Weekly Report for Week Ending July 3, 2003


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
Adv. LIGO Development
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  July 7, 2003 will be:

CANCELLED DUE TO AMALDI MEETING


Special Announcements:


Weekly Report Highlights
 


LSC Issues (Saulson)


   The Executive Committee of the LIGO Scientific Collaboration met on 27 June 2003,
and considered three of the S1 papers (Stochastic, Pulsar, and Inspiral) for
possible approval for publication.
   I am pleased to announce that the results presented in each of the three papers
were approved as the final S1 results of their respective searches. This means that
the LSC Executive Committee authorizes the use of these results as approved and
final results.
   We did, however, find some editorial problems in each of the three papers.
For this reason, none of the three papers is yet approved to be distributed
outside the LSC, posted on the archives, or submitted to a journal for publication.
The LSC Executive Committee created ad hoc subcommittees to work with each of the
three Search Groups to resolve these issues. We expect that this process can be
completed shortly. After a subcommittee is satisfied, the paper will be posted for
final checking by the LSC. As long as nothing wrong is found after one week's
posting, the Spokesperson will authorize the posting of the paper to the
gr-qc archive.
   A tremendous amount of good hard work has gone into the S1 analysis. We should
all be very proud of how well it has gone, and how close we are to concluding it.
 

Peter Saulson
LSC Spokesperson


LIGO I Construction/LIGO Laboratory Administration (Lindquist)


LIGO Weekly Site Telecon (Lindquist)

A site teleconference was held on Thursday, July 3, 2003.  The following were among the items discussed:

The Construction effort is complete and we are accumulating the final costs.  Current estimates indicate that we will be within $20K of the $292.1 million target cost.

Finacial reports for Operations as of the end of June 2003 have also been published on the web.  Our current expense rate is slightly less than $3 million per month, which is up a tad since we have moved all cost away from Construction.  Also procurements are increasing.  Seven purchase requisitions have been prepared for the external pre-isolation.

Livingston Construction: the storage building is complete, and the gate is basically complete (missing only the actual gate).

The list of current actions revised to reflect the status of open actions assigned through July 3, 2003 may be found at ACTION LIST.


PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACCOMPLISHMENTS

> From: Cleveland Mak <mak_c@ligo.caltech.edu>

ACTIVITY


07/03/03 Packages Faxes
In  31 32
Out 20 37

Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman, Salone)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA .

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

From: Gina Salone <gsalone@ligo.caltech.edu> From: Florence Kaufman <fkaufman@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>

CONSTRUCTION:

OPERATIONS:

SUPPORT (Baldon, Lloyd, Tischler)

>Irene Baldon

>Dorothy Lloyd >From: Ryan Tischler <rtischle@ligo.caltech.edu>

Advanced LIGO (Frey)

From: Thomas Frey <tfrey@ligo.caltech.edu>

For list of documents that are being used to develop Adv. LIGO Cost and Schedule, see http://www.ligo.caltech.edu/~tfrey/Cost_MTG_082002/

Advanced LIGO MRE Proposal (Highest Priority) Project Plan for the 40-Meter Lab Upgrade continues. Project Plan for the TNI Lab Project continues. Continue to update the LASTI Schedule and incorporate any changes. Cost Book Tool. Development of the Advanced LIGO Project Controls Guidebook continues.

Project Web Site for posting schedule and progress related data continues to be updated with the latest and greatest.



Reports (Lindquist)

The Construction Project Quarterly Report for the end of February has been sent to the NSF.

I have distributed a proposed outline and writing assignments for contributions for the Operations Annual Report and Work Plan for FY 2004.  I am requesting input by Friday, July 25, 2003 (sooner if possible).  I am also preparing a strawman for the budgets, to be distributed shortly.

During the executive committee meeting held on June 23, 2003, we discussed the fact that once the Construction effort is closed, we must submit a final report for Cooperative Agreement PHY-9210038.  This can be handled simply as just an obligation to be completed or as an opportunity to brag about very significant accomplishments.  So far a preferred approach has not been settled.



Change Control/Contingency (Lindquist)

As previously reported, the following change requests were reviewed during the executive committee meeting on June 23, 2003:
 
CR-030008 Furniture for the auditorium lobby, interaction area underneath the skylight atrium in the OSB, and on the second floor interaction area of the new laboratory/office building. (ON HOLD pending additional cost data.) M. Coles April 29, 2003
CR-030011 Seismic External Pre-Isolation at LIGO Livingston Observatory D. Coyne May 16, 2003
CR-03--13 Atomic Clock Timing System Marks, Sigg June 9, 2003
Change Requests CR-030011 and CR-030013 were both approved.  New quotes for the furniture proposed by CR-030008 substantially reduce the cost estimate to an amount less than the threshold, and approval is not required.  Minutes are being prepared.



Human Resources (Akutagawa)

From: Cindy Akutagawa <cindy@ligo.caltech.edu>


Quality/Safety (Tyler)

>From: Bill Tyler <tyler@ligo.caltech.edu>

LIGO Hanford Observatory (LHO) and Interferometer Operations (Raab)


no report


LIGO Livingston Observatory (LLO) and Interferometer Operations (Zucker)


LIGO Livingston Observatory (Zucker et al)
-------------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------------
 

Commissioning:
-------------------------------------------------------------------------------------------------------------
A productive week. We are concentrating on baseline measurements in preparation for
an upcoming vent to alter the Schnupp asymmetry and recycling cavity length and
to install the anti-light-saber baffles. Highlights (and bummers) include:
 

- A power-damaged EO modulator was removed and diagnostics initiated.
A power budget was made for the PSL and losses localized to help
us consider further steps.
 

- Our NPRO master oscillator laser appears to be going multimode over a
significant fraction of its tuning range. We have a complete MOPA waiting in the wings for a swap
opportunity,  so rather than fix it we're limping along avoiding the trouble spots to get other
measurements done.
 

- Due partly to this problem, which frequently triggered laser frequency stabilization disease, we have backtracked to a prior version of our frequency stabilizer, which is less twitchy than our newer "high bandwidth" model.
 

- We had an intermittent connection in an ETM coil driver which prevented going to RUN (low noise) mode without breaking lock; this fixed itself during diagnostics, and will  be monitored to see if we can isolate it if it fails again.
 

- Despite these issues we are getting an S2-like (low noise) strain spectrum and  have been able to engage all 5 wavefront sensors such that the alignment is well  optimized. We feel we're close to a routine and robust WFS operating mode sufficient
for S3.  We will do further characterization of the sensing matrix and work on optimizing filters after the asymmetry/recycling length change.
 

- Our remote PSL power adjust is installed and working.
 

- We haven't made much progress understanding the anomalous PRC-->AS_Q coupling highlighted last week by Rana; in addition, a strange temporal
variation in the optimal demodulation phase has been added to the open
mystery list.
 

LLO PSL (Peter King)
-------------------------------------------------------------------------------------------------------------
The laser power at various places on the PSL table was measured with a
Scientech calorimeter.  The laser output power was 4.80 W.  After the
pre-modecleaner the power was 3.13 W and at the base of the IO periscope
the power was 1.88 W.  The 24.483 MHz Pockels cell was visibly damaged and was replaced.
 

The mode-matching to the pre-modecleaner was improved slightly, with the
transmitted power being increased to 3.39 W.  The output of the laser was scanned with the pre-modecleaner and the number of modes between TEM00s was counted.  The count was constant at the positive end of the SLOW actuator adjust slider.
 

A quote for new phase modulators was received.  New Focus have
not told me if we'd get a discount of any kind.
 

ISC table acoustic enclosure & misc. (J. Kern)
-------------------------------------------------------------------------------------------------------------
Acoustic enclosure for ISCT-4 was delivered Tuesday, considerably
blemished externally because of carelessly applied tarps by the common
carrier. http://www.ligo-la.caltech.edu/~jkern/AcousticEnclosureDamage/
Refused delivery, but worked with the vendor to locate a local shop that
could receive the unit and repair it locally.
 

Spec-ed and ordered RD
modulated, fiber coupled laser diodes for Rai.  These to make RF PD
calibration of ISC tables easier.
 

Outreach (B. Wooley)
-------------------------------------------------------------------------------------------------------------
A relatively quiet week before the July 4th holiday.
 

Site construction actiivity (Sibley, Kern):
-------------------------------------------------------------------------------------------------------------
The storage building is complete, just waiting to complete the exterior grading (delayed
by weather, i.e., mud).
 

Our front entry gate is complete except for hanging of the gate proper
and finish grading (again,  weather).
 

The LDAS repowering and HVAC rework
is done but we need to revise some air conditioning routing to suit the as-built heat
loads (see LDAS report below).
 

The facility pneumatic line rework is done except
for backfilling the holes.
 

Cabinetry installation in the laboratory is completed.  Worked with the
installer and signed off on the DI water plant tonight.
 

LLO seismic retrofit (Kern):
------------------------------------------------------------------------
Working closely with Ken Mason and Marcel Hammond
to complete the checking, and
release of fabrication drawings for the External Pre-isolator. Marcel
has traveled to MIT to help Ken with detailing. 4 large purchase
requisitions for catalog items, and 3 for machine and fabrication work
have been sent to Ed Jasnow. Engineering estimates of projected
procurement costs for LLO/LASTI installation are still in the works.
Working on a Solid Works model for the actuator bypass, and ordered misc
fittings to build a prototype.
 

General Computing (Shannon Roddy)
-------------------------------------------------------------------------------------------------------------
Installed a new web server for support issues at support.ligo-la.caltech.edu.  The only page up currently is a page detailing how to install printers, but more will be added in the coming weeks.  Much of the informatin that we have scattered around will be moved to this new web site.
 

Performed a security audit on our web server in preparation for the "hacker contest" that was announced on some of the news outlets which is supposed to happen this Sunday.  I may block our web site at the firewall for Sunday.
 

Setting up a .6 TB server to perform some testing with various backup software.  Eventually this will be a larger scale server (2 to 4 TB) for workstation/laptop backups.  I will test a couple methods of backups for windows and UNIX clients.
 

Patched a few machines with security patches this week.
 

Tried to contact Sun sales to find out about charges for the LDAP server offered by them, but their offices are closed all week.
 

Troubleshooting one of our servers here.  I suspect it is having memory problems.  It will not make it completely through an OS install.
 

LDAS (Shannon Roddy):
-------------------------------------------------------------------------------------------------------------
Installed a KVM extender for Igor.  There may be some issues that I will have to work on with the
vendor, but I have not had a chance to look at it yet.
 

LDAS (Igor Yakushin)
-------------------------------------------------------------------------------------------------------------
LDAS admin:
 

1) Continued working on the new cluster hardware installation: wiring
(with Excel), labeling (with Paul Armor from UWM), putting property
tags, etc.
2) Together with Paul labeled all the tapes for L700.
3) Ordered more LC-LC FC cables to connect servers to FC switch.
4) The existing AC does not dissipate heat behind the rack fast enough
(the temperature behind the rack was 83F while the rest of the room was
cold as usual). I had to buy a few fans as a temporary solution (now it
is under 70F behind the racks) until the new AC is installed.
5) Bought some tools for LDAS room.
6) Datacon and beowulf machines passed 90 hours of memtest86 without
errors. Running memtest86 on the nodes, so far no errors.
Node 3 has no LED lights. Node 33 at the beginning had problems with the
network connection which seem to disappear later.
 

LDAS data analysis:
 

Looking at the injection data using waveburst and wavemon to see how
well waveburst detects the injections and how well wavemon's vetoes
work.


Detector/Technical Support (Coyne)


no report


40 Meter Interferometer (Weinstein)




Thermal Noise Interferometer (Libbrecht)


no report


Data Analysis and Computing (Lazzarini)


--------------------------------
Simulation and Modeling (Bhawal)
--------------------------------
 

Mirror Phase map
-------------------
Raghu Dodda wrote a program to convert the measured phasemap data into
the format which can be used by the FFT program. This is still limited
in the central region. The discussion to run FFT using these phasemaps
will be held this afternoon among, Bill Kells, Biplab Bhawal, Raghu Dodda
and Hiro Yamamoto. This will be the first run evaluating the LIGO I
performance using the real phasemap. Extension of the measured data to
cover the entire region is being developed by Hiro, and will be completed
together with Raghu.
 

Signal simulation
-------------------
Jeff Jauregui studied how the GW strain signal affects the phase of the
laser propagating between mirrors of a cavity. He has started writing C++
codes (1) to generate a source and (2) to convert the strain to phase
changes in the two arms. Once these codes are completed, the phase
distortion can be used as a input to a propagator so that e2e can simulate
the effect of the GW signal. Some of the calculation done by K.Cooksey, 2001
SURF stundet, are used.
 

Noise hunting
---------------
Xiao Xu has start running SimLIGO to understand the difference between
the SimLIGO best and SimLIGO nominal. SimLIGO nominal is a sensitivity
including all known noises and SimLIGO best is the one which suppresses all
known noises amap, including the 16 bit digitization noise by using 30 bits.
Hiro found that SimLIGO best has some problem, and is hunting for a fix.
SimLIGO nominal is reasonably close to the Hanford 4k measured noise, and
we hope this study will shed a light which noise is the most problematic.
 

Dual Recycling Code
----------------------
Keiko Kokeyama worked with Osamu Miyakawa to start validating the
approximation to be used in the dual recycling summation
cavity module. Using old matlab code written by Malik as a guidance,
she tried to start the code in matlab.
 

LLO SOS modeling
--------------------
Sany Yoshida and Tiffany are working to build a SOS box to simulate the
small optics suspension using the LOS box as a template. They studied the
effect of the control gain and measured spectrum, and overall behaviors
look OK. They are studying the details. Hiro will provide the fit of the
seismic motion so that they generate the HAM table top motion by combining
with the HAM transfer function.
 

Transfer Fn of LIGO for changed length
----------------------------------------
(Biplab) Rainer Weiss suggested Ken Yoshiki Franzen of U. Florida to use e2e
 in order to check how the fact that "RM is displaced 2 cm at LLO" affects
 the output signals. Helped Ken to make his model and run it.
 Also interacted with Rana and Ken on some issues related to validation of
 signals.
 

Code development and maintenance
---------------------------------
(Hiro) Dynamic linking of FUNC code:
 In SimLIGO, FUNC (expression parser) module is spending majority of the
 simulation time. Code improvement has been done by Hiro and Melody, but
 not much of gain has been accomplished. Now Hiro and Melody are designing
 to use a dynamic linking. I.e., all FUNC codes are compiled using a c++/c
 compiler to generate a dynamically linkable library so that FUNC modules
 are be executed much faster. The algorithm toward this direction was
 discussed, and Melody is preparing a simple example and a wrapper needed
 to minimize the overhead doing this.
 

(Melody)
 - Evaluated several products/research projects in search for an API
   to dynamically compile a C module during runtime.   Came to the
   conclusion that doing incremental compiles is a more doable
   approach.  Started working on a prototype that performs dynamic
   linking.
 

Alfi
-----
(Bruce) - Writing full Alfi documentation.  ugh.
 
 

----------------------------------------------
LIGO Data Analysis System Software (Blackburn)
----------------------------------------------
 

The issues with using optimizations with the new GCC compiler have been traced
to changes in the nightly build process. We are now definitely compiling at
night with the -O2 -finlining options that we want to target for the next
release of LDAS. There are some issues in the frameAPI and eventMonitorAPI
at this optimization level, but it is thought that these are issues that would
exist without optimization only less frequently - the optimization level is
giving us a better look into existing bugs. The performance of typical data
pipelines jobs is now up by about 40% from the optimization and the RDS frame
creation is up by about 10%.
 

A set of changes to the LDAS resource files between the 0.6.0 release which
is currently running at UWM and the 0.7.0 release which is currently running
at the Lab sites was posted on the LDAS website under the FAQ link. This will
facilitate UWM's efforts to upgrade over the next couple of weeks to the
current official LDAS version.
 

Significant progress was made in getting the metaDataAPI treaded this week.
The infrastucture for writing to the database has been developed and is now
being heavily tested. Sevearl issues with this code have been discovered in
testing and are being worked on. The infrastructure for reading concurrently
from the database still needs to be developed.
 

A new utility called ldasinfo is being developed to trace the metadata about
how LDAS was compiled each night. This will provided better visibility into
changes in how LDAS code is built.
 

Testing of the controlMonitorAPI on the LDAS-CIT system as new nodes are
becoming available has revealed several issues with configuration and the
management of our new much larger Beowulf cluster there. These are being
addressed in the form of problem reports and bug fixes as they are discovered.
 

Building LDAS against the new IBM DB2 version 8.1 continues to cause issues
under both Redhat9 and Solaris. This week a set of fixpacs were installed on
a test Sun box to determine if any of these issues have been fixed in recent
updates to the database. IBM has been contacted and some initial feedback has
taken place with IBM, but no solution has been provided at this time.
 
 
 

-------------------------------------------------
LIGO Data Analysis System Administration (Stuart)
-------------------------------------------------
 

Caltech
-------
(Dan Kozak)
 

* Got Sun to send us a replacement 3510 controller for the one that failed.
 

* Configured all but one of the 3510s with 10+1 RAID 1 and 1 hot spare.
 

* Working to figure out why ldas-archive can't utilize disks bigger
  than 1TB.
 

* Continued re-archiving data in SAM-QFS to higher density tape format.
 

* Packed up all beta test Qlogic hardware and had it shipped back to them.
 

* Started prep work for LHO visit (L700 set up).  Arranged travel for LHO trip.
 
 

(Stuart Anderson)
 

* Diagnosed and fixed problem with Linux SMP kernel and the Copper GigE
  device driver (tg3) for the IDE-RAID servers.
 

* Investigated problem with new 15-slot GigE switch--1 slot appears to
  be bad and Foundry will be out Monday morning to look at it.
 

* Brought up the first 39 new beowulf nodes into production use in the
  LDAS-CIT system.
 

* Identified 2 more dead-on-arrival nodes out of the 210 units at Caltech.
  One spontaneously reboots itself after 10's of minutes and the other
  refuses to boot or generate a video sync signal to get to the BIOS.
 
 

MIT
---
(Keith Bayer)
 

* Retrieved new NDAS frames from Caltech and mounted NDAS
  on ldas and dmt machines.
 

* In contact with ASA regarding configuration for new pcraid boxes at MIT.
 

* Working with Al to update our cfdefs files for new beowulf/datacon boxes.
 

* Received test cluster node from Ben at LHO.
 

* Beginning transfer of S2 double coincidence data via LDR utility.
 
 
 

Livingston
----------
(Igor Yakushin)
 

* Continued working on the new cluster hardware installation: wiring
  (with Excel), labeling (with Paul Armor from UWM), putting property
  tags, etc.
 

* Together with Paul labeled all the tapes for L700.
 

* Ordered more LC-LC FC cables to connect servers to FC switch.
 

* The existing AC does not dissipate heat behind the rack fast enough
  (the temperature behind the rack was 83F while the rest of the room was
  cold as usual). I had to buy a few fans as a temporary solution (now it
  is under 70F behind the racks) until the new AC is installed.
 

* Bought some tools for LDAS room.
 

* New Datacon and beowulf machines passed 90 hours of memtest86 without
  errors. Running memtest86 on the nodes, so far no errors.
  Node 3 has no LED lights. Node 33 at the beginning had problems with the
  network connection which seem to disappear later.
 
 

(Shannon Roddy)
 

* Installed a KVM extender for Igor.  There may be some issues that I wil
  have to work on with the vendor, but I have not had a chance to look at
  it yet.
 
 
 

Hanford
-------
(Greg Mendell)
 

* A level 2 RDS with the LLO L1:LSC-AS_Q channel for S2 is now
  available at LHO.  On fortress the data is under
  /frame40/rds/S2/LLO/L2ASQ/Data[0-310]. To access the data from an LDAS
  framequery specify the interferometer as L and the frametype as
  RDS_R_L2.
 

* Currently working with Robert Schofield to create an intersite S2 PEM
  RDS for his analysis.
 

* Ben Johnson has continued to work on installing the new beowulf
  cluster. All but two of 140 nodes have passed memtst.  (The two that did
  not would not even boot. One other node also would not boot, but worked
  after reseating cables.)  The failed nodes were sent back to the
  manufacturer and have returned, but have not yet been tested.  The
  current effort is to install RedHat 9 and configure the nodes using
  systemimager.  As usual, there are some issues with getting this to
  work, but we expect these will be overcome soon.
 
 
 

-------------------------------------------------
Data Analysis Activities (Anderson for Lazzarini)
-------------------------------------------------
 

(Greg Mendell)
 

Mike Landry and I have begun work on the stack-slide algorithm to search
for periodic gravitational waves. At the PULG F2F meeting June 16-17 we
gave our initial report and discussed various versions of the algorithm
and how to implement it.  What targets to consider, based on the
available computing power, was also discussed. Mike's priority for the
past week has been to get the calibration ready and mine has been to get
the knownpulardemod code working with latest versions of LAL.  The
former is need by all the S2 analyses, and the latter code will form the
basis of the stack-slide code.  The stack-slide code will be designed to
incoherently add the power from either SFTs for the F-statistic,
correcting for spindown and modulations induced by the detectors
motions, and will run in parallel under LDAS.
 
 

(Igor Yakushin)
 

Looking at the injection data using waveburst and wavemon to see how
well waveburst detects the injections and how well wavemon's vetoes
work.
 
 

(Laura Cadonati)
 

- Continued detector characterization glitch investigation with Mayur
  Desai and with the rest of the S2 glitch team. The status report is
  available at http://ligo.mit.edu/ldas/dc/dc20030703.html - Completed a
  set of S1 Zwerger Muller injections and efficiency determination
  (simulations performed by B. Shields, UROP student for the spring
  semester) and produced a smaller set of the same simulations for S2.
  Performed also efficiency studies for sine gaussians and gaussians in
  a portion of the S2 playground. Roughly speaking, the analysis being
  the same, we gain about a factor 10 in sensitivity from S1. Plots and
  numbers, for a first analysis of the S2 playground,  are available at
  http://emvogil-3.mit.edu/~cadonati/S2/PlaygroundFirstPass/index.html
 

- Completing the hardware-software injection comparison with fits of
  ETG response vs injected amplitude:
  http://emvogil-3.mit.edu/~cadonati/S2/Inject/S2injections.html
 

- Preparing my r-statistics talk for Amaldi
 
 

(Peter Shawhan)
 

Working with Evan Ochsner (SURF student) on filtering for inspiral
chirps, first with a simple program, and now moving toward using the
standard search code in LAL/LALwrapper.
 
 

(Alan Weinstein)
 

- Reviewed the comments from the LSC reviewers on the S1 burst draft.
- Studied the characterization of burst amplitude with h_char.
- Calculated poisson upper limits on S1 burst results.
 
 
 

---------------------------
General Computing (Wallace)
---------------------------
 

MIT:
-Working on X30 laptop with memory problems
-Investigating DVD burner with linux (for ldas laptop users)
-Looking onto large external SCSI drive as backup for gc fileserver
 

Livingston:
(Shannon)
-Installed a new web server for support issues at
support.ligo-la.caltech.edu.  The only page up currently is a page
detailing how to install printers, but more will be added in the coming
weeks.  Much of the information that we have scattered around will be
moved to this new web site.
-Performed a security audit on our web server in preparation for the
"hacker contest" that was announced on some of the news outlets which is
supposed to happen this Sunday.  I may block our web site at the
firewall for Sunday.
-Setting up a .6 TB server to perform some testing with various backup
software.  Eventually this will be a larger scale server (2 to 4 TB) for
workstation/laptop backups.  I will test a couple methods of backups for
windows and UNIX clients.
-Patched a few machines with security patches this week.
-Tried to contact Sun sales to find out about charges for the LDAP server
offered by them, but their offices are closed all week.
-Troubleshooting one of our servers here.  I suspect it is having memory
problems.  It will not make it completely through an OS install.
 

Hanford:
 

-Setting things up for the OC3 upgrade. The upgrade was delayed a few days and
should take place on July 7th.
-Setup new alias lists and updated existing lists.
-Working on a e-mail vacation message program/setup.
 

CIT:
(Mike)
-Performed the end of the month back ups on all NTSRV's and updated OS &
security patches; this also included updating firewall software.
-Loaded three PC's with OS & General Computing Software plus multiple
engineering packages, for surf students that are working under Riccardo. I
also had to enable/test multiple data ports for these additional workstations.
-Swapped out Lee's old computer with an updated PC. This included loading
2000 pro and all GC software and recovering his old data setting up e-mail
and network printer.
-Loaded a PC with OS & GC software plus added additional hardware for
backup purposes; plus I run a separate data drop from DCC to our Server Room.
-Backed up Ryan & Cindy's computer plus updated OS & Security patches.
-This past week I have been real busy with onsite support that includes
networking, printing and e-mail issues. I also had to load additional
software for surf students.
 

(Lisa)
- Began looking into new spam software.  Blackhole looked promising but requires
every individual user to forward their e-mail into the blackhole program.  This
clearly won't be appropriate in our environment.  There are a couple of other
open-source programs I am going to look at before looking at commercial
software.
- Fixed a problem with a rav loop that one user was getting between their ligo
account and their ITS account.
- Did monthly backups.
- More user support.
 

(Veronica)
- LIGO website: Prepared high-resolution images for a UK Government
Research Council. Burned a CD with copies of the images for Dave Beckett's
archive.
Obtained pricing and ordering information on a software package for Larry.
Working on issues of access to Internal Bulletin Board.
Evaluating a proposed DCC system setup change. Working with George Stokes
on troubleshooting of the DCC database.
Videotaped part 2 of a lecture on LIGO by Alan Weinstein for SURF
students.
Caltech Public Relations office requested video footage of aerial overview
of LHO for a PBS special. I checked the existing video archive of VHS and
DV tapes to see if we have it. We don't, so I offered the PR office DV
videos of Hanford construction progress. Awaiting a reply.
Edited the roster database. Posted updates to LIGO home page and to
several subpages. Captured a LIGO-related web article by GSFC as a
complete package of files/images/animations and migrated it to LIGO
webserver for archiving and long-term access.
- LSC website: continue working with Peter Saulson on
updates/modifications of the website. Posting updates as they come.
- Project Science: user support. Provided Sydney with an 'address book'
importable to Pine for mass announcements to the PS mail list.
- CaJAGWR: website update. User support.
 

(Larry)
-Spent a great deal of time setting up accounts and getting visitors, SURF
students and others setup. It appears we will shuffling things around for most
of the summer.
-Worked a number of procurements. Most are supply or low-end items.
-Setup another color printer for testing. So far it looks pretty good. Started
checking out a color B-size laser printer for a couple of areas.
-Worked a couple of network issues. Spent time on a LDAS Foundry switch and a FE
will be coming in to work on it.
ITS has scheduled the CISCO upgrade in the server room for the week of July
14th.
-Helped out the DCC with some minor issues. Mostly printing and file movement
problems.


Advanced LIGO Development (Shoemaker)



 

Advanced LIGO and supporting R&D

Seismic Isolation

No report

Suspension

From: JaneenRomie <romie_j@ligo.caltech.edu>


Working on MC FEA and quad layout.
Caroline Cantley and Justin Greenhalgh are visiting from the UK.


From: "Mark Barton" <mbarton@ligo.caltech.edu>

    This week I finished off and posted on my models page (<http://
www.ligo.caltech.edu/~mbarton/SUSmodels/>) the restructured Matlab
modelling code that I was working on last week. In the process of this I
examined the feasibility of adjusting the matrix elements to allow for
the fact that the blade springs are actually horizontal) as opposed to at
right angles to the wires, as in the current approximation). I got the
vertical working, but the other degrees of freedom look too hard to be
worth pursuing, at least as a retrofit. Instead I created a 'lite'
version of my Mathematica quad model, with most (5 out of 6 DOFs) of the
over-fussy modelling of the blade springs stripped out. This will be
useful to Aidan Crook who I've been helping with a modelling project for
Mike Smith. (We're going to get him to add violin modes to it and
incorporate it into a global control model to investigate the best way to
apply the laser actuator being developed.)
 

Pre-stabilized Laser

No report.

Input Optics

No report.

Core Optics

From: GariLynn Billingsley <Billingsley_G@ligo.caltech.edu>


Recycling mirror blanks ordered for LASTI have arrived from Corning.

Auxiliary Optics

From: Michael Smith <smith@ligo.caltech.edu>

PHOTON DRIVE R&D
Tom Essinger-Hileman is designing the optical system using the ABCD matrix formulation with Mathematica. He has made a preliminary layout of the 40m photon drive experiment using ACAD. Most of the parts have been received for the apparatus. Steve Vass will place a 3ft x 4ft optical table at the end of the MC chamber for mounting the apparatus and will move the OSEM wiring to the side viewport; the actuation beam will enter through a new viewport in the end of the MC chamber and will reflect from the back side of MC2 mirror. No steering mirrors will be needed on the MC2 optical table inside the chamber. Tom has written a progress report.
Aidan Crook has made a Simulink model of an SOS mirror suspension having displacement and pitch motion with photon force actuation on the mirror; the model includes velocity damping for both motions. He has written a progress report.

Interferometer Sensing and Controls

No report

Data Acquisition, Diagnostics, Network & Supervisory Control

No report

Other Laboratory R&D



 

 


For additional information about this report, contact sanders@ligo.caltech.edu