|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday August 12, 2002 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
Special Items:
no report
LIGO Operations--Administration
There was a site teleconference held on Thursday, August 8, 2002. The following issues were among those discussed:
1) Nile Virus Situation in Louisiana--minimize work outside, avoid dawn and dusk work outside, acquire and provide protective clothing. With regard to risk being small, statistics don't cut it. LIGO is expected to be good steward of public funds provided. Some things that we can do. Make sure that we have a healthy fish population in the ponds. Primarily along the y-arm there are some areas that are swampy that could be filled and dried. Oil sprays are effective but have to be reapplied after every rain, and it rains so frequently that it is not practical.
2) Finishing and Furnishing Staging Building at Livingston--Draft RFP for time and material contract to finish and furnish the offices at Livingston has been prepared for review. Physical Plant people recommend as much quantization as possible. Also supposed to have a drawing of the proposed office configuration. Only thing received so far is a brief statement of work. Action #106 retained open.
3) Telescope Building--may need to have an architect that has access to a mechanical engineer.
4) Traffic Control at Livingston (New Action #112)--Need to investigate approach for Livingston to control traffic and increase security. There are local security companies that can make an assessment and provide a bid. At Hanford a gate with two arms located just to the OSB side of the Laboratory Building is proposed under the control of the control room. One objective is to keep traffic as far as possible from the interferometer. Key issue in Livingston is geography for parking.
5) End of July Costs and Budget--From a cash flow point of view, at the end of September we should have 5.5 million left to help with expenses during the first month or so of FY 2003. However, it is emphasized that these funds are all spoken for. Items have been deferred that must ultimately be covered by FY 2002 budgets.
6) Outreach--budget for incremental outreach was zeroed when the five year budget was reduced from $175 million to $160 million after direction received last year from the NSF. The budget for incremental Outreach is still zero in current budget for FY 2003. This needs to be worked (Action #113).
7) Livingston Staging Building HVAC--Finger pointing. System needs to be balanced, and we are getting the system balanced. We will then negotiate to retain compensating funds from the contractor.
8) Livinsgton Staging Building Auditorium Floor--going to withhold value of floor from retained funds. Will be negotiated with contractor. Estimate $30,000.
9) Hanford Laboratory Building--LSC meeting in Hanford in nine days...still do not have air conditioning, carpet may be about to happen, electrical still to be done. Completion of facilities sufficient to support LSC meeting is going to be close. Will also need to be cleaned.
10) 'Gator for Livingston--Request from Livingston for some kind of inexpensive vehicle for carrying stuff around the swamps (Military version available from John Deere).
The list of current actions revised to reflect
the status of open actions assigned through August 8, 2002 may be found
at ACTION
LIST.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
ACTIVITY
| WE 08/08/02 | Packages | Faxes |
| In | 34 | 21 |
| Out | 16 | 31 |
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA .
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
SUPPORT (Baldon, Torres, Lloyd, Tischler)
>Irene Baldon
Oracle will be upgraded to the 11i level and the system will be shutdown campus wide next week August 16-22 for the upgrade. For those of you contemplating a large purchase or have an invoice that will require payment during this time period, it is suggested that you submit your requisition(s)/invoice(s) no later than 5 PM, Wednesday, August 15. Note that for emergency procurements, our group will have a block of numbers pre assigned and will be able to prepare and order off line. -pel]
>Rita Torres
Progress Period from 08.01 to 08.08
Accomplishments:
The following change requests have been submitted:
| CR-010012
Revision B |
WBS 1.4.4.1 | Closeout Construction Budgets for Initial Computer Equipment Complement at the Sites | P. Lindquist |
| CR-020008 | WBS 1.1.4 | Purchase and Install Audio Visual Equipment in the New Hanford Auditorium | O. Matherny |
| CR-020009 | OPs | Digital Common Mode Servo to Mode Cleaner Path | D. Coyne |
| CR-020010 | OPs | Additional Funding for Low Frequency Seismic Isolation | P. Lindquist |
| CR-020011 | OPs | High Power Test in Suspended Interferometer (Gingin) | D. Coyne |
| CR-020012 | OPs | dditiona Funds to Complete 40-Meter Facility Upgrade | A. Weinstein |
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
No report.
Summary of Commissioning Activities at LIGO Hanford Observatory (compiled
by F. Raab)
-------------------------------------------------------------------------------------
(see ilog for details - if it's not in the ilog, it didn't happen...)
This was a frustrating week with no progress on commissioning despite
a lot of hard work. Eventually some issues were sorted out which should
allow better progress next week.
2K IFO Repair
-------------
We had generally good locking behavior for the machine and were able
to run in common mode most of the time when there was no downtime for other
work. The main issue was to get light levels up at the antisymmetric port
to hopefully return us to previous sensitivity above 300 Hz. Then we would
investigate alignment issues. We know we have some clipping of beams coming
out of the vacuum system in the current alignment that may need attention
prior to S1. We also see some "mechanical-looking" noise peaks in the 100-300
Hz range that come and go. Normally we would have liked to clean this up
first, but with limited time before the S1 run we did not feel we could
linger on this unless it was a proven show stopper. We ran into more problems
than expected trying to get the new EOM shutter configuration implemented.
This has now been weeded out. During running time, we encountered some
problems with strong transients that were traced down to voltage fluctuations
in the PZT mirror prior to the mode cleaner. The reflected spot from MC1
noticeably hopped in sync with the transients. Eventually Josh found that
this system had been acting up since the quake just before the wire-cutting
incident that stalled S1. The PZT control board has been replaced and behavior
is much improved although we are attentive for any further problems.
4k IFO investigations
---------------------
The effort ot implement common-mode servo has been set back by confusing
measurements of transfer functions. Eventually it was found that we had
been plagued by saturation in the mode cleaner DSC for MC2. This was relieved
by jumpering out some dewhitening filtering. Eventually we may need to
restore to higher filtering for noise issues, but we should be able to
make a lot of progress with the current level of filtering. Work continues
on.
We have had a stability problem with timing on the 4K that was improved
by reconfiguring clocks.
FACILITIES
------------------
Carpeting is being installed in the office wing. Carpeting will be
completed Sunday evening in the auditorium. All the audio/visual equipment
is on hand except the podium. The system has the capability to be operated
manually without the podium, if need be. The bathrooms are complete.
The
HVAC system is still not operational, it could be a sticky situation
if it
is not complete by the LSC meeting.
HEPI: Final efforts have been made to pick up all redlines and drawing
improvements for the HEPI Drawings. (sheets 1-32) All of the sheets have
been forwarded to P&N (the fabricator from Houston) and the first batch
of parts should be completed by the end of this week and received by early
next week. We have every indication that all is going well with the fabrication.
The machined springs are being fabricated in Lafayette, Louisiana by Digital
Machine. The promised fab date is this coming Monday (the 12th) and they
have given every indication that they are right on target. All of the drawings
for HEPI and the machined springs are backed up on Basin due to the potential
of hard disk crash. (which was the case in fact. Shannon, Tom and myself
spent a good amount of time recovering and rebuilding the operating system
with no loss of data) All of the parts, drawings, and PDF's are there as
well as Autocad translations under the following three folders: actuator,
hydraulic_acuator, and DSCW D020408 (double start Counter wound) They are
in my home directory ~mhammond on Basin and are available for read access.
The pieces parts and instruments that we have accumulated for Advanced
LIGO will have a new home in the new building in the back storage room.
You can contact me if you need information on any of the equipment. First
batch of parts for the actuator is expected next week. Also promised on
Monday is the set of 8 machined springs for LASTI-HEPI. We've issued a
PO to the machine shop doing the springs to assemble, braze and plate the
springs for which they promise an additional 2 weeks time. HYSPAN states
that they will ship the bellows on Aug 15. Hammond, Kern
Work continues on the implementation of the PEPI actuators on ITMx and
ITMy in preparation for the science run.
CDS: Finished installing Big Brother software on all the CDS Sun workstations.
Edited the conf file to set alarm limits. Studying the working of Big Brother
to add temperature monitoring of sun workstations to the web reports. Created
a web - perl - epics interface to have a big brother medm screen showing
the status of CDS SUN WORKSTATIONS. Created a database file with 150 channels
for the cds big brother system and loaded it on the pem processor in the
mass storage room. We now have a centralized medm/epics monitoring of the
SUN worksations on CDS. Added 4 more channels for PEPI to the master.config
file and rebooted the DAQ. Changed the SUN workstations in the control
room to 24 bit color mode. Added more documentation to the CDS Redbook
at LLO. Chethan
We continued the characterization of MMT3 motion, taking into account HAM1 table motion. We made two new MMT3 e2e boxes for this purpose. The first box takes HAM1 table motion as the input to the suspension point and computes optics motion relative to ground. The second box takes ground motion as the input to HAM table box, which is part of the MMT3 box, and computes optics motion relative to ground. Currently, the HAM box uses seismic correlation measured at LHO. We are planning to make seismic coherence measurement at LLO so that the HAM box can take more realistic input. The new MMT3 boxes run under the new release of e2e (version 1.7.7). Dodda, Yamamoto, Yoshida
First batch of parts for the
actuator is expected next week.Also
promised on Monday is the set of 8 machined springs for LASTI-HEPI.We’ve
issued a
·Pump Station (Ken Mailand)
LIGO
SEI RETROFIT
HYDRAULIC
PUMP STATION:
SYSTEM
OPERATION
System
being upgraded for tests and shipping to MIT.
TEST
OBSERVATIONS
Finished
setup to do tests at all [5] sensor locations with various accumulator
pressures,
and
speed/flow settings to get a basic data set.
ON
GOING
A
new pump mount adaptor has been cimpleted to attach the existing motor
to the new screw style pump.
A
new aluminum coupling has been modified for the existing pump, and new
screw style pump.
A
new Buna coupling spider material will be tried to smooth flow ripple.
The
existing motor pump adaptor will has been modified [opened] to allow air
flow thru coupling area.
The
motor will be detached from the base and allowed to contact the floor independent
of the
station
plumbing base, with brackets with the hope of further isolation of vibrations
from pump and motor.
New
Base board is ready which is more stable than the current and of a more
durable material.
ELECTRONIC
SENSORS
Sensors
are being electrically isolated from the piping.
MANIFOLD
[fluid distribution]
The
manifolds [5] with their mounting bases are finished, including hardware
and accumulators,
with
the exception oftapped holes for
the pressure sensors
TESTS
Start
tests 8-1 at several accumulator pressure settings to optimize the operation
of the pump isolation.
Determine
which improvements or modifications might be made to improve performance.
DESIGN
A
site installation version of the test pump station to be designed, when
final configuration is
known.
This would be more compact, have a mass dampened mount base, and be in
an isolation
enclosure,
to control temp and exhaust vapor.
STANFORD
[information needed from]
A
range of acceptable viscosities will guide us in the design, re. the allowable
temp rise of the oil in the system.
An
acceptable sensor for the main distribution manifold ‘Brian’
MIT
Sent
ref. motor data to Myron re. voltage and phases.
The
oil to ship with the rest of the pump station.
Distribution
manifold drawings were sent 7-2 to MIT to show the configuration, and the
pillar attaching method.
Need
to design and build a bypass resistor for MIT configuration. [need pressure
drop requirement]
SHIPPING
A
quote is in, est ~ 1 week to deliver.
A
large box crate is ready for shipping all items not on bases.
LAYOUT
DRAWING
I have finished a scale plan
view and partial elevation [acad 2D] layout drawing, of station component
assembly.
Mason, Ottoway, Mittleman, Megan,
Kern
No report.
John Zweizig reporting:
This week I continued to prepare the
DMT software for S1, including tagging and testing
version 2.2.3.
1.Shipped
all the remaining items for the MEPI pre-isolator to MIT this week.All
items have been reportedly received intact. 2.The
boards for the 8 channel valve drivers have been stuffed and mounted in
a box.They have BNC inputs and DB-9
outputs.I will test them this week. 3.Wrote
an initial definition for the motor speed control servo to be used in the
hydraulic actuator.Initial design
has started. Jay Heefner reporting
Jay
will be attending the IEEE EMC symposium in an effort to develop industry
contacts. a.
We had a 23.71 Hz oscillation on the MC1 PD readback that was the dominant
noise source for that optic.Dennis
Ugolini and I made and installed a Q of 100 digital notch filter that effectively
attenuated this peak below the bounce mode level. b.
Bob has started wiring the cross connects of the 1X1 auxiliary controls
rack. c.
I have been helping in the effort to lock the mode cleaner, by debugging
and troubleshooting suspected electronic contributors to the locking difficulty. d.
I am still redesigning the ISS DC photodiode with updated features and
footprints. 2.1
Engineering and R&D Installation
of the phase-correcting Pockels cell does not appear to
have altered the output of laser #119.The
output power of the laser on delivery
was measured to be 10 W.After tweaking
the alignment, the output power
was measured to be 11 W.However in
the days since the re-alignment the
output power has fallen back to 10 W. Some
parts for the experimental VCO have arrived. 2.2
AdLIGO PSL After
last week’s systems telecon, I discussed with Benno the schedule for
the intensity stabilization.I suggested
a rough schedule, which will be
put together later, in which we had broad agreement.After
going through
the schedule presented in last week’s meeting, I will tie in the PSL
schedule. Benno
also told me that LZH have cracked the 100-W barrier.Admittedly
the output
of the laser is multi-mode at the moment but it is a significant milestone.Mode
control apertures will be inserted in order to obtain single-mode
operation. Dave Ottaway
Input
Optics Ray
tracing calculations were performed to determine the maximum safe angular
misalignments of the MMT input optics. By safe it is meant that the
5 Watt beam cannot reach the suspension wires. Sideband
Imager This
program has been limited by the distorted phase images that the The metrology lab has developed another
bug. It appears that one of the "Johnson Controls" heater controller modules
has gone on the fritz. The temperature climbs until it reaches it's safety
shut-off. I'm hoping it's a simple replacement.
Bill Kells
Since
returning from been
mostly occupied with analyzing data which I
measured on the 2k for determining the COC optical performance: 1.
mirror blemish identification 2.
Arm visibilities 3.
Best interferometer alignment (are beams clipped?). 4.
Mirror microroughness scatter (comparative via “scatterometer”). Some
very promising intial result! Then
also: Planning OTF contamination and RTS upcoming work/upgrades, AdL
optics issues (sapphire downselect). Erika D’Ambrosio
I
have been working on the “parametric instability” for the general case when
the excited mode is not a TEM00; the dangerous case is when an
excited mode having a lower resonating frequency is excited. I
am finding this cannot happen since the transition is forbidden. I
used the formalism of discretized modes but I want to translate that in
an “interference problem” for an easier presentation at the LSC Meeting. I am also collecting the previous
notes that constitute our first paper on this subject that has been accepted
by Phys. Lett. A but remains unpublished.
CDSGDS Software
CDS Hardware
PSL/IO
Optics Characterization and Analysis
Garilynn Billingsley
Optical Contamination Cavities
Contamination
Cavity # 1
It
is pumping and baking is in progress as right now.
New
Lab at RSE
Cavity
#3 Reference Cavity still pumping down. RGA scan taken and the sum of masses
(amu:41,43,53,55
& 57 ~ 4E-12 torr. It is considered clean cavity.
Cavity
waiting for the laser to be aligned into the cavity.
Cavity
#2 Test cavity
This
cavity is pumping now.waiting on
optics installation and laser alignment.
OTF
Lab
The
refurbished 100mw NPRO S/N 267 Laser from Lightwave is running now on the
new optical table used for the transmission test setup. We are continuing
measurementof transmission and reflectance
of some partially transmitted mirrors and beam splitters from REO.
I
have finished refurbishing another vacuum pump unit and it is being used
to pump the cavity#1
Laser
warning signwiring and assembling
is in progress.
no report
no report
no report
Simulation and Modeling (Bhawal)
E2E weekly Physics meeting
-------------------------------
Biplab presented some results on degeneracy of the recycling cavity
and comparison
between FFT and E2E outputs. Bill Kells, Hiro and Biplab discussed
about proper
ways of making such comparisons and some anomalies in results.
PC Linux for e2e simulation
-------------------------------
(Hiro)For the fast simulation of e2e, multi fast (~2GHz) CPU PC running
linux was
decided to be purchased. The final choice will be a quad CPU unit at
1.7GHz XEON.
This will run 4 times the speed as compared to 400MHz SUN box. The
speed benefit
will be more for running multimode case, and even more when a new simulation
code
will be implemented, which will utilize thread even more extensively.
Mechanical simulation at LLO
-------------------------------
(Hiro) The e2e package was installed at LLO, and Sany and Raghu worked
to model
the HAM table on which there are several mirrors hanging. This setup
is used to
understand the motion of mirrors due to the seismic motion together
with SEI
characteristics. The measurements will be used to validate the simulation
of
mechanical parts and to generate the inputs for the simulation to make
it more
realistic. Some of the SimLIGO boxes were modified for this use.
COC phasemap
-----------------
(Hiro) Basic software development is almost over, and the actual mirror
data
will be used to generate the full map and to calculate the mode decomposition
matrix. Adlib needs to be modified to accept arbitrary mode mixing
matrix
and to generate necessary data file on demand.
Code development and maintenance
----------------------------------
(Hiro) Internal code developments to add new capabilities and improvements
of
the existing modules are going on, especially the FUNC modules - support
of bundle inputs and outputs and speed improvements.
(Biplab) A variant of the Han2k model, the Han2kFP model specialised
for studying
single-arm locked state of the full LIGO was modified so that multimode
studies could be made using it. Bill Kells requested this. This new
version
with a simple README file is now available for download from our homepage.
(Matt) Began restructuring of internal E2E field model.
Alfi
-----
(Bruce)
- Fixed several bugs and implemented several small features involving
ease
of use in creating connections and manipulating them.
- Continuing work on implementation of repositionable ports in the
external view of a node.
(Melody)
- Working on the automated tester for alfi5. Evaluated other testing
package
frameworks. Found one that is able to record the events
from alfi5.
Also fixed some PRs.
LIGO Data Analysis System
Software Systems (Maros for Blackburn)
Software Systems (Edward Maros for Kent Blackburn)
This week saw the release of LDAS 0.4.0. It has been installed at LHO, LLO and MIT. This version of LDAS will be the one used for S1. No new features will be added for S1.
Work has started on the creation of two new commands to LDAS to support the GriPhyN Project. These commands are dataStandAlone and putStandAlone. They effectively break the dataPipeline commnad into two parts. The dataStandAlone retrieves frame data and does some processing and data reduction. The putStandAlone retrives the GriPhyN results and ingests them back into LDAS. The code has been written and is currently being tested on some local systems.
Work has also started on supporting a single server in the datacondAPI to communicate with the wrapperAPIs. This is being done to reduce overhead and increase system reliability.
The frameCPP library continues to be worked on to bring it into conformence with the Frame Version 5 spec.
Efforts continue to increase the through put capabilities of the frameAPI. Currently, code is being reviewed and excessive mutex locks are being removed.
The datacondAPI's documentation for linfilt has been expanded in responce to user's request for clarification. The abs(), real(), and imag() actions are being modified to preserve the input type for the output type. This feature will not be available for S1.
LDAS source code continues to be corrected to fix minor problems.
Hardware Systems (Anderson)
No report received (Anderson is out of the country through 23 August)
Lazzarini: 2 2.5 TB RAID units have been ordered (1 ea for the LDAS installations at the observatories). These should be ready for S1 to hold reduced data sets, etc.
The same technology is planned for a ~20TB cache system at LDAS/Caltech to support spinning-media copies of the S1 data for user access without relying on HPSS. In addition, this cache will be enable us to evaluate SAM-QFS performance as we make a final decision on this product.
In addition Bayer at MIT is also ptesting a prototype 2.5TB device. It will eventually be installed at MIT to augment its LDAS disk cache volume.
Data Analysis Activities (Lazzarini)
Shawhan:
* Revisited veto optimization for E7 inspiral search. Evaluated
the
efficiency/deadtime for Sergey Klimenko's "WaveMon" veto events, comparing
to the absGlitch and template-based veto events. Tracked down
a bug reading
which caused the deadtime to be substantially overestimated for absGlitch
events, and also interfered with the efficiency calculation.
The upshot is
that the veto performance for L1 is better than previously thought.
* Helped Carl Ebeling and Nelson Christenson with software to evaluate
potential veto channels for the low-noise data collect at LLO on July
11-12.
Creighton:
T. Creighton finished writing a multi-detector injection program, and
debugged signal generation code for pulsars in binary systems.
Yakushin:
Writing lalwrapper part of the correlation DSO
Weinstein:
- Running more simulated burst injections
into E7 playground, at ldas-mit
- Ran full E7 H2/L1 double coincidence data through three
burst DSOs at ldas-mit,
dealt with bookkeeping and database complications.
- Running tests on various burst DSO modifications.
Katsavanouidis et al:
E7-Bursts work continued as follows:
o Stefan: vetoes generation on entire E7 set completed and
documented. Veto events are stored in appropriate DB table.
Bookkeeping information is on MIT's CVS repository.
o Stefan: continued debugging and testing MICH_CTRL/AS_Q veto
routines within the event tool.
o Laura/Jacob: completed re-analysis of TFClusters DSO (on
playground data) in separate bandwidths. Work reported on
2002-08-06 Bursts conf call.
o Erik: looked at E7 software injections (ZM/sine-gaussians)
in order to establish sensible threshold and sensitivity
for the excess power statistic DSO. Work is in progress.
Immediate goals are for the next 7 days:
o run the analysis defined on playground to the entire E7 set
o work with Sam Finn and Peter Saulson on preparing the Bursts
E7 final report.
General Computing (Wallace)
MIT:
(Keith)
-Installed star office on several machines
-Configured networking on several laptops
-Ordered several more IP addresses
Livingston:
(Shannon)
-Received a report from Larry that phillip.ligo-la.caltech.edu was
an open mail
relay. I will be blocking this machine at the firewall.
-Attending the Usenix conference. I learned some valuable stuff in
the
VPN class. This builds on what I have been testing for LDAS,
and could
be useful elsewhere, such as "road warrior" VPN access to GC.
(Tom)
-We are continuing to work on the upgrade from Solaris 8 to
Solaris 9. So far things are going smoothly, and there have
been no major compatibility problems.
-We have ordered a Sun V120 to test in a server application.
-We are discussing with Bell South the possibility of improving
the lines for our analog modems.
Hanford:
(Christine)
- The LHO network has been upgraded to 10 Mb ethernet, unfortunately
there are errors and the performance is not what we had hoped.
I'm
still working with PNNL and Larry Wallace to try to improve the
performance and eliminate the errors. Right now PNNL believes
the
errors are caused by running ethernet over a distance of 26 km, anything
over 10 km is outside the recommended specs. If we can't resolve
the
problems we will have to go back to T1 next week.
- Continued network setup for the LSC meeting. Projectors and
laptops
on loan from the other sites have started arriving. Allocated
125 IP
numbers to be used by DHCP for the LSC.
- Provided the usual user support for e-mail, file access, and printer
problems. Purchased some more network supplies for the new building
and
LSC meeting.
CIT:
(Veronica)
- LIGO website: working on a webpage of commonly used e-mail lists.
Working on an updated webpage of LIGO-related experimental groups.
Posted various updates the LIGO website.
Provided user support for the GNATS database.
- LSC website: posted various updates to the LSC August meeting
announcement page.
Reworked the list of talks to be presented; as it grew out of proportion,
separated it into past and future talks.
Updated the MOUs list.
Working with Rita and Irena on a new document for LSC participation
count and FTEs.
- CaJAGWR website: processing videos of the last two seminars, to be
posted.
(Lisa)
- Got quotes for an SSL accelerator board for the webmail server.
- Began working on the tape restoration project. We are restoring
old 8mm tapes
and then writing the data off to AIT-2. This also allows us to
generate an list
of all the files restored. Trained Mick and Wendy on how to do
this.
- Changed the Matlab startup scripts so that when the licenses on sirius
are all
taken matlab will fail over to the ITS license server.
- Ran more patches on algol to try and fix the xlock problem Szabi
was having.
- Updated the firmware on all of the Orinoco access points. This
should improve
the wep and allow visitors running XP to connect.
(Mike)
-Worked on a LapTop then ghosted it for loaner pool.
-There was a problem with the Roster webpage.
This turned out to be a licensing issue that is corrected.
-Loaded MatLab software for two surf students.
-Upgraded Mike Smiths computer. This turned out to be a big job for
I had to
flash BIOS and download all drivers for intergrated hardware. Then
I
had to reload Mathematica, Norton, Acrobat distiller and print drivers.
-I had a lot of reconfiguring to do on Clevelands computer due to an
upgrade
from win98 to win2000. This included reloading software and installing
print
drivers. Then there was some networking issues that I had to correct.
-Ghosted Ed's computer and am helping Wendy on upgrading his computer
to
win 2000.
-Ghosted Rita's computer to get her ready for an upgrade to win 2000.
-Working on antares but have been coming across a few
problems but am with Time Target and WebBase and have corrected these
problems.
I ran a test on the new Antares Server this morning, which failed.
I still
have some database issues and more testing that have to be worked out
before I can swap this server out.
(Wendy)
-ghosted and upgraded machines to win2k with Mike
-did one clean rebuild to win2k
-helped users with minor computer problems
-working on documentation for upgrading to win2k, with the problems
we've
encountered and how we got around them
(Larry)
-Been a busy week in the procurement and financial arena. A number
of
maintenance contracts have been renewed with two more in the works.
Setup a new
account with Florance for the WAN connection for Hanford. This should
be out
soon. Tracking a few procurements for the LDAS group .
-Worked with Veronica and Mike on Solaris server configuration. The
gnats s/w
will be moved from a LDAS box to a GC server. Veronica will be the
new caretaker
for the gnats system to be installed on the GC server. The installation
should
wrap up in a week or so.
-Installed IDEAS version 9 on to sargas. The major problem on the install
was
getting to talk to a live person at EDS which now own IDEAS. Since
we had not
upgraded for the past few years they dropped us off their maintenance
list which
caused problems in getting licenses for the latest version of IDEAS.
There is
still some configuration that needs to be done but I will need one
of the main
users to get involved with that part of the install.
-Worked more on the cabling of the server room. Setting up a new KVM
switch
which is working well so far. Also, rebuilt another of the Solaris
server units.
-Worked on the WAN installation for Hanford, remotely. This has been
a real team
effort: Richard McCarthey, Christine Patton, Albert Lazzarini, John
McCoy,
Cullen Tollbom and representatives of NoaNet, have all put in a deal
of time and
effort on this project.
Presently, there appear to be a number of issues to be resolved. We've
shipped a
newer router to the Hanford site which should take care of two issues;
too many
media converters and more speed for handling rule sets. The present
router hits
100% of cpu usage when the T1 line becomes saturated. Christine was
going to
change the rule-sets to see if this would help lower the workload on
the CPU.
Once the installation and changes have taken place we will run a few
more tests
to see where we have to go from there, but down time should be minimal.
-Assisted a couple of SURF students with computer issues.
-Restored a number of files/directories for different people.
-Worked a couple of virus issues and a large number of spam issues.
We are blocking a large number of ISP's and domains. We are working
on a list to
publish to see if there are exceptions that should be made on who we
are
blocking. If you receive a 550 error on a e-mail you send to someone
please let
us know so we can adjust the access list for that person.
From: Peter King <pking@ligo.caltech.edu>
2.2 AdLIGO PSL
After last week's systems
telecon, I discussed with Benno the schedule
for the intensity stabilization. I suggested a rough schedule,
which will
be put together later, in which we had broad agreement. After
going
through the schedule presented in last week's meeting, I will tie in
the
PSL schedule.
Benno also told me that LZH have cracked the 100-W
barrier. Admittedly the
output of the laser is multi-mode at the moment
but it is a significant
milestone. Mode control apertures will
be inserted in order to obtain
single-mode operation.
From: Janeen Romie <romie_j@ligo.caltech.edu>
AdLIGO Suspensions
Five local machine shops are working on our mode cleaner controls prototype
suspension parts. We're still on track for a mid-August delivery on most
items. Working on more design details.
Still working on osem procurement process.
Attended a second meeting with Norna, Glasgow, Phil, Mark and Szaby
on eddy current damping.
From: Helena Armandula <ahelena@ligo.caltech.edu>
Advanced LIGO Coatings
SMA / Lyon
The coating lab is closed until the last week of August.
Jean-Marie has been manufacturing thin films on which the Ta2O5 is
modified by doping. He tries to change Young's modulus in the film, expecting
to improve the material's mechanical loss.
He'll be coating "Q" substrates, with what he thinks may be the best
material combination, when the lab resumes operation.
MLD
Nb2O5 / SiO2 coatings are going to be annealed at 400º C following
MLD's annealing procedure.
400º C seems to be the maximum temperature at which MLD's coatings
can be safely annealed.
Wave Precision
Wave Precision (formerly GO) will deliver "Q" substrates next Monday
(August 12th) coated with 30 layers of Ta2O5 / Al2O3.
The object of this coating run is to see if "Q" results differ between
same coating materials coated by different vendors.
Previous "Q" results, indicated that Ta2O5 / Al2O3 films, manufactured
by Wave Precision, had lower mechanical loss than Ta2O5 / SiO2 films, however,
results from MLD's coating run (Ta2O5 / Al2O3) showed higher losses.
Most information on "Q" substrates as well as absorption loss results
can be found at:
http://ligo.caltech.edu/~coreopt/AdLIGO/AdLIGOindex.htm
Interferometer data, before and after annealing of MLD's Ta2O5 / SiO2
coating run, can be found in the DCC (docspublic) under doc. #:
E020741; E02742; E02743 and E02744.
------------------------------------------------------------------------------------------------------
LSC LASERS WORKING GROUP
Minutes of telecon Aug 1 st 2002:
1) updates
LZH
- got 100W multimode operation of resonator with
two laser heads for 360W of pump
light, no saturation of slope curve so far, did
not try higher pump power because power
meter was limited to 100W
- put in quarz rotator rotator for birefringence compensation and brewster
plate to force
polarized operation, this reduced output power by 5%
- plan to change resonator and insert aperture to optimize beam profile
Stanford
- power supply of Lightwave Amplifier had problems and was replaced
by Lightwave
- during realignment of first edge-pump slab the beam hit the spectralon
which caused the
slab to crack
- will use spare slab to replace the first edge pumped slab, and continue
to work on the
triple pass of the second edge pump slab once the first one is back
up
Adelaide (update from Jesper by eamil)
The news here is not too hot. We have determined that our super expensive
and specially grown crystals were not manufactured to our
specifications..and are not useful as they are. We are shipping them
back
to
the manufacturer. We think that the problem cannot be corrected by
further
polishing. Our special slab design is not very forgiving to errors
in
manufacturing.
Where does this leave us?
We are ordering new material to cut new crystals, while hoping that
we will
also solve the problem with the present ones. This means that in the
worst
case we will have several good ones...and perhaps too many, but we
feel we
cannot wait.
Still, we cannot avoid a delay of several months.
In the meantime we shall study thermal birefringe at lower power with
an
imperfect crystal, and we shall also attempt to assemble the final
resonator, even though we cannot run it up to very high power.
next conference call: Sept 5th
For additional information about this report, contact sanders@ligo.caltech.edu