses and the license test in February.

    P-cards--P-card training for LHO will take place on Tueday, September 16.  Ed Jasnow and Criselda Rodriguez-Brodeur will participate in the training.

    Weber Bar Display--Fred Raab and John Worden are investigating raising the Weber bar display a few inches to make the base more finished.
    The list of current actions revised to reflect the status of open actions assigned through August 7, 2003 may be found at ACTION LIST.


    PROPERTY MANAGEMENT (Chargois)

    From: Ed Chargois <chargois_e@ligo.caltech.edu>


    DOCUMENT CONTROL CENTER (Turner, Mak)

    >From: Linda Turner - turner@ligo.caltech.edu>

    Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

    ACCOMPLISHMENTS

    > From: Cleveland Mak <mak_c@ligo.caltech.edu>

    ACTIVITY
    Scanned a handful of documents for electronic access.  Over 100 electronic documents were submitted during this period.  Organized and sorted documentation.
    .
    08/14/03 Packages Faxes
    In 21 23
    Out 16 24

    Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


    COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman, Salone)

    From: Esther Cunningham <esther@ligo.caltech.edu>

    Press here for ACCOUNTS PAYABLE HISTORY DATA .

    From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

    From: Gina Salone <gsalone@ligo.caltech.edu> From: Florence Kaufman <fkaufman@ligo.caltech.edu>
    SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

    From: irena@ligo.caltech.edu (Irena Petrac)

    From: Ed Jasnow <jasnow@ligo.caltech.edu>

    SUPPORT (Baldon, Lloyd, Tischler)

    >Irene Baldon

    >Dorothy Lloyd >From: Ryan Tischler <rtischle@ligo.caltech.edu>

    ADVANCED LIGO (Cost Schedule Control Systems) T. Frey
    From: Thomas Frey <tfrey@ligo.caltech.edu>

    Accomplishments:

    For list of documents that are being used to develop Adv. LIGO Cost and Schedule, see http://www.ligo.caltech.edu/~tfrey/Cost_MTG_082002/

    Advanced LIGO Request
    Cost Book Tool.
    Development of the Advanced LIGO Project Controls Guidebook continues.

    Project Web Site for posting schedule and progress related data continues to be updated with the latest and greatest.


    Reports (Lindquist)

    We are working on three proposals and work plans:

    The focus now is to prepare budgets for FY 2004 Operations.

    Change Control/Contingency (Lindquist)

    The following change requests have been distributed Executive Committee for possible discussion July 28, 2003.
     
    CR-030015 FY 2003 Livingston Observatory Detector Maintenance Expenses (Increment) R. Wooley July 14, 2003
    CR-030016 Hanford Facilities 2.2--Divide the Large Equipment Access J. Worden July 31, 2003

    Change Request CR-030016 was discussed during the Executive Committee Meeting on August 4, 2003.  Three questions were raised:

    Current direction is to put this item on the liens list.  Sanders and Barish will view the facilities during the next site visits.  Notes from the discussion will be published.

    Human Resources (Akutagawa)

    From: Cindy Akutagawa <cindy@ligo.caltech.edu>


    Quality/Safety (Tyler)

    >From: Bill Tyler <tyler@ligo.caltech.edu>



    LIGO Hanford Observatory (LHO) and Interferometer Operations (Raab)


    Summary of Commissioning Activities at LIGO Hanford Observatory
    (compiled by M. Landry)

    The week opened with decent locking on both interfereometers, however, events knocked both machines offline for some time.  The 2k POY beam was improperly dumped, resulting in a shuttering of the beam for several hours on Wednesday.  The 4k was downed for most
     of Wednesday due to REFL EO shutter stuck in the LO state, but reporting HI.  Despite these events, commissioning continued apace:

    Work on the mechanical resonances and acoustic coupling on the output ports produced serveral interesting results this week.  A comprehensive report on mechanical testing of the new ISCT periscope design was elogged here .  Findings include that the new periscope reduce rms motion by nearly a factor of two in the 100-600Hz band, and that damping can reduce the periscope peak by a factor of five.  A second report noted the reduction in 4k acoustic coupling by an order of magnitude since S2.  This is thought to arise from the removal of limiting aperatures such as an EO shutter and associated small polarizers.  Lastly, the meat locker enclosures were assessed regarding acoustic suppression.

    2K IFO

    Refl work included an EO shutter alignment, which has a handy reference elog for future alignments.

    The 2k WFS characterization work continued, this time on WFS3 .

    The 2k MC developed angular instabilities associated with higher power and a new alignment.  The ISS servo is in better shape after some debugging .

    4K IFO

    An ASI servo has been commissioned for the 3rd antisymmetric port photodiode, as described here .  However, the new servo had the deleterious effect of introducing broad line features at 1.445kHz and 2.98kHz (unseen in ASQ spectra yet, given the frequency noise).  Gains were reallocated between AS2 and AS3.

    A calibrated displacement spectrum corresponding to a 4k inspiral range of 1.5Mpc was posted on the weekend .

    A photon calibrator was installed in the x-end station.  A peak is seen in DARM control at the expected frequency of 113Hz as the laser modulates the cavity length.  A rough calibration compares well with a previous spectrum

    A new mode cleaner board was installed on the 4k.


    LIGO Livingston Observatory (LLO) and Interferometer Operations (Zucker)


    no report


    Detector/Technical Support (Coyne)


     
    see also the Revision Technical Review Board (RTRB) status here

    Seismic Upgrade Project

    Jonathan Kern

    At Parker's Hydraulic Valve Division last week, and was given an

    hands-on introduction to the manufacturing and assembly of the

    proportional valves controlling the HEPI actuators.  Broached the

    possibility of providing Parker with one of LIGO's calibration manifolds

    so that they might deliver properly calibrated valves to us.  They are

    quite receptive to the idea and I am working to complete a fixture for

    them ASAP.  Received and QC'd 7 sets of test manifolds from Digital

    Machine and parts have been sent to a dip brazer in Houston, Texas.

    Checking with vendors of purchased catalog items for HEPI, to make

    certain that our orders have been received properly.  Received a

    SolidWorks model of a proposed geophone mount from Stanford, from which

    I will manufacture 2 mounts for the LASTI HEPI HAM. We've received

    approval from the NSF to contract for the manufacture of machined parts

    for 96 hydraulic actuators.  With this approval I was able to meet with

    the awardee and this morning I met with them and went over the order in

    which we'd like to receive the machined parts.  The shop will place

    orders for material immediately, and prepare a production schedule.  I

    expect to have a preliminary delivery schedule by the end of this week.

    Also meeting with us was the awardee of the assembly contract.  Ken

    Mason completed a round of updates on the EPI housing.  DCN approved

    here and forwarded to Stanford.  Likewise updates made to the actuator

    model and these sent to Stanford for approval as well. 

    The seismic retrofit has captured the interest of Parker and Claude

    Mixon, a Senior System Engineer based in New Orleans came to visit this

    afternoon.  In part to learn about our installation but also to offer

    their experience should we need it.  In particular he hopes to provide

    us with helpful advice in the care and treatment of the aqueous mixture

    we'll be using at LLO.

    Ken Mailand

    The fluid biological growth test is showing nothing after 36 weeks.

    The assembly of the dummy load network is in process at CIT, the final design has been coordinated with MIT, to mate-up with their plumbing.

    The finished assembly should ship out tue.8-19.

    MIT will modify the pump station base, and install the part of the plumbing that will mate to the dummy load sub-assembly.

    The distribution manifolds [6] are in process all the longer lead parts have been ordered. The design is for a simplified single manifold for supply and return.

    The manifolds require some machined parts, and welding, they could be ready by the end of next week, pending the arrival of the accumulators.

    Rolf Bork

    Alex and I are at MIT this week to install a prototype LIGO-style HEPI

    control system. 

        - Installed L4C interface chassis, Anti-aliasing chassis, and output

    driver chassis and connected associated power. Power is derived from the

    previously installed SOS +/-24VDC and +/-15VDC power supplies. We also

    installed new +/-5VDC to drive the AA chassis. Connection is via fuse

    blocks in the SOS rack.

        - Tested system by injecting signals at L4C chassis and tracing

    through output driver. All hardware and software tested satisfactory. At

    the end of yesterday, we connected the signals from MEPI and the signals

    appear to be correct. 

        - Added the new HEPI channels to DAQ and verified DAQ and GDS

    operation, including excitation/test points and transfer functions. Note

    that actual filters still need to be loaded into the system as derived

    from the DSpace system.

    Sander Liu

    Completed building a new low noise L4C pre-amplifier prototype. In the process of studying the effect of component variation on the performance of the pre-amplifier.

    CDS

    see also 8/13 weekly CDS meeting minutes in the commissioning archives:

    CDS Software

    Rolf

    Issued a memo to the LSC (L030119-01) alerting the data analysts to the fact that there is a (recoverable) error (swapped samples) for some of the S2 data channels.

    CDS Hardware

    Rich Abbott reporting

    1.  Worked with Gabby on solving a signal inversion problem associated with the wavefront sensors.  The problem was most likely caused by a poor connection to the input of the Pentek 6102

    2.  Working with Rusyl on the choice and testing of RFI feed throughs.

    3.  Worked with Peter King on diagnosing the apparent multi-mode operation of the laser.  Noted that the transfer function of the phase correcting EOM in the FSS varies significantly as a function of the slow actuator voltage.  Much of the unstable performance could be attributed to the change in phase of this transfer function.  I have no idea as to how the slow actuator communicates with the phase correcting EOM, but we will look more tomorrow.  It is not unusual for things like this to be a red herring and simply attributable to something else.

    Ben Abbott

    The stands and boxes for the ISS PDs are finished being fabricated, anodized and silkscreened.  I will go and pick them up on Friday.

    PSL

    PeterKing

    The high power photodetector boards have come in from PCBExpress.

    I tried a different a different beam pointing servo configuration,

    incorporating a high voltage amplifier to drive the PZTs.  Unfortunately

    the bandwidth was limited by a ~300 Hz mechanical resonance in the mirror

    mount.  The peak-to-peak fluctuations were reduced from +/- 0.25 mm to

    about 0.005 mm

    Errant Beam Blocks

    Ken Mailand

    The MC1 and MC3 baffles are being re made to eliminate any possibility of the beam striking a wire when the baffle is rotated at a high angle to the SOS. The baffles will go into the high temp bake next week the final outside service.

    Optical Metrology

    Lee Cardenas, Liyuan Zhang

    OTF Lab. (W. Bridge)

    Contamination Cavity # 1 

    We took out the Aluminum wire spool for the OSEM.

    Results from the plots for absorption, ring down and thermal lensing will be released (Dr.Zhang)

    Cleaned mirrors installed, alignment, mode match done and cavity is locked.

    Visibility is ~ 60%improvement on mode match and alignment in progress in order to get

    the cavity visibility needed (~ 85-90% ) for ring down and beat frequency measurements.

    ·New test sample PEEK wire spool for the OSEM is ready and it will go in as soon as the cavity is ready.

    ·Another sample collected. Solder joints for the OSEM assembly is in preparation as more samples needed. 

    Absorption Test Measurement prototypein standby ( New laser coming soon?)

    Scatterometer system 

    Complete Modification in Progress. Continue meeting with Mike Gerfen to coordinate new base design

    (Main shop) to hold the new Sapphire ITM mirror (~13" dia. X ~7 3/4 thick).

    The new optical train plate for the RTS scanner is completed with some other modifications that has been done as

    to accommodatemirror base design and fabrication is in progress.

    Modification of the base holder to adapt a rotating base for the 6"Dia. X 3" thick Sapphire mirror is in progress right now.

    This sapphire mirror substrate is under test for its surface birefringence (polarization rotation).

    OTF Lab at Lauritsen ROOM 38

    Cavity #3 

    It is pumping withtwo new mirrors from REO .

    mode match completed and alignment completed and cavity is locked.

    cavity visibility is ~55% so far. We find out that these mirrors have higher beam scattering,

    therefore, We can not achieve the cavity visibility desired (~85-90% )

    We will change the mirrors again. this time we'll use the new REO mirrors that Helena Armandula ordered,

    and cleaned them.All these efforts are in progress.

    Cavity #2 Test cavity in STANDBY.

    We will be installing a new cavity with cleaned mirrors as soon as we learn from the other cavities which set of mirrors

    we'll need to install.


    40 Meter Interferometer (Weinstein)




    Thermal Noise Interferometer (Libbrecht)


    no report


    LASTI


    no report


    Data Analysis and Computing (Lazzarini)


    Simulation and Modeling (Bhawal)
    --------------------------------

    FFT Studies
    -----------

    Raghu and Hiro made a good progress in developing the algorithm and
    code to extend the limited measured area (15cm diameter) to the full
    mirror map (24cm diameter). The test of the algorithm was done using
    smaller region (10cm) to see if the outer are (10 to 15cm region) can
    be restored. The results was yes and no. The extrapolation was mild,
    and no harm due to the large power of rho is observed, this is positive.
    Negative news is that, any specific structure which is isolated outside
    of the fit region cannot be reproduced. This does not improve by using
    larger number of Zernike modes. Using too many modes is rather harmful
    to produce peculiar pattern in the extrapolated region, But no algorithm
    will be able to predict this kind of structure. The difference between
    the measured data and the fit is uniform within 15cm region, so this
    pattern of noise is used to fill the entire 24cm region, on top of the
    fit using Zernike polynomial. The contrast defect predicted for LLO was
    worse than the real measurement. This could be caused by the fact
    that the tilt component of the phasemap was not fully subtracted (from
    the FFT software point of view) and the next run with this fully patched
    mirror map will apply tilt removal procedure before the run.

    Interpretation of the result of the FFT run caused some confusion
    regarding the shot noise limited sensitivity. This is summarized by Bill.

    Biplab finished FFT runs for the cold state of H1 using lab-measured
    optics loss values given by Bill.

    Radiation Pressure
    ------------------

    Hiro used a simple FP model with radiation pressure to study the case
    corresponding to the Danniel's calculation. Danniel's calculation takes
    only the yaw pendulum into account, so z and pitch DOF are disabled in the
    simulation. (FP is the LIGO I arm) The FP stability was tested using
    different input powers, with the suspension point moving at 10^-7
    radian at DC and falling down as f^-2. If there is no ASC, the system
    becomes unstable above 100 W, or 10K in arm. But once a simple ASC is
    engaged, the FP cavity becomes stable up to 7k W input or 0.7 MW in arm.
    When the power goes up more, the unstable mode is excited and the system
    becomes unstable. Here, stable means that the mirror rotates at theta = 0,
    and unstable means the mirror tilts to other angle,
    ~10^-7 radian and rotates at around that DC tilted equilibrium.

    Xiao studied the radiation pressure effect and found that similar
    phenomena can happen in the current LIGO I configuration. He also found
    that 1% level of OSEM asymmetry can induce a DC tilt of the order of 1e-7
    radian. All of these depends on the details of the ASC design, but this is
    an interesting observation. Xiao is going to give a talk at LHO on
    August 14th, together with other SURF students.

    Signal simulation
    -----------------

    Jeff has completed his modeling of the optical path length change due
    to the GW signal, directly modifying the phase of the propagating laser
    field in a cavity. He is also giving a talk at LHO on August 14th.

    WFS (Biplab)
    ------------

    Generated H2 IFO WFS signal matrix in hot state and gave it to Virginio
    who is working on H2 WFS. Working with Luca on WFS loops of H1.

    Code development and maintenance (Ed Maros)
    -------------------------------------------

    1. Fixed several issues concerning code compilation so cvs
       checkouts would compile.
    2. Added missing header file to AdlibMM/Makefile.am so tarballs
       would compile.

    (Ed and Biplab)
    Updated code at Hanford. It would be available from ~e2e/Current/e2e-1.7.12
     
    (Melody)
    --------

     - Modifying the e2e source code to dynamically create C++ source from
       FUNC_xxx equation modules, which would be compiled, combined to a shared
       library, and used during runtime execution. Currently working on source
       file creation.

    Alfi (Bruce)
    ------------

    Implementing bundles and bundlers in Alfi (PR 272.)

    LIGO Data Analysis System
    -------------------------

    LDAS Software Systems
    ---------------------

    (Blackburn)
    GCC has released a new compiler (3.3.1). We began the process of testing
    the rebuild of LDCG using this new compiler and an automated script known
    as "Sinstall". Several issue came up including the annoucement that GNU's
    primary software distribution server was hacked into. We know have enough
    of LDCG rebuilt with the new compiler to start building LDAS. Too soon to
    report on compiling or running LDAS with the new compiler.

    Continued to fix problems with iterators and other container methods in
    the total code base. LDAS is gradually running more smoothly (reliably)
    as these changes are made. There is still a lot of work to do in this
    area.

    The frameCPP version 6 dictionary class was reworked this week to non-
    iterator based keys in an effort to resolve some of the core dumps seen
    in this code base.

    The diskcacheAPI was seen to occasionally create 50 or more threads when
    a new file system was added to LDAS with lots of subdirectories. This was
    causing other processes on the same box to struggle for CPU cycles. To
    resolve this a thread throttle was added to the TCL layer of this API.

    A relatively large effort went into improving documentation this week.
    We have begun removing email addresses to prevent crawlers from spamming
    LDAS staff and also improved the accuracy of documention for the runLDAS
    script and the managerAPI's protocol with client software.

    A new user command is now working on the development system which allows
    users to delete their own data products once they have copied these of
    the LDAS system with URL technology. The new user command is called
    rmJobFiles.

    Changed logic in managerAPI used to detect host server's name to better
    support running the managerAPI on a gateway server.

    This week we made significant progress in re-running our standard suite
    of system tests. This has fall considerably behind this summer and as a
    result a couple of test were discovered to fail that worked in the last
    release.
     

    LDAS Hardware Systems
    ---------------------

    Caltech:
    -------

    (Hari Pulapaka)
    * I have taken over the administration of the rls server on ldas-archive,
      and there was a problem where the rls-server was stuck in a loop and all
      the client requests were timed out. So I was looking into this, but it is
      already logged in a bug and is fixed with the next version of rls-server.

    * I have been trying to install VDT-1.1.10, but VDT 1.1.10 is not supported
      on RH 9.0. The VDT team might support 1.1.10 in some time, but till then
      we can either install each individual component or make our head node RH 7.3

    * So I have been installing and testing globus, rls-server and gsi-openssh
      on a test RH 9.0 machine. Installing Rls-server was a really long process
      and I think this is where the advantage of having VDT will come to the fore.

    (Stuart Anderson)
    * Worked on an IDE-RAID server that had a double disk failure with the
      resulting loss of 1TB of S2 RDS data. These data are currently being
      transferred back to the rebuilt RAID system using LDR from UWM.

    * Tracking down problem with one of the dual-Xeon software development
      servers crashing on a daily basis. It appears to be a problem with
      the unit running out of memory and the kernel making bad choices.

    * Obtaining price quotes to buy another 4 tape drives for the central
      archive to increase the number of drives from 6 to 10. The current
      use pattern is keeping all current 6 drives busy.

    * Fixed a problem with the large 210 node cluster that appears to
      have been caused by a search code using too much memory and crashing
      some of the nodes. This has been addressed by setting a per user/per
      processes maximum memory limit (limit vmemoryuse).

    Hanford:
    -------

    (Ben Johnson)
    * Module 9 of switch (nodes 65->80) went offline off and on last
      Friday. Moved the module to slot 7, and have run several inter module
      netburn tests since. No problems have occurred since.

    * tekoa/datagateway2 froze on Sunday, August 10. Updated the kernel to
      Redhat's 2.4.20-19.7 uniprocessor kernel.

    * Continuing work on script for tape archiving process for the upcoming
      science run. Most of the substance of the disk2disk copy script is
      finished, but it still needs to be fully fleshed out and fully
      debugged.... Afterwards, I will begin work on an error handler/log
      analyzer script, which monitors the status of the disk2disk copy process
      and alerts/emails as necessary.

    Livingston:
    ----------

    * LDAS is down since Sunday night for AC replacement work that is still in
      progress. I was told that I can restart LDAS Friday morning.

    MIT:
    ---

    (Keith Bayer)
    * New datacon / beowulf completed burn tests on RH7.3.
    * Working on power distribution for lab.
    * Received power watt meter from Caltech.
    * A/C service breakers replaced at panel (35amp from 30amp).
    * Pointed LDR to free disk space to continue S2 2x RDS download
      (averaging 3+MB/s from UWM).
    * Moved 'borrowed by cds' test cluster pc back into ldas lab.
     

    Data Analysis Activities
    ------------------------

    (Creighton)
    This week I finished modifications to the template placement code to
    account for regions of degenerate parameter metrics, and have started
    testing/debugging.

    (Reilly)
    I have started a run through the H1L1 coincidences during S2 with the
    goal of producing  a plot of the theoretical sigma of the CC statistic
    as a function of time throughout the S2 run. I made an initial plot of
    this for the first 174 jobs of H1H2 coinicidences.  For most of the week
    I have been debugging the stochastic DSO. Several problems have
    come up with ldas which have made the process a bit slow. I am
    currently stuck on getting things into and out of the database when
    running the wrapper in standAlone mode.

    (Shawhan)
    Investigated veto safety by looking at S2 hardware injections and seeing
    if they show up in auxiliary sensing channels.  I confirmed that signals
    show up quite strongly in AS_I, but not in REFL_I, REFL_Q, POB_I, or POB_Q,
    so these latter four channels should be usable for vetoes.  Details may be
    found at http://www.ligo.caltech.edu/~pshawhan/s2/veto/safety.

    (Yakushin)
    Still working on parallelizing waveburst. It turned out that in order
    to benifit from that and avoid bottlenecks in mpiAPI communication,
    ligolwAPI, and eventmonAPI, I would have to do the output manually to
    disk bypassing part of the standard LDAS pipeline. Preliminary
    experiments seem to indicate that otherwise all the benefit of
    parallelizing would be taken away by overhead.

    Helping Sergey to prepare for his talk about waveburst at LSC
    meeting.

    General Computing (Wallace)
    ---------------------------

    No Report this week.
     


    Advanced LIGO Development (Shoemaker)


    Suspension

    From: "Mark Barton" <mbarton@ligo.caltech.edu>


    In between sessions at the AdvLIGO SUS meeting in Glasgow, I've created
    versions of my quad and triple Mathematica suspension models with uneven
    force constants in the blade springs to check on the effect of assymetry
    for Justin Greenhalgh.

    Pre-stabilized Laser

    From: Peter King <pking@ligo.caltech.edu>


    Benno sent me a copy of the LZH laser costing estimate.  Whilst I have
    not had a good look at it, I will be going through it to rustle up loose
    ends and the costs to be divided between AEI/LZH and the LIGO Lab..

    Core Optics

    From: GariLynn Billingsley <Billingsley_G@ligo.caltech.edu>


    The RTS scanner is being modified to allow for absorption measurement and to accommodate Advanced LIGO sized optics.  A 30W laser is due to arrive mid-August, Lee Cardenas and Mike Gerfen are in the process of making the mechanical modifications.

    GariLynn has taken a couple of shots at measuring the change in radius of curvature of a coated thin Q sample.  The data is not making sense yet, but there are a couple of more things to try.  The trick is in being sure to separate the Interferometer drift from the real data.

    LASTI RM blanks are in.

    GariLynn attended the international optics symposium in San Diego last week.  Hot new items are EUV and X-ray lithography, magnetorhealogical finishing (MRF), and advances in nano-technology.  We have been considering MRF as a means of removing the final polishing layer, leaving a low damage surface on the optic face.  To date, no one who does MRF polishing has the level of metrology needed to fabricate LIGO optics. If the process turns out to be promising, metrology can be bought.

    Another interesting technique has come out of LLNL in the EUV coatings arena.  They use IBD, as we do, but have another Ion source to smooth the coating layers in between deposition of layers.  This technique relieves the polisher of achieving both figure and microroughness simultaneously, leaving them to concentrate on figure.  The microroughness can then be improved during the coating process.  LLNL is working with a lot of different materials, and has developed the ability to analyze those materials.  It should be worthwhile to open up a dialogue with them about their experiences.

    From: Bill Kells <kells@ligo.caltech.edu>

    The message for
    this report concerns LIGO I commissioning results,
    but also has a strong implication for AdL optics
    performance.

    Over the last few months we (I, and recently joined
    by Hiro and Biplab) have had time to digest and
    review (with respect to older, pathfinder and
    LIGO I optics fabrication data) various results on
    as built LIGO I performance. The best of this has
    been from H1. Although the qualitative conclusions had
    been clear [to me] for some time (for instance I had
    given a seminar in the Spring on the H1, H2 visibility
    and scatterometer measurements), these have just now been
    nicely summarized in an initial round of "as built"
    LIGO I FFT simulations (Yes! at long last). THis was finalized
    by Hiro and Biplab's (and summer students) effort to
    creat FFT versions of the TM metrology HR phase maps.

    The results are no suprise. The SRD value of 30 as a likely
    recycling gain was based on pathfinder and pre-pathfinder mirror
    data. As the actual fabrication proceeded it was clear that
    the "as built" mirrors were consistantly much better (both in
    surface figure and scattering roughness. This translates into
    very significantly lower arm cavity effetive loss and thus higher
    recycling gain. For instance FFT runs for H1 using the best known
    TM mirror metrology numbers give G~94. So, with respect to SRD the
    LIGO I ifosare performing well. However with respect to "as built"
    metrology the performance is poor.

    In situ measurements at LHO (most solidly H1: arm visibilities; maximum
    achieved recycling gain; and extrapolated individual TM scatterometer
    data) are all consistant with much higher (>5 times "as built" metrology)
    HR effective loss (~50-80 ppm/HR surface).

    For LIGO I we appear to be in good shape, since the goal was so conservative.
    However we are anticipating mirror losses closely consistant with best
    metrology for AdL design.


    Auxiliary Optics

    From: Michael Smith <smith@ligo.caltech.edu>


    PHOTON DRIVE R&D
    Tom Essinger-Hileman has aligned an optical system with 4 bounces from the MC2 mirror, with the addition of 8 bounces if necessary, and is awaiting the locking of the mode cleaner to complete his photon acuation of the mode cleaner cavityi.

    Aidan Crook has designed the filter for the additional photon actuation servo loop. Ben is making a hardware filter. Aidan and Tom will test the photon actuation control of the mode cleaner after it is locked.

    Other Laboratory R&D

    LASTI WEEKLY 8/14/03RichMittleman

    MEPI

    Now that Bill Rankin has left MEPI has been mothballed.

    MIT Quadruple Prototype

    Andrew has straightened out the electronics problems and is now taking transfer functions from actuators between the two penultimate masses and the bottom mass.

    HEPI

    We have installed a second reaction mass driver, on pier #4. The transfer function to the pier top is not the same as what was previously measured on pier #3. We are currently investigating the possibility that the difference is due to a different mounting platform (data and details are on the LASTI Ilog).

    The plumbers are currently working on the hydraulic lines for the other three chambers.
     


    From: HareemTariq <htariq@ligo.caltech.edu>

    Weekly - 4th Aug to 8th Aug:
    Allyson:
    Simone is x-raying the samples and most look pretty much glassy. There is
    a small strange peak that seems to appear in quite a few of the x-rays and
    now I have to talk to Bill about them because samples probably have
    crystalline contamination. The SEM is having a slight problem too and I
    hope to have that looked at shortly so I can begin measuring.

    Mike:
    Finishing paper and some vacation.

    Charles:
    I helped Francesco with the stress-strain machine, showed him how to
    solder the LVDTs' wires, and ordered the missing parts. We also took care
    of the compressed air for cooling down the heated rod. I characterized the
    ringing obtained from filtering a Gaussian Pulse with different filters
    used on the real signal.

    Francesco:
    I made some good splats of MoRuB (B19,B20,B21,B22,B18) that can be sent to
    the X ray test. For the analytical prediction of thermal noise for the
    joint, I am consulting some books on elasticity theory and waiting for the
    ANSYS simulation of strain energy.
    I'm also putting together all the pieces of the stress strain machine,
    charles and I have completed the assembly of the mechanical parts and now
    remains to make the electrical control system for the heating rope.

    Greg:
    Finished x-raying previous casts. Started preparing and casting samples
    to measure other mechanical properties (tensile strength, compression
    test).

    Chiara:
    I did measurements on samples of metglass using copper tape and soldering
    copper leads on it. Results are not good as maybe there is no proper
    thermal contact between copper tape and sample or between solder and
    copper tape!
    So now I want to do measurements with copper tape and epoxy to understand
    where is the problem.

    Xavier:
    Done with 80% load, Max angle and Effective Bending Length for 10 microns
    thick, 20 microns thick and 40 microns thick blade considering 10% of 7GPa
    as a Yield point.
    Starting on Strain Energy Study.

    Enrico:
    Finishing the report.

    Simone:
    I assisted Chris remeltingPdNiCuP alloy, using induction coil technique
    in order to purify his sample with B2O3.  I began working with DSC,
    scanning my sample from 473K to 923K to observe all the thermal transition
    in that range of temperature [a glass transition, a peak of
    crystallization, a small peak of melting, a big peak of melting
    accompanied a peak of reorganization]. All those transitions happen before
    873K. At 873K a strange peak is observed, it must be a contamination of
    the Pt plats {it was just reported by other operators in the DSC
    composition book.  I have ordered 1 oz [something like 30 gr] of Pd to
    produce the amount of alloy I need at the lower price on KITCO.  I have
    started scanning isothermally the samples Chris gave me, to find a good
    temperature of scan. 638K or lower should be good [it is about 20K before
    Tx recorded on a 0.67K/s scan], a higher temperature don^t give a good
    signal [crystallization just occurs before the instrument begins to work
    isothermally]. Finally I got a good scan at 633 K. I heated one sample for
    6 minutes at 633K, which should correspond to 17 % of cristallinity.

    Hareem:
    Was on vacation for half of the week. Numata-san wrote part of his code in
    C using Borland's C++ builder. LIGO does not support this platform
    currently and I cannot find any machine around, which I can use
    either. Looking into resolving the matter.


     


    For additional information about this report, contact sanders@ligo.caltech.edu