|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday July 29, 2002 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
Special Items: Status towards S1, report on EMI/RFI visit with Nat. Radio Astro. Observatory
no report
LIGO Operations--Administration
There was no site teleconference held on Thursday, July 25, 2002.
The list of current actions revised to reflect
the status of open actions assigned through July, 18, 2002 may be found
at ACTION
LIST.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
ACTIVITY
| WE 07/25/02 | Packages | Faxes |
| In | 39 | 28 |
| Out | 12 | 31 |
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA .
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
CONSTRUCTION:
The wooden auditorium floor of the LLO Staging Building has been accepted. As a result, the check in the amount of approximately $48,000 for the last invoice, that has been held for nearly three months, has been released. This leaves $110,000 in retention still being held. The only outstanding issue concerns some problems with the HVAC. These may be resolved under our warranty.
The LHO Laboratory Building remains on schedule, but completion by the LSC meeting of August 19 will be close.
OPERATIONS:
Evaluations continue on ways to regulate vehicular traffic at both sites in order to reduce discernible noise. So far, gates with cameras operated from the control room seem like the best candidates.
SUPPORT (Baldon, Torres, Lloyd, Tischler)
>Irene Baldon
Oracle will be upgraded to the 11i level and the system will be shutdown campus wide August 16-22 for the upgrade. For those of you contemplating a large purchase or have an invoice that will require payment during this time period, it is suggested that you submit your requisition(s)/invoice(s) no later than 5PM, Wednesday, August 15. Note that for emergency procurements, our group will have a block of numbers pre-assigned and will be able to prepare and order off-line. -pel]
>Rita Torres
Progress Period from 07.19 to 07.25
Accomplishments:
Schedule 07.26 to 08.01:Out of the office Monday the 15th though the 19th. Traveling to MIT / LASTI to meet with Mike Z. regarding Adv. LIGO ISC cost and schedule. Out of the office Thursday the 25th through Monday the 29th attending conference. See (http://conferences.timberline.com/conference/index.asp?confid=118) Weekly Advanced LIGO Project Controls meeting was not held last week. Advanced LIGO MRE Proposal (Highest Priority) Per direction of Gary, Dennis, David, and Phil, I am updating the presentation from November with most current data for meeting to be scheduled in August. Continuing the development of the Cost Estimate. The following is a summary of status by sub system: COC - Work on action items per second review continues. Garilynn had me run a schedule report for her to mark up and changes to costing are ongoing. PSL - I have not received any data from Peter as of 7.23.02 regarding the coding of LIGO Lab and LZH scope. AOS - Work on action items continues. Next meeting date has not been scheduled. IO - Work on action items continues. Received an update from David Reitze on his progress. SUS - Continue to process update data provided. SEI - Work on action items continues. Next meeting date has not been scheduled. ISC - Mike continues to work on the WBS dictionary. No comments as of 7.23.02 on the draft detailed schedule. LDAS - No data / feedback from Albert to date. All other subsystems have yet to be scheduled for their first review. These dates are pending per direction from Gary Sanders and Dennis Coyne. Continue to update the TNI Schedule and incorporate any changes. Updated the plan with progress as of 07.19.02 and posted to site. Sent out update data requests for progress as of 08.02.02. Another plan revision is pending per Eric Black. Continue to update the LASTI Schedule and incorporate any changes. Updated the plan with progress as of 07.19.02 and posted to site. Sent out update data requests for progress as of 08.02.02. Prepared disk with pictures and video for David B. to use for the newsletter. Project Plan for the 40-Meter Lab Upgrade continues. Updated the plan with progress as of 07.19.02 and posted to site. Sent out update data requests for progress as of 08.02.02. Cost Book Tool.
- ROSTER DATABASE:
- Working with BK on the Z-Doc Template so that it is as automated as possible.
- Issued request to working group leaders for participant listing.
- COST BOOK DATABASE:
- Continue to verbally communicate the username and password to users.
- Gang of 5+:
- Nothing new to report.
DCAA - Work continues on the incurred cost audit. All quiet on the Western Front. Development of the Advanced LIGO Project Controls Guidebook continues. Project Web Site for posting schedule and progress related data continues to be updated with the latest and greatest. See http://www.ligo.caltech.edu/~tfrey/index.html
The following change requests have been submitted:
| CR-010012
Revision B |
WBS 1.4.4.1 | Closeout Construction Budgets for Initial Computer Equipment Complement at the Sites | P. Lindquist |
| CR-020007 | WBS 1.1.4 | Finishing and Furnishing of Livingston Staging Building | G. Stapfer |
| CR-020008 | WBS 1.1.4 | Purchase and Install Audio Visual Equipment in the New Hanford Auditorium | O. Matherny |
| CR-020009 | OPs | Digital Common Mode Servo to Mode Cleaner Path | D. Coyne |
| CR-020010 | OPs | Additional Funding for Low Frequency Seismic Isolation | P. Lindquist |
A LIGO Change Control Board (CCB) was held Tuesday, July
2, 2002. Change Request CR-020007 was discussed. Items totaling
$157K were approved. Minutes were distributed (LIGO-M020281).
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
No report this week.
Summary of Commissioning Activities at LIGO Hanford Observatory (compiled
by M. Landry)
---------------------------------------------------------------------------------------
2k IFO investigations
---------------------
MMT2 forensics: SEM images of the broken wire are available at
http://blue.ligo-wa.caltech.edu/ilog/pub/ilog.cgi?group=detector&date_to_view=07/19/2002&anchor_to_scroll_to=2002:07:19:12:12:24-RaiW
Gate valves were reopened on Monday morning. Shortly after, the
water load into each arm was
calculated to be 0.5 Torr litres/day, with the expectation this would
fall as 1/t. The load was
deemed low enough to allow the gate valves to remain open indefinitely.
An initial ioo and core optic alignment was performed, resulting in
single arm and Michelson
locks (no PRM or full locks yet). Alignment is currently being
revisited owing to inadequate
centering of the input beam on the BS.
Complicating matters somewhat is the concurrent upgrade of the ISCT10
table layout. Taking
advantage of ifo downtime, the new AS port layout scheme was implemented.
An iterative process
of ifo and ISCT10 component aligment is nearly complete. Some
astigmatism in the AS beam
is noted, possibly due to aligment into the beam-reducing telescope.
The primary remaining
table task involves setting AS EO shutter trigger levels.
4k IFO investigations
---------------------
A host of visitors worked on many parallel investigations on the 4k,
including frequency-noise
suppression in the MC, improving mean-time-to-ifo lock, duration of
lock, and the implementation
of the common mode (CM) servo. Frequency noise supression was
improved with an MC_L gain
reduction and additional filtering:
http://blue.ligo-wa.caltech.edu/ilog/pub/ilog.cgi?group=detector&date_to_view=07/20/2002&anchor_to_scroll_to=2002:07:20:18:31:12-peterF
The optimization of loop gains and resetting of RF phases resulted in
swifter locking of the
full ifo. Saturations in RM and POB electronics were characterized.
The MC2 controller was upgraded to include 16kHz processing and the
capability to digitally sum
in the CM's MC_L signal. The additive offset and modecleaner
length paths have been switched
on but a final servo configuration has not yet been found.
LSC code changes eliminated switching transients in ETM dewhitening
filter application.
Frequencies of five internal modes of the BS optic were measured.
PEPI Installation Overmeyer, Traylor, Langdale, Fyffe, Kovalik, Giaime,
Busby, Kern plus a host of others)
PEPI went perfectly. Installation began as
scheduled on Monday, July 15
and was completed a week ahead of schedule!
Thanks to all assisting.
(THIS IS REALLY AN AWARD WINNING PERFORMANCE!
CONGRATULATIONS TO ALL INVOLVED IN THIS FEAT! _GHS)
Laser Safety (Fyffe, Kern)
Discovered that the MOPA-126 safety shutter is tripping unpredictably
(probably because we have the system misconfigured) Working on that,
and
had the installer out 2 days this week to correct a fault in the PSL
table reed switches.
General Computing (Shannon Roddy)
Ran a security audit last week and went over the results with Larry
while he was at LLO. There are some action items that we agreed
I
should look at.
Larry and I had a meeting at LSU with Ric Simmons, Charlie McMahon,
and
Shawn Robins concerning bandwidth and connectivity to LLO. The
results
of the meeting were promising. There are some new options we
will be
looking at.
There are some issues with the virus scan software I am looking at.
Specifically they involve the actions of the scheduled scans and why
some files are not being quarantined.
Working on blocking some SPAM that is coming in on our mail server.
A
couple individuals have been getting various SPAM including some porn
advertisements. I should be able to have these blocked soon.
Investigating a problem with the Samba server.
Planning my travel to Usenix and Pasadena in August.
Installed some software packages on the SURF and guest computers in
the
new building.
LDAS (Ygor Yakushin)
* Helped Greg to restore E7 injection data from tape to disk.
* Using an offline backup, recreated LLO_TEST (380 Mb) on one of the
test machines and replicated it on the other through VPN. It took about
3 hours. Everything seemed to work fine.
* Double checked that federated database configuration on DB 7.1 does
not work with BLOBs.
* Installed DB2 7.2 on a laptop. Playing with it.
(Shannon Roddy) I am looking at what I will need to
do to add a third leg to the WAN VPN while I am in Pasadena Aug
11-14th. Also note the meeting with LSU in the GC portion of
my weekly.
HEPI (Hammond, Kern)
Chips are falling on the floor in the machine shop. Bellows issues were
finally resolved and MIT has issued a PO. HYSPAN is manufacturing
them
now. The LLO spring tester has been modified to incorporate a
positive
mechanical stop limiting spring elongation.
ETF (Hammond, Kern)
Still waiting to hear from the shop about correcting manufacturing
errors found in the Pods (housings for the geophones). These
were
returned to the machine shop 2 weeks ago.
A revised project schedule has been issued (M020142-04)
PEPI
Overmeyer,Traylor,Langdale,Fyffe,Kovalik,Giaime,Busby,Kern
plus a host of others
PEPI
went perfectly. Installation began as scheduled on Monday, July 15 and
was completed a week ahead of schedule!Thanks
to all assisting.
Initial checkout
indicates that the the Fine Actuation System (FAS) is working fine. The
balance of the PEPI installation and commissioning (dSpace controller,
wiring, signal conditioning) is underway.
MEPI
Dennis Coyne reporting
The first 3 MEPI units have been assembled. A few small dimensional problems were fixed in real-time with the MIT/LIGO machine shop (and capable machinists like Myron, Mike, Ken, …) Assembly procedures are being refined.
An installation of one of the MEPI units on HAM20 at LASTI was attempted as a fit check (this is a chamber with only the HAM support structure installed – no isolation stack). There is a fit problem with the spring/actuator housing (the weldment that is common to both the HEPI and MEPI designs); The housing interferes with the HAM door. Ken Mason designed a fix involving a rotation and translation of the housing. The modifications are being machined Friday and it is anticipated that all 4 MEPI units will be installed next week (on the HAM with the isolation stack).
HEPI actuator and springs
Jonathan Kern, Marcel Hammond
Chips are
falling on the floor in the machine shop. Bellows issues were
finally resolved
and MIT has issued a PO.HYSPAN is
manufacturing them
now.The
LLO spring tester has been modified to incorporate a positive
mechanical stop limiting spring elongation.
HEPI Pump Station/Distribution
Ken Mailand
·Running
system daily.
·Getting
setup to do tests at all sensors with various accumulator pressures.
·Manifolds
[fluid distribution]: The manifolds [5] with their mounting bases are finished
machined and are being welded.
·Tests:
Start tests 7-25 at several accumulator pressure settings to optimize the
operation of the pump isolation. Determine which improvements or modifications
might be made to improve performance.
·Design:
A site installation version of the test pump station to be designed, when
final configuration is known. This would be more compact, have a mass dampened
mount base, and be in an isolation enclosure, to control temp and exhaust
vapor.
·Stanford
[information needed from]: A range of acceptable viscosities will guide
us in the design, re. the allowable temp rise of the oil in the system.
·LASTI:
Sent motor data to Myron re. voltage and phases. The oil will ship with
the rest of the pump station. Distribution manifold drawings were sent
7-2 to MIT to show the configuration, and the attachment method. Need to
design and build a bypass resistor for MIT configuration. A large box crate
is ready for shipping all items not on bases.
·Layout
Drawing: I have finished a scale plan view and partial elevation [acad
2D] layout drawing, of station component assembly.
·On
Going:
1.A
new pump mount adaptor will be designed to attach the existing motor to
the new screw style pump.
2. A
new aluminum coupling will be modified and balanced for the existing pump,
and new screw style pump.
3.The
lighter coupling will be finned to reduce heat in pump shaft. A new Buna
coupling spider material will be tried to smooth flow.
4.The
motor pump adaptor will be modified [opened] to allow air flow thru coupling
area.
5.The
motor will be detached from the base and allowed to contact the floor independent
of the
6.station
plumbing brackets with the hope of further isolation of vibrations from
pump and motor.
7.The
plumbing will be mounted on an existing base board which is more secure
than the current and of a better material.
- Most of
the past week spent on changes to Digital Suspension Control (DSC)
software necessary
to operate LHO4k MC2 similar to a large optic for CARM
control. This
included:
-
Removing all but sensor inputs for MC2 in the SOS controller and adding
reflected
memory signals to send this data to the MC2 controller. While were we
at it, we
also replaced the two MIPS processors, which were providing the EPICS
interfaces,
with a single Pentium processor.This
processor is running EPICS
release 3.13,
ported to a Pentium by Alex.It's
been in since last Thursday or
Friday and
have had no complaints of problems thus far.If
this proves
successful,
we may also want to consider changing out the ASC front end EPICS
processors
(presently a MIPS CPU), as these are also over taxed by the number of
EPICS database
records required support the standard filter modules (ASC has up
to 100 digital
filter banks, 10 filters per bank).
-
LSC front end code modified to send CARM error signal to MC2 controller.
-
Large optic controller software modified to run MC2.This
involved adding
an input and
filter bank for IOO-MCL and removing optical lever controls.At
Peter's request,
we also moved the UL and LL coil excitation points to send
excitation
signals into the LSC and IOO_MCL paths for MC2 testing.
- All large
optic DSC software modified to move the dewhitening filters to be
the last filter
in the coil output stages (as per Peter, Sigg, Rana).
- Alex installed
the GDS tools at the 40m lab.He
is also working on getting
the Arbitrary
Waveform Generator (AWG) running.This
requires code changes, as
the sites
use the VME reflected memory and the 40m lab only uses the newer PCI
versions.
- New version
of ASC code has been modified to operate with the DSC in the
LHO4k.Two
versions are ready to go (with or without Microseismic FF).End
station code
for DSC also modified to handle microseismic FF.This
new code
will not be
installed until after S1.
- I will get
together with Jay on his return Monday to discuss the best approach
for a phased
installation of DSC on the LHO2k (and perhaps LHO4k) between S1 and
S2.We
will also try to work out a schedule for this phased install, as the
time between S1 and S2 is relatively short.
Rich Abbott reporting
1.Flavio
designed and sent to board house a test fixture to be used with the +/-
10 amp drivers.
2.Ran
the +/- 10 amp drivers through a variety of stress tests including maximum
power dissipation tests.The units
performed within the design envelope even at 115 watts of thermal dissipation
per channel (there are 6 channels per chassis).We
are writing a test procedure to formalize the release of the first prototype
to LASTI next week.
3.Received
the 8 channel valve driver boards and have begun the stuffing process for
evaluation quantities.
4.Ordered
more +/- 10 amp driver circuit boards.
5.Finished
CAD of new adapter board for L4C geophone head.
6.Released
drawing of seismic retrofit electronics topologies and am in the process
of writing up cable lists.
7.Finished
CAD and sent a BNC adapter board to PCB manufacture that adapts the valve
driver board to BNC inputs for use with the dSpace system.
Mohana Mageswaran
I am getting
ready another seismic interface box. It will be tested
and ready
to be shipped by next week. I am also trying to use the
web version
of the Altera's Quartus II software package in my earlier
designed New Variable Timing Board.
The schematic
for the modified experimental VCO was drawn up.I
was more than
50% of the way through laying out the board when a computer
problem resulted
in the loss of the PCB file - the file was not actually
saved even
though the "Save" button was hit.Most
of the board layout has
been done.Parts
for the board were also being searched for - large value
capacitors
in particular.The an effort to simplify
things for now, the new
board does
not include the automatic gain control and power sensing of the
previous version.This
will be added back in once the phase noise of the
circuit has
been characterized.
In the meanwhile,
I have been gathering information about components
suitable for
measuring the VCO phase noise and calibrating the phase noise
of an IFR
oscillator at 80 MHz.
Lightwave
have apparently made some minor engineering changes to the 10-W
laser.The
fifth Microlock is no longer present and there have been some
silkscreen
changes to the master oscillator interface board.
This week
I have been working on implementing a DMT message tunnel to
allow users
outside of the control room to access DMT monitor data
directly.
At present a copy of the DMT viewer running on a GC node can't
see any data
from monitors running on the new Blade 1000s that are
connected
only to the CDS network. The tunnel process would run on sand or
delaronde
and echo the requests to the monitors as well as the replies
produced by
the monitor processes. The nameserver will automatically
provide a
route via a tunnel (if one exists) when a client requests the
address of a monitor that is not on an accessible network.
2 LIGO 1 Beamsplitters were coated at REO with the help of Helena Armandula.They will be coming back to CIT for evaluation.
I am doing
analytical calculations to see where the sidebands imbalance comes
from, since
we see that in the simulation results and want to understand which
effect brings
that up.
Part of the
problem is due that for general perturbations not only light goes
from one mode
to another but there is also an impact on the phase shift which
seems to redefine
the optimal lengths that minimize the sidebands imbalance. I
am going through
a lot of algebra to check all the quantities that contribute
to the overall
phenomenon.
Bill Kells
OTF Lab.
Contamination
Cavity # 1 with glycerin still running and it will be running for another
week.
No discernable
change in absorption and only ~2ppm increase in scatter loss (step change
after introduction of the sample).
New Lab at
RSE
Cavity #3Reference
Cavity is pumping down now and it will be used as reference.
The optics
has been installed and aligned and waiting to be aligned into the cavity.
I have replaced
the exhaust filter on this pump with a bigger filter and it is just fine.
Cavity #2Test
cavity
This cavity
is waiting to be pumped ( no vac. pump available)
I am working
on a pump now, refurbishing the one we have.
Bob Taylor
gave me one but it does not work.It
has electronic problem.
We continue
bringing the rest of the equipment needed here at RSE from OTF Lab.
I have received
the 100mw NPRO Laser from Lightwave and replaced it for the 700mw that
was
used for the
transmission test setup.The 700mw
NPRO laser will be used to run again the Mineral test sample,
running the
laser at max. power ~750mw.
The wooden
crate with optic and mounts was shipped to MIT (Nergis Mavalvala)
no report
> Since our last report we have attempted to lock the TNI and take noise
> data with the new optical configuration (optimized polarizations)
and
> the new servo electronics. Unfortunately, we were not able to lock
> reliably to the TEM00 mode and so were not able to take data.
>
> Lock acquisition is not a problem. We are able to acquire the TEM00
mode
> every minute or so, but the lock will not hold for more than 20 or
30ms
> at a time. (We can tell we are locking to the TEM00 mode by the
> visibility, which is around 60% for this mode and much less for other
> modes.) This hold time of 20-30ms is very consistent, and we have
no
> trouble locking to and holding on higher-order modes.
>
> We have observed modes in the system at 27Hz, 21Hz, and 30Hz that
> produce fairly large amplitudes in the error signals of the arm
> cavities. Moreover, we observed that the 27Hz mode shows up in the
mode
> cleaner's shadow sensors, and the 21Hz and 30Hz modes show up only
in
> the arm cavities' shadow sensors. This led us to suspect that theses
> were mechanical modes in the suspensions. The periods of these modes
are
> on the order of 30-50ms, and they could be kicking the system out
of
> lock after approximately a half period. Moreover, we would expect
these
> mechanical modes to get rung up by acquisition to the relatively
> high-gain TEM00 mode, but not the lower-gain, higher-order optical
modes.
>
> Some very quick calculations, verified with dummy masses suspended
in
> air, revealed that these frequencies were those of the "bounce" and
> "roll" modes of the suspended optics. In fact, the mode cleaner
mirrors
> exhibit a "roll" mode around 38Hz (root 2 above the bounce mode)
that
> does not show up in the shadow sensors. Nergis had warned us some
time
> ago that, if our OSEM heads were not vertically aligned with some
> precision, the bounce mode might couple into the shadow sensors and
> excite the mirrors. With that in mind, we vented, opened the chamber,
> and began re-optimizing the OSEM heads, some of which were
substantially
> far from their optimum positions.
>
> We also found some electrical problems with the mode cleaner's
> input-mass controller, and we repaired that. While we had the system
> locked to high-order modes, we also took some ringdown data on the
> mirror modes to measure internal Q's.
>
no report
Simulation and Modeling (Bhawal)
Commissioning meeting on Monday
--------------------------------
Matt presented SimLIGO model at the commissioning meeting. There were
suggestions for inclusion and/or improvement of the following noise
sources:
(i) scattering noise (ii) low frequency components of the intensity
noise
(iii) 60 Hz noise. Also the following investigations were suggested:
(a) bilinear couplings from low freq intensity noise and 60Hz noise,
and
(b) how the pitch-position coupling of mechanical system leads to optical
lever noise and then couples to AS_Q signal.
E2E Physics meeting on Thursday
---------------------------------
Luca, Matt, Virginio (LHO) and Biplab and Hiro (Caltech) discussed
details
related to SimLIGO, suspension system model, locked states of IFO in
FFT and
E2E, COC phasemap implementation in E2E etc.
Latest e2e and SimLIGO installation
--------------------------------------
The full package was installed at LHO. A few glitches were found and
some are
yet to be fixed. At LLO, the latest softwares necessary for e2e installation
were not available. Raghu is working on this with help from Tom Evans.
If
the installation is not completed by next Monday, Ed will need to help.
SimLIGO
-----------
(Matt) Helped Andrea with her characterization of LSC electronics.
Investigated digital ASC system design for inclusion in the next version
of
SimLIGO. Tested SimLIGO installation at LHO.
Seismic measurements at LLO
-------------------------------
(Hiro) Sany and Raghu (SLU) are working at LLO to measure the seismic
motion and
coherence. They are also building e2e models of the suspended mirrors
to
understand the measurements. Hiro is working with them to make a realistic
HAM table with several suspensions, of different sizes and orientations,
placed.
The OSEM senses the relative locations of the mirror wrt to the cage,
not
table nor ground. This difference seems to be observed, and an e2e
model is
being built which has this granularity included.
Locked states of IFO in E2E and FFT
-----------------------------------
(Biplab) The correspondence between an FFT run and E2E run under the
same
mode-mismatched condition has been established. Wrote a simple matlab
code
that takes optimized lengths from an FFT run and converts those
appropriately into mirror positions for the corresponding E2E run.
With
mirror positions fixed at these points Han2k model can build up power
to
the saturation levels. Carrier power levels from this run agree very
well
with the FFT run but Sideband values differ presumably for these reasons:
(i) the finite number of modes considered in E2E (ii) no diffraction
losses
considered in E2E runs.
When lock acquisition is started in Han2k model after the above-mentioned
saturation level is reached, the mirrors get displaced to certain extent
from the FFT-specified positions (i.e., initial conditions for these
runs).
In this locked state the carrier power for TEM00 at dark port increases
by
about 5 times from the FFT value. This is an interesting consequence
of the
realistic locking that the Han2k model provides and the study of the
reason
behind this may provide good insight into the actual IFO locked state.
COC phasemap
-----------------
(Hiro) Software development was started to create a phase map of the
LIGO
mirror covering the entire surface (radius R1) using the measured data
covering smaller portion of it (radius R2). The measured phasemap is
expanded by Zernike polynomial with the normalization radius of R1
by
minimization, and the result is used to extrapolate. Residual noise
psd in
radius < R2 is used to generate random noise in radius > R2. This
software
also provides a facility to generate a phasemap with arbitrary pixel
size.
The main purpose of this development is to calculate the mode decomposition
matrix of as-built mirrors to be used in the e2e simulation. The effect
of
the as-built mirror will be studied using FFT. This is an interesting
topic
by itself and is also necessary to validate the e2e implementation.
Alfi
-----
(Bruce)
- Completed work on positionable ports in Alfi5 for the internal view.
- Cleaning up code in MemberNodeWidget prior to implementing positionable
ports in the external view.
(Melody)
- Working on the automated tester for alfi5. Also fixed problem reports.
LIGO Data Analysis System
Software Systems (Blackburn)
The week long effort to come up with a single coherent C++ code to
manage
concatenation of data from frames in the frameAPI which also allowed
additional threads and more CPUs to be used in the LDAS system was
not
fruitful in the alloted time necessary to be ready for the release.
Instead,
we fell back to the existing TCL code and worked to inhance its performance.
This proved much more successful and within a day we were able to
significantly reduce the First In, Last Out (FILO) bottleneck. This
does not
thread so there is still a serialization issue, but we now feel like
the
performance will be satisfactory for the science run.
We have added significant new plotting features to the controlMonitorAPI
to
allow more insight into queued up jobs and jobs that the system is
rejecting.
We are now able to detect the impact of various nightly activities
(such as
nightly compiles of LDAS) on the system performance.
It was discovered that in going back to the new TCL frame concatenation
code,
a bug existed which was incorrectly building up large time series data
from
reduced data set frames that had been resampled. This bug was eventually
traced down and fixed.
A Tcl script was developed to test every combination of argument for
each
binary arithmetic action (scalar/vector, float/double, real/complex,
add,
sub, mul, div). This showed that some scalar/vector combinations are
still
not implemented. These are not combinations that are used often so
the
priority for fixes is mostly post science run.
Routine nightly testing of LDAS is consistently showing about a 0.1
- 0.2
percent failure rate. The remaining issue contributing to this failure
rate
is a new bug that has only recently shown up (last week) in the frameAPI
which causes it to core dump a couple of times a night. No luck in
identifying the source yet.
Hardware Systems (Anderson)
Caltech
-------
(Dan Kozak)
* HPSS migration to 9940 tape continued for most of the week.
I've stopped
it (as of today) until CACR's 9940 tape order comes in.
* Lots of HPSS/hsi problems, worked with Mike Gleicher to fix Scott
Koranda's hsi problem on saiph (ongoing, he's been on vacation
since
Monday).
* Installed new ATM NIC (on loan from CACR) in saiph to see if that's
the
cause of the connectivity problem.
* Set up pseudo-site and pseudo-CIT QFS filesystems on ldas-archive.
Worked on setting up rules to control migration of data to particular
tapes.
(Al Wilson)
* Changed racks in LDAS-TEST. Moved some of the servers out of a large
rack
to a standard size one.
* Worked on RedHat 7.3 release.
* Working on system configuration for the new IDE raid systems.
(Stuart Anderson)
* Worked with Albert to place an order to procure 2TB of IDE RAID
for S1 reduced data set storage for both LHO and LLO.
* Investigated 135GB IDE disk limit in the current version of Linux
used by LDAS and determined that an upgrade to RedHat7.3 will
be required to address all of the space on large IDE disk drives.
* Discussed future storage products with Sun Microsystems.
* Made frames from the nightly Observatory mirror/archive visible
to the LDAS-DEV system at Caltech for testing LDAS against
current frame files.
MIT
---
(Keith Bayer)
* Moving shelving and equipment around for a/c install.
* Recabling machines due to room restructuring.
* Installed GigE cards in datacon / beowulf.
Livingston
----------
(Igor Yakushin)
* Helped Greg to restore E7 injection data from tape to disk.
* Using an offline backup, recreated LLO_TEST (380 Mb) on one of the
test machines and replicated it on the other through VPN. It
took about
3 hours. Everything seemed to work fine.
* Double checked that federated database configuration on DB 7.1 does
not work with BLOBs.
* Installed DB2 7.2 on a laptop. Playing with it.
(Shannon Roddy)
* Nothing to report other than I am looking at what I will need to
do to add a third leg to the WAN VPN while I am in Pasadena
Aug
11-14th. Also note the meeting with LSU in the GC portion
of my weekly.
Hanford
-------
(Greg Mendell)
* ASA returned two beowulf nodes with new memory and mother boards.
I
am currently working to get these nodes back on line.
* Working on plans to move LDAS into the new building at LHO at the
end
of Sept or early Oct.
* At LHO I have copied from tape to disk 6 hours of data taken at LLO
during a period of low noise, as organized by Szabi. (As previously
announced by Igor to lal-discuss, this data is available at
LLO from
decatur and LDAS at LLO. Also, this data is available via getFrames
as
announced by Peter Shawhan to dc-ligo.)
The GPS time are:
710472128 to 710493712
which correspond to
Jul 11, 2002 20:21:55 CDT (Jul 12, 2002 01:21:55 UTC)
to
Jul 12, 2002 02:21:39 CDT (Jul 12, 2002 07:21:39 UTC)
The data is available from fortress in these directories:
/frame10/LOWNOISE/LLO/Data[0-5],
and it is available from LDAS jobs.
The data will remain on disk until we need to free up the space
for the
restart of S1.
Information about lock stretches and injections are at this URL:
http://london.ligo-la.caltech.edu/engrun/DataTaking/071202/index.html.
Data Analysis Activities (Lazzarini)
Mendell:
1) The knownpulsardemod code has been submitted to lalwrapper cvs.
(For
a summary of the knownpulsardemod DSO, see last week's report.)
Minor
bugs reported in last week's report were in the calling script, and
have
been fixed. I have run test jobs in stand-alone mode AND using
the LDAS
system at LHO. Thus the code has been shown to work on an LDAS
production beowulf system in that it produces numbers without crashing.
Verify and testing that it produces correct numbers on synthetic data
is
now starting. Bugs in the LALDemod function have also been reported
this week by the AEI group, which will have to be dealt with before
testing can begin in earnest.
2) Work with my SURF student this past week has focused on studying
leakage caused by gaps in the locked stretches and other statistical
issues. He has added the ability to multiply his test data by an
arbitrary window function, and is also studying how to deal with side
lobes created by amplitude modulation.
Creighton: (report from last week)
Finished writing LAL code to generate modulated signals from simulated
continuous sources (pulsars) in binary systems.
Wen: Working on a paper with CaRT group on the Kozai effect and its implications for inspiraling binary searches.
General Computing (Wallace)
MIT:
(Keith)
-Patches loaded on several windows 2K boxes.
-Setting up SB1000 compute server with NFS mounts.
-Loading MU7 patches on SUN boxes.
-Performed a couple of NIS+ table updates.
(Larry)
-Assisted Keith on a couple of NIS+ updates.
-Reviewed the security audit with Keith and tested a couple of machines.
Overall things were OK but there are few items Keith will be correcting.
Livingston:
(Shannon)
-Ran a security audit last week and went over the results with Larry
while he was at LLO. There are some action items that we agreed
I
should look at.
-Larry and I had a meeting at LSU with Ric Simmons, Charlie McMahon,
and
Shawn Robins concerning bandwidth and connectivity to LLO. The
results
of the meeting were promising. There are some new options we
will be
looking at.
-There are some issues with the virus scan software I am looking at.
Specifically they involve the actions of the scheduled scans and why
some files are not being quarantined.
-Working on blocking some SPAM that is coming in on our mail server.
A
couple individuals have been getting various SPAM including some porn
advertisements. I should be able to have these blocked soon.
-Investigating a problem with the Samba server.
-Planning my travel to Usenix and Pasadena in August.
-Installed some software packages on the SURF and guest computers in
the
new building.
(Larry)
-Spent time going through the auditorium setup. There are a number
of things
that we need to test out. Shannon has a good start on equipment that
should
improve the quality of the network presentation system.
-Reviewed the equipment needs for the new building. Shannon and I have
a few
more things to work out but it looks like the new building will have
a GigE
backbone.
-Reviewed the security audit items with Shannon and ran a few test
systems.
Shannon has discovered a number of security issues. Most were with
the PC's and
it will take some time to get them all cleared up. Fortunately none
of the
problems are major and the firewall takes care of most the issues.
-Shannon and I met with a few of the LSU representatives concerning
the WAN
connection at the Livingston Observatory. They are going to check on
options
with COX cable. They now have a strong presence and LSU is working
with them. I
will be contacting BellSouth again to find out if they have any better
deals
than what they offered in the past.
Hanford:
(Christine)
- All the hardware for the network bandwidth increase is ready.
Planning to schedule the switch to the new increased bandwidth the
week
of Aug 5th.
- All the ethernet and wireless networking hardware is ready to go
into
the new building. The fiber and ethernet cables are scheduled
to start
installation on Aug 1. I still need to purchase a new color laser
printer for the new building office area.
- Installed more matlab toolboxes. Working on getting the matlab
license log file to work consistently.
- User support: created new user accounts, changed the password on
some
others, installed printers on a visitor's laptop and fixed problems
caused by the latest email virus.
- Procurement: purchased a flat panel monitor for CDS, contacted Dell
and Mathworks for refunds on sales tax, purchased the hardware for
the
bandwidth upgrade and worked with Richard on purchases for the new
building network.
CIT:
(Veronica)
- LDAS website: rewrote and installed the LDAS hardware page for MIT.
Installed the images of LLO and LHO hardware diagrams updated by Albert.
- LSC website: posted agenda of the LSC meeting. Adding to the list
of
participants as they register. Updated the list of MOUs.
- LIGO website: posted several updates. Attended a presentation on
a new
release of QuickTime Pro. This is a good media authoring tool that
delivers a lot for its $30 pricetag. In LIGO or CaJAGWR it can be used
for editing and enhancing videos, i.e., by adding a powerpoint slide
show.
Attended a meeting on the final design of the folder for press &
media
kit.
(Wendy)
-Rebuilt and ghosted some machines
-Upgraded a machine from win98 to win2k to see what would happen--it
seemed all right and it seems that Norton and PCard software should
be
removed before upgrading (it didn't seem to cause any problems though)
-Played around with VNC
-Played around with VRVS, but there were some problems that Mike will
look
into
-Wrote some documentation on VNC, will do same for VRVS when the problem
is smoothed out
-Wrote other documentation to be posted on the FAQ page
-Helped users solve random computer problems
(Bruce Sears)
- General Ilog Maintenance:
(0.5 days)
- Moved log at MIT to a
new server.
(Mick)
-Continued documentation of luna rebuild
-Installed programming environment on dt140m with Lisa
-Setup rana ssh shortcut for Steve Vass
-Upgraded openssh on beli (in Synchotron) with Lisa
-Created POs for ORiNOCO equipment (2 APs, 10 cards), AIT-2 tapes,
and
Solstice Backup s/w
-Helped troubleshoot VRVS with Mike and Wendy
-Created RMA to return broken hard drive under warranty
(Lisa)
- Looking at a java based webmail application. I am still working
out the
installation glitches, but it looks very promising.
- Fixed some ssh authentication problems on mirfak and sargas by adding
/usr/local/bin/tcsh and /usr/local/bin/bash to the systems.
- Put pine on mirfak, sargas and alterf.
- Installed a development environment on dmt140m in the 40meter martian
network.
- Installed openssh on beli in the synchatron.
- Moved grumium, an ultra30 to WB 251.
- Helped configure Ruth's new pc.
- Worked on some email problems for Hongyu.
- More new accounts and visitor support
- Spent quite a lot of time working with Mick and Christian.
(Mike)
-Setup an upgraded computer for Linda and I got a ghost image.
-Swapped out Gina's computer with a new Dell computer and got a ghost
image.
-Finished up working on Ruth's computer getting her data moved to her
new
computer and setting up her email by connecting her to the ATC exchange
server.
-Loaded an engineering workstation for a surf student that is working
for
Riccardo.
-Loaded MatLab 12.1 on a visitor's workstation.
-Ran a cable drop to Ed Chargois office to eliminate Ed C. and Ed J.
from
being connected to Veronica's hub that is dangling in the middle of
Veronica's office.
-Terminated the new data run in Ed Chargois office, both Ed's are on
the
own dedicated hub.
-Rerouted ethernet cables in Veronica's office.
-Performed some trouble shooting a networking problem for Gary Sanders;
this
seemed like a bad hub.
-Swapped out the hub and replace it with a switch.
-Made an updated ghost image of Irene Baldon's and Irena Petrac computer.
-Performed some maintenance on the NT servers.
-Started looking over on what I need to do in order to upgrade the
Amaldi box to
2000 Server.
-Showed Wendy how to used VNC, and have her working on Documentation
that
will include step-by-step instructions on how to use VNC software.
-While showing Wendy and Mick how VRVS software works, I came across
some
problems with the MIC and ended up having to reinstall
VRVS software. This included cleaning up the registry and clearing
out VRVS
launcher.exe from Netscape and Internet Explorer then reinstalling
VRVS
software. This is now ready for use.
(Larry)
-Worked a few procurement issues. Presently, trying to get a number
of
maintenance contracts renewed.
Purchased, a number of items that we normally keep stocked. With the
influx of
students and fixing different items our cabinet became empty of essentials
like
power strips and hubs.
-Worked on a number of documents including a reply to the security
audit and
some items related to the GC budget.
-Worked on a number of logistical items concerning the WAN at Hanford.
Christine
and Richard have things under control.
-Started working on the computer and VRVS logistics for the LSC meeting
being
held at Hanford.
Adv. SEI -- ETF
Marcel Hammond, Jonathan Kern
Still waiting to hear from the shop about correcting manufacturing
errors found in the Pods (housings for the geophones). These
were
returned to the machine shop 2 weeks ago.
From: GariLynn Billingsley <Billingsley_G@ligo.caltech.edu>
Gingin
The 100 mm x 50 mm A axis sapphire piece slated to be the Gingin Input
test mass has been shipped to Insaco for OD polish. I have just received
the mirror specifications from Peter Veitch.
Crystal Systems
We have placed an order for two full size sapphire
pieces. CSI expects to have the proper core drill by the beginning
of August and hopes to deliver the two pieces with inspection polish by
mid to late October. This is an estimate and not a commitment.
Goodrich
The final compensating polish run has finished,
preliminary metrology indicates that modeling was correct and the piece
comes in at 9 nm rms. The specification was less than 10 nm
rms. The piece is going through final metrology and inspection and
is due to us by mid August.
From: Janeen Romie <romie_j@ligo.caltech.edu>
AdLIGO Suspensions
Local machine shops have been able to take our orders for machined
parts for the MC controls prototypes with a proposed delivery date of Aug
16th. Mike in CES is still on track for a mid-August delivery of a MC structure,
along with a number of mechanical parts for the suspension assembly and
some fixtures.
Calum, Russell Jones and I are trying to get Solidworks 3D Teamworks
to work between us all with some success. More work is needed. We're
starting to feel like a beta site for the Solidworks software creator.
Lisa Bogue has put my IDEAS data directory on my UNIX box from the back-up tapes after my external hard drive died. Many thanks to her.
Still working on suspension design and procurement issues and
osem procurement.
From: ctorrie <ctorrie@ligo.caltech.edu>
Advanced LIGO Suspensions
Machined parts for the MC controls prototypes have been distributed between several local shops, CES and Physics Shop. Hopefully the majority of these parts should be delivered by August 15th.
Work is being done in the Synchrotron Laboratory to prepare for the 2 prototype suspensions.
Russell Jones, Janeen and I are trying to get SOLIDWORKS 3D Teamworks to work between us all with some success.
15 coils and associated parts have been ordered in Glasgow.
Several parts that are prototypes for the August tests are being tested
in the Synchrotron with the help of Dan Mason and john Veitch
From: Michael Smith <smith@ligo.caltech.edu>
ADVANCED LIGO
Photon Acuation:
I have estimated the hours for an R&D activity to create a preliminary
design for a Photon Actuator. The design method relies on extensive simulink
modeling in lieu of an experimental prototype. The work plan is based on
the Conceptual design outlined by Mike Zucker on 10/13, T000113-00-R. I
have included an alternate approach which substitutes a Fabry-Perot cavity
in place of the 30 bounce "modified White cell" to increase the photon
force on the mirror.
From: Peter King <pking@ligo.caltech.edu>
3.0 AdLIGO PSL
Shally Seraf reports that
there is a problem with the Lightwave
power supply used with the power amplifier. The front panel displays
"Ck St Sw", the message for checking the standby switch. The
error message
has apparently appeared more frequently in the past few days.
Dan Feehan
of Lightwave Electronics has been contacted.
From Riccardo DeSalvo:
Papers
LVDT and actuator papers:
From NIM about the LVDT:
We are pleased to inform you that your paper is due to be published
in
volume 489, issue 1-3, on pages 570 - 576, cover date 21 August 2002.
Naturally the actuator paper, per our request will be published just
next to it.
Alessandro integrating the author's comments to the accelerometer
papers, then will submit the draft for referee. If you are an author
and
did not send yet your comments do it now or do not bother at all.
Szabi and Virginio overdue with MGAS and IP drafts.
Alessandro
Shipped LVDT to Stefano for mini-stress-strain machine.
Studying how to laser zap Nickel over MoRuB oxyde, may abandon if
confirmed success elsewhere (see below).
Akiteru
Work here is going well. I am implementing optical lever control in
the
end tower (the front tower is finished). I am running a measurement
to
re-diagonalize the sensors on the IP tonight and will take a set of
measurements for actuator di
agonalization. Hopefully the in vacuum, SAS
suspended F.P. cavity will be back on line this weekend or early next
week.
On glassy metals. As a group, now that we are bringing all the
measurement instruments online we will characterise MoRuB with all
B
concentrations from 14 to 24%. These are incomplete measurements from
the past and will make a nice paper.
Eric
Scanned last week X-rays and identified uniformity problems both with
the X-ray field from the gun and film inhomogeneities. Refined
procedures to offset the inhomogeneities. Trained Stoyan on matlab
analysis of X-rays.
Made the first melts of MoRuB at various concentrations of B.
Stoyan Nikolov
Learning X-ray scanning.
Designed new splat pistons, in production. E.t.a. Thursday. Made melts
of MoRuB with Eric.
Brian
Compared X-ray diffraction spectra of glassy, poly and mixed MoRuB
Working on a sample positioner.
Stefano, Hareem
Initially failed again in brazing, but then SUCCEEDED brazing to MoRuB
with A
gTnTiGaCe braze AND mechanical scrubbing of the hot surface. But
the braze has problems wetting CuBe. It may still be a good solution,
the MoRuB surface could be primed this way, then drained with a solder
wick and mated to the CuBe surface, primed with another braze. Work
to
follow. Will test also on Vitralloy
Stefano, Chenyang
More work on LVDT and load cell readoutcircuit for mini stress-strain
machine. Waiting for the other parts.
Will make asap tests of braze effectivness.
Hareem
After testing the silver braze which worked and therefore ordered more
things (hot plate and ultrasound pen) for brazing. Have been reading
papers on specific heat capacity measurement to prepare for the
analysis. Learnt how to calibrate and use DTA for glass transition
and
crystallization temperature measurements; need to test the machine
as it
has not been used for a long time. Catching up with everyone on what
they are doing.
Francesco Fidecaro
Welcome back. Getting tuned in and
helping in data analysis tasks.
Mike
One of the thermal conductivity thermometers in the cryostat broke,
replaced and recalibrated, back online.
Taking final measurement on Glasmet.
Training new student in fitting of data.
Valerie Cervantes
Welcome, Junior student at Mayfield High School.
Making fits of thermal conductivity.
Kelin
Mounted LED to fibers and to cryostat vessel. LED replace the laser
diode with advantage and can be easily modulated. Now ready for test
of
split photodionde in cryostat.
For additional information about this report, contact sanders@ligo.caltech.edu