|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday October 28, 2002 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
Executive Committee only 11:30 - noon
Topics:
Special Items: NSF review reprise
Closeout Summary
• Successful completion of the first
science run with all three interferometers in lock for science for 25%
of the time for two weeks signals the beginning of LIGO science.
The Panel wishes to congratulate the members of the LIGO team (the LIGO
Laboratory and the LIGO Science Collaboration) for this outstanding achievement.
In addition, during this period the three LIGO interferometers were also
operating in coincidence with the GEO and TAMA interferometers simultaneously
for ten hours.
The LIGO team is to be commended for its
effective response to many of the panel concerns expressed last year.
The panel was pleased with the decision to move to the SAM-QFS mass data
storage technology. This allows LIGO to chart its own course and
removes their critical dependence on the CACR facility at Caltech.
The LIGO team is to be congratulated on the rapid commissioning and initial operation of the three interferometers. The application of the end to end model by Matt Evans to develop the lock sequence for the interferometers was essential to achieving lock. Operations have now progressed to essentially fully automatic lock acquisition using this technology.
• The panel notes the important contributions of the LIGO Scientific Collaboration in the commissioning and the initial operation of the interferometers and in exercising the data analysis system.
• The formation of the four analysis
groups within the LSC, focused on the four likely sources of gravity waves,
appears to be working well. Electronic logbooks along with dedicated
web pages are providing an effective means of communication and tracking
analysis progress within the collaboration.
• The panel was pleased to see excellent progress on the development of a computer security plan. A draft document has been prepared and accepted by LIGO management and many of its recommendations have been implemented. The items of concern during the last review have been addressed. These were
· Multiple, independently secure
copies of data and metadata
· Facilities augmentations at CACR
and other sites appropriate to the needs of the LIGO production facility
· Network vulnerability, data and
system integrity, and robustness under partial system failures
· Independent development, test
and production systems
· Protection against hackers, especially
for critical systems.
The panel notes the success of LIGO in negotiating
cost-effective access to high-speed network connections between the Hanford
and Pasadena sites. A similar connection to the Livingston Observatory
has not been achieved and continues to be a concern. LIGO may benefit
from seeking advice from the NSF and local universities.
The panel is pleased to note the addition
of a full time systems administrator for the LDAS system at Caltech and
a full time scientist at LLO who is both a scientific liaison and a data
base administrator.
The panel was pleased to see the successful
efforts by the leadership and staff of LDAS in building direct working
relationships with other groups and organizations in the high-performance
computing, communications and data storage and retrieval communities.
The R & D efforts leading to developing
the advanced technologies essential for achieving the factor of 15 in strain
sensitivity projected for the Advanced LIGO interferometers need continuing
support. The panel is concerned that the necessary funding for these
activities is vulnerable in these times of limited budgets.
The panel is pleased to see the very effective
collaboration with GEO, ACIGA and other international groups in relevant
R&D for reaching higher strain sensitivity.
The panel feels it is appropriate for the
LIGO team to submit a proposal for Advanced LIGO by the end of calendar
year 2002.
The panel encourages the LSC to continue
its efforts in developing collaborative connections with the astrophysical
community. The makeup of the LSC Upper Limit Teams is a good beginning.
The panel notes the efforts of the LIGO
team in using the excitement of LIGO science to stimulate the minds of
our potential future scientists and engineers. The panel is pleased
with the progress toward the addition of experienced personnel outside
of LIGO to help with this critical task so that this potential can be transformed
into reality. Adequate resources will be needed to continue this
important effort.
no report
There was no site teleconference held on Thursday, October 24, 2002 due to the NSF Review in progress at MIT.
The list of current actions revised to reflect
the status of open actions assigned through October 10, 2002 may be found
at ACTION
LIST.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
ACTIVITY
| For Week Ending
10/24/02 |
Packages | Faxes |
| In | 13 | 40 |
| Out | 16 | 36 |
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA .
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
SUPPORT (Baldon, Torres, Lloyd, Tischler)
>Irene Baldon
Working from home on Friday the 25th. I will be checking email and voice mail.
I attended the Primavera User's Conference at San Diego on Monday and Tuesday (21 and 22 of Oct.)
Advanced LIGO MRE Proposal (Highest Priority)
Project Web Site for posting schedule and progress related data continues to be updated with the latest and greatest.
The Quarterly Status Report for the LIGO Construction Project for the end of August 2002 was sent to the NSF.
There are no open change requests, and there were no change requests considered this week during the Executive Committee meeting..
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
No report this week.
Summary of Commissioning Activities at LIGO Hanford Observatory (compiled
by M. Landry)
---------------------------------------------------------------------------------------
2K IFO (H2)
-----------
MC misalignments and wandering PZT-driven periscope mirrors plagued
the 2k this week.
This was traced to problems on the MC1 SOS driver board (e.g. shorted
UL and UR bias
inputs), which were repaired. LOS coil drivers received checkouts
and fixes. Single
arm locks have been achieved.
4K IFO (H1)
-----------
Full locking in common mode has resumed on the 4k. Some longer
locks have been achieved
and the ifo has been relocking in a fairly robust fashion. Work
continues to raise
the power on the AS port; the EO shutter has been checked out, and
the beam reducing
telescope is installed on the periscope.
The good, the bad and the ugly regarding WFS: a solution (good) was
devised for the
164MHz oscillations (bad) in WFS3 and 4. Ugly? Dangling
cables make signal
propogation difficult. See the elog for the mod to kill the oscillation:
http://blue.ligo-wa.caltech.edu/ilog/pub/ilog.cgi?group=detector&date_to_view=10/23/2002&anchor_to_scroll_to=2002:10:23:21:33:15-paul
Measurements of the 4k xarm free spectral range and transverse mode
frequencies
were obtained.
Since before S1, MMT3 has been prone to spontaneous alignment shifts.
Hopefully the
repair to a bad solder joint on the MMT3 coil driver board will clear
up these dives.
DAQ
---
Much booting and installing of code ensued as Alex(Fri), Dave and Rolf
made a series of
software and hardware changes. New ASC/LSC/MC2 code is in place
on both the 2k and the
4k ifos.
Commissioning:
Working on vibration characterisation for the ITMX optical lever and
Orlando is beginning to get involved. We intend to characterise the
source of the vibrations and see what remedial measures can be taken.
Worked with Andri to do test mass calibrations, see elog for
details. (Brian O'Reilly)
Measured the bandwidth (FWHM) of the new optically contacted Pre-mode
cleaners to be 1.2 MHz which agrees with the calculated value from
the
mirror parameters.
Tried locking x and y arms to understand the mirror misalignments when
locked. This was eventually traced to the run/acquire resistors that
were
damaged by high currents on the current driver boards. (Joe Kovalik)
CDS:
Installed new version of MATLAB on CDS network. Installed a Sun Blade
2000
in
the control room with flat panel monitors. Called the Sun Tech support
to
fix a
problem with cdrom mount. Sorting out Sync problems with flat panel
monitors
when interfaced with the overhead projector. Cleaned up some files
in the
web
area on london. Planning on doing some timing measurements at LLO.
(Chethan)
HEPI / LASTI
The first welded actuator was delivered to Stanford for characterization
last week, and we've almost completed the welding assembly of the second
article. We're doing so using the revised procedure sequencing
our
welding to minimize the heat buildup. Ordered and installed a much
simplified strain gage for the spring tester which will permit more
accurate measurements of force. Marcel and I designed a dual bracket
to
support the L4Cs on the LASTI BSC boot, which Marcel has detailed and
sent out for quotes.
ETF / Advanced LIGO pod bases
Marcel and I have designed a simplified base and flexure to support
the
GS-13 geophone on the ETF without benefit of a pod. Marcel is
detailing
that and will supply to Joe Giaime for production in the LSU Physics
shop. (Hammond,Kern)
LDAS admin:
1) Replaced 4 dead batteries in T3s.
2) Upgraded DB2 to 7.2 on LDAS-CIT.
3) Mounted some S1 RDS data to LDAS on Isabel's request.
4) Finished uploading calibration excitation data to LDAS.
LDAS data analysis
1) Debugging LALWrapper part of waveDSO.
2) Improving LDAS script for calibration calculations.
(Igor Yakushin)
GC:
Performed some maintenance on the tape backup software to change a
couple of the configuration items. This takes into account the
new file
server. Continued working on the firewall subnetting using the Solsoft
software. This software is pretty complex due to the nature of
what it
does and will take some time to master.
Looking into some network problems. The network became unbearably
slow
last night. This is further evidence that there is a problem
at LSU's
border router. Tom had noticed some problems since the weekend,
and I
saw the first evidence last night.
Installed a new video card in Marcel's machine since it was having
dismal performance using Solid Works. The card increased the
performance significantly, but I think he needs an upgraded machine.
Showed Bernie how to use his email account and set up a computer for
him
to use.
LDAS:
Started reading the firewall documentation for the LDAS VPN.
I will
start working on the configuration sometime in the next week.
(Shannon Roddy)
Seismic Array:
We are retrieving the seismic equipment borrowed from IRIS-PASSCAL
consortium. The data from the recorders was uploaded and the items
are now
being packed in preparation for shipment. The 6 wheeled vehicle has
proven
extremely useful in retrieving this equipment as conditions in the
array
field are still very swampy. (Coles, Langdale)
Jonathan Kern
The first
welded actuator was delivered on Tuesday to Stanford for
characterization.
We're in the process if installing it in the test
stand and
routing the hydraulic and control systems. Minor issues have
appeared with
some of the bleed valves but we've been able to fix those
by reworking
the parts in the machine shop. We expect to run the system
later today
or Thursday. The leakages reported last week in this unit
have been
repaired by rewelding some parts, and Loctite.This
would not
be appropriate
for LIGO's clean installation but will suffice for
testing.I
think we've identified the cause of the leaks reported last
week, and
much advice was sought within the project (Sibley, Worden,
Jones, Coyne,
Weiss) as well as the bellows manufacturer.Best
guess is
that we caused
the leak by an overly aggressive attempt to make sure the
bellows had
a solid weld.I'm now using a different
sequencing of our
welding to
minimize the heat buildup, and permit more time for cooling
prior to initiating
the next pass.The second actuator
is being
assembled
this week using the revised procedure.
Hydraulic
actuator testing on the 1 DOF test stand at Stanford was successful. The
actuator performed as expected.
We completed
the assembly of the 2nd actuator and found after all our
pains that
we have a single, small leak. The revised procedure called for sequencing
our
welding to
minimize the heat buildup. The bellows were individually
tested in
a fixture which permitted them to be pressurized to 90psi, and
then immersed
in water.Crude but effective in
the shop.This time we
took extra
care to stagger the welds and use minimum heat.The
unit
looks beautiful
but we ended up with a single, small leak at the
actuator plate
and as before it is leaking between the bellows and the
weld assist
band.
I'm ready
to state that we've received marginal welds from HYSPAN. We
couldn't have
taken any more care to pamper these bellows than we did
with this
unit.
I don't know
how many more options we have with these bellows. Gerry
suggested
an indium solder which I've looked into and did order this
afternoon.~1
week delivery
I had a brief
conversation with an engineer at Ameriflex
http://www.ameriflex.net/Pointed
him to some of our pictures.He
didn't understand
why HYSPAN didn't machine the rings, and e-beam weld.
Gave the opinion
that the poor tolerancing is contributing to our
problem.I'm
giving him a drawing and asking for a quote. They did
overnight
a sample bellows, which makes HYSPAN's look pretty sorry.
Engineer says
that they may make 2 week delivery.
Ordered and
installed a much
simplified
strain gage for the spring tester which will permit more
accurate measurements
of force. Marcel and I designed a dual bracket to
support the
L4Cs on the LASTI BSC boot, which Marcel has detailed and
sent out for quotes.
Ken
Mailand, Lee Cardenas, Rich Abbott
The pump station
has been disassembled and cleaned, for use with a glycerin mixture fluid.
Re-assembly
is partially complete, with the addition of a secondfixed
R/C stage which can be
valved on
or off. The pump station is being revised to eliminate the possibility
of any leaks.
Packing of
the Shipping Crate is in progress, one wood box to be shipped to MIT 10-25,
est. 5 days
to delivery.
some final
assembly req'd at MIT.
Rich Abbot
and Paul are working on the motor control box filters and need the motor
for testing,
if this is not ready in time, motor and control can be shipped ups.
Assembly of
the second resistor internal parts and packing a tool and parts kit the
week of 10-28.
To make the
final viscosity tests on the alternate fluid mixture of alcohol and glycerin,
as soon as
a tantalum material ball arrives late this week, or early next week, this
material
allows the instrument to measure more accurately in our range.
- At LLO this
week to install/test latest DSC software and finish timing
tests.Also,
trying to move the GDS router back into the ASC system, as
this router could take up too much time in the LSC.
1.Flavio
and I have been working on the ISS.We
have the inner loop functional under epics control in the 40 meter lab,
and are planning on closing the outer loop on Thursday.
M. Zucker, F. Nocera, R. Savage, P. Fritschel, R. Adhikari and R. Abbott,
completed draft design requirements and supporting model simulations for
upgrade to intensity stabilization servo (ISS) electronics. Specs are now
out for review.
2.2.Mohana is putting together all the pieces of the Common Mode Servo from the sites.She is testing one of the old boards for use by Rana at LLO (as well as a spare).She is also writing DCNs and starting the requirements for next generation boards with input from site technical staff.
3.3. Having electrical filters installed on the hydraulic pump motor controller to cut down on the EMI issues.
Jay Heefner reporting
FPGA Based
Timing Module
===============================
- Requirements
for the "new" variable delay timing module are being developed and should
be available for comment next week.
- The test
board for the FPGA has been received. Testing should begin 10/17.
LLO and LHO
DSC Installation
================================
-All
schematics have been updated to as-built and are out for final review.
-M.
Zucker, J. Heefner, P. Fritschel and R. Adhikari, iterated draft requirements
for LOS coil readout filter electronics. Specs to be released for review
shortly.
FPGA Based
Timing Board
==============================
- The requirements
document for the new board is 90% complete and will be sent around for
review by 10/23/02
- The prototype
board is assembled and the FPGA has been programmed. Right now I am working
on getting the board to the VMEbus. Hopefully it should be operational
by the end of the week.
Mike Zucker
Continued adaptation/interpretation of MIL-STD-461E (Electromagnetic Compatibility Testing) for proposed future application to LIGO electronics equipment qualification.
Mohana Mageswaran
CM Servo:
I worked on the CM Mode Servo Block Diagram
and included
the changes which I have got from
Rana. Now,
I am working on the Common Mode
Servo design,
and in the new design the entire MCL
section which
splits off from the common path does
not exist.
I am testing,
simulating and documenting the Common Mode Servo
Boards; A
spare board needs to be shipped to LLO ASAP.
Timing Board
I am also
testing and supervising the production of 10 of our current design Variable
Timing Boards for spares for the Observatories.
Distributed
the draft earthquake stop design requirements document to Dennis and Doug
Cook. Working on alternative earthquake stop design concepts.
The new osems are at the laser marking company, except 2 which were rejected for unacceptable coating. They should be completed by Monday, 10/28. They'll be sent to the coil winders after that.
Tests were conducted with full face mask/mask mounted blower and with half face mask/belt mounted blower, blowing into a desiccant-filled cannister, to measure the life of the desiccant before saturation. In both cases, the pressure drop of the cannister prevented adequate air flow for safety and the tests were scrubbed.
The remaining
two optically contacted pre-modecleaners were completed
with the PZTs
being aligned and epoxied into place.A
quick measurement of
the cavity
bandwidth, assuming a NPRO FAST actuator coefficient of 4 MHz/V,
was made revealing
a full bandwidth of approximately 4 MHz.After
calibrating
the FAST actuator, the FAST actuator coefficient was more like
1 MHz/V resulting
in the pre-modecleaner bandwidth approaching the design
bandwidth.
Joe Kovalik
has measured the full bandwidth to be 1.28 MHz for both of
the two optically
contacted pre-modecleaners.No particular
effort was
made to improve
the cavity visibility.The measured
value is consistent
with the design value.
I went on
studying tilt control reproducing the results in literature.
I checked
that the formalism of "perturbation theory" is equivalent to
the "modal
model" as the latter is used in Ligo.
I calculated
the error signal and corrected equation (23) in LIGO-P960024-A-D
(that is inconsistent
with the results obtained by perturbation theory
while my version
of that is consistent).
I made some
simulations for tilt with spherical mirrors and compared
the data with
the predictions of perturbation theory and the "correct"
modal model
and they agree within 0.1% so that I could implement the
control system
response to compensate for the amount of power that is
in an odd component and the suppression worked with the expected reduction.
OTF Lab.
(Bridge)
Contamination
Cavity # 1
Cavity has
the new test sample
65 % Glycerin
and 35% Ethyl.We have replaced the
cavity with new mirrors.
Alignment,
mode match andbeam scan in progress.We
have a small situation in
reference
of visibility.
Scatterometer
Scatterometer
instrument resurection is in process (worked on last week, not this week
due to other higher priorities).
New OTF
Lab at Lauritsen ROOM 38
Cavity #3
Reference Cavity still pumping down. Optical train ready.
Continue taking
RGA measurements.
Cavity #2
Test cavity
This cavity
still pumping, optical alignment and installation in progress.
Continue taking
RGA measurements.
no report
LASTI (Coyne, Mason, MacInnis, Mittleman, Ottaway, Shoemaker, Zucker)
---------------------------------------------------------------------
Infrastructure:
-----------------------------------
Staged equipment to prepare for NSF review and
for installation of hydraulic fluid supply lines into high bay (see
below).
PSL:
-----------------------------------
Kirk found that FSS/PMC summing box is costing us twenty degrees of
phase
at 1MHz. Paul S noticed a similar problem at Hanford and had given
us
suggestions on how to fix it. Jamie has received copies of the new
high
power low frequency intensity photo-diode cards and will begin stuffing
them.
EPI design and installation (Mason)
-----------------------------------
Plumbing has begun on the hydraulic lines from the pump room to the
HEPI manifolds mounted in the LASTI high bay. VCO o-ring face couplings
will be placed at all manifold connections. We will install the rough
plumbing up to the top of the four piers and do a helium leak check
of
the lines. The plumbers will then return to hook up the pump and
actuators when they have been installed
An additional degree of freedom was added to the HEPI design for easier
installation of the hydraulic actuators. Changes to fabrication
drawings are being done.
A modal analysis of the EPI housing with the 2 added stiffeners and
internal bracing was done. The first mode of the structure is
at 177
Hz.
MEPI Characterization and Test (Ottaway, Coyne, Mittleman)
----------------------------------------------------------------------
Last week we used single input single output to control corners of
the
support table. We could simultaneously engage corners of the piers
but
when the fourth was engaged the whole sytem oscillated. A transfer
function of the fouth corner was taken with the other three corners
controlled and uncontrolled. These two transfer functions were
significantly different above 20 Hz.
Prof Samir Nayfey's group have completed a low frequency, high resolution
modal survey of the MEPI system. We have discussed the results and
have
come up with four different control strategies to investigate and
evaluate.
We have now started to look at the optimum way to combine the sensors
to
perform modal control. We will soon close a loop on the horizontal
as a
first attempt at this.
Simulation and Modeling
This weeks items will be placed in the next report.
LIGO Data Analysis System
Software Systems (Wallace for Blackburn)
Charlton:
This week I mainly spent time fixing numerous problems with ingesting
of
data into the datacon from frames.
- time-series data coming from Proc structures was being ingested with
the wrong time-span, giving all zeroes in the data (this was the problem
Duncan encountered with the inspiral DSO)
- ingestion of frequency series was failing because the "sampleRate"
field was removed in Frame vers. 6. This was causing Greg and Scott's
jobs to fail (the "Scott's problem" PR). I've changed the ingestion
of
frequency series drastically so that now things are ingested as the
right type wherever possible ie. PSD's are ingested as PSD's, CSD's
are
ingested as CSD's etc etc. Formerly the individual sub-types could
not be
distiguished because the frame spec did not classify them.
- fixed some things in the frame output from the datacon so that the
fields are set correctly for each data type
Other activities:
- run datacon MDC tests several times on ldas-test and ldas-dev, with
no new problems so far.
- tested createRDS to some degree. The test is the following steps,
which has been automated into a single script:
1) use createRDS to downsample 40 channels from
several raw frames
2) use conditionData to read in and concatenate
the same 40
channels, and in the same job read in and concatenate the same 40
channels from the RDS frames
3) downsample the raw data and output the difference
between it and
the downsampled data read from the RDS frames.
- tested reading/ingestion of version 6 frames produced by createRDS
and by conditionData
Lei:
-metadataAPI: more fixes to streamline slave handling of database connections;
ran exception tests, deadlock tests to ensure metadata is not tied
up; updated
dev and test with database parameter upgrades recommended for multithread
processing; ran insertion tests on dev.
-cmonClient: revamped MPI jobs page to resemble the LDAS jobs page
with one
entry per job and action buttons; also improved LDAS job page data
structures;
miscellaneous fixes for resources, logs, nodes and job statistics per
problem
reports and user feedback.
-Testing: testing ligolw and metadata deadlock problem on ldas-pctest2.
-Other: Closed out some problem reports for cmonClient and metadataAPI.
Barnes:
- frameAPI: Helping Ed to test/debug new framecpp/frameAPI.
- wrapperAPI: Analyzed problem report #1706 filed by Duncan: problem
is
reassigned to the datacondAPI.
Hardware Systems (Wallace for Anderson)
Caltech
-------
Kozak:
1)HPSS: Continued to migrate data off of Redwood tapes. The success
of
this can be measured by the fact that I've actually gotten some
complaints from users who couldn't get their data in a timely fashion
(since the migration was using all the drives).
2)Worked on figuring out why the GigE/HPN connection to UWM isn't faster.
3)Spent some more time on the 2Gb FC stuff without any success.
Wilson:
1)Worked on BigBrother configuration for beowulf nodes.
2)Repaired memory problem on dataserver and dev.
3)Upgraded LDAS-cit to RH 7.3.
MIT
---
Keith:
1)Moved PIX / PC Raid / UPS into new rack
2)Cabled up new cluster machines
3)Added 16 nodes to cluster
4)Received/installed new batteries into failed UPS box
5)Working on revised GEO data
Livingston
----------
Shannon:
1)Started reading the firewall documentation for the LDAS VPN.
I will
start working on the configuration sometime in the next week.
Yakushin:
LDAS admin:
1) Replaced 4 dead batteries in T3s.
2) Upgraded DB2 to 7.2 on LDAS-CIT.
3) Mounted some S1 RDS data to LDAS on Isabel's request.
4) Finished uploading calibration excitation data to LDAS.
Hanford
-------
Mendell:
1) Made LHO S1 RDS frames for the GPS interval [714383936 714387616)
available to LDAS at LHO. This covers the same RDS frames visible to
LDAS-CIT.
2) Provided the usual support to users of the LHO LDAS system.
Otherwise, I have been concentrating on the periodic search.
Data Analysis Activities (Lazzarini)
Creighton:
-Teviet is preparing his presentation for the PSU data analysis focus
meeting.
Mendell:
1) Continued working with the PULG group to debug LALDemod. Reports
are
on the PULG web page, http://www.lsc-group.phys.uwm.edu/pulgroup/,
under
the S1 investigations link (which is password protected).
2) Continued to provided support to the GriPhyn effort and to the PULG
users of SFTs.
Weinstein:
- continued work on understanding the power DSO
- continued work on understanding and implementing
time dependence of response function for burst simulations
- continued work on developing burst simulation infrastructure
Yakushin:
LDAS data analysis
1) Debugging LALWrapper part of waveDSO.
2) Improving LDAS script for calibration calculations.
MIT Data Analysis Activities (http://ligo.mit.edu/ldas/
General Computing (Wallace)
MIT:
(Keith)
-NSF review activities
-Removed suspect win98 pc from network after MIT warned of
suspicious network activity
Livingston:
(Shannon)
-Performed some maintenance on the tape backup software to change a
couple of the configuration items. This takes into account the
new file
server.
-Continued working on the firewall subnetting using the Solsoft
software. This software is pretty complex due to the nature of
what it
does and will take some time to master.
-Looking into some network problems. The network became unbearably
slow
last night. This is further evidence that there is a problem
at LSU's
border router. Tom had noticed some problems since the weekend,
and I
saw the first evidence last night.
-Installed a new video card in Marcel's machine since it was having
dismal performance using Solid Works. The card increased the
performance significantly, but I think he needs an upgraded machine.
-Showed Bernie how to use his email account and set up a computer for
him
to use.
Hanford:
(Christine)
- Worked with Larry, Stuart, Albert and Greg troubleshooting the network
slowdown. Tried to connect the network into Greg's Linux laptop
and run
nttcp to determine if the network slowdown was on our router, on our
internal network or on the DOE esnet connection into our site.
The test
was inconclusive because we were never able to get nttcp running from
Greg's laptop. After the test the network was even slower.
Apparently
during the test something auto negotiated down to half-duplex causing
late collision errors and slowing the network to a crawl. A reboot
of
the Cisco router cleared the problem and we are now back to where we
were before the test. Meanwhile, Larry contacted Cullen at PNNL
and
Cullen now thinks that our slow down may actually be caused by a problem
with one of the routers on the DOE esnet.
- Worked with Fred on a remote access ssh and e-mail problem.
- Setup a PC and Sun computers in the new building Computer User's
room. Moved the color laser printer from the old building to
the new
building and set it up in the Computer User's room.
- Moved some computers around and setup a new computer for people who
are moving into offices in the old building.
CIT:
(Veronica)
- LIGO website: posted various updates. Edited and posted an image
for the
Press Information webpages. Updated Internal Bulletin Board.
Working on the interferometer sensitivities webpages for Albert.
- LSC website: posted a late-arrival presentation from the August meeting.
- CaJAGWR website: compressed and posted a video of Anna Nobili's talk.
Playing with the QuickTime Pro 6 editing a movie of a previous talk.
(Lisa)
- Installed gimp and related packages on Luna.
- Working on installing grace on Luna. It is compiled and installed
on
vega, but I'm still trying to resolve some motif related issues with
the
compile on Luna.
- Talking to Sun regarding the Crypto Accelerator card. They
are sending
the latest drivers out which will improve performance and upgrade openssl
to the latest version. A sun engineer will be helping me figure
out how to
fix problems with the simap/spop services.
- Worked on the backup system in the 40meter. When op140m reboots,
the
external hard disk wouldn't come up. I reorganized the scsi chain
and that
seems to have fixed the problem.
(Mike)
-Updated Bill Kells laptop with OS patches & software.
-Rebuilding a PC for the Synchrotron lab that had a hardware failure
on a
previous computer that was pulled from there.
The computer that I am trying to replace this with is an older PC that
is
having problems loading 2000 Pro.
I have a few more tricks up my sleeve to try and get this computer
to work.
-Reloading Dennis Coynes engineering workstation due to hacking intrusion
that
caused serious damage.
-Donna was having problems with her office scanner. I tried to get
this
working on Donna's and my own workstation by downloading updated software
and firmware but didn't have any luck with this. We ended up ordering
a new
scanner that installed with know problem and is working just fine.
-Reloading a Laptop that has been infected with a virus.
-This week I had a lot of onsite/phone user support that included mostly
software problems and a few hardware issues that I took care of.
-Reloaded my workstation from win98 to 2000 Pro due to OS problems.
-Loaded the LIGO s/w pkgs on to two laptops.
-Loaded Solidworks on to another PC.
(Larry)
-Spent time building documentation for Albert. Along that same line
the GC usage policy has been signed and is now on the net. We will
make
a more formal announcement after everyone returns from the NSF review.
-A great deal of time spent on network performance testing. Both
Observatories have had things going on as seen in their reports.
-Purchased a couple of computers which have arrived and Mike has installed
the local software loads.
-The Matlab licensing is now in progress. A few more things to work
out and
the paperwork should start in a few weeks. The new licensing should
help those
that have to go on travel and need the pkg.
-Rebuilt one of the servers. Presently, reworking the raid systems
on the units.
-Resolved a couple of printer issues.
-Resolved a couple of security issues. Two were machines that were
infected
with viruses and one was a false positive sent in from ITS.
-Worked on the CDS remote stations at CIT and started getting them
back up to
date.
-Went over a couple of property issues with Ed.
-Added a large number of e-mail locations to be blocked by the mailserver.
-Resolved a couple of web issues.
-A little more than normal in the amount of user support. Both local
and
those on travel.
From: "Mark Barton" <mbarton@ligo.caltech.edu>
This week I finally got the Australian interferometric sensor working
again and wrote up my notes on its operation into a report: T020163-00-D.
From: ctorrie <ctorrie@ligo.caltech.edu>
AdLIGO Suspensions
Mode Cleaner
Almost all of the parts to allow us to put the mode-cleaner back together
have now been delivered.
Janeen, Helena and I are planning to work on this from Wednesday the
22nd.
The travelling microscope is set up and next we have to set up the
optical lever Betsy help to install.
Phil Willems, Helena and I, with input from Glasgow, have been working on an adjuster for an eddy current damper. A single test unit of an eddy current damper adjuster is in workshop and should be available for testing in a week or so. Drawings and assemblies have also been completed.
I have been working on updating some of the assembly parts and drawings for the mode cleaner suspension and with Russell and Mike Lloyd in Glasgow we have been looking at drawing standards and templates for the Glasgow group.
In the Synchrotron laboratory we now have a working drill press. This
will be kept locked although anyone is welcome to use it. I will put the
keys for this and the various toolboxes and cabinets we now have in a lock-box
with a combination code. I will let those interested know the code as soon
as I have it set up.
From: Janeen Romie <romie_j@ligo.caltech.edu>
AdLIGO Suspensions
Worked on GEO questions for their PPARC meeting.
Working on mode cleaner design tasks. MC height adapters should be
delivered 10/30.
LIGO I
Distributed the earthquake stop design requirements document to Dennis
and Doug Cook. Working on alternative earthquake stop designs.
The new osems are at the laser marking company, except 2 which were
rejected for unacceptable coating. They should be completed by Monday,
10/28. They'll be sent to the coil winders after that.
From: Peter King <pking@ligo.caltech.edu>
2.2 AdvLIGO PSL
I have been working out a few details with Benno
Willke and Andreas
Weidner about the up-coming visit to the University of Hannover.
Providing
some hardware information such as EEPROMs and burners. In addition
to the
technology transfer kick-off we will provide them with an extra set
of
EPICS boot ROMs for the Motorola processor.
Adv LIGO Suspension Prototype
Jay Heefner
- The anti-image board layout is complete and has been sent to the
board house. Boards are due back by 10/25/02. The connector adapter board
used to mate the anti-image board to the Dspace is complete and ready.
- The schematic for the whitening board is 90% complete. Layout should
begin by 10/18/02.
- The Rev C Anti-Image Boards have been received and are being stuffed.
We should have one tested by 10/31/02. We made a few extra for test on
LIGO.
For additional information about this report, contact sanders@ligo.caltech.edu