|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday November 25, 2002 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
Executive Committee only 11:30 - noon
Topics:
Special Items:
no report
LIGO Operations--Administration
There was a site teleconference held on Thursday, November 21, 2002. The following issues were among those discussed:
Financial Status--During October LIGO had $2.7 million actual costs. Of this, $1.3 million covered FY 02 expenses, and $1.4 million was for FY 03. These costs include all R&D effort, so expenses were higher than previous years. Florence estimates that there will be an additional $700 accrued for FY 02 costs.
Livingston Staging Building--Ed Jasnow is at Livingston to close out the Brunt contract. They are making progress. The weather and the availability of some components may preclude finishing this week.
Hanford Laboratory Building--The most significant punch list item remaining open is for a warped metal exterior door. The contractor is getting new doors.
The front door needs an atrium and second set of doors to keep the Hanford environment out. This will be placed on the Construction contingency list with an estimate of $25K.
The LDAS room has turned out well.
Traffic Control (Actions 108 and 112)--The sites have been instructed to start. The cost is below the threshold fo a Change Board action.
Outreach (Action 113)--Mark Coles, Fred Raab, and Jill Andrews
are working on a proposal. The action remains open.
Use of Auditorium at Hanford (Action 114)--the email has been
prepared and sent. However, no formal response has been received
from the NSF. Therefore, the action remains open.
The list of current actions revised to reflect
the status of open actions assigned through November 21, 2002 may be found
at ACTION
LIST.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
ACTIVITY
| For Week Ending
11/21/02 |
Packages | Faxes |
| In | 34 | 38 |
| Out | 9 | 38 |
From: Esther Cunningham <esther@ligo.caltech.edu>
No report this week (vacation).
Press here for ACCOUNTS PAYABLE HISTORY DATA .
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
We were informed that Lab-view software had been stolen, which originally cost $1,900.00. [Gina explained] our problem, [and National Instrument too pity on us.] [Gina] was able to negotiate an up-graded version 6.1 for the cost of $ 395.00 with an educational discount of 35 percent, which will cost LIGO $ 256.75. [Go Gina! -pel]
From: irena@ligo.caltech.edu (Irena Petrac)
Ed Jasnow has been in Livingston all week attempting to close out the contract with Brunt Construction for the Staging Building. A great deal of progress was made towards finishing out the punch list, agreeing on replacing part of and finishing the auditorium floor, and arriving at a method to reduce the noise of the HVAC.
OPERATIONS:
The designs for traffic control gates at both sites are coming together, and it is anticipated that work should begin early next year.
SUPPORT (Baldon, Torres, Lloyd, Tischler)
>Irene Baldon
Weekly Advanced LIGO Project Controls meeting was not held this week.
Advanced LIGO MRE Proposal (Highest Priority)
Project Web Site for posting schedule and progress related data continues to be updated with the latest and greatest.
I have distributed a "strawman" outline for the FY 2002 annual report
to selected people for suggestions. The annual report is due to be
submitted to the NSF at the end of December, covering activities from December
2001 through November 30, 2002. This Annual Report is required for
the old (Construction Funds) Cooperative Agreement, and the focus is the
end of Construction, Installation, and Commissioning, not Scientific Results.
Mt objective is to keep this simple. We will be asking for contributions
before theDecember holdays.
There are currently no open change requests to be considered
by the LIGO Chnage Control Board, and there were no change requests addressed
during the Executive Committee Meeting on Monday, November 18, 2002.
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
Arranged for a briefing (LDAS and PMA personnel) regarding operation of the new fire suppression system recently installed in room 215 Synchrotron. This system uses compressed gas (CO2) for fire suppression by reducing the O2 content in the room. The author can testify to no ill effects after discharge of the system other than excessive sound during gas discharge (similar to standing behind a 757 at takeoff). A vendor representative explained how the system operates, the alarm sequence (with demonstration) and override provisions (without gas discharge).
Worked with C. Scislowicz (Caltech safety) to assess the potential safety
risks associated with a proposed hydraulic fluid for a new hydraulic isolation
system. We recommended that the system demo test at MIT could proceed
as long as MIT's laboratory safety policies were satisfied. We also recommended
that once these tests were successfully completed, that a "safer" (less
flammable) hydraulic fluid and supplier should be selected from the "Factory
Mutual Research Approval Guide-Flammable Liquid Equipment" list.
Summary of Commissioning Activities at LIGO Hanford Observatory (compiled
by F. Raab)
-------------------------------------------------------------------------------------
(see ilog for details - if it's not in the ilog, it didn't happen...)
Lots of WFS work going on this week. Josh has been modifying heads
to stop internal oscillations. H2 operation has been restored. Improved
spectrum was seen on H1.
2K IFO (H2)
-----------
Optical-lever (OL) photodiodes were uniformly up to current rev. A
problem with locking was identified as an improper setting for the MCF/MCL
crossover in the mode cleaner, causing an instability, so locking is now
restored but still flaky at times. WFS1 operation was restored. The new,
partially digital, common-mode servo was engaged for the first time. A
new optical-lever laser is being tested on ETMY after successfully passing
testing in the Optics Lab. The new laser (new vendor) promises to ease
supply pipeline problems we have experienced in the past. Repairs
to ETM dewhitening boards to improve hardware reliability (intermittent
jumper problem) and kill 1.5 MHz oscillations were made. The CARM drives
to the ETMs and drives to FMs (used by MICH and PRC control loops) were
recalibrated.
4K IFO (H1)
-----------
Josh brought OL photodiodes uniformly up to current rev. Also updated
photodiode interface boards. WFS1 was installed and turned on, after some
troubleshooting we are seeing good reduction of alingment fluctuations.
WFS2 is being installed and tested on POX, instead of designed implementation
on REFL. The investigation of optical lever peaks induced by mechanical
excitation of the optical lever structures led to the observation that
peaks could be shifted in frequency and lowered in amplitude by torquing
bolts. We await instructions on tighening these bolts to a uniform spec.
We got a particularly good alignment for reducing AS_I fluctuations
and this allowed us to increase ASPD light more than we could in the past.
The resulting spectrum dips to about 8-9e-18 m/rHz at approximately 300
Hz, running with about 8 times the light transmission to ASPD used in S1.
Facilities
------------
The last remaining problem with the punch list for the new building
is the entry doors, which are warped and will be replaced. The new soft-start
water-well pumping system has been installed and tested. A significant
source of lock loss in S1 was traced to the seismic jolt from the sudden
turn-on of the well pump. A soft-start system was installed to reduce the
jolt. Now a person standing at the pump can barely detect the pump start,
whereas before it could be felt. We will see if we can get a more quantitative
ruling from the seismometers.
Interferometer Commissioning: We are setting up the phase camera and measuring the x pick-off beam. Work continues on the commissioning of the WFS. We are also making progress in the implementation of the tidal servo system. It was discovered that the optical lever piers in the LVEA were not assembled correctly when they were originally installed. The bolts connecting the upper and lower parts of the pier were found to be only hand tight. Once these were tightened and the solid connection (the aluminum tube) between the vacuum tube and photodiode case was removed, there was a significant reduction in the power spectrum of the optical lever displacement. Greg Harry is here working on the measurement of the modes and Q's of the suspended optics and making good progress.
HEPI / LASTI Ameriflex provided replacement bellows in 2 days, and we completed assembly of the first 2 actuators for MIT Saturday afternoon, and delivered them to MIT Monday morning. 2 more were completed yesterday and delivered today (11/20). We should deliver the final 4 by Monday, December 2. L4C brackets completed and sent for anodizing. (Hammond,Kern)
Optics / Laser Spent a lot of time with the Laser Safety Interlock system this week. We found an idiosyncrasy the logic, which resulted in an alarm if an individual working on a laser table completely closed, and then reopened a table. This while they were properly authorized to be there. Thursday the installer is returning to reprogram the tables as separate areas which will prevent this. Issued multiple Laser Access cards and, conducted walkthroughs with 4 new basic trained persons. (Kern)
LDAS admin:
1) Generated RDS from LLO S1 data. fb2 can write to /frame11, /frame20,
/frame12 again and overwrite full S1 frames.
2) Upgraded DB2 to 7.2 at MIT
LDAS data analysis:
Working on database output from WaveDSO
Igor Yakushin
GC:
With the assistance of Larry Wallace, installed the new network switches.
We now have a gigabit backbone with 100 mbit ports to all workstations.
The only exceptions are a couple of machines, such as the machines in the
LVEA.
Continuing to work on the firewall configuration.
Met with Charlie McMahon, and Terry Doub today to discuss issues with
LSU's network. Making a bit of headway with a couple of issues. Some issues
are still up in the air.
Attended the annual LSU computing meeting on campus today. There are
a couple of issues that may affect LIGO, but nothing major. LSU is installing
an IDS system at the border router. This may be an issue, though it will
probably be transparent. They will start blocking port scans in the near
future. This will be a huge step in protecting their network. This includes
our subnet. I will be meeting with Terry and Charlie again concerning some
more issues with the network. * No new news on getting a better network
connection to LLO. We are still stuck at two T1s.
found out that it is relatively easy to get an account on LSU's beowulf
cluster. Anyone that is interested can contact me. This is the 2nd fastest
cluster in the world owned by an academic institution. 17th fastest overall
in the world.
Ordered a Cisco VPN for the LLO network. I have the initial configuration
installed on it, but I will need a couple of weeks before I make it available.
I have a lot of testing to do on the unit.
(Shannon Roddy)
Jonathan Kern,
Marcel Hammond
Ameriflex
provided replacement bellows in 2 days, and we completed
assembly of
the first 2 actuators for MIT Saturday afternoon, and
delivered
them to MIT Monday morning.2 more
were completed yesterday
and delivered
today (11/20). We should deliver the final 4 by Monday,
December 2.
L4C brackets completed and sent for anodizing.
Hydraulic
fluid selection
Ken Mailand
4 fluid samples
along with their specifications and MSDS are arriving at CIT by early in
the week of 11/25.
One fluid
will be selected as best of the lot for use in the LASTI setup.
Longer term
refinement of the mix will continue for the site installation or LASTI
upgrade.
These formulas
will be water soluble, fire resistant, and non toxic.
LASTI Pump
Station
Ken Mailand
Pump Station
arrived safely at MIT and has been assembled on site.
The electrical
pressure sensor box has been sent back to CIT for upgrades.
A Fluid Level Sensor and /or a motor / pump over temp circuit will be added.
- Updated
LSC code to provide an extra filter bank for ASI correction.
This bank
gets its input from the ASI summing junction and outputs to
DAC channel
one.This is installed on the LHO4k
and operation verified
thru the LSC
dewhitening filter.
- Framebuilder
and Dataviewer being worked to allow lookup of old
signals (signals
no longer being acquired or have had name changes)
still stored
on disk.This should be installed
at LHO in the next few
days.
- New Dataviewer
(using xmgrace) is being tested at LHO.
- Framebuilder
code has been updated to use FrameCpp version 6.This
has been installed
on LHO FB3 for testing.
- Performed
a number of timing tests on LHO systems last week.A
document on
timing, diagnostics and initial test results will be out by
next week.
- Working
on modifying suspension control software for use in the 40m
lab.We
are hoping to have it ready and installed some time first week
of December.
This week
I modified the DMT data accessor classes (DaccIn, FrWrite,
FrameF and
other classes and programs) to use FrameCPP-0.5.0 and to
read/write
version 6 frames. At present, the modified software seems to
work at a
very basic level, although it will need a lot of testing before
it can be
inflicted on the rest of the world.
I have also been preparing for the Mini-run at LLO Saturday.
1.Work
has progressed on the seismic isolation system, we have developed and integrated
two temperature sensors for use on the Pump Servo.The
local display now reads an interesting hybrid of degrees centigrade and
PSI.The temperature sensors are
to monitor the pump and load temperature.As
well as differential monitoring of the load pressure for regulation purposes,
there are 4 channels of pressure monitoring to be used on the local piping
associated with the pump and filters.
2.Mohana
is working on fixing some electronics problems associated with the seismic
interface chassis she designed.These
problems were relayed by Richard Mittleman of MIT.
3.150
foot long cables are being made for the pressure and temperature sensors
at MIT to be used with the Pump Servo.Research
is being done to choose a suitable liquid level sensor for the hydraulic
reservoir.
4.I
am preparing for the RFI review this Friday.
5.Mohana
is working on a cure for the mad slider problem reported with the step
gain adjust circuit in common use at the sites.The
fix will involve a local 5 volt regulator to eliminate the power supply
dependence.A DCN will be issued.
Mohana Mageswaran
Designing
and testing the requirements on a daughter card for the Variable Delay
Timing Boards. And will send the daughter board design to the PCB express
this week.
Preparing
a recipe for the Gain Sliders voltage regulation issue and will release
a DCN change along with it.
Helping Charles
King to build & test 4 Photodiode DC Driver Boxes for the observatories.
Sander Liu
With the exception of the actuators, I now have enough information to start writing a detailed requirement for the micro-seismic pre-isolator. Will be working on this document for the next few weeks.
I have been
testing out a high-current, high-bandwidth buffer for use
in a photodetector
circuit.A preliminary circuit has
been drawn up.The
constituent
parts have been crudely breadboarded and seem to function as
expected.
An analysis of the ASAP results and a final report are still pending.
I have been
in touch with Jean-Marie Mackowski for getting an overview
of the current
state-of the-art technology that could be used for
the fabrication
of the mexican hat mirrors.
He states
he can make the surface Kip S. Thorne has been designing
within 2nm
in the central area.
In fact the
bump we have in the middle of the mirrors is just ~20nm
and it is
quite responsible for the beam to be flattened.
Simulations
have shown that if the bump is perturbed ~4nm the desired
properties
of the field are lost. There are many ways to look at this;
my personal
interpretation is that the paths of the photons have roughly
the same length
and this make them superimposed in a contructive way
so that the intensity profile of the field becomes quite flat.
OTF Lab.
(Bridge)
Contamination
Cavity # 1 operating continuously.
Cavity with
test sample 65 % Glycerin and 35% Ethyl.
We continue
taking ringdown and beat frequency measurements every day.
We had some
incident that prevented the cavity from remaining locked.We
couldn't see the
side band
from the EOM( no modulation)Fortunately
the EOM was not damaged.
We increased
the RF and the EOM responded.After
careful check, we found the
input photodiode
damaged. We switched it for another one and we locked the cavity.
Now the cavity
is locked and the output power has increased and it is more stable.
Scatterometer
Scatterometer
recovering is in progress. Design for a new base platform still in progress
on and off.
New OTF
Lab at Lauritsen ROOM 38
Cavity #3
Reference Cavity it is pumping down.
We have installed
new cleaned mirrors ~70ppm each(Flat & Curve)
The vacuum
pressure is very good ~ 7E-10 torr.
We have aligned
the cavity mirrors with opened flanges insuring a very good alignment and
having two reference points for the YAG.
Cavity #2
Test cavity
This cavity
is locked. We are taking ring down measurement.
We are setting
up the electronics for beat frequency measurements.
We need a
new pulse generator.The old one
was given to P.Russel for repair.
We borrowed
one from PR in the meanwhile.
Lab. arrangement
still in progress.
I have ordered more optical mounts, posts and power meters.
Working on
the earthquake stop requirements document and associated calculations.
New osem assemblies
have been sent from the coil winding company. There are 153 in all. Bob
Taylor will start assembly of these osems soon.
These OSEMs are for observatory spares, 40m, Gin Gin, etc.
no report
no report
Simulation and Modeling (Bhawal)
E2E Physics meeting
-------------------------
Luca and Matt from LHO and Virginio, Hiro and Biplab from CIT discussed
pros and cons of using SimLIGO for WFS, mode mismatch and Frequency
response
studies.
SimLIGO
---------
Valera Frolov from LLO is interested in obtaining the WFS sensing matrix
from
SimLIGO and comparing it with measurement and then playing with model
parameters to understand the disagreement. Matt will give her a SimLIGO
setup
designed specifically for measuring the WFS sensing matrix.
Frequency Response
----------------
(Biplab, Hiro) Continued working on improvement of the Frequency response
of the power recycled Michelson cavity formulation.
Alfi
-----
(Bruce)
- Box unload implementation completed (PR 249).
- Box reload implementation being completed (PR 249).
(Melody)
- Continued working on the modeler to read the revised file format
and implement discussed optimizations.
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS was successfully used in the Super Computing 2002 Conference for
demonstration of using a hybrid of LDAS and Grid Technology to carry
out
directed pulsar searches. Over 58 pulsar searches were carried out
in this
hybrid system involving 330 tasks and 469 data transfers between Grid
enabled centers (including LDAS). The job statistics can be viewed
for the
moment at http://smarty.isi.edu:8680/cgi-bin/final.pl (Lazzarini: CREDITS
FOR THIS ACHIEVEMENT GO TO KENT, PETER,
PHIL EHRENS, the other LDAS team members who supported this effort
from the Lab. In addition SCOTT KORANDA at UWM and the ISI Computer Science
team who has been working with us should be recognized: they invested a
lot in this effort and it has been successful through there hard work.)
Worked on improving the performance of the controlMonitorAPI while filtering
on the log files in an LDAS system. Added support to remember a user's
access credentials for a fixed length of time. This information is
no longer
required to be reentered during a system control session. Began the
migration towards using the faster plotting package BLT.
All of LDCG and LDAS are currently being ported to the new GCC compiler
3.2.1 for the next release. LDCG is now compliant with the new compiler
and
LDAS is slowly being reworked to handle the changes strstream and
stringstream classes.
The FrStatData structure is now fully supported in the frameCPP library.
The
support for compression is underway. A bug in the handling of FrDetector
data from frames was discovered in the translation of that data to
ILWD and
fixed.
The dataConditionAPI effort focused on documentation and developing
a new
action which allows users to specify the target sample rate in a resampling
step.
Added a new stageData user command to allow users to stage input data
sets
for their LDAS jobs onto an LDAS system. This will be widely available
in
the next LDAS release.
Made many of the verbose monitoring messages in LDAS logs optional to
decrease the background noise in the log files and improve performance.
Made sure that all emergency sockets on APIs required connections from
within the private network.
Support for gaps in frame queries was discovered to be improperly handled
by
the test suite. This caused a bug to get into the 0.5.0 release when
data
with gaps is allowed. This has been corrected in the test suite and
the bug
is being fixed.
Worked closely with the sites and LSC to upgrade to the new release
of LDAS
and to the new database server from IBM.
Hardware Systems (Anderson)
Caltech
-------
(Dan Kozak)
* HPSS: Continued cataloging the LIGO presence on 3590 tapes, also did
account creations and general
HPSS support (since James is at SC2002).
* Got some quotes for another 1000 9940 tapes.
* No luck getting a response from Sun/LSC vis a vis our SAM-QFS eval
license.
Will take it to the next level.
* No luck getting StorageTek to cough up a correct invoice for maint.
on
the 9940 drives. Ditto.
(Al Wilson)
* Repaired datacache7, one RAID was running in degraded mode. Found
a bad
drive carrier and replaced it with one of the unused ones on
the sixth floor.
* Ldas-pcdev1 network connection died over the weekend. While I was
troubleshooting, it magically fixed the problem. Very Strange.
I will
continue to keep a eye on this.
* Metaserver on the CIT system had what appeared to be a memory problem.
Called sun out. The final score was One CPU PCB, and two memory
dimms.
* Found some files that needed to be updated for cfdef, on the MIT 7.3 upgrade.
* Setting up cfdef for Big brother files.
(Stuart Anderson)
* Helped with the LDAS system upgrade at MIT which is now running the
latest LDAS release (0.5.0).
* Testing OpenSSL, OpenSSH, and Apache security updates on LDAS-DEV.
* Started working with Larry Wallace and Lisa Bogue to use a central
Laboratory wide Certificate Authority for signing SSL enabled
web
server certificates.
* Finished configuring ldasbox1 as a full stand-a-long LDAS server system
for one of the LDAS programmers.
* Started working with Sun engineers to understand the large number
V880
memory failures experienced over the last year.
MIT
---
(Keith Bayer)
* Upgraded cluster machines to RH7.3
* Upgrade Dell servers to RH7.3
Livingston
----------
(Igor Yakushin)
* Generated RDS from LLO S1 data. fb2 can write to /frame11, /frame20,
/frame12 again and overwrite full S1 frames.
* Upgraded DB2 to 7.2 at MIT
Hanford
-------
(Greg Mendell)
* Worked with Caltech to regenerate the RDS data for S1 at LHO using
LDAS and the rdsloop.tcl driver script. I was able to run 3-4
copies of
the script in parallel, with no problems.
The script ran on GPS times 714150000 to 715618848 and
completed in 6.5 times real time. The remaining task is
to generate the
RDS data for the post S1 injection times.
* Disk 4 has failed on t3-4 at LHO (indicated by a slowly blinking
amber drive status light, a "fru stat" and syslog messages).
I've called
Sun and they are sending a replacement disk.
The T3s are raid 5 boxes, and tolerate a single disk failure
without loss of data. The disk should be automatically
reconstructed
upon replacement.
* Started setting up a Sun Ultra 10 on the LHO GC network to act as
the
ldas-jobs server. This box will run scripts to drive LDAS
jobs, with a
control interface to the web and the control room. Unfortunately,
the
hard drive has failed on this box; a replacement drive will
be ordered
soon.
Data Analysis Activities (Lazzarini)
Shawhan:
Still working on the inspiral upper limit analysis.
Mendell;
1) The main work the last week has been to get the knownpulsardemod
DSO
and driver scripts to work with the 0.5.0 release of LDAS. Several
problems remain, but I should today be able to try several proposed
fixes.
2) Work with the PULG group on our a report of our progress with the
S1
data
Creighton:
Finished debugging SkyCoordinates routines in LAL, and provided
a test program for astronomical coordinate transformations,
geodetic <-> geocentric coordinate transformations, and
GPS time <-> UTC time <-> sidereal time transformations.
Weinstein:
- made plots, and wrote words, for the burst group report.
- started organizing code for cvs repository of burst code.
Lazzarini:
Completed an X62 analysis of the HW and SW injections for the stochastic
background analysis. Determined that the hardware injections suffered
from an apparent 1.2 - 1.5 msec
timing offset w.r.t. GPS time stamps. Part of the source of this offset
may be due to documented timing offsets measurements
in the GPS timing monitors during S1; however, it appears that the
determined offset cannot all be explained by this.
General Computing (Wallace)
MIT:
(Keith)
-Installed new harddrive / os on lap pc to ship to LLO
-Purchased shrinkwrap software for laptops
-Configuring Sparc5 box for wireless NAT router in NW22
-Testing SSL wrapper on POP e-mail server
Livingston:
(Shannon)
-Attending LSU network meeting. Will report on it next week.
-Working on Solsoft pkg. for Cisco configurations.
-Purchased VPN unit for connections on the GC side of the house.
-Installed the new GigE backbone. There has been a noticeable improvement
in local network performance.
-Checking with LSU to go over a couple of network performance issues
on
the WAN side of the house.
Hanford:
(Christine)
- Created some "how to" web pages for users using a software package
that snapshots screens, windows or regions then provides an editor
to
annotate the snapshots. Started redoing all my web page documentation
using this software.
- Added access to the new color printer on all the Sun workstations
and
all the guest PCs. Helped several people install the new printer
driver
on their PCs.
- Purchased several items for people. Purchased a larger disk
for
Fred's laptop. I will be trying out some new software to create
and
restore a disk image over the network.
- Lots of user support
CIT:
(Lisa)
- Built and installed a blade 100 to replace Syd's old sparc5
- Worked on some problems with the cron jobs on canopus
- Fixed the incident reporting mailing list and mailman archives
- Updated the wireless APs
- Worked on getting the backups to work on the windows servers after
installation of the firewall software
- Loaded OS 9 on blade2000
- Looked into a problem with the pop services on acrux. There
is a timing
problem that occurs sporadically with remote connections. Becrux
has a newer
version of the pop daemon. I am still testing to see if the problem
is resolved
with the newer version of the code.
(Mike)
-Reconfigured and updated two laptops for Helena & Ryan for travel.
-Updated security on all windows workstations running 2000 Pro.
-Spent a lot of time configuring firewall software on all servers.
-Loaded a new server with 2000 Server OS to replace the current Elba
server that is hosting the Elba Website running on NTSRV 4.0. I am
still in
testing phase and hope to have the updated server in place before the
end
of the week.
-Went around and took inventory on all printing accessories to place
an
order that was seriously behind.
-Performed a lot of user support this week that included mostly software
& some networking problems that I took care of.
-Re-ghosted three NTSRV's and will be ghosting the rest of our servers
before this week is up.
(Veronica)
- Project Science: Posted transparencies from last week's workshop.
Some
required conversion to pdf. Burned the presentations files onto a CD
for a
backup.
- GNATS database: this took most of the time in the first half of the
week. Worked on Szabi's request to modify and expand the GDS part of
the
database. Keep working on the Detector Hardware and CDS parts, per
Dennis
Coyne's request.
- CaJAGWR: Updated the website; provided some administrative support.
- LIGO website: posting updates to the Aspen 2003 GWADW website. Updated
various webpages. Working on Albert's request for setting up a
restricted-access area for certain LSC documents. This will require
modifications to several DCC databases to allow searching for these
documents and to mark up those to which access is restricted. This
is
still a work in progress.
(Larry)
-Worked with Shannon on setting up the new GigE backbone at the Livingston
Observatory. Overall things went well.
-Still working on WAN network performance issues. Waiting for a reply
from
PNNL on some tests they were to run this week. Shannon is checking
on some
performance issues with LSU. Ran a few more tests between MIT and Livingston
and still no change in performance.
-Turned a number of old computer systems and related items over to
Caltech
property. Ed C. is now working on the paperwork to make it happen.
-Installed another UPS unit in the main computer room and redistributed
some
of the power loads.
-Assisted DCC on a number of different issues.
-Setup a new temporary web service for the LSC. After the holiday a
new more
permanent solution will be installed.
-Worked a couple of PC h/w issues. Nothing major.
-Working on a number of PC, SUN, and S/W purchases. Resolved a number
of past
purchases.
-Still working a number of document issues related to policy and computer
security.
-Performed a great deal of regular user support, making account changes,
moving equipment, the usual items.
From: "Mark Barton" <mbarton@ligo.caltech.edu>
I fitted the interferometric sensor experiment out with a infrared
monitor to view the fringes and a motorized drive to vary the internal
arm length smoothly. After a lot of scanning back and forth I finally
found the sweet spot that makes the arm lengths equal enough to give
good
fringes with the internal LED source.
From: GariLynn Billingsley <Billingsley_G@ligo.caltech.edu>
We have received the Gin Gin test masses from Wave Precision.
These will be coated in the near future. The HR coating runs will
have only one optic in each (the AR can be shared.) If there is anyone
who would like to put something in the run to be coated, please contact
GariLynn or Helena.
E021063-A ITM, transmission 1000 ± 500 ppm
E021064-A ETM, transmission < 50 ppm
The specs and associated drawings can all be found at:
http://www.ligo.caltech.edu/~gari/Gingin/
From: Phil Willems <willems@ligo.caltech.edu>
ADLIGO Suspension design
------------------------
Developed a revised recycling mirror design that is about 15cm shorter
than the
previous design, allowing a lot more flexibility in the position of
the RM
optics (it just barely fit before, and the folded IFO layout had not
been
finalized). This design employs metal wire suspensions, an option
here thanks
to the relaxed requirements for these optics, and a truncated metallic
penultimate mass. This design has been distributed to other suspenders
for
review.
A set of positions and orientations for all the magnets on cavity optics
in the
HAM chambers (as best we know them) has been compiled and sent to the
SEI team
in preparation for a measurement of the stray magnetic fields from
the SEI that
might interfere with suspensions operation.
Sapphire Q
----------
We are revamping the fused silica Q apparatus to measure sapphire Q's
again.
This should be easy but much of the equipment has wandered around and
needs to
be gathered together again. We are setting up with an old sapphire
to prepare
for the 40kg monsters due soon at Caltech.
From: ctorrie <ctorrie@ligo.caltech.edu>
SolidWorks
Janeen, Mike and I attended a Q.&A. session at GO Engineer. During
the session we got help on related dimensions, bill of materials and drawing
trees. Most of this work is covered in the advanced course, that we plan
to attend in January.
Mode Cleaner
Helena, Mike and I have been working on the assembly of the 2 suspensions,
this should hopefully be completed by this time next week.
Mike and I have been working on the various sub-assemblies.
Recycling Mirror
Norna, Caroline and I have been looking at the latest revision of the
RM MATLAB model released by Phil and we hope to have finished looking at
this by tomorrow.
Mike Lloyd and I have completed the converting of the set of MC files
to a new RM folder. The last stage is to shake down all of the assemblies
to ensure this method of conversion has worked.
From: Helena Armandula <ahelena@ligo.caltech.edu>
Advanced LIGO SUS
Silicate bonding
We'll start loading a 1/2" dia. fused silica / SF4 bond; completed the modification of a fixture for that purpose.
Had the surface of a sapphire / silica bond characterized across the
bonding joint with a surface profilometer.
The bonded parts will be loaded to test for creep. The fixtures for
the test are ready.
From: Peter King <pking@ligo.caltech.edu>
2.2 AdvLIGO PSL
A Laser-Zentrum-Hannover (LZH)
NPRO laser has been locked with the PSL
frequency electronics. Some field changes
were required due to a small
difference between a LZH NPRO and the Lightwave
Electronics NPRO that
we're more familiar with and the bandwidth of
the reference cavity employed
at the University of Hannover. The
FAST actuator on the LZH NPRO is about
2 MHz/V and is unipolar. In its normal configuration at the University
of
Hannover they use a high voltage amplifier for the FAST actuator whereas
at
LIGO we do not.
The controls for the frequency servo and frequency reference have been
exercised and work as expected. There is a problem with the 50
Hz mains
showing up in various signals but there are some problems with the
grounding in the building that we are working in. As for providing
technology transfer, I feel it has been a successful exercise.
Thanks to
Rolf Bork and Dave Barker for some remote EPICS/vxWorks related support.
The wiring harness diagram was modified to reflect some in-the-field
changes. The updated diagram was submitted to the DCC.
From: Janeen Romie <romie_j@ligo.caltech.edu>
LIGO I
Working on the earthquake stop requirements document and associated
calculations.
New osem assemblies have been sent from the coil winding company. There
are 153 in all. Bob Taylor will start assembly of these osems soon.
Gingin
Working on the ITM suspension design.
40m
Made small changes to the 40m TM top assembly drawing.
AdLIGO Suspensions
Working with Norna, Phil and Calum on the max. length of a quad pendulum
suspension for the LASTI BSC seismic RFP.
Supporting MC suspension work.
For additional information about this report, contact sanders@ligo.caltech.edu