Weekly Report for Week Ending August 29, 2002


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  September 2, 2002 will be:

 CANCELLED DUE TO HOLIDAY


Special Announcements:


Weekly Report Highlights
 


LSC Issues (Weiss)


Subject: Notes from LSC Executive committee meeting 8/20/02

to: LSC executive committee
from: R. Weiss August 29, 2002
concerning: Notes from the LSC Executive Committee meeting August 20,2002

LSC Service Functions
-------------------------------------------------------------------
A new proposal was made by Keith Riles to populate the scientific
support during LIGO runs. The concept is to have LSC groups contract
in proportion to the FTE in the group to carry out a range of service
functions. The types of service functions include:

*   scientific monitoring of shifts (highest priority)
*   commissioning and instrument improvement
*   investigations providing detector characterization
*   validation of analysis software

The relative importance of the various types
of activities other than shifts are still being discussed.
Nevertheless, the concept was accepted in outline and
will be incorporated in the MOU's between the Laboratory
and the LSC groups.

In the next year as we approach full scientific operation, more scientists
than presently taking shifts will need to be trained. Once we are
in steady operations (probably S3) it may well be enough to change
the character of the scientific monitoring so that a single scientific
shift per site will be adequate.

Analysis of E7 and S1 data
-----------------------------------------------------------------
The structure of the "upper limit" groups will be continued for the
S1 data analysis. (After the Executive meeting, the "upper limit"
groups gave reports on their work with E7 data most of which was
impressive and gave the LSC the confidence that S1 data can be
analysed with interesting results in a timely manner.) One week
after the end of the S1 run, the groups will give a short
prospectus of their goals and strategy for S1 analysis and also
provide a preliminary estimate of the quality of the data. A LSC
wide telephone conference will be organized for this.
Drafts of initial papers will be circulated by the groups to the
LSC involved in LIGO I for discussion on November 1. The aim is to
provide vetted papers to the scientific community by January 1.
 

In order to maintain this tight schedule, the reduced data sets should
become available to the collaboration during the S1 run and the final
data available within days of the end of the S1 run.
 
 

GEO/LIGO data exchange and roles in the "upper limit" groups
----------------------------------------------------------
A significant discussion of the way the GEO and LIGO data
is used by the "upper limit" groups and how it becomes available
to the groups took place both at the executive meeting and then
later in the "upper limit" sessions of the main meeting. It is clear
that high level discussions between LIGO and GEO management are
needed and will begin immediately.
 


LIGO I Construction/LIGO Laboratory Administration (Lindquist)



 

LIGO Operations--Administration



LIGO Weekly Site Telecon (Lindquist)

There was a site teleconference held on Thursday, August 29, 2002. The following issues were among those discussed:

Livingston Staging Building--Still a lot of noise and vibration in the HVAC systems.  Some things need to be changed.  Also have not yet received as-built drawings, installed equipment manuals, warranties, and certificates.  There are remaining punch list items.  Mark will fax the list to Ed.

A job walk for the Time and Material contract for partitions in the Staging Building is scheduled for Tuesday, September 3.  Proposals are due on September 10th.  The target is to have a contractor on board by the end of September.

Hanford Laboratory Building--Otto is on vacation.

Amphibious Vehicle for Livingston--Mark has sent a borchure to Barry.  No issues with insurance as long as the vehicle is used for appropriate purposes by responsible people who have been trained and are on a list of authorized users.

Property--Ed Chargois previously reported that NIH in Bethesda, MD might prove to be a good source of almost new furniture for both sites.  He is getting pictures of candidate items.

Use of Auditoriums by General Public--two issues: requires notification of NSF DGA of intentions, and the NSF should inform the DOE of intentions.  Outreach related activities should not be a problem.

The list of current actions revised to reflect the status of open actions assigned through August 29, 2002 may be found at ACTION LIST.


PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACCOMPLISHMENTS

> From: Cleveland Mak <mak_c@ligo.caltech.edu>

ACTIVITY

Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.

COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA .

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>

CONSTRUCTION:

OPERATIONS:

SUPPORT (Baldon, Torres, Lloyd, Tischler)

>Irene Baldon

>Dorothy Lloyd >Rita Torres >From: Ryan Tischler <rtischle@ligo.caltech.edu>

Template meeting with Bill/Linda.  Meeting prep with graphic designer re: press kit.  NSF Boardroom images sent to representatives for review.  Work with Livingston site re: photo shoot.


Advanced LIGO (Frey)

From: Thomas Frey <tfrey@ligo.caltech.edu>

There was no Advanced LIGO Project Controls meeting this week.  The Advanced LIGO MRE Proposal continues to have the Highest Priority.  Continuing the development of the Cost Estimate.

Finished re-programming the baseline in accordance with the program plan endorsed by management.  Will post data with budget data requested by David Shoemaker.

The following is a summary of status by sub system:

Continue to update the TNI Schedule and incorporate any changes.  Nothing new to report.

Continue to update the LASTI Schedule and incorporate any changes.  Nothing new to report.

Project Plan for the 40-Meter Lab Upgrade continues.  Nothing new to report.

Cost Book Tool.

Project Web Site for posting schedule and progress related data continues to be updated with the latest and greatest.

Reports (Lindquist)

I have placed a draft proposal file (.pdf format) on the web for review and comment.  I think that this is more or less ready for entry into FastLane except
1) I received the MIT Proposal today.  The Proposal Budgets will have to be modified to reflect a modest increment.
2) There is no discussion of actual costs for FY 2002.  I propose to add a section that shows actual costs vs budgets graphically for FY 2002 for Caltech, Hanford, Livingston, MIT, and R&D.  Data for August will be available late next week or early the following week (Florence has some work to do to combine various WBS elements to give me the summarizations proposed.)

We are preparing the budget model fof FY 2003.  All reserve will be allocated in Planning Packages for items that have been identified on the contingency liens list.  We will also establish separate budget lines for items budgeted but not yet purchased in FY 2002.



Change Control/Contingency (Lindquist)

The following change requests have been submitted:
 

Open or Recent Change Requests
CR-010012 
Revision B
WBS 1.4.4.1 Closeout Construction Budgets for Initial Computer Equipment Complement at the Sites P. Lindquist
CR-020009 OPs 1.3 Digital Common Mode Servo to Mode Cleaner Path D. Coyne
CR-020011 OPs 5.15 High Power Test in Suspended Interferometer (Gingin) D. Coyne
CR-020012 OPs 1.6 Additional Funds to Complete 40-Meter Facility Upgrade A. Weinstein
CR-020013 OPs 1.3 Digital Common Mode Servo to Mode Cleaner Path D. Coyne/J. Heefner

I propose to present CR-020011 and CR-020012 during the next Executive Committee Meeting.


Human Resources (Akutagawa)

From: Cindy Akutagawa <cindy@ligo.caltech.edu>


Quality/Safety (Tyler)

>From: Bill Tyler <tyler@ligo.caltech.edu>

No report this week.


LIGO Hanford Observatory (LHO) and Interferometer Operations (Raab)


Summary of Commissioning Activities at LIGO Hanford Observatory (compiled by F. Raab)
-------------------------------------------------------------------------------------
(see ilog for details - if it's not in the ilog, it didn't happen...)
 

We are in the midst of the science run. Both H2 and H1 have been having troubles during the days, when noise from construction of the vitrification plant at Hanford peaks. Typically seismic levels are about 3 times normal background, which is not bad by Louisiana standards, but the 1-minute band-limited seismic RMS from 1-3 Hz drives up by a factor of 5 from that level with about a 50% duty cycle. Both interferometers will hold lock during these episodes, but once lock is lost H2 has trouble regaining its composure and H1 will not lock again until backgrounds return to more reasonable levels in the late afternoon or early evening. We have gotten locks of more than 12 hours, but we cannot hold science mode that long because of a need to dress up alignments to prevent loss of sensitivity and lockability. The need for working wavefront sensors is obvious. By the time we lose lock alignment is awful and needs quite a bit of tweaking. We have been holding a duty cycle of 40-45% for H1 and 65-75% for H2 - pretty dismal compared to spec. I expect that we could do better on duty cycle if we could spend a day trouble-shooting, but S1 prevents this.
 

In the high seismic noise periods, H2 has a higher rate of glitches - principally related to  POB degrees of freedom. H1 does not seem to have the same sensitivity. At night we go hours with no glitches being picked by ZGlitch - but the monitor is not very useful unless glitches are so strong they can overcome the low-frequency noise. We have requested some band-limit filtering in some monitor prior to glitch finding. Nonetheless, I expect ZGlitch would have had no trouble finding glitches of the size we experienced in E7. So there has been some progress.
 


LIGO Livingston Observatory (LLO) and Interferometer Operations (Coles)


GC: * Reinstalled an IDS between the LSU router and our firewall. I have been examining the logs, and the most common priority 1 traffic seen has been microsoft web server exploits. The other common one is rpc.statd exploits against linux. Most (but not all) have been self replication type stuff. I did see a couple items that looked like manual network probes. * Worked a few user support issues. * Looked into the CalTech site licensing which just came about in the last couple of months. Still trying to get a determination of whether or not the observatories are eligible. The person that administers this program is evidently in the hospital which is the reason for lack of responses. * Set up a web demo of some software for this afternoon. * Once again looking at how to effectively consolidate some of the computer services here. (web, mail, SQL, etc.) * Deciding where to place "Big Brother" to do network monitoring. * Ordered a small VPN appliance to evaluate for use here at Livingston for local staff to use. * Checking into a new hack that allows any attacker to lock up a windows machine that has NetBios enabled (pretty much any windows machine!) LDAS * Ordered the remaining 7 machines for the VPN network. They will be shipped to the individual sites and billed separately. (Shannon)

Data analysis:
1) playing with correlation DSO; 2) writing wave DSO.
LDAS hardware:
Sent 20 tapes with raw data to Caltech, 3 tapes with RDS to MIT and 3
tapes with RDS to UWM. No sign of P4 RAID so far.
(Igor)
 

Interferometer:
The interferometer has been running very smoothly at night, although we have experienced very high seismic levels during the day as soon beginning at dawn as a consequence of the logging activity approaching the LVEA.

We are making detailed plans for installation and commissioning activities immediately following S1. The highest priority will be the conversion of the electronics to support the DSCs. During the S1 run, we will organize commissioning teams to address the check out, characterization, and implementation of the new electronics as well as other activities that need to be addressed prior to S2. Advance preparation of of modified electronics boards is now underway.

We have made all modifications to turn 10 Universal Dewhite boards from rev B1 to rev B5. Modifications to the LOS controlllers is ongoing. We have completed 2 of 8 boards and chassis. Completed the modification to the new 1X6 (sos suspensions). The modifications allows MC2 to be independently controlled. Installed interface boards for all LVEA optics which will allow us to use the existing field cables after the digital suspension installation. Began building the interface cables that connect the new suspension racks to 1X22. Built the cross-connects for the end stations. I'm waiting for more material so that we can begin wiring them. (Rus)

HEPI: All fabricated components of the hydraulic External Pre-Isolator were delivered to MIT this morning. The machined springs are completed and Marcel has them back at LLO for characterization. This will take a few days and next week we will have everything in hand to begin HEPI installation on the LASTI BSC (excluding the actuators). From the machine shop we've received the Actuator Plate, Diaphragm, Diaphragm Restraint, Bypass Resistor, Bypass Resistor Cap, and from HYSPAN the order for 24 Bellows. A first article of the actuator assembly has been sent to Solar Atmospheres in Souderton, PA for vacuum brazing and we're waiting to receive it back for inspection. I just received from the machine shop the quote for the balance of machine parts (primarily the tripod assembly) and will give to Marie Woods at MIT to issue a PO. It looks like we'll receive the bulk of the actuator parts from the machine shop in about 3 weeks, at which time we can begin assembly. My plan is to assemble 1 or 2 units as pathfinders. Unless we meet some unexpected problems it looks like we will have hydraulic actuators ready for installation in LASTI in late October. (Hammond, Kern)

I have been quite busy with spring characterization (machined springs) as well as supporting the vendor in drawing questions and concerns. Bottom line is that we are trying to keep the fabrication of parts flowing smoothly. I have resorted to sending the vendor (P & N Machine) E-Drawings because it is quicker to produce this medium than traditional drawings, plus there is an added advantage of having the luxury to look at the part in 3-D and manipulate it in real time. I spent sometime this week preparing these for the vendor and gave him a quick tutorial over the phone on how to best use the program. He quickly saw the benefits of the E-Drawing application and was delighted. We should certainly try to use this technology to advance design communications internal to LIGO as well as external. (Jonathan Kern also suggested this last week) We are still waiting from the Stanford group on information regarding the co-location of the L4C sensors. There are a few more design issues to address for the HEPI actuator, but Jonathan Kern, Ken Mason and myself are in the process of ironing them out. (Marcel)


Detector/Technical Support (Coyne)



 

DETECTOR SCIENCE & ENGINEERING

Seismic Upgrade Project

Electro-Magnetic External Pre-Isolation (MEPI) at LASTI
Mason, Ottoway, Mittleman, MacInnis, Kern

The EPI work on HAM-13 is moving along.Last week we completed the

installation of all 4 External Pre-Isolators and magnets.This week we're

installing the suspension springs and load cells.As of this (Wed)

afternoon we've installed springs into three of the EPIs, and have them

tensioned so they are suspended just above their vertical stops.Table

alignment has held very well, considering the trauma our inexperience is

imposing on the stack.Yaw remains <100 u-rad from our initial position and

pitch <140 u-rad.Tomorrow morning we'll suspend the fourth pier on its

springs.Cabling is substantially complete and we hope to enable a MEPI

system sometime next week.

Hydraulic External Pre-Isolation (HEPI)
Hammond, Kern

All of the fabricated components of the hydraulic External Pre-Isolator were

delivered to MIT this morning.The machined springs are completed and

Marcel has them back at LLO for characterization. This will take a few days

and next week we will have everything in hand to begin HEPI installation on

the LASTI BSC (excluding the actuators). From the machine shop we've

received the Actuator Plate, Diaphragm, Diaphragm Restraint, Bypass

Resistor, Bypass Resistor Cap, and from HYSPAN the order for 24 Bellows.A

first article of the actuator assembly has been sent to Solar Atmospheres in

Souderton, PA for vacuum brazing and we're waiting to receive it back for

inspection. I just received from the machine shop the quote for the balance

of machine parts (primarily the tripod assembly) and will give to Marie

Woods at MIT to issue a PO. It looks like we'll receive the bulk of the

actuator parts from the machine shop in about 3 weeks, at which time we can

begin assembly.My plan is to assemble 1 or 2 units as pathfinders. Unless

we meet some unexpected problems it looks like we will have hydraulic

actuators ready for installation in LASTI in late October.

Ken Mailand

4 basic sets of tests on the pressure noise spectrum and pump station operating conditions (pressures, temperatures) completed by the end of week 8-26. Motor and pump on integral mount adaptor and on separate mounts for these tests. This set up was tested for both the gear pump and screw pump.

The manifolds [5] with their mounting bases are finished and are being shipped to MIT the week of 9-1.

The pump station will be shipped after Rich tests the speed control electronics, probably ~9/16.

CDS Software

Rolf Bork reporting

- New DSC/LSC/ASC code pretty much ready to go for installation after S1 on all 

interferometers.We've tested as much as we can with what we have here and have 

put all the object code into installation directories.We used Sigg's dscgen 

script to build all the screens and checked that all the front end and EPICS 

code matched up.

- Lori, Alex and I will travel to LHO week of Sept. 9-13 to install and test new 

software on LHO4k.Along with DSC/LSC/ASC code, we will install new DAQ code, 

which supports the new GDS scheme, and install a Pentium for use as the EDCU.

- We will then travel to LLO Sept. 15 thru Sept.25 to do the same install there. 

Alex will leave there early (Sept. 21) and travel on to MIT to install the new 

Abitrary Waveform Generator (AWG) hardware/software and update the MIT DAQ 

system to the latest revs the week of Sept 23.

CDS Hardware

Rich Abbott reporting

1.Finished board layout for the hydraulic pump speed control and pressure readout module.The boards will be back in house on the 4th of September.

2.Work continues on the Altera version of the timing board.The board is in CAD layout stage.

3.4 additional timing boards were checked out and are ready to ship once the travelers are made out.

4.Finished preliminary checkout of the 8 channel valve drivers and are ready to ship once the paperwork has been filled out.We made one version as a standalone module, and one version as a Eurocard format pcb.

Sander Liu

In the process of testing a new EO shutter controller for the 40M. One of the high voltage power supply (10KV) was found to be defective and replaced. Testing should be completed today for deliver to 40M tomorrow.

EMI/RFI mitigation

(Zucker, Heefner, Wooley)

Chasing down vendors, specs and budgetary quotes on shielded racks and hardware for EMI containment.

Specified a suite of low-noise Kepco linear series-pass regulated power supplies to replace Sorenson switchers at the LLO end stations. Thesewill be tested during the DSC retrofit after S1 before taking a decision to upgrade DC supplies elsewhere. The Houston Kepco sales visited Rusyl at LLO to work through specifications and procurement issues.

PSL

PeterKing

NPRO #259 was aligned, mode matched and locked to the reference cavity.

Tests of the PSL frequency stabilization related boards are in the initial

stages of testing.The VCO has been tested and is functional.The 80 MHz

acousto-optic modulator was aligned with a diffraction efficiency of 95%.

Optics Analysis

Erika D’Ambrosio

Back on the flat top beams; I am revisiting all the investigations I made with

a view to the paper Kip has been preparing on the optimal cavities design, for

reducing thermoelasic noise in advanced Ligo (in order to be able to reach the

quantum limit for which the best suited detection scheme is currently studied)

and we are trying to get ready for the discussion we will have on this matter.

Bill Kells

I have been continuing work with Erika on the analysis

of SB balancing in generic interferometers.

Also I have resurected the paper draft (partially left by Stan) on

the old 40m recycling experiment. I am intending to finish this (edits)

and submit to committee.

Planning next measurement trip to Hanford: to complete arm visibitities (on

which much e2e modeling has been done) with a systematic plan for

obtaining meaningfull loss results.

Optical Contamination Cavities

Lee Cardenas, Liyuan Zhang

OTF Lab. 

Contamination Cavity # 1 

Cavity is locked and we'll continue taking ringdown measurements for at least 1000 hours.

We have finished taking measurement of transmission and reflectance of some partially transmitted mirrors and beam splitters from REO.And this 100mw laser is in standby ready for further test.

New Lab at RSE 

Cavity #3 Reference Cavity still pumping down. Optical train ready.

Cavity waiting for the laser to be aligned into the cavity due to lab safety regulation.

Cavity #2 Test cavity 

This cavity still pumping, waiting on optical train installation and laser alignment.

Labview programing for ringdown measurements in progress by Liyuan.

Need to get a PC computer to install the new LAB View card. I am still working in the lab by setting and fixing the walls in place that will separate the laser enclosure from the visiting area.Installing power strips around the two optical table and accommodating all the cables for the three lasers, I still need to get a new NPRO from Shanti.

Some misc... tasks, placed orders, I have requested the service of an electrician to change the light switch in the room sinceit has to be done up to the building code.


40 Meter Interferometer (Weinstein)



 



Thermal Noise Interferometer (Libbrecht)


no report


LASTI (Zucker)


LASTI (Kern, Goldman, Harry, MacInnis, Mason, Mittleman, Ottaway,
Rollins, Shoemaker, Zucker)
=============================================================
 

PSL (Dave O and Jamie R):

This week the Alternative FSS Servo was resurrected. A few modifications
were done and a unity gain frequency of 1 MHz was achieved.
        #MZ: cool! good job.

Photodiodes (Dave O and Mike Z):

A couple of photodiodes from Electro Optic Systems were received and a
basic charaterization was done. Regrettfully these found to have
properties inferior to our best photodiodes from alternative vendors.
For the record Junction Capacitance = 180 pF (9 V bias voltage) Quantum
Efficiency = 75% It was also noticed that the substrate had significant
amounts of contamination, this was easily removed once the glass window
was removed using a nitrogen purge.

EPI Modeling (Dave O, Rich M and Dennis C):

This week we held a telecon to review the state of our current modeling
effort to understand the HAM MEPI system. Following this we are
pursuing the following approach.  For frequencies below the lowest
support structure resonance (18 Hz) we are treating the support
structure as a solid body and are considering the dynamics of the
spring and masses as discreet objects. Above the 18 Hz resonance the
effective mass of the stack is significantly less than that of the
support table so we are neglecting the mass of the stack and are doing
a finite element model of the support structure as an elastic body.
Brian Lantz's model for the control of a BSC is being modified to a HAM
system.

  Brian has just release a new version of his BSC model which is
significantly different from the previous version.  We are currently
modifying this to accommodate the HAM model.  We have also received a
program which runs a stepped sine analysis on the DSpace system from
Katie Lilienkamp, a mechanical engineer graduate student who is
considering working with us.  This program is currently being modified
to meet our needs.

MEPI / LASTI (Mason, Ottoway, Mittleman, MacInnis, Kern):

The EPI work on HAM-13 is moving along.  Last week we completed the
installation of all 4 External Pre-Isolators and magnets.  This week
we're installing the suspension springs and load cells.  As of this
(Wed) afternoon we've installed springs into three of the EPIs, and
have them tensioned so they are suspended just above their vertical
stops.  Table alignment has held very well, considering the trauma our
inexperience is imposing on the stack.  Yaw remains <100 u-rad from our
initial position and pitch <140 u-rad.  Tomorrow morning we'll suspend
the fourth pier on its springs.  Cabling is substantially complete and
we hope to enable a MEPI system sometime next week.

HEPI (Hammond, Kern):
        #MZ: maybe also reported under LLO?
All of the fabricated components of the hydraulic External Pre-Isolator
were delivered to MIT this morning.  The machined springs are completed
and Marcel has them back at LLO for characterization. This will take a
few days and next week we will have everything in hand to begin HEPI
installation on the LASTI BSC (excluding the actuators). From the
machine shop we've received the Actuator Plate, Diaphragm, Diaphragm
Restraint, Bypass Resistor, Bypass Resistor Cap, and from HYSPAN the
order for 24 Bellows.  A first article of the actuator assembly has
been sent to Solar Atmospheres in Souderton, PA for vacuum brazing and
we're waiting to receive it back for inspection. I just received from
the machine shop the quote for the balance of machine parts (primarily
the tripod assembly) and will give to Marie Woods at MIT to issue a PO.
It looks like we'll receive the bulk of the actuator parts from the
machine shop in about 3 weeks, at which time we can begin assembly.  My
plan is to assemble 1 or 2 units as pathfinders. Unless we meet some
unexpected problems it looks like we will have hydraulic actuators
ready for installation in LASTI in late October.


Data Analysis and Computing (Lazzarini)


Simulation and Modeling (Bhawal)
SLU
--------------
Hiro visited SLU to meet with Jim Howatt, the head of the computer division of SLU,
where e2e will be installed to be used for the simulation and educational
purpose by Sany Yoshida.

S1
----
Biplab and Hiro are in LHO and LLO respectively for the S1 run and taking
shift duties.

SimLIGO
-----------
(Matt) SimLIGO_020827.tar.gz is in ~mevans/tmp/ and seems to be working.
This intermediate version of SimLIGO contains working wavefront sensors
which control the pitch degree of freedom for all core optics except the BS
(which is to be controlled with signals from QPDX and QPDY).  The yaw DOF is not
controlled because there appears to be a bug in the recycling summation cavity.
Biplab is looking into this.

The optical lever servos, still used for yaw on all optics, have been
made a little more realistic.  They now run at 16k and are routed into
the suspension controller independent of the OSEM signals.

The common-mode servo is not turned on in this version, though I suspect
it could be made to work with little effort.  I expect that on my next
visit I will get the yaw DOF working, use QPDX and QPDy to control the BS,
and upgrade the CM servo to the latest version found on the LHO 4k.

FP cavity tilt
-----------------
(Hiro) performed more calculations, analytically and numerically, related to the
time dependence of powers of a cavity with time dependent mirror tilts. The
observed "energy non conservation" is still not understood whether it is a real
physical effect, or a limitation of the modal model or a bug of e2e
implementation.

software distribution
------------------------
(Hiro, Ed maros) Worked to build a new tarbal. A new script is created to simplify
the creation of new tarbal. During this process, some ambiguous points in the
distribution / installation documents are refined. Based on this new tarbal, the
e2e softwares at LLO are updated to the latest.

(Ed Maros) created script for generating an e2e tarball.

Alfi 5
------
(Bruce)Continued work on the parser for better error messaging.

(Melody) Continued work on the automated tester for alfi5.

LIGO Data Analysis System

Software Systems (Blackburn)
At this time there has been only light use of the LDAS systems at the
sites. The DMT is generating triggers and placing these in the database and
the Reduced Data Set Frames are being generated, but only a couple of
dataPipeline jobs have  been sent to date.

[A Lazzarini note: If this is a real trend in the LIGO/LSC computing model, then we will
have to re-think the distribution of computing power at the observatories vs. universities.
Originally, we had anticipated a need to process data at a rate equal to its generation, near the
interferometers. If the collaboration does not find this useful, we should re-locate nodes
to a centralized facility where theiir aggregated power is greater than their distributed sum -- also easier to maintain.
I am frankly puzzled why UL gropus have been patiently awaiting their RDS sets to show up at their home institutions before looking at the data -- if something is wrong with S1, we will not have known for almost 1/2 of the S1 run!]

The issue with the "state data object" creation, storage and re-ingestion
that were discovered last week have been tracked down and fixed. It is now
working again. This is fortuitous since it was reported at the LSC meeting
last week that the Burst Group is ready to start using this function. This
required changes to the wrapperAPI, dataConditionAPI and the
eventMonitorAPI, as well as to the user command macros.

Several new issues in the metaDataAPI were discovered in association with
the fix for the ILWD objects with comments causing ingestions to fail. This
fix caused duplication errors when processing an ILWD with two table
contained within. This now works and a set of test scripts have been added
to the repository to allow us to track this issue in future modifications.

Several issues with resampling and the metadata used to resample were
identified by the dataConditionAPI working group. These issues have been
logged as bugs in the bug tracking system. The Matrix class was also revised
for the dataConditionAPI.

The rewrite for the frameAPI to use more CPUs has shown some mixed results
this week. Earlier it was found to work extremely well but when these
changes were integrated into CVS with other major changes, and then rebuilt
from CVS it was found to not work. This has been traced to a file missing
from CVS and LDAS is being rebuilt with this file included to see if this
fixes the problem.

There are several new examples on the web for using the frameCPP library
that is used by several packages within the LIGO Laboratory and the LSC.
These should help authors of applications more easily use the data in
FrProcData structures found in the Reduced Data Set Frames being written by
LDAS for the Science Run.

The new version 6 frameCPP is still under development. Most of the code is
in place, and in fact is now in CVS. However, very little testing has been
carried out and it has yet to be integrated into the LDAS frameAPI.

The emergency socket and operator socket code has been re-worked to be
entirely event driven. This should put an end to the partial strings
received from user requests. It may also improve overall performance in the
system.

Hardware Systems (Anderson)
Caltech
-------
(Dan Kozak)

* HPSS: Resumed migration of large files off of Redwoods (CACR took delivery of
        more 9940 tapes).

* SAM-QFS: Did more test runs simulating writing tapes at a site and importing
           them into the CIT archive. Started setting up to ingest real S1 data.

* Did some work to try to get hsi from saiph to HPSS over HPN working.
  So far, nothing that has been suggested has helped.  I'll continue to
  pursue this with Mike Gleicher and James Patton.

(Al Wilson)

* A lot of work with the CIT and TEST systems.

* Installed a new Fast Iron II switch and hooked up GigE to all of the
  machines in the CIT system (minus nodes).

* Install PCI GigE cards in Beowulf and Datacon.

* Prepped Fiber runs for the New Raid systems and the Ldas in a box systems.

* Did some house keeping in the computer room.

(Stuart Anderson)

* Started archiving S1 data to HPSS.

* Upgraded the LDAS-CIT network switch and all remaining servers to
  Gigabit Ethernet.

* Determined that the 10 Mbit/s network bandwidth to LHO is a factor
  of 2 too slow to replicated the Reduced Data Set (RDS) frames to
  Caltech in real-time.

MIT
---
(Keith Bayer)

* Loaded PreS1 data onto ldas.

* Started burntest on pc raid box (Tuesday).

* Begun loading S1 data onto pc raid box.

* Running jobs to cull out asq channel from E7 RDS frames.

* Ordering 19" rack unit and rack mount UPS.

* Got quote for Gigabit Fiber Ethernet card (Antares).

Livingston
----------
(Igor Yakushin)

* Sent 20 tapes with raw data to Caltech, 3 tapes with RDS to MIT and
  3 tapes with RDS to UWM.

* No sign of P4 RAID so far. [A. Lazzarini note: it appears that UPS lost the unit somewhere between pickup and their So. Calif. distribution hub. We are re-allocating
one of the units designated for Caltech to LLO in the interim. Lesson learned: do not use UPS!]

(Shannon Roddy)

* Ordered the remaining 7 machines for the VPN network.  They
  will be shipped to the individual sites and billed separately.

Hanford
-------
(Greg Mendell)

* Coordinated with Igor the running of tapecontrol scripts to archive
  raw frame data for preS1 injections and during S1 at LHO and LLO. The
  first 20 tapes from each site have been sent to Caltech.

* Coordinated with Isabel, Igor, and Shannon the running of tapecontrol
  scripts to write RDS output from LDAS to tape.  Currently tapes are
  written simultaneously for UWM and MIT and each site has received 4
  tapes with data.

* Working to finish the set up of the new 2 TB Raid Server at LHO. The
  burntest should end today (but was still running this morning).

Data Analysis Activities (Lazzarini)
Data Analysis activities at MIT
===============================

o Establish criteria on selecting locked segments and apply
  them on E7 bursts analysis (Laura with input from Alan).
o Document Excess Power DSO status after E7 investigations
  and communicate it to its authors (Erik).
o E7 bursts analysis bits and pieces (Stefan, Laura, Erik).
o Prepare infrastructure to reduce E7 data (currently on MIT
  disks) down to the AS_Q channel (Keith, Erik - in progress).
o Prepare infrastructure to perform sanity checks between
  various levels of reduced data (full raw frames, RDS',
  strain only). The goal is to confront analysis output on a
  statistically significant sample to establish confidence in
  the data reduction scheme (Erik, Laura, Tania).
o Setting up stochastic DSO LDAS pipeline at MIT (Tania).

Shawhan:
* Helped Anand Sengupta (IUCAA) figure out how to run his search code (prototype of
the Extended Hierarchical Search for binary inspirals) on the LDAS test
system using data from E7.  Previously, he had just been using the standalone
wrapperAPI.

* Currently re-implementing the LARS server to provide remote access to the
E7 (and soon S1) data in the HPSS archive.

Yakushin:
1) studying a correlation DSO; 2) writing wavelet DSO.

Weinstein:
- Took S1 shifts at LHO. Watched the Rayleigh monitor.
When the IFOs are in lock, it's pretty quiet - very few bursts!
- Working on running burst DSOs online,
interfacing with Duncan's online dso monitoring web tool.

General Computing (Wallace)

Lazzarini: We held a site-wide teleconference to review an IT Security Plan I drafted with input from GC, LDAS and CDS.
There was much discussion and a number of useful resolutions to outstanding issues. The Plan should bne ready in time to send it to NSF for our Fall review.

MIT:
(Keith)
-Installed updated license/version of mathematica on gc
-Removed 'lancelot' DMT machine from gcnet and dedicated it to DMT/LDAS
-Copied home dirs of remote DMT / LDAS users over to lancelot

Livingston:
(Shannon)
- Reinstalled an IDS between the LSU router and our firewall. I
have been examining the logs, and the most common priority 1
traffic seen has been microsoft web server exploits.  The
other common one is rpc.statd exploits against linux.  Most
(but not all) have been self replication type stuff.  I did
see a couple items that looked like manual network probes.
- Worked a few user support issues.
- Looked into the CalTech site licensing which just came about
in the last couple of months.  Still trying to get a
determination of whether or not the observatories are
eligible.  The person that administers this program is
evidently out sick which is the reason for lack of
responses.
- Set up a web demo of some software for this afternoon.
- Once again looking at how to effectively consolidate some of
the computer services here. (web, mail, SQL, etc.)
- Deciding where to place "Big Brother" to do network
monitoring.
- Ordered a small VPN appliance to evaluate for use here at
Livingston for local staff to use.
- Checking into a new hack that allows any attacker to lock up a
windows machine that has NetBios enabled (pretty much any
windows machine!)

Hanford:
(Christine)
- Provided comments to Albert's IT Security Plan Document.  Attended a
meeting on Thursday morning to discuss the document.
- On vacation the rest of the week.

CIT:
(Mike)
-Taking Microsoft training courses for the next few weeks.

(Wendy)
-Finished loading software and ghosting two machines, including one
high-end user machine
-Worked on restoring tapes
-Delivered mail to 40m house
-Random tasks, such as printers

(Veronica)
- LSC website: re-worked a database of meeting transparencies to add a
table for closed session talks. Posted remaining talks as they kept coming
in. Tracked down a problem with one of the database tables that was
causing an error message on loading.
- LIGO website: rewrote a webpage for other GW projects with LIGO-related
activity; the new page is now posted.
Working on webpages for the upcoming Aspen 2003 Winter Conference.
Posted a link to the new Visitors Program webpages.

(Lisa)
- Vast and voluminous amounts of work on the mailman/mhonarc/webglimpse mailing
list system.  This includes helping folks configure their privacy settings and
setting up apache authentication into the archives.  Next I will be looking at
how to automatically filter out administrative notices from the archives.
- Worked with ITS security as questions/problems came up.

(Bruce Sears)
- General Ilog Maintenance:            (0.5 days)

(Larry)
-Spent a deal of time working on printer fixes. One issue that came up was HP
not having recorded our extended warranty after many hours on the phone I
finally was able to get a person to look into the issue.
-Worked a couple of IT security issues. Both were viruses on machines. Both
machines did have the latest virus-scan files. We've not had time to track down
how the machines were infected but both machines were rebuilt.
-Working a number of VRVS issues. Still trying to get better resolution out of
the system.
-Performed a few more network tests with new WAN connection at Hanford. I was
able to get 4.8 Mb/s on a steady basis, which is a big improvement over the
past.
-Worked a number of procurement issues and spent time reconciling items on the
P-card. Reconciling orders has become a real time sink but I guess it beats the
alternative.
Distributed a number of items to various users.
-Helped DCC out on a couple of file downloads/fixes as well as checked out one
of their pc's that was having a problem. So far nothing major but we will keep
an eye on it since it was a unit that needed a major h/w overhall a few months
ago.


LIGO II/Advanced R&D (Sanders)


From: Peter King <pking@ligo.caltech.edu>

2.2 AdLIGO PSL

    Testing of the frequency stabilization related electronics destined for
the University of Hannover is about to commence.  Thus far only the VCO has
been tested whilst the laser has been checked out with the PSL Lab's set of
cards.
 

From: "Mark Barton" <mbarton@ligo.caltech.edu>

    This week I attended a training session on the use of the dSpace
controller system at the dSpace facility in Michigan. I also submitted a
report and request for information about a weakness I encountered in the
system: the output of some Simulink blocks (e.g., the elliptic filters)
can depend critically on the order of the ODE solution method selected
and it's not obvious what order will be adequate in a particular case.

From: Bill Kells <kells@ligo.caltech.edu>

Besides usual monitoring of ongoing sapphire development
issues (with
Garilynn and J. camp) I've been focusing on the newly
brought up issue
of "flattop beams" . We (Erika and I) had done much work
(~ FFT simulations)
on this in the past but put it asside as a "beyond ADvL"
project". so
we are revisiting. Working now to have something
coherent to contribute
next week (by phone).

Also working on other simulations pertinant to AdL
design (normal Gaussian beams)
using FFT and e2e (have actually spent large amount of
time this week on
algorithmatic issues I found: with Hiro and Biplab).
Overall focus is on problems
pertaining to the upcoming downselect.
 

From: ctorrie <ctorrie@ligo.caltech.edu>

Advanced LIGO Suspensions

I) Mode Cleaner

i) Cantilever Blades
See report from Janeen Romie
ii) Wire Jigs
Mike Plissi and I have measured all of the wires for the 3 stages of the first prototype suspension. Mike has recommended a couple of small changes that have been incorporated into the design.
iii) Masses
The 3 masses have been assembled successfully, this has taken longer than expected as we have been organising our delivery of silver plated and stainless steel bolts.
iv) Coils
GEO should be delivering the coils for the mode cleaner this week.

II) Workshop
Both the Physics workshop and Central Engineering have been delivering the last of the piece parts for the suspension.

III) Single Pendulum Experiment
Norna Robertson and I have been analysing some initial results taken by John Veitch on a Single Pendulum with crossed blades and 2 wires off one blade. We are interested in extending our bank of results on how big an effect the crossing of the blades and 2 wires off one blade has on the pitch mode of a pendulum.
 

From: Janeen Romie <romie_j@ligo.caltech.edu>

AdLIGO Suspensions
Superior Jig has delivered four large MC blades. Calum and Mike Plissi have been characterizing them, finding curious results. The balance of four more large blades will be delivered from Superior Jig, via Gina courier, tomorrow morning. Four more small blades will be shipped from SJI on Friday, 8/30. Superior Jig made these blades by EDMing them out a billet of maraging steel. I will be picking up the Lobart blades, produced by the traditional rolling process, this afternoon. It will be interesting to compare the results of these blades, made from two different processes.
I've spend most of the week procuring parts or chasing procurements for the AdLIGO MC prototype suspensions or the new osem assemblies.

Working with UFl on penultimate mass designs. It's good to start interfacing with them.
 


For additional information about this report, contact sanders@ligo.caltech.edu