|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday June 16, 2003 will be:
STAFFING COMMITTEE MEETING
THANKS TO ALL WHO BROUGHT US TO THIS SUCCESSFUL REVIEW THROUGH THE HARD WORK ON ADVANCED LIGO DEVELOPMENT AND THE HARD WORK ON INITIAL LIGO THAT THE PANEL CITED AS REASON TO HAVE CONFIDENCE IN US.
GHS
SUMMARY REPORT TEXT:
• Advanced LIGO will provide the capability to observe a variety of astrophysical phenomena including inspiral events, continuous-wave sources, bursts, and stochastic backgrounds. Achievement of the design strain sensitivity (more than a factor of ten beyond Initial LIGO) is feasible and detection of events is plausible. Detection of any source would be a dramatic direct confirmation of the existence of gravitational waves and would have exciting and wide-ranging implications for gravitational physics, astrophysics, and our understanding of the universe.
• The committee agrees that the current state of the proposed project is at a sufficiently mature level that the process leading to construction should proceed. Although technical challenges remain, the plan for solving the technical problems appears sound and no major obstacles have been identified that would justify delaying the construction of Advanced LIGO.
In detail the committee has observed that:
• The procurement of optimal coatings for the advanced LIGO detector
represents a significant technical risk, but the evaluation and down-selection
processes for this item have been identified. Given the potential
options available, the range of uncertainty encompasses variations of a
factor of 20% in sensitivity to the detection of sources.
• Two options exist for the test mass substrate material for advanced LIGO: sapphire and fused silica. There are appropriate technical evaluation and selection processes in place. Only one vendor currently appears capable of supplying sapphire substrates and the required low absorption in large sapphire material is yet to be demonstrated. The range of uncertainty associated with the available options encompasses potential variations of a factor of 20% in sensitivity to detection of sources.
• The plan for procurement of the 180-Watt laser for Advanced LIGO is sound. A major challenge for the laser program is the demonstration of amplitude stability at the level of 2 10-9/ Hz 1/2. The potential risk is a factor of 20% in sensitivity for the detection of sources if design goals are not met.
• The optical components must be tested at the expected high-power operating levels associated with Advanced LIGO to insure that potential issues including charging, absorption in sapphire, mechanical losses in the coatings, and long-term degradation are addressed.
• The seismic isolation concept is based on substantial experience at JILA. The control of a two stage platform, with the required gain, in the 1-10 Hz band is a challenging task. Results of the simulation and first dynamical tests on the Stanford prototype (ETF) are encouraging. Further testing at the ETF will be valuable for the control strategy and to demonstrate the satisfaction of the requirements.
• We commend basing the suspension design on the mature and proven GEO600 design. The planned integration of a full scale prototype combining the suspension together with the active seismic isolator in the LASTI facility will be very valuable test. Damping of internal modes is required. Special attention is required to avoid introduction of sensor noise into the observation band. Full modeling of the seismic isolation and the suspension system is encouraged.
• We recommend that the Advanced LIGO team investigate the importance of the electrostatic charging of the mirrors soon. Charge buildup mitigation measures may influence the mirror design.
• End to end (e2e) modeling has been critical in predicting operating parameters of Initial LIGO. We encourage the adoption and expansion of the e2e-modeling to Advanced LIGO prior to the construction phase. Additional resources may have to be added.
• The committee commends the progress in creating the data analysis community within the LSC. We support the distributed computing model and their expanding use of the Grid. Their plan for Advanced LIGO computing is sound.
• The committee looked at the cost estimate for Advanced LIGO construction and in a few selected cases examined how the estimates were arrived at down to the most detailed WBS level. The committee concludes that the cost estimate is the result of a very thorough and well executed process and found no reason to question the reliability of the estimate. Given the good track record of their management team in the cost estimates and execution of the initial LIGO project, the committee concludes that the present management team has a high probability of completing Advanced LIGO with the cost estimate presented.
• Based on the quality of the cost estimate and the good contingency experience in the initial LIGO construction project, the committee concludes that there is a good chance that the level of 27 %contingency will be sufficient to complete the project. As protection, a list of possible scope reductions was identified, totaling somewhat over 10% of the total project cost. Some of the items on the list allow the scope to be recovered at a later date without severe schedule penalty, others are of a nature that the scope reduction can not be restored and thus lead to significant reductions in the eventual sensitivity of Advanced LIGO.
• The estimated operating budget for Advanced LIGO represents a substantial increase over the present level of operating and R&D support of Initial LIGO. The committee believes that given the added complexity of Advanced LIGO such an increased level is reasonable but should be revisited as the project matures.
• Given the good schedule performance of the initial LIGO project the committee has no reason to doubt the validity of the schedules presented for the completion of the Advanced LIGO project.
• The management plan for Advanced LIGO is based directly on the approach and tools that have already proved to be successful in managing initial LIGO essentially on time and budget. This approach could well serve as a model for other major scientific construction projects.
• The total funding plan relies on a number of different sources of support – new funds for construction, R&D funding from the current operations budget, installation and commissioning funds from the anticipated cooperative agreement for 2007-2011, individual grants to members of the LSC, and contributions from foreign partners. Close collaboration with the NSF will be required to ensure that both adequate coordination of funding sources and compliance with internal regulations at NSF are maintained.
• An installation plan has been developed which makes maximum use of existing manpower and minimizes the need for extra contract labor. It assumes roughly a six month stagger between the start of installation at each of the laboratory sites and extends for about two years including the commissioning. To aid in the installation of the significantly more complex in-vacuum components, the LASTI facility at MIT will be used as an instructional test bed for training personnel for the installation. The committee endorses this plan.
• The LSC and LIGO observatories are to be commended for a sustained commitment and planning process to produce a coherent strategy for developing future education and outreach initiatives. The current NSF proposal for the observatories has been developed through an excellent planning process that builds community support. The timeline is reasonable and the new staff is adequate for the start-up period.
• Scaling up the assessment of educational needs from 2 to 30 - 40 institutions requires careful planning so that LSC members build local community support through personal contacts. The relationships among scientists, teachers and community members are key to the success of local programs. One possibility is to build an inventory of core program models for K-12 from which LSC member institutions can pick and choose to create their own focus. These programs should not replace participation in ongoing local programs that are outside the scope of the core programs.
• Depending on the number of LSC member institutions that offer
education and outreach activities, and the design and scope of the core
program, it may be necessary to hire additional outreach assistants to
maintain an adequate support level that assures program quality and supports
evaluation and reporting requirements in 2006. A realistic staff member/member
institution ratio might be 1:12 – 15.
no report
LIGO Weekly Site Telecon (Lindquist)
There was no site teleconference held on Thursday, June 12, 2003 due to the NSF Review of the Advanced LIGO Proposal.
The list of current actions revised to reflect
the status of open actions assigned through May 29, 2003 may be found at
ACTION
LIST.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
ACTIVITY
Press here to
access the DOCUMENT CONTROL
CENTER WEB PAGE.
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA .
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
SUPPORT (Baldon, Lloyd, Tischler)
>Irene Baldon
Attended NSF review meetings on June 11th and 12th.
For list of documents that are being used to develop Adv. LIGO Cost and Schedule, see http://www.ligo.caltech.edu/~tfrey/Cost_MTG_082002/
Advanced LIGO MRE Proposal (Highest Priority)
Project Web Site for posting schedule and progress related data continues to be updated with the latest and greatest.
The Construction project quarterly report for the end of February was scheduled to be submitted at the end of March. Irena has been working on this, but has been distrtacted by a number of other priority issues: LSC, contract activities for seismic isolation, optics coatings, etc. We have discussed priorities, and the quarterly report is still slipping.
Things we are going to need to do in the near future include the work
plan for FY 2004 Operations, the Final Report for the Construction Project.
The following change requests are pending or new. Dennis Coyne submitted CR-030013 for Atomic Clock Timing Systems. I will request that these change requests be placed on the agenda for the next meeting of the Executuve Committee.
| CR-030008 | Furniture for the auditorium lobby, interaction area underneath the skylight atrium in the OSB, and on the second floor interaction area of the new laboratory/office building. (ON HOLD pending additional cost data.) | M. Coles | April 29, 2003 |
| CR-030011 | Seismic External Pre-Isolation at LIGO Livingston Observatory | D. Coyne | May 16, 2003 |
| CR-030013 | Atomic Clock Timing Systems
|
D. Coyne | June 9, 2003 |
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
Summary of Commissioning Activities at LIGO Hanford Observatory (compiled by M. Landry)
We have had another incident on the LHO 2k IFO in which a small optic wire has broken. Unfortunately, the wire supporting MMT1 was severed by the laser during positioning of the RM to land the beam on the new combined MMT2 baffle and beam dump. Currently a spare MMT1 optic is being prepped, plus additional baffles for installation in HAM7, likely mid or late next week. Modelling is underway to better understand stray beam paths; for the time being we've shuttered both the 2k and 4k lasers. Work that does not require the interferometers, such as PSL/PMC/RefCav tuning, and AS sensing chain measurements, is underway.
A series of elogs relating to MMT1 can be found starting here.
SURF students have a arrived at the lab, including Katherine Pegors, Anah Mourant, Rachel Berkowitz, Jared Markowitz and Drew Barker.
4K IFO
After last week's vent, the 4k ITMX pointing was restored with a 0.55mrad rotation in yaw via the coarse actuation system (Guenther, Radkins, Sigg). Radkins notes that flaky behaviour and delays in coarse actuation startup were due to faulty cable connections at the CA computer. Initially, floating of the air bearings excited the optics, possibly due to underuse: the remainder of the yaw actuation was smooth. Read some CA entries here.
The 4k MC and PRM had been relocked earlier in the week, but we have
not been able to expose the arms to the cornerstation. It is likely
that the vacuum will be at a sufficient level to do so next week.
no report
Jonathan Kern
Ameritech, the manufacturer of HEPI bellows was given
a small order for
quantities manufactured of 300 series alloy as well
as 17-7ph. Both
bellows types have now arrived and both look very
nice. The 17-7 PH
have a slight straw color due to the heat treating.
We have prepared one
of the 304 bellows for test. It is welded to
a replica of the stainless
flanges and spaced apart by spacers of the correct
length. The bellows
under test will be filled with water and placed in
a sealed chamber with
an acrylic lid. As the pressure is increased
inside of the bellows, air
pressure in the chamber will be monitored with a 0
to 20 inches of water
gauge. This will detect any yielding that occurs
on the bellows,
regardless of it's location. Expect test results later
this week.
RFQs were sent to numerous shops for the machining
of actuator parts,
assembly of the actuator, machining and assembly of
the double-start
springs and quantities of Parker servo valves. Replies
were asked for by
June 10. Not unexpectedly a few have missed
the deadline and I'm
prevailing on them to get me their quotes ASAP.
HEPI Pump Station
Ken Mailand
Continuing on the following HEPI tasks:
Myron will sent me the LASTI pump, filter, coupling
and a sample of the working fluid
The replacement pump and motor and coupling sent to
LASTI have been installed and are running well and quiet after 2 weeks.
I will forward the received items to the lab for examination.
I have received a quote on a contaminant characterization
assessment for the LASTI pump station 3 micron filter.
I received a preliminary quote on time and delivery
of the site installation stainless reservoir
I have contacted the manufacturer of the LASTI 'Aquamil'
fluid and have been referred to their lab that will do an analysis of the
fluid in use now.
I have contacted IMO pump and discussed the issues
with pump noise, and described the type fluid we are using, and the operating
conditions of the pump.
IMO has sent me a return authorization for the pump,
they will set up the pump in the lab and run it, then take it apart to
find what may be making the noise.
A request for quote on price and delivery of a 55
gal quantity of clear Chem-Sol has been made, as a possible alternate fluid.
The fluid biological growth test is showing nothing after 27 weeks.
(past CDS weekly meeting minutes can be found in the commissioning archives)
Primary goals for this week are to get the ETM controls
installed and running
the the 40m lab and, now that we have enough high
speed (2Gbit/sec) network
interface boards, to remove the slower network completely
from the 40m lab and
go with the single fast network.
The first objective is almost complete. The ETM control
PC and ETMY VME systems
are installed and running. There is about a day of
testing remaining, primarily
DAQ and GDS connections. The ETMX VME is a direct
copy, so should come up
quickly after ETMY testing.
The move to the single network is complete, but there
was a snag. The Arbitrary
Waveform Generator (AWG) software was written to run
on the older MIPS
processors, but the new network cards do not work
on these CPU boards (don't
even get power indications on the cards). So, we have
had to port the AWG code
to Pentium processors. While this seemed straight
forward and compiled fine, it
did not work properly. It looks like Alex got it running
last night though, so
we'll test it more thoroughly today.
Hongyu is working on a change request to dataviewer.
This change is to provide
"drag-and-drop" channel selections to simplify this
procedure.
Alex and I will be at MIT next week. We'll be there
to look at EPI and plan the
controls and their integration with the LLO system.
We also want to look at the
AdvLigo suspension controls for eventual port to LIGO style controls.
Jay Heefner reporting
LOS Coil Whitening Board
- 15 boards are now in fabrication and test. They
should be ready for shipment by 6/19.
EMI Retrofit
- Met with Knurr to discuss the test results and requirements
for the VME crates and racks. It turns out that the Knurr factory in Europe
has produced shielded VME crates and racks that have specs much closer
to what we need.
- Worked on the equipment relocation proposal with
Rus. A draft of the proposal has been sent to Dennis for review.
- Equipto has submitted a drawing for the feedthrough panel on the top of their rack. On first glance it appears to be too small (2.25"x17.25").
Sander Liu
Working on the L4C preamplifier design.
NPRO S/N #259, originally from the 10-W laser at LLO,
was shipped to
LLO to replace the master oscillator. A return
home, in some sense. Joe
Kovalik installed the NPRO and brought the laser approximately
back to
where it was.
I made a few measurements on the
10-W laser power supply. The current
loads when the laser was on standby and lasing were
noted. In a discussion
with Shannon Gomes of Lightwave Electronics, I found
out that the fuse
holder in the 10-W laser power supply has a tendency
to get extremely hot
when the contacts oxidize or when any dust gets in.
The power supply
installed in LLO:1X3 has had the fuse holder changed to a different style.
The 2K RM beam dump located on the MMT2 baffle was placed too low, beyond the range of the pitch OSEM. The beam dump will be relocated on the MMT1 baffle 50mm below the beam line; to hit the beam dump will require a an upward pitch angle of the RM of 0.3 mrad. The 4K beam dump will also re relocated on the MMT1 baffle 50mm below the beam line, and will require an upward pitch angle of the RM of 0.5 mrad.
OTF Lab. (W. Bridge)
Contamination Cavity # 1
we are continuing taking ring down and beat frequency every day for
the test sample a 10mm Capacitance position sensor (given By:
Rich Abbott)
which consist of a sma cable and a ceramic connector at the end.
So far we can tell from the Beat frequency and ring down that this
sample is clean.
Basically there is no contamination.
Please see Dr. Zhang graphs for absorption, ring down and thermal lensing.
Absorption Test Measurement prototype in progress
Scatterometer system is in STANDBY for measurements.
We are taking more absorption measurements for the 6 inches in diameter
by ~ 3 inches thick Sapphire mirror.
We are characterizing a new sapphire mirror given by Garilynn.
This mirror has different diameter (5.90 inches) than the previous one
and as right now I am making the new base holder for this mirror.
We will be measuring the scattering, transmission and more important
its birefringence measurement.
OTF Lab at Lauritsen ROOM 38
Cavity #3
This cavity has 70 ppm mirrors and hung with one end at 1.8 degree
higher that the other end.
Cavity is locked and we have 147 mw of power with a 95% ! visibility.
We are taking ring down and beat frequency every day.
Cavity #2 Test cavity STILL in STANDBY.
Optical train upgrading is in progress.
New cavity assembly still in progress.
Misc. tasks.. placing orders to modify the scatterometer system.
no report
report in Advanced LIGO report
Simulation and Modeling (Bhawal)
SimLIGO
--------
(Matt) This week I worked on turning out an update to SimLIGO. The
new version
includes a working Common Mode servo (using the standard control
scheme
rather than non-resonant sidebands), ASC control of all DOF,
functional
if not robust lock acquisition, and many automated measurement
scripts.
The noise curves produced by SimLIGO continue to show an unidentified
noise source between 30 and 300Hz that fills in the bottom of
the spectrum.
We suspect that this noise arises from some non-linear effect,
but
the details are not understood. If this is not an artifact
of simulation
it has potential to be a limiting noise source for LIGO, so finding
its origin is of some importance. Interersted readers may refer
to:
www.ligo.caltech.edu/~e2e/pdfs/SimLIGONoise030611.pdf .
WFS signals
------------
(Biplab) Calculated WFS signals for the as-built LIGO hot-state and
near-hot
states. Trying to understand trends for some differences.
Code development and maintenance
---------------------------------
(Melody)
- Worked on figuring out why NaN's were being generated for
the SimLIGO
output file by the modeler compiled with no optimizations
using
gcc 3.2.2. The cause was an unitialized value in
one of the modules.
- Finished comparing the results generated by Sun and Linux
systems
using different compiler versions and optimization
levels.
- Started looking into using a compiler to process the FUNC_xxx
modules.
(Hiro) Studied Matt's new optics model; Worked with Melody to understand
the compiler dependence/CPU dependence.
Alfi
-----
(Bruce)
- Completed work on Copy/Paste
problems with Macro and settings not
being copied
into the new nodes properly (PRs 394 and 413).
- Fixed problem with junction
removal (PR 412).
- Implemented changes in
Alfi which cleared up inconsistencies in
where the E2E_PATH
was being found/generated (PR 395).
- Created a script for Unix
for startup of Alfi via WebStart which
will allow command
line arguments to be used (PR 401).
- Created documentation
on the Web for many of these new features
as download/install
instructions where needed (partial PR 376).
LIGO Data Analysis System
Software Systems (Blackburn)
A problem with the database tables at LHO was discovered while upgrading
that
site to the new release of LDAS. This required a full days effort by
Mary and
Igor to sort out and test. It eventually evolved to require a full
back up and
restore of the database tables there. The problem is thought to be
related to
the T3 crash that occurred during the S2 run at Hanford.
We have started testing the RDS frames in the archive on the LDAS-CIT
system.
This is being done by running a couple of the burst jobs on all the
lock data
sections. We are about half way through the Hanford RDS frames at this
time.
So far we have discovered one bad RDS frame and one lock section (according
to the DMT lock segments in the database) with missing frames. Once
a complete
list of suspicious RDS frames are generated Philip Charlton will look
into the
details to see if the lock segment info is incorrect and if the source
frames
for the RDS generation were erroneous before attempting to fill in
any missing
frames (currently thought to be order a couple for LHO). We will then
repeat
the procedure for LLO RDS frames.
Since the code freeze has been lifted, we have begun working on our
targets
for the next release of LDAS we plan the following optimistic goals:
a) migration to GCC 3.3 and possibly GCC 3.3.x (we've already identified
a
necessary patch for GCC 3.3's string class!)
b) migration to 64 bit compilations for Solaris (this will increase
the
amount of memory that can be used in the frameAPI to all
that is in
the server).
c) migration to Redhat 9 (support for Redhat 7.x is being dropped by
Redhat
this year).
d) migration to TCL/TK 8.4.x (this will fix several instabilities in
TCL
code).
e) rewrite the metaDataAPI to be multi-threaded and push computationally
demanding TCL procedures into C++.
f) introduce C++ threaded functions in the diskCacheAPI to eliminate
the
blocking of jobs when the diskCacheAPI is learning about
new frames in
the system.
g) migration to IBM's DB2 version 8.1 or above (Version 7.2 doesn't
work
under Redhat 9 and vesion 8.1 just barely is working and
may require
a new release from IBM to fix the issues DB2 is having
with Redhat 9's
new thread model).
We have improved the distribution of the wrapperAPI's master process
onto
the Beowulf cluster this week. We have started improvements on the
framequery
option to better handle datasets from multiple interferomenters. The
command
to get channel names has been extened to support other data structures
in the
frame spec besides FrADCs.
Several of us in the group have also been involved with the PAC and
NSF
reviews late last week and this week.
Hardware Systems (Wilson for Anderson, who is traveling)
CIT
Al
Set up new nodes for the Dev system. Datacon and Beowulf machines are
upgraded to RH9.0 Also setting up desk top machines for SURF students.
The rack for the Cit system are in place and are ready for the
computers. Also The A/C unit is installed and ready for final plumbing.
Dan
continued refreshing NDAS frames to 9940B (higher density) drives.
Am
continuing to try to get Sun to figure out why the first few tapes
were
written with small block sizes (16k). Subsequent tapes are being
written with the correct block size (256k).
Got StorageTek to bring our 2 new 9940Bs online. Their power
supplies
still don't have the correct mounting hardware. But they are
ready to
go from our end.
(In Powell-Booth, with Stuart) Swapped in our new Jupiter FC switch
to
replace the beta edition we had been using. Installed 3510 disk
arrays
in rack.
LHO
Ben & Greg
Ben Johnson has been doing most of the LDAS system administration work
at LHO the past week, while I have worked with my SURF student and
prepared for next week's PULG F2F meeting. However, Ben and I
(mostly
Ben) continue to work on the installations of the new LDAS beowulf
cluster, new L700 tape library system, new switches, and the recabling
of the LDAS room to work with the new switches. I have also continued
to
work with Igor Yakushin to exchange AS_Q only S2 RDS frames between
the
sites.
LLO
Igor
Reinstalled DB2 at LHO to fix the corrupted database catalog. Copied
LLO's AS_Q only RDS to tape and sent to LHO. Copying LHO's AS_Q only
RDS
to disk (for some reason it is very slow - 10 hours per tape). On Sunday
I discovered water dripping from the ceiling in the LDAS room. AC
repairman told that the problem was that PVC vent, that is supposed
to
be closed, was actually open and sucked an air which condensed inside
the system. The problem was fixed. No damage to LDAS equipment. Writing
scripts to automatically set up replication sources and subscriptions.
Ordered a replacement for yet another failed T3 disk.
Data Analysis Activities (Lazzarini)
Mendell:
1) Started work with my Surf Student, Anah Mourant, on her project
to
estimate signal parameters from simulated continuous wave data.
2) Wrote a simple simulation of the stackslide search and prepared for
the PULG F2F meeting next week. The work in focusing on very basic
things at the moment: understanding the algorithm, its computational
complexity, and associated statistics.
Charlton:
FCT:
The FCT group is working on a new paper describing the "generalised"
FCT
algorithm and comparing it with matched filtering methods.
I have been working on code to demonstrate the fraction of SNR recovered
by the FCT algorithm as a function of chirp times (\tau_0 and \tau_1)
of
an inspiral signal using the LIGO I noise curve.
Chirplets:
I have been working on some prototype code in matlab to decompose a
data
set in a chirplet basis.
Weinstein:
- last week, I prepared & gave a talk on burst search to PAC14
- working on burst S1 paper editing
- trying to quantitatively compare our results with bar results.
Reilly, K.:
This week I finished up the cvs move and helped with getting
people their GC accounts so they can access the stochastic disk space.
I am back to working on the re-design of the stochastic DSO. After
working through some LDAS issues, the intermediate data products
are now being generated here at Caltech. It will take several
days
to have these products in hand.
Shawhan:
I spent several days investigating a peculiar thing that I noticed
about
the Monte Carlo simulation which is used to measure the efficiency
of the
analysis pipeline for the S1 inspiral upper limit analysis: a significant
number of very large simulated signals were not found by the search
code.
Some loss was expected due to the chi-squared cut we make in the analysis,
but the observed loss was much higher than expected. After tracking
this
down with Duncan, Patrick and Jolien at UWM, it turns out that part
of
the loss was due to a bug in the code which caused some of the planned
simulated signals to be skipped; this will require re-running some
of the
Monte Carlo jobs. The rest of the effect is apparently a real
effect in
the chi-squared test which is mysterious but is not as serious a concern,
since the analysis pipeline is identical for Monte Carlo and regular
data.
General Computing (Wallace)
MIT:
(Keith)
-Continuing to investigate triplesync problems with brownbear tech
support
-Investigating samba over SSH for windows PC's
Livingston:
(Shannon)
-Set up several workstations for our summer visitors.
-Attending a Usenix conference and tutorials.
Hanford:
(Christine)
- More SURF student account and computer set-up.
- Computer and account set-up and purchases for summer outreach teachers
and new hires.
- Rack mount and initial configuration of the new Cisco router
completed. Nothing is connected to it yet.
- Spoke with Jim Schroeder of ESnet to schedule connection of our new
OC3 network. The plan is to connect the week of 6/21/03, actual
day and
time to be determined by 6/19/03. ESnet will accept their new
OC12
connection on 6/16 and will do the change over on the evening of 6/19.
LHO will have a short network outage on 6/19 when they do the change
over.
- The PR for the GigE network equipment was sent to Dot last week,
but
there have been some changes to the quote that need to be modified
in
the PR.
- Setting up a new laptop for Fred. Finished setting up a new laptop
for
the new optics lab.
- Lots of user support.
CIT:
(Mike)
-Worked on Barry Barish's laptop due to a wireless problem. I had to
call
this laptop in, after many hours of trouble shooting plus many hours
of
dealing with IBM tech support on the phone trying to order the part.
IBM is
sending me out a replacement part to correct this problem.
-Worked on finishing up loading a workstation for Enrico Campagna.
This
included loading multiple engineering software packages, plus General
Computing software.
I also swapped out his old computer and slaved his old drive to the
new
computer to have this user back up and running, right away.
-Worked on loading two new computers with General Computing software
and
additional engineering software for Alan Weinstein. I also took these
computers over to 40meter and set these workstations up.
-Fixed a problem with M91 our media server that was having a problem
with
backups. I ended up having to stop and restart services. Then I had
to
reboot several times after going through and cleaning up registry errors
that were coming up at the startup after a reboot.
-Updated all NTSRV's with security/os updates.
-Started loading a computer that we inherited from LDAS. I will be
loading
this computer as my master image to load an additional seven computers
to
swap out some of our older computers that will be used for visitors/surf
students.
-Performed a lot of onsite/phone user support this week, that included
software,
networking & printer issues.
-Helped Larry & Lisa set up the NSF conference.
(Lisa)
- Preparation and support for the NSF review.
- Added a new block of IP numbers to DHCP.
- Worked on solaris 9 jumpstart server.
- User support - mostly for the students.
(Veronica)
- LIGO website: installed PAC14 talks. Posted updates to various pages.
Tracked a late Aspen talk and added to the conference website.
Edited a high-res image per a request from MIT for a paper submission.
Made a DVD copy for Kip Thorne. After some trial and error, we decided
that an upgrade was needed for my CD/DVD authoring software. Installed
the
upgrade; picked up a copy of the package for Mike. Use the last CaJAGWR
video as a tryout for video capturing and editing.
Working on an inventory of 'non-static' directories on Windows servers
for
more selective backup, to save tape space.
Provided user support.
- Advanced LIGO website: posted last-minute updates.
- LSC website: discussed with Peter Saulson changes/updates to be made
to
the website. Implementing them one by one.
- CaJAGWR website: taped the last seminar. Processing the video for
web
streaming. Provided user support. Making a backup CD of presentations
located outside of ITS disk space.
(Larry)
-Spent time working on a number of procurements and related issues.
Purchased a
number of misc. items for different people. Spent a number of hours
getting the
warranty upgrade on Barry's laptop. This should help Mike with the
problem he
has had in getting IBM to repair a defective part in a unit we recently
purchased.
-Assisting on the setup for the NSF review has take a great deal of
our time the
past few days. Many thanks to Lisa and Mike for putting in the extra
effort and
time to make sure things worked, not only with the computers but with
the room
setups, catering, audio visual work, moving furniture in and out from
the
different rooms and assisting the visitors with their needs.
-Setup a number of user accounts and reactivated a number of old accounts.
Setup
items for the SURF students. Working with Mike on getting computers
setup for
the visitors we will be having this summer.
-Worked a number of issues concerning the server room.
Prepared
for the NSF Review.
Supported damping work on the MC triple.
From: ctorrie <ctorrie@ligo.caltech.edu>
Mode Cleaner
The mode cleaner suspension has now been damped in all degrees of freedom
and all modes damp down with a settling time of 10s or less.
I have measured the range of mode frequencies and all seem to be within
the expected band. I have measured about 50% of the modes and matched them
successfully with the theory.
The suspension has also been adjusted to be at the correct height above
the optical table within 0.5mm
MATLAB modelling
Ken Strain, Mark Barton, Norna Robertson, Caroline and I met to discuss version control, updates to the MATLAB files used to design a suspension and layout of these files. Several new concepts will be adapted.
Suspensions
Norna and I met to discuss the layout of the ETM. Several key aspects were discussed in detail with Ken Strain and others.
I have been working with BennoWillke
on the material for the NSF
Review. In the process we came across a few items that need to
be updated
in the costing.
.
NSF PROPOSAL
Technical and Cost/schedule information for the AOS subsystem was prepared
for the NSF Proposal review.
- Updated the PSL EPICS screens
- Re-aligned 1 reference cavity
MEPI (Myron, Ken, Rich, Dave, Bill)
We now have a reasonably good data on the sensor correction coefficient
for all three directions. The best coefficient is within 15%
+/- 10%, of
the calculated value in each case. The next step is to investigate
what is
limiting the resolution in these measurements,
we increased the loop gain
past the point where we are gain limited. After that we will
look into
the possibility of filteringStreckhiesen
ground signal to improve the
sensor correction.
HEPI (Myron, Ken, Rich, Dave, Bill)
Nothing new to report
EPI Installation (Ken Mason)
I received all quotes from potential suppliers for the machined and
fabricated parts required to build 11 HEPI systems for LLO and the
remaining HAMS at LASTI. Marie is putting all quotes in excel format
for
comparison.
ISC Optical Periscope (Ken Mason)
The newly designed optical periscope was presented to the commissioning
group for comments. The design was very well received and several
excellent suggestions are being added which will further increase its
stiffness.
Thermal Compensation Advanced LIGO (Dave)
Spent time preparing for NSF Review.
Quadruple Pendulum Prototype (Rich, Andrew)
Andrew Thomas (a summer UROP) has started working on the quadruple
pendulum prototype with the goal of testing global control schemes.
For additional information about this report, contact sanders@ligo.caltech.edu