Weekly Report for Week Ending June 6, 2002


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  June 10, 2002 will be:

 (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

  1. Announcements
  2. LSC Issues (Weiss)
  3. Comments on Weekly Report
  4. WBS 1 LIGO I Construction (Lindquist)
  5. WBS 2 LIGO Lab Operations
  6. WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
Executive Committee only 11:30 - noon   Topics:
 

Special Items:


Special Announcements:


Weekly Report Highlights
 


LSC Issues (Weiss)


Subject: Notes from LSC Executive Meeting May 31, 2002

to: LSC executive committee
from: R. Weiss June 6, 2002
concerning: Notes from the LSC Executive Committee meeting May 31, 2002

Data analysis and "upper limit"  group activities (Alan Wiseman)
-----------------------------------------------------------------
An LDAS "boot camp" was held at the University of
Wisconsin@Milwaukee May 13 and 14. Approximately seven people in addition
to the UWM group attended.

Face/face meetings of the "upper limit" groups were held in the
past two weeks. A biweekly LSC wide phone call is planned to facilitate
communication between the "upper limit" groups and the rest of the LSC.

Barry suggested a meeting to bring the data analysis of the E7 in the
various groups to closure in preparation for the S1 run.

Report on the current state of the detectors prior to S1 (R. Weiss)
-------------------------------------------------------------------
The 2km at Hanford and the 4km at Livingston in the past two weeks
have surpassed the strain sensitivity of the 40 meter system in 1994
and the TAMA detector in June 2001. The improvement is a factor of
10 or better in strain sensitivity relative to the LIGO interferometers
during E7.

Much of the effort in the weeks before S1 will be dedicated to facilitate
locking and improve the robustness of the interferometers

Discussion of the new roles for ASIS (B.Allen, P. Brady)
------------------------------------
A proposal for ASIS to play a dual role with dual membership was discussed
and accepted. ASIS will become one of the connections of the LSC to the
source modeling community while also performing its previous
function of developing new source detection algorithms for the LSC.
Those members of ASIS with MOU with Laboratory will have access to LIGO data
and will be authors on LIGO papers. ASIS will also include members with particular
interest in source modeling but who have not become LSC members and not
developed MOU with the Laboratory. The ASIS committee will hold meetings of different
types some closed to members who are not involved in the data analysis.

The proposed organization of ASIS can clearly be changed if it proves awkward
and unworkable, however, alternatives considered by the Executive Committee to make
better connection to the source modeling community were less attractive. These
included:

1) Making no change. The Executive Committee was of the opinion that there is
scientific value in fostering source modelling and a mutual benefit in the desire
by both NASA and NSF to bring the source modeling closer to the observations.
Furthermore, ASIS members dedicating most of their time to algorithm development
would benefit intellectually from the closer coupling to the source modelers.

2) Separating the functions and asking the "upper limit" groups or subsequent
source detection groups to take on the algorithm development. Although
the development of special software is driven by the needs of the source detection
groups and will be carried out in them, the Executive Committee considers
it important to retain a group within the LSC that fosters and oversees algorithm
development in general.

Next LSC Executive Committee meeting
-------------------------------------
Friday June 28, 2002 at 11AM EDT


LIGO I Construction/LIGO Laboratory Administration (Lindquist)



 

LIGO Operations--Administration



LIGO Weekly Site Telecon (Lindquist)

There was a site teleconference held on Thursday, June 06, 2002.  The following items were discussed:

Action 106: Outfitting and Populating the Building at Livingston, Ed Chargois will visit Landover, MD (GSA collection point) next week to check out some furniture.  The plan for floor layout for the staging building at Livingston has not been finalized.  Gerry to provide sketches.

Timeline for spendout of construction funds:  Gerry has identified up to $325,000 to be requested for completing the new facilities.  Some of this will be for outfitting the laboratory for MRE effort.  Air conditioning and fire suppression for LDAS room also included.  Gerry to prepare change request.  Otto to provide similar change request for Hanford ($30,000) excluding laboratory equipment.

Livingston Staging Building: Punch List status--biggest concerns relate to mechanical issues and floor repairs in the auditorium.

Building at Hanford: Otto is seeking cost estimates for traffic control measures and will provide a change request.  Stainless siding supposed to be delivered by tomorrow.

LSC:  The LSC is at Hanford mid-August.  Livingston may be sending a l;arger contingent than usual.

Safety: Bill Tyler is preparing a procedure to re-emphasize the process for reporting injury incidents.  Injuries must be reported to Workman's Comp office within 24 hours.

The list of current actions revised to reflect the status of open actions assigned through June 06, 2001 may be found at ACTION LIST.


PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACCOMPLISHMENTS

> From: Cleveland Mak <mak_c@ligo.caltech.edu>

ACTIVITY

Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA .

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>

CONSTRUCTION:

OPERATIONS:

SUPPORT (Baldon, Torres, Lloyd, Tischler)

 
>Irene Baldon >Dorothy Lloyd >Rita Torres >From: Ryan Tischler <rtischle@ligo.caltech.edu>

Advanced LIGO (Frey)

From: Thomas Frey <tfrey@ligo.caltech.edu>

Progress Period from

Progress Period from 05.31 to 06.06

Accomplishments:

Schedule 06.07 to 06.13:

Reports (Lindquist)

Change Control/Contingency (Lindquist)

The following additional change request has been submitted:
 

CR-010012 
Revision B
WBS 1.4.4.1 Closeout Construction Budgets for Initial Computer Equipment Complement at the Sites P. Lindquist


Human Resources (Akutagawa)

From: Cindy Akutagawa <cindy@ligo.caltech.edu>


Quality/Safety (Tyler)

>From: Bill Tyler <tyler@ligo.caltech.edu>


LIGO Hanford Observatory (LHO) and Interferometer Operations (Raab)


Summary of Commissioning Activities at LIGO Hanford Observatory (compiled by F. Raab)
-------------------------------------------------------------------------------------
(see ilog for details - if it's not in the ilog, it didn't happen...)
 

It has taken longer than expected to get all hardware and software ready to go. As this is written it looks like we have a clear shot to lock 'em both up for E8. Good thing, we still have 40 hours to go and the company has arrived.
 

4k IFO investigations
---------------------
Still shaking down new software. As of this afternoon, it appears naming is fixed, filters are mostly fixed, and a few problems remain but should not stop the show. Thanks to Stan, Alex, Ash and Dave for hanging in there! In the background we have been able to make some progress on commissioning. at spec, but it should not hurt us for a while. A side benefit was the removal of glitches that were apparent previously, due to actuator range issues that are now cured.
 

2k IFO investigations
---------------------
Rolf, Dave and Richard have struggled immensely to overcome an instability in the CDS system that would shut down controllers and disorient optics. Sometimes the system would run for 1/2 a day and sometimes only for 1/2 a minute. The trend was getting worse over time. After many iterations of hardware and software it is still causing problems and is receiving lots of attention. We have continued other work as possible.
 

A gain boost was added to the common-mode servo to further reduce noise below 100 Hz, by orders of magnitude. The net effect is to bring RMS displacment below 3e-13 m, within 1/2 order of magnitude of target. (See ilog entry at http://blue.ligo-wa.caltech.edu/ilog/pub/ilog.cgi?group=detector&date_to_view=06/02/2002&anchor_to_scroll_to=2002:06:02:19:19:38-daniel for details.) Beam jitter measurements were made at mode-cleaner output to see whether drive signals from main interferometer or winds cause large changes. They do not. De-whitening filter switching transient problem is now cured. The interferometer was totally disabled for an evening due to huge glitches on PSL. This was later traced to rerouting a tempertature sensing cable to the chiller. New intensity servo also implemented on this PSL.
 

FACILITIES
------------------
The laboratory Building construction is more or less on schedule. The
contractor is installing the windows and sheet rock. In the auditorium the
acoustical clouds are partially installed. The plumbing rough in is
complete, electrical rough in is still on going. Only flashing is remaining
to be complete on the siding.
 


LIGO Livingston Observatory (LLO) and Interferometer Operations (Coles)


Interferometer Commissioning: We made multiple attempts to fully implement the "super" common mode servo which feeds back from the arms via the MC to the laser all the way to DC. We were unable to get it to work stably. The central problem appears to be a difficulty engaging the LSC de-whitening filters without creating transients which disturb the laser frequency. Because the beginning of S1 is only about three weeks away, we are restoring the interferometer to the conventional common mode topology and will now concentrate on preparing a stable operating environment for S1. Current displacement sensitivity is about 5.e-16 m/rthz at 100 Hz, dominated by DAC noise below 300 Hz. We will revisit the "super" approach following S1.

LDAS:
Together with Rus, Mike and Ken finished building 3 racks.
Playing with DataJoin Replication Administration tool which gives more control over administering replication than db2cc but unfortunately only runs under Windows. In particular, it allows configuring external CCD tables for staging data for multi-target replication. db2cc does not provide a way to configure CCD tables.
Did all the paperwork for the new equipment: sent receipts to those who need them, tagged all the equipment and filled the papers (serial number, tag number, etc.).
Flattened the LDAS network.
Tested the new switch.
CDS: We fixed the DAQ problem at the south end station. The brown out during our last major electrical storm caused the -5 VDC power supply to trip. The inability to switch in the dewhitening filters at the west end station was chased down to a faulty output on one of the xycom 220's. That board has been replaced. Installation of the piezo motor/sei servo at the west end will be complete this week. We also restarted the ISX1000 in the mass storage room in an effort increase the network speed. There is a noticable improvement but, it could be better. Further investigation is ongoing. Chethan is installing two new sunblades 1000's in the control room, with 4 new flat screens. We have completed the replacement of the power and fiber down the south arm. The fiber will be terminated on Tuesday. We have also received the patch panels and termination kits for both of the new fiber cables that go from the mass storage room to the communication room in the new building. Those cables will also be terminated next week (Wooley)
 
 


Detector/Technical Support (Whitcomb, Coyne)



 

DETECTOR SCIENCE & ENGINEERING

Seismic Upgrade Project

Rich Abbott shipped an L4C geophone interface electronics module to LASTI for evaluation.

Machined maraging steel spring, first article is now at the plater (electroless nickel plating). Will do spring rate measurements at LSU next week. Quotes from EDM shops are being sought for the springs needed for the LASTI HEPI testing.

Hydraulic External Pre-Isolation (HEPI)
·Hydraulic Actuator (Jonathan Kern): Stanford (Corwin & Dan DeBra) have suggested a modification of the welded actuator so that the bleed valve is ported back into the return line within the welded actuator so that fluid is not released in the LVEA. Jonathan is detailing the drawings for these changes based on the solid model from Corwin. Quotes from vendors are being received. Expect the cost of the machined parts for the actuator assembly will be from $2.5K to $3K per actuator. Quote from Hyspan for the bellows is due next week. Expect the hydraulic actuators for LASTI to be available in early August.

·Hydraulic Servo-control Valve (Jonathan Kern): Planning a teleconference discussion with Parker Inc.on potential failure modes in assembly of the new nozzles and to go over the assembly and calibration procedure that we would like for them to follow on our customized values.

·Pump Station (Ken Mailand): The prototype pump station (intended for LASTI) has been running for a number of days in the CES building at CIT. Found inadequate inlet pressure (causes intermittent cavitation or hydraulic hammer). Interim solution is pressurizing the reservoir with air (4 psi). Final design will include more hydraulic head. Reviewing pressure drops, flow rates and temperatures to assure ourselves that all is OK.

·Pump Station Pressure Stabilization Servo (Rich Abbott): Will take transfer function measurements this week as well as a baseline pressure fluctuation noise spectrum.

·Ken Mailand beginning work on the distribution manifold design for LASTI testing. Held discussions on distribution design at LLO as well.

Electro-Magnetic External Pre-Isolator (MEPI)
The MEPI Spring/Actuator assembly parts will be received at LASTI within about 2 weeks. Will put together one assembly and evaluate before building all 4. Installation on a HAM chamber should start mid-July.

CDS Software

Rolf Bork reporting:

·Alex and Ash completed EPICS database changes for LHO4k digital suspensions; being tested at LHO.

·Alex found/fixed problem with filter switching in standard filter module software. Change has been incorporated in LHO2k LSC software and is being tested at LHO.

·Continued to have problems with LHO2k ASC front end losing comms with Y mid station.Shipped a new CPU to LHO and this appears to have fixed the problem.

·Working on putting new ASC code on LHO2k.Having some difficulty as the code does not seem to work same there as on our development system here (filters don't switch properly unless DEBUG flags are set).For tonight, they are running with those DEBUG flags set and we will try to further debug the problem tomorrow.We will probably have to debug on their system as the problem couldn't be recreated here. 

·Sigg has requested added dewhite switching capabilities in the end stations; Will work that tomorrow.

CDS Hardware

Rich Abbott reporting

·Shipped out the new field interface box for the L4Cs and Inductive position sensors to MIT for test.Began building 6 more for other customers.

·Continuing to work on the hydraulic pump servo system.Flavio and Mohana are getting involved in the process in addition to their normal duties to broaden their scope.

·Flavio returned after successfully installing the ISS systems in all interferometers.There are issues to be solved regarding a power supply related latch up condition in the DCPD.Bench testing should be able to be performed to analyze the problem and two units from LHO are being sent back to CIT for Flavio to examine.

Sander Liu

LEMO Antialiasing Filter Chassis: Fabrication and test on S/N 212, 213 and 214 is complete. They will be delivered to 40M as soon as Ben has a chance to take them over. We are recalling S/N 208, 209, 210 and 211 from 40M to incorporate DCN LIGO-E020580-00-C.

Micro-Seismic Signal Processor:

·Remote Interface Box: In the process of building chassis internal inter connect cables.

·Post Processor: Building of the twelve circuit boards is complete. The front plate has a mechanical mistake and Fred is in the process of correcting them. Writing of the Acceptance Test Procedure is in progress.

PSL

PeterKing

The instrumentation rack in the PSL Lab is in the midst of being re-assembled.The power supplies, reference cavity heater jacket power supply, VME crate and Eurocard cage have been installed on supporting shelves. The wiring is being re-organized.

Optics Analysis

Erika D’Ambrosio

I prepared a draft on the sidebands imbalance that ended up to be quite large.

I am studying the detection scheme and I have to say that, from a mathematical point of view is rather complicated (the real design with the bandpass filter, the square waves generator and so on). This has to be done because I still am not sure of the impact of the sidebands imbalance on the strain sensitivity. There is no mention of any numerical estimation in the paper I have prepared. 

I have a lot of nice things I only understood by putting in order all my notes and I am looking forward to talk about them with Bill. One big issue is related with the way the FFT-code and Melody lock the cavity lengths. 

For the simulations I have been doing on the thermal lensing the difference is quite impressive: the adjustments are linear with the perturbation in Melody while for the FFT-code they look like quadratic.

Optical Contamination Cavities

Lee Cardenas, Liyuan Zhang

OTF Lab.

We continue taking measurements for both Contamination Cavities.We are continuing to plot both the cavity ringdown and cavity thermal lensing for both the control (empty) and the mineral oil sample cavities.

Cavity #2which has the mineral oil sample we have determined the surface absorption be kept at ~2ppm saturated level.But, Its ringdown still shows a big fluctuation.We blame to the room temperature change which has been taken care of already.

Took measurement of the Beam waist for the new NPRO S/N 415 as to be 0.208 mm.

We have completed the assembly of optical transmission test set-up.We are waiting on the base support which is coming next week.We took transmission measurements for a 300 ppm mirror from the old cavity#2 (JCamp)

We measured this mirror transmission to be 250 ppm. Instead of the 300 ppmwritten on the box.

We have used a fast responseGaAs THORLABS photodetector PDA255 instead of the Silicon chip type.

We also have tested different Photodetectors to find the difference but they all fluctuate.

The Ga Aschip Photodetector is more efficient and stable.

Zoom Optical Lever Objective Lens (40 m focal length)

Mike Smith (from Virgo)

An afocal design with a telecentric final focus lens was analyzedand was found to be acceptably stable with respect to the tolerance of the placement of the lens elements. Working drawing are in process, using an Italian language version of ACAD. The overall length including zoom lens front element and QPD sensor is approximately 11 in. A prototype of the lens system will be built and tested when I return to CIT later in June. An intensity stabilized 830 nm laser with beam expander/collimator will be purchased for use as the optical lever beam.


40 Meter Interferometer (Weinstein)



 


Thermal Noise Interferometer (Libbrecht)


no report


LASTI (Zucker)


no report


Data Analysis and Computing (Lazzarini)


Simulation and Modeling (Bhawal)
============================

Working with TAMA
--------------------
At GWADW in Elba, Hiro talked with Dr.Sato, Dr.Arai and Dr.Ohashi about
the continuation of the modeling efforts. The MOU attachment is already
(supposedly) updated to cover the near future activities. One specific
topic discussed was the effect of misalignments on the performance of the
power recycling configuration.

Working with SLU
-------------------
On May 16th, Hiro discussed with Dr.Yoshida about the collaboration with
SLU on modeling related activities, involving undergraduate students.
One practical issue is the installation of e2e on their machine, and this
will be completed after Dr.Yoshida comes back from Japan in the middle of June.

SimLIGO
---------
(Matt) Implemented SimLIGO frequency noise and common mode servo.
A bug was found in the Michelson summation cavity when the laser
frequency was changed as a part of the common mode servo, and Biplab
is looking into it.

FFT and E2E for Mode Mismatch
------------------------------
(Biplab) In order to understand the capability of the modal model
( what kind of physics, under what kind of condition, how accurately , etc)
e2e calculation is compared with the FFT calculation. In general, they seem
to agree each other, but some differences are observed, especially fields
in the Michelson cavity. One question raised was how similar or different
the "locked" state of FFT is compared to the real locking mechanism, which
is used in e2e. A few approaches are suggested and are being investigated.

Code development and maintenance
---------------------------------
(Hiro)
Keep working on feature enhancements and bug fixes.
Updated parameters  of the DAC noise to be more consistent with measurements.
Started to revise the "Getting started" document to be included in the next release.
Revised "Primitive reference manual" to include new features added and clarify confusing points.

Alfi
-----
(Melody)
- Continuing on the implementation of the 'Find' feature for alfi5.
(Bruce)
- Implemented long waited JUNK feature, and improving it based on early feedback.
 

LIGO Data Analysis System
======================

Software Systems (Blackburn)
========================

The focus this week has been on fixing mid-size to large-size memory leaks that have crept into LDAS during our rapid development. As of today we have been reasonably successful in removing these. A 450 KB per inspiral dataPipeline leak was isolated and removed. This allowed us to be able to run the dataPipeline jobs through the dataConditionAPI for a full night without a restart. There is still a 10 to 20 KB leak in the dataConditionAPI which we are looking for which will force a restart every couple of days on systems with the limited performance of our development and test systems. We also tracked down and fixed a memory leak in the frameCPP C++ I/O frame library. This leak only occurred when reading in processed frames and resulted in a stunning 4 GB per minute leak when processing the Short Fourier Transform (SFT) frames produced by the periodic DSO. We have also found a significant memory management issue in the frameAPI. While this memory management issue does not leak memory, it cause significant amounts of excess memory to be used and slows down the frameAPI by factors. This issue should be resolved in a couple of days.

We have been testing LDAS overnight on three to four different systems with pre-release software. Between 5000 and 10000 jobs are being sent through a night to track down problems with the system so that we have a reliable efficient release to turn over to the authors of DSO search codes early next week. The two most significant bugs we have discovered in this process are a server socket circular buffer mangling issue in the dataConditionAPI which causes about one out of fifty jobs to fail when the jobs are not all identical in resource requirements, and a problem recognizing when a remote data resource is available for usage in a job. These are both actively being worked on and hopefully will be fixed soon.

The reliability of this pre-release of LDAS is still very unstable. Failure rates are fluctuating up and down on almost a nightly basis. This has been do to the unusually large about of code development that has had to go on so late in a “development-release” cycle. As of mid week this week, it looks like we are starting to ramp down the number of changes to the code and seeing a hint that the system will be in very good shape by the middle of next week.

Several meeting were held with week to coordinate plans for LDAS to produce reduced frames during the E8 run this weekend. The reduced frames will have approximately 130 channels in them and fast channels will be resampled by a factor of 2x. This will result in about a 5:1 ratio between full frames and the reduced frames. We will also spend some time running a DSO that makes heavy use of the frameAPI concurrent with the jobs in LDAS that reduce frames.

We also begun holding meeting with the LSC to coordinate schedules and plans for the Science Run. This activity will ramp up over the next couple of weeks as we zero in on the specifics of what we will be performing with LDAS beginning a couple of week before and carrying through the Science Run.

Hardware Systems (Anderson)
========================

Caltech
-------
(Al Wilson)

* Sent master-node files to the sites. These will be used to build the new
  Beowulf nodes.

* Final testing of the System Imager procedure.

* Assisted Ed and Masha setting up the Password Request page on the ldas-sw
  https.

* Placed an order with Ed to get "bakers racks" for the cit system.

* Received the Cat-5 cable order, not what I wanted so returned the calve to
  shipper
 
 

MIT
---
(Keith Bayer)

* Replaced Sun LCD monitor (shipped defective one back to Sun).

* PC Raid Box:
  * decided on 16 node rack mount unit.

  * getting quotes for PC equipment.

  * researching power specs on rackmount unit.
 

Livingston
----------
(Igor Yakushin)

* Together with Rus, Mike and Ken finished building 3 racks.

* Playing with DataJoin Replication Administration tool which gives more
  control over administering replication than db2cc but unfortunately only
  runs under Windows. In particular, it allows configuring external CCD
  tables for staging data for multi-target replication. db2cc does not
  provide a way to configure CCD tables.

* Did all the paperwork for the new equipment: sent receipts to those
  who need them, tagged all the equipment and filled the papers (serial
  number, tag number, etc.).

* Flattened the LDAS network.

* Tested the new switch.
 
 

Hanford
-------
(Greg Mendell)

* Ran tests on the new QFS file system and found that an "ls" command
  run on a shared_reader and the NFS client of a shared_reader did not
  alway show the latest files (in fact an "ls" command could be days out
  of date).  Worked with Dan Kozak, Dave Barker, and Stuart Anderson to
  solve the problem.  On advice from Sun we have upgraded qfs to version
  3.5-57 and added "invalid=0" to the mount options in /etc/vfstab  for
  shared_readers. (This mount option should cause file system changes to
  update immediately on the shared_readers.)  I am rerunning my tests.

* Flattened the LDAS network at LHO to place all servers and beowulf
  nodes on the same private network.

* Began installation of the new 64 node beowulf cluster, with help from
  Larry Wallace.

* Preparing disk space and the writing of data to tape during E8.
 

General Computing (Wallace)
=======================

MIT:
(Keith)
-Installed new gcc / pine software
-Continued to install MU7 on Solaris machines
-Investigating / testing wireless options for PAC meeting (end of month)
-Trimmed relay-domains on mail-server (attempt to limit spam)
-Relayed information on network performance testing.

Livingston:
Nothing to report.

Hanford:
(Christine)
- Set up another new guest PC and installed the standard configuration
software on it.
- Started cleaning personal files off 9 old PCs which will be used as
spares and some sent to Larry at Caltech.
- Created a new account for a SURF student and helped get her laptop on
our network and installed some software.  Showed her how to use our
computers and helped get her settled in.
- Lots of user support and new accounts for E8 visitors.  Cleaned up the
Computer User's Room for E8 visitors and put out more ehternet hubs.
- Attended a meeting about new and increased bandwidth network
connections.
- Followed up on a complaint received that one of our computers was
probing ports on someone's computer.  Tracked down the offending
computer and owner.  Ran virus scan software and trojan scan software on
the offending computer, nothing was found.  The computer is a Macintosh
and the owner is a long term visitor.
-Went over a number of issues with Larry and will be working on the VRVS
system and some of the computer security items while he is visiting.

(Larry)
-Toured the new building with Richard M. and will be talking with Otto
concerning noise issues with the computer room.
-Talked with Richard and Christine concerning the meeting with NoaNet.
This meeting is to try and narrow down what is needed, to get the Observatory
more bandwidth.
-Worked with Greg on installing LDAS equipment.

CIT:
(Mike)
-Loaded a PC with Win98 and all General Computing software; plus set this
workstation up on the second floor in RM: 252.
-Surplussed some old equipment that was in a cubicle, that I had to setup for
a visitor's workstation. Then I setup this cubicle with a PC and Monitor.
-Worked on the Pherkab copying DATA over from old server to new server,
setting up ODBC drivers, and running some tests.
-Setup a loaner laptop for Florance K. that included reinstalling some software,setting up a dialup account and configuring email.
Also, installed a zip drive on her office computer.
-Moved a portable 9000 BTU air conditioner for 40M to use. This unit
came out of the server room. This is to be used as a test to get a better idea
of what is needed for that area of the 40M.
-This was a busy week for onsite/phone support that included restoring data
from backups, software/hardware troubleshooting, upgrading software and
printer problems.

(Lisa)
- About halfway through building the new luna.
-Finished up the build of alterf that Larry started.  Alterf is a sandbox that
is now available for simulations.
-Put up a couple of new FAQs.  For those who have not recently looked over the
GC FAQs, you will find some useful information at the following URL:
http://docuserv.ligo.caltech.edu/docuserv/computing/faq/faq.html
-Created some new accounts and helped out the new surf students.
-Did some research on wep including intermixing non-orinoco wep schemes and
40bit wep compatibility.
- Still working out some glitches with the permissions on the lsc-all and
citonly mailing lists.
-Ran patches on bellatrix
-Tried to run patches on atria but the pkginfo for one of the core architecture
components was corrupt and atria will need a rebuild.
-Heavier than usual round of user support.

(Larry)
-Started new OS loads on the sandbox units. Alterf is now finished with four
other units at various stages. These are all SUN boxes with multiple CPU's.
-Worked a number os spam and forged e-mail issues. A number of the latest
problems are from Europe with spoofed names of those that had attended the ELBA
conference. All that have attended the conference are encouraged to change
their password and those with a PC should run virus-scan on their entire system.We are also blocking e-mail from a number of locations in Europe. The list
grows on a daily basis.
-Worked a number of procurement related issues. Mostly, supplies and checking
on late deliveries.
-Working on various documents covering Budget, Policy, Security and network
usage.
-Updated the web usage statistics for LIGO. Because, of a corrupted file there
are a number of weeks in May that have been eliminated and pretty much all of
March is gone.
-Still looking into security items for the remote control room. So far the
remote control rooms are being used by a limited number of people.
-Working a number of logistical issues for different users needing special
setups.

(Veronica)
- Made several updates to the LIGO home pages. Most of the time was spent
working on the webpages for LIGO Press and Media Kit. Attended a meeting
on the subject, which also covered the design of handout folders.
Attended a presentation by the Caltech Digital Media Center on the basics
of platter burning.
Working on the Policies and Procedures webpages.
The Elba Conference transparencies are now almost completely online, with
just a few still missing. Collecting photos for an online slideshow,
similar to the one at the last year's Aspen Conference.
- CaJAGWR: updated the seminars page. Met with a student from TAPIR to
discuss how-to of digital video; he is the one who records a series of
TAPIR lectures. The same setup would be useful for LIGO (i.e., taping LIGO
seminars and posting them online for those at the sites to view).
 
 


LIGO II/Advanced R&D (Sanders)


From: Janeen Romie <romie_j@ligo.caltech.edu>

AdLIGO Suspensions
Blade maraging steel has been delivered from Alloys International. This is blade stock for the RM and ETM controls prototypes. We will start blade procurement soon. Ric in the Physics machine shop is making MC prototype blades. He has made two from the annealed (American) material and two from the age hardened (French/GEO) material. The blades now need to be heat treated after a bit more forming. We've consulted Riccardo and Marcel Hammond for techniques and baking recipes.
We are preparing the Synchrotron lab for our SURF students, who'll be here in a week or so.

Dennis has determined that Algor doesn't like parts with millimeters for units, which explains some faulty results I've received from Algor for some natural mode analysis of the MC structure. I've checked and changing to centimeters seems to do the trick. I'll continue the analysis in centimeters to keep Algor happy.

Working on updating the SUS schedule for Thomas. I should be submitting a redlined schedule to him tomorrow morning.

Working on a table of callouts for oversized tapped holes, based on Hytec experience, to avoid galling. I'll distribute it when complete.

Still waiting for a GinGin PTA to buy new osems.

Coordinating Jay Heefner and Harry Ward to make sure we get a complete electronics system for the first MC controls prototype in August.

Still playing phone tag with IDEAS/EDS Unigraphics Solutions technical support rep. about the best translator from Solidworks to IDEAS and back. Quite frustrating.

Coordinating with GEO and Todd Etzel to fabricate and test the controls prototypes local control sensor/actuators. I gave the circuit boards, LEDs and photodiodes to Todd. I've given Todd an idea of when the heads (fabricated in Glasgow) will be delivered to him to start assembly and when we need them back.
 

From: ctorrie <ctorrie@ligo.caltech.edu>
ADVANCED LIGO SUSPENSIONS

Mode Cleaner

Continuing to work on obtaining a complete set of drawings that can be sent out to machine shop in the Pasadena or Los Angeles area.
Janeen Romie and Larry Jones have been  helping with this. I hope to have the parts in a machine shop by the end of June.
Janeen and I have been working with Richard in machine shop on a set of prototype blades

MIT quad.

Norna and I have been working with some measured numbers supplied by Rich Mittleman.
Rich has produced some impulse responses, see his report. These show very good damping in both pitch and longitudinal and as a result show that the changes implemented on the quad at MIT have been a success.
There is one more set of physical parameters of the quad that we are investigating.

From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>

Eric,
first summer student arriving, welcome.
Starting working on glassy metal film x-ray micro densitometry.

Hareem
Splatting more samples.  Working on AuSi brazing alloy.

Aso
Back from Hanford, calculating speing constant for flex joints.

Mike
Ordered heat conductivity epoxy for thermal conductivity measurements, prepared heat capacity dummy puck.  Also making special patch cable for heat capacity sensing.
Thermal conductivity measurements, perhaps seeing the light at the end of the tunnel.  Hi-Vac working after changing also the pressure gauge and fixing cabling problem.

Kelin
Building setup for Q measurement in West Bridge subbasement lab.

Ric Hareem
Restarted creep measurement on June 3rd, acquisition had stopped since May 13th due to a software interference.
 


For additional information about this report, contact sanders@ligo.caltech.edu