|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday January 20, 2003 will be:
CANCELLED DUE TO HOLIDAY
Special Items:
At Caltech: The following talk may be of interest:
@Caltech
SCIENCE, ETHICS, AND PUBLIC POLICY SEMINAR
Date: January 24, 2003 4:00 PM - 5:00 PM
Location: 25 Baxter - Find on Campus Map
"A Non-Expert Investigates Experts: A Long Term Sociological Study
of Gravitational Wave Scientists," Harold M. Collins, Andrew W. Mellon
Visiting Professor of History, Caltech, and professor of sociology, Cardiff
University.
_____________________________________________________________________________________
Date: Tue, 14 Jan 2003 10:55:28 -0800
To: excomm@ligo.caltech.edu
From: "Gary H. Sanders" <sanders@ligo.caltech.edu>
Subject: The S2 Interferometer Configuration Freeze (LIGO -M030008-00-M)
In order to assure stability in entering into a science run, to facilitate operator expertise, integration of the Lab and LSC shift presence and awareness of the interferometer state, and to balance commissioning progress with consolidation of the performance gains into a stable, scientifically useful instrument set, we have followed the practice of freezing the interferometer configurations at a significantly earlier date than the scheduled start of the planned run. Between the freeze and the initiation of the run, we expect that the interferometer operations will focus on the transition from commissioning to stable operation in a scientific mode, with a progression from tuning and minor adjustments to addressing stability and operating the entire system including the data analysis system.
Since S1, very impressive gains have been made in the interferometer sensitivities, promising a successful S2 run. Similarly, the progress in data analysis capability has advanced, also positioning LIGO for this most important milestone in our field.
The interferometers are at slightly different stages of sensitivity and commissioning maturity. In order to optimize the possibility for S2 to include comparably sensitive coincidence data from each of the three interferometers, and to focus the very small group of expert commissioners on to the critical path tasks, we will place the interferometers into a frozen configuration on different dates. We also include the E9 run schedule in making this decision.
The interferometer hardware and software will be frozen for our 3 interferometers as follows:
H1 on 17 January
L1 on 23 January
H2 on 3 February
These dates recognize the varying readiness of the interferometers and the desire to focus the remaining commissioning efforts, while preserving sufficient time to bring each instrument into stable science running by 0800 Pacific time on 14 February, the beginning of the S2 run.
The freeze cannot be defined precisely but it should mean that:
* all installations of hardware and software should be planned so that
they are
completed and working by the time of the freeze.
* Broken things, both hardware and software, can be fixed.
* The DAQ channel configuration cannot be changed without S2/commissioning leadership approval.
* Commissioning can continue (e.g., tuning the filters in the LSC loops, characterizing the WFS sensors and tuning their feedback loops, etc), but any change to the operational state of the machine (e.g., a decision to use a revised filter, or to use WFS2) would require the approval of the S2/commissioning leadership.
For the management of the transition from commissioning to science running, Stan Whitcomb will serve as the S2/commissioning leader and will make the decisions on the proposed departures from the freeze as outlined above. Stan will consult as appropriate, with the observatory Heads (Fred and Mark), the commissioning leaders (Rai and Peter), and with the Lab Directorate. In addition, Keith Riles should be consulted in his role leading the LSC Detector Characterization group.
Barry and Gary
no report
LIGO Weekly Site Telecon (Lindquist)
There was a site teleconferences held on Thursday,
January 16, 2003. The following issues were among those discussed:
Civil Construction at Livingston----We would like to close down
construction contracts at Livingston. However, there isstill some
work to be done. There is approximately $9K open encumbrance for
completed contracts that will be recovered. Also there is approximately
$57K open for completing the interior walls. Offsetting this, there
are some items for traffic control and erosion control.
Interior walls are estimated to be 85 percent complete.
Civil Construction at Hanford--We would like to get the changes needed for the new building into the Archetect's contract. Vacations are interrupting proposals for design work.
Property--The inventory at Livingston went well. Cooperation was excellent.
Traffic Control Systems--Discussed alternative locations for a traffic control gate. Constraints may force the location closer to the end of the road towards the facility. Thisd is still being studied.
Safety--There will be a safety audit at Livingston in two weeks.
The list of current actions revised to reflect
the status of open actions assigned through January 2, 2003 may be found
at ACTION
LIST.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
Re-designed the forms for the Laser Eye Exams. Consolidated multi-page form from Huntington Hospital's Center for Occupational Health into a two-sided one page form. Caltech safety office likes the redesign and is exploring its use campus-wide.
For some reason, all the process traveler templates were lost on my computer. Began to redo each of the four. To date, both the generic process traveler and the small optics process traveler have been redone. The remaining two--large optics and vacuum process travelers, will be finished tomorrow.
Supplied a working option to Ryan for use of the various storage areas with the goal of relocating several items from an office on the third floor into the third flooor storage room. This option would also give the DCC four large file cabinets in the alcove of WB51. The only downside is finding a place for the MITA copy machine presently housed in the ECR area.
Scanned in six more months of the IFIS budgets. It appears that I'm down to about 10 - 12 months and then I can begin to burn on to CDs. After this has been completed, it will be time to shred and dispose of the pounds of original IFIS reports from inception through 1999.
FY
2002 STATISTICS
There's never a better time to look backward
than when we begin a new year. During 2002, A total of 3,709
documents were processed into the DCC. The charts below show the
breakdown first by month, and secondly by category.
| JAN | FEB | MAR | APR | MAY | JUNE | JULY | AUG | SEPT | OCT | NOV | DEC |
| 446 | 127 | 206 | 130 | 141 | 116 | 314 | 321 | 301 | 1013 | 467 | 137 |
| C | D | E | G | L | M | P | T |
| 1,256 | 168 | 200 | 579 | 580 | 391 | 232 | 303 |
| 33% | 5% | 5% | 16% | 16% | 11% | 6% | 8% |
ACTIVITY
| WE 01/16/03 | Packages | Faxes |
| In | 17 | 37 |
| Out | 10 | 17 |
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA .
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
SUPPORT (Baldon, Lloyd, Tischler)
>Irene Baldon
Accomplishments:
Weekly Advanced LIGO Project Controls meeting was held on Monday the 13th of Feb. The subject of the meeting was the status of the detailed cost estimate and a forecast of a request amount.
For list of documents that are being used to develop Adv. LIGO Cost and Schedule, see http://www.ligo.caltech.edu/~tfrey/Cost_MTG_082002/
Advanced LIGO MRE Proposal (Highest Priority)
Project Web Site for posting schedule and progress related data continues to be updated with the latest and greatest.
The Annual Progress Report for Construction has been sent to the NSF..
Change Request CR-030002 to adjust the FY 2003 operating
budgets to reflect actual staffing during the first quarter has been prepared.
Additional information is required.
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
No report this week.
Summary of Commissioning Activities at LIGO Hanford Observatory (compiled
by R. Savage)
January 9, 2003 - January 16, 2003
-------------------------------------------------------------------------------------------------
It has been a very busy week for both interferometers as final software and hardware changes are being implemented in anticipation of the configuration freezes on 1/17 for the 4k and on 2/3 for the 2k.
The wavefront sensing system was again the principal effort for the 4k ifo. Aided by robust and consistent locking, significant progress was made resulting in four of the five WFS servos being engaged simultaneously.
Locking has been less consistent for the 2k and efforts are underway to realign the ISC tables in hopes of improving performance. Backscattered light was found to be responsible for a number of peaks in the noise spectrum. It appears that the source of the anomalous loss in the x-leg of the recycling cavity is the anti-reflection coating on ITMX.
DaveB has been busy with RolfB and LoriI upgrading software and is presently trying to get security patches installed on Blue to get the ilog back on-line.
Visitors included RolfB and LoriI (LSC and ASC software upgrades), BillK (thermal lensing, etc.) and NergisM.
2K IFO (H2)
-----------
DanielS made major modifications to the modecleaner servo card that
resulted in achieving a unity gain frequency of 93 kHz with 50 degrees
of phase margin, close to the design specifications. (Details: http://blue.ligo-wa.caltech.edu/ilog/pub/ilog.cgi?group=detector&date_to_view=01/10/2003&anchor_to_scroll_to=2003:01:10:12:19:07-daniel).
RobertS discovered that backscattered light from
the x-arm pickoff beam on ISCT9 was responsible for several peaks in the
noise spectrum and can affect locking.
(Details: http://blue.ligo-wa.caltech.edu/ilog/pub/ilog.cgi?group=detector&date_to_view=01/10/2003&anchor_to_scroll_to=2003:01:10:21:51:42-robert)
He is in the process of properly dumping the beam on ISCT9 and reducing
backscattered light on the other optical tables which he has shown can
reduce some of the peaks in the noise spectrum by more than a factor of
30.
It appears DickG discovered the source of the anomalous losses in the ITMX path of the recycling cavity reported earlier by BillK. He measured that the power in the x-arm pickoff beam is about 0.5 watts, about 40 times the expected level. A back-of-the-envelope calculation by BillK indicated that the anti-reflection coating on ITMX is reflecting approximately 2.5% (spec. ~ 6e-4) and that this is likely the source of the anomalous loss (see: http://blue.ligo-wa.caltech.edu/ilog/pub/ilog.cgi?group=detector&date_to_view=01/15/2003&anchor_to_scroll_to=2003:01:15:15:26:16-BillK). Garilyn B. is researching the coating records. Doug just measured the reflectivity of the witness samples for the AR coating run and they are close to spec.
MichaelL and DickG did a major realignment of ISCT7 in efforts to improve
the 2k performance. ISCT10 has also been realigned.
4K IFO (H1)
-----------
LucaM, PaulS, and RickS have made some significant progress with the wavefront sensing system. They were able to engage 4 of the 5 sensors in both pitch and yaw degrees of freedom. The servos have not been fully characterized or optimized, but early results giving clear indications of increased power levels and reduced fluctuations are encouraging.
Bill K is investigating thermal lensing using a new technique that involves
modulating the carrier loss by misaligning the ETMs (see http://blue.ligo-wa.caltech.edu/ilog/pub/ilog.cgi?group=detector&date_to_view=01/16/2003&anchor_to_scroll_to=2003:01:16:16:03:57-BillK).
no report
The low frequency response of the actuators is far lower than expected (and needed). The cause is being investigated.
Marcel Hammond, Jonathan Kern
Last weekend we machined 2 manifold plates at the
valve midlines to
physically inspect the manufacturing
errors. One was sent to Stanford
for examination. No decision
has been made about modifying the pin
valves, pending more system
tests at MIT. We have determined at least 2
possible options that would
ameliorate the problem. Dynamic measurements
using compressed air were
conducted on an actuator assembly at LLO at
the request of the Stanford
group. These were done as a sanity check,
demonstrating that the internal
components were correctly assembled and
installed. The assembly
behaves as expected. Marcel is meeting with Joe
Lacour to bring the engineering
package up to 'as built' status
incorporating the machine
shop's redlines. This is required soon in
order for the shop to submit
an accurate bid for a production quantity
for LLO. When complete we
will submit to Dennis (at long last) for a DCN
on the package.
Gains and conversions for the dSpace controller and all electronics have been checked out and all appears to be functioning properly.
We are able to close any single, local SISO vertical loop with some modest performance, but the significant change in the transfer function for each of the other piers does not permit the same controller to work on successive vertical loops. Four horizontal SISO loops have been closed but with poor performance; better control laws are being formulated. Modal based controllers are being developed and will be tried soon.
This week I have continued to work on the DMT configuration
for the E9 and
W2 runs, and on the injection monitor. I have written
and am now debugging
a Wiener filter class which
will be used to detect injected signals in
various IFO channels, and presumably many other future applications.
- Lori and I spent last week at LLO, updating basically
all the digital control
software. Changes include:
- LSC: Added third Pentek
module and moved GPS clock ramp signal from
secondPentek
to this new unit. Idea was to try and get rid of GPS ramp
crosstalk problem and Pentek
ADC polling noise.
- LOS controllers: New dewhite
and run/acquire switching.
- ASC: New input phase shifters, pitch/yaw/sum
matrices and ability to send
ASC WFS servo signals to any optic (except SM).
- EDCU and DAQ EPICS software moved to
a Sun workstation, same as LHO.
The new ASC code had problems, so we reverted back
to the previous code
version. After some mods,
we have brought the code to LHO for testing, which is
underway. We hope to
have the testing complete on the LHO4k by tomorrow so we
have time to propagate the
change to the other IFO before the S2 freeze.
Initial tests on the LHO4k this evening look good.
- Because the addition of LSC ETMX/ETMY calibration
signals as permanent LSC
DAQ channels has added even more time to the critiically
loaded LSC controller,
we have come up with an alternative.
The DAQ controller has been modified to
pick up these signals and
record them directly from the Arbitrary Waveform
Generator. Therefore,
the LSC controller is relieved of the burden of having
to relay them. Alex
sent up new DAQ controller software for this and it
appears to be working properly.
We will now modify the LSC code to remove
these signals from its DAQ
list (already installed on LHO4k).
- Alex finished up the code and testing for the new
LHO DAQ FrameBuilder
network last week.
The new network seems to be working well. The last S2 DAQ
requirement is the final
list of EPICS channels to be recorded and then ensure
that the EDCU can handle the load.
1. Working with Flavio
on the ISS. The electronics noise no longer appears to limit the
outside the loop performance. Flavio modified
the board for much more aggressive filtering of the DC reference.
The limit to the servo performance now appears to be acoustic modulation
of optical components on the table. We are looking at beefing up
the DCPD used for servo control (Ben's prototype design).
2. Working on documentation changes to accommodate
the changes for LHO on the MC servo and the PSL temperature box.
Jay Heefner reporting
Pentek Noise and Glitch
Testing: Testing has been completed and the report issued. The document
number is T020201-A-C and should be available in the dcc.
LOS Coil DAQ Readout: Preliminary circuit design and
simulation continues.
EMI Upgrade: Met with several vendors of EMI rated
VME crates and racks.
Universal Dewhite Boards: Issued DCN and schematics for Rev B6 version of the Universal Dewhite board.
The high current photodetector
was taken out for a test drive. The
prototypephotodetector
ran with a light level consistent with 165 mA
of
photocurrent. No problems
were noticed during the 30 minute trial, apart
from the smell of warm electronics
(due to not having the right power-rated
components on hand).
The dark noise was re-measured after the exposure
trial and was found to be
the same as that reported last week. The best
noise measured thus far has
been 1.4 nV/Sqrt[Hz] at 10 Hz but this has
not
been reproducible during
the day. I have also been looking into other issues
such as appropriate heatsinking
and packaging of the photodetector.
A 10 kHz peak present in the output of the photodetector
was tracked down to
an interaction between the
1 uF capacitor used on the output of a
5 V
regulator used to bias the
photodiode. The de-coupling capacitor was
varied and its effect on
the dark noise of the photodetector was
measured,
resulting in the end use of a 0.33 uF capacitor.
Lee Cardenas
10 watt laser, MOPA S/N 119 sent to be repaired on
Lightwave Electronics contacted, laser is
under test and still waiting its arrival.
An errant laser beam analysis was completed and submitted
to the DDC: Errant Beam Analysis, LIGO1, LIGO-T030006-00-D.
Simple heat flow models were used to estimate the heating of suspension
wires caused by errant laser beams directed by rogue mirrors. The laser
spot size, power, and energy of errant laser beams were calculated using
the parameters of the 2K and 4K interferometers. Errant beams were located
by drawing rays on the ACAD integrated layout drawing and by tracing rays
using the ASAP ray trace program. The wire heating estimates are in agreement
with the demonstrated failure of the MMT2 suspension wire. Based on the
temperature rise estimates of heated suspensions wires by errant beams,
it is concluded that in the 2K IFO and in the 4K IFO the MMT1 (or SM1/SM2),
MMT2, and MC2 are potential rogue mirrors that might misdirect laser beams
and cause damage to the suspension wires and to the OSEM signal cables.
The following recommendations for additional baffling are made:
Protective baffles should be mounted on the MC1, MC3, SM1, SM2, MMT1,
and MMT3 mirror suspension structures to shield the suspension wires and
OSEM cables from the line of sight to the MMT2 mirror and the MC2 mirror.
Baffles should also be placed on the HAM1/HAM 7 optical tables in order
to shield all OSEM cables from the line of sight to MC2 and MMT2.
Protective baffles should be mounted on the MC2 and MMT2 mirror suspension
structures to shield the suspension wires and OSEM cables from the line
of sight to the MMT1 (or SM1/SM2) mirror.
A baffle should be placed on the AR side of the RM to shield the suspension
wires of the RM from the line of sight to the MMT1 rogue mirror.
I have some results regarding the performance of Ligo
I when realistic maps
are used (for the mirror
error figures) obtained by adapting the measurements
done by Garilynn
to the FFT-code grid. The radii of curvature are all matched
and I have not gone through
the sideband case. The reflectivities might
not be
the "measured" values so
the impact on the power gain should be rescaled
according to the real Finesse
of each cavity.
No map R.M. R.M., one ITM
R.M., two ITM R.M., two ETM R.M., ITMs, ETMs
Gain r.c. ~same
-6.5%
-12.5%
-38% -42%
Gain arm ~same -6.6%
-12.6%
-38% -43%
The biggest contribution is due to the ETM mirrors
for two reason:
1) of course the spot
size is larger on those mirrors and thus the beam profile
samples areas of the surface
that are not as good as the central part.
2) However I wanted to make a special test by putting
those error figure maps
on the top of the ITM mirrors.
I expected a reduction ~12.5% assuming the
microroughness
were not very different in the ITM and ETM mirrors. On the
contrary I obtained a large
reduction:
~20% in the case R.M., two ITM with ETM microroughness.
All the mirrors have a structure that repeats itself
on a range ~3mm.
The Fourier Transform of the data shows the corresponding
peak and several
of what I presume are its
harmonics. It should be caused by some spatially
repetitive mechanism that applies when the surfaces of the mirrors are treated.
With many thanks to Dennis Ugolini,
the metrology lab is back in control (thermal that is.) The temperature
controller had been out of commission. Dennis volunteered to track
down the problem and found a burnt out relay inside the controller unit.
It appears all the smoke had leaked out.
Now all we need to get the lab back in full service is a visit from Veeco to re-align the interferometer internally. It now shows a visible mis-alignment and is not useable for much of anything. Having the room temperature stable is important for the re-alignment.
OTF Lab at Lauritsen
ROOM 38
Cavity #3 Reference Cavity.ready!
Taking CAVITY measurements every day as well as RGA.
The ring down measurement has increased due to mirror surface film
being cleaned by
the continuous pumping.
Cavity #2 Test cavity
The chamber is pumping with new cleaned mirrors ~ 70ppm each.
We are taking RGA measurements. Total pressure
~8E-10 torr.
preparing and gathering the necessary optics
for the optical train for this contamination cavity.
New chamber ready for modification ( silver
solder a new base and make base insulator)
Still waiting on the machine shop.
I got the new spare NPRO YAG Laser from Shanti
Model # 126-1064-700 S/N 414.
This laser will be used for the new contamination chamber.
New Laser Aluminum base blocks are being fabricated for the other lasers to match the optical height.
New Laser being tested.
This laser is running at 1047 mm wavelength with max. power
of 500 mW. optical
alignment completed.
Measurements of current vs power are
in progress by MohanaMageswaran.
OTF Lab. (W. Bridge)
Contamination Cavity # 1
Cavity with test sample aquamill still
in progress and taking measurements every day.
We'll continue taking measurements for one more week.
I have received a new test sample of Glycol plus water and some additives
from Ken Mailand.
We'll test this sample next week. New mirrors are being prepared
for this new test.
Scatterometer at West bridge
Scatterometer
optical train recovering is in progress.
This week we turned down the power in the TNI to see if we could
achieve long-term locks in the arm cavities. We were successful, but
only after turning the power down by a factor of ten. Even with this
low power, our enhanced visibility (due to careful realignment) and
removal of several collimating lenses has given us a pretty good
displacement sensitivity. Preliminary measurements show that our
sensitivity is comparable to what we were seeing previously.
We still
do not understand the source of the transient locks at high powers,
and
are continuing to investigate this phenomenon.
We also produced a fairly good spectrum of the photothermal response
in fused silica. The spectrum compares well with our models,
and with
what we saw previously using an aluminum substrate. We achieved
a high
signal-to-noise by coating the silica mirror with gold, thereby increasing
the absorbed power relative to a dielectric coating. We will
soon measure
gold-coated sapphire as well.
LASTI (Coyne, Forbes, Hammond, Kern, Mason, MacInnis, McKenzie,
Mittleman, Ottaway, Rankin, Rollins, Shoemaker, Zucker)
---------------------------------------------------------------------
MEPI characterization & test
-----------------------------------------------------------------------
Control of the Ham stack has been found to be
more difficult than the
BSC due to the weakness of the HAM crossbeams.
A meeting was held with
Professor Samir to develop solutions and a design to help resolve this
problem. A structure has been designed which will connect the
crossbeams. In addition structural dampeners will be designed
which
will run along the length of the crossbeams.
In the interim we have managed to close a loop around all four vertical
actuators. This was accomplished using a local control strategy
with
moderate gain between 1 and 10 hertz, and multiple unity gain
crossing.
HEPI characterization & test
-------------------------------------------------------
After bleeding the actuators over the weekend to remove collected
air, we are recharacterizing the system and investigating the
differences between the measurements and the model predictions.
We've had a succession of new noises from the hydraulic pump. Ken
Mailand is helping us work through diagnostics; in the meantime he
has
procured a spare pump and motor for us, just in case.
We believe we've found a usable workaround for the leakage problem
on the actuator needle valves while Jonathan, Marcel and Corwin
work through the valve tolerance and manufacturing issues more thoroughly
(see Jonathan Kern's report). We still have some instances of weeping
but are monitoring them carefully.
Triple Suspension Prototype Test
-------------------------------------------------------
We are taking delivery of the HAM support structure for the
triple suspension test shortly and will send it out for cleaning and
baking,
but have been persuaded to hold off shipping the suspension itself
from
Caltech for a few weeks. We currently have our hands full with
HEPI and
MEPI, and Janeen et al can use more time to understand the system
at home before we install it.
SIMULATION AND MODELING (Bhawal)
E2E MODELLING:
Weekly Physics Meeting
Luca discussed various issues related to the progress made
in WFS work in H-1 and ASC in general. Matt reported some studies
he made on WFS using SimLIGO.
LLO seismic isolation requirements
Virginio, Matt and Hiro discussed how to evaluate the requirements of
the preisolation system for LLO.
More information is gathered to identify how the simulation can be
used
to provide complementary information to help to quantify the requirements.
SimLIGO
(Matt) Tested SimLIGO with mode-matching. Mode-matching allows us to
simulate
mirror curvature effects and is very important to understanding
the
sideband behavior in the IFOs, since the power recycling cavities
are,
at present, very poorly mode-matched. This has implications
in both
LSC (including lock-acquisition) and ASC control systems.
Configured lock-acquisition for multi-mode simulation. LA
now works
in SimLIGO with slightly less than perfect mode-matching (about
10%
of the way to the real "cold" IFOs).
Added QPDs to SimLIGO's ASC control system. The QPDs are
used to control
the BS and MMT3. Since MMT3 is not currently included in
SimLIGO, only
BS control was added.
Modal Model update
(Hiro) The modal model C++ class code is updated to implement unlimited
number of modes in the simulation. The documentation is updated,
and the
simulation engine code is being updated to use these new codes.
Alignment signals
(Biplab, Hiro) Worked on validation of the alignment signals from the
output port of a LIGO model by comparing with analytical calculation
and
with corresponding values given in '97 paper by Peter Fritschel
et al.
Alfi
(Bruce)
- Continued work to distribute
Alfi using Java's Web Start,
which involves
educating myself on public/private key
security, digitally
signing our jar files, and working with
our systems
people to configure the web server appropriately.
- Worked on misc minor PR
feature requests like saving options
and window space
between Alfi sessions.
(Melody)
- Continued with the automated
tester for alfi5.
- Did some regression testing
using the newest version of Java (1.4.1).
- Fixed some PRs.
LIGO DATA ANALYSIS SYSTEMS
SOFTWARE SYSTEMS (Blackburn)
The problems encountered with using the new MPI library from LAM were
tracked
down to having Red Hat Linux version of LAM pre-installed on all LDAS
beowulf
nodes in combination with the definitive LDAS version stored in the
/LDCG tree.
This Red Hat LAM was the same version previously and caused no noticible
issues
at build or run time. However, with the newer LAM libraries and header
files it
was unstable. Once the Red Hat PRMs were removed, the issues with the
new LAM
ended. We will therefore adopt the new version 6.5.8 in the next release
of
LDAS.
We began enhancing the LDAS username/password application web site to
support
user requests for account extensions. This is expected to be in place
around
the time of E9, well in advance of S2. With this new feature, users
will not
be trouble by expiring accounts at critical times such as science runs.
There continues to be a large effort required to support the compression
modes
outlined in the frame spec. Several of these compression modes do not
work for
particular data types or in particular combinations as outlined in
the spec.
We continue to work closely with VIRGO to sort out all the issues that
reside
in the details of implementing compression support.
LDAS stability did improve this week. The two largest failure modes
are now
a 3600 second timeout in the frameAPI which is now thougtht to be due
to the
Solaris Kernal's thread scheduler and an initialization failure in
MPI. To-
gether, they account for about a 1% failure rate in our nightly testing.
At
this time, there is not a solution that will reduce these random failures.
The LDAS hardware at the sites are being upgraded this week. We hope
to push
a pre-release of LDAS this friday assuming that the upgrades complete
in time.
This will not be the version of LDAS to be used in E9. But because
our CVS
repository is in a code freeze and only bug fixes are allowed to be
committed,
the functionality should be very similar to what is in place for E9
late next
week.
HARDWARE SYSTEMS (Anderson)
CALTECH
(Dan Kozak)
* Continued testing SAM-QFS 4.0, also installed and tested QFS 4.0 as
a
shared reader (of a filesystem created under 3.5). The
"known problem"
mentioned in the README doesn't seem to affect us: a test read
of 4000
files averaged ~65Mb/sec, on par with the performance we saw
under 3.5.
* Placed order for 420 9940 tapes.
* Continued to work with Qlogic on 2Gb FC HBAs.
(Stuart Anderson)
* Finished building development tools for the Solaris 9 version of /ldcg.
* Upgraded LDAS-CIT to Solaris 9 and documented the procedure for
LHO, LLO, and MIT to follow.
* Upgraded 6 Millikan desktop machines to Solaris 9.
* Mirrored 2000s of coincident full frames from LHO and LLO to test
the
compatability of the new version 6 frames being written by CDS
with
the new release of LDAS.
MIT
(Keith Bayer)
* Removed earliest ldas_archive file from /export to solve space crunch.
* Received new DDR rackmount cluster node and installed RedHat 8.0.
* LDAS Solaris 9 upgrade underway.
* ldas-pcdev1 upgraded to cluster machine version with SSL apache and CVS.
LIVINGSTON
(Igor Yakushin)
* Upgrading Solaris 8 to Solaris 9 on E450s and V880.
(Shannon Roddy)
* Connected ControlMon to the ldas network. I had some difficulty
connecting it, since I am at the distance limit for the media
converter
that we are using. It is connected in a temporary fashion
now, but will
be permanently connected next week.
* Had some trouble evaluating the AMD systems for the next beowulf
purchase. This turned out to be an oversight by the vendor.
The
motherboard that was used will only allow 1 piece of DDR 400
ram. They
had two pieces in there to supply the requested 1 GB of ram.
This
caused severe stability problems. The vendor is working
with me to
solve this problem. It will probably amount to them sending
me two
pieces of 512 MB DDR333 memory.
* Completed the LDAS move last week. Everything came up without
too much
difficulty. As far as I am aware, there are no problems
so far.
HANFORD
(Greg Mendell)
* Set up the ldas-jobs box on the GC network, working with Christine
Barker, Patrick Brady, Duncan Brown, and Igor Yakushin. This
box will
serve as the LSC interface to LDAS at LHO, and provide monitoring
of the
search code running on LDAS from the control room.
* Recovered the T3s used by the framebuilder fb0 for use with LDAS.
* Currently working to upgrade the LDAS LHO Sun computers to Solaris
9.
DATA ANALYSIS (Blackburn)
Alan Weinstein:
- Prepare proposal for hardware burst injections for E9/S2;
submitted to Marka and Shawhan on Wednesday.
- Working with Patrick on readying burst scripts for online
running during E9/S2. In progress.
- Work with Philip Charlton to develop respfilt()
datacond action to filter bursts through time-dependent
calibration (strain -> AS_Q). Currently under testing. Thanks,
Philip!
- Communicating with Gaby on status of S1 and S2 time-dependent calibration.
- Working with PSU student on testing PSU LDAS with burst scripts.
- Discussing coincident cross-correlation approaches with Julien.
- Working with Laura Cadonati on completing memo on burst efficiency for S1.
Peter Shawhan:
Attended a meeting at SLAC to help plan a conference on statistical
methods
for physics data analysis ("PHYSTAT 2003"). Many of the topics
to be discussed
are things which are relevant for LIGO data analysis, including signal
significance measures, confidence intervals, systematics, and techniques
for
combining results from multiple measurements or limits. There
was a very
lively discussion on many of these topics during the planning meeting.
Teviet Creighton:
Worked at firming up numbers of templates and computing resources required
for LIGO-II inspiral searches.
Igor Yakushin:
Making last minute corrections to waveburst DSO and its documentation
to
prepare for the new LAL/LALWrapper release.
Greg Mendell:
1) Updated driver scripts for the knownpulsardemod to request the
calibration data from ldas and successfully ran jobs using the
calibration at LHO. One problem is that the calibration data itself
is
not valid when the IFO is not locked, but I have SFTs that cover
nonlocked times (and padded out these times when the SFTs were
generated). I'll have to figure out a way to handle this.
For now I am
only working on contiguously locked stretches of data.
2) Checked into lalwrapper cvs knownpulsardemod code updated to output
a
real8 value to the summvars database table. Added the option
to output
calibrated SFTs. Removed a factor of from the definition of the
power
spectral density noise estimation that is done from the SFTs.
This was
to agree with the PULG groups definition of S_h.
3) Started implementing an option to high pass filter and window the
input time series data before generating SFTs. This will be used
when
generated short SFTs, e.g., from 64 s of data, as opposed to generated
2048 s SFTs.
GENERAL COMPUTING (Wallace)
MIT:
-Upgraded file server with new SCSI drive
-Worked on matlab/mathematica software licenses for new year
-Restored data from tape for user
-Working to restore 1999 data for old user
Livingston:
(Shannon)
-Looked at some problems I have been having with my tape library for
GC
backups. The tapes are catching on something in the tape
drive when
they are ejected. It is probably just a rough edge somewhere
on the
tape drive. This is the first problem I have had in over
two years of
using the Exabyte library. I have disabled that drive until
I can solve
the problem. There are two drives, so backups are still
being done
nightly.
-Found a problem with the GC switch in the new building. I was
getting
10-15% packet loss between the core switch and the edge switch.
This
has been determined to be a bad fiber connection. I am
not sure if they
need to be cleaned or terminated again, but I have fixed this
just by
switching to a better pair of fibers.
-Looking at some problems on touro, the secure shell daemon will drop
a
secure shell connection after a couple of hours. I will
probably just
upgrade this machine to Solaris 9 later this week or early next.
-Had Larry arrange for some DNS name changes at CalTech to accommodate
some new LDAS machines.
Hanford:
(Christine)
- Helping with an audit which required backups of PCs and e-mail files,
making DVD and tape copies of files, pulling old backups off
tapes and
securing an account.
- Dealing with suspicious activity on the network. Had to block
a
couple of addresses and finally tracked the problem to an internal
computer which has been removed from the network and is being
re-built.
- Mounted some files from the DMT computer to the LSC sandbox computer.
- Created another special LSC user group and added user accounts to
it.
- Attended a phone conference meeting with PNNL, DOE, UW Gigapop and
Ligo to discuss an OC3 WAN network connection for LHO.
CIT:
(Lisa)
- Did beta testing and troubleshooting on certificate based mail relay.
This is
fully functional with Netscape 7. I have not yet tested
other mail clients.
Mail over secure socket layer is also working well and is ready
for people to
use.
- Worked on the build of markab to replace www.ligo.
- Cleaned up the log rotation on the mail servers.
- Did some account management.
- Generated a number of certificates to support web servers and code
signing.
(Veronica)
- LIGO website: posted various updates (SURF 2003 program, Aspen
conference, roster etc). Did some troubleshooting of one of
the DCC
databases. Working on the Advanced LIGO proposal.
- LSC website: posted updates and did usual maintenance.
- CaJAGWR website: videotaped the talks by Roger Blandford. Posted
updates
to the seminars webpage.
(Mike)
-Worked on all the NT servers doing administration that included reviewing
security, application and system logs.
After reviewing logs I found that Pictor, which hosts the Primavera
software & flexlm-licensing server for ansys, is coming to
its maximum
capacity towards disk space. I will have to move some data around
until our
new replacement server comes in. This server is due for an upgrade,
which
is already ordered.
-Working on moving the real media server to a larger disk drive to
allow much more needed space for media files, which are eating
disk space
rather quickly.
-Finished up loading Hareem's computer with G/C software and multiple
engineering software packages.
-Loading two other PC's that included hardware upgrades/OS and software
rebuilds. These computers are will be designated to users who
have older
computers.
-Cleaned up four laptops and updated service packs to put back into
the
loaner pool; these are ready to go and are back into the pool.
-Loading another laptop that needed some hardware replaced & a
complete
reload of OS/General computing software.
-Tested the SolidWorks software from the "its.caltech.edu" archive,
so far
everything looks okay but I well still need to run more tests
and have Dennis
Coyne approved of this before switching some of our users over
to the ITS site
license server. This well free up some of our single user licenses
that
could be used for travel.
(Larry)
-This past week I have been doing a lot of procurement related activities.
-Worked a couple of network and security issues.
-Added a couple of new users.
-Modified a couple of user accounts.
-Worked/working on the WAN connections for the Observatories.
-Working issues with the GigE connection on Campus.
From: "Mark Barton" <mbarton@ligo.caltech.edu>
This week I spent several days in the Synchrotron
identifying the
normal modes of the mode-cleaner triple suspension prototype. All were
fairly close to the predicted values based on measured properties of
the
as-built version in my Mathematica model - within a few percent in
most
cases. By far the largest discrepancy was 26% for the fundamental pitch
mode, but this is not unexpected given the sensitivity of this frequency
to the equilibrium height of the tips of the blade springs.
I also released version 1.4 of my Mathematica triple
model and v 2.5
of my quad model, as well T020011-00 describing comparisons I did a
while
back between the Mathematica and Matlab suspension models. Both new
model
version have additional functions for calculating transfer function,
and
the triple has a new case reflecting the MC prototype.
Finally, I finally got the SOS to be used for the
earthquake stop
test under servo control in a vacuum. Jay Heefner set me up with a
terminal that I could use to adjust the gains on the controller. The
gains had been set for use with MOSs at the 40 m and were too high
for SOS.
From: Peter King <pking@ligo.caltech.edu>
2.1 PSL
=======
The high current photodetector was taken out for
a test drive. The
prototype photodetector ran with a light level consistent with 165
mA of
photocurrent. No problems were noticed during the 30 minute trial,
apart
from the smell of warm electronics (due to not having the right power-rated
components on hand). The dark noise was re-measured after the
exposure
trial and was found to be the same as that reported last week.
The best
noise measured thus far has been 1.4 nV/Sqrt[Hz] at 10 Hz but this
has not
been reproducible during the day. I have also been looking into
other issues
such as appropriate heatsinking and packaging of the photodetector.
A 10 kHz peak present in the output of the photodetector was tracked
down to
an interaction between the 1 uF capacitor used on the output of a 5
V
regulator used to bias the photodiode. The de-coupling capacitor
was
varied and its effect on the dark noise of the photodetector was measured,
resulting in the end use of a 0.33 uF capacitor.
2.2 AdvLIGO PSL
===============
I spoke with Chris Thalken of Coherent about getting
an updated
quotation for the laser diodes. Apparently Coherent were shutdown
over the
Christmas/New Year period, hence the delay in getting back to me.
Since
the original quotation for the diodes was requested, Coherent have
a new
model of laser diode that incorporates an internal power monitor and
temperature cooler. The good news is that the new and improved
laser pump
diode costs less than the old ones in the costing ($6950 for 50 or
more as
opposed to $7500). The original diodes have also decreased in
price to
$4950 from the original $7500.
From: Michael Smith <smith@ligo.caltech.edu>
40 METER IFO
OPTICS PARTS LIST
Received parts:
Some of the mechanical parts for the mode matching telescope were received.
Orders pending:
Input mode-matching telescope off-axis parabolic mirrors are pending
from SORL; re-worked half-wave plates from KLC, for the Faraday isolator;
drive electronics to drive the x and y axes of the 2nd PZT vacuum IFO steering
mirror, from Piezo-Jena. Mounting collar for mounting the PZT tilt platform
onto the DLC vacuum mirror mount and the mirror holder, from CA Machine.
IFO MODE-MATCHING TELESCOPE
Some of the telescope mechanical parts are still in process of being
fabricated.
OPTICAL LEVER
Mechanical parts for magnified focus lens are in process of being fabricated
by two outside machine shops.
LIGO
ERRANT LASER BEAMS
An errant laser beam analysis was completed and submitted to the DDC:
Errant Beam Analysis, LIGO1, LIGO-T030006-00-D. Simple heat flow models
were used to estimate the heating of suspension wires caused by errant
laser beams directed by rogue mirrors. The laser spot size, power, and
energy of errant laser beams were calculated using the parameters of the
2K and 4K interferometers. Errant beams were located by drawing rays on
the ACAD integrated layout drawing and by tracing rays using the ASAP ray
trace program. The wire heating estimates are in agreement with the demonstrated
failure of the MMT2 suspension wire. Based on the temperature rise estimates
of heated suspensions wires by errant beams, it is concluded that in the
2K IFO and in the 4K IFO the MMT1 (or SM1/SM2), MMT2, and MC2 are potential
rogue mirrors that might misdirect laser beams and cause damage to the
suspension wires and to the OSEM signal cables.
The following recommendations for additional baffling are made:
Protective baffles should be mounted on the MC1, MC3, SM1, SM2, MMT1,
and MMT3 mirror suspension structures to shield the suspension wires and
OSEM cables from the line of sight to the MMT2 mirror and the MC2 mirror.
Baffles should also be placed on the HAM1/HAM 7 optical tables in order
to shield all OSEM cables from the line of sight to MC2 and MMT2.
Protective baffles should be mounted on the MC2 and MMT2 mirror suspension
structures to shield the suspension wires and OSEM cables from the line
of sight to the MMT1 (or SM1/SM2) mirror.
A baffle should be placed on the AR side of the RM to shield the suspension
wires of the RM from the line of sight to the MMT1 rogue mirror.
From: Helena Armandula <ahelena@ligo.caltech.edu>
Silicate bonding - SF4 glass
Continued testing more parts from the first bonding batch.
Pull test -
SF4-6 - I was able to pull this bonded substrate to 26 kg when one
of the substrates separated from the fixture holder. Re-bonded and tested
again, this time 54 kg of pulling force was applied when once again, the
bond to the fixture broke. Part remains to be fully tested. No apparent
changes observed on the bond.
SF4-2 - Pulled to 61 kg, held the tension; the bond separated within
seconds. Glass from the SF4 substrate was pulled mainly around the edge.
SF4-1 - Pulled to 12 kg and held the load. Stress could be observed
as I was pulling; the stress remains on the part still under tension now
for about 4 hr
Sheer test
SF4-5 - Encouraged by the latest results, loaded this bonded substrate
under sheer stress with 4.5 kg; it has been loaded for the last 2 hr
I have no explanation as why the first two bonds failed.
From: ctorrie <ctorrie@ligo.caltech.edu>
I have been helping Mark Barton to measure and compare the modes of the prototype triple pendulum with theory. In order to do this I have been working to ensure that the parameter file in the model resembles as close as possible the actual setup. Using both the original MATLAB model and Mark's MATHMATICA model we have been investigating discrepancies between the theory and experiment. Mark has included the results in his weekly report.
Helena and I have been working to on the 2nd suspension suspension,
in particular to include the global control OSEMs and there associated
magnet and dumbbells. This also involves replacing the suspension wire
and adding a roll adjuster to the upper mass.
Once this is completed we are going to test the LIGO 1 rotational adjusters
on the structure.
Report on visit to IGR at the U. of Glasgow
Eddy Current Damper
Mike Plissi at the U. of Glasgow has 3 XYZ shakers under a triple pendulum
set up that he has been using to test a 4x4 array eddy current damper in
the vertical direction. Over the course of my visit we set up the Caltech
designed 2x2 array with fine adjuster on the Glasgow triple pendulum. This
can be seen at the following link: - http://www.ligo.caltech.edu/~ctorrie/ecd.html.
Q measurements were made on one of the vertical modes of the pendulum
and the results compared very well with what was expected. The adjustment
mechanism, allowing you to align the copper wrt the magnet array proved
to be fairly easy to use. It was also noted that for ease of alignment
that the copper array should be made longer and have 4 removable inserts.
Several other upgrades were noted from observations made, by Alastair Grant,
during the alignment of the array and these will be included in the re-worked
design.
The next steps include: -
1) Testing the 2x2 array on other degrees of freedom on a single pendulum
at Caltech (Willems and Torrie)
2) 6 re-worked 2x2 arrays will be tested on the 2nd prototype suspension
at Caltech
Blade Wire Clamps
http://www.ligo.caltech.edu/~ctorrie/bladewireclamp/bladewireclamp.html
Several designs of blade wire tested in Glasgow. In particular the Breaking
Stress for the combination of clamp - wire - clamp was investigated. 2
rounded blade wire clamps used in combination with spring steel wire, as
outlined in the above link, led to an improvement of ~15% in the Breaking
Stress when compared to 2 straight edged blade wire clamp used in combination
with spring steel wire.
The next steps include: -
1) Testing of an upgraded design of the rounded clamp that has a sharp
edge incorporated in order to define the break off of the wire from the
clamp. this will be carried out in Glasgow. (Cantley, MPL, Jones)
Library of Clamps
http://www.ligo.caltech.edu/~ctorrie/upperbladeclamp/upperbladeclamp.html
The so called library of clamps were tested on several different designs
of cantilever blades. The library of clamps consists of set of clamps,
used to fix the cantilever blades, that are incrementally angled in the
direction of the blade from 0.5 degrees to 3.5 degrees, see above link.
These have proved to be an excellent asset in correcting the error
associated with the deflection of a cantilever blade under load.
The idea behind testing these clamps of various blades was to build
up a set of data sheets that can be used when selecting a particular clamp
set for a blade with a known deflection under load.
Other discussions
A second set 15 coil formers and there associated parts were sent to
be machined. These included a couple of small upgrades that were included
after a fit test was carried out by Janeen and I in late December.
Norna Robertson and I spent some time with Caroline Cantley bringing
her up to speed on the Recycling Mirror Design. We hope to have final parameters
for this design in the next couple of weeks.
Mike Lloyd, Russell Jones and I have been testing using the LIGO SSH
secure shell file transfer as a method of exchanging files between Glasgow
and Caltech. This looks like it will be a working solution in light of
3D-TeamWorks being removed by SolidWorks.
Jim Hough has offered that Mike Lloyd could return to Caltech gain
for a month or so to work on the Recycling Mirror design. He also suggested
that Caroline Cantley join us for the MC installation test at MIT and invited
me back again for a month or so in the summer to work on aspects of the
prototype quadruple suspension, for LASTI, with Engineers from both U.
of Glasgow and Rutherford.
From: Janeen Romie <romie_j@ligo.caltech.edu>
AdLIGO Suspensions
Still inputing proposal changes. Finally done this morning.
In the MC prototype meeting on Tuesday, we discussed the status of
the triples and the test plan.
From: Dennis Coyne <coyne@ligo.caltech.edu>
ETF / Advanced LIGO pod bases
We are getting all of our source and history files to Linda Turner,
and
will clean up or complete the technical notes and data representing
Marcel's modeling efforts. (Hammond, Kern)
For additional information about this report, contact sanders@ligo.caltech.edu