|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday February 10, 2003 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
Special Items: Outreach Proposal status, Adv LIGO proposal status, Aspen meeting reprise, Status of UL papers and AAAS talk
no report
LIGO Weekly Site Telecon (Lindquist)
There was a site teleconferences held on Thursday, February 6, 2003. The following issues were among those discussed:
Outreach proposal should be ready to go into FastLane today.
LLO LN2 Tank Incident: Truck driver hooked to tank and attenpted to drive away still hooked. There was considerable slack in the 2 inch copper piping, which prevented leakage. Tank is undamaged. Valve at top was closed; no spillage. Air Liquide has provided an accident report, and LIGO will be preparing an accident report. Air Liquide plans a safety meeting and will come back with a response after that. Potential fix is to only allow trucks on site that have appropriate interlocks. Onus is on Air Liquide.
Traffic Control Gates: Alan wants to set up a time for a presentation by the archetects next week to go over alternate ideas for location and approaches. More information tomorrow.
At Hanford, electricians are wiring. Gate should be up and mechanically operational shortly. Operation will be via keypad or from Control Room. There are sensors for permitting exit.
Hanford Construction: Hope to have cost estimates for proposed modification for the Laboratory Building by next week.
Livingston Construction: Still do not have final occupancy certificate. Will be inspected next week. Expect that we have addressed all issues.
Reporting Time for Shift Operators: Operators work 40 hour schedule, on four days and off four days with an adjustment every eight weeks, working often weekends and holidays. Time keeping system is not set up to handle time reporting for shift operators. Action is for Fred, Ed and Cindy to take this to Alan Rice for discussion and awareness to be followed up by discussions with HR.
Property Issues: Hanford Inventory in process and going well.
Fred Raab Comments On Limitations of Caltech TimeSheet for Recording Operator Time
The list of current actions revised to reflect
the status of open actions assigned through January 16, 2003 may be found
at ACTION
LIST.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
Reminder to LIGO staff: Please make sure that as a minimum, each document submitted has a LIGO number, author's name, and date. It's surprising how many documents are missing one of more of these essential pieces of information!
ACTIVITY
| WE 02/06/03 | Packages | Faxes |
| In | 25 | 27 |
| Out | 9 | 17 |
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA .
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
>Irene Baldon
No report this week...they are working hard on the Advanced LIGO Proposal, which has been delayed a week or so for thorough review.
Project Web Site for posting schedule and progress related data continues to be updated with the latest and greatest.
Advanced LIGO and Outreach Proposals.
Change Request CR-030002 to adjust the FY 2003 operating
budgets to reflect actual staffing during the first quarter has been prepared.
Additional information is required.
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
No report this week.
Summary of Commissioning Activities at LIGO Hanford Observatory (compiled
by M. Landry)
---------------------------------------------------------------------------------------
2K IFO (H2)
-----------
Compensation and stopband filters on the 2k MICH loop were brought in
line with that of
the 4k, improving the displacement noise. Good spectra rivaling
the 4k are obtainable but noise levels
(particularly in the acoustic-peaked range 90Hz-few hundred Hz) are
nonstationary.
A shot noise calibration was performed on the AS PD #2:
http://blue.ligo-wa.caltech.edu/ilog/pub/ilog.cgi?group=detector&date_to_view=02/04/2003&anchor_to_scroll_to=2003:02:04:18:29:54-daniel
4K IFO (H1)
-----------
WFS work continues; currently the all WFS loops with the exception of
2B can be closed,
controlling eight of ten d.o.f, with resultant benefits to arm and
spob powers. While
the setup to close the loops is somewhat tricky and not yet fully automated,
once closed
they appear stable, running for hours without a hitch. See the
elog
http://blue.ligo-wa.caltech.edu/ilog/pub/ilog.cgi?group=detector&date_to_view=02/04/2003&anchor_to_scroll_to=2003:02:04:03:21:35-luca
Later efforts included more scripted
acquisition:
http://blue.ligo-wa.caltech.edu/ilog/pub/ilog.cgi?group=detector&date_to_view=02/06/2003&anchor_to_scroll_to=2003:02:06:18:03:09-luca
DAQ
---
New ASC code was loaded on the 2k, which appears stable.
Interferometer: Joe Kovalik measured the bandwidth of a re-glued
PMC to be 1.40+/- 0.03 MHz.
Valera, Andri, and Gaby worked on diagonalization of mirror actuation.
LDAS admin:
1) Sent 35 tapes with LHO's RDS to LHO;
2) Sent E9 tapes to Caltech
LDAS data analysis:
1) Fixing bugs in waveburst DSO in preparation for S2.
(Igor)
CDS:
1) Released the beta version of the diagnostic software smt.pl for
testing.
2) A script is being written that automates the tidal servo operation.
It
generates the tidal data file periodically as a cron job.
3) Setting up a testing environment in our lab area.
-Ash
Gathering together cad files and updating an as built directory of PDFs
from Parsons, PSI, CBI and John Desmond. Looking into electro-mechanical
actuators to replace the pneumatic actuator on the 80K fill valves.
(Jonathan)
Modelling: We started to construct e2e boxes for small IO optics.
Since the floor
motion box for LLO has not been completed, the first version of IO
e2e box
will take inputs to the suspension point. The local damping gain setting
does not seem to work properly, for some unknown reason. We will look
into
this problem with help by Hiro Yamamoto. (Sany)
GC:
I have been troubleshooting network problems with LSU for the last
week. I think that things may have staightened out now, but there is still
a bit of packet loss. This could be due to ICMP filtering at LSU so I am
looking for some other means of testing for lost packets. Worked with American
Electronics today to come up with a plan for the new conference room. Also
working with them to make some changes to the A/V equipment in the auditorium.
I will have to reinstall linux on one of the workstations here. The disk
space is just about used up in hte current partition scheme. In order to
change this, I need to reinstall. Had a request to store a lot of data
on the web server for "as built" drawings. I will probably have to add
some disk space to alix due to that.
LDAS:
Still working on benchmarking the evaluation units. I have a few more
things to test before I am satisfied.
-Shannon
no report
no report
no report
Simulation and Modeling (Bhawal)
SimLIGO
--------
(Matt) Worked to increase robustness of SimLIGO locking, add useful
diagnostic and demonstration scripts, and produce up-to-date
noise curves.
Mode mismatch
---------------
(Biplab) Melody (with modal order 4) and E2E (same number of modes)
models for 4km IFO matched well with each other for both carrier
and
sideband lights - which probably says that the difference between
FFT
and E2E may not be due to some E2E bug and may be more related
to the
limitation of the number of modes in e2e. On the way .. the convention
for Melody's mirror displacements was sorted out after discuusing
with
Ray Beausoleil.
WFS signals
---------------
(Biplab, Matt, Hiro) After checking sideband power at different ports,
we found one parameter that was not quoted correctly in the '98
alignment
paper by Fritschel et al, the Schnupp asymetry length of the
recycling
cavity: it was factor of 2 off. After taking that into account,
E2E
signals match better with the results in the paper but the guoy
angles
are still off from the quoted values.
New Code development
-----------------------
(Matt) Continued work testing new optics components.
Alfi
-----
(Bruce)
- Option and previous session
windows are now saved to be reloaded
in the next
session.
- Option files are now working
for both command line start and
WebStart usage.
(Melody)
- Worked on optimizing the
modeler's FUNC_xxx modules.
- Worked on some PRs in
alfi5.
LIGO Data Analysis System
Software Systems (Blackburn)
This week we have continued to find and fix bugs in the LDAS software
in preparation for the scheduled (and agreed upon) release date of
next
Tuesday. One set of fixes to the diskcacheAPI and frameAPI introduced
a new failure mode in the createRDS command used to produce the reduced
data sets. This has now been fixed.
On Monday of this week, a pre-release version of LDAS, along with LAL
and LALwrapper were pushed to the sites for testing against E9 data
and
the current search codes.
Over the weekend, we saw long term testing results with about a 0.05%
failure rate - roughly two orders of magnitude better than seen in
E9.
This was futher improved with last nights testing to a single failure
out of 10,500 jobs (0.01% failure rate). We were also able to insert
and read back out one million rows per day in the database during this
weekend run.
We still have a significant amount of testing of other LDAS functionality
before we are ready to release. We hope to get a handle on all the
needed
testing by the end of the week.
Testing of the use of calibration data has identified several issues.
All
issues have been resolved. We await more complete testing of calibration
which includes the new search codes being developed by the LSC. The
plan
is for the LSC to conduct these tests this weekend.
We continue so see unusual failure modes on the standalone boxes that
do not occur on the full hardware platforms. This may be to Linux or
it
may be an issue with the load on these standalone boxes which are running
all of LDAS and the database, webserver, etc. on one box.
There was a new release of LAM which we are currently testing. It looks
very promising and may be a contributor to the improved performane
and
reliability of last night's test run.
A decision to test an LDCG version of SSH for solaris was made and is
being tested on the LDAS development system. This may fix some of the
issues with API and SSH processes not completely being killed by the
operators. More testing is necessary before moving to this version.
Hardware Systems (Anderson)
Caltech
-------
(Dan Kozak)
* Worked with Qlogic/Sun to get beta 2Gb FC switch working. It's
been
working this between ldas-archive, T3s and 9940As but not working
with
saiph (1Gb HBA/Solaris 8).
* Archived all E9 data to SAM-QFS (dual copies on tape, all files have
been written to tape).
* Received batch of 9940 tapes (420 cartridges) and started labeling
them
and importing them into the silo.
* With Larry Wallace's help, got our 9940A tape drives under maintenance
again.
(Al Wilson)
* Building a new datacache IDE Raid with 16 200GB drives. Got the drives
installed and striped as two 1.4 TB file systems. Installing
RH7.3 on
it today.
* Minor tweaks to BigBrother. Removed all connective ping test to remote
sites. And have set up LHO so the local sysadmin. Get
mail on the local
mail server. Still need LLO and MIT address.
(Stuart Anderson)
* Finished reading all LHO and LLO E9 tapes and copying them to SAM-QFS
at Caltech for archiving and the IDE-RAID systems for quick
random access.
* Mirrored 1hr of triple coincident E9 data to all LDAS systems for
software testing and validation prior to S2.
* Continuing to gather/negotiate quotes for LDAS archive hardware and
software licenses.
Livingston
----------
(Igor Yakushin)
* Sent 35 tapes with LHO's RDS to LHO.
* Sent E9 tapes to Caltech.
(Shannon Roddy)
* Still working on benchmarking the evaluation units. I have a
few more
things to test before I am satisfied.
Hanford
-------
(Greg Mendell)
* Preparing the tapecontrol script for S2. Igor and I will begin
archiving data Mon Feb 10, to get the injections. The
script will be
configured to get data between 6 pm CST and 6 am CST (-/+ a
some) every
evening, starting with Mon Feb 10, to get the raw frames with
injection
data. During the run, it will archive all the data 24/7,
of course.
After then run it will return to just archiving data during
the evenings
until post-S2 injections are finished. All the data will
be sent to
Caltech as usual.
* Updating the rds loop script that ran during E9 to run during S2.
RDS data will be kept on disk at the sites. (Note that
raw data is
overwritten after ~12 days at LHO and ~9 days at LLO.)
Data Analysis Activities (Lazzarini)
Weinstein:
- Set up, and ran, three burst searches (power, tfclusters, slope)
ONLINE during E9, and maintained a web page summarizing the
results:
http://lancelot.mit.edu/~ajw/burstdsos.html
- Attended the joint burst/inspiral workshop on vetos at LSU,
and made numerous constructive comments which were ignored
(as well as some that people actually listened to).
- Began to look at the results of the burst hardware injections
done on Saturday night during E9.
- Made recommendations (in a memo) for future hardware injections.
- Finalized a note by me and Laura Cadonati on burst efficiency
evaluation for S1.
- Working on moving burst online running into the dsorun format.
Shawhan:
* With Stefan Ballmer's help, figured out how to run glitchMon to generate
veto
triggers to be used in the S1 inspiral upper limit analysis, in place
of the
veto triggers we had been using, which were generated using the inspiral
search
code.
* Updated the inspiral upper limit paper draft, and the internal report,
to
reflect the new glitchMon-based veto condition.
* Working on planning and software for hardware signal injection during
S2.
Yakushin:
Fixing bugs in waveburst DSO in preparation for S2.
Mendell:
Added options to the knownpulsardemod DSO to high pass filter and window
data before generating SFTs, and to output calibrated SFTS. Currently
I
am updating the knownpulsardemod.loop.tcl driver script that ran during
E9 to generate SFTs during S2. The script is monitored from the LDAS
LHO
Search Summary web page. Before S2 the script needs to be updated to
get
calibration data under the S2 plan, and to detect clean locked science
mode stretches in real time.
Last week --The main activity of the last week was to run the
knownpulsardemod.loop.tcl driver script during E9 to generate SFTs.
The
script was monitored from the LDAS LHO Search Summary web page. It
was
shown that the script correctly handled keeping pace with the data.
It
was also shown that the SFTs jobs could run in parallel with the other
jobs on a loaded LDAS system. Before S2 the script needs to be updated
to handle calibration data and to detect clean locked science mode
stretches in real time.
General Computing (Wallace)
MIT:
(Keith)
-Assisting in document conversion. There are some issues with going
from XP to
WIN2K.
-Working with the MIT networking people to solve some performance issues.
-Received the MATLAB licenses and have them installed.
Livingston:
(Shannon)
-Troubleshooting network problems with LSU for the last week.
I think that things may have straightened out now, but there is still
a
bit of packet loss. This could be due to ICMP filtering at LSU
so I am looking
for some other means of testing for lost packets.
-Worked with American Electronics today to come up with a plan for
the
new conference room. Also working with them to make some changes
to the
A/V equipment in the auditorium.
-I will have to reinstall linux on one of the workstations here.
The
disk space is just about used up in the current partition scheme.
In
order to change this, I need to reinstall.
-Had a request to store a lot of data on the web server for "as built"
drawings. I will probably have to add some disk space to alix
due to that.
Hanford:
(Christine)
- Hand carried the Computer Use Policy around to people who had not
signed off on it. Answered questions and dealt with requests
for
exceptions to the policy.
- Set up some PC files to be viewed from a UNIX computer as part of
a
property audit.
- Rescued a PC used for building environmental controls. The
hard drive
is going south. I have it working temporarily until I can replace
it
with another computer and reinstall the environmental controls
software.
- Downloaded and investigated installation of SSL for IMAP.
- Searched for a vendor that sells supplies for one of the color
printers. Found the toner cartridges easily, but not the fuser
and drum
kits.
- Installed the scsi card into the LDAS/CDS emergency tape backup
computer and got the tape robot working on the computer. Set
the
computer up as an nis+ client on the GC network. This computer
will be
on the GC network most of the time and will only be put on the CDS
network when needed for emergency frame backup if LDAS crashes.
- The usual user support for e-mail problems, computer crashes, hardware
failures, user account problems, etc.
(Larry)
-Working on the procurement for the new router to provide GbE connection
from LIGO Laboratory to Caltech/ITS.
It has been approved and getting some minor changed made on the
original quote. There has been a rush put on it.
CIT:
(Mike)
-This week I was real busy with onsite/phone user support that included
mostly networking issues, this was due to two network switches going
down.
-Ran a few cable drops, here in Bridge Annex for our new
copier/scanner/printer.
-Working on loading two laptops that well be used to the loaner pool.
-Updating our users computers with current service packs to
insure that they are updated with current OS security patches. This
will help
prevent virus attacks and make it more difficult for hackers to break
in.
-Started loading a backup server for Pictor, to be safe until our
replacement server shows up.
I had a lot of users that were having problems mapping their previous
mapped drives. I ended up having to reboot all servers, which seem
to
correct most of these issues with mapped drives to our NTSRV's.
(Lisa)
- I was on vacation last week.
- Helped Larry out as much as I could with the network problems on
Monday.
Checked out all of the workstations the next day.
- Looking into wireless problems with the 3d floor access point.
Working on
wireless problems with some new dell laptops.
- Backed up home6.
(Veronica)
- LIGO website: updated roster database. Working with the Digital Media
Center on processing LIGO VHS tapes; DMS suggests to do it in small
batches, the 1st batch has been shipped off for processing. Updated
document listings on the Internal Bulletin Board. Posted various updates
to several webpages.
- LSC website: started working on a webpage for the upcoming LSC meeting.
Posted updates to the 'talks to be presented' page.
- CaJAGWR: Updated the website. Recorded the video of the last seminar,
and am compressing it in preparation for posting. Processed the video
from
the previous talk; will post it as soon as it passes JPL clearance.
Expereimenting with the smil combos of video and slides. This can also
be
useful for LIGO seminars.
(Larry)
-Worked a number of procurements. Mostly, software and licensing purchases.
The
Matlab licensing needs to be sorted out, we've not received what has
been
promised.
-Generated a list of those that have signed off on the GC Policy. A
list of
those that still need to sign off is being created.
-The major item for the week was the CIT LIGO LAN going down. The edge
switch
that connects the network to the outside world just went down with
a hardware
problem and is being replaced. The core switch for the LAN had a problem
with
the backplane, the system is up and running but this unit, too, will
be replaced.
The last item that went down was a GigE card to one of the main servers,
it has
been replaced with a fastethernet card.
Thanks to Lisa and Mike things were not down as long as they could
have been.
Having extra hands and eyes made a big difference in getting things
back
on-line.
-The regular items of setting up accounts and adding more sites to
be filtered
out of the mail server is being done continually.
The RAV s/w demo license has expired and presently waiting for the
permanent
license to arrive. Most of the users had positive comments about this
package.
Livingston has been using it successfully for some time. However, everyone
still
needs to keep up their virus-scan s/w.
From: Phil Willems <willems@ligo.caltech.edu>
Sapphire Q:
-----------
We have received the two prototype sapphire test masses in our lab.
These are
the ones that have chips in them at their edge, one apiece.
For one sapphire the chip may be the least of our problems. The
whole thing is
visibly pink, and much of the outer third contains numerous inclusions,
a few
the size of grains of rice. Also, the circumference has a very
poor polish.
The second sapphire is much, much better, although it has the larger
chip and
slightly worse barrel polish. The interior is clean and clear.
Repolishing
could make this sapphire pristine. We will test this one first.
We have the Q-measurement rig for these masses set up in our vacuum
and are
making adjustments. (Phil Willems, Dan Busby)
From: Janeen Romie <romie_j@ligo.caltech.edu>
AdLIGO Suspensions
I've missed two days to illness this week so please review Calum Torrie's
and Mark Barton's reports for status.
Working with Bob Taylor on the HAM table spacers that came in from
MIT for cleaning and baking. One spacer was damaged in shipment. Bob brought
them all over to the machine shop for machining. He'll clean and bake them
after machining.
From: ctorrie <ctorrie@ligo.caltech.edu>
Mode Cleaner Assembly
Janeen and I are working on the various assemblies associated with the MC suspension with a view to create a full set of drawings, parts and assemblies that can be sent out to vendors.
Helena and I have re-assembled the coils for the Caltech MC and are waiting on some silver plated bolts before we re-install these on the table cloth.
Recycling Mirror Suspension
Russell Jones and I have been working on the coil and the associated parts for this suspension. We hope to start the manufacturing process for these next week.
Norna Robertson et. al met to discuss the RM pendulum parameters again
this week. A final set should be ready for the 14th of February.
From: "Mark Barton" <mbarton@ligo.caltech.edu>
This week I did some calculations and experiments
to check the
plausibility of Janeen's SolidWorks/Algor model of the Advanced LIGO
MC
suspension structure. In particular I measured the stiffness and resonant
frequencies of a sample of the aluminium tube stock used in the
prototype. It turns out that under certain circumstances that seem
to
have to do with the units in effect when the model is exported from
SolidWorks, the mode frequencies can be wrong by a factor of about
3.
I also worked with Paul Russell and Jay Heefner to
get the various
electronic modules for the MC prototype (GEO-supplied sensor/actuator
board, CDS-supplied anti-aliasing and whitening/dewhitening filters,
dSpace controller) integrated.
From: Jay Heefner <jay@ligo.caltech.edu>
Advanced LIGO Suspension
==========================
- Began checkout of electronics and rack components for advanced LIGO
suspension prototype. Checkout should be complete by 2/6.
Advanced LIGO DAC
==========================
- Held a telecon with Frequency Devices. In this telecon we discussed
progress to date and some of the problems that they are having with the
prototype. By this Friday they hope to be runnig clean sine waves out of
the module. Noise testing should be started next week. As of last Friday
they plan to ship the prototype on or before 2/21. We will have another
status update telecon this Friday.
For additional information about this report, contact sanders@ligo.caltech.edu