|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday July 7, 2003 will be:
CANCELLED DUE TO AMALDI MEETING
The Executive Committee of the LIGO
Scientific Collaboration met on 27 June 2003,
and considered three of the S1 papers (Stochastic,
Pulsar, and Inspiral) for
possible approval for publication.
I am pleased to announce that the
results presented in each of the three papers
were approved as the final S1 results of their
respective searches. This means that
the LSC Executive Committee authorizes the use
of these results as approved and
final results.
We did, however, find some editorial
problems in each of the three papers.
For this reason, none of the three papers is
yet approved to be distributed
outside the LSC, posted on the archives, or submitted
to a journal for publication.
The LSC Executive Committee created ad hoc subcommittees
to work with each of the
three Search Groups to resolve these issues.
We expect that this process can be
completed shortly. After a subcommittee is satisfied,
the paper will be posted for
final checking by the LSC. As long as nothing
wrong is found after one week's
posting, the Spokesperson will authorize the
posting of the paper to the
gr-qc archive.
A tremendous amount of good hard
work has gone into the S1 analysis. We should
all be very proud of how well it has gone, and
how close we are to concluding it.
Peter Saulson
LSC Spokesperson
LIGO Weekly Site Telecon (Lindquist)
A site teleconference was held on Thursday, July 3, 2003. The following were among the items discussed:
The Construction effort is complete and we are accumulating the final costs. Current estimates indicate that we will be within $20K of the $292.1 million target cost.
Finacial reports for Operations as of the end of June 2003 have also been published on the web. Our current expense rate is slightly less than $3 million per month, which is up a tad since we have moved all cost away from Construction. Also procurements are increasing. Seven purchase requisitions have been prepared for the external pre-isolation.
Livingston Construction: the storage building is complete, and the gate is basically complete (missing only the actual gate).
The list of current actions revised to reflect
the status of open actions assigned through July 3, 2003 may be found at
ACTION
LIST.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
ACTIVITY
| 07/03/03 | Packages | Faxes |
| In | 31 | 32 |
| Out | 20 | 37 |
Press here to access
the DOCUMENT CONTROL CENTER
WEB PAGE.
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA .
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
CONSTRUCTION:
SUPPORT (Baldon, Lloyd, Tischler)
>Irene Baldon
For list of documents that are being used to develop Adv. LIGO Cost and Schedule, see http://www.ligo.caltech.edu/~tfrey/Cost_MTG_082002/
Project Web Site for posting schedule and progress related data continues to be updated with the latest and greatest.
The Construction Project Quarterly Report for the end of February has been sent to the NSF.
I have distributed a proposed outline and writing assignments for contributions for the Operations Annual Report and Work Plan for FY 2004. I am requesting input by Friday, July 25, 2003 (sooner if possible). I am also preparing a strawman for the budgets, to be distributed shortly.
During the executive committee meeting held on June 23, 2003, we discussed
the fact that once the Construction effort is closed, we must submit a
final report for Cooperative Agreement PHY-9210038. This can be handled
simply as just an obligation to be completed or as an opportunity to brag
about very significant accomplishments. So far a preferred approach
has not been settled.
As previously reported, the following change requests were reviewed during the executive committee meeting on June 23, 2003:
| CR-030008 | Furniture for the auditorium lobby, interaction area underneath the skylight atrium in the OSB, and on the second floor interaction area of the new laboratory/office building. (ON HOLD pending additional cost data.) | M. Coles | April 29, 2003 |
| CR-030011 | Seismic External Pre-Isolation at LIGO Livingston Observatory | D. Coyne | May 16, 2003 |
| CR-03--13 | Atomic Clock Timing System | Marks, Sigg | June 9, 2003 |
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
no report
LIGO Livingston Observatory (Zucker et al)
-------------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------------
Commissioning:
-------------------------------------------------------------------------------------------------------------
A productive week. We are concentrating on baseline measurements in
preparation for
an upcoming vent to alter the Schnupp asymmetry and recycling cavity
length and
to install the anti-light-saber baffles. Highlights (and bummers) include:
- A power-damaged EO modulator was removed and diagnostics initiated.
A power budget was made for the PSL and losses localized to help
us consider further steps.
- Our NPRO master oscillator laser appears to be going multimode over
a
significant fraction of its tuning range. We have a complete MOPA waiting
in the wings for a swap
opportunity, so rather than fix it we're limping along avoiding
the trouble spots to get other
measurements done.
- Due partly to this problem, which frequently triggered laser frequency
stabilization disease, we have backtracked to a prior version of our frequency
stabilizer, which is less twitchy than our newer "high bandwidth" model.
- We had an intermittent connection in an ETM coil driver which prevented
going to RUN (low noise) mode without breaking lock; this fixed itself
during diagnostics, and will be monitored to see if we can isolate
it if it fails again.
- Despite these issues we are getting an S2-like (low noise) strain
spectrum and have been able to engage all 5 wavefront sensors such
that the alignment is well optimized. We feel we're close to a routine
and robust WFS operating mode sufficient
for S3. We will do further characterization of the sensing matrix
and work on optimizing filters after the asymmetry/recycling length change.
- Our remote PSL power adjust is installed and working.
- We haven't made much progress understanding the anomalous PRC-->AS_Q
coupling highlighted last week by Rana; in addition, a strange temporal
variation in the optimal demodulation phase has been added to the open
mystery list.
LLO PSL (Peter King)
-------------------------------------------------------------------------------------------------------------
The laser power at various places on the PSL table was measured with
a
Scientech calorimeter. The laser output power was 4.80 W.
After the
pre-modecleaner the power was 3.13 W and at the base of the IO periscope
the power was 1.88 W. The 24.483 MHz Pockels cell was visibly
damaged and was replaced.
The mode-matching to the pre-modecleaner was improved slightly, with
the
transmitted power being increased to 3.39 W. The output of the
laser was scanned with the pre-modecleaner and the number of modes between
TEM00s was counted. The count was constant at the positive end of
the SLOW actuator adjust slider.
A quote for new phase modulators was received. New Focus have
not told me if we'd get a discount of any kind.
ISC table acoustic enclosure & misc. (J. Kern)
-------------------------------------------------------------------------------------------------------------
Acoustic enclosure for ISCT-4 was delivered Tuesday, considerably
blemished externally because of carelessly applied tarps by the common
carrier. http://www.ligo-la.caltech.edu/~jkern/AcousticEnclosureDamage/
Refused delivery, but worked with the vendor to locate a local shop
that
could receive the unit and repair it locally.
Spec-ed and ordered RD
modulated, fiber coupled laser diodes for Rai. These to make
RF PD
calibration of ISC tables easier.
Outreach (B. Wooley)
-------------------------------------------------------------------------------------------------------------
A relatively quiet week before the July 4th holiday.
Site construction actiivity (Sibley, Kern):
-------------------------------------------------------------------------------------------------------------
The storage building is complete, just waiting to complete the exterior
grading (delayed
by weather, i.e., mud).
Our front entry gate is complete except for hanging of the gate proper
and finish grading (again, weather).
The LDAS repowering and HVAC rework
is done but we need to revise some air conditioning routing to suit
the as-built heat
loads (see LDAS report below).
The facility pneumatic line rework is done except
for backfilling the holes.
Cabinetry installation in the laboratory is completed. Worked
with the
installer and signed off on the DI water plant tonight.
LLO seismic retrofit (Kern):
------------------------------------------------------------------------
Working closely with Ken Mason and Marcel Hammond
to complete the checking, and
release of fabrication drawings for the External Pre-isolator. Marcel
has traveled to MIT to help Ken with detailing. 4 large purchase
requisitions for catalog items, and 3 for machine and fabrication work
have been sent to Ed Jasnow. Engineering estimates of projected
procurement costs for LLO/LASTI installation are still in the works.
Working on a Solid Works model for the actuator bypass, and ordered
misc
fittings to build a prototype.
General Computing (Shannon Roddy)
-------------------------------------------------------------------------------------------------------------
Installed a new web server for support issues at support.ligo-la.caltech.edu.
The only page up currently is a page detailing how to install printers,
but more will be added in the coming weeks. Much of the informatin
that we have scattered around will be moved to this new web site.
Performed a security audit on our web server in preparation for the
"hacker contest" that was announced on some of the news outlets which is
supposed to happen this Sunday. I may block our web site at the firewall
for Sunday.
Setting up a .6 TB server to perform some testing with various backup
software. Eventually this will be a larger scale server (2 to 4 TB)
for workstation/laptop backups. I will test a couple methods of backups
for windows and UNIX clients.
Patched a few machines with security patches this week.
Tried to contact Sun sales to find out about charges for the LDAP server
offered by them, but their offices are closed all week.
Troubleshooting one of our servers here. I suspect it is having
memory problems. It will not make it completely through an OS install.
LDAS (Shannon Roddy):
-------------------------------------------------------------------------------------------------------------
Installed a KVM extender for Igor. There may be some issues that
I will have to work on with the
vendor, but I have not had a chance to look at it yet.
LDAS (Igor Yakushin)
-------------------------------------------------------------------------------------------------------------
LDAS admin:
1) Continued working on the new cluster hardware installation: wiring
(with Excel), labeling (with Paul Armor from UWM), putting property
tags, etc.
2) Together with Paul labeled all the tapes for L700.
3) Ordered more LC-LC FC cables to connect servers to FC switch.
4) The existing AC does not dissipate heat behind the rack fast enough
(the temperature behind the rack was 83F while the rest of the room
was
cold as usual). I had to buy a few fans as a temporary solution (now
it
is under 70F behind the racks) until the new AC is installed.
5) Bought some tools for LDAS room.
6) Datacon and beowulf machines passed 90 hours of memtest86 without
errors. Running memtest86 on the nodes, so far no errors.
Node 3 has no LED lights. Node 33 at the beginning had problems with
the
network connection which seem to disappear later.
LDAS data analysis:
Looking at the injection data using waveburst and wavemon to see how
well waveburst detects the injections and how well wavemon's vetoes
work.
no report
no report
--------------------------------
Simulation and Modeling (Bhawal)
--------------------------------
Mirror Phase map
-------------------
Raghu Dodda wrote a program to convert the measured phasemap data into
the format which can be used by the FFT program. This is still limited
in the central region. The discussion to run FFT using these phasemaps
will be held this afternoon among, Bill Kells, Biplab Bhawal, Raghu
Dodda
and Hiro Yamamoto. This will be the first run evaluating the LIGO I
performance using the real phasemap. Extension of the measured data
to
cover the entire region is being developed by Hiro, and will be completed
together with Raghu.
Signal simulation
-------------------
Jeff Jauregui studied how the GW strain signal affects the phase of
the
laser propagating between mirrors of a cavity. He has started writing
C++
codes (1) to generate a source and (2) to convert the strain to phase
changes in the two arms. Once these codes are completed, the phase
distortion can be used as a input to a propagator so that e2e can simulate
the effect of the GW signal. Some of the calculation done by K.Cooksey,
2001
SURF stundet, are used.
Noise hunting
---------------
Xiao Xu has start running SimLIGO to understand the difference between
the SimLIGO best and SimLIGO nominal. SimLIGO nominal is a sensitivity
including all known noises and SimLIGO best is the one which suppresses
all
known noises amap, including the 16 bit digitization noise by using
30 bits.
Hiro found that SimLIGO best has some problem, and is hunting for a
fix.
SimLIGO nominal is reasonably close to the Hanford 4k measured noise,
and
we hope this study will shed a light which noise is the most problematic.
Dual Recycling Code
----------------------
Keiko Kokeyama worked with Osamu Miyakawa to start validating the
approximation to be used in the dual recycling summation
cavity module. Using old matlab code written by Malik as a guidance,
she tried to start the code in matlab.
LLO SOS modeling
--------------------
Sany Yoshida and Tiffany are working to build a SOS box to simulate
the
small optics suspension using the LOS box as a template. They studied
the
effect of the control gain and measured spectrum, and overall behaviors
look OK. They are studying the details. Hiro will provide the fit of
the
seismic motion so that they generate the HAM table top motion by combining
with the HAM transfer function.
Transfer Fn of LIGO for changed length
----------------------------------------
(Biplab) Rainer Weiss suggested Ken Yoshiki Franzen of U. Florida to
use e2e
in order to check how the fact that "RM is displaced 2 cm at
LLO" affects
the output signals. Helped Ken to make his model and run it.
Also interacted with Rana and Ken on some issues related to validation
of
signals.
Code development and maintenance
---------------------------------
(Hiro) Dynamic linking of FUNC code:
In SimLIGO, FUNC (expression parser) module is spending majority
of the
simulation time. Code improvement has been done by Hiro and Melody,
but
not much of gain has been accomplished. Now Hiro and Melody are
designing
to use a dynamic linking. I.e., all FUNC codes are compiled using
a c++/c
compiler to generate a dynamically linkable library so that FUNC
modules
are be executed much faster. The algorithm toward this direction
was
discussed, and Melody is preparing a simple example and a wrapper
needed
to minimize the overhead doing this.
(Melody)
- Evaluated several products/research projects in search for
an API
to dynamically compile a C module during runtime.
Came to the
conclusion that doing incremental compiles is a more doable
approach. Started working on a prototype that performs
dynamic
linking.
Alfi
-----
(Bruce) - Writing full Alfi documentation. ugh.
----------------------------------------------
LIGO Data Analysis System Software (Blackburn)
----------------------------------------------
The issues with using optimizations with the new GCC compiler have been
traced
to changes in the nightly build process. We are now definitely compiling
at
night with the -O2 -finlining options that we want to target for the
next
release of LDAS. There are some issues in the frameAPI and eventMonitorAPI
at this optimization level, but it is thought that these are issues
that would
exist without optimization only less frequently - the optimization
level is
giving us a better look into existing bugs. The performance of typical
data
pipelines jobs is now up by about 40% from the optimization and the
RDS frame
creation is up by about 10%.
A set of changes to the LDAS resource files between the 0.6.0 release
which
is currently running at UWM and the 0.7.0 release which is currently
running
at the Lab sites was posted on the LDAS website under the FAQ link.
This will
facilitate UWM's efforts to upgrade over the next couple of weeks to
the
current official LDAS version.
Significant progress was made in getting the metaDataAPI treaded this
week.
The infrastucture for writing to the database has been developed and
is now
being heavily tested. Sevearl issues with this code have been discovered
in
testing and are being worked on. The infrastructure for reading concurrently
from the database still needs to be developed.
A new utility called ldasinfo is being developed to trace the metadata
about
how LDAS was compiled each night. This will provided better visibility
into
changes in how LDAS code is built.
Testing of the controlMonitorAPI on the LDAS-CIT system as new nodes
are
becoming available has revealed several issues with configuration and
the
management of our new much larger Beowulf cluster there. These are
being
addressed in the form of problem reports and bug fixes as they are
discovered.
Building LDAS against the new IBM DB2 version 8.1 continues to cause
issues
under both Redhat9 and Solaris. This week a set of fixpacs were installed
on
a test Sun box to determine if any of these issues have been fixed
in recent
updates to the database. IBM has been contacted and some initial feedback
has
taken place with IBM, but no solution has been provided at this time.
-------------------------------------------------
LIGO Data Analysis System Administration (Stuart)
-------------------------------------------------
Caltech
-------
(Dan Kozak)
* Got Sun to send us a replacement 3510 controller for the one that
failed.
* Configured all but one of the 3510s with 10+1 RAID 1 and 1 hot spare.
* Working to figure out why ldas-archive can't utilize disks bigger
than 1TB.
* Continued re-archiving data in SAM-QFS to higher density tape format.
* Packed up all beta test Qlogic hardware and had it shipped back to
them.
* Started prep work for LHO visit (L700 set up). Arranged travel
for LHO trip.
(Stuart Anderson)
* Diagnosed and fixed problem with Linux SMP kernel and the Copper GigE
device driver (tg3) for the IDE-RAID servers.
* Investigated problem with new 15-slot GigE switch--1 slot appears
to
be bad and Foundry will be out Monday morning to look at it.
* Brought up the first 39 new beowulf nodes into production use in the
LDAS-CIT system.
* Identified 2 more dead-on-arrival nodes out of the 210 units at Caltech.
One spontaneously reboots itself after 10's of minutes and the
other
refuses to boot or generate a video sync signal to get to the
BIOS.
MIT
---
(Keith Bayer)
* Retrieved new NDAS frames from Caltech and mounted NDAS
on ldas and dmt machines.
* In contact with ASA regarding configuration for new pcraid boxes at
MIT.
* Working with Al to update our cfdefs files for new beowulf/datacon
boxes.
* Received test cluster node from Ben at LHO.
* Beginning transfer of S2 double coincidence data via LDR utility.
Livingston
----------
(Igor Yakushin)
* Continued working on the new cluster hardware installation: wiring
(with Excel), labeling (with Paul Armor from UWM), putting property
tags, etc.
* Together with Paul labeled all the tapes for L700.
* Ordered more LC-LC FC cables to connect servers to FC switch.
* The existing AC does not dissipate heat behind the rack fast enough
(the temperature behind the rack was 83F while the rest of the
room was
cold as usual). I had to buy a few fans as a temporary solution
(now it
is under 70F behind the racks) until the new AC is installed.
* Bought some tools for LDAS room.
* New Datacon and beowulf machines passed 90 hours of memtest86 without
errors. Running memtest86 on the nodes, so far no errors.
Node 3 has no LED lights. Node 33 at the beginning had problems
with the
network connection which seem to disappear later.
(Shannon Roddy)
* Installed a KVM extender for Igor. There may be some issues
that I wil
have to work on with the vendor, but I have not had a chance
to look at
it yet.
Hanford
-------
(Greg Mendell)
* A level 2 RDS with the LLO L1:LSC-AS_Q channel for S2 is now
available at LHO. On fortress the data is under
/frame40/rds/S2/LLO/L2ASQ/Data[0-310]. To access the data from
an LDAS
framequery specify the interferometer as L and the frametype
as
RDS_R_L2.
* Currently working with Robert Schofield to create an intersite S2
PEM
RDS for his analysis.
* Ben Johnson has continued to work on installing the new beowulf
cluster. All but two of 140 nodes have passed memtst.
(The two that did
not would not even boot. One other node also would not boot,
but worked
after reseating cables.) The failed nodes were sent back
to the
manufacturer and have returned, but have not yet been tested.
The
current effort is to install RedHat 9 and configure the nodes
using
systemimager. As usual, there are some issues with getting
this to
work, but we expect these will be overcome soon.
-------------------------------------------------
Data Analysis Activities (Anderson for Lazzarini)
-------------------------------------------------
(Greg Mendell)
Mike Landry and I have begun work on the stack-slide algorithm to search
for periodic gravitational waves. At the PULG F2F meeting June 16-17
we
gave our initial report and discussed various versions of the algorithm
and how to implement it. What targets to consider, based on the
available computing power, was also discussed. Mike's priority for
the
past week has been to get the calibration ready and mine has been to
get
the knownpulardemod code working with latest versions of LAL.
The
former is need by all the S2 analyses, and the latter code will form
the
basis of the stack-slide code. The stack-slide code will be designed
to
incoherently add the power from either SFTs for the F-statistic,
correcting for spindown and modulations induced by the detectors
motions, and will run in parallel under LDAS.
(Igor Yakushin)
Looking at the injection data using waveburst and wavemon to see how
well waveburst detects the injections and how well wavemon's vetoes
work.
(Laura Cadonati)
- Continued detector characterization glitch investigation with Mayur
Desai and with the rest of the S2 glitch team. The status report
is
available at http://ligo.mit.edu/ldas/dc/dc20030703.html - Completed
a
set of S1 Zwerger Muller injections and efficiency determination
(simulations performed by B. Shields, UROP student for the spring
semester) and produced a smaller set of the same simulations
for S2.
Performed also efficiency studies for sine gaussians and gaussians
in
a portion of the S2 playground. Roughly speaking, the analysis
being
the same, we gain about a factor 10 in sensitivity from S1.
Plots and
numbers, for a first analysis of the S2 playground, are
available at
http://emvogil-3.mit.edu/~cadonati/S2/PlaygroundFirstPass/index.html
- Completing the hardware-software injection comparison with fits of
ETG response vs injected amplitude:
http://emvogil-3.mit.edu/~cadonati/S2/Inject/S2injections.html
- Preparing my r-statistics talk for Amaldi
(Peter Shawhan)
Working with Evan Ochsner (SURF student) on filtering for inspiral
chirps, first with a simple program, and now moving toward using the
standard search code in LAL/LALwrapper.
(Alan Weinstein)
- Reviewed the comments from the LSC reviewers on the S1 burst draft.
- Studied the characterization of burst amplitude with h_char.
- Calculated poisson upper limits on S1 burst results.
---------------------------
General Computing (Wallace)
---------------------------
MIT:
-Working on X30 laptop with memory problems
-Investigating DVD burner with linux (for ldas laptop users)
-Looking onto large external SCSI drive as backup for gc fileserver
Livingston:
(Shannon)
-Installed a new web server for support issues at
support.ligo-la.caltech.edu. The only page up currently is a
page
detailing how to install printers, but more will be added in the coming
weeks. Much of the information that we have scattered around
will be
moved to this new web site.
-Performed a security audit on our web server in preparation for the
"hacker contest" that was announced on some of the news outlets which
is
supposed to happen this Sunday. I may block our web site at the
firewall for Sunday.
-Setting up a .6 TB server to perform some testing with various backup
software. Eventually this will be a larger scale server (2 to
4 TB) for
workstation/laptop backups. I will test a couple methods of backups
for
windows and UNIX clients.
-Patched a few machines with security patches this week.
-Tried to contact Sun sales to find out about charges for the LDAP
server
offered by them, but their offices are closed all week.
-Troubleshooting one of our servers here. I suspect it is having
memory
problems. It will not make it completely through an OS install.
Hanford:
-Setting things up for the OC3 upgrade. The upgrade was delayed a few
days and
should take place on July 7th.
-Setup new alias lists and updated existing lists.
-Working on a e-mail vacation message program/setup.
CIT:
(Mike)
-Performed the end of the month back ups on all NTSRV's and updated
OS &
security patches; this also included updating firewall software.
-Loaded three PC's with OS & General Computing Software plus multiple
engineering packages, for surf students that are working under Riccardo.
I
also had to enable/test multiple data ports for these additional workstations.
-Swapped out Lee's old computer with an updated PC. This included loading
2000 pro and all GC software and recovering his old data setting up
e-mail
and network printer.
-Loaded a PC with OS & GC software plus added additional hardware
for
backup purposes; plus I run a separate data drop from DCC to our Server
Room.
-Backed up Ryan & Cindy's computer plus updated OS & Security
patches.
-This past week I have been real busy with onsite support that includes
networking, printing and e-mail issues. I also had to load additional
software for surf students.
(Lisa)
- Began looking into new spam software. Blackhole looked promising
but requires
every individual user to forward their e-mail into the blackhole program.
This
clearly won't be appropriate in our environment. There are a
couple of other
open-source programs I am going to look at before looking at commercial
software.
- Fixed a problem with a rav loop that one user was getting between
their ligo
account and their ITS account.
- Did monthly backups.
- More user support.
(Veronica)
- LIGO website: Prepared high-resolution images for a UK Government
Research Council. Burned a CD with copies of the images for Dave Beckett's
archive.
Obtained pricing and ordering information on a software package for
Larry.
Working on issues of access to Internal Bulletin Board.
Evaluating a proposed DCC system setup change. Working with George
Stokes
on troubleshooting of the DCC database.
Videotaped part 2 of a lecture on LIGO by Alan Weinstein for SURF
students.
Caltech Public Relations office requested video footage of aerial overview
of LHO for a PBS special. I checked the existing video archive of VHS
and
DV tapes to see if we have it. We don't, so I offered the PR office
DV
videos of Hanford construction progress. Awaiting a reply.
Edited the roster database. Posted updates to LIGO home page and to
several subpages. Captured a LIGO-related web article by GSFC as a
complete package of files/images/animations and migrated it to LIGO
webserver for archiving and long-term access.
- LSC website: continue working with Peter Saulson on
updates/modifications of the website. Posting updates as they come.
- Project Science: user support. Provided Sydney with an 'address book'
importable to Pine for mass announcements to the PS mail list.
- CaJAGWR: website update. User support.
(Larry)
-Spent a great deal of time setting up accounts and getting visitors,
SURF
students and others setup. It appears we will shuffling things around
for most
of the summer.
-Worked a number of procurements. Most are supply or low-end items.
-Setup another color printer for testing. So far it looks pretty good.
Started
checking out a color B-size laser printer for a couple of areas.
-Worked a couple of network issues. Spent time on a LDAS Foundry switch
and a FE
will be coming in to work on it.
ITS has scheduled the CISCO upgrade in the server room for the week
of July
14th.
-Helped out the DCC with some minor issues. Mostly printing and file
movement
problems.
Working
on MC FEA and quad layout.
Caroline Cantley and Justin Greenhalgh
are visiting from the
From: "Mark Barton" <mbarton@ligo.caltech.edu>
This week I finished off and posted on my models
page (<http://
www.ligo.caltech.edu/~mbarton/SUSmodels/>) the restructured Matlab
modelling code that I was working on last week. In the process of this
I
examined the feasibility of adjusting the matrix elements to allow
for
the fact that the blade springs are actually horizontal) as opposed
to at
right angles to the wires, as in the current approximation). I got
the
vertical working, but the other degrees of freedom look too hard to
be
worth pursuing, at least as a retrofit. Instead I created a 'lite'
version of my Mathematica quad model, with most (5 out of 6 DOFs) of
the
over-fussy modelling of the blade springs stripped out. This will be
useful to Aidan Crook who I've been helping with a modelling project
for
Mike Smith. (We're going to get him to add violin modes to it and
incorporate it into a global control model to investigate the best
way to
apply the laser actuator being developed.)
PHOTON DRIVE R&D
Tom Essinger-Hileman is designing the
optical system using the ABCD matrix formulation with Mathematica.
He has made a preliminary layout of the 40m photon drive experiment using
ACAD. Most of the parts have been received for the apparatus. Steve Vass
will place a 3ft x 4ft optical table at the end of the MC chamber for mounting
the apparatus and will move the OSEM wiring to the side viewport;
the actuation beam will enter through a new viewport
in the end of the MC chamber and will reflect from the back side of MC2
mirror. No steering mirrors will be needed on the MC2 optical table inside
the chamber. Tom has written a progress report.
Aidan Crook has made a Simulink model
of an SOS mirror suspension having displacement and pitch motion with photon
force actuation on the mirror; the model includes velocity damping for
both motions. He has written a progress report.
For additional information about this report, contact sanders@ligo.caltech.edu