Weekly Report for Week Ending May
16, 2002
The LIGO Executive Committee
Agenda for Monday May 20, 2002 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
-
Announcements
-
LSC Issues (Weiss)
-
Comments on Weekly Report
-
WBS 1 LIGO I Construction (Lindquist)
-
Field Change Orders/Contingency Liens/Change Requests
-
WBS 2 LIGO Lab Operations
-
Administration (Lindquist)
-
Sites (Raab, Coles, Shoemaker, Sanders)
-
Detector (Whitcomb, Coyne)
-
Campus Research Facilities (Weinstein (40 Meter), Libbrecht (TNI), Zucker(LASTI))
-
Data Analysis and Computing (Lazzarini)
-
WBS 3 and 4 Advanced R&D and LIGO II
(Sanders)
Executive Committee only 11:30 - noon
Topics:
Special Items:
Special Announcements:
Weekly
Report Highlights
LSC Issues (Weiss)
no report
LIGO I Construction/LIGO Laboratory
Administration (Lindquist)
LIGO Weekly Site Telecon (Lindquist)
There was a site teleconference held on Thursday, May 16, 2002.
The following items were discussed:
Action Item #104: Determine Weber Bar Display Locations.
Closed. At Hanford the bar itself will be displayed inside the new
building while the enclosure will be outside.
Action Item #106: Prepare punch list for building at Livingston.
We are currently several punch lists beyond that referenced by this action
assignment. For status, see below. This action is closed.
Action Item #109: Provide estimates for furnishing new buildings
for contingency list. This action is closed. Estimates provided
by Otto and Gerry. Ed Chargois is looking for excess property furniture.
Action Item #110: Provide pointer to Operating and Control Room
Procedures on the Web Site. These procedures are actually a part
of the Visitor's Site. The site has been checked and includes the
appropriate material. This action is closed.
Action Item #111: Review Visitor's Program Proposal for constraints
regarding High School Teachers. Response provided. There appear
to be no constraints. Still governed by PMA rules. This action
is closed.
Construction Livingston: Work on punch list items continues.
Gerry has forwarded eight page copy of new punch list to Ed Jasnow and
the contractor is working some of the issues. Biggest item is floor,
which has not been started. HVAC contractor being pressured (pun
intended) to address problems.
Construction Hanford: There will be a claim (arguably without
foundation) regarding stainless steel radius wall siding. The siding
was fabricated approximately 20 inches too short. In any case will result
in six week delay. The audio/visual equipment is due to be delivered
next week.
Inventory: Inventory at Hanford went well.
The list of current actions revised to reflect
the status of open actions assigned through May 16, 2001 may be found at
ACTION
LIST.
PROPERTY
MANAGEMENT (Chargois)
From: Ed Chargois <chargois_e@ligo.caltech.edu>
-
Assisted the Detector Group (D. Coyne ) with shipping of two crates containing
Spring Testers weighting 2000 and 3000 lbs via Air Cargo International
and Domestic Freight to HYTEC INC. Los Alamos NM. Attention Eric
Ponslet. Schedule arrival time 20-23 May 02. Account Number LIGO.FAS 1
NSFLIGO.FY02CA.
-
Assisted the Project Office (G. Sanders) with packing and shipping of a
mini Interferometer via Federal Express to Columbia University New York,
NY Attn, Dr A.Kehl, received confirmation of receipt. Account Number P204198.
-
Provided copies of photographs of the Weber Bar to LHO Site Manager (O.
Mathatney), Federal Express additional copy to LLO Site Manager (G. Stapfer),
and a copy was provided to the DCC.
DOCUMENT
CONTROL CENTER (Turner, Mak)
>From: Linda Turner
- turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy
access to the latest on-line documents, and search capabilities for the
DCC database.
Take
a look. . .
ACCOMPLISHMENTS
>
From: Cleveland Mak <mak_c@ligo.caltech.edu>
ACTIVITY
-
Electronic document activity picked up quite a bit for this period.
-
Continued working on contractual close-out files.
-
Progress continues on conversion of old charge account files to electronic
form.
|
05/16/02
|
Packages
|
Faxes
|
|
In
|
32
|
26
|
|
Out
|
12
|
26
|
COST SCHEDULE
CONTROL SYSTEMS (Cunningham, Brambila, Kaufman)
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS
PAYABLE HISTORY DATA .

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
-
Completed the new contract to JaniKare, and change order 1 to Moon Security.
-
Working on change order #2 to Coastal Bridge, change order #7 to High Precision,
and an internal mod to Excel Group.
-
Working with Norman Gordon to resolve the tax issue on Superior Jig.
With the concurrence of Norman Gordon faxed over amendment 8 to the Cooperative
Agreement showing Caltech is purchasing equipment on behalf of the U.S.
Government.
From: Florence Kaufman <fkaufman@ligo.caltech.edu>
SUBCONTRACTS MANAGEMENT (Petrac,
Jasnow)
From: irena@ligo.caltech.edu (Irena Petrac)
-
EGO: CO No. 1, extending the AdLIGO optics coating R&D collaboration
(through Dec. 31, 2002), was released to Purchasing.
-
SIOM: CO No. 5, extending the AdLIGO sapphire R&D collaboration (through
Dec. 31, 2002), was released to Purchasing
From: Ed Jasnow <jasnow@ligo.caltech.edu>
CONSTRUCTION:
-
The contractor continues to work off a nine-page punch list as the final
step in completing the LLO Staging Building.
-
The siding contractor for the LHO OSB East Building intends to file a claim
to recover costs of purchasing new stainless steel siding because of
cutting the original siding twenty inches too short. He scaled the drawings,
even though there are instructions not to do that. Ed Jasnow and
Otto Matherny will review the claim when it is submitted.
OPERATIONS:
-
The sites continue to prepare for the beginning of the first science run
at the end of June.
SUPPORT (Baldon, Torres, Lloyd,
Tischler)
>Irene Baldon
-
PLEASE NOTE: I was out all of last week (May 6 thru May 10) due to a medial
emergency. This report is for only 3 days -- May 13 thru May 15.
-
Processed the paper work for fourteen (14) new/revised trip and there are
eight (8) trips in various stages of completion before ticketing can be
done and paper work completed.
-
Completed three (3) Expense Reports and there are twenty-one (21) reports
yet to be done.
-
Reconciled forty-one (41) P-Card items this week which requires phone calls
to hotels to track down which traveler incurred which charge and pulling
each traveler's file to assure that charges are correct for each airline
fee.
-
Of the original thirty-eight (38) SURF students traveling either to Caltech,
Hanford or Livingston, travel for thirty-seven (37) students are completed
and I have one (1) student still being worked out.
-
Prior to my medical leave I work with Ed Jasnow on revising the LIGO Travel
Policy Manual which is being redone for reissuing soon.
-
Worked on the preparation and distribution of the Travel/Vacation Itinerary
for May 14, 2002.
-
Performed normal recording and filing associated with Travel and Reimbursement.
-
Also performed miscellaneous duties as requested by various members of
the LIGO Project here at Caltech as well as from members of the staffs
of each of the two (2) sites.
-
I continue to do MIT's travel to the sites for installation activities
and also to assist them wherever possible.
>Dorothy Lloyd
-
Approximately 45 invoices were processed for payment this reporting period
by Esther and I.
-
Tracked and followed up on some invoice problems, and reviewed and recorded
payments processed by Esther the week of May 6. For the total number of
incoming invoices received for this period see "Cost Schedule Control Systems"
report by Esther Cunningham.
-
Processed the usual requisitions and change orders.
-
Continue to monitor contract and blanket order encumbrance and notify task
managers when supplements are needed.
-
Jim continues with data entry in the LIGO database and helping out in the
DCC.
>Rita Torres
-
Formatted the incoming progress report from U. of Oregon, submitted the
report to the DCC.
-
Continue to track progress of orders placed for M. Smith while he's away.
-
Submitting the incoming partial orders to S. Vass.
-
Placed several Pcard orders, and reconciled several more after chasing
after the documentation. Followed up on a couple of delayed orders. If
items were in stock as indicated, then these should have arrived in a couple
of days, not a couple of weeks.
-
Updated telecon info for the Core Optics group. Stored away the toner and
supplies ordered for the Sys Admin group.
-
Changes to LIGO roster this week: Rana Adhikari appears under LLO, and
also under MIT. Katrina Carter was added under LLO, Anthony Rizzi and Kerry
Stiff were removed from LLO.
-
INFORMATION : US postal rates change on June 30, 2002. Visit -- http://www.usps.com/ratecase
>From: Ryan Tischler <rtischle@ligo.caltech.edu>
-
No report this week due to illness.
Advanced LIGO (Frey)
From: Thomas Frey <tfrey@ligo.caltech.edu>
Progress Period from 05.10 to 05.16
Accomplishments:
-
Weekly Advanced LIGO Project Controls meeting was held on 5.14. Focus
of the meeting was the continued development of the MRE request.
-
Continued to work with Primavera regarding an outstanding technical issue
and received a program patch that I am now using and testing.
-
Advanced LIGO MRE Proposal (Highest Priority)
-
Continuing the development of the Cost Estimate.
-
Issued meeting recap from meeting of 5.14 to all estimators.
-
The following is a summary of status by sub system:
-
COC - Work on action items per second review continues. Next meeting
date has not been scheduled.
-
PSL - Next meeting date has not been scheduled.
-
AOS - Work on action items continues. Next meeting date has not been
scheduled. Updated meeting minutes and issued for information.
-
IO - Work on action items continues. Next meeting date has
not been scheduled. Updated meeting minutes and issued for information.
-
SUS - Working with SUS group to incorporate current comments.
-
SEI - Work on action items continues. Next meeting date has not been
scheduled. Updated meeting minutes and issued for information.
-
ISC - Corresponding with Mike Zucker to meet at MIT to make significant
progress towards developing an estimate..
-
LDAS - Initiated start of estimate with Albert.
-
All other subsystems have yet to be scheduled for their first review.
These dates are pending per direction from Gary Sanders and Dennis Coyne.
-
Continue to update the TNI Schedule and incorporate any changes.
-
Data pending to revise plan to version 3 due to additional efforts to isolate
noise.
-
Nothing new to report.
-
Continue to update the LASTI Schedule and incorporate any changes.
-
Project Plan for the 40-Meter Lab Upgrade continues.
-
Set up primavera post office on Alan's new computer at his office.
-
Cost Book Tool.
-
ROSTER DATABASE:
-
Continue work on my action items providing BK with needed data.
-
Attended meeting with "Gof5" on 5.16.
-
COST BOOK DATABASE:
-
Attended meeting regarding project accounting and item classification.
-
DCAA - Work continues on the incurred cost audit.
-
Nothing new to report (All Quiet on the Western Front).
-
Development of the Advanced LIGO Project Controls Guidebook continues.
-
Project Web Site for posting schedule and progress related data continues
to be updated with the latest and greatest.
Schedule 05.17 to 05.23:
-
Next weekly Advanced LIGO Project Controls meeting is to be scheduled for
early June. Subject: MRE Cost and Proposal Development.
-
Advanced LIGO MRE Proposal (Highest Priority Task)
-
Highest priority is the development of the Cost Estimate.
-
Will continue to pursue all other sub system schedules.
-
PSL - Will complete estimate and schedule changes.
-
AOS - Continue inputting changes to and prepare for next meeting TBD.
-
IO - Continue inputting changes to and prepare for next meeting TBD.
-
SUS - Continue inputting changes to and prepare for next meeting TBD.
-
Will update the plan when data is made available.
-
SEI - Continue inputting changes and prepare for next meeting TBD.
-
COC - Work on action items by Garilynn continues. Anticipate schedule
changes prior to next meeting TBD.
-
ISC - Will plan travel to MIT and meet with Mike Zucker to develop details.
-
LDAS - Will work with Albert to develop details.
-
Will issue updated meeting minutes for every subsystem as action items
from most recent review are completed.
-
Will Continue to update the TNI Schedule and incorporate any changes.
-
Will update the plan with progress as of 05.17.02 and post to site
by the 20th.
-
Will Continue to update the LASTI Schedule and incorporate any changes.
-
Will update the plan with progress as of 05.17.02 and post to site
by the 20th.
-
Will continue updating the 40 meter schedule and incorporate any changes.
-
Will update the plan with progress as of 05.17.02 and post to site
by the 20th.
-
Roster Database
-
Will continue to work with BK and executing action items.
Cost Book Tool development continues. (Highest Priority Task)
-
Mapping and formatting of OPS cost data for input will now continue with
co-operative agreement approved.
-
Will continue to work with BK executing action items.
-
Will continue to provide support to PL for DCAA audit(s).
-
Will continue the development of the Advanced LIGO Project Web Site.
-
Will continue the development of the Advanced LIGO Project Controls Guide
Book.
Reports (Lindquist)
Over the next few months we must prepare and submit the following proposals,
work plans, and reports:
-
June 2002 - Quarterly Report for Construction (end of May)
-
August 1, 2002 - Annual Work Plan for FY 2003 Operations
-
September 2002 - Quarterly Report for Construction (end of August)
-
September 2002 - Final Report Advanced R&D Grant
-
December 2002 - MRE Proposal
August 1 we are scheduled to submit an annual work plan to the NSF for
LIGO FY 2003 Operations. This week I prepared and distributed a first
draft budget for FY 2003 based on the proposal budget developed last summer
with some modifications to reflect current staffing plans and change requests.
We are reviewing the staffing plan to assure consistency with current staff.
We will initiate the preparation of written material for this (FastLane)
submittal. I conceive of something relatively short, like the current
quarterly report, but emphasizing Operations. Sections will be required
for Hanford, Livingston, Caltech (Science Runs, milestones, Data Analysis,
40-Meter Upgrade), MIT, Seismic Prototype, LSC, and Cost vs. FY 2002 Budget
Status. We will also require a proposal for FY 2003 from MIT.
Change Control/Contingency (Lindquist)
The following change request has been submitted:
CR-010012
Revision B |
WBS 1.4.4.1 |
Closeout Construction Budgets for Initial Computer Equipment Complement
at the Sites |
P. Lindquist |
Human
Resources (Akutagawa)
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
Various personnel/payroll /HR related work.
Quality/Safety (Tyler)
>From: Bill Tyler <tyler@ligo.caltech.edu>
No report this week.
LIGO Hanford Observatory (LHO) Operations
(Raab)
Summary of Commissioning Activities at LIGO
Hanford Observatory--May 9, 2002 Report
(see elog for details - if it's not in the elog, it didn't happen...)
Better locking behavior was obtained on both interferometers in the
last week. Rolf, Alex I. and Ashfaq K. are working with David and Richard
to install new hardware and software on 4K. Matt, Rana and Stan are up
working on commissioning.
4k IFO investigations
One-arm investigations continued to understand frequency noise on the
light and saturation effects in the control signals. Notches were added
to the 4k mode cleaner (MC) to reduce RMS frequency noise associated with
bounce resonances. Peter F. sent us new 4kMC filters to eliminate 30-Hz
edge seen in earlier measurements, when MC mirror damping was increased.
Rick, Stan and Gerardo implemented the filters and measured significantly
improved frequency noise with new filters and higher damping from 20-200
Hz. It was also found that the changes made last week to increase the high-frequency
drive to the ETMs did not succeed due to limiting elsewhere in the controller.
Additional modifications to PA85 drive limiters allowed nearly a doubling
of drive and afforded better (symmetrical) saturation properties than were
the case earlier. Notably the drive increase still fell short of expectations,
so this still needs to be understood. Heat sinks were also installed on
PA85s and fans turned off to reduce near-60 Hz noise. Improved locking
behavior was observed on the 4K IFO with generally longer hold times and
one stretch of 4-hour lock. This allowed 4k loop gain measurements. Some
tuning based on these measurements was successful in reducing the PRC/CARM
coupling by approximately 10x. Then the DAC controller died, just
in time for the arrival of CDS reinforcements. Along the way, a bad laser
was identified on the ITMx optical lever. The improved frequency noise
still looks somewhat marginal, since estimates of the RMS residual frequency
noise in full IFO operation is still comparable to the passband of the
double cavity. Line harmonics on the 4k PSL appear to be a large contributor
and these are being tracked down as the CDS installation and troubleshooting
work continues. The CDS task (new Pentek hardware and the software fixes
for S1) is now the main priority on this machine.
2k IFO investigations
It was noticed that the mode cleaner reflected
beam pitched and yawed excessively. Looking at archived spectra of MC_F
it was found that the 1-Hz component had increased by about an order of
magnitude since last fall and winter. Butler tracked this down to a change
of damping gains in January and fixed the 1-Hz problem by retuning damping
parameters. It was also noticed that re-zeroing of the mode-cleaner servo
control offset when the common-mode script was run typically threw the
IFO out of lock. Mike Landry altered the MC autolocking script to zero
this offset every time the mode cleaner re-acquires lock and this eliminated
this problem.
Mike Landry was looking at free-swinging 2k IFO fringes and Stan's sharp
eye picked out odd-looking sideband fringes, indicating that 2-omega sidebands
might be too close to antiresonance in the arms, which could be expected
to cause trouble. The RF frequency had been re-tuned a few weeks ago to
match better the mode-cleaner passband and it was feared this may have
precipitated our locking problems on the 2k IFO. RF was tuned part-way
off (300 Hz out of 29.5 MHz) causing a dramatic change in the sideband
fringes as they returned to a more normal appearance. Unfortunately, this
did not help the locking behavior.
Mark Guenther and Landry searched the e-log and con-log to document
all changes between when we last had good locking behavior and the more
recent weeks of poor behavior. They identified not a sharp step, but an
inexorable slide into bad behavior. In the midst of this slide we had increasing
problems with "ratty-looking" SPOB signals, reflecting the sideband power
resonating in the PRM. The large and sudden SPOB fluctuations cause large
fluctuations in the input matrix optimization used by the lock-acquisition
code during "acquire" mode and may cause bad coefficients to be "locked-in"
to "detect" mode. This could cause problems in acquisition, hold time in
"acquire" mode and variable results from lock to lock in "detect" mode
unless a known good set of matrix coefficients is reloaded consistently.
Stan and Fred investigated the SPOB signals and decided to test whether
the rattiness might be a saturation phenomenon. Not wishing to beat about
the bush and taking advantage of a good signal to noise ratio, the light
intensity on the SPOB photodiode was reduced dramatically by 10x. This
appears to have cured the rattiness problem. At some later time we may
want to optimize the attenuation, but this should do well for the near
future.
Another impediment to stable locking has been the occasional large and
frequent bursting in in the MICH loop. Occasionally the bursting has been
severe enough to throw the IFO out of lock and, even when smaller, the
bursts contaminate data runs with frequent glitches. Episodes of good and
bad burst behavior were often demarcated by incredibly slight (mV) touch-ups
of alignment, but lately the problem has become more dramatic and stubborn
to reduce. Rana analyzed the 2k MICH loop and found that its phase margin
was quite poor near the unity gain point. Theorizing that fluctuating gain
due to angular fluctuations could destabilize the loop and cause bursting,
he reconfigured the loop gain profile to improve phase near the unity gain
frequency. This dramatically improved the bursting behavior and MICH_CTRL
looks about the best it has ever looked. There is still significant bursting
in the PRC_CTRL in detect mode, but this should be improved by running
with common-mode servo engaged.
Matt Evans and Rana have been attempting to reconfigure gains so that
we can better suppress the total RMS fluctuations with the servoes and
buy enough head room to increase the light levels on the antisymmetric
port (AS) photodiode. (Our best sensitivity above 500 Hz with good stability
has been dark-noise limited.) So far, they have not succeeded to get a
good transfer to stable operation in common-mode configuration at higher
dark-port power. Single-arm 2k frequency noise measurements made at 8x
higher power on the AS photodiode confirm that frequency noise on the light
is limited by radiation pressure fluctuations that shake the mode cleaner
mirrors from 40-200 Hz. The frequency noise at 100 Hz is approximately
10x spec due to 200 ppb/rHz fluctuations in laser intensity. Nonetheless,
this leaves room for significant improvements or identification of other
noise sources in this frequency regime. Work will continue on this effort.
FACILITIES
The Laboratory Building (new building) has 20% of the siding completed.
The contractor is working on the internal stud framing, electrical and
plumbing. We anticipate to do the paving next week which means that there
will be considerable seismic noise.
Summary of Commissioning Activities at LIGO
Hanford Observatory May 16, 2002 Report
(see elog for details - if it's not in the elog, it didn't happen...)
Work focused on recovery from software upgrades on 4k, and work on 4k
PSL and input optics. Repair of a "glitchy" coil driver seems to have cured
stability problems on the 2K. Construction work has shifted to extreme
noise generation this week as asphalting is being done. Expect this will
terminate on Monday, May 20.
4k IFO investigations
The CDS crew left us with new hardware and software installed on the
4K. It may take a bit of time to get the 4k back on its feet after this
fix. We have lost connectivity to past settings and signal routing is a
bit different, but it looks like we can make it work. A big push is underway
to verify optic-by-optic that the settings are correct and the functionality
is there. At this time we do not have the ability to inject signals from
AWG into some excitation points to verify transfer functions, but we have
been getting damping into spec, getting mappings right from optical lever
quadrants into pitch/yaw, etc. We have even seen some 1-arm locks.
As we recover functionality of the core optics, work has continued to
improve the frequency noise on light delivered by the input optics. Bill
Kells has been working to level the mode cleaner, so that some of the electronic
notch filtering of MC bounce modes can be removed. This would simplify
the configuration to allow more flexibility in moving down crossovers in
the frequency control system. Another major contributor to RMS frequency
noise has been line harmonics on the PSL output light. Rick has been leading
an effort on grounding of equipment to mitigate this and it appears that
this noise contribution will be drastically reduced. Rana tested the "Super
Optical Levers" on the 4k end mirrors, which worked extremely well. We
will be implementing these as we get the 4k IFO back on its feet. Rana
also installed a digital comb filter that can deal with residual line harmonic
noise.
2k IFO investigations
A new calibrated noise curve was made of the 2k, which pretty much
agrees with data from Jan 24. Mike Landry is close to releasing software
for automating the process of taking calibrated displacement spectra. After
the removal of the main source of MICH bursting last week, we have uncovered
a further problem with "glitching" on the AS_Q channel, that Daniel tracked
down to a single coil driver on one of the ETMs. Eventually it was found
that a resistor had failed. Once the coil driver was repaired, the 2k appeared
to be dramatically cured. It locked up easily in common mode and held for
about 9 hrs. Daniel has been using the improved filtering capability of
the 2K LSC to insert resonant gain stages and reshape loops to greatly
quiet a number of the control loops. All of these changes have dramatically
improved machine behavior. The IFO output last night was audibly very quiet
and the traces were largely free of what had previously been frequent bursting.
There were still some audible bursts every few seconds, which appeared
to correlate with the larger, mostly common-mode, vertical motions of the
spots on the end mirrors. This is believed to be due to limitations in
the ability to diagonalize the length drive to the ETMs. The dynamic balancing
of the ETM drive (a.k.a. frequency-dependent diagonalization) that will
come with digital suspensions, or the super optical lever damping that
will come with digital suspensions, or a common-mode WFS with high gain
at pendulum frequencies could all help alleviate this problem. Paul Schwinberg's
work on implementing the remaining WFS should now benefit greatly from
finally attaining a more stable locking regime. Matt Evans has left behind
code that automates the initial alignment process using the DC readout
of the WFS-1 photodiode.
Hugh is continuing to make progress understanding the common mode tidal
actuator.
FACILITIES
The siding for the Lab Building is 50% complete. The paving preparation
is complete, paving will be complete on the 17th. The contractor is working
on
electrical and mechanical rough in. The interior framing is 90% complete
and the contractor started on the dry wall in the building.
LIGO Livingston Observatory (LLO) Operations
(Coles)
From: Gerry Stapfer
Commissioning
No Report
External Pre-Isolation
(Jonathan) Much of the past week I've spent working with Larry Jones
and Hugh Radkins devising a procedure that will facilitate the installation
of fine actuators on our ITMs. Had several telecons with the Stanford
group discussing fabrication issues of the new welded actuator. Began a
much closer collaboration with Marcel Hammond and Ken Mason in order to
tie loose ends up and move toward completing the drawing details and getting
work into the shop. Met with a few local fabricators to discuss the practicability
of various assembly schemes.
(Marcel) Efforts to fabricate a "first article" pre-isolator springs
are complete. Fabrication began 5/15, est. complete-5/22
Work continues for post-fab i.e. procuring vendors for heat treat, surface
coating, joining etc
Work on stiffness calculations continues. i.e. forming the stiffness
matrix. The matrix is formed. I am in a model refining mode
I am integrating the pre-isolator springs into the Ken mason's pre-isolator
model
Laser Safety
(Jonathan) So far, so good. We appear to have uncovered all of the obvious
bugs, and the only alarms we've received all week were caused by people
inadvertently opening an exit door before swiping their cards. This is
an easy mistake to happen, but people are developing the habit and it's
occurring much less frequently.
GC
(Shannon) Finished building a workstation for a software package that
will help with the computer management here. installed VNC on a couple
more computers. Updated the access rules on the firewall. Looking
into some classes on the PIX offered by Cisco. Loaded some more CDs
into the "online" software storage. Installed P-card software on
a couple of new machines.
CDS
(Chethan) Working on clearing out some disk space on LLO1 to have sufficient
disk space for S1. Wrote a script to clear all core files. Investigating
file transfer speed between CDS and the PC machine in control room. Preparing
to setup Sun Blade 1000's for DMT. Setup ip addresses for these machines
in host table on LLO1.
LDAS
(Igor) Attended Bursts group meeting at MIT. Attended LDAS bootcamp
at UWM.
SCIENCE
& ENGINEERING SUPPORT (Coyne)
Seismic Upgrade Project
Dennis Coyne reporting
External Pre-Isolation
-
The group decided on an approach (designed by Ken Mason) for the coarse
alignment capability, which will be added to the ITM chambers. It consists
of a set of pneumatically lifted roller plates at the base of the integrated
sensor/actuator assembly and X-Y driven translation stages from the initial
SEI coarse actuation system. Ken Mason will detail out the changes
to accommodate the coarse actuation design and get them to the prototype
venders. All of the machining is underway for the spring/actuator assembly.
-
Ken is building configuration drawings for the different options (hydraulic
actuator, electro-magnetic actuator, HAM, BSC, etc.)
-
Ken and Myron have devised a method of installation at LASTI using a 3
ton, low friction, ball screw actuator which is electric motor driven.
This ball screw actuator will be used to lift the crossbeam above a pier
slightly to allow the current hardware to be removed and the new assembly
to be installed.
-
Larry Jones has drafted a procedure for the installation of the fine actuation
system (FAS) on the LLO ITM chambers for the Piezo-electric External Pre-Isolator
(PEP) system. The load on the pier will be relieved by use of the overhead
crane and a load cell. Then the scissors table will be lowered to permit
removal of the current spacer block.
-
Marcel has performed finite element analysis on the machined spring design.
Stresses appear to be within acceptable limits (though further analysis
with reduction due to chamfering is needed). Finite element analysis indicates
that a lightened version has a first frequency at 100 Hz, when the boundary
condition is assumed to be clamped. More analysis with realistic rotational
compliance from the adjustment mechanism is pending. Some further lightening
of the spring is possible and may be necessary to have a minimum frequency
of ~100 Hz. (For reference the upper unity gain frequency of the system
might be ~25Hz in order to enable some suppression of the 12 Hz vertical
bounce mode – if possible. Hence the need for a spring resonance of >~
100 Hz.). The spring stiffness matrix will be defined, from further FEA,
by next week for use in the servo analysis.
-
A first prototype of the machined spring will be made. Heat treatment for
the maraging steel has been defined. A test plan is pending.
Electronics status (Rich Abbott, Mohana
Mageswaran):
-
About 75% done on the schematics for the pump station servo. Pump station
enclosure into silk screening. Rack mount unit designed; schematics in
review. Pump servo controller consists of 2 microprocessors with a 4 line
LCD display on the front on the unit. There are currently no communications
from this (stand-alone) controller to the outside world. (This may change
once requirements for such communication are defined.) However, there is
a single composite alarm bit (which is programmable) and can be run anywhere
by using a set of closures.
-
Pump station pressure stabilization servo topology: drives pump speed and
by-pass valve; sense low frequency pressure fluctuations at the load; sense
high frequency pressure fluctuations at the valve; cross over in a blended
actuator; analog servo for the high frequency, digital servo for the low
frequency; cross-over re-programmable with coefficients entered into the
controller.
-
Design for the L4C geophone and Kaman inductive position sensor field interface
electronics boxes have been completed. Boards due back this week. Electronic
components are in-house. Enclosures due soon.
-
Decided to interface to the L4C geophones (which are integral to the actuator)
with a custom designed, low profile, circuit board which converts from
the Bendix connector on the L4C to a standard board mounted connector (e.g.
DB9) The circuit board will have pins to mate to the L4C connector. The
Stanford group will design the circuit board and its strain relief.
BSC Stack Transfer function measurements
at LASTI (Rich Mittleman): Measured X-to-X, Y-to-Y, Z-to-Z. Also looked
at angular transfer functions as well as off-diagonal terms (e.g. X-to-Y).
Signal to noise ratio is good even on the off-diagonal terms. Work continues.
Comparison to analysis pending.
Hydraulic External Pre-Isolation (HEPI)
-
Tests by Jamie at Stanford on the passive RC integral manifold block have
indicated a pressure fluctuation attenuation of 5, whereas analysis predicts
an attenuation of ~10. Results are being studied. Will also revise pump
station pressure fluctuation limits to be clear about requirements at the
load and at the pump station.
-
Pump Station (Ken Mailand)
-
CONSTRUCTION: Basic station Finished.
-
MOTOR SPEED CONTROL: Wired and tested 'ready to run'.
-
PRESSURE LEAK TEST 'air 80/100 psi' Solder joints by CIT plumbing shop.
Solder leaks remain in 3 places, 3 fixed, one reworked and still leaking
will try to seal all solder joint leaks by 5-16-02.
-
DESIGN: A future modification to the reservoir filler cap for a float level
sensor.
-
LAYOUT DRAWING: I have finished a scale plan view and partial elevation
[acad 2D] layout drawing, of station component assembly.
-
HARDWARE ASSEMBLY: Resistors are finished and installed.
-
LONG TUBE RUN: Finished.
-
TEST LOAD: Finished.
-
The nozzle design for the hydraulic servo valve has been completed and
a drawing exists (though not yet into LIGO template & DCC). Parker
no-bid the nozzle but gave Jonathan the names of several companies that
produce nozzles for Parker’s products. Parker is willing to assemble and
possibly calibrate and adjust our servo-valves for us. Brian Lantz and
Jamie will define the adjustment and calibration procedure. Jonathan will
pursue quotes for the nozzles and assembled servo-valves.
-
The distribution manifolds at the load (chamber end) are yet to be designed.
-
Hydraulic actuator (Jonathan, Corwin, Brian): Working on issues of accessibility
and repairability for the proposed welded design (vs bolted). Issues are
related to the fluid manifold which is integral to the actuator structure
and the integral bellows, bellows shield and limit stop. Resolution expected
this week.
-
Modeling (Brian): “real world” model with 6 dof and compliance of the real
structural plant is in process. Ken Mason will do an FEA on the stiffness
of the V-block weldment (spring/actuator assembly structure) to determine
the actuator support compliance.
Electro-Magnetic External Pre-Isolator (MEPI)
-
Greg Harry measured the temperature rise of the coil to be 11C for 3A drive
current. With suitable heat sinking and free convection, this is reduced
to 1C. This seems adequate.
-
Started to measure the EM coupling from the coil to the L4C geophone.
CDS Software
Rolf Bork reporting
-
Alex, Khan and I completed installation of new Digital Suspension software
at LHO. Still remaining is addition of new timing modules for LVEA large
optics (Khan).
-
Alex is preparing the digital suspension software for the 40m lab. The
software and VME system for the small optics will be installed Thursday
or Friday. We will still need to modify the AWG and TP manager to
use the 5579 (PCI) reflected memory network instead of the VME based reflected
memory used at the sites for DAQ.
-
I'm at LLO remainder of this week and thru the weekend. The latest LSC
code and new timing modules are being installed/tested.
-
Lori has modified the ICS110B ADC module initialization software to reduce
the sigma delta pipeline delay from ~38 samples to 10 samples. This
sofware will be incorporated into systems using the 110B after some further
testing, specifically noise characterization.
CDS Hardware
Jay Heefner
Differential Driver/Receiver:
-
Two of each of the 4 board types have been stuffed and are being tested.
A design ommission that set the gain of the DAC to AI path to 1/2 has been
corrected. The correction will be incorporated to the design prior to shipment
to the sites. The A-A to ADC path boards will be tested next.
Optical Lever Whitening:
-
A schematic for the upgraded board has been circulated for comments. It
should be complete and ready for layout next week.
-
A new differential driver/receiver chip has been found and tested. It is
the THS4150. Preliminary tests show that it may work very well in applications
where we need differential in and/or out. The noise is ~20nV/rtHz at 100Hz
and the common mode rejection should be better than 60dB. The measured
CMRR is ~54 db but the number is not final. If this part works out, it
will be incorporated into the design for the board. This will make all
off board connection completely differential.
Rich Abbott, Falvio Nocera, Ben Abbott
Testing is underway of the new ISS at the 40m lab.
Preliminary results indicate that the auto-zero function is behaving well
and a first look at the residual noise outside the loop shows that the
servo is performing according to the design. The variable gain amplifiers
seem to function well. Much more to follow before Friday when we
ship the first unit to LLO for installation next week.
Sander Liu
LEMO
Anti-alias Filter chassis - Working on three new units for the 40M
Micro-Seismic
Signal Processor-
Remote Interface Box: Testing of the first article is complete. It works
well. We will proceed to design the metal chassis so that the rest of the
units can be built.
-
Post Processor: In the process of testing the first article.
PSL
PeterKing
The optically
contacted pre-modecleaner fabricated in the PSL Lab is completed.
Only two small defects in the optical contact were noted and recorded (see
image).They are sufficiently small
enough that they should not affect the performance.
NPRO
#393, returned from Lightwave after a warranty repair, was tested.
The output power remained stable during an overnight test.In
addition the relative intensity noise seemed to have improved.
Optics Analysis
Erika D’Ambrosio
I took a lot
of data regarding the thermal lensing effect, taking into account only
the phenomenological change in the refractive index. The simulations were
aimed to see the level of power increase when from the "cold" configuration
the interferometer attain the "hot" values that are the ones the radii
of curvature have been designed to match. I used both the FFT-code and
Melody and looked at both the sidebands and the carrier. The sidebands
start from a power gain that is ~25% of the "maximum hot value" according
to the FFT-code and ~50% according to Melody. There is no discrepancy between
the carrier results obtained by the two codes and both show the carrier
is almost not affected as theoretically predicted.
I also plotted
the adjustments of the lengths performed by the two programs and I observed
similarities and differences. Both show that the length of the arms does
not need to be readjusted and shorten the length of the recycling cavity.
However the decrease of the recycling cavity length is much larger for
Melody. For the FFT-code that "retuning" is only "quadratic" in the distortion
while it is "linear" for Melody.
Optical Metrology
GariLynn Billingsley
A discrepancy
between CSIRO and CIT Radius of curvature results has been resolved.There
was a nearly constant offset of ~ 6nm when measuring the Sag of the PRMs
for the 40M.This turned out to be
the result of a re-calibration of the CSIRO WYKO frame grabber card.Measurements
are back to the traditional ~< 2nm level of agreement.
Optical Contamination Cavities
Lee Cardenas, Liyuan Zhang
OTF Lab.
Contamination
Cavity #2 Continue taking measurements for ring down and beat frequency.
Contamination
cavity # 1It breaks lock easily
due to the electronics (oscillator and RF supplier malfunction)
We looking
into fixing the electronics.
40 Meter Interferometer (Weinstein)
Suspension Controllers (B. Abbott, Heefner, Taylor, Ugolini)
-
From Jay: Digital suspension controller Front End and epics software for
the mode cleaner mirrors is complete and will be installed in the 40M starting
today. It should be fully operational by next week.
-
From Ben: I am working to have all the front panel cabling ready for the
mode cleaner front end installation this week.
-
Bob has put in the shelves needed for the CDS timing crate installation
in the DAQ rack (1Y9), and for the frequency sources in the IOO controls
rack (1Y2).
-
Bob should be finished with wiring the cross-connect for the IOO controls
rack (1Y2) by the end of the week.
DAQ (Rolf, Ivanov): Alex Ivanov is installing a new DAQ system,
featuring support for a second reflective memory loop (for all front end
fast controls: suspension controllers and global LSC and ASC), and a new
database /cvs/cds/caltech/chans/master.config to log the new suspension
controller channels. New frame builder (for 16-sec frames) to come later.
PSL: Rich Abbott, Flavio Nocera, and Ben Abbott have been testing
the PSL intensity stabilization servo (ISS), and integrating the DCPD with
the servo. Testing was hampered by the discovery of a 7kHz oscillation
on the light intensity, which has been isolated to the frequency stability
servo. Therefore, the FSS has been disabled in order to test the ISS. Preliminary
results look good... a 20 dB reduction in intensity noise at ~ 1kHz. We
will investigate the FSS oscillation next week.
Optical Layout (Smith, Ugolini, Miyakawa, Vass)
-
The components in the IOO diagnostics path have been laid out. Some pieces
are still missing, (a polarizing cube, half-wave plate before the periscope,
and intensity stabilization servo), but we can work without them.
-
The optical spectrum analyzer (Tropel) used in the IOO diagnostics is apparently
broken, and has been sent back for repair.
-
It just dawned on us that we don't have a pockels cell for the MC transmitted
sidebands, just the one for the MC reflected sidebands. That means that
we cannot easily measure the MC length during commissioning. This will
be ordered ASAP.
-
Osamu has laid out the components in the IMCT path (on the PSL table),
and continues to inventory the components in the IMCR path (on the SP&MC
table). That table has been cleared off so that the parts can be laid out.
STACIS seismic isolation system (Ugolini):
-
After an exhaustive set of tests, including transfer function measurements,
it was determined that there really is something wrong, and not easily
fixable, with the SV-NW isolator z-axis control (which goes haywire when
an RS232 cable is plugged into the controller module). That isolator, and
the known-bad EE-NW isolator (z-axis control) have been removed, crated,
and shipped back to the manufacturer (TMC) for repair.
-
Dennis continues the laborious debugging of the STACIS readout software.
To isolate where the problem is, he changes the code; each change must
be in place for ~ 5 days to see if it will fail.
Optics (Billingsley, Armandula): Received polished ETMs and ITMs
from CSIRO. Helena inspected them for surface quality and all of them meet
specs.; currently she is checking them for surface figure. They will then
be prepared for shipment to REO for polishing.
Computing:
-
The op140m sun operator's console was moved from the IFO hall (where it
was blocking access to racks and was in the path of a soon-to-be-installed
beam tube) to the control room. A loaner laptop is now in use as an EPICS
display near the PSL.
-
Three new laptops, for use as convenient EPICS display heads, have been
received from Dell and are being built by Mike Pedraza. He and Lisa Bogue
are setting up a secure wireless access point on our martian network (40MARS),
for these,
-
Lisa Bogue is working on installing disk and tape backups for the critical
disk on our martian network.
-
Many more VME cpus are being installed as part of the digital suspensions
and fast controls. An evolving list of 40m computers is in
40m
computers.
Facilities and vacuum envelope (Vass, Jones):
-
Bob baked the repair kit for the leaky V1 vacuum valve, and Steve used
it to repair the valve. A pumpdown of the manifold indicates that if it
leaks at all, it is 20x smaller than it was before the repair. No evidence
for the cause of the leak was found, but tiny metal particles are present,
origin unknown. He declares victory, and now will proceed with the swapping
of the two turbopumps TP2 and TP3 with new ones that have dry scroll forepumps.
-
Larry Jones reports that beam tubes to the AP table, the PSL, and the SP
table are still in process at CES, and we can expect them no sooner than
next week. The enclosure for the SP table is expected no sooner than 2
weeks. Fixed parts for the AP table enclosure is expected no sooner than
next week. Video camera housings are expected no sooner than next week.
-
Caltech HVAC has confirmed that the AC is inadequate in our new control
room (where SURF students will sit), and barely adequate in the main North
Annex room (where Dennis, Steve, and Osamu sit). They estimate a cost of
$75K to fix this!!! No chance to get this work done before the summer.
Caltech has to deal with this...
-
A box of 3 kittens was removed from the 40m storage cage, and given to
someone who will knows how to deal with such matters. The mother remains
at large.
E2E modeling (Miyakawa): Osamu continues to learn E2E, is running
alfi5, and is studying the Han2K model and the DRLIGO model.
South Annex Bake Ovens (Taylor, Cardenas):
-
All ovens are idle, and on standby.
-
We are holding off on baking the Dynamic Light Controls mirror mounts until
Mike Smith returns.
-
Bob will install new SRS ionization and pirani gauges onto the main volumes
of the two large bake chambers (E and F), which can be baked up to 250C.
-
Bob plans to redo the exhaust lines in the South Annex to handle all the
chambers that need them.
Thermal Noise Interferometer (Libbrecht)
In our last report we had achieved rapid lock acquisition in both arm
cavities at any time of the day or night. We observed that the noise
in both arm cavities is about the same, and it is slightly higher than
the noise floor observed in the South Cavity in December of last year.
We have spent our time since the last report measuring various noise
sources, including electronic noise and laser frequency noise. In the North
Cavity, we find that electronic noise at its present levels will prevent
us from reaching the same sensitivity level achieved in the South Cavity
in December. Because of its higher optical gain, we do not expect this
limitation to apply to the South Cavity.
One thing we discovered while hunting down the source of our excess
electronic noise was that our gain-boost stage was no longer operating
according to spec. If no boost stages were active, or if only one stage
was switched in, the unit worked as designed. When both boost stages were
engaged, however, the output developed a large dc offset, nearly railing.
We adjusted an internal trimpot to remove this dc offset, and the unit
is now performing well with any number of boost stages active.
LASTI (Zucker)
LASTI (MacInnis, Mageswaran, Mason, Mittleman, Ottaway, Rollins, Shoemaker,
Zucker)
VACUUM ENVELOPE:
We resurrected the electron multiplier on our Balzers RGA and can now
in principle detect much lower partial pressures of hydrocarbons or other
high-mass contaminants (as little as one part in 107 of the
base pressure, which is predominantly water vapor at 1-2 x 10-6
torr or so). At this increased sensitivity, we're finally able to
see some putative HC peaks. However, they behave as if they could be generated
on the RGA ionizer itself, which is well known to generate CO and CO2
on its own. We thus may only have an upper limit (in the 10-13
torr range) to the HC levels inside the machine. Lesson of the week:
if you look hard enough you will ALWAYS find something.
We did some minor modifications to the turbopump controller settings
to force tripping and backfill on forepump faults (e.g., empty or soft
seal gas dewar).
Speaking of which, the membrane air dryer components have arrived from
Ballston; Myron is installing them now. Next week we will commission
the dryer and wean ourselves off N2 seal gas dewars for good.
EXTERNAL PRE-ISOLATORS:
Ken Mason reports-
Completed the coarse actuation system design for both the hydraulic
and electromechanical isolators. The system will allow +/- .2 inch coarse
adjustment in two horizontal axes and in the vertical axis using many of
the existing parts. The drawings for parts already being built have been
updated and sent to the suppliers. Changes to the housing caused the delivery
to be changed from May 17th to June 3rd.
A weldment has been added which will allow the isolator to be preassembled
in a bench area. The parts are held in position with locking screws,
which are backed off when the assembly is on the pier in its final position.
Myron has begun design and specs on a precision HAM installation fixture
based on commercial precision ballscrew jacks. A manufacturing rep will
visit Monday to detail the requirements.
PSL:
No report.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
E2E for LIGO I meeting
A list of noise sources/mechanisms (including
bi-linear coupling mechanisms) needed for the next version(s) of the e2e
tool and limits or estimates of the relevant parameters was presented by
David Shoemaker in monthly E2E for LIGOI meeting on wednesday. Details
in http://www.ligo.caltech.edu/~e2e
Next e2e package release
Due to various problems, the release of the new e2e package is delayed
until the beginning of June.
Noise from newly developed SimLIGO
(Matt) Continued noise modeling, including the creation of a Matlab
representation of the noise sources present in SimLIGO. Currently adding
frequency and intensity noise as well as the common mode servo path.
Mode Mismatch studies
(Biplab)
-
FFT runs: ran FFT for as-built LIGO parameters in cold state but with input
beam that is matched in hot state. Got high level of sideband power in
higher order modes. Trying to compare these results with Han2k model.
-
E2E runs: Some instability problems encountered in locking Han2k beyond
a certain degree of mismatch. Discussing with Matt, tried gain changes
and now calibrating input matrix again.
Code development and maintenance
(Hiro)
-
DAC noise model is improved with Matt.
-
PSD module is improved to work when connected to outputs digitized data
-
Misc bug fixes and improvements
(Ed Maros) Started revision of installation document
Alfi
(Bruce) (3.0 days)
-
Completing implementation of junctions back into Alfi5.
(Melody)
-
Fixed and closed some problem reports for alfi5.
-
Updated the Tips and Shortcuts document.
LIGO Data Analysis System
Software Systems (Blackburn)
The migrations from TCL eventloop driven data sockets to TCL channel
based data sockets finally payed off this week. We've been working with
the new TCL channel interface for less than a day so results are preliminary,
but indications are that we are looking at roughly a 40% improvement in
the system performance and about a factor of 3 increase in reliability.
Many thanks to everyone in the LDAS software development group for the
effort to get this ready for the next release.
The frameAPI resampling code is now directly returning the appropriate
data structure for storing resampled channel data into processed frames.
The controlMonitorAPI's client now has to ability to point and click
on a graphical representation of jobs issued to the system and pull up
the associated log files.
The data products constructed by the eventMonitorAPI are now collected
into a single container before transmission to the designated API. This
decreased the time spent in the eventMonitorAPI during a dataPipeline command
by a factor of as much as 5 in typical upper limit search codes.
The lightWeightAPI was modified to correctly work with the new Xerces-1.7
XML C++ I/O library. We will be migrating to this version in the next
release.
A set of cgi based webpages are being designed in PERL for a secure
seb server and will provide an automated means to request an LDAS user
name and password. The next release of LDAS will require users to apply
for passwords through this webserver.
The GCC 3.1 compiler is now available. We have begun the first phase
of testing with this compiler and hope to be building and testing LDAS
using it in the next week.
The ILWD socket test has been updated to use the new TCL channel calls
to the data sockets. Test results from using this new script indicate that
data transmission is about 20% slower do to the overhead of the TCL channel.
A small price to pay in exchange for the overall 40% speed up in LDAS jobs
and increased reliability.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
-
HPSS: Continued migration from Redwoods to 9940s. Finished phase I (the
low fruit) of HPSS user directory reconfiguration (moving towards no data
in user home directories). Finished all outstanding account create/retire
requests. Spending some time (on going) trying to dig out of the
current 3590 situation (a user dumped 1000s of small files into HPSS and
used up all the tapes).
-
SAM-QFS: discovered mode where stopping and starting the SAM daemons doesn't
kill the old archiver daemon which then prevents archiving from occurring.
Not able to reproduce on demand, but it has happened a couple of times.
The fix is easy (kill the daemon by hand and restart).
-
Discovered odd (IHMO) caveat: when expanding filesytem you _must_ add metadata
space (can't just add more data disks). Need to ask LSC about this
as it will render the feature mostly useless to us (if it was ever useful).
Successfully retrieved data from tape using nothing but standard UNIX tools
(dd and tar) and without using any of SAM's log files. It does seem
that you lose information this way i.e. you get the file, but not the full
directory tree. Given that our frame files are all uniquely named,
this wouldn't present a problem for us.
-
I'm currently working with samfsdump and samfsrestore, which seem to provide
the functionality we're looking for in terms of getting data from one SAM-QFS
instance (LHO/LLO) to another (CIT).
(Al Wilson)
-
Tested, installed, and configured AIDE for system intrusion detection.
-
With the release of RH 7.3 I am revisiting the kickstart installation disk.
They have made some improvements to the program.
-
Tested, installed, and configured a sample Beowulf node computer--2GHz
P4 512M memory, 20g hard drive.
-
Added some cosmetic html stuff to big brother.
MIT
(Keith Bayer)
-
Continue to investigate bandwidth between MIT & Caltech.
-
Continue to investigate alternative hardware for TB PC NAS file server.
Hanford
(Greg Mendell)
-
To free disk space for jobs on the LDAS system at Hanford I have removed
the sample of E6 data at this site (about 100 GB). This data is available
at most other LDAS sites, and can be restored to LHO if needed.
-
Backed up SFTs at LLO onto tape (Ignor will retrieve and store the tape).
(SFTs at LHO were backed up to tape last week.)
Data Analysis Activities (Lazzarini)
Mendell:
-
Attended the LDAS workshop held at UWM May 13-14.
-
The new version of the LALDemod function that turns SFTs into DeFTs was
checked into CVS by Steve Berukoff. This version computes the maximum
likelihood estimator that maximizes signal to noise when amplitude modulation
is accounted for; the previous version just accounted for phase modulation.
-
Worked with Maria Alessandra to incorporate the latest LALDemod function
into the knownpulsardemod DSO, discussed I/O of SFTs into our codes, and
other issues concerning our work on the periodic search.
-
Worked with David Chin to modify the LALDemodTest.c code to output test
SFTs that include phase and amplitude modulation effects plus gaussian
random noise into ascii files. These will be converted into frame
format and used as test data for input into LDAS jobs.
Shawhan:
Other data analysis activities (Shawhan)
-
Revised the LIGOtools "dataflow" package to work efficiently with the latest
version of LDAS, and to fix a number of bugs.
-
Working on revising the LIGOtools "ldasjob" package to fix bugs and to
add features.
Lazzarini:
I finished analyzing data from 1999.10.01 - 2000.09.30 on the US power
grid manins (60 Hz) frequency variations for the Western and Eastern sectors
(they abut roughly along the eastern front range of the Rockies). I put
together a number of PDF plots from Matlab outputs. See:
http://www.ligo.caltech.edu/~lazz/distribution/LSC_Data/matlab/MainsCorrelationsPlots_all.pdf
The narrow band features correspond to the periodic frequency corrections
imposed on the 60Hz mains in order to maintain frequency stability in the
presence of varying loads.
It is surprising that the East-West cross-correlations of the frequency
errors exhibit coherence over periods of order 1 yr. It is not clear whether
this is going to be a problem for, e.g., long-term integrations of cross-correlations
between sites. The degree to which these grid correlations couples into
the detector(s) needs to be understood first.
The U.Fl. group has been looking at mains peaks in power monitors and
AS_Q signals as part fo the Stochastic Working Group activities. Long term
correlations we observed and were also seen to decay; however the time
scale provided by these grid authority datasets is much longer than anything
we would have seen to ate during engineering runs.
General Computing (Wallace)
MIT:
(Keith)
-
Working on new backup strategy using SB100 to hold nightly updates from
file server
-
Installed SCSI card in SB100
-
Purchased new printer for copyroom
-
Purchased new laptop for scientist
-
Troubleshot windows/excel problems
-
Updated printer drivers on gc machines
-
Tested out new OpenSSH/Entropy/Zlib/TCPwrappers packages for install on
gc computers
-
Burned cd of MU7 (off of ldas computers) for use on gc solaris machines
(Larry)
-
Working with Keith on the installation of the hardware for the MIT Control
Room. Software installation should be wrapped up by the end of the week.
Livingston:
(Sroddy)
-
Finished building a workstation for a software package that will help with
the computer management here.
-
Installed VNC on a couple more computers.
-
Updated the access rules on the firewall. Looking into some classes
on the PIX offered by Cisco.
-
Loaded some more CDs into the "online" software storage.
-
Installed P-card software on a couple of new machines.
Hanford:
(Christine)
-
Called the repair person to fix a printer.
-
Installed the newest version of Acrobat Reader on the Unix application
server.
-
Created a new user account and a couple new modem accounts.
-
Provided various other miscellaneous user support.
-
Continued work on a cgi to put the work permit form on the web.
-
I have been investigating a theory that ATM packets to the 3810 which connects
to the Cisco router and T1 line are given priority over ethernet packets
to the same 3810 and that direct OC3 packets to the 3810 are given priority
over Fast Ethernet. This prioritizing by the 3810 appears to determine
the priority by which packets go out to the T1 line and I believe it creates
a situation where certain computers can monopolize the T1 line.
CIT:
(Mike)
-
Upgraded and reloaded two PC's with all GC software to setup two cubicles
W/B 2ed floor RM: 251.
-
Started working on loading another PC to setup on the second floor.
-
Loaded a new PC for Alan Weinstein with all GC software and additional
engineering packages. This is now setup in his office.
-
Moved a lot of equipment around to make room and set up three cubicles
on W/B RM: 251 to get ready for surf students.
-
Loaded two Laptops with all GC software and put back into loaner pool.
-
Placed equipment to be put on the surplus list which includes: monitors,
computers, and gsparc.
-
Started working on loading three new laptops for 40meter.
-
Worked with Larry and Veronica on testing VRVS and VNC, by running these
programs concurrently in order to be able to broadcast a meeting by using
VRVS software for video and audio. Then using VNC software if the Host,
desired to present a presentation with Power Point, PDF document, or Post
Script files. This approach seems to work rather than trying to zoom
in with the camera using VRVS software that does not pick up the fine print,
equations, etc. This has seem to be an success but must run some
more test in order to clear out a few bugs and document the procedures
for future broadcasted meetings.
(Lisa)
-
Still working on getting a test environment up.
-
Started looking into a web indexing project.
-
Resolved a problem with the modem pool ISDN lines. The major problem was
with the phone company. They needed to reset some of their equipment.
-
Baked a cake for gsparc's wake.
-
Made changes to the IP inventory system.
(Larry)
-
Worked a number of procurements. It looks like the items for LDAS have
all gone through. A number of other minor items to work on in the PC area.
-
Resolved a couple of PC network issues. Along that same line there have
been a number of spam mails and e-mails with virus attachments. We are
filtering a number of locations and the list is growing every day.
-
Worked a few issues on the VRVS and other video conferencing solutions.
Also, started distribution of the calcium calendar tool.
-
Still working on a number of server and sandbox unit builds. Should get
a number of them up next week.
-
Worked a number of licensing issues. Still have a few to go.
-
Working on documentation concerning the security audit. Also, working on
security plans with Livingston and CDS. Definitly more intereset in computer
security over the past few months.
(Veronica)
-
LIGO website: Working on the Press Kit website. Kept working on the LIGO
Policies and Procedures webpages; attended a meeting of the Gang of Five
on the status of the document preparation for web posting. Discussed
with Linda a need to implement a new document flow/document control system.
Met with Gary, Dennis, and Linda to discuss the requirements for the new
system. Linda contacted a company that specializes in need assessment and
offers recommendations on possible solutions - software packages, deployment
strategy, cost/labor estimates. We plan to meet with the company's representatives
for a round of interviews close to the August'02 LSC meeting, to have better
feedback from other LSC members. Posted the new Internal Bulletin
Boards webpage. Posted last-minute announcements and updates to the Elba
2002 GWADW webpages, as well as a few updates to the LIGO website. Together
with Mike, looked into setting up a VNC connection for some of the talks
from Elba Conference.
-
CaJAGWR: posted William Hamilton's talk.
LIGO II/Advanced R&D (Sanders)
>From: "Alan Weinstein" <ajw@hep.caltech.edu>
Burst working group meeting at MIT:
The Burst UL working group met at MIT from May 5-8 to push E7 data through
the burst analysis pipeline. Attending were: Peter Saulson, Sam Finn,
David Shoemaker, Alan Weinstein, Laura Cadonati, Stefan Ballmer, Ed Daw,
Igor Yakushin, Julien Sylvestre, John Zweizig, Daniel Sigg, Rauha Rahkola,
Szabi Marka, Erik Katsavounidis (host).
It was a very productive meeting. Over 1000 LDAS jobs were submitted
to ldas-mit for generating burst triggers using three different burst filters,
and most of them succeeded. Veto triggers were generated by DMT monitors
absGlitch and Gide. The EventTool/ROOT was used to study and optimize
the vetos. Then EventTool was used to cluster burst triggers; apply
vetos, plot veto efficiency, livetime, and trigger rates; form coincidences
and delayed coincidences between H2 and L1. We studied the efficiency
for a variety of burst signals injected into the data (as far away as 10
pc!). We got almost all the way through the pipeline, on triple-coincidence
playground data (3.2 hours). Significant progress was also made on
the external (grb) trigger analysis pipeline. There was much discussion
of the final statistical analysis and the form that final results might
take. Much progress was made, and much more work is planned
for refining and finalizing the procedure and then running on the full
E7 data.
From: Peter King (PSL)
Lee Cardenas and I traveled to Stanford to check the performance of
the 10-W laser loaned to the laser group up there. Shally Saraf had
reported that the laser output power was only 4-4.5 W. On arrival
a quick check of the state of the laser revealed:
| master oscillator diode current |
1.89 A |
| master oscillator output power |
250-260 mW |
| power amplifier diode current |
23.01 A |
| laser output power |
~5 W |
| diode temperature set point |
25.5 degrees C |
| operating hours |
11,268 hours |
| master oscillator monitor |
89 |
| power amplifier monitor |
60 |
It was decided to increase the NPRO diode current to bring back the
NPRO power close to the same level at which the laser was shipped, so that
now the NPRO current was 2.21 A. This brought the NPRO power to 415
mW, c.f. 405 mW when shipped. The optical train to the power amplifier
was re-aligned and adjustments were made to the thin-film polarizers.
Afterwards the state of the laser was:
| master oscillator diode current |
2.21 A |
| master oscillator output power |
415 mW |
| power amplifier diode current |
23.00 A |
| laser output power |
10.6 W |
| diode temperature set point |
24.9 degrees C |
| master oscillator monitor |
214 |
| power amplifier monitor |
135 |
>From: Lee Cardenas
Stanford University Laser Lab. (Shally)
126 MOPA S/N 104 with NPRO # 248
Completely re-aligned and power output obtained to be 10.5
watts.
Symptoms found:
water level very low in the cooler. Water is very dirty - we
added distilled water. Shally will replace water later.
NPRO output power 262 mw after EOM (original power 380mw) with 1.89
Amps of current. Current did not change.
Both Thin Film Polarizer on the optical train was reflecting ~100 mw
of power (major offset)
NPRO power going into the Amplifier only 85mw (original power 290mw)
MOPA output power ~ 6.00 watts after laser window with a 33.0 amps
of current with a 25.5C diode temperature.
The potentiometer to adjust laser parameters on the power supply not
functioning properly.
Remedies:
Increased NPRO current to 2.22 Amps to bring NPRO power output
to be 415 mw after EOM in place.
Re-aligned optical train completely
Fixed and aligned both Thin Film Polarizer to minimum reflectance ~
0.5 - 1.0 mw.
NPRO power going into the Amplifier is now 340 mw
MOPA output power is now 10.5 watts with 33.0 Amps. of current and
24.8C of diode temperature adjusted and running cooler.
Replaced a new potentiometer.
Phil Willems
Fused silica fiber research
The vertical bounce experiment is installed in vacuum in the OTF and
collecting data. This is an all-fused-silica, triple pendulum suspension,
and the vertical bounce motion of the small intermediate mass allows one
to cleanly measure the Q of a fiber at high strain (due to a much heavier
bottom mass). Initial data are that the Q of this mode is 12 million
at the strain intended for advanced LIGO. This compares very favorably
with the Q's of bending modes measured previously for an identically prepared,
but unstrained fiber, which was 11 million.
This suspension is rich with modes to study, but large seismic excitation
of the lowest vertical bounce mode is complicating the measurements.
The next step is to float the optical table to reduce the excitation.
Mark Barton
Added the corrected thermal noise code to my triple pendulum model,
bringing it up to date with the quad model.
This week I extended the validation of my suspension models to asymmetrical
cases, to check for errors and to see whether imperfections made a big
difference to the thermal noise predictions. In the toy and triple models,
I made one of the fibres 1 mm shorter than the others. Initially
I found a surprising result: there was a strong cross-coupling of roll
to yaw which inflated the yaw thermal noise by a considerable amount at
frequencies above the roll mode peak. It turns out that the result is strictly
correct for the precise sense of "yaw" implied by the setup of the problem,
but that this doesn't correspond to the obvious sense of rotation about
a vertical axis for problems with a static pitch displacement, due to issues
having to do with non-commutativity of finite angular displacements. It's
easy enough to add a correction to make the results more interpretable
but this has not yet been done.
From: Riccardo DeSalvo
Akiteru
SAS suspended Fabry-Perot.
Here is a result of a naive analysis on the 3m FP spectrum. This
is a spectrum of the error signal of the 3m cavity, corrected with a single
pendulum transfer function (the simplified version of the open loop transfer
function). This approximation should be correct up to a few hundred of
Hz, as the UGF is around 1 kHz. Of course I have measured the loop
trf, and will calibrate the spectrum accurately). The SAS inertial damping
was turned off on both the towers. I guess, the measurement was limited
by the laser frequency noise above 2 Hz at time. I will take other measurements
with laser frequency stabilization on, next week, and of course I will
turn on the inertial damping as well. Though there should be various noises,
and it will be hard to investigate their sources, the result seems quite
good at low frequencies. As far as I experienced, all the peaks below 2
Hz must disappear after installing the damping, without injecting control
noises. So we are very close to what we promised (10-8 m r.m.s.
above 100 mHz), if I didn't make stupid mistakes on the calibration.
Michael
Cryo setup still down, Quantum Design spent lots of time replacing parts,
both present and replacement cryo pump look bad, they will be back next
week with more thoroughly tested components.
Hareem, Kelin, Bill
Finally found the correct splatter setup and splatted several samples,
the first one was polycrystalline (breaks into dust if you touch it), the
other samples are glassy (not fragile) on increasing fraction of the sample
surface. Tuning for optimal point The setup process ate a lot
of samples, now we are short of supplies, need to make more samples.
Tried also a MoRuBAlSiP, chickensoup sample, for fun for now.
Kelin
Prepared fiber vacuum feedthrough in view of Q-factor measurement
in cryo setup.
Preparing platform for room temperature Q-factor measurement in large
vacuum chamber.
Aso
Calculated folded pendulum suspension thermal noise. There is
no advantage in using a folded pendulum. The resonant frequency is
pushed down and the effective K goes down, but the term 1/2K X2
at fixed frequency stays constant. A posteriori, since the mechanical
K stays the same, this is not surprising. Now concentrating on calculating
thermal noise in thin flex joints.
For additional information about this report, contact sanders@ligo.caltech.edu