Weekly Report for Week Ending August 22, 2002


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  August 26, 2002 will be:

  (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

   1.Announcements
   2.LSC Issues (Weiss)
   3.Comments on Weekly Report
   4.WBS 1 LIGO I Construction (Lindquist)
               Field Change Orders/Contingency Liens/Change Requests
   5.WBS 2 LIGO Lab Operations
               Administration (Lindquist)
               Sites (Raab, Coles, Shoemaker, Sanders)
               Detector (Whitcomb, Coyne)
               Campus Research Facilities (Weinstein (40 Meter), Libbrecht (TNI), Zucker(LASTI))
               Data Analysis and Computing (Lazzarini)
   6.WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
   7.CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION AS NEEDED

  As of Wednesday, August 21, no additional information has been received regarding open Change Requests and requested actions.
Executive Committee only 11:30 - noon   Topics:

Special Items:


Special Announcements:


Weekly Report Highlights
 


LSC Issues (Weiss)


No report, LSC meeting this week.


LIGO I Construction/LIGO Laboratory Administration (Lindquist)



LIGO Operations--Administration


LIGO Weekly Site Telecon (Lindquist)

There was no site teleconference held on Thursday, August 22, 2002.

The list of current actions revised to reflect the status of open actions assigned through August 15, 2002 may be found at ACTION LIST.


PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACCOMPLISHMENTS

> From: Cleveland Mak <mak_c@ligo.caltech.edu>

ACTIVITY

Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.

COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA .

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>

CONSTRUCTION:

OPERATIONS:

SUPPORT (Baldon, Torres, Lloyd, Tischler)

>Irene Baldon

>Dorothy Lloyd >Rita Torres >From: Ryan Tischler <rtischle@ligo.caltech.edu>

Advanced LIGO (Frey)

From: Thomas Frey <tfrey@ligo.caltech.edu>

Progress Period from 08.09 to 08.22 (Two Weeks)

Accomplishments:

Schedule 08.23 to 08.29:

Reports (Lindquist)

Change Control/Contingency (Lindquist)

The following change requests have been submitted:
 

Open or Recent Change Requests
CR-010012 
Revision B
WBS 1.4.4.1 Closeout Construction Budgets for Initial Computer Equipment Complement at the Sites P. Lindquist
CR-020009 OPs Digital Common Mode Servo to Mode Cleaner Path D. Coyne
CR-020011 OPs High Power Test in Suspended Interferometer (Gingin) D. Coyne
CR-020012 OPs Additional Funds to Complete 40-Meter Facility Upgrade A. Weinstein

Human Resources (Akutagawa)

From: Cindy Akutagawa <cindy@ligo.caltech.edu>


Quality/Safety (Tyler)

>From: Bill Tyler <tyler@ligo.caltech.edu>

No report this week.


LIGO Hanford Observatory (LHO) and Interferometer Operations (Raab)


No report this week.

LIGO Livingston Observatory (LLO) and Interferometer Operations (Coles)


HEPI: This week's main goals have been to fit the HEPI actuator up into the boot that was made for the MEPI design. Final efforts have been made towards the mate of the hydraulic actuator to the boot. Concerns of L4C sensor location still concern me, as well as Jonathan Kern. Hopefully, this will be resolved by tomorrow. I spoke with Ken Mason late last night and we discussed several possible solutions for the placement of the L4C sensor. Once I finish the mounting of the aforementioned, I can once more proceed with the plumbing all of the actuators together (on each BSC assembly). During some of my free time I have been assembling the HAMS and BSC's with the changes made by EPI into one large assembly (of the entire LIGO) with the intention that other groups, i.e. suspension, optics, et al will be able to benefit from the digital model. This is an ongoing effort and is done mostly on weekends, so when I finish it, I will advertise this so that it can be utilized. The pre-isolator machined springs have been the Electroless Nickel Plating of Louisiana (ENP) and have been promised for tomorrow (Friday the 23rd). I delivered a shipping box designed especially for the springs and they have conformed that the springs will be ready midday. The fabrication for the HEPI units continues. The Actuator plates have been delivered and we are picking up vendor concerns as redlines into the drawings so that the drawing package stays up to date. The bellows have still not arrived on site yet but are expecting them any day. (Marcel Hammond)

First batch of parts for the actuator was received from P&N Monday. The parts comprising the actuator plate and resistor assembly were to spec, and were received carefully wrapped and in first class condition. An Actuator Plate, Diaphragm and Diaphragm Restraint set have been sent to Solar Atmospheres in Souderton, PA for vacuum brazing of a first article. HYSPAN shipped the bellows on Aug 15. (Jonathan Kern)

GC: Attended the Usenix conference in San Francisco and made some valuable contacts. I learned of a software product for configuring PIX firewalls (among others) that looked very useful. I will be arranging a web demo with them to further evaluate the product. I think this will be very useful for the project. LDAS: Set up a vpn tunnel between LLO and CIT last week. I will be doing some further testing once Stuart and I can coordinate some tests. (ShannonRoddy)

Preparation for S1: We have been able to easily lock the interferometer in a low noise state and maintain it in that state for hours during the night. During the day, the seismic noise continues to worsen. Logging activity is approaching the vertex area, creating some of the highest BLRMS 1-3 Hz readings we've seen on a continuous basis - around 100 counts and rising daily. Logging activity is about one half mile distant at present but will approach the property line around the LVEA over the next 2-3 weeks. We have been preparing the general area within the LVEA and VEAs to remove sources of electronic noise and mechanical vibration that can be turned off or removed during the run, such as lights in the VEAs, dust monitors, annulus turbo pumps, etc. Signs and chains directing and controlling traffic flow around the site will set up Friday morning. The auto-locker script which acquires interferometer lock, turns on the common mode, increases the optical power, and recovers if lock is broken, has been tested repeatedly this week and seems to work very well.

LSU Chancellor Mark Emmert will visit LLO on September 5. Louisiana Secretary of Economic Development Don Hutchison will make a presentation to the Southern Governors Conference this Saturday that will include mention of LIGO as a contributor to the technical resources of the southeastern Louisiana region.


Detector/Technical Support (Coyne)


DETECTOR SCIENCE & ENGINEERING

Seismic Upgrade Project

EPI modeling
Brian Lantz discussed and shared a version of the basic Matlab code for dynamics and control simulation with Dave Ottaway, Rich Mittleman and Dennis Coyne. This version includes a more general formulation for handling the sensors. Dennis is making progress on a more realistic dynamics model of the HAM support structure to be used in conjunction with the existing stack model. Rich and Dave are progressing in adaptation of Brian’s BSC/HEPI code to the HAM/MEPI application.
 
MEPI / LASTI
(Mason, Ottoway, Mittleman, MacInnis, Megan, Kern)  The installation of the External Pre-Isolators is proceeding very well.  We installed the last 2 of 4 EPI housings this week and the heavy lifting is completed.  The HAM is now supported on the EPI's hard stops, and the assemblies have been shimmed and leveled.  The pneumatic lifts for coarse actuation have been installed and tested.  Myron designed a clever fixture that allowed us (with considerable manhandling) to remove the old piers and install the EPIs in the very cramped area between the vessel and wall. After completing all four installations, we're pleased that the measured displacement in all three axes, at all four corners is < 0.005" and yaw <50u-rad. Next week we will install the EPI suspension springs and load cells, and begin the task of leveling and aligning the table.  See some images of the installation at here
 
HEPI Actuator
(Hammond, Kern)  First batch of parts for the actuator was received from P&N Monday. The parts comprising the actuator plate and resistor assembly were to spec, and were received carefully wrapped and in first class condition.  An Actuator Plate, Diaphragm and Diaphragm Restraint set have been sent to Solar Atmospheres in Souderton, PA for vacuum brazing of a first article. HYSPAN shipped the bellows on Aug 15.
 
HEPI Pump Station
(Mailand)  Four sets of tests completed by the end of week 8-26.  The motor/pump in 'current' single unit mount assembly and motor/pump separately mounted, both the current gear pump and the alternate screw pump style.  Set up is being assembled for the screw pump tests in the week of 8-19, to determine if this type pump is an improvement over the current gear style pump.
Tests at all [5] sensor locations with standard pump/motor adaptor configuration and separated motor pump this setup shows improvement with separation. Lowest flow ripple in psi., also various accumulator pressures, and speed/flow settings tested for a basic data set.  Tested two types of coupling spider materials, buna-n material shows best performance.  Pressure noise spectrum is below the required level.
A new pump mount adaptor has been completed to attach the existing motor to the new screw style pump.  The existing motor pump adaptor will has been modified [opened] to allow air flow thru coupling area, to help dissipate heat.  The motor has been detached from the station base and allowed to contact the floor slab, with brackets, this further isolated the system from motor vibrations.  Need to design and build a bypass resistor for MIT configuration. [need pressure drop requirement]  Electrical isolation adaptors for the pressure sensors are being fabricated which will provide 'o' ring seals to mating parts.
The manifolds [5] with their mounting bases are finished, including hardware and accumulators, with the exception of ms port tapped holes for the pressure sensors.  The standard pump station sensor will be used in the distribution manifolds except now using an 'o' ring seal instead of npt thread. Manifold electrical isolation not required

CDS Software

(Rolf Bork)
 
Continued work to get new digital servo control code ready for installation after S1:
Overall, the code is almost complete, with extensive testing of interconnected systems next week.  Alex, Lori and I will then travel to LHO week of Sept. 9 for installation and testing on LHO4k.
 
CDS Hardware
(Rich Abbott)
Jay is attending a conference on electromagnetic compatibility and interference.
 
PSL
(PeterKing)
 
NPRO #259 is currently being aligned into the system, since M6000 #119 was returned last week for servicing.  #119 started showing signs of decay after 200 hours --- 186 of them were accumulated by Lightwave.  This is the worst case we have seen to date.
There are a number of problems with the second version of my experimental VCO circuit.  The most serious being an oscillation in the AD797 summing stage used to sum the VCO tuning voltage, the output of the modecleaner servo and the frequency modulation test input.  The configuration worked with the previous version, so there might be a problem with the way that I laid the traces out.  The more rigorous input coupling scheme to the 1.1 GHz pre-scaler does not appear to have affected the output.  Another problem is the increase in voltage noise at 10 Hz added to the voltage reference used to set the default tuning voltage.  I have not figured out where the extra noise comes from.
Optics Analysis
(Erika D’Ambrosio, Bill Kells)
 
No report
 
Optical Contamination Cavities
(Lee Cardenas, Liyuan Zhang, Bill Kells)
 
No report

40 Meter Interferometer (Weinstein)



August 23, 2002

Thermal Noise Interferometer (Libbrecht)


No report this week.

LASTI (Zucker)


MEPI / LASTI
(Mason, Ottoway, Mittleman, MacInnis, Megan, Kern)

The installation of the External Pre-Isolators is proceeding very well.  We installed the last 2 of 4 EPI housings this week and the heavy lifting is completed.  The HAM is now supported on the EPI's hard stops, and the assemblies have been shimmed and leveled.  The pneumatic lifts for coarse actuation have been installed and tested.  Myron designed a clever fixture that allowed us (with considerable manhandling) to remove the old piers and install the EPIs in the very cramped area between the vessel and wall. After completing all four installations, we're pleased that the measured displacement in all three axes, at all four corners is < 0.005" and yaw < 50u-rad. Next week we will install the EPI suspension springs and load cells, and begin the task of leveling and aligning the table.  See some images of the installation at
http://emvogil-3.mit.edu/~jkern/MEPI082302/index.htm

HEPI
(Hammond, Kern)

First batch of parts for the actuator was received from P&N Monday. The parts comprising the actuator plate and resistor assembly were to spec, and were received carefully wrapped and in first class condition.  An Actuator Plate, Diaphragm and Diaphragm Restraint set have been sent to Solar Atmospheres in Souderton, PA for vacuum brazing of a first article. HYSPAN shipped the bellows on Aug 15.


Data Analysis and Computing (Lazzarini)


Simulation and Modeling (Bhawal)

Bistable locking in mode-mismatched IFO

(Biplab) The following studies were made to understand degeneracy of the recycling cavity and differences between FFT and Han2k locked states.

Energy conservation in misaligned cavity

(Biplab & Matt) We made some progress in understanding differences in energy conservation error (in E2E runs) between static and dynamic misalignments of mirrors in a cavity. The time-evolution of internal fields turned out to be a crucial factor and must be included in error calculation.

Code development and maintenance

(Ed Maros) Gave Biplab instructions on how to tag and build a release.

Alfi

LIGO Data Analysis System

Software Systems (Blackburn)

The work continued on writing a new frameCPP C++ I/O library for the version 6 frame specification.  The effort necessary to maintain backwards support was probably underestimated but the plan is still to have this ready for integration starting with LDAS early late next week.

Work also continued on adding new functionality to the frameAPI to push the bulk of a user request into a unique thread, all within the C++ layer to allow multiple CPUs to be used by the frameAPI application, while also increasing efficiency by removing some TCL layer management of data objects.

The reusable state vector data objects used by the wrapperAPI search codes was found to be broken this week. A fix is being implemented and a standard system test written up to allow us to completely test this feature in every release.

Three releases of LAL and LALwrapper have been announced this week. These are part of our ramping up for the science run. The LDAS team has found several problems in these releases and provided the LSC authors with the details of the failure modes, facilitating a timely fix and new release.

The latest release of Bwidgets has been integrated into the cmonClient. This fixes several refresh issues but has removed some color from the interface.

The ldasjobs package has been updated to automatically handle a newly discovered (post-release) bug in the managerAPI. The fix will reissue the job when the error is detected. This error is seen with the T1 line to the sites are near full utilization which results in packets piling up at the managerAPI.

Hardware Systems (Mendell for Anderson)

(Greg Mendell)

(Dan Kozak) (Igor Yakushin)
At LSC meeting.
(Keith Bayer) (Al Wilson) Data Analysis Activities (Lazzarini)

(Mendell)

(Shawhan) General Computing (Wallace)

MIT:
(Keith)

Livingston:
(Shannon) Hanford:
(Christine) (Larry) Caltech:
(Mike) (Wendy) (Mick) (Veronica) (Lisa) (Larry)

LIGO II/Advanced R&D (Sanders)


Advanced LIGO Suspensions
(From: Janeen Romie <romie_j@ligo.caltech.edu>)

Superior Jig is having problems producing the larger of the two mode cleaner blades. They started work on these quite late - on the original delivery date to be exact. Gina Salone is supporting me in working with them. They have delivered four small blades. Lobart is due to deliver their blades on Aug. 29th. We will get drawings of the RM blades to Gina as soon as possible to start that procurement.

Mike in CES says that he can most likely meet our Sept 15th delivery date for the second MC structure. We plan to get the second suspension's parts cleaned and baked while we're still working with the first suspension. This should facilitate a mid- October delivery of a clean MC prototype to LASTI.

Currently, I'm working on the magnet gluing fixture for the MC suspension. This fixture can also be used, with a bit of modification, for one of the Gin Gin suspensions.

Advanced LIGO Suspensions
(From: ctorrie <ctorrie@ligo.caltech.edu> )

Prototype Mode Cleaner Suspension

Mike Plissi is visiting us for one month from the University of Glasgow, he can be contacted by email on m.plissi@pgysics.gla.ac.uk or by phone on x ???
Janeen and I have been receiving parts from the various Campus workshops as well as piece parts from outside shops. Mike and I have been going through and sorting all of the parts in the Synchrotron Laboratory and I believe he is happy with most of the parts. A couple of extra parts have had to be machined and one or two are back in machine shop getting re-machined but this was expected and both Ric and Mike in the two main machine shops had set aside some time for this.  Mike and I have started assembly of the wire jigs and some aspects of the upper mass.

SURF

John Veitch and Dan Mason are coming to the end of their surfing time and both hope to have a report written before the weekend.

SOFTWARE

1) After a long struggle I believe we have persuaded SolidWorks to remove the restrictions imposed in their recent service pack They have just released a new service pack 4.1 as follows:

SolidWorks 2001Plus Service Pack 4.1
SolidWorks 2001Plus SP4.0 included a change that prevented commercial or research versions of SolidWorks software from opening files generated using Education or Student versions of SolidWorks software.  SolidWorks 2001Plus SP4.1 removes the restriction that was added in Service Pack 4.0 of opening files created in Educational and Student versions in the commercial or research versions. Please note that this is the only change that went into Service Pack 4.1.  SolidWorks Corporation maintains the position that the Education or Student generated files are for instructional use and not intended to be used with commercial software.

Who should upgrade to Service Pack 4.1
Customers should upgrade to SolidWorks 2001Plus SP4.1 only if they intend to use Educational and Student versions of software in the
commercial or research versions.

I have updated to service pack 4.1 and have had no problems opening educational files.

2) Tony Jones, from Rutherford Laboratory, and I have been exchanging Pro Engineer and SolidWorks files in order to investigate compatibility.  So far I have been able to open .igs files with SOLIDWORKS and as I have FeatureWorks I can recognise the various features like the hole etc., but for some reason it does not allow me to edit the original sketch?  In contrast when I take a AutoCAD file and save it as a .sat file and then open it with SOLIDWORKS I can recognise the features and edit the original sketch.

3) Go Engineer have Marcel's information and have promised to get back to us all this week to fix up the second licence for 3D-TeamWorks. When this happens I will ask Marcel for some help with the PDM Works.

Advanced LIGO Coatings
(From: Helena Armandula <ahelena@ligo.caltech.edu>)

Received the Ta2O5 / Al2O3 coating run from Wave Precision.  Two 3" dia. x 1" thick coated parts plus an uncoated annealed substrate have been shipped to Glasgow.  One of the thin coated substrates was shipped to MIT ; the other to Syracuse University.  1" dia. coated substrates will be shipped to Stanford for absorption measurements.

Sent "Q" substrates to SMA / Lyon to be coated with doped Ta2O5 and SiO2.


For additional information about this report, contact sanders@ligo.caltech.edu