|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday September 9, 2002 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
General Computing has an action to update CR-010012
Executive Committee only 11:30 - noon
Topics:
Special Items: S1 performance summary from Fred, Mark and Albert
no report
LIGO Operations--Administration
There was a site teleconference held on Thursday, September 05, 2002. The following issues were among those discussed:
Proposed Travel Rules--Caltech has proposed new travel policies that would affect contract employees, visitors, and new hires. It is our opinion that these new policies would seriously affect LIGO's ability to conduct business. The issues will be raised with the Division Office.
Livingston Staging Building--Expecting a more definitive report this week concerning causes and proposed corrective action for the HVAC problems.
A job walk for the Time and Material contract for partitions in the Staging Building was held on Tuesday, September 3. Proposals are due on September 10th. The target is to have a contractor on board by the end of September.
Hanford Laboratory Building--Otto is on vacation. The installation of the audio/visual systems is at least close to completion. Expect to begin moving people in soon.
Bid for traffic control came in very high. Looking at alternatives.
All Terrain Vehicle for Livingston--Expect to have three estimates and issue a PO by tomorrow or Monday.
Property--Ed Chargois previously reported that NIH in Bethesda, MD might prove to be a good source of almost new furniture for both sites. He has been told that they will have good furniture for the Hanford building by the end of next week. The plan is still to provide pictures.
Use of Auditoriums by General Public--two issues still open: requires notification of NSF DGA of intentions, and the NSF should inform the DOE of intentions. Outreach related activities should not be a problem. Ed Jasnow has a new action (#114) to prepare an email for NSF.
The list of current actions revised to reflect
the status of open actions assigned through September 05, 2002 may be found
at ACTION
LIST.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
ACTIVITY
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA .
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
CONSTRUCTION:
SUPPORT (Baldon, Torres, Lloyd, Tischler)
>Irene Baldon
There was no Advanced LIGO Project Controls meeting this week. The Advanced LIGO MRE Proposal continues to have the Highest Priority. Continuing the development of the Cost Estimate.
Posted data with budget comparison of R&D vs. Cost Book as requested by David Shoemaker.
The following is a summary of status by sub system:
We have reviewed the Annual Report against the
requirements in the Cooperative Agreement. Items that need to be
addressed include:
1) MIT has sent me electronic versions of their
proposal. I will be incorporating these.
2) Fred Raab has sent me an Outreacg section
for Hanford. I will be including this.
3) I will add sections for actual costs, staffing,
PAC meetings, etc.
I have prepared a budget model for FY 2003.
All reserve has been allocated in Planning Packages for items that have
been identified on the contingency liens list. We will also establish
separate budget lines for items budgeted but not yet purchased in FY 2002.
The following change requests have been submitted:
| CR-010012
Revision B |
WBS 1.4.4.1 | Closeout Construction Budgets for Initial Computer Equipment Complement at the Sites | P. Lindquist |
| CR-020009 | OPs 1.3 | Digital Common Mode Servo to Mode Cleaner Path | D. Coyne |
| CR-020011 | OPs 5.15 | High Power Test in Suspended Interferometer (Gingin) | D. Coyne |
| CR-020012 | OPs 1.6 | Additional Funds to Complete 40-Meter Facility Upgrade | A. Weinstein |
| CR-020013 | OPs 1.3 | Pentec VME Digital Signal Processing Boards | D. Coyne/J. Heefner |
I propose to present CR-020009, CR-020011, CR-020012, and CR-020013 during the next Executive Committee Meeting.
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
No report this week.
Summary of Commissioning Activities at LIGO Hanford Observatory (compiled
by F. Raab)
-------------------------------------------------------------------------------------
(see ilog for details - if it's not in the ilog, it didn't happen...)
Science run continues. H1 has been improving in its "science" cumulative
duty factor, now 58% compared to about 42% in last week's reporting. We
expected we would see some improvement over the holiday weekend with lower
seismic noise, but H1 is behaving better during noisy weekday times as
well. We have no wisdom to share about why this improvement has occurred.
The cumulative "science" duty cycle for H2 remains at approximately 72%.
The lock-holding record, exceeding 21 hours, is currently held by H1. We
were all promised beers by a certain detector group leader if we could
keep H1 in lock for 24 hours straight, leading to great drama as the interferometer
approached the 20-hr lock mark, but we did not make it on this try. (Rumors
that lock was broken by a long-distance phone call to the LVEA from Australia
were not supported by the data.)
We have been tracking associations between loss of lock on either interferometer
and transients recorded by seismometers. In one class of events, we see
a transient in only one building's seismometer. For example, a lock loss
in H2, but not H1, might show an associated transient in the MY seismometer.
This would be consistent with a vibration source local to that building.
It is unclear what causes these events. We have made a positive identification
of another class of lock losses associated with turn-on transients of the
well pump out at EY. We see a consistent trend where the FMCS records pump
activation, H1 immediately drops lock coincident with a seismic transient
at EY and, six seconds later, we get a seismic transient at MY and H2 drops
lock. Since run initiation, there have been about sixty such seismic event
pairs, not all leading to lock losses. Masahiro Ito is now working up the
efficiency of these events driving lock losses. In the meantime we have
shut down the irrigation system - a major water user on site - and we are
planning to charge the water storage system outside the prime lock times
for Livingston, in an effort to optimize triple-coincidence times.
The strangest phenomenon to date is a regular "heartbeat" developed
by H1. On microphones the dominant sound of H1 heard yesterday was a "thump-thump"
at 88 beats per minute, beginning after an interferometer alignment on
Tuesday. This remained constant until a magnitude 4.7 earthquake in the
Queen Charlotte Islands occurred during the early morning hours of Thursday.
The earthquake knocked both IFOs out of lock. H1 recovered once the shaking
subsided, but required some realignment. Once the realignment was complete
the 2-thump beat had become a 4-thump beat. The "heartbeat" is obvious
in calibrated spectra, but we do not see it causing a big change in ZGlitch
or SenseMon reporting. Without visibility into results
from on-line DSOs in the control room we are unsure whether we should take
invasive measures to diagnose and stop the "heartbeat", or just let H1
run unmolested.
Interferometer: We are preparing for installation of the DSC's beginning Sept. 10. A significant activity that needs to be completed prior to this date is the modification of the universal dewhitening boards. This is a labor intensive activity involving three or more staff continuously. There were two additional modification that needed to be made to all the universal dewhites for the digital suspension installation. This involved replacing some caps and op-amps on every board. That work is complete. Modification to the los controllers is nearly complete. The six that we need for the installation are done - only the two spares are left. I have purchased and received new linear power supplies for the rework of the end stations. Interface cables that connect the new suspension racks to 1X22 are complete. Basically, we are ready to start on Tuesday morning. (Wooley)
LDAS system administration:
1) Sent 25 tapes with S1 raw data to Caltech, 7 tapes with S1 RDS to
MIT
and 7 RDS tapes to UWM;
2) Cleaned /frame10 to make room for RDS, together with Greg archived
old data from /frame10.
3) Troubleshooted LDAS after Wednesday's power accident.
LDAS data analysis:
1) Writing wave DSO. gor)
(Igor)
GC:
* Fixed a problem with the dhcp server today.
* Most of this week has been spent pulling Cat5 cable into the
conduit in the new building.
* ordered & received a symantec VPN server to test on GC
* created several accounts for the elog
LDAS:
* Helped fix a power problem on the beowulf. There was an
outlet that was shorting, which caused 1/4 of the nodes to
lose power. The repair involved shutting down the entire
beowulf so breakers could be turned off. Igor helped reboot
the beowulf.
--
Shannon Roddy
HEPI / MEPI / LASTI Completed characterization of 8 machined springs for the LASTI HEPI installation. Hastily packed and shipped 200# of springs for Friday delivery to MIT. Made 2 more purchase requisitions of MIT for balance of machined parts and assembly of initial 2 units. Ordered 8 additional load cells and panel displays for HEPI. Still working with Power Dynamics to close out open items on spring tester. Hammond, Kern Optics/Laser Safety Playing catch-up with LLO paperwork. The ophthalmologist I have been using to dispense the laser prescription glasses has closed his dispensary, so have made arrangements to deal directly with the lab for single vision users. Working to find a oculist who will measure and fit bifocal users. Updated registered user list with new employees. (Kern)
The first set of eight springs has been characterized and have been shipped to MIT to be installed. I am still looking at the collected data, but my preliminary findings look good. I have ordered four more springs to make a complete set of springs (8) because it appears that the coil springs were in adequate. The resolution on the load cell for the spring cell is roughly 50 lbs. The resolution advertised by the manufacturer is in the magnitude of 10/1000th. I have asked Russyl Wooley to trouble shoot and try to correct the problem. Russyl is quite busy with the upcoming installation, but promised to take a look at it before the next Tuesday. I have also solicited help from Russyl for the GS-13 installation into the pods (along with the Lockdown device). I will need help with the mechanical installation as well. This effort is to expedite the Streikheisen sensors as well as the GS-13s so they can be married into the ETF prototype at Stanford. My main effort has been to marry the latest and greatest HEPI unit into the EPI unit provided by Ken Mason at MIT. I am still finding mating problems but feel that this exercise will prevent the possibilities of installation problems. (Marcel Hammond)
Other: LSU Chancellor Mark Emmert toured LIGO Thursday afternoon. He was accompanied by Profs. Joel Tohline, Gabriela Gonzalez, and Joe Giaime. Logging activites and resultant ground motion are intense (<140 cnts in the 1-3 Hz band). Cutting is occurring simultaneously at the South end station and near the vertex.
System tests
are finished, a motor control circuit is being fabricated and should be
complete by week of9-16.
Pressure sensors
may not require additional isolation outside of the servo control loop,
howeverisolator bushings will remain
for any future testing at MIT.
The manifolds
[5] with their mounting bases are ready for shipping to MIT the week of
9-2.
Actuator fabrication continues. All machined parts are expected by early October in Livingston for assembly and He leak testing. Bellows are already available.
Jonathan will go to Stanford in the next week or two to work with Amite to refine a procedure for servo valve balancing and calibration. Twelve servo valves will be balanced and calibrated. These valves are needed for the hydraulic actuators for the LASTI prototype.
The HAM was supported completely by the MEPI offload springs and it was found that the table could be leveled accurately (< ~50 microrad error) and set in vertical position accurately (< ~50 microns), but the table shifted laterally by ~1 mm. The lateral shifts can in principle be taken out by floating the EPI on the pneumatic lifters and sliding the EPI on top of the piers, or by adjusting the springs pairs to have a differential spring load, or a resulting lateral load. However the cause of the significant lateral shift is almost surely a result of the poor dimensional control on the wound coil springs.
The counter-wound coil springs installed on the HAM MEPI system at LASTI were found to be binding due to large dimensional errors. A large lateral load (~50 lbf) was required to even bring the springs into alignment sufficient for assembly. Installing spherical washer sets at both ends of the spring assemblies significantly improved the situation. A decision was made to install the machined springs onto the HAM MEPI instead of trying to work with the would springs; The final spring design is machined – we will not pursue coil springs for the production systems. The machined spring set will arrive at LASTI 9/6 and be installed 9/6 & 9/9. An additional set will be fabricated for the BSC HEPI system. This set is expected to be available in ~3 weeks (well before the hydraulic actuators are available in late October).
We have vented the LASTI vacuum system and are preparing to go into the HAM chamber (9/7) to put the SOS onto their stops and place a STS-2 seismometer on the table. The system will be left at atmosphere for some weeks as we characterize the system and develop control laws.
Brian Lantz has issued another preliminary release of the BSC HEPI matlab/simulink model. This model also has a simple SISO controller. The basic architecture and array structure are now thought to be stable. Rich Mittleman is in the process of adapting this model to the HAM MEPI application. Dave Ottaway is adapting the Hytec HAM stack model to the HAM MEPI application for incorporation into Rich’s version of the matlab model. Dennis has developed a HAM/EPI elastic support structure model and imported the mass & stiffness matrices into matlab with the intent of mating this flexible support model to the stack model.
Obtained quotations
for shielded racks, linear power supplies, EMI filters, shielded crates,
and module shielding kits.Assembled
a budgetary cost estimate for retrofitting site electronics hardware and
wrote supporting text documentation; these are currently under review.
Rich Abbott reporting
1.Got
together stuff for the digital suspension installation and made travel
plans to go help and learn.
2.Finished
pcb layout of motor speed control servo and pressure readout module.Boards
arrived on 4 Sept. and are about 70 percent stuffed.
3.Wrote procedures to allow the release of the hydraulic valve driver modules.
Jay Heefner reporting
·DSC
Upgrade: Preparations continue for the DSC upgrade of the LHO and LLO IFOs.
Final module testing and shipment should be completed by 9/6/02.
·Pentek
Interface: As part of the DSC upgrade a generic whitening interface for
the Penteks has been designed and built. These modules are used on the
MC2 path but can also be used to input and whitening signals into Penteks.
It may come in handy in the future.
·FPGA Timing Module: FPGA design is complete and waiting on board layout and fab.
Sander Liu
Shipped four
sets of micro-seismic signal processors ( remote interface + post processor)
to LHO and two sets to LLO.
Delivered one EO Shutter Controller to 40M.
NPRO #259
was put through its paces with the electronics destined for
the University
of Hanover.Without the ability to
control the slow
actuator -
due to having to cable up the NPRO power supply to the wiring
harness -
the laser remained locked overnight to the reference cavity.
Some of the
field wiring will have to be replaced as there seem to be at
least one intermittent connection (to the phase-correcting Pockels cell).
OTF Lab.
Contamination
Cavity # 1
Cavity still
locked and continue taking ringdown measurements (second test of mineral
oil).
New Lab
at RSE
Cavity #3
Reference Cavity still pumping down.Optical
train ready.
taking RGA
measurements.
Cavity #2
Test cavity
This cavity
still pumping, waiting on optical train installation and laser alignment.
Labview programing
for ringdown measurements still in progress by Liyuan.
In the meanwhile,
I have requested from Rick Savage the previous lab view card
NI AT- MIO-16XE-10that
we had at PSL.If I get it, then
I'll be saving some $$$.
I have finished
the wiring and installing of the laser warning signal. (It needs Garilynn's
approval).
The wallsthat
will separate the laser enclosure from the visiting area are fixed in place
and completed. Installing power strips around the two optical table are
in progress.
Misc... tasks, placedsome orders for the PSL Lab.Electrician have changed the light switch in the room.
no report
LASTI (Kern, Goldman, Harry, MacInnis, Mason, Mittleman, Ottaway,
Rollins, Shoemaker, Zucker)
=============================================================
VACUUM SYSTEM (Zucker)
We have vented to put the test cavity suspensions on their stops
and to permit temporary installation of a seismometer in HAM13 to facilitate
end-to-end characterization of the MEPI system (see below). Since the system
has been at hard vacuum for over 3500 hours, we
took a residual gas spectrum before venting. With an overall system
pressure of 3.3e-7 torr (dominated by water vapor), we can set an upper
limit of about 1e-11 torr for possible hydrocarbon fragments. This
limit is bounded (we think) by generation of HC signatures in the RGA itself.
The corresponding flux, if this limit were attributed to the
LASTI chamber and tube walls (surface area 2e6 cm^2), is about 5e-15
torr-liters/sec/cm^2.
EXTERNAL PRE-ISOLATORS (Hammond, Kern)
Completed characterization of 8 machined springs for the LASTI HEPI
installation. Hastily packed and shipped 200# of springs for
Friday
delivery to MIT. Made 2 more purchase requisitions of MIT for
balance of machined parts and assembly of initial 2 units. Ordered
8 additional load cells and panel displays for HEPI.
Still working with Power Dynamics to
close out open items on spring tester.
MEPI INSTALLATION (Mason, MacInnis, Kern, Coyne)
The spacers used to maintain the gaps between the electromagnetic coils
and fields were removed. The HAM stack is now floating on the pre-isolators.
The springs are stiff and maintain position
as monitored with the optical lever. We were able to bring the height
and level of the table back to its original position easily. Forces on
7 springs were within 5%. The eighth spring had been overstressed during
testing and appears to be causing us problems. Slight adjustments appear
to cause large fluctuations in load. With a lot of effort we were able
to bring this spring within 10% of the others, however when acted upon
by the actuator it might cause trouble in operation.
#MZ:
on later inspection it was found that the
errant spring's adjustment
screw was jammed up due to its excessive length;
a workaround is in progress.
We wil be opening up the chamber today to place the optics on their
stops.
MEPI MODELING & DYNAMICAL TESTING (Mittleman, Ottaway)
The electronics for the HAM magnetic pre-isolator are mostly installed,
lacking one cable to connect the DSpace and the raw power supply, which
should be finished today. The DSpace PC has been installed and
the DSpace system will be tested as soon as the missing cable is installed.
The DSpace stepped-sine analyzer has been tested on the quadruple pendulum
and should work on the HAM system.
Brian's Hydraulic-BSC model has been morphed into a magnetic-HAM model
and is ready to be loaded with the more realistic M-K matrices from the
stack analysis.
Simulation and Modeling (Bhawal)
Mirror rotation simulation
------------------------------
(Hiro) The rotation of the mirror is simulated by 6 DOF motion of the
ground,
passed to the top through 6x6 transfer functions and via suspended
mirror
model. At the last LSC meeting, it was pointed out that the coupling
of
translational mode to table yaw motion can be the major source of the
table
yaw motion. This coupling comes from the asymmetry of the stack and
is now
neglected in the simulation. Virginio will look into this issue ...together
with Sany.
Tilted cavity study
------------------------
(Hiro) The analytic solution of the time evolution of fields in a FP
cavity
with tilted mirrors is obtained. It is being compared with the e2e
simulation result to understand the physics meaning.
Code development and maintenance
----------------------------------
(Matt) Continued development of new E2E field model.
(Biplab) Change of yaw in common mode in recycling cavity was generating
wrong result in dark port. The bug was traced and the following files
were
modified to correct and improve the implementation: align_matrix.*,
sum0x0.*,
recycling_sum.*.
(Hiro) Code management: Because alfi is JAVA based and does not share
c++
codes with AdlibMM (the simulation part), ALParser (a CVS repository
keeping
codes shared by alfi and adlib) has become obsolete. The next release
is
expected to be made gcc 3.1 compliant by doing minor modifications
to make
the code more C++ standard compliant.
Alfi
-----
(Bruce)
- Continued work on the parser for better error messaging.
(Melody)
- Continued work on the automated tester for alfi5.
LIGO Data Analysis System
Software Systems (Blackburn)
Jobs are now being sent regularly to the LIGO site LDAS systems. A
summary
of the jobs sent based on ldas command type is show in the table below.
Most
failures are due to frames not being available. However, a very few
are due
to other issues which will be discussed below. Specifics of the failures
have been summarized to LAL-DISCUSS on a regular basis this week.
A summary of jobs sent to the sites during S1.
Interval: 08/23/02 12:00:00 PDT - 09/05/02 10:00:00 PDT
_______________________________________________________________________
|
|
||
|
|
| LHO
|| LLO
|
|
|__________________________||__________________________|
| User- |
| | ||
| | |
| Command | Submitted | Failed |
% || Submitted | Failed | % |
|______________|___________|________|_____||___________|________|_____|
|
| |
| ||
| | |
| createRDS | 14225 |
157 | 1.1 || 14132 | 32
| 0.2 |
| dataPipeline | 16044 | 1714 |
11 || 5658 | 534
| 9.4 |
| inspiral | 4468
| 732 | 16 || 676
| 2 | 0.3 |
| power |
4265 | 105 | 2.5 || 1802
| 6 | 0.3 |
| slope |
3676 | 381 | 10 ||
1638 | 326 | 20 |
| tfcluster | 3630
| 491 | 14 || 1538
| 196 | 13 |
| getMetaData | 6839 |
22 | 0.3 || 4055 |
7 | 0.2 |
| putMetaData | 22520 |
12 | 0.1 || 9027 |
12 | 0.1 |
|______________|___________|________|_____||___________|________|_____|
|
| |
| ||
| | |
| All Jobs | 59672
| 1910 | 3.2 || 32877 |
587 | 1.8 |
|______________|___________|________|_____||___________|________|_____|
There was a power outage at the LIGO Livinston site which abruptly shutdown
the LDAS Beowulf nodes. This required completely shutting down the
LDAS
system at Livingston during repairs to electrical circuitry. Several
issues
ensued from this that required correcting a permissions problem in
the IBM
DB2 server and restarting the metaDataAPI and mpiAPI. At this time
LDAS at
Livingston appears to be fully functional again.
After a careful code read of the frameCPP version 6 code base, a decision
was made to make a more coherent effort to capture the requirements
in the
new specification by going back to the drawing board on the code
development. This is not expected to delay the next release of LDAS,
though
it does push the limit of when new code can be added before a release.
Stay
tuned for timeline developments.
New asynchronous mpiAPI - to - wrapperAPI communication procedures were
implemented in the wrapperAPI's master. In addition several other
optimizations of communications were added to decrease even further
the
serialization of code blocks. The time-frequency "bothD" enumerated
type was
tested and shown to work properly.
A set of test scripts have been completed and used to test the use of
state
data objects in dataPipeline commands. This is now working again. State
data
objects contain DSO defined information from one job that can be reused
by
future DSO jobs.
It has been identified that the secure webserver used to administer
applications for LDAS accounts can fail with error messages on a regular
basis when used from the LIGO Observatories over the slower networks.
This
is in general not an issue since virtually all administration takes
place
locally here at CIT, but we are looking to see if there is a fix.
Several new users applied for LDAS users accounts this week. We currently
have 61 authorized users of the LIGO LDAS systems.
A port of LDAS to the new Solaris 9 Operating System has been underway
this
week. It looks like the included loader will not work with LDAS and
we will
have to continue to rely on the GNU loader on this OS.
A new operator and emergency socket handler was added to the TCL layer
of
the genericAPI . This has significantly improved the reliability of
message
transmission between APIs. A similar effort to rework the assistant
manager
socket handler is underway but has not been fully debugged yet.
The new job request handing layer in C++ for the frameAPI has greatly
improved the throughput of the frameAPI. We are already seeing a 1.5X
improvement in the overall system throughput from this. It has also
allowed
the job ordering code to be removed as it only interferes with performance.
Hardware Systems (Anderson)
Caltech
-------
(Dan Kozak)
* HPSS: continued migration of files off of Redwoods. Did a large
batch
of project/account creations.
* SAM-QFS: Started archiving S1 data. Sorted out StorageTek maintenance
(with Gina Salone's help) and got broken 9940 drive replaced
and
functioning. Got another 60 day extension on our SAM-QFS
evaluation
license.
(Al Wilson)
* Did prep work for the raid systems for Caltech.
Installed, Cat 5, Fiber, Racks, etc. Also tested the Kickstart
script
for the systems.
* I configured Big Brother to run properly on the CIT system. Minor
setup
files problems. I will be adding node monitoring in the near
future.
(Stuart Anderson)
* Started archiving the full S1 data: 2 copies into HPSS, 2 copies into
SAM-QFS, and 1 copy over Internet2 to UWM. This is pushing the
responsible
SB1000 to its limits and slightly beyond.
* Identified and copied 1hr of coincident S1 data from LHO and LLO to
be used in all LDAS systems for software testing and validation.
This
is a subset of the S1 "playground" data identified by the burst
group.
MIT
---
(Keith Bayer)
* Troubleshooting PC Raid unit (timeouts from drives).
* Installed 3dm web based raid mgmt utility.
* Continuing to load S1 data (RDS) from sites.
* Continuing to create AS_Q channel frames from E7 reduced frames.
* Built/started webserver on lancelot for LDAS/DMT users.
* Completed burntest of PC Raid unit.
Lazzarini: I am working with David Shoemaker to develop a plan to improve bandwidth between LIGO MIT and the rest of the LIGO WAN.
Livingston
----------
(Igor Yakushin)
* Sent 25 tapes with S1 raw data to Caltech, 7 tapes with S1 RDS to
MIT
and 7 RDS tapes to UWM;
* Cleaned /frame10 to make room for RDS, together with Greg archived
old data from /frame10.
* Troubleshot LDAS after Wednesday's power accident.
(Shannon Roddy)
* Helped fix a power problem on the beowulf. There was an
outlet that was shorting, which caused 1/4 of the nodes to
lose power. The repair required shutting down the entire
beowulf so breakers could be turned off. Igor helped reboot
the beowulf.
Hanford
-------
(Greg Mendell)
* Continued, with Igor, the running of tapecontrol scripts to archive
raw frame data for S1; 50 tapes have been sent to Caltech from
LHO,
45 from LLO.
* Continued, coordinating with Isabel and Igor, running of tapecontrol
scripts to write RDS output from LDAS to tape. Currently
tapes are
written simultaneously for UWM and MIT and each site has received
~9
tapes with data.
* Ran scripts to copy preS1 injection data from the framebuilder disk
cache to ldas disks to preserve this data on disk at the sites
after
S1. (The data was previously archived to tape.)
Continuing to monitor
disk space for RDS data and injection data.
* The new 2 TB Raid Server at LHO has passed the burntest.
Data Analysis Activities (Lazzarini)
Data Analysis Activities at MIT
===============================
Laura: worked with Alan in real time plotting of bursts DSO outcome-
check
out LDAS-MIT web page
Erik: worked with Alan on new threhold investigation for POWER.
Laura+Erik: prepared S1 analysis outline as requested by Finn/Saulson
and communicated to the Bursts group
Keith: produced E7 RDSs with AS_Q channel only- E7 full frames will
be deleted soon.
Igor:
LDAS data analysis:
1) Writing wave DSO.
Weinstein:
- Set up, and began running three burst DSOs on three IFOs
online during S1.
- After initial problems, all 9 sets of jobs
are running smoothly.
- Assembled web status page and instructions:
http://lancelot.mit.edu/~ajw/burstdsos.html
- Continuing to monitor and improve the online running
and monitoring system.
Data analysis activities (Shawhan)
* Debugged the "loop" scripts for the burst and inspiral on-line searches
now running at the sites.
General Computing (Wallace)
MIT:
(Keith)
-Created AIT-2 tape of julien directories and sent it to Caltech
-Patched a number of Windows machines
-Investigating VRVS audio
-Placed order for CAD PC + software
Livingston:
(Shannon)
- Fixed a problem with the dhcp server today.
- Most of this week has been spent pulling Cat5 cable into the
conduit in the new building.
- Ordered & received a symantec VPN server to test on GC
- Created several accounts for the elog
Hanford:
(Christine)
- Bought Visio to do drawings for the IT Security Plan document.
- Started processing to replace a broken monitor that is still under
warranty.
- Modified the cisco router access list to allow some new computers
access to the trinet seismic computer.
CIT:
(Mike)
-Nothing to report. Still at class for the week.
(Veronica)
- LIGO website: posted various updates. Reworked a webpage on LIGO
correspondence templates and standards, to be posted along with the
new
templates.
-Posted updates at the Internal Bulletin Board.
-Working with the DCC on various related issues.
-Meeting with Gary and others regarding the final design of LIGO handout
folders.
- LSC website: posting remaining LSC meeting transparencies as they
arrive.
-Edited MOU lists for several institutions.
-Contacted Caltech Digital Media Center w.r.t. digitising the VHS tape
of
the public lecture given at the August LSC meeting.
-Updating the LSC Talks webpage.
(Lisa)
- More user support on managing mailman mailing lists.
- Began writing a MySQL database for the inventory data.
- Spent time working with Mick on the tape restoration project.
- Still trying to get a response from the Caltech Telephone Office
regarding
converting the 800 number of the modem pool to ISDN.
- Did Monthly backups.
- Misc. user support.
- Worked on a couple of PC's and e-mail issues.
(Wendy)
- Checked out a few computers for viruses, noise, etc.
- Restored some more tapes.
- Installed programs on various PC's for users.
(Larry)
- Worked a number of procurements. Mostly computers for other people
and misc.
items for different groups. Also, spent time working on the p-card
reconciliations.
- Worked a number of PC issues including getting PC's for lab use.
- A major thorn was the VRVS system being played with and all of the
settings
and hardware being disabled. We are going to purchase a new system
to be
dedicated for the VRVS system which will have limited access.
- The general paperwork and user support. A lot of assistance for SURF
students.
(Bruce)
- General Ilog Maintenance:
- Dealt with many requests for additions and some changes to
existing logs.
Mode Cleaner
Mike Plissi and I have been testing and characterizing the 2 sets of
cantilever blades to be used in the prototype suspensions. Virginio, Mike
and I have been discussing some of our preliminary results.
On Friday we ran a successful test assembly of a triple pendulum without
the upper blades and support structure.
Janeen and Helena have started to assemble the cage structure and its
associated parts and we are almost ready to assemble the upper blades.
New and edits to existing drawings are being kept up to date as much
as possible, as are changes to the drawing tree. The next stage to aid
this is to get the laptop set up with SOLIDWORKS and /sirius access.
Photographer
From next week a student photographer will
start work for LIGO for ~ 2 hours / week. Over the next 10 weeks or so
he is going to photograph and document on a LIGO web-site the fixture and
assembly procedures for the first advanced LIGO prototype. However, he
will be available during this time if others are interested. For now please
send me an email with your request at ctorrie@ligo.caltech.edu.
From: Bill Kells <kells@ligo.caltech.edu>
This last week has been spent on the following AdL
optics issues:
1. Reviewing the optics design and its consequences of
the flat top beam refinement (aka
MH= Mexican hat). This, in advance of the (telecon)
meeting on the subject at MIT.
I will have several comments and analysis to present
on this. Have had discussions with
Erika, and Garilynn on this.
2. Clarified the issue of AdL (sapphire) AR surface
micro-roughness with D. Reitze and Garylynn.
Turns out that The spec we were
carrying for this is
[way] too stringent and the Goodrich
compensation polish is not marginal in
this respect.
So it seems clear that with the level of
homogeneity we could reasonably expect
plus demo'd
compensation, the unique problem with
sapphire is bulk absorption.
3. Completed the long on the back burner analysis of
Carrier matching into a (AdL) double cavity with
PRC distortion (a la thermal lensing). Such a PRC
distortion produces a net mismatch of input beam
power to FP arm power (which is what counts for GW
detection) which is about the same (within
factors involving Guoy phase of order 1) as the same
distortion would within the [stable] arm itself.
Will be writing this up in detail shortly.
From: Peter King <pking@ligo.caltech.edu>
2.1 Engineering and R&D
NPRO #259 was put through its paces with the electronics
destined for
the University of Hanover. Without the ability to control the
slow
actuator - due to having to cable up the NPRO power supply to the wiring
harness - the laser remained locked overnight to the reference cavity.
Some of the field wiring will have to be replaced as there seem to
be at
least one intermittent connection (to the phase-correcting Pockels
cell).
2.2 AdLIGO PSL
All the electronics modules destined for the University
of Hanover have
been tested except for the 21.5 MHz RF photodetector, as this will
require
a minor re-organization of the wiring harness relating to the pin-outs
on
the DB15 connector used. The only other board not tested is the
Motorola
IOC, since this requires a little fiddling around but should be trivial.
Of
the commercially-sourced boards, the VMIC 3123 failed on boot.
A spare board
will be tested later this week.
Suggestions for various tests to be performed on
the high power laser
technology demonstrator systems are being made. The idea is to
converge on
a standard set of tests to apply to each laser and then with the results
make the decision as to which approach to adopt.
From: Janeen Romie <romie_j@ligo.caltech.edu>
AdLIGO Suspensions
Superior Jig will deliver the balance of the blades, 8 small MC blades,
on Thursday afternoon or Friday morning. Mike Plissi and Calum have been
testing and characterizing the blades. They have been assembling the MC
prototype suspension. Bob Taylor has started soldering the components to
the circuit boards for the hybrid osems. The osem bodies, with coils wound,
are due here from Glasgow this week. Bob will bake them as soon as they
come in so he can assemble the boards in them next week. After that, he
will continue on with the LIGO I osem fabrication to support the MC suspension
and the remainder of the 40m suspensions. Helena will assemble the magnet/flag
assemblies tomorrow. She's already assembled the magnet/dumbbell assemblies
for the global/LIGOI osems. We're still working part procurement and fabrication.
The LASTI dSPACE computer will arrive there on Friday, 9/6.
40m Suspensions
Helena has been assembling the TM and BS suspension structures in preparation
for Betsy's arrival on Sept 9th. She has also been making magnet assemblies.
This morning, Bob Taylor started baking the osems needed for this assembly
work. The PZT, PZT driver and the translation stage have arrived and are
in the So. Annex.
New Osems
All of the alumina heads were sent FedEx to the plating company this
afternoon.
From: Helena Armandula <ahelena@ligo.caltech.edu>
Shipped to Stanford 1" dia. substrates for absorption measurements.
Six 1" dia. substrates were coated by Wave Precision with Ta2O5/Al2O3;
3 of them were annealed and 3 were not annealed.
Only two 1"dia. substrates were coated by MLD with Nb2O5 / SiO2 because
with had previous absorption data on these materials.
One substrate was annealed; the other was not.
Shipped Nb2O5/SiO2 coated "Q" substrates to Glasgow and MIT.
From: Hareem <htariq@ligo.caltech.edu>
Stoyan:
Verified that the density measurement of the sample did not have errors
due to the micrometer. Micrometer leaves no plastic deformation on the
sample during the measurement only some elastic deformation takes place.
Pistons and anvils for the splat quencher are all ready to be tested.
ANSYS started working but need more RAM and CPU power to run the simulations.
Learning stress/ strain measurements from Stefano.
Lia:
Wrapped up at Caltech and left for Italy this week. Working on creep
data analysis for her 3rd year theses at University of Pisa.
Brian:
Leaving this week. Will submit a research paper on work done for credit
once back at Cambridge university.
Verified absence of X-ray diffraction pattern shifts with the changing
incident angle of the beam on the sample; no effect on the peak position
noticed.
Crystalline samples of Boron 17, 20, 21 show no change in number of
peaks in diffraction pattern, as the chemical composition remains same.
Documented all scanned peaks present in X-ray diffraction pattern for Boron
17, 20 and 21 samples.
Noticed variation in peak position with respect to the day data was
acquired; the problem probably due to the small displacements of monochromator
stage in the x-ray diffractrometer.
Doing more data analysis on peak shifts in B17, 20, 21.
Finished soldering all the stepper motor controller cards for automating
the sample stage in the x-ray diffraction machine.
Maddalena:
Conducted multiple Vicker Hardness tests on MoRuB samples. Found a
discrepancy in the length of diagonals of diamond indentations that could
have been caused by the mass on top of diamond dropping too quickly on
the sample rather than gradually. Fixing this problem removed the systematic
error. The diagonal lengths still vary but there are no jumps in lengths
as going across the sample.
Stefano/ Chenyang:
Power supply for stress gauge finally working properly and the circuit
for stress gauge controller in order. Labview programme for the controller
finished. Starting the data taking but encountering problems with managing
data buffers, as computer is too slow.
Barbara/ Hareem:
Having noise problems above 100 degrees Celsius on the DTA therefore
only was able to see two transitions below that temperature in the initial
measurement. Discovered that the instrument and thermocouple noise levels
were off therefore fixed them. Recalibrating the DTA now. Spanning out
the thermal analyzer network.
Xavier:
Finding the small meshing limits for flex joint membrane simulations
on ANSYS. Computers are too slow for simulation; needs faster computers.
Mike:
Trying to measure the conductance of the shoes but having trouble with
the Quantum design thermometers. Calibrated the new thermometers under
QD instructions but apparently the instructions were wrong! Recalibrated
thermometers correctly. A thermometer broke during the measurement; this
is the 6th thermometer which broke.
Running heat capacity measurement for determining heat capacity of
addenda.
Helped write the Excel macro for exporting ANSYS data.
Studying and defining the radiation losses in TTO measurements.
Jumps observed in temperature control in cryostat due to the
National Instrument DAQ card. These jumps caused problems in feedback loop
and thus made the temperature control unstable.
For additional information about this report, contact sanders@ligo.caltech.edu