Weekly Report for Week Ending August
22, 2002
The LIGO Executive Committee
Agenda for Monday August 26, 2002 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
1.Announcements
2.LSC Issues (Weiss)
3.Comments on Weekly Report
4.WBS 1 LIGO I Construction (Lindquist)
Field Change Orders/Contingency Liens/Change Requests
5.WBS 2 LIGO Lab Operations
Administration (Lindquist)
Sites (Raab, Coles, Shoemaker, Sanders)
Detector (Whitcomb, Coyne)
Campus Research Facilities (Weinstein (40 Meter), Libbrecht (TNI), Zucker(LASTI))
Data Analysis and Computing (Lazzarini)
6.WBS 3 and 4 Advanced R&D and LIGO II (Sanders)
7.CHANGE CONTROL BOARD/TECHNICAL
REVIEW BOARD SESSION AS NEEDED
As of Wednesday, August
21, no additional information has been received regarding open Change Requests
and requested actions.
Executive Committee only 11:30 - noon Topics:
Special Items:
Special Announcements:
Weekly
Report Highlights
LSC Issues (Weiss)
No report, LSC meeting this week.
LIGO I Construction/LIGO Laboratory
Administration (Lindquist)
LIGO Operations--Administration
LIGO Weekly Site Telecon (Lindquist)
There was no site teleconference held on Thursday,
August 22, 2002.
The list of current actions revised to reflect
the status of open actions assigned through August 15, 2002 may be found
at ACTION
LIST.
PROPERTY
MANAGEMENT (Chargois)
From: Ed Chargois <chargois_e@ligo.caltech.edu>
-
Assisted the Detector Group (H. Armandula) with packing and shipping of
a Substrate, Serial Number 21, to Wave Precision, Moorpark, CA, attention:
Cindy Marschik,. Account Number P157746.
-
Assisted the Detector Group (H. Armandula) with the preparation of US Customs
Documentation, packing, and shipping of four (4) Substrates, serial numbers
18, 23, 24, and 25, to SMA-VIRGO (DR.JM Mackowski), Lyon, France. Account
Number P157746.
-
Disposed of thirty pieces of uneconomically repairable surplus equipment.
All monitors are being disposed of by CALTECH's recycling facility in accordance
with theEPA Directive.
-
Submitted a request to the National Institute of Health (T. Harris) of
Gaitherberg, MD for Office furniture for Livingston and Hanford Observatories;
awaiting confirmation.
DOCUMENT
CONTROL CENTER (Turner, Mak)
>From: Linda Turner
- turner@ligo.caltech.edu>
Web pages for
the DCC give simple how-to's for document numbering, easy access to the
latest on-line documents, and search capabilities for the DCC database.
Take
a look. . .
ACCOMPLISHMENTS
-
LSC. . . LSC. . . and more LSC!
Over 40 presentation have been turned in so far. ALL that were
turned in were posted immediately, both in the database and on the web.
There are still nearly 20+ yet to come in, but most of those have been
promised in the next day or two.
>
From: Cleveland Mak <mak_c@ligo.caltech.edu>
ACTIVITY
-
Focused on processing LSC documents from the LSC Meeting this week at Hanford.
More progress to report on reorganization of DCC files.
DCC Activity
| WE 08/22/02 |
Packages |
Faxes |
| In |
28 |
24 |
| Out |
12 |
24 |
Press here to access
the DOCUMENT CONTROL CENTER
WEB PAGE.
COST SCHEDULE
CONTROL SYSTEMS (Cunningham, Brambila, Kaufman)
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS
PAYABLE HISTORY DATA .
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
-
Prepared the requisition to add funds to the Intelligent Video Systems
to add funds for the additional scope to the work in Hanford. Revised
the draft for the Time and Material contract for Livingston.
-
Oracle is down for the 11i upgrade. Holding requisition and invoice
questions to be resolved.
From: Florence Kaufman <fkaufman@ligo.caltech.edu>
-
Continued trying to straighten out charges from JPL for the contractor
services from Raytheon for the Data Group. Progress is being made
albeit very slowly.
-
Completed first draft of procedures used in preparation of monthly report
for Operations.
-
Prepared a chart of FTE's charged to Operations accounts identified
by major occupational categories - i.e. Scientists, Post Docs & Term,
Tech & Engineering and Administrative.
-
Continued working on template for Operations reports for fiscal year 2003.
-
Financial reports can be found at: http://docuserv.ligo.caltech.edu/~fireport
SUBCONTRACTS MANAGEMENT (Petrac,
Jasnow)
From: irena@ligo.caltech.edu (Irena Petrac)
-
Nothing significant to report.
From: Ed Jasnow <jasnow@ligo.caltech.edu>
CONSTRUCTION:
-
The air conditioning for the auditorium of the Hanford Laboratory Building
was successfully tested, and functioned for the LSC meeting. The
remainder of the construction on the building should be completed shortly.
-
We still have not received an invoice from Brunt Construction for the $110,000
of retention being held on the contract. The HVAC system was scheduled
to be balanced this week to see if that would mitigate the noise and condensation
being experienced.
OPERATIONS:
-
Precautions are being taken at Livingston in light of the West Nile Virus
incidents in Louisiana. Specifically, staff members working outside
for any length of time are wearing mosquito netting suits, as well as insect
repellent.
SUPPORT (Baldon, Torres, Lloyd,
Tischler)
>Irene Baldon
-
Processed the paper work for four (4) new/revised trips and there are eighteen
(18) trips which are in various stages of completion before ticketing can
be done and paper work completed. Continue to worked on a couple
of upcoming relocation trips and worked with Ed Chargois for their household
moving. Also continued to work on a number of long-term visits which
will require long-term housing, etc.
-
Completed seventeen (17) Expense Reports and there are nineteen (19) reports
yet to be done. Contacted a couple of travelers who have long-term
outstanding Expense Reports and asked for their cooperation in sending
me their receipts so that the trip(s) in question can be closed.
-
Reconciled one-hundred-sixteen (116) P-Card items last week which required
numerous phone calls to hotels in order to track down which traveler incurred
which charge and pulling each traveler's file to assure that charges are
correct for each airline fee. Assisted a few travelers with their
questions in regard to their P-Card and/or reconciliation.
-
Attended a class on Travel which explained the new changes being made effective
October 1, 2202. Also obtain a copy of the long awaited Caltech Travel
Policy. There have been changes and they can be found on the WEB
or I have a couple hard copies which you can make a copy of.
-
Worked on the preparation and distribution of the Travel/Vacation Itinerary
for August 21, 2002. Performed normal recording and filing associated
with Travel and Reimbursement.
-
I continue to do MIT's travel to the sites for installation activities
and also to assist them wherever possible.
>Dorothy Lloyd
-
Processed the usual incoming invoices for payment. Tracked and followed
up on invoice problems, and reviewed and recorded payments processed by
Esther for the week of August 12. For the total number of incoming invoices
received for this period see "Cost Schedule Control Systems" report by
Esther Cunningham.
-
Processed the usual requisitions and change orders on-line.
Continue to monitor contract and blanket order encumbrance and notify
task managers when supplements are needed.
-
Jim continues with data entry in the LIGO database.
>Rita Torres
-
Scanned several documents from CaRT, submitted to DCC out, and verified
the LSC roster data with their Attachment Z. Formatted reports from:
CEGG, Carleton College, and GEO and submitted these to the DCC.
-
Completed edits to the nearly 50 names on the list for LSC experimental
groups, submitted to V. Kondrashov who will make available on the web.
-
Formatted report from the LLO safety review in July (struggled with a misbehaving
footer). Made the report (M020316-00-P) available to distribution.
-
Coordinated the last exit eye exams for Surf students.
-
Placed several Pcard orders, and reconciled lots after chasing down the
documentation. Reconciled 63 this period.
-
Returned a wrong part sent by vendor, and arranged for them to send the
correct part.
-
Name change to LIGO roster this period: Christine Patton is now Christine
Barker.
-
Got a chance to file and update logs for: AT&T telecons, safety
exams and training, and LIGO roster changes.
>From: Ryan Tischler <rtischle@ligo.caltech.edu>
-
Assited with LSC preparations at Hanford. Attended SURF talks.
Advanced LIGO (Frey)
From: Thomas Frey <tfrey@ligo.caltech.edu>
Progress Period from 08.09 to 08.22 (Two Weeks)
Accomplishments:
-
Out of the office the 22nd and 23rd of August.
-
Requested opportunity to attend the Primavera User's conference with a
P3e specialty track. October 20 - 23.
-
Weekly Advanced LIGO Project Controls meeting was held 8.16, see below.
-
Advanced LIGO MRE Proposal (Highest Priority)
-
Per direction of Gary, Dennis, David, and Phil, I updated the presentation
from November with most current data.
-
Executed meeting on August 16 at 1pm at SCR.
-
Continuing the development of the Cost Estimate.
-
The following is a summary of status by sub system:
-
COC - Work on action items per second review continues. Garilynn
continues to execute action items.
-
PSL - Completed input of data provided from Peter that facilitated the
separation of LZH scope from LIGO Lab scope.
-
AOS - Work on action items continues. Next meeting date has not been
scheduled.
-
IO - Work on action items continues. Next meeting date has
not been scheduled.
-
SUS - Finished processing update data through 5.31.02. Currently
processing update data through 08.16.02.
-
SEI - Work on action items continues. Next meeting date has not been
scheduled.
-
ISC - Mike continues to work on the WBS dictionary. No comments as
of 8.21.02 on the draft detailed schedule and no WBS dictionary.
Input of the ISC cost sheets completed.
-
LDAS - No data / feedback from Albert to date.
-
All other subsystems have yet to be scheduled for their first review.
These dates are pending per direction from Gary Sanders and Dennis Coyne.
-
Continue to update the TNI Schedule and incorporate any changes.
-
Updated the plan with progress as of 08.16.02 and posted to site.
-
Sent out update data requests for progress as of 08.30.02.
-
Continue to update the LASTI Schedule and incorporate any changes.
-
Updated the plan with progress as of 08.16.02 and posted to site.
-
Sent out update data requests for progress as of 08.30.02.
-
Project Plan for the 40-Meter Lab Upgrade continues.
-
Updated the plan with progress as of 08.16.02 and posted to site.
-
Sent out update data requests for progress as of 08.30.02.
-
Cost Book Tool.
-
ROSTER DATABASE:
-
Rita completed working group coding input as of the 12th.
-
Posted the Roster Database meeting minutes with DCC.
-
Minimal feedback on the Email utility as of 08.21.02.
-
COST BOOK DATABASE:
-
Continue to verbally communicate the username and password to users.
-
Started preparing data requested by David Shoemaker regarding 2003 budgeting.
-
Gang of 5+:
-
DCAA - Work continues on the incurred cost audit.
-
All quiet on the Western Front.
-
Development of the Advanced LIGO Project Controls Guidebook continues.
-
Project Web Site for posting schedule and progress related data continues
to be updated with the latest and greatest.
Schedule 08.23 to 08.29:
-
Out of the office the 23rd of August.
-
Next weekly Advanced LIGO Project Controls meeting has not been scheduled.
-
Advanced LIGO MRE Proposal (Highest Priority Task)
-
Highest priority is the development of the Cost Estimate.
-
Will continue to pursue all other sub system schedules.
-
PSL - Will finish input of coding for cost items with information provided.
-
AOS - Continue inputting changes to and prepare for next meeting TBD.
-
IO - Continue inputting changes to and prepare for next meeting TBD.
-
SUS - Continue inputting changes to and prepare for next meeting TBD.
-
Will complete update the plan with progress through 8.16.
-
Add cost data changes received.
-
SEI - Waiting for information from SEI group per their action items.
-
COC - Work on action items by Garilynn continues. Will begin schedule
changes when data received.
-
ISC - Will complete input of cost data and incorporate any changes and
comments.
-
LDAS - Will work with Albert to develop details.
-
Will issue updated meeting minutes for every subsystem as action items
from most recent review are completed.
-
Will Continue to update the TNI Schedule and incorporate any changes.
-
Will update the plan with progress as of 08.30.02 and post to site
by the 5th.
-
Will Continue to update the LASTI Schedule and incorporate any changes.
-
Will update the plan with progress as of 08.30.02 and post to site
by the 5th.
-
Will continue updating the 40 meter schedule and incorporate any changes.
-
Will update the plan with progress as of 08.30.02 and post to site
by the 5th.
-
Roster Database
-
Will continue to work with BK and executing action items.
-
Cost Book Tool development continues. (Highest Priority Task)
-
Mapping and formatting of OPS cost data for input will now continue with
co-operative agreement approved.
-
Will continue to work with BK executing action items.
-
Finish preparing data requested by David Shoemaker regarding 2003 budgeting.
-
Gang of 5+
-
Will continue to work on procurement guidelines.
-
Will continue to provide support to PL for DCAA / NSF IG audit(s).
-
Will continue the development of the Advanced LIGO Project Web Site.
-
Will continue the development of the Advanced LIGO Project Controls Guide
Book.
Reports (Lindquist)
-
Still working on the annual report/work plan for
LIGO Operations FY 2003..
Change Control/Contingency (Lindquist)
The following change requests have been submitted:
Open or Recent Change Requests
CR-010012
Revision B |
WBS 1.4.4.1 |
Closeout Construction Budgets for Initial Computer Equipment Complement
at the Sites |
P. Lindquist |
| CR-020009 |
OPs |
Digital Common Mode Servo to Mode Cleaner Path |
D. Coyne |
| CR-020011 |
OPs |
High Power Test in Suspended Interferometer (Gingin) |
D. Coyne |
| CR-020012 |
OPs |
Additional Funds to Complete 40-Meter Facility Upgrade |
A. Weinstein |
Human
Resources (Akutagawa)
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
-
Various personnel/payroll /HR related work.
Quality/Safety (Tyler)
>From: Bill Tyler <tyler@ligo.caltech.edu>
No report this week.
LIGO Hanford Observatory (LHO) and
Interferometer Operations (Raab)
No report this week.
LIGO Livingston Observatory (LLO) and
Interferometer Operations (Coles)
HEPI: This week's main goals have been to fit the HEPI
actuator up into the boot that was made for the MEPI design. Final efforts
have been made towards the mate of the hydraulic actuator to the boot.
Concerns of L4C sensor location still concern me, as well as Jonathan Kern.
Hopefully, this will be resolved by tomorrow. I spoke with Ken Mason late
last night and we discussed several possible solutions for the placement
of the L4C sensor. Once I finish the mounting of the aforementioned, I
can once more proceed with the plumbing all of the actuators together (on
each BSC assembly). During some of my free time I have been assembling
the HAMS and BSC's with the changes made by EPI into one large assembly
(of the entire LIGO) with the intention that other groups, i.e. suspension,
optics, et al will be able to benefit from the digital model. This is an
ongoing effort and is done mostly on weekends, so when I finish it, I will
advertise this so that it can be utilized. The pre-isolator machined springs
have been the Electroless Nickel Plating of Louisiana (ENP) and have been
promised for tomorrow (Friday the 23rd). I delivered a shipping box designed
especially for the springs and they have conformed that the springs will
be ready midday. The fabrication for the HEPI units continues. The Actuator
plates have been delivered and we are picking up vendor concerns as redlines
into the drawings so that the drawing package stays up to date. The bellows
have still not arrived on site yet but are expecting them any day. (Marcel
Hammond)
First batch of parts for the actuator was received from P&N Monday.
The parts comprising the actuator plate and resistor assembly were to spec,
and were received carefully wrapped and in first class condition. An Actuator
Plate, Diaphragm and Diaphragm Restraint set have been sent to Solar Atmospheres
in Souderton, PA for vacuum brazing of a first article. HYSPAN shipped
the bellows on Aug 15. (Jonathan Kern)
GC: Attended the Usenix conference in San Francisco and
made some valuable contacts. I learned of a software product for configuring
PIX firewalls (among others) that looked very useful. I will be arranging
a web demo with them to further evaluate the product. I think this will
be very useful for the project. LDAS: Set up a vpn tunnel between LLO and
CIT last week. I will be doing some further testing once Stuart and I can
coordinate some tests. (ShannonRoddy)
Preparation for S1: We have been able to easily lock the
interferometer in a low noise state and maintain it in that state for hours
during the night. During the day, the seismic noise continues to worsen.
Logging activity is approaching the vertex area, creating some of the highest
BLRMS 1-3 Hz readings we've seen on a continuous basis - around 100 counts
and rising daily. Logging activity is about one half mile distant at present
but will approach the property line around the LVEA over the next 2-3 weeks.
We have been preparing the general area within the LVEA and VEAs to remove
sources of electronic noise and mechanical vibration that can be turned
off or removed during the run, such as lights in the VEAs, dust monitors,
annulus turbo pumps, etc. Signs and chains directing and controlling traffic
flow around the site will set up Friday morning. The auto-locker script
which acquires interferometer lock, turns on the common mode, increases
the optical power, and recovers if lock is broken, has been tested repeatedly
this week and seems to work very well.
LSU Chancellor Mark Emmert will visit LLO on September 5. Louisiana
Secretary of Economic Development Don Hutchison will make a presentation
to the Southern Governors Conference this Saturday that will include mention
of LIGO as a contributor to the technical resources of the southeastern
Louisiana region.
Detector/Technical Support (Coyne)
DETECTOR
SCIENCE & ENGINEERING
Seismic Upgrade Project
EPI modeling
Brian Lantz discussed and shared a version of the
basic Matlab code for dynamics and control simulation with Dave Ottaway,
Rich Mittleman and Dennis Coyne. This version includes a more general formulation
for handling the sensors. Dennis is making progress on a more realistic
dynamics model of the HAM support structure to be used in conjunction with
the existing stack model. Rich and Dave are progressing in adaptation of
Brian’s BSC/HEPI code to the HAM/MEPI application.
MEPI / LASTI
(Mason, Ottoway, Mittleman, MacInnis, Megan, Kern)
The installation of the External Pre-Isolators is proceeding very well.
We installed the last 2 of 4 EPI housings this week and the heavy lifting
is completed. The HAM is now supported on the EPI's hard stops, and
the assemblies have been shimmed and leveled. The pneumatic lifts
for coarse actuation have been installed and tested. Myron designed
a clever fixture that allowed us (with considerable manhandling) to remove
the old piers and install the EPIs in the very cramped area between the
vessel and wall. After completing all four installations, we're pleased
that the measured displacement in all three axes, at all four corners is
< 0.005" and yaw <50u-rad. Next week we will install the EPI suspension
springs and load cells, and begin the task of leveling and aligning the
table. See some images of the installation at
here
HEPI Actuator
(Hammond, Kern) First batch of parts for the
actuator was received from P&N Monday. The parts comprising the actuator
plate and resistor assembly were to spec, and were received carefully wrapped
and in first class condition. An Actuator Plate, Diaphragm and Diaphragm
Restraint set have been sent to Solar Atmospheres in Souderton, PA for
vacuum brazing of a first article. HYSPAN shipped the bellows on Aug 15.
HEPI Pump Station
(Mailand) Four sets of tests completed by
the end of week 8-26. The motor/pump in 'current' single unit mount
assembly and motor/pump separately mounted, both the current gear pump
and the alternate screw pump style. Set up is being assembled for
the screw pump tests in the week of 8-19, to determine if this type pump
is an improvement over the current gear style pump.
Tests at all [5] sensor locations with standard
pump/motor adaptor configuration and separated motor pump this setup shows
improvement with separation. Lowest flow ripple in psi., also various accumulator
pressures, and speed/flow settings tested for a basic data set. Tested
two types of coupling spider materials, buna-n material shows best performance.
Pressure noise spectrum is below the required level.
A new pump mount adaptor has been completed to attach
the existing motor to the new screw style pump. The existing motor
pump adaptor will has been modified [opened] to allow air flow thru coupling
area, to help dissipate heat. The motor has been detached from the
station base and allowed to contact the floor slab, with brackets, this
further isolated the system from motor vibrations. Need to design
and build a bypass resistor for MIT configuration. [need pressure drop
requirement] Electrical isolation adaptors for the pressure sensors
are being fabricated which will provide 'o' ring seals to mating parts.
The manifolds [5] with their mounting bases are
finished, including hardware and accumulators, with the exception of ms
port tapped holes for the pressure sensors. The standard pump station
sensor will be used in the distribution manifolds except now using an 'o'
ring seal instead of npt thread. Manifold electrical isolation not required
CDS Software
(Rolf Bork)
Continued work to get new digital servo control
code ready for installation after S1:
-
At Sigg's request, filters can now be up to 10 second order sections and
there is an added feature that all coeffs for an optic/LSC/ASC are loaded
thru a single EPICS button.
-
End station code updated to handle 16KHZ GDS signals.
Overall, the code is almost complete, with extensive
testing of interconnected systems next week. Alex, Lori and I will
then travel to LHO week of Sept. 9 for installation and testing on LHO4k.
CDS Hardware
(Rich Abbott)
-
Finished the schematics for the motor speed servo and pressure readout
for the HEPI pump station. In the process of laying out the board
for manufacture.
-
Flavio has almost finished the schematic of the Altera timing solution.
We will be laying out the board next week.
-
Tested the first article of the 8 channel valve driver board for the HEPI
actuator. The board functions well with no deviations from the design.
We tested the board into a 100 foot cable and the actual valve to be used
at LIGO.
Jay is attending a conference on electromagnetic
compatibility and interference.
PSL
(PeterKing)
NPRO #259 is currently being aligned into the system,
since M6000 #119 was returned last week for servicing. #119 started
showing signs of decay after 200 hours --- 186 of them were accumulated
by Lightwave. This is the worst case we have seen to date.
There are a number of problems with the second version
of my experimental VCO circuit. The most serious being an oscillation
in the AD797 summing stage used to sum the VCO tuning voltage, the output
of the modecleaner servo and the frequency modulation test input.
The configuration worked with the previous version, so there might be a
problem with the way that I laid the traces out. The more rigorous
input coupling scheme to the 1.1 GHz pre-scaler does not appear to have
affected the output. Another problem is the increase in voltage noise
at 10 Hz added to the voltage reference used to set the default tuning
voltage. I have not figured out where the extra noise comes from.
Optics Analysis
(Erika D’Ambrosio, Bill Kells)
No report
Optical Contamination Cavities
(Lee Cardenas, Liyuan Zhang, Bill Kells)
No report
40 Meter Interferometer (Weinstein)
August 23, 2002
-
Alan, Dennis, and Osamu are at the LSC meeting. Steve is on vacation.
-
The 40m Technical Advisory Committee met on Wednesday morning for an hour.
Dennis presented the status report, with emphasis on our mode cleaner.
There was some discussion of Marcus' results on AdvLIGO wavefront sensing.
-
SURF students Ilya, Marcus, David, and Aya gave stellar talks at Tuesday's
SURF seminar day. It's the last week for all but Dave.
-
Optical sensing (Smith):
-
AP2, OMC_R, SPS, BS PO, ITM PO ISC Optical Trains: The spot size
matching lenses in the AP2, OMC_R, BS PO, and ITM PO ISC table optical
trains were determined, and components were moved to establish the appropriate
beam spot sizes throughout the optical train. The generalized equations
for calculating the Guoy phases on all the PO paths were set up. The actual
values and positions of the Guoy telescope lenses for the OMC_R, SPS, BS
PO, and ITM PO will be determined after the Guoy phases have been established
The integrated layout drawing was updated to reflect the changes.
-
IO Diagnostics: A technical note is being written to describe the
design and calibration procedure for the IO position sensing and angle
sensing optical systems.
-
Optics Parts List: Purchase orders were placed for most of the opto-mechanical
parts for the AP1, AP2, ITM PO, BS PO, ETM PO, and SPS ISC beams
and sensing table optical trains. Parts were received from Thorlabs and
Watec. Missing lenses for the IO diagnostics optical train were received.
-
CDS (from Ben):
-
I have been helping Illya and Dave with some technical aspects of their
SURF projects.
-
Bob and I have run coaxial video cable and power for the cameras to the
auxillary rack.
-
I ordered connectors that will allow me to test and install the WFS whitening
interface boards.
-
I tried to find the 500KHz noise on the PSL light that Peter Fritchel talked
about notching out of the ISS DC photodiode. As it stands, I cannot find
it at the 40m. I will try with the laser in Lauritzen, to see if it is
there.
-
(From Bob):
-
Wiring and OSEMs have the big players this week, I have completed and tested
10 long OSEM boards and 3 short boards. The short OSEM board seem to be
more of a problem. I think I just had a few bad diodes that have been giving
me problems but I have reworked those boards and am now ready to test them
today.
-
Ben and I have put in six of the camera / power cables and more will likely
go in today.
-
I have built the rheostat panel and am still waiting on the relays from
Phoenix Contact.
-
I have the temperature controller for oven "F" designed and in the machine
shop.
-
The baseline scan on oven "C" has been done and I am waiting for Steve
to give me instructions on the seismic stack cables.
-
Oh yes, one of the M200 Daycor RGAs is giving me problems and I have attempted
to repair it but I think I will have to send it back for repair. This RGA
was repaired in 1999 and was sent in by Yehuda and at that time it seem
to have the same scanning problem. I will get a quote on fixing it from
Ametek.
Thermal Noise Interferometer (Libbrecht)
No report this week.
LASTI (Zucker)
MEPI / LASTI
(Mason, Ottoway, Mittleman, MacInnis, Megan, Kern)
The installation of the External Pre-Isolators is proceeding very well.
We installed the last 2 of 4 EPI housings this week and the heavy lifting
is completed. The HAM is now supported on the EPI's hard stops, and
the assemblies have been shimmed and leveled. The pneumatic lifts
for coarse actuation have been installed and tested. Myron designed
a clever fixture that allowed us (with considerable manhandling) to remove
the old piers and install the EPIs in the very cramped area between the
vessel and wall. After completing all four installations, we're pleased
that the measured displacement in all three axes, at all four corners is
< 0.005" and yaw < 50u-rad. Next week we will install the EPI suspension
springs and load cells, and begin the task of leveling and aligning the
table. See some images of the installation at
http://emvogil-3.mit.edu/~jkern/MEPI082302/index.htm
HEPI
(Hammond, Kern)
First batch of parts for the actuator was received from P&N Monday.
The parts comprising the actuator plate and resistor assembly were to spec,
and were received carefully wrapped and in first class condition.
An Actuator Plate, Diaphragm and Diaphragm Restraint set have been sent
to Solar Atmospheres in Souderton, PA for vacuum brazing of a first article.
HYSPAN shipped the bellows on Aug 15.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
Bistable locking in mode-mismatched IFO
(Biplab) The following studies were made to understand degeneracy of
the recycling cavity and differences between FFT and Han2k locked states.
-
Keeping arm cavity mirrors fixed at positions specified by locked lengths
from FFT runs, the recycling mirror was moved at slow speed (only l+ changes)
-
Repeated the same procedure but this time fixed the arm cavity mirrors
at positions specified by locked states of Han2k model which are found
to be different from FFT-locked positions. It was observed that the
Sideband resonance curves generated by these time-sweep procedures have
two humps in it which originate from mismatches in cavities (also seen
by Bill Kells in FFT studies). While FFT-locked state sits at around the
crest in between these two peaks, the Han2k lock acquisition system, being
more realistic, tries to approach one of these peaks. This also explains
why we were getting a sudden transition in locked positions in Han2k model
at a heated state characterised by refractive index of about 1.25 (in a
scale of 1.45 at cold to 0.9 at final hot state). Han2k locked position
shifts from one peak to another at near this state.
Energy conservation in misaligned cavity
(Biplab & Matt) We made some progress in understanding differences
in energy conservation error (in E2E runs) between static and dynamic misalignments
of mirrors in a cavity. The time-evolution of internal fields turned out
to be a crucial factor and must be included in error calculation.
Code development and maintenance
(Ed Maros) Gave Biplab instructions on how to tag and build a release.
Alfi
-
(Bruce) Refitting the parser with better error messaging and graceful
handling of problems involving bad formatting in an Alfi file.
-
(Melody) Continuing work on the automated tester for alfi5.
LIGO Data Analysis System
Software Systems (Blackburn)
The work continued on writing a new frameCPP C++ I/O library for the
version 6 frame specification. The effort necessary to maintain backwards
support was probably underestimated but the plan is still to have this
ready for integration starting with LDAS early late next week.
Work also continued on adding new functionality to the frameAPI to push
the bulk of a user request into a unique thread, all within the C++ layer
to allow multiple CPUs to be used by the frameAPI application, while also
increasing efficiency by removing some TCL layer management of data objects.
The reusable state vector data objects used by the wrapperAPI search
codes was found to be broken this week. A fix is being implemented and
a standard system test written up to allow us to completely test this feature
in every release.
Three releases of LAL and LALwrapper have been announced this week.
These are part of our ramping up for the science run. The LDAS team has
found several problems in these releases and provided the LSC authors with
the details of the failure modes, facilitating a timely fix and new release.
The latest release of Bwidgets has been integrated into the cmonClient.
This fixes several refresh issues but has removed some color from the interface.
The ldasjobs package has been updated to automatically handle a newly
discovered (post-release) bug in the managerAPI. The fix will reissue the
job when the error is detected. This error is seen with the T1 line to
the sites are near full utilization which results in packets piling up
at the managerAPI.
Hardware Systems (Mendell for Anderson)
(Greg Mendell)
-
Set up a new RAID server with 2 TBs of disk space. This is almost
complete, though some problems with network connections may be occuring,
and some configuration is still needed.
-
Prepared drawings for the move of the LHO LDAS equipment in the staging
building to the new building. The plan is to move at the end of September
or early October, after S1 data has been backed up into HPSS and distributed.
-
Prepared to archive S1 data onto tape, and injections and calibration data
from Wednesday and Thursday of this week.
-
Trouble-shot two crashes of the network switch. The switch is working
now; Foundry has agreed to send a backup for the chassis.
(Dan Kozak)
-
HPSS: continued migration of small files off of 3590 tapes.
-
Successfully tested SAM-QFS configuration for sites/CIT. This involved
writing data to a SAM-QFS instance which dual copied the data to tape,
then exporting one of the sets of tapes (and associated metadata) and importing
it into another SAM-QFS instance. I'm continuing to fine tune this
process, but it is working quite well so far.
(Igor Yakushin)
At LSC meeting.
(Keith Bayer)
-
experimented with sw raid on PC Raid Box (datawulf)
(Al Wilson)
-
Released RH7.3 to the rsync server
-
Fixed mail problems with stand alone ldas systems.
Data Analysis Activities (Lazzarini)
(Mendell)
-
Attended that August 2002 LSC meeting; worked with the PULG group on our
analysis; chaired the PULG individual session.
(Shawhan)
-
Helped Anand Sengupta (Dhurandhar visiting student) to read LIGO data into
his prototype search code running within the standalone wrapper. This code
implements a time-decimated hierarchical and mass templated search for
iinspiraling binaries.
General Computing (Wallace)
MIT:
(Keith)
-
Finishing off the MU7 update
-
All solaris machines now running patched versions of openssl / openssh
-
Troubleshooting wireless difficulty with new IBM laptop
-
Dedicating lancelot to DMT / LDAS work (off of gc network)
-
Purchased PC + software for CAD work (Jamie)
-
Finally purchased PC for D-space work (Peter/Richard)
Livingston:
(Shannon)
-
Attended the Usenix conference in San Francisco and made some valuable
contacts. I learned of a software product for configuring PIX firewalls
(among others) that looked very useful. I will be arranging a web
demo with them to further evaluate the product. I think this will
be very useful for the project.
Hanford:
(Christine)
-
It's been a very busy time getting the network into the new building and
getting it to work in time for the LSC meeting. By late Sunday night
the wireless network in the auditorium worked and most of the ethernet
jacks at each of the auditorium seats worked.
-
For the LSC meeting I setup five breakout rooms with computers, projectors
and overhead projectors and setup a computer and printer for admin in the
reception area of the new building.
-
Larry worked on the VRVS video conferencing computer and was able to get
periods of transmission with fairly good video and audio.
-
Helped many people with network and file transfer problems during the LSC
meeting.
-
Monday night esnet took our network down to upgrade the operating system
on their cisco router in hope of eliminating the errors we've had on our
original bandwidth upgrade. The IOS upgrade made no difference.
-
Meanwhile during the network down time it was decided to remove a switch
from between our cisco router and our ATM 3810 hub. It was late at
night after a long stressful day and no one noticed that by removing the
switch the DHCP server which was plugged into the switch now had no network.
The lack of a DHCP network was very noticeable on Tuesday morning.
Adding to the chaos, workers pulling fiber for LDAS into the GC server
room knocked the keyboard cables which went to the file server and e-mail
server out of the KVM switch, which caused the servers to freeze. Due to
"too many cooks in the kitchen" more damage was done, files were deleted
that didn't need to be deleted and then had to be recreated later and it
took three times longer to repair the problem than it should have taken.
-
PNNL and esnet have found that their cisco hardware is not able to provide
the 10 megabits upgrade we had wanted. PNNL was able to put a switch
between the esnet cisco router and the ligo connection which has brought
us back to T1 bandwidth and has eliminated the errors on the cisco routers.
The next step is to explore what hardware upgrades need to be made to improve
the bandwidth.
-
Created five new user accounts and changed the passwords on two others
for people who had forgotten their passwords.
-
Helped some remote users with account and disk problems on the DMT computers.
Shared the license server Matlab files with the DMT machines for software
development.
-
Worked on hardware problems on Otto's computer and finally setup a temporary
computer for him until I can get his computer fixed.
(Larry)
-
Helped with with a number of things for the LSC setup. Mostly, cabling
and cleanup. Also, helped a number of attendees with their computer setups.
Assisted Linda Turner with her setup and helped her get things going to
get the presentation files transferred to Caltech. Also, wound up donating
my laptop for presentation usage. Richard, Christine, Dave, Otto, Terry
and any others really got things together for the LSC meeting.
-
Met with Albert and John McCoy (from PNNL) concerning the network upgrade.
John is working setting up a meeting with the ESnet and a few others to
start discussing the hardware options needed for the upgrade. Albert will
be contacting ESnet concerning related issues.
-
Continued testing the network connections and passed the information to
Cullen who has really been doing a good job working out the performance
issues. Since, Cullen has resolved a few issues today the network is now
running well above T1 speeds.
-
Spent a deal of time with the VRVS system. The Hanford machine would lock
up on a regular basis. No reason discovered. Also, tested the direct audio
feed from the microphone system, so far it is not working very well, more
testing and debugging needs to be done. For some reason the audio would
have transmission breaks on a regular basis. We did have good audio and
video for short periods of time. We will be working on resolving the issues
to get better performance on the VRVS system and looking into some alternatives.
Caltech:
(Mike)
-
We were having a few database problems on Anteres but as of now everything
seem's to be running okay. I have transferred this server back into the
server room.
-
Loaded a 2000 server to replace Amaldi that is currently running on NTSRV4.0.
I have more testing and to do before I swap out
-
servers. This is currently hosting the ELBA website.
-
Wendy and I have upgraded multiple PC's that were running win98 and now
have them upgraded to 2000 Professional. This has been going pretty good
with minimal problems. I have not heard any complaints from users other
than a few software adjustments.
-
Performed a-lot of user support that included software, virus, hardware
and printing problems. It looks like we got a handle on things as
of this morning.
(Wendy)
-
Loaded and ghosted more machines with win2k, including one that we loaded
from the Ghost image.
-
Worked on tape restoration a bit.
(Mick)
-
Rewired 3rd floor network closet with Lisa and Christian
-
Helped move some equipment in subbasement
(Veronica)
-
LSC website: as the transparencies from the LSC meeting keep coming, I
am posting them. Posted a few last-minute updates to the meeting
webpage. Updated MOUs webpage.
-
LIGO website: posted several updates to the Internal Bulletin Board.
Tracked down a problem in the DCC document search; the problem was related
to an incorrect drive mapping between internal and public components of
the DCC, and is now fixed. Together with Lisa and Mike, looked into an
unrelated problem with a document not being linked to its pdf file.
Attended a presentation on Adobe digital video editing tool collection.
Posted the new webpage 'Commonly Used Email Archives.' Posted
July newsletter. Started working on webpages for the Aspen'03
Winter conference. Per Lisa's request generated a few banner graphics.
Tracked down a cause for a log file error for LIGO homepage. Working
on the updates for the 'Experimental GW Groups' webpage.
(Lisa)
-
Worked on some web server issues.
-
Spent most of the week working implementation of a new archiver for the
mailman mailing lists. It is mime aware and includes a search engine. The
new archiver is ready to be put into production as soon as I can get off-hours
down time on the system.
-
Recabled the 3d floor Bridge network closet with the help of Mick and Christian.
(Larry)
-
Went through a number of procurement issues.
-
Worked through a few application installations. Went over the mailman upgrade
with Lisa. It is looking pretty good.
LIGO II/Advanced R&D (Sanders)
Advanced LIGO Suspensions
(From: Janeen Romie <romie_j@ligo.caltech.edu>)
Superior Jig is having problems producing the larger of the two mode
cleaner blades. They started work on these quite late - on the original
delivery date to be exact. Gina Salone is supporting me in working with
them. They have delivered four small blades. Lobart is due to deliver their
blades on Aug. 29th. We will get drawings of the RM blades to Gina as soon
as possible to start that procurement.
Mike in CES says that he can most likely meet our Sept 15th delivery
date for the second MC structure. We plan to get the second suspension's
parts cleaned and baked while we're still working with the first suspension.
This should facilitate a mid- October delivery of a clean MC prototype
to LASTI.
Currently, I'm working on the magnet gluing fixture for the MC suspension.
This fixture can also be used, with a bit of modification, for one of the
Gin Gin suspensions.
Advanced LIGO Suspensions
(From: ctorrie <ctorrie@ligo.caltech.edu> )
Prototype Mode Cleaner Suspension
Mike Plissi is visiting us for one month from the University of Glasgow,
he can be contacted by email on m.plissi@pgysics.gla.ac.uk or by phone
on x ???
Janeen and I have been receiving parts from the various Campus workshops
as well as piece parts from outside shops. Mike and I have been going through
and sorting all of the parts in the Synchrotron Laboratory and I believe
he is happy with most of the parts. A couple of extra parts have had to
be machined and one or two are back in machine shop getting re-machined
but this was expected and both Ric and Mike in the two main machine shops
had set aside some time for this. Mike and I have started assembly
of the wire jigs and some aspects of the upper mass.
SURF
John Veitch and Dan Mason are coming to the end of their surfing time
and both hope to have a report written before the weekend.
SOFTWARE
1) After a long struggle I believe we have persuaded SolidWorks to remove
the restrictions imposed in their recent service pack They have just released
a new service pack 4.1 as follows:
SolidWorks 2001Plus Service Pack 4.1
SolidWorks 2001Plus SP4.0 included a change that prevented commercial
or research versions of SolidWorks software from opening files generated
using Education or Student versions of SolidWorks software. SolidWorks
2001Plus SP4.1 removes the restriction that was added in Service Pack 4.0
of opening files created in Educational and Student versions in the commercial
or research versions. Please note that this is the only change that went
into Service Pack 4.1. SolidWorks Corporation maintains the position
that the Education or Student generated files are for instructional use
and not intended to be used with commercial software.
Who should upgrade to Service Pack 4.1
Customers should upgrade to SolidWorks 2001Plus SP4.1 only if they
intend to use Educational and Student versions of software in the
commercial or research versions.
I have updated to service pack 4.1 and have had no problems opening
educational files.
2) Tony Jones, from Rutherford Laboratory, and I have been exchanging
Pro Engineer and SolidWorks files in order to investigate compatibility.
So far I have been able to open .igs files with SOLIDWORKS and as I have
FeatureWorks I can recognise the various features like the hole etc., but
for some reason it does not allow me to edit the original sketch?
In contrast when I take a AutoCAD file and save it as a .sat file and then
open it with SOLIDWORKS I can recognise the features and edit the original
sketch.
3) Go Engineer have Marcel's information and have promised to get back
to us all this week to fix up the second licence for 3D-TeamWorks. When
this happens I will ask Marcel for some help with the PDM Works.
Advanced LIGO Coatings
(From: Helena Armandula <ahelena@ligo.caltech.edu>)
Received the Ta2O5 / Al2O3 coating run from Wave Precision. Two
3" dia. x 1" thick coated parts plus an uncoated annealed substrate have
been shipped to Glasgow. One of the thin coated substrates was shipped
to MIT ; the other to Syracuse University. 1" dia. coated substrates
will be shipped to Stanford for absorption measurements.
Sent "Q" substrates to SMA / Lyon to be coated with doped Ta2O5 and
SiO2.
For additional information about this report, contact sanders@ligo.caltech.edu