|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday May 19, 2003 will be:
(Meeting time: 10:30 am Pacific Time)
STAFFING MEETING
It gives us great pleasure to announce that Mike Zucker has accepted our offer to lead the team at the LIGO Livingston Observatory. Mike is a widely respected member of the LIGO Laboratory and the gravitational wave community. He is a pioneer in this field and is currently involved with some of the most demanding problems in our field. He will bring to Livingston his very deep knowledge of our field, his long experience in interferometry and his great leadership skills.
Mike will assume this post this summer and will begin by dividing his time between Livingston and MIT, where he will play a role in the delivery of the new isolation systems to LLO over the next few years.
Mike replaces Mark Coles who will leave LIGO for a very important role at NSF in the oversight of large facilities like LIGO. We thank Mark for his able leadership of the facilities group during LIGO construction and for the fine observatory that he has played an important role in establishing. Mark can be very proud of having arrived on a green field and that, as he departs, the LLO sensitivity to inspirals at 1.2 megaparsecs is world leading. It has been a long path from a green field to sensitivity outside our galaxy. Thank you Mark and good luck at NSF!
Congratulations Mike!
Barry Barish and Gary Sanders
no report
LIGO Weekly Site Telecon (Lindquist)
There was a site teleconference on Thursday, May 15, 2003. The following issues were discussed:
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
Worked with David Shoemaker on compiling a complete bilographic listing of relevant Advanced LIGO documents. Some were already in the DCC, some were downloaded from a website, but many remain unavailable for processing. Will continue working on collecting these missing documents so the list will be fully represented by electronically available versions from the DCC.
Had several major viruses on my computer and Mike and Larry have been working all week to rebuild it. It will hopefully be ready by the end of this week.
To ensure that everything is up and working on my computer, we postponed the start of work for George Stokes until next Monday.
ACTIVITY
| WE 05/15/03 | Packages | Faxes |
| In | 30 | 20 |
| Out | 32 | 18 |
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA .
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
SUPPORT (Baldon, Lloyd, Tischler)
>Irene Baldon
Weekly Advanced LIGO Project Controls meeting was not held this week.
For list of documents that are being used to develop Adv. LIGO Cost and Schedule, see http://www.ligo.caltech.edu/~tfrey/Cost_MTG_082002/
Advanced LIGO MRE Proposal (Highest Priority)
Project Web Site for posting schedule and progress related data continues to be updated with the latest and greatest.
The Construction project quarterly report for the end of February was scheduled to be submitted at the end of March. Irena has been working on this, but has been distrtacted by a number of other priority issues: LSC, contract activities for seismic isolation, core optics, etc. We have discussed priorities, and the quarterly report is still slipping.
I have prepared and distributed a third model for projecting FY 2009 operating costs, and I will now be preparing a supporting document for Gary/Barry review.
I have prepared a response to the NSF DCAA Audit Report Questions.
This material has been provided to Gary before forwarding to Caltech Administration.
The following change requests were considered by the LIGO
Change Control Board (during the Executive Committee Meeting on Monday,
May 5, 2003):
| CR-030008 | Furniture for the auditorium lobby, interaction area underneath the skylight atrium in the OSB, and on the second floor interaction area of the new laboratory/office building. | M. Coles | April 29, 2003 |
| CR-030009 | Cabinets, Case Work, Furnishings at Livingston | A. Sibley | April 29, 2003 |
| CR-030010 | Revised scheme for Technical and Facility grounds at Livingston | A. Sibley | May 2, 2003 |
Change Board minutes have been signed and will be sent to the DCC (LIGO-M030091-00-P).
CR-030008 was held pending additional information--specifically, competitive
bids
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
Met with the individual that is preparing the cost estimate for the server room fire suppression system. Also toured the room and adjacent office space to assess the extent of the modifications required for the fire suppression system. The cost estimate for an Inergen type of system is expected to be available by the end of next week.
Reviewed the draft LHO safety audit action item list with C. Scisiowicz for the final draft of the audit report.
Also reviewed at that time, was the new LLO SOP for Personnel Accountability for the laser safety interlock system and a proposed policy for alarm system trips of the laser shutter. Agreement was made to adopt the proposed alarm trip policy.
LIGO LASER SAFETY ALARM TRIP POLICY
This alarm trip and restart policy is to be
implemented at both observatories, and has two important features:
1. The policy permits laser restart to be administered locally if the alarm trip incident DOES NOT involve an errant beam situation.
2. However, if an ERRANT BEAM condition occurs at any time, then the approval for restart must be obtained from the Deputy Director (G. Sanders).
In all cases, the events are to be recorded
and a summary of these events reviewed at the annual safety audit.
The sites have been asked to make sure that they incorporate this policy
into LIGO laser safety documents where appropriate and that all laser personnel
are aware of this policy.
Summary of Commissioning Activities at LIGO Hanford Observatory (compiled
by M. Landry)
---------------------------------------------------------------------------------------
Locking problems plagued both ifo's, with possible causes including
code changes and
increased vit plant noise.
A suggestion for a possible H1 S2 epoch veto can be found at
http://blue.ligo-wa.caltech.edu/ilog/pub/ilog.cgi?group=detector&date_to_view=05/11/2003&anchor_to_scroll_to=2003:05:11:21:19:31-robert
A measurement of the RF-AM of the 4k MC transmitted light was made,
see
http://blue.ligo-wa.caltech.edu/ilog/pub/ilog.cgi?group=detector&date_to_view=05/14/2003&anchor_to_scroll_to=2003:05:14:13:03:37-gustafso
The 4k relative phase between the I and Q phase signals for both AS1
and AS2 was measured,
http://blue.ligo-wa.caltech.edu/ilog/pub/ilog.cgi?group=detector&date_to_view=05/13/2003&anchor_to_scroll_to=2003:05:13:17:39:46-rick
A 4k y-arm length measurement was performed,
http://blue.ligo-wa.caltech.edu/ilog/pub/ilog.cgi?group=detector&date_to_view=05/14/2003&anchor_to_scroll_to=2003:05:14:17:07:59-rick
The LSC, ASC and endstation code was cycled through several upgrades
and debugging
sessions, in part to accomodate high power operation. A list
of the changes to the code
can be found at
http://blue.ligo-wa.caltech.edu/ilog/pub/ilog.cgi?group=detector&date_to_view=05/09/2003&anchor_to_scroll_to=2003:05:09:17:23:10-rolf
Interferometer: We installed the spare MOPA in the optics lab and are preparing it for a swap with the one on the PSL table. We now see 9.3 Watts out of the laser with the pockels cell installed and aligned. Efforts continue to measure the length of the recycling cavity. Andri now has a preliminary result. The counterpoiseground surrounding the X-end station has been reworked and brought up to code. Work on the X-mid station is underway. Interferometer spectra will be acquired to assess the benefit of this. Work continues on the implementation of the WFS loops. This work has been frustrated by slow angular drifts in ETM-x which have made it difficult to maintain a stable alignment.
LDAS admin:
1) Replaced failed T3 disk.
2) Ordered UPSes and cables for the new hardware.
3) Copying NDAS frames from tapes to hard disk.
LDAS data analysis:
Working to add noise estimate for each event in the waveburst to have
a
consistent procedure for setting thresholds for corresponding events
in
different ifos.
(Igor)
GC:
Setting up a laptop for Bonnie to use next week for a presentation.
Setting up Gerry's old machine for Doug's use as a dual boot workstation.
Helped Ed Daw look at Alvar since it did not come up properly after
a power failure in the mass storage room.
Considering buying a couple more RHN accounts from Red Hat since more
and more people are wanting to dual boot their machines. This helps me
keep up with whether or not they are doing security updates, etc.
Working on the modem issue. Bellsouth changed our phone lines from
analog to ISDN this week and the modems will need to be replaced/reconfigured.
The connect speed is about the same after the conversion, but I have a
new piece of hardware I need to try. Hopefully this will improve the dial
up speeds and allow me to replace the portmaster which appears to be dying.
Reinstalled the OS on the scanner machine and bought a USB drive adapter
so that the old files are still on the machine.
set up a couple of new accounts and also did some work on the form
that I am using for new accounts. I am requiring people to fill out this
form and agree to the computer usage policy before I activate the account.
This form has worked pretty well so far.
LDAS:
Discussed the power and cooling requirements for the new LDAS hardware
in the LDAS room. Long term I believe that the cooling system in the room
will have to be changed. Short term, I think we are OK. Allen is looking
into this. Also Rusyl is working with the contractor on the power requirements.
We have added 12 more pieces of CAT5 cable between the LDAS room and
the comm. closet so that we can get away from the temporary GC connections.
This will also allow me to hook up the KVM to Igor's office.
(Shannon)
Other: Barry announced to an all hands meeting of the LLO staff that Mike Zucker will become the new Head of the LIGO Livingston Observatory. Congratulations Mike!
Detector/Technical Support (Coyne)
The EPI review committee report is likely to be released Friday 5/16. A CCB request will also be submitted Friday for allocation of required funds. (Fabrication accounts have already been established.)
Jonathan Kern
Activity limited to planning, scheduling and obtaining
estimates of
prices and deliveries of purchased components.
Distribution of duties
remains:
- Ken Mason is bringing his EPI package up to
date. ASAP, production
drawings of the general purpose EPI will be sent to
several shops for
competitive bids for ~49 units (3 MIT HAMS, 4 LLO
HAMS & 5 LLO BSCs = 12
vessels, + 1 spare)
- Jonathan will update hydraulic actuator drawings.
- Ken Mailand is designing the production pumping
station, based upon
T030034-00.pdf. Likewise piping runs in the
LLO LVEA.
- Rich Abbott will begin a skeletal instrumentation
diagram. Stefan and Rolf are working on getting a VME system running at
LASTI for migration of the dSpace controls to VME.
- Marcel is lightened the spring design.
- Jonathan is getting competitive bids on ~100
spring assemblies.
Ken Mailand
I received a preliminary quote on time and delivery
of the site installation stainless reservoir
I have contacted the manufacturer of the LASTI 'Aquamil'
fluid and have been referred to their lab that will do an analysis of the
fluid in use now.
I have contacted IMO pump and discussed the issues
with pump noise, and described the type fluid we are using, and the operating
conditions of the pump.
IMO has sent me a return authorization for the pump,
they will set up the pump in the lab and run it, then take it apart to
find what may be making the noise.
A request for quote on price and delivery of a 55
gal quantity of clear Chem-Sol has been made, as a possible alternate fluid.
The fluid biological growth test is showing nothing after 23 weeks.
files that were lost when the T3s crashed at LHO on
March 5th. Keeping
several jobs reading data synchronously required that
I distribute data
to the processes via the shared memory mechanism used
online. This was
problematic because of several incompatibilities between
the new gcc
streams and the previous implementation. I chased
down several bugs and
inefficiencies and have fixed them in the DMT code.
I have also started to modify the Trigger client class
to optionally write
triggers directly to LigoLW files rather than sending
the triggers to the
trigger manager. This will simplify running trigger
generation jobs
offline.
able to get a few short lock stretches, but there
are still a couple of
problems:
for many hours before this occurs. I've put in a few
traps to try to track this
down, but the system gets rebooted before I'm made
aware that a problem occurred
and my trap indicators are erased. I've informed Barker
as to what to look for
when it happens again. I have been unable to reproduce
this problem at Caltech,
having left the LSC here running for days and injecting
signals everywhere I can
think of.
get overloaded, resulting in slow screen updates and
EPICS can freeze after some
number of hours. I've rebuilt the EPICS part to run
on a MIPS CPU to see if that
will help. I'm thinking of possibly moving the EPICS
out of VME all together to
a Linux box. The Linux EPICS has been running very
well in the 40m lab for a
month or two.
I am continuing to test here, but will return to LHO
next Monday to try and
track the problems, as I haven't been successful in
reproducing the problems
here.
- Worked on 40m systems. Code had to be fixed this
week to get the all the
suspension signals into DAQ properly and the MCL signal
properly sent to EPICS
from the suspension PCs. Also, added the capability
of the IOO VME system to
acquire 16KHz channels to the DAQ as well as 2KHz
channels. This allows the IOO
VME system to acquire all IOO/PSL DAQ channels, thereby
removing the previous
long DAQ cable runs from the PSL area down to the
DAQ analog data collection
unit (ADCU).
Remaining problems:
corrected and needs a reboot to move the outputs back
to the first Pentek.
should be an easy fix in the DAQ router software.
Work will start next week on the 40m end station controllers,
which should only
take a few days (very minor mods to existing software).
New ISS ready for installation next week at LLO by Rich Abbott and Flavio Nocera.
has been deployed with the spare LLO 10-W laser.
The spare broadband electro-optic
modulator (EOM) has been installed in
the spare LLO 10-W laser. At the moment the
laser is undergoing an alignment
tweak to optimized the output power. When the
laser was last turned on
(around 2 years ago) the output power was 9 W.
Upon turn on we measured 9 W
which settled to 8.5 W overnight. Which is typical.
So the good news is that
the laser did not degrade without use over time.
Something which makes sense
but is also nice to know experimentally. Whilst
the gross alignment tasks
are largely complete, still the laser needs to be
temperature tuned. A few
other trivial hardware modifications need to be performed
before the laser
is brought up to the current hardware level.
The MMT2 and MC2 baffles have been fabricated and
cleaned
and put in bags to travel to the bake oven.
The parts will go to West Coast Porcelain in Corona,
CA tomorrow and will go thru the bake process. The parts should be back
at CIT tomorrow afternoon. Next week will be cleaned again and vacuum baked
including the tooling and the aluminum feet, then packaged and sent to
LHO for arrival Thursday, 5-29
The three 304 stainless beam trap assemblies are finished
and will also be baked tomorrow 5-15
The stainless parts will be baked using the same method
as used for the existing tube baffles.
This is in the continuous furnace set at a temp of
849C, and make two passes thru at 12 min. each.
This process produces an absorptive surface at 1064nm,
on 304 stainless materials.
Tooling for alignment of the ITMY PO Telescope at
LHO has been completed, this is one method
that could be used to align the ITMY beam out the window.
Absorption Test Measurement prototype in STANDBY
Scatterometer
The large mirror ITM S/N 2ITM03 measurements completed and it is gone
to LHO.
We have installed in the Scattering System the mirror 2ITM01( R~600
PPM, T~ 3% Manuf.) AR coating reflectance previously measured ~ 1800 PPM.
We measured its reflectance again and it checks as before.
We have rotated the mirror at 90 degree angle and measured it
reflectance and once again the result
is the same ~1800 ppm reflectance. Right now, scattering
measurements of a surface area of
80 mm x 80 mm. of the AR coating is in progress. We'll continue
with HR transmission and scattering.
OTF Lab at Lauritsen ROOM 38
Cavity #3
Test sample SR FR HF from Chem-Sol, Inc. an Undyed Fire retardant Hydraulic
Fluid,
contamination measurements (ring down and beat frequency) has been
completed.
Please see Dr. Zhang's graphs for absorption, ringdown and cavity
thermal lensing measurements.
We have removed the test sample and introduced a new fresh clean cavity
with 50 ppm mirrors.
Aligned and beam out. Locking is not stable, power is only ~90
mw and its visibility ~70%.
We re-aligned it again and check mode match and noticed that it was
off. Fixed mode match, and
scan the beam and noticed that it is elliptical shape not gaussian.
We need cylindrical lenses to correct it.
plus we encounter with noise from cavity interference. We opened
the chamber and this time, we decided
to hung the cavity with a 2 degree angle (measured 1.8 degree)
to eliminate interference. After we pumped it
down and aligned it again, we still could not get a TEMoo gaussian
beam. This time we concluded that definitely we need cylindrical
lenses to correct the shape of the beam in order for us to use 50ppm mirrors.
We opened the chamber again and replaced it with a cavity with
70 ppm mirrors and hung with one end at 1.8
degree higher that the other end and pumped it down and made alignment.
Locking of the cavity is in progress.
Cavity #2 Test cavity is in STANDBY.
misc. tasks, made parts to hold the micrometer for the scatterometer system. Placed orders etc...
no report
no report
Data Analysis and Computing (Lazzarini)
LSC-related: the LIGO data group met for extensive discussions with
the PSU
Tier II center people. This was a very beneficial and productive face-to-face.
In addition, we took advantage of the PSU visit to host a second face-to-face
for the
LSC Computing Committee. A number of issues were discussed and are
being addressed
that cover planned deployment of new software configurations and operating
system kernels
across the sites; unified accounts management using globus grid security
infrastructure; development of the
MOU between the Tier II centers and the iVDGL PIs (Avery, Foster, et
al.); upcoming PSU hardware procurement
for their Tier II center. A set of minutes will be issued and
made available for distribution.
Simulation and Modeling (Bhawal)
Outreach (TAMA)
---------------
Dr. Hayakawa and Prof. Ohashi of Institute of Cosmic Ray Research,
a
member institution of TAMA, have contacted us notifying that
Dr.Hayakawa is going to start using e2e for CLIO and LCGT modeling.
He
has downloaded the software and has started playing with it. Hiro
provided guidance to him. This is part of the collaboration documented
in a LIGO-TAMA MOU-attachment.
SimLIGO
-----------
(Matt) This week I worked on understanding, in the context of SimLIGO,
the current ASC control problems seen at LHO. The problem
is the
translation of a non-diagonal and somewhat variable sensing matrix
into a stable control matrix and gain hierarchy. I have had some
success,
but have yet to develop a general solution.
Dynamical misalignment
------------------------
(Biplab) Ran Daniel's Mathematica code to generate plots for the transfer
functions of LIGO for dynamical misalignments and compared with
e2e
results. Some differences still exist.
Code development and maintenance
---------------------------------
(Hiro) e2e distribution:
The e2e package has made a evolutional change and the current
distribution package is not appropriate any more. Hiro, Matt,
Bruce and
Melody discussed the issue. Melody will update the document.
Bruce will
look into reorganizing the distribution package.
(Hiro) modeler code:
Hiro and Melody kept working on looking into code integrity.
This
includes the treatment of threads (it seems RH9 linux has solved
a
problem which caused modeler crash when thread is used), validation
of
codes recently updated and the speed improvements due to code
modifications and compilation conditions.
(Melody)
- Tested the modeler's
performance with different optimization
levels
and the multithreaded capabilities in the Linux box.
- Currently updating
the E2E build instructions.
(Ed Maros) Worked with Melody on optimization
Alfi
-----
(Bruce)
- Working on problems with
trim connection and junctions.
- More preparation work
for implementation of bundler widget.
- Implementing new Unconnected
data type.
(Melody) Tested alfi5 in the Linux box.
LIGO Data Analysis System
Software Systems (Blackburn)
A significant amount of knowledge concerning the migration of LDAS
to RedHat
9 was gained this week, but little new progress. It was discovered
that the
new fast thread model in RH 9 causes problems for TCL when compiled
with
the two versions of GCC we are most familiar with and have slated as
being
in our pool of candidates for a GCC compiler. There have been some
suggestive
words in news groups that it is best to use a newer version of GCC
which will
be coming out in the near future when using RH 9, but this is not an
option
if we want to meet our schedule. We are presently investigating if
the slightly
customized version of GCC that is shipped with RH (and not available
to us
for Solaris) can solve the TCL problem. We have also attempted to use
the
TCL which comes with RH9 and it does solve the thread issue, but it
has its
own long list of parsing bugs which are too extensive to justify a
brut force
approach based on that TCL which comes with RH 9. Another issue with
RH 9 is
that the currently adopted version of DB2 (version 7.2) which we have
been
using for the LDAS database for the past year can not be successfully
installed
at this time on RH 9. We were successful, after jumping through a few
hoop,
able to install DB2 version 8.1 on RH 9. Once we migrate to RH 9, we
will be
forced to upgrade our database server's version. This will require
a new
investigation to assure that LDAS works with DB2 version 8.1, and we
do have
some evidence that this is the case under Linux, but we will need to
pursue
this under Solaris as well in the immediate future, but no problems
are
expected.
We have tested running the wrapperAPI that has been constructed based
on the
Redhat 7.3 development environment on nodes running Redhat 9. The wrapperAPI
runs but coredumps on exit from processing. We may have found a fix
for this
but testing was interrupted yesterday by needs to prepare for a power
outage
in Millikan. This is the configuration we hope to have working for
the next
release of LDAS (0.7.0). All LDAS APIs except the wrapperAPI will be
strictly
supported only under Redhat 7.3, while the wrapperAPI will (hopefully)
be
supported under Redhat 7.3 and Redhat 9. We have been working on this
goal
for about a month now and have yet to find the "key" that unlocks all
the
problems. Some of the issues were resolved by upgrading the autoconfig
and
automake tools under RedHat 7.3 to be the same as those under Redhat
9. This
require a one week effort in rewriting the configuration scripts for
LDAS
with lots of supporting testing. I'm optimistic that we have almost
"cracked"
this "nut". However, because of these issues we have desided to postpone
the
code freeze for the next release of LDAS that had been tentatively
scheduled
for the end of this week.
The new version of the createRDS command that will support ingesting
frames
from multiple interferometers and writing out them out in a single
RDS is now
in place and about 90% tested. It uses the Frames table of contents,
which
the previous version did not. It was hoped that this would give about
a 10 to
20 percent increase in performance since the whole frame no longer
needs to
be read but it did not.
We have made no progress in getting LDAS software to work with higher
levels
of optimization and function inlining under solaris. This is degrading
our
performance and needs serious attention, though the solution may also
involve
a newer version of GCC since the problem first showed up once we migrated
to
a new more ANSI/ISO compliant version of GCC. As an aside this upgrade
did
fix many thread issues and memory leaks issues we were experiencing
with the
older versions of GCC so its a case of having to take some loses with
some
gains. The net sum is a gain for the long term maintainability of LDAS.
The controlMonitorAPI now has a working test menu which allows users
designated
with control level privileges the ability to test each type of user
command
with a simple click of the mouse in the GUI. The test script are now
integrated
into CVS and built into the controlMonitorAPI as part of each build.
We spent two days this week meeting with the technical staff from Penn
State
that will be responsible for the Tier II center there. Discussions
covered
planned hardware to be purchased at the PSU center, database federation
and
replication, grid technologies and DMT. One of significant outcomes
of the
meeting was the formation of a team including participation from the
PSU
group to help bring our database federation/replication solution on-line.
The new team was given an overview of the solution LDAS had committed
too.
This lead to some concerns so we generated a new set of requirements
to
address these concerns. The new Database Team has been tasks with taking
these new requirement and determining what topology of federation/replication
best meets them. Another significant outcome of the meeting was the
disclosure
of a "wrapper" to the off-line DMT that allows it to run under a globus
enabled grid environment. This is still prototype, but there was consensus
that this approach had appeal.
The ability to save to file results which fail to be inserted into the
LDAS
database due to internal database server deadlocks was added to the
metadataAPI.
This will allow users to issue a putmetadata command with the saved
file at a
later date when the deadlock is resolved without repeating an analysis.
A new memory leak has been introduced in the metaDataAPI this week.
All code
changes have been in the TCL layer so the localization of the bug is
somewhat
easy and has been isolated to code used for the putMetaData command.
Efforts
continued to the remaining small memory leaks still present in the
data-
ConditionAPI but no progress to report at this time.
The creation of RDS frames for the S2 Science Run on the LDAS-CIT system
has
completed. The availability of the RDS frames has been announced to
the Tier
II centers by Philip Charlton. They are being mirrored to these sites
using
LDR, a grid/globus tool for data replication. For convenience, the
last task
Philip needs to do on this is move some data from one disk to another
so
that data is organised into single directories of 100,000 seconds each
(~6000 files).
Hardware Systems (Anderson)
Caltech
-------
(Dan Kozak)
* Continued to managed SAM-QFS resources in support of RDS creation
(S2 data).
This is now completed.
* Worked with STK field service to replace one of our old 9940As that
was
having positioning errors.
* Got SB1000 (saiph) to see Fibre Channel devices again, by running
the
SAN 4.2 install script for a third time allowing it to pick
up more patches.
* Investigated release behavior of SAM-QFS and discovered that
/archive/ndas had been marked "do not release" which meant that
all the
directories and files subsequently created under it had inherited
this
behavior. After setting the release behavior of these
directories/files back to the default, the release behavior
of the
system as a whole got better (since 90% of the disk cache had
been
filled with NDAS files before).
* Replaced all the power supplies in the T3 RAID arrays in Powell-Booth.
(Al Wilson)
* Set up the 3.0GHz boxes for the new Datacon, and Beowulf in the LDAS-DEV
system. They have RH7.3 and are ready to go.
* Have two of the new nodes on line in the dev system, Node17 and node18.
These are being tested for node compatibility for RH9.
* Doing system imager testing with node19, so far so good.
(Stuart Anderson)
* Visit with Albert Lazzarini to the LDAS Beowulf cluster vendor to
check on the status of our 420 node order.
[Lazzarini note: we have learned that the ship is in transit.
The date they have proposed for last delivery is holding firm (early
June).]
* Obtained shipping schedule on the remaining Sun Microsystems order--last
partial shipment on May 22.
* Worked with Al Wilson to shutdown and restart all 6th floor Millikan
computers for the scheduled building power outage.
* Worked with Ed Maros to rebuild the /ldcg tools with the new bug-fix
version of gcc (3.2.3).
MIT
---
(Keith Bayer)
* Submitted paperwork from extra power to ldas lab to support cluster
nodes.
* Collected data for current network speeds.
* Continuing to administer LDR to get S2 segments to MIT.
* Setting up new pc raid units (burntests, benchmarking
different raid / non raid filesystems, different o/s's).
* Shifting equipment in racks to accommodate new datacon
and beowulf rack mount units.
Livingston
----------
(Igor Yakushin)
* Working to add noise estimate for each event in the waveburst to have
a
consistent procedure for setting thresholds for corresponding
events in
different ifos.
(Shannon Roddy)
* Discussed the power and cooling requirements for the new LDAS hardware
in the LDAS room. Long term I believe that the cooling
system in the
room will have to be changed. Short term, I think we are
OK. Allen is
looking into this. Also Rusyl is working with the contractor
on the
power requirements.
* We have added 12 more pieces of CAT5 cable between the LDAS room and
the
comm. closet so that we can get away from the temporary GC connections.
This will also allow me to hook up the KVM to Igor's office.
Hanford
-------
(Greg Mendell)
* Completed orders for UPS units, a transformer, and cables for
the
new FC and GigE switches, and new beowulf cluster for LDAS at
LHO.
* Circuits for the new equipment are being added to the LDAS room today
and tomorrow.
* Installed new ASA Raid box on the LDAS LHO network. It is currently
running our burntest.
* Working with Igor to read S2 ndas data from tape onto disk at LLO.
(Ben Johnson)
* Finished comm program for the Omega RD820 temperature monitor. Will
perform final long-run in situ tests next week.
* Assisted with the replacement of final batch of batteries for the
T3
arrays, and with the replacement of a memory bank and a system
board for
dataserver.
* Replaced faulty T3 disk 4 in t3-5.
* Performed basic hardware and software setup new beowulf and datacon
units. They have not been placed on the network yet.
* Continuing to work with ASA Computers on repairing node32 of our
present beowulf cluster.
Data Analysis Activities (Lazzarini)
Weinstein:
- working on burst paper.
- set up routines for filtering bursts through S2 calibration
in matlab, to facilitate work by Laura Cadonati.
Creighton:
I have finished my study of precision issues in band-pass IIR
filtering. In addition to the round-off noise introduced by the
original digitization, there is significant additional round-off noise
introduced by (single-precision) IIR filters, which can dominate the
filtered output if the input spanned a large dynamic range. This
can
be effectively eliminated by (1) copying the single-precision data
to
a double-precision array and performing double-precision filtering,
or
(2) rewritiing the filtering routine so that intermediate variables
*and* auxiliary arrays are double precision. The second will
require
significant rewriting of the code, so for now the PULGroup will be
using the first method. Eventually I will revise the LAL code
to do
the second, which should be marginally more efficient.
K. Reilly:
Friday through Monday I spent reading v13 of the S1 stochastic paper
and giving comments to the group (Peter F.). The rest of my time
I have
been spending learning about writing LAL code, so that we can start
to turn the DSO into LAL routines while leaving it compatible
with LDAS. Joe and I spent sometime further discussing the ultimate
structure of the stochastic data analysis codes.
Mendell:
1) Working with the PULG group to update the SFT specification.
The
main issues to decide are what metadata should be stored in the SFT
frames, naming conventions, and how to organize documentation.
2) Working with the PULG group and Malik Rakhmanov to write test code,
independent of LAL, to check the beam pattern response functions that
are in LAL. We have started with code written by my SURF student,
Brian
Cameron, last summer. Other code written by David Chin already does
checking within LAL. We will also add independent tests of timing
routines in LAL as well. The most important of these, for the purposes
of computing the detector response, are the LAL routines that convert
GPS time to sidereal time. It is important to understand that
all of
this functionality has been tested and verified in many ways in the
past. What Malik and I will do is incorporate existing code and
standardize it so that a complete set of test functions run during
every
"make check" of LAL when it is built. We will also provide documentation
in LAL on how to run exhaustive versions of these tests from the command
line.
Yakushin:
Working to add noise estimate for each event in the waveburst to have
a
consistent procedure for setting thresholds for corresponding events
in
different ifos.
Peter Shawhan:
* S1 inspiral analysis: Checked lists of events used in analysis, and
found
that several LDAS jobs had actually failed without returning an error
message, so they were not noticed at the time. The failed jobs
are being
re-run to fill in the gaps.
* S2 data quality: Went through files of segment-by-segment Epics channel
differences during S2, and collected information about all of the LSC
filters during the run.
Lazzarini:
Working to complete the final draft of the stochastic upper limits
paper.
General Computing (Wallace)
MIT:
(Keith)
-Installed up2date utility on several ldas user machine
-Received certificate from DOEgrid CA service
-Running test server with new certificate
-Created accounts for MIT urop summer students
Livingston:
(Shannon)
-Setting up a laptop for Bonnie to use next week for a presentation.
-Setting up Gerry's old machine for Doug's use as a dual boot workstation.
-Helped Ed Daw look at Alvar since it did not come up properly after
a
power failure in the mass storage room.
-Considering buying a couple more RHN accounts from Red Hat since more
and more people are wanting to dual boot their machines. This
helps me
keep up with whether or not they are doing security updates, etc.
-Working on the modem issue. Bellsouth changed our phone lines
from
analog to ISDN this week and the modems will need to be
replaced/reconfigured. The connect speed is about the same after
the
conversion, but I have a new piece of hardware I need to try.
Hopefully
this will improve the dial up speeds and allow me to replace the
portmaster which appears to be dying.
-Reinstalled the OS on the scanner machine and bought a USB drive adapter
so that the old files are still on the machine.
-Set up a couple of new accounts and also did some work on the form
that
I am using for new accounts. I am requiring people to fill out
this
form and agree to the computer usage policy before I activate the
account. This form has worked pretty well so far.
Hanford:
(Christine)
- Received the final GigE network upgrade quotes for both Foundry and
Cisco from CDWG. The prices are almost identical.
- Setup two new laptops. Helped a new laptop user to understand
how to
use their laptop.
- Contacted reps for Sun and Reliaty backup to get maintenance contracts
renewed for another year and to get upgraded software from Reliaty.
- Helped swap out PCs for the FMCS system. The old PC had lost
it's
hard drive, so I swapped it out for one of my spare PCs.
- Spent some time working on my laser power, rotation stage, epics
software.
CIT:
(Mike)
Moved and rack mounted M91 & Pictor from my office back into the
server room
due to a maintenance issues and a hardware failure. I also did update
ghost
images on both of these servers.
-Our ghost server had an OS problem that ended up in me having to reload
this server it is now back up and running. I would like to let all
our
users know that a good percentage of the ghost images that are stored
on
the server are win98 and I now have most of you updated to 2000 pro.
I would like to get current ghost images from all our users that are
running windows workstations. I will start this process in the early
morning hours and hope to have everyone updated ASAP, without any down
time. I will notify you the night before I would even make an attempt
to
update any of our users.
-Worked on Linda Turner's laptop due was having problems with the OS
and
it turned out to be a virus. I had to wipe the disk and reload the
OS and
reload all applications. This is still in the process.
-Loaded a new laptop for Barry with all General Computing Software
and today
I will be transferring over his data over to the new laptop.
-Finished up loading an engineering workstation for a visitor that
is
coming from Glasgow.
(Veronica)
- Time was spent almost exclusively on building and support of the
Advanced LIGO website. The website is ready for the reviewers to use;
some
setup and editing need to be finished.
- LIGO website: started on catching up on what's accumulated in the
past
days as I was working on Advanced LIGO. Updating account information
at
Internal Bulletin Board at the moment.
- LSC website: the same - catching up on postings left to wait until
now.
- CaJAGWR website: user support at an urgent request by Kip, website
maintenance.
(Lisa)
- Hardening the security on the new www.ligo.
- Worked with Larry on putting more disk space on rigel.
- Still doing a fair amount of user support on e-mail, mostly helping
people
learn how to secure their home connections.
- Made DVD's for people who needed help managing their home account
disk space
usage.
- Reprogrammed the wireless access points many times.
- Fixed the Forte 7 licensing on ldas-suntest1.
- Looked at what it would take to upgrade all of the solaris boxes
to netscape
7. It's a fairly major task that would be difficult to roll out.
(Larry)
-Spent more time than usual working on PC's. Most of the issues were
cleared up by
running maintenance programs on the units.
-Continued working different issues with the VRVS and related video
conferencing
programs. There appears to be enough interest that we are working on
a noon-time
seminar on how to use the system. We'll announce the time and place
when we get things
lined up. We are shooting for the first of June before the reviews
start.
-A lot of work going over licensing issues. Each company, that has
provided a EDU site
license, is treating how their s/w can be used differently.
The SDRC pkg. has been purchased by EDS and will be incorporated into
their
Unigraphics system in the near future.
We have a few more Matlab group licenses but it appears all but a few
have been
checked out. We've also added to our network license pool.
-Worked on a number of procurement issues. This should slow down now
that we are
coming to the end of the construction budget.
-Went over the form Livingston is using for their new accounts. The
CIT group will
probably be using a similar form.
Along that same line we need people to inform us ASAP when they are
going to have
visitors needing wireless access. It does take some time to update
the wireless access
points.
-Worked on a few of the servers and edge switches.
-Regular user support, adding of accounts and checking e-mail issues.
We are still
adding locations to be blocked and reviewing the logs for false positives.
-The new LIGO web server is just about ready to be put on-line. Just
a few more items
to take care of but they will have to wait a few more weeks. Also,
another internal
secure web server is about to be put on-line.
MEPI
We retuned the MEPI Modal controller to take advantage of the
tuned mass
damper. We hope to get results this weekend. The local/modal
controller
hasn't made any progress due to the differences between the piers.
HEPI
We have been investigating the zero in the
horizontal transferfunction
abound 23Hz, which is thought to be casue
by the BSC pier compliance.
BennoWillke
will arrive prior to the NSF Review. In the days before
the review we expect to go through some aspects of the planning program
and
perhaps the costing, given that LZH are currently going through their
cost
and scheduling preparation.
- We've ordered 16 more of the thin, 32 more of the thick Q samples
(FS and Sapphire 16
each)
- We've ordered LASTI RM blanks
- We're about to order substrates for thermal noise/Q experiments at
TAMA, just need a
final review of the specs.
From: David Reitze <reitze@phys.ufl.edu>
Status reports for the CO Working Groups, Thursday,
May 15, 2003
An RFP for Coating Research and Development for Advanced
LIGO Core Optics as
well as a RFP for Advanced
LIGO Production Coatings should be released to vendors
this week. We requested delivery
of the first coating run by August 1st.
Garilynn: Sapphire Status
Absorption measurement results from
The absorption appears to be fairly uniform along the
opticalaxis(z), but is asymmetric
by ~100% (x,y).
See the pictures esp. slide 6 (thousand words saved right there.)
- We've ordered 16 more of the thin, 32 more of the
thick Q samples (FS and Sapphire 16
each)
- We've ordered LASTI RM blanks
- We're about to order substrates for thermal noise/Q
experiments at TAMA, just need a
final review of the specs.
Mechanical Loss:
Sheila/Steve/Peter/David
Shiela:
systems. Item for agenda:
before
mechanical measurements begin, are their optical tests
which would be useful first?
Send to JMM for absorption map etc?
Annealing Q tests - silica 3" by 1" piece is cooling
down after being annealed.
Stanford: We passed a second coated MLD alumina/tant
ala sample to Pierre Khuri-
Yakub's
people for measurement of Young’s modulus.
Pierre's RA and Student (GoksenYaralioglu
and Ira Wygant) now have (preliminary)
measurements of 3 coatings,
each on a silica substrate.
- One SiO2/Ta2O5 coating from MLD (part no 8107)
- One Al2O3/Ta2O5 coating from MLD (part no 5701)
- One Al2O3/Ta2O5 coating from Waveprecision
(part no. 8223).
They made two measurements on each coating to test
reproducibility. In essence they
measure the difference in
(acoustic) reflectivity between water and the coating and water
and the substrate and thus
extract information about the properties of the coating. They
then model their experimental
results using a combination of values for the coating
From: RiccardoDeSalvo
<desalvo@ligo.caltech.edu>
Greg
New alloys ready for press injection, Waiting to use injector.
A few more tests with braze and more failures.
Eric
Working on additions of Brians
draft of X-ray diffraction paper.
Molten more MoRuB witch brews. A
possible and suspicious candidate.
Aso
Wrote program (and its documentation) to design MGAS blades.
Inputting load and scale factor, it outputs stress, width and thickness
or inputting load and scale it outputs scaling, etc.
Designed few blades, we will produce the ones for his suspension,
as well those for Mark Notcutt (J. Halls
group) to fine tune the programs parameters.
Measured angular and other resonances in the 2 blade
MGAS prototype.
EnricoCampagna
Learning Bench and playing around, getting
started with Ansys.
Allyson
Presented her poster session at Westridge
high school (Riccardo, Gregg and Eric attending).
Good success.
Made control indentations in a UCLA indenter, proceeding to measure
indents in the electron microscope.
Alessandro
Working on fiber interferometric sensor to read resonance ringdown
for metallic AND dielectric samples for Francesco Cordero.
Francesco Fidecaro
TAMA-SAS tower in custom in
For additional information about this report, contact sanders@ligo.caltech.edu