|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday September 2, 2002 will be:
CANCELLED DUE TO HOLIDAY
Subject: Notes from LSC Executive committee meeting 8/20/02
to: LSC executive committee
from: R. Weiss August 29, 2002
concerning: Notes from the LSC Executive Committee meeting August 20,2002
LSC Service Functions
-------------------------------------------------------------------
A new proposal was made by Keith Riles to populate the scientific
support during LIGO runs. The concept is to have LSC groups contract
in proportion to the FTE in the group to carry out a range of service
functions. The types of service functions include:
* scientific monitoring of shifts (highest priority)
* commissioning and instrument improvement
* investigations providing detector characterization
* validation of analysis software
The relative importance of the various types
of activities other than shifts are still being discussed.
Nevertheless, the concept was accepted in outline and
will be incorporated in the MOU's between the Laboratory
and the LSC groups.
In the next year as we approach full scientific operation, more scientists
than presently taking shifts will need to be trained. Once we are
in steady operations (probably S3) it may well be enough to change
the character of the scientific monitoring so that a single scientific
shift per site will be adequate.
Analysis of E7 and S1 data
-----------------------------------------------------------------
The structure of the "upper limit" groups will be continued for the
S1 data analysis. (After the Executive meeting,
the "upper limit"
groups gave reports on their work with E7 data
most of which was
impressive and gave the LSC the confidence that
S1 data can be
analysed with interesting results in a timely
manner.) One week
after the end of the S1 run, the groups will give a short
prospectus of their goals and strategy for S1 analysis and also
provide a preliminary estimate of the quality of the data. A LSC
wide telephone conference will be organized for this.
Drafts of initial papers will be circulated by the groups to the
LSC involved in LIGO I for discussion on November 1. The aim is to
provide vetted papers to the scientific community by January 1.
In order to maintain this tight schedule, the reduced data sets should
become available to the collaboration during the S1 run and the final
data available within days of the end of the S1 run.
GEO/LIGO data exchange and roles in the "upper limit" groups
----------------------------------------------------------
A significant discussion of the way the GEO and LIGO data
is used by the "upper limit" groups and how it becomes available
to the groups took place both at the executive meeting and then
later in the "upper limit" sessions of the main meeting. It is clear
that high level discussions between LIGO and GEO management are
needed and will begin immediately.
LIGO Operations--Administration
There was a site teleconference held on Thursday, August 29, 2002. The following issues were among those discussed:
Livingston Staging Building--Still a lot of noise and vibration in the HVAC systems. Some things need to be changed. Also have not yet received as-built drawings, installed equipment manuals, warranties, and certificates. There are remaining punch list items. Mark will fax the list to Ed.
A job walk for the Time and Material contract for partitions in the Staging Building is scheduled for Tuesday, September 3. Proposals are due on September 10th. The target is to have a contractor on board by the end of September.
Hanford Laboratory Building--Otto is on vacation.
Amphibious Vehicle for Livingston--Mark has sent a borchure to Barry. No issues with insurance as long as the vehicle is used for appropriate purposes by responsible people who have been trained and are on a list of authorized users.
Property--Ed Chargois previously reported that NIH in Bethesda, MD might prove to be a good source of almost new furniture for both sites. He is getting pictures of candidate items.
Use of Auditoriums by General Public--two issues: requires notification of NSF DGA of intentions, and the NSF should inform the DOE of intentions. Outreach related activities should not be a problem.
The list of current actions revised to reflect
the status of open actions assigned through August 29, 2002 may be found
at ACTION
LIST.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
ACTIVITY
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA .
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
CONSTRUCTION:
SUPPORT (Baldon, Torres, Lloyd, Tischler)
>Irene Baldon
Template meeting with Bill/Linda. Meeting prep with graphic designer re: press kit. NSF Boardroom images sent to representatives for review. Work with Livingston site re: photo shoot.
There was no Advanced LIGO Project Controls meeting this week. The Advanced LIGO MRE Proposal continues to have the Highest Priority. Continuing the development of the Cost Estimate.
Finished re-programming the baseline in accordance with the program plan endorsed by management. Will post data with budget data requested by David Shoemaker.
The following is a summary of status by sub system:
Continue to update the LASTI Schedule and incorporate any changes. Nothing new to report.
Project Plan for the 40-Meter Lab Upgrade continues. Nothing new to report.
Cost Book Tool.
I have placed a draft proposal file (.pdf format)
on the web for review and comment. I think that this is more or less
ready for entry into FastLane except
1) I received the MIT Proposal today. The
Proposal Budgets will have to be modified to reflect a modest increment.
2) There is no discussion of actual costs for
FY 2002. I propose to add a section that shows actual costs vs budgets
graphically for FY 2002 for Caltech, Hanford, Livingston, MIT, and R&D.
Data for August will be available late next week or early the following
week (Florence has some work to do to combine various WBS elements to give
me the summarizations proposed.)
We are preparing the budget model fof FY 2003.
All reserve will be allocated in Planning Packages for items that have
been identified on the contingency liens list. We will also establish
separate budget lines for items budgeted but not yet purchased in FY 2002.
The following change requests have been submitted:
| CR-010012
Revision B |
WBS 1.4.4.1 | Closeout Construction Budgets for Initial Computer Equipment Complement at the Sites | P. Lindquist |
| CR-020009 | OPs 1.3 | Digital Common Mode Servo to Mode Cleaner Path | D. Coyne |
| CR-020011 | OPs 5.15 | High Power Test in Suspended Interferometer (Gingin) | D. Coyne |
| CR-020012 | OPs 1.6 | Additional Funds to Complete 40-Meter Facility Upgrade | A. Weinstein |
| CR-020013 | OPs 1.3 | Digital Common Mode Servo to Mode Cleaner Path | D. Coyne/J. Heefner |
I propose to present CR-020011 and CR-020012 during the next Executive Committee Meeting.
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
No report this week.
Summary of Commissioning Activities at LIGO Hanford Observatory (compiled
by F. Raab)
-------------------------------------------------------------------------------------
(see ilog for details - if it's not in the ilog, it didn't happen...)
We are in the midst of the science run. Both H2
and H1 have been having troubles during the days, when noise from construction
of the vitrification plant at Hanford peaks. Typically seismic levels
are about 3 times normal background, which is not bad by Louisiana standards,
but the 1-minute band-limited seismic RMS from 1-3 Hz drives up by a factor
of 5 from that level with about a 50% duty cycle. Both interferometers
will hold lock during these episodes, but once lock is lost H2 has trouble
regaining its composure and H1 will not lock again until backgrounds return
to more reasonable levels in the late afternoon or early evening. We have
gotten locks of more than 12 hours, but we cannot hold science mode that
long because of a need to dress up alignments to prevent loss of sensitivity
and lockability. The need for working wavefront sensors is obvious. By
the time we lose lock alignment is awful and needs quite a bit of tweaking.
We have been holding a duty cycle of 40-45% for H1 and 65-75% for H2 -
pretty dismal compared to spec. I expect that we could do better on duty
cycle if we could spend a day trouble-shooting, but S1 prevents this.
In the high seismic noise periods, H2 has a higher rate of glitches
- principally related to POB degrees of freedom. H1 does not seem
to have the same sensitivity. At night we go hours with no glitches being
picked by ZGlitch - but the monitor is not very useful unless glitches
are so strong they can overcome the low-frequency noise. We have requested
some band-limit filtering in some monitor prior to glitch finding. Nonetheless,
I expect ZGlitch would have had no trouble finding glitches of the size
we experienced in E7. So there has been some progress.
GC: * Reinstalled an IDS between the LSU router and our firewall. I have been examining the logs, and the most common priority 1 traffic seen has been microsoft web server exploits. The other common one is rpc.statd exploits against linux. Most (but not all) have been self replication type stuff. I did see a couple items that looked like manual network probes. * Worked a few user support issues. * Looked into the CalTech site licensing which just came about in the last couple of months. Still trying to get a determination of whether or not the observatories are eligible. The person that administers this program is evidently in the hospital which is the reason for lack of responses. * Set up a web demo of some software for this afternoon. * Once again looking at how to effectively consolidate some of the computer services here. (web, mail, SQL, etc.) * Deciding where to place "Big Brother" to do network monitoring. * Ordered a small VPN appliance to evaluate for use here at Livingston for local staff to use. * Checking into a new hack that allows any attacker to lock up a windows machine that has NetBios enabled (pretty much any windows machine!) LDAS * Ordered the remaining 7 machines for the VPN network. They will be shipped to the individual sites and billed separately. (Shannon)
Data analysis:
1) playing with correlation DSO; 2) writing wave DSO.
LDAS hardware:
Sent 20 tapes with raw data to Caltech, 3 tapes with RDS to MIT and
3
tapes with RDS to UWM. No sign of P4 RAID so far.
(Igor)
Interferometer:
The interferometer has been running very smoothly
at night, although we have experienced very high seismic levels during
the day as soon beginning at dawn as a consequence of the logging activity
approaching the LVEA.
We are making detailed plans for installation and commissioning activities immediately following S1. The highest priority will be the conversion of the electronics to support the DSCs. During the S1 run, we will organize commissioning teams to address the check out, characterization, and implementation of the new electronics as well as other activities that need to be addressed prior to S2. Advance preparation of of modified electronics boards is now underway.
We have made all modifications to turn 10 Universal Dewhite boards from rev B1 to rev B5. Modifications to the LOS controlllers is ongoing. We have completed 2 of 8 boards and chassis. Completed the modification to the new 1X6 (sos suspensions). The modifications allows MC2 to be independently controlled. Installed interface boards for all LVEA optics which will allow us to use the existing field cables after the digital suspension installation. Began building the interface cables that connect the new suspension racks to 1X22. Built the cross-connects for the end stations. I'm waiting for more material so that we can begin wiring them. (Rus)
HEPI: All fabricated components of the hydraulic External Pre-Isolator were delivered to MIT this morning. The machined springs are completed and Marcel has them back at LLO for characterization. This will take a few days and next week we will have everything in hand to begin HEPI installation on the LASTI BSC (excluding the actuators). From the machine shop we've received the Actuator Plate, Diaphragm, Diaphragm Restraint, Bypass Resistor, Bypass Resistor Cap, and from HYSPAN the order for 24 Bellows. A first article of the actuator assembly has been sent to Solar Atmospheres in Souderton, PA for vacuum brazing and we're waiting to receive it back for inspection. I just received from the machine shop the quote for the balance of machine parts (primarily the tripod assembly) and will give to Marie Woods at MIT to issue a PO. It looks like we'll receive the bulk of the actuator parts from the machine shop in about 3 weeks, at which time we can begin assembly. My plan is to assemble 1 or 2 units as pathfinders. Unless we meet some unexpected problems it looks like we will have hydraulic actuators ready for installation in LASTI in late October. (Hammond, Kern)
I have been quite busy with spring characterization (machined springs) as well as supporting the vendor in drawing questions and concerns. Bottom line is that we are trying to keep the fabrication of parts flowing smoothly. I have resorted to sending the vendor (P & N Machine) E-Drawings because it is quicker to produce this medium than traditional drawings, plus there is an added advantage of having the luxury to look at the part in 3-D and manipulate it in real time. I spent sometime this week preparing these for the vendor and gave him a quick tutorial over the phone on how to best use the program. He quickly saw the benefits of the E-Drawing application and was delighted. We should certainly try to use this technology to advance design communications internal to LIGO as well as external. (Jonathan Kern also suggested this last week) We are still waiting from the Stanford group on information regarding the co-location of the L4C sensors. There are a few more design issues to address for the HEPI actuator, but Jonathan Kern, Ken Mason and myself are in the process of ironing them out. (Marcel)
The EPI work
on HAM-13 is moving along.Last week
we completed the
installation
of all 4 External Pre-Isolators and magnets.This
week we're
installing
the suspension springs and load cells.As
of this (Wed)
afternoon
we've installed springs into three of the EPIs, and have them
tensioned
so they are suspended just above their vertical stops.Table
alignment
has held very well, considering the trauma our inexperience is
imposing on
the stack.Yaw remains <100 u-rad
from our initial position and
pitch <140
u-rad.Tomorrow morning we'll suspend
the fourth pier on its
springs.Cabling
is substantially complete and we hope to enable a MEPI
system sometime
next week.
All of the
fabricated components of the hydraulic External Pre-Isolator were
delivered
to MIT this morning.The machined
springs are completed and
Marcel has
them back at LLO for characterization. This will take a few days
and next week
we will have everything in hand to begin HEPI installation on
the LASTI
BSC (excluding the actuators). From the machine shop we've
received the
Actuator Plate, Diaphragm, Diaphragm Restraint, Bypass
Resistor,
Bypass Resistor Cap, and from HYSPAN the order for 24 Bellows.A
first article
of the actuator assembly has been sent to Solar Atmospheres in
Souderton,
PA for vacuum brazing and we're waiting to receive it back for
inspection.
I just received from the machine shop the quote for the balance
of machine
parts (primarily the tripod assembly) and will give to Marie
Woods at MIT
to issue a PO. It looks like we'll receive the bulk of the
actuator parts
from the machine shop in about 3 weeks, at which time we can
begin assembly.My
plan is to assemble 1 or 2 units as pathfinders. Unless
we meet some
unexpected problems it looks like we will have hydraulic
actuators
ready for installation in LASTI in late October.
Ken Mailand
4 basic sets
of tests on the pressure noise spectrum and pump station operating conditions
(pressures, temperatures) completed by the end of week 8-26. Motor and
pump on integral mount adaptor and on separate mounts for these tests.
This set up was tested for both the gear pump and screw pump.
The manifolds
[5] with their mounting bases are finished and are being shipped to MIT
the week of 9-1.
The pump station
will be shipped after Rich tests the speed control electronics, probably
~9/16.
- New DSC/LSC/ASC
code pretty much ready to go for installation after S1 on all
interferometers.We've
tested as much as we can with what we have here and have
put all the
object code into installation directories.We
used Sigg's dscgen
script to
build all the screens and checked that all the front end and EPICS
code matched
up.
- Lori, Alex
and I will travel to LHO week of Sept. 9-13 to install and test new
software on
LHO4k.Along with DSC/LSC/ASC code,
we will install new DAQ code,
which supports
the new GDS scheme, and install a Pentium for use as the EDCU.
- We will
then travel to LLO Sept. 15 thru Sept.25 to do the same install there.
Alex
will leave there early (Sept. 21) and travel on to MIT to install the new
Abitrary Waveform
Generator (AWG) hardware/software and update the MIT DAQ
system to the latest revs the week of Sept 23.
1.Finished
board layout for the hydraulic pump speed control and pressure readout
module.The boards will be back in
house on the 4th of September.
2.Work
continues on the Altera version of the timing board.The
board is in CAD layout stage.
3.4
additional timing boards were checked out and are ready to ship once the
travelers are made out.
4.Finished
preliminary checkout of the 8 channel valve drivers and are ready to ship
once the paperwork has been filled out.We
made one version as a standalone module, and one version as a Eurocard
format pcb.
Sander Liu
In the process of testing a new EO shutter controller for the 40M. One of the high voltage power supply (10KV) was found to be defective and replaced. Testing should be completed today for deliver to 40M tomorrow.
Chasing down
vendors, specs and budgetary quotes on shielded racks and hardware for
EMI containment.
Specified a suite of low-noise Kepco linear series-pass regulated power supplies to replace Sorenson switchers at the LLO end stations. Thesewill be tested during the DSC retrofit after S1 before taking a decision to upgrade DC supplies elsewhere. The Houston Kepco sales visited Rusyl at LLO to work through specifications and procurement issues.
NPRO #259
was aligned, mode matched and locked to the reference cavity.
Tests of the
PSL frequency stabilization related boards are in the initial
stages of
testing.The VCO has been tested
and is functional.The 80 MHz
acousto-optic modulator was aligned with a diffraction efficiency of 95%.
Back on the
flat top beams; I am revisiting all the investigations I made with
a view to
the paper Kip has been preparing on the optimal cavities design, for
reducing thermoelasic
noise in advanced Ligo (in order to be able to reach the
quantum limit
for which the best suited detection scheme is currently studied)
and we are
trying to get ready for the discussion we will have on this matter.
Bill Kells
I have been
continuing work with Erika on the analysis
of SB balancing
in generic interferometers.
Also I have
resurected the paper draft (partially left by Stan) on
the old 40m
recycling experiment. I am intending to finish this (edits)
and submit
to committee.
Planning next
measurement trip to Hanford: to complete arm visibitities (on
which much
e2e modeling has been done) with a systematic plan for
obtaining
meaningfull loss results.
OTF Lab.
Contamination
Cavity # 1
Cavity is
locked and we'll continue taking ringdown measurements for at least 1000
hours.
We have finished
taking measurement of transmission and reflectance of some partially transmitted
mirrors and beam splitters from REO.And
this 100mw laser is in standby ready for further test.
New Lab
at RSE
Cavity #3
Reference Cavity still pumping down. Optical train ready.
Cavity waiting
for the laser to be aligned into the cavity due to lab safety regulation.
Cavity #2
Test cavity
This cavity
still pumping, waiting on optical train installation and laser alignment.
Labview programing
for ringdown measurements in progress by Liyuan.
Need to get
a PC computer to install the new LAB View card. I am still working in the
lab by setting and fixing the walls in place that will separate the laser
enclosure from the visiting area.Installing
power strips around the two optical table and accommodating all the cables
for the three lasers, I still need to get a new NPRO from Shanti.
Some misc... tasks, placed orders, I have requested the service of an electrician to change the light switch in the room sinceit has to be done up to the building code.
no report
LASTI (Kern, Goldman, Harry, MacInnis, Mason, Mittleman, Ottaway,
Rollins, Shoemaker, Zucker)
=============================================================
PSL (Dave O and Jamie R):
This week the Alternative FSS Servo was resurrected. A few modifications
were done and a unity gain frequency of 1 MHz was achieved.
#MZ:
cool! good job.
Photodiodes (Dave O and Mike Z):
A couple of photodiodes from Electro Optic Systems were received and
a
basic charaterization was done. Regrettfully these found to have
properties inferior to our best photodiodes from alternative vendors.
For the record Junction Capacitance = 180 pF (9 V bias voltage) Quantum
Efficiency = 75% It was also noticed that the substrate had significant
amounts of contamination, this was easily removed once the glass window
was removed using a nitrogen purge.
EPI Modeling (Dave O, Rich M and Dennis C):
This week we held a telecon to review the state of our current modeling
effort to understand the HAM MEPI system. Following this we are
pursuing the following approach. For frequencies below the lowest
support structure resonance (18 Hz) we are treating the support
structure as a solid body and are considering the dynamics of the
spring and masses as discreet objects. Above the 18 Hz resonance the
effective mass of the stack is significantly less than that of the
support table so we are neglecting the mass of the stack and are doing
a finite element model of the support structure as an elastic body.
Brian Lantz's model for the control of a BSC is being modified to a
HAM
system.
Brian has just release a new version of his BSC model which is
significantly different from the previous version. We are currently
modifying this to accommodate the HAM model. We have also received
a
program which runs a stepped sine analysis on the DSpace system from
Katie Lilienkamp, a mechanical engineer graduate student who is
considering working with us. This program is currently being
modified
to meet our needs.
MEPI / LASTI (Mason, Ottoway, Mittleman, MacInnis, Kern):
The EPI work on HAM-13 is moving along. Last week we completed
the
installation of all 4 External Pre-Isolators and magnets. This
week
we're installing the suspension springs and load cells. As of
this
(Wed) afternoon we've installed springs into three of the EPIs, and
have them tensioned so they are suspended just above their vertical
stops. Table alignment has held very well, considering the trauma
our
inexperience is imposing on the stack. Yaw remains <100 u-rad
from our
initial position and pitch <140 u-rad. Tomorrow morning we'll
suspend
the fourth pier on its springs. Cabling is substantially complete
and
we hope to enable a MEPI system sometime next week.
HEPI (Hammond, Kern):
#MZ: maybe also reported
under LLO?
All of the fabricated components of the hydraulic External Pre-Isolator
were delivered to MIT this morning. The machined springs are
completed
and Marcel has them back at LLO for characterization. This will take
a
few days and next week we will have everything in hand to begin HEPI
installation on the LASTI BSC (excluding the actuators). From the
machine shop we've received the Actuator Plate, Diaphragm, Diaphragm
Restraint, Bypass Resistor, Bypass Resistor Cap, and from HYSPAN the
order for 24 Bellows. A first article of the actuator assembly
has
been sent to Solar Atmospheres in Souderton, PA for vacuum brazing
and
we're waiting to receive it back for inspection. I just received from
the machine shop the quote for the balance of machine parts (primarily
the tripod assembly) and will give to Marie Woods at MIT to issue a
PO.
It looks like we'll receive the bulk of the actuator parts from the
machine shop in about 3 weeks, at which time we can begin assembly.
My
plan is to assemble 1 or 2 units as pathfinders. Unless we meet some
unexpected problems it looks like we will have hydraulic actuators
ready for installation in LASTI in late October.
Simulation and Modeling (Bhawal)
SLU
--------------
Hiro visited SLU to meet with Jim Howatt, the head of the computer
division of SLU,
where e2e will be installed to be used for the simulation and educational
purpose by Sany Yoshida.
S1
----
Biplab and Hiro are in LHO and LLO respectively for the S1 run and
taking
shift duties.
SimLIGO
-----------
(Matt) SimLIGO_020827.tar.gz is in ~mevans/tmp/ and seems to be working.
This intermediate version of SimLIGO contains working wavefront sensors
which control the pitch degree of freedom for all core optics except
the BS
(which is to be controlled with signals from QPDX and QPDY).
The yaw DOF is not
controlled because there appears to be a bug in the recycling summation
cavity.
Biplab is looking into this.
The optical lever servos, still used for yaw on all optics, have been
made a little more realistic. They now run at 16k and are routed
into
the suspension controller independent of the OSEM signals.
The common-mode servo is not turned on in this version, though I suspect
it could be made to work with little effort. I expect that on
my next
visit I will get the yaw DOF working, use QPDX and QPDy to control
the BS,
and upgrade the CM servo to the latest version found on the LHO 4k.
FP cavity tilt
-----------------
(Hiro) performed more calculations, analytically and numerically, related
to the
time dependence of powers of a cavity with time dependent mirror tilts.
The
observed "energy non conservation" is still not understood whether
it is a real
physical effect, or a limitation of the modal model or a bug of e2e
implementation.
software distribution
------------------------
(Hiro, Ed maros) Worked to build a new tarbal. A new script is created
to simplify
the creation of new tarbal. During this process, some ambiguous points
in the
distribution / installation documents are refined. Based on this new
tarbal, the
e2e softwares at LLO are updated to the latest.
(Ed Maros) created script for generating an e2e tarball.
Alfi 5
------
(Bruce)Continued work on the parser for better error messaging.
(Melody) Continued work on the automated tester for alfi5.
LIGO Data Analysis System
Software Systems (Blackburn)
At this time there has been only light use of the LDAS systems at the
sites. The DMT is generating triggers and placing these in the database
and
the Reduced Data Set Frames are being generated, but only a couple
of
dataPipeline jobs have been sent to date.
[A Lazzarini note: If this is a real trend in the LIGO/LSC computing
model, then we will
have to re-think the distribution of computing power at the observatories
vs. universities.
Originally, we had anticipated a need to process data at a rate equal
to its generation, near the
interferometers. If the collaboration does not find this useful, we
should re-locate nodes
to a centralized facility where theiir aggregated power is greater
than their distributed sum -- also easier to maintain.
I am frankly puzzled why UL gropus have been patiently awaiting their
RDS sets to show up at their home institutions before looking at the data
-- if something is wrong with S1, we will not have known for almost 1/2
of the S1 run!]
The issue with the "state data object" creation, storage and re-ingestion
that were discovered last week have been tracked down and fixed. It
is now
working again. This is fortuitous since it was reported at the LSC
meeting
last week that the Burst Group is ready to start using this function.
This
required changes to the wrapperAPI, dataConditionAPI and the
eventMonitorAPI, as well as to the user command macros.
Several new issues in the metaDataAPI were discovered in association
with
the fix for the ILWD objects with comments causing ingestions to fail.
This
fix caused duplication errors when processing an ILWD with two table
contained within. This now works and a set of test scripts have been
added
to the repository to allow us to track this issue in future modifications.
Several issues with resampling and the metadata used to resample were
identified by the dataConditionAPI working group. These issues have
been
logged as bugs in the bug tracking system. The Matrix class was also
revised
for the dataConditionAPI.
The rewrite for the frameAPI to use more CPUs has shown some mixed results
this week. Earlier it was found to work extremely well but when these
changes were integrated into CVS with other major changes, and then
rebuilt
from CVS it was found to not work. This has been traced to a file missing
from CVS and LDAS is being rebuilt with this file included to see if
this
fixes the problem.
There are several new examples on the web for using the frameCPP library
that is used by several packages within the LIGO Laboratory and the
LSC.
These should help authors of applications more easily use the data
in
FrProcData structures found in the Reduced Data Set Frames being written
by
LDAS for the Science Run.
The new version 6 frameCPP is still under development. Most of the code
is
in place, and in fact is now in CVS. However, very little testing has
been
carried out and it has yet to be integrated into the LDAS frameAPI.
The emergency socket and operator socket code has been re-worked to
be
entirely event driven. This should put an end to the partial strings
received from user requests. It may also improve overall performance
in the
system.
Hardware Systems (Anderson)
Caltech
-------
(Dan Kozak)
* HPSS: Resumed migration of large files off of Redwoods (CACR took
delivery of
more 9940 tapes).
* SAM-QFS: Did more test runs simulating writing tapes at a site and
importing
them into
the CIT archive. Started setting up to ingest real S1 data.
* Did some work to try to get hsi from saiph to HPSS over HPN working.
So far, nothing that has been suggested has helped. I'll
continue to
pursue this with Mike Gleicher and James Patton.
(Al Wilson)
* A lot of work with the CIT and TEST systems.
* Installed a new Fast Iron II switch and hooked up GigE to all of the
machines in the CIT system (minus nodes).
* Install PCI GigE cards in Beowulf and Datacon.
* Prepped Fiber runs for the New Raid systems and the Ldas in a box systems.
* Did some house keeping in the computer room.
(Stuart Anderson)
* Started archiving S1 data to HPSS.
* Upgraded the LDAS-CIT network switch and all remaining servers to
Gigabit Ethernet.
* Determined that the 10 Mbit/s network bandwidth to LHO is a factor
of 2 too slow to replicated the Reduced Data Set (RDS) frames
to
Caltech in real-time.
MIT
---
(Keith Bayer)
* Loaded PreS1 data onto ldas.
* Started burntest on pc raid box (Tuesday).
* Begun loading S1 data onto pc raid box.
* Running jobs to cull out asq channel from E7 RDS frames.
* Ordering 19" rack unit and rack mount UPS.
* Got quote for Gigabit Fiber Ethernet card (Antares).
Livingston
----------
(Igor Yakushin)
* Sent 20 tapes with raw data to Caltech, 3 tapes with RDS to MIT and
3 tapes with RDS to UWM.
* No sign of P4 RAID so far. [A. Lazzarini note: it appears that UPS
lost the unit somewhere between pickup and their So. Calif. distribution
hub. We are re-allocating
one of the units designated for Caltech to LLO in the interim. Lesson
learned: do not use UPS!]
(Shannon Roddy)
* Ordered the remaining 7 machines for the VPN network. They
will be shipped to the individual sites and billed separately.
Hanford
-------
(Greg Mendell)
* Coordinated with Igor the running of tapecontrol scripts to archive
raw frame data for preS1 injections and during S1 at LHO and
LLO. The
first 20 tapes from each site have been sent to Caltech.
* Coordinated with Isabel, Igor, and Shannon the running of tapecontrol
scripts to write RDS output from LDAS to tape. Currently
tapes are
written simultaneously for UWM and MIT and each site has received
4
tapes with data.
* Working to finish the set up of the new 2 TB Raid Server at LHO. The
burntest should end today (but was still running this morning).
Data Analysis Activities (Lazzarini)
Data Analysis activities at MIT
===============================
o Establish criteria on selecting locked segments and apply
them on E7 bursts analysis (Laura with input from Alan).
o Document Excess Power DSO status after E7 investigations
and communicate it to its authors (Erik).
o E7 bursts analysis bits and pieces (Stefan, Laura, Erik).
o Prepare infrastructure to reduce E7 data (currently on MIT
disks) down to the AS_Q channel (Keith, Erik - in progress).
o Prepare infrastructure to perform sanity checks between
various levels of reduced data (full raw frames, RDS',
strain only). The goal is to confront analysis output on a
statistically significant sample to establish confidence in
the data reduction scheme (Erik, Laura, Tania).
o Setting up stochastic DSO LDAS pipeline at MIT (Tania).
Shawhan:
* Helped Anand Sengupta (IUCAA) figure out how to run his search code
(prototype of
the Extended Hierarchical Search for binary inspirals) on the LDAS
test
system using data from E7. Previously, he had just been using
the standalone
wrapperAPI.
* Currently re-implementing the LARS server to provide remote access
to the
E7 (and soon S1) data in the HPSS archive.
Yakushin:
1) studying a correlation DSO; 2) writing wavelet DSO.
Weinstein:
- Took S1 shifts at LHO. Watched the Rayleigh monitor.
When the IFOs are in lock, it's pretty quiet - very few bursts!
- Working on running burst DSOs online,
interfacing with Duncan's online dso monitoring web tool.
General Computing (Wallace)
Lazzarini: We held a site-wide teleconference to review an IT Security
Plan I drafted with input from GC, LDAS and CDS.
There was much discussion and a number of useful resolutions to outstanding
issues. The Plan should bne ready in time to send it to NSF for our Fall
review.
MIT:
(Keith)
-Installed updated license/version of mathematica on gc
-Removed 'lancelot' DMT machine from gcnet and dedicated it to DMT/LDAS
-Copied home dirs of remote DMT / LDAS users over to lancelot
Livingston:
(Shannon)
- Reinstalled an IDS between the LSU router and our firewall. I
have been examining the logs, and the most common priority 1
traffic seen has been microsoft web server exploits. The
other common one is rpc.statd exploits against linux. Most
(but not all) have been self replication type stuff. I did
see a couple items that looked like manual network probes.
- Worked a few user support issues.
- Looked into the CalTech site licensing which just came about
in the last couple of months. Still trying to get a
determination of whether or not the observatories are
eligible. The person that administers this program is
evidently out sick which is the reason for lack of
responses.
- Set up a web demo of some software for this afternoon.
- Once again looking at how to effectively consolidate some of
the computer services here. (web, mail, SQL, etc.)
- Deciding where to place "Big Brother" to do network
monitoring.
- Ordered a small VPN appliance to evaluate for use here at
Livingston for local staff to use.
- Checking into a new hack that allows any attacker to lock up a
windows machine that has NetBios enabled (pretty much any
windows machine!)
Hanford:
(Christine)
- Provided comments to Albert's IT Security Plan Document. Attended
a
meeting on Thursday morning to discuss the document.
- On vacation the rest of the week.
CIT:
(Mike)
-Taking Microsoft training courses for the next few weeks.
(Wendy)
-Finished loading software and ghosting two machines, including one
high-end user machine
-Worked on restoring tapes
-Delivered mail to 40m house
-Random tasks, such as printers
(Veronica)
- LSC website: re-worked a database of meeting transparencies to add
a
table for closed session talks. Posted remaining talks as they kept
coming
in. Tracked down a problem with one of the database tables that was
causing an error message on loading.
- LIGO website: rewrote a webpage for other GW projects with LIGO-related
activity; the new page is now posted.
Working on webpages for the upcoming Aspen 2003 Winter Conference.
Posted a link to the new Visitors Program webpages.
(Lisa)
- Vast and voluminous amounts of work on the mailman/mhonarc/webglimpse
mailing
list system. This includes helping folks configure their privacy
settings and
setting up apache authentication into the archives. Next I will
be looking at
how to automatically filter out administrative notices from the archives.
- Worked with ITS security as questions/problems came up.
(Bruce Sears)
- General Ilog Maintenance:
(0.5 days)
(Larry)
-Spent a deal of time working on printer fixes. One issue that came
up was HP
not having recorded our extended warranty after many hours on the phone
I
finally was able to get a person to look into the issue.
-Worked a couple of IT security issues. Both were viruses on machines.
Both
machines did have the latest virus-scan files. We've not had time to
track down
how the machines were infected but both machines were rebuilt.
-Working a number of VRVS issues. Still trying to get better resolution
out of
the system.
-Performed a few more network tests with new WAN connection at Hanford.
I was
able to get 4.8 Mb/s on a steady basis, which is a big improvement
over the
past.
-Worked a number of procurement issues and spent time reconciling items
on the
P-card. Reconciling orders has become a real time sink but I guess
it beats the
alternative.
Distributed a number of items to various users.
-Helped DCC out on a couple of file downloads/fixes as well as checked
out one
of their pc's that was having a problem. So far nothing major but we
will keep
an eye on it since it was a unit that needed a major h/w overhall a
few months
ago.
From: Peter King <pking@ligo.caltech.edu>
2.2 AdLIGO PSL
Testing of the frequency stabilization related electronics
destined for
the University of Hannover is about to commence. Thus far only
the VCO has
been tested whilst the laser has been checked out with the PSL Lab's
set of
cards.
From: "Mark Barton" <mbarton@ligo.caltech.edu>
This week I attended a training session on the use
of the dSpace
controller system at the dSpace facility in Michigan. I also submitted
a
report and request for information about a weakness I encountered in
the
system: the output of some Simulink blocks (e.g., the elliptic filters)
can depend critically on the order of the ODE solution method selected
and it's not obvious what order will be adequate in a particular case.
From: Bill Kells <kells@ligo.caltech.edu>
Besides usual monitoring of ongoing sapphire development
issues (with
Garilynn and J. camp) I've been focusing on the newly
brought up issue
of "flattop beams" . We (Erika and I) had done much work
(~ FFT simulations)
on this in the past but put it asside as a "beyond ADvL"
project". so
we are revisiting. Working now to have something
coherent to contribute
next week (by phone).
Also working on other simulations pertinant to AdL
design (normal Gaussian beams)
using FFT and e2e (have actually spent large amount of
time this week on
algorithmatic issues I found: with Hiro and Biplab).
Overall focus is on problems
pertaining to the upcoming downselect.
From: ctorrie <ctorrie@ligo.caltech.edu>
Advanced LIGO Suspensions
I) Mode Cleaner
i) Cantilever Blades
See report from Janeen Romie
ii) Wire Jigs
Mike Plissi and I have measured all of the wires for the 3 stages of
the first prototype suspension. Mike has recommended a couple of small
changes that have been incorporated into the design.
iii) Masses
The 3 masses have been assembled successfully, this has taken longer
than expected as we have been organising our delivery of silver plated
and stainless steel bolts.
iv) Coils
GEO should be delivering the coils for the mode cleaner this week.
II) Workshop
Both the Physics workshop and Central Engineering have been delivering
the last of the piece parts for the suspension.
III) Single Pendulum Experiment
Norna Robertson and I have been analysing some initial results taken
by John Veitch on a Single Pendulum with crossed blades and 2 wires off
one blade. We are interested in extending our bank of results on how big
an effect the crossing of the blades and 2 wires off one blade has on the
pitch mode of a pendulum.
From: Janeen Romie <romie_j@ligo.caltech.edu>
AdLIGO Suspensions
Superior Jig has delivered four large MC blades. Calum and Mike Plissi
have been characterizing them, finding curious results. The balance of
four more large blades will be delivered from Superior Jig, via Gina courier,
tomorrow morning. Four more small blades will be shipped from SJI on Friday,
8/30. Superior Jig made these blades by EDMing them out a billet of maraging
steel. I will be picking up the Lobart blades, produced by the traditional
rolling process, this afternoon. It will be interesting to compare the
results of these blades, made from two different processes.
I've spend most of the week procuring parts or chasing procurements
for the AdLIGO MC prototype suspensions or the new osem assemblies.
Working with UFl on penultimate mass designs. It's good to start interfacing
with them.
For additional information about this report, contact sanders@ligo.caltech.edu