Weekly Report for Week Ending May
30, 2002
The LIGO Executive Committee
Agenda for Monday June 3, 2002:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
-
Announcements
-
LSC Issues (Weiss)
-
Comments on Weekly Report
-
WBS 1 LIGO I Construction (Lindquist)
-
Field Change Orders/Contingency Liens/Change Requests
-
WBS 2 LIGO Lab Operations
-
Administration (Lindquist)
-
Sites (Raab, Coles, Shoemaker, Sanders)
-
Detector (Whitcomb, Coyne)
-
Campus Research Facilities (Weinstein (40 Meter), Libbrecht (TNI), Zucker(LASTI))
-
Data Analysis and Computing (Lazzarini)
-
WBS 3 and 4 Advanced R&D and LIGO II
(Sanders)
Executive Committee only 11:30 - noon
Topics:
Special Items:
Special Announcements:
Weekly
Report Highlights
(Rai Weiss)
As a result of work at both Hanford (on the
two-kilometer interferometer) and Livingston (four-kilometer interferometer)
we achieved strain sensitivities during the last week a little better than
that measured on the 40-meter system in 1994. This is the case over the
entire gravitational wave band, from 100 Hz toward the higher frequencies.
The sensitivity is better than has been achieved with any previous broad
band detector. And two of them, that is really a first. Two
interferometers at separated sites support coincidence techniques for the
gravitational wave search.
Daniel Sigg and Rana Adhikari are the recent
heroes standing on the shoulders of a lot of other people.
LSC Issues (Weiss)
no report.
LIGO I Construction/LIGO Laboratory
Administration (Lindquist)
LIGO Weekly Site Telecon (Lindquist)
There was a site teleconference held on Thursday, May 30, 2002.
The following items were discussed:
Status of Commissioning: (See below.)
Action 106: Outfitting and Populating the Building at Livingston,
Ed is planning a trip to Landover, MD (GSA collection point) on June 11
to check out some furniture. The plan for population at Livingston
has not been finalized; still looking at some options. Gerry is on
route to Pasadena and will be here next week.
Time line for spend out of construction funds: Gerry has identified
up to $325,000 to be requested for completing the new facilities.
Some of this will be for outfitting the laboratory for MRE effort.
Air conditioning and fire suppression for LDAS room also included.
We have not yet seen a change request. Phil to help Gerry prepare
a Change Request next week. Money for outfitting labs basically to
be provided at time needed, especially since needs cannot be known at this
time.
Livingston Staging Building: working on punch list (75 - 80 percent
complete). Some will drag on.
Building at Hanford: Reported progress is good. Getting
PO today for audio/visual equipment. $80,000 purchase order will
include two projectors.
Property: Ed is looking for 1) a good street sweeper for
Otto, and 2) a small Bobcat for Gerry, kind of tough right now.
The list of current actions revised to reflect
the status of open actions assigned through May 30, 2001 may be found at
ACTION
LIST.
PROPERTY
MANAGEMENT (Chargois)
From: Ed Chargois <chargois_e@ligo.caltech.edu>
-
Nothing significant to report.
DOCUMENT
CONTROL CENTER (Turner, Mak)
>From: Linda Turner
- turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy
access to the latest on-line documents, and search capabilities for the
DCC database.
Take
a look. . .
ACCOMPLISHMENTS
-
On vacation May 29th thru June 20th.
>
From: Cleveland Mak <mak_c@ligo.caltech.edu>
ACTIVITY
-
It was a short week with Monday being a holiday and was out on Tuesday
as well.
-
Progress continues on conversion of old charge account files to electronic
form.
-
Electronic document activity remains steady.
|
05/30/02
|
Packages
|
Faxes
|
|
In
|
37
|
25
|
|
Out
|
9
|
17
|
COST SCHEDULE
CONTROL SYSTEMS (Cunningham, Brambila, Kaufman)
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS
PAYABLE HISTORY DATA .

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
-
Closed out and removed encumbrances on several contracts as requested by
Irena Petrac jointly with Florence Kaufman.
-
Completed the no-cost extensions to S.I.O.M. and E.G.O.
-
Working on sending out the results of the RFQ to all the bidders of the
AV Presentation system for Hanford, and issuing the order to the lowest
bidder. The decision was made late yesterday after a site meeting
with the lowest bidder.
-
Working on resolving the tax issue with Superior Jig.
From: Florence Kaufman <fkaufman@ligo.caltech.edu>
SUBCONTRACTS MANAGEMENT (Petrac,
Jasnow)
From: irena@ligo.caltech.edu (Irena Petrac)
-
Nothing significant to report.
From: Ed Jasnow <jasnow@ligo.caltech.edu>
CONSTRUCTION:
-
Construction on the OSB East Building at Hanford is going well and is on
schedule. Ed Jasnow was at Hanford on May 28 and 29 to observe the construction
progress and meet with the low bidder for the audio/visual equipment, Intelligent
Video Systems (IVS). The president of IVS, Brian Greenwood, toured the
auditorium and confirmed that he could do the work for his proposed price
of about $80,000. He will get a purchase order this week. The $80,000 price
compares with $100,000 budgeted for this effort.
-
The punch list items continue to be worked on the Livingston Staging Building.
The list is over 80% complete, but effort on the wooden stage floor continues
to flounder. Additionally, Ed Jasnow confirmed with the supplier of the
crane that he still intended to install the stops as previously agreed.
OPERATIONS:
-
There has been no further word on the possibility of using the Livingston
access road as a landing strip for crop dusting planes. We still have not
had official contact with Weyerhauser on this issue.
SUPPORT (Baldon, Torres, Lloyd,
Tischler)
>Irene Baldon
-
Please note that this report is for three (3) days only since there was
a holiday and I was out ill for one (1) day.
-
Processed the paper work for three (3) new/revised trip and there are eight
(8) trips in various stages of completion before ticketing can be done
and paper work completed.
-
Completed sixteen (16) Expense Reports and there are fourteen (14) reports
yet to be done.
-
Reconciled twenty-eight (28) P-Card items this week which required phone
calls to hotels to track down which traveler incurred which charge and
pulling each traveler's file to assure that charges are correct for each
airline fee. Assisted a couple of P-Card holders who were/are out of town/country
with their reconciling and/or expense reporting.
-
Worked on the preparation and distribution of the Travel/Vacation Itinerary
for May 28, 2002.
-
Performed normal recording and filing associated with Travel and Reimbursement.
-
Performed miscellaneous duties as requested by various members of the LIGO
Project here at Caltech as well as from members of the staffs of each of
the two (2) sites.
-
I continue to do MIT's travel to the sites for installation activities
and also to assist them wherever possible.
>Dorothy Lloyd
-
On vacation May 27th thru May 31st.
>Rita Torres
-
Formatted milestones report from Oregon, placed it onto the small web page
for review along with their Attachment A, and progress report.
-
Placed into the DCC out box Stanford reports for sections B-D, and also
Southern University A&M progress report, after these were reviewed.
-
Formatted a lengthy report from GEO, this is now in review.
-
Continue to track progress of orders placed for M. Smith while he's away.
-
I'm submitting the incoming partial orders to the 40m staff. Finally got
info on an item that was returned for repair.
-
Arranged for another eye exam and laser training. The Caltech Weekly Update
lists dates for upcoming laser training sessions.
-
Continue working on update to the addresses contained in the LSC-ALL alias.
Working only on the LIGO portion, the non-LIGO portion to be done later.
-
Arranged a telecon for: Burst injected signals.
-
Placed several Pcard orders, reconciled a few after chasing down the paper
work. Started a $90 requisition for a vendor that does not take credit
card.
-
Changes to LIGO roster this week: SURF students Kyle Barbary, and Eric
Kort.
-
INFORMATION : US postal rates change on June 30, 2002. Visit -- http://www.usps.com/ratecase
>From: Ryan Tischler <rtischle@ligo.caltech.edu>
Advanced LIGO (Frey)
From: Thomas Frey <tfrey@ligo.caltech.edu>
Progress Period from 05.24 to 05.30
Accomplishments:
-
Out of the office Friday the 24th.
-
Weekly Advanced LIGO Project Controls meeting was not held this week.
-
Continued to work with Primavera regarding an outstanding technical issue
and received a program patch that I am now using and testing.
-
Advanced LIGO MRE Proposal (Highest Priority)
-
Per direction of Gary, Dennis, David, and Phil, I am updating the presentation
from November with most current data for meeting to be scheduled in June.
-
Continuing the development of the Cost Estimate.
-
The following is a summary of status by sub system:
-
COC - Work on action items per second review continues. Next meeting
date has not been scheduled.
-
PSL - Next meeting date has not been scheduled.
-
AOS - Work on action items continues. Next meeting date has not been
scheduled.
-
IO - Work on action items continues. Next meeting date has
not been scheduled.
-
SUS - Working with SUS group to incorporate current comments.
-
SEI - Work on action items continues. Next meeting date has not been
scheduled.
-
ISC - Made arrangements for trip to MIT and work plan for interface with
Mike. Started work preparing draft data for Mike to review / fine
tune during trip to MIT.
-
LDAS - No data / feedback from Albert to date.
-
All other subsystems have yet to be scheduled for their first review.
These dates are pending per direction from Gary Sanders and Dennis Coyne.
-
Continue to update the TNI Schedule and incorporate any changes.
-
Data pending to revise plan to version 3 due to additional efforts to isolate
noise.
-
Continue to update the LASTI Schedule and incorporate any changes.
-
Project Plan for the 40-Meter Lab Upgrade continues.
-
Cost Book Tool.
-
ROSTER DATABASE:
-
Continue work on my action items providing BK with needed data.
-
COST BOOK DATABASE:
-
Gang of 5+:
-
Continue work on procurement documents per request of Phil / Gina / Dot.
-
DCAA - Work continues on the incurred cost audit.
-
Nothing new to report (All Quiet on the Western Front).
-
Development of the Advanced LIGO Project Controls Guidebook continues.
-
Project Web Site for posting schedule and progress related data continues
to be updated with the latest and greatest.
Schedule 05.31 to 06.06:
-
Next weekly Advanced LIGO Project Controls meeting is to be scheduled for
early June. Subject: MRE Cost and Proposal Development.
-
Advanced LIGO MRE Proposal (Highest Priority Task)
-
Highest priority is the development of the Cost Estimate.
-
Will continue to pursue all other sub system schedules.
-
PSL - Will complete estimate and schedule changes. Should be meeting
with Peter King to look through estimate to separate LIGO Lab scope from
LZH scope.
-
AOS - Continue inputting changes to and prepare for next meeting TBD.
-
IO - Continue inputting changes to and prepare for next meeting TBD.
-
SUS - Continue inputting changes to and prepare for next meeting TBD.
-
Will update the plan when data is made available. Hoping for progress
through May 31, 2002.
-
SEI - Continue inputting changes and prepare for next meeting TBD.
-
COC - Work on action items by Garilynn continues. Anticipate schedule
changes prior to next meeting TBD.
-
ISC - Travel planned to MIT for the week of June 24th.
-
LDAS - Will work with Albert to develop details.
-
Will issue updated meeting minutes for every subsystem as action items
from most recent review are completed.
-
Will Continue to update the TNI Schedule and incorporate any changes.
-
Will update the plan with progress as of 05.31.02 and post to site
by the 5th.
-
Will Continue to update the LASTI Schedule and incorporate any changes.
-
Will update the plan with progress as of 05.31.02 and post to site
by the 5th.
-
Will continue updating the 40 meter schedule and incorporate any changes.
-
Will update the plan with progress as of 05.31.02 and post to site
by the 5th.
-
Roster Database
-
Will continue to work with BK and executing action items.
Cost Book Tool development continues. (Highest Priority Task)
-
Mapping and formatting of OPS cost data for input will now continue with
co-operative agreement approved.
-
Will continue to work with BK executing action items.
-
Gang of 5+
-
Will continue to work on procurement documents.
-
Will continue to provide support to PL for DCAA audit(s).
-
Will continue the development of the Advanced LIGO Project Web Site.
-
Will continue the development of the Advanced LIGO Project Controls Guide
Book.
Reports (Lindquist)
August 1 we are scheduled to submit an annual work plan to the NSF for
LIGO FY 2003 Operations. We are modifying the first draft budget
for FY 2003 based on the current staffing plan and information provided
by group leads.
Change Control/Contingency (Lindquist)
The following additional
change request has been submitted:
|
CR-010012
Revision B |
WBS 1.4.4.1
|
Closeout Construction Budgets
for Initial Computer Equipment Complement at the Sites
|
P. Lindquist
|
We are expecting an additional change request from G. Stapfer for effort
to complete Livingston building.
Human
Resources (Akutagawa)
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
-
Various personnel/payroll /HR related work.
Quality/Safety (Tyler)
>From: Bill Tyler <tyler@ligo.caltech.edu>
-
Nothing significant to report.
LIGO Hanford Observatory (LHO) Operations
(Raab)
Summary of Commissioning Activities
at LIGO Hanford Observatory
(see elog for details - if it's not in the elog, it didn't happen...)
4k IFO investigations
Lots of activity to bring IFO back after software changes. Unfortunately
this was complicated by a number of hardware problems that lost a lot of
time. We have now been able to get all cavities to resonate separately
and are setting up to test full locking as this is written. We still have
a filter anomaly tofix in the software. Glitches in the PSL were traced
to a range problem in the shunt actuator. Flavio is now working with Rick
to get intensity stabilization working.
2k IFO investigations
Landry has released the autocalibration software so we can now easily
(and more frequently) produce calibrated spectra to track stability. The
spectra have been remarkably stable in the region of a few hundred Hz with
amplitude falling like f-3 until Sunday night, May 26, when
a change in loopology had the unintended effect of dropping this low-frequency
noise by about a factor of 4. The background is that operation in common
mode with higher ASPD light levels had improved the high frequency end
of the spectrum as expected by getting us above dark noise. But the change
was accompanied by a dramatic vertical bouncing of the spots on the end
mirrors, caused by position to pitch coupling of ETMs with the large common
mode drive. When the "bounce" was large, we would hear burst noise in the
DARM_CTRL loop. In an attempt to alleviate this problem, Daniel tried to
remove the CARM_CTRL drive to the ETMs by bringing all common mode feedback
back to the input optics. The change was successful, and also caused changes
in the displacement spectra, dropping the noise at low frequencies, but
raising the noise around 1 kHz. This is not understood, which is bad. But
it has produced the first warm clue on the origin of the low-f noise that
we have had in long time. Investigation of this continues. The LSC front
end code was also updated to utilize the new timing cards and reduce polling
noise in the ADC.
FACILITIES
The siding, with exception of the stainless steel panels is installed.
The Stainless steel panels are ordered and will be here in a few weeks.
HVAC, plumbing, electrical and insulation work is ongoing. The outside
area was seeded and mulched to keep the wind from blowing the sand away.
Additional landscaping will be done in September when the building contract
is complete.
LIGO Livingston Observatory (LLO) Operations
(Coles)
Higher power on the anti-symmetric photodetector
and further refinements in the common mode servo have resulted in strain
sensitivity improvements on the interferometer sufficient to be somewhat
better than the strain performance of the 40 meter system in 1994.
The improvements have been made in the band above 100Hz. Preliminary measurements
of the amplitude spectrum of the anti-symmetric error signal, the signal
that contains the gravitational wave information, exhibits Gaussian behaviour
to approximately 5 sigma in a data stream with high pass filtering above
100 Hz. Command scripts have been written to engage the common mode servo
through the many gain and filter changes required to bring it into operation.
A script has also been written to increase the light power incident on
the antisymmetric photo detector which increases the shutter transmission
while reducing the digital gain in the DARM control loop. An important
finding has been that the alignment servo using wavefront sensor 1 keeps
the ASI signal (which is not controlled directly by any servo) bounded
so that the saturation does not occur in the RF amplifiers as the light
power is increased. Work has been done in closing the servo loop from the
wavefront sensor at the symmetric port (WFS2). The pitch servo on the recycling
mirror works while the yaw servo does not. We have traced the problem to
the software.
We will freeze changes in the hardware after Friday June 7 to prepare
for the S1 run at the end of the month. The improvements we anticipate
before S1, other than clean up and improvements in operating procedures,
are:
-
installation of the piezo motor/seismometer sensor servo system at both
end masses (PEPI) which may improve the duty cycle.
-
installation of new digital filters in the optical lever damping loops
to reduce the noise between 40 to 70 Hz
-
a trial of the new common mode servo configuration that has been developed
during the past week at Hanford. We will make the decision by June 5 of
which configuration to use and make more robust for S1.
-
repair of the ASC software to re-enable the microseism feedforward system
and enable the use of the WFS2.
Active Seismic Isolation
We've redrawn ~80% the Stanford model of the Hydraulic Actuator on LIGO
templates and issued DCC numbers. Detail checking and tolerancing are in
progress. Five machine shops have been contacted, which are preparing preliminary
estimates for the production of 12 sets for the LASTI instillation. Most
shops are slow right now and several can begin work immediately. A quantity
of Stanford's modified nozzles was ordered 5/21, ~ 3 wk delivery. Ordered
12 DPY2S Parker differential proportional valves on 5/28, ~ 1 mo delivery
(These are the standard valves. Special testing and calibration using our
procedure will increase the price and delay delivery). Provided Hyspan
with drawings for the revised details of the weld-assist/shield rings on
5/28. They will reply soon with a price for the LASTI units. Returned to
Stanford Wednesday and am meeting with Dennis and the group here today
and tomorrow. Goal here is to learn more of the test and qualification
procedure for the valve, and to document the procedure for LIGO. (Jonathan)
I have made arrangements to start the heat treat-coating-joining process
for the machined spring pathfinder. I will meet with Metal improvement
Inc. tomorrow (Friday) to have them start the heat treat efforts and discuss
with them a greater quantity of springs. I have also made arrangements
with the LSU Civil Engineering department Materials lab to perform the
materials test on the machined spring. I will meet with Dr. Vojyadtis to
show him the pathfinder before I bring it to Lafayette to have it heat-treated
I along with Jonathan Kern have been working to get the pre-isolator hydraulic
actuator fabricated in time to support the current schedule. Preliminary
outlook looks promising, and we hope to be able to down select a fabricator
and start cutting by next week. I am also looking very closely at ways
to assemble and properly tension the springs, and I have come up with a
design that piggy backs the current design that uses a load cell to give
proper tension indication. I have been assessing potential interferences
with the digital model to help ensure an expedient installation . The work
continues on implementing the pre-isolator design into the BSC and HAM
stacks then utilizing techniques to successfully produce a finite element
model that reflects the physical model. This is still part of the effort
to refine the 6x6 stiffness matrix that I have been working on. (Marcel)
LDAS
Performing extensive tests for metadatabase replication from sites.
Tested various 2,3 node configurations.
-
Faulty disk replaced on gateway.
-
Received 48 new PCs. Building the racks together with Rus and Mike.
RET Program
Two teachers will participate in this summer's RET program. One is a
returning teacher and the other is from the New Orleans Public Schools.
SCIENCE & ENGINEERING SUPPORT (Coyne)
Seismic Upgrade Project
Hydraulic External Pre-Isolation (HEPI)
-
Hydraulic Actuator (Jonathan Kern): I've redrawn ~80% the Stanford
model of the Hydraulic Actuator on LIGO templates and issued DCC numbers.
Detail checking and tolerancing are in progress. 5 machine shops have been
contacted, which are preparing preliminary estimates for the productionof
12 sets for the LASTI instillation. Most shops are slow right now and several
can begin work immediately.
-
Hydraulic Servo-control Valve (Jonathan Kern): A quantity of Stanford's
modified nozzles was ordered 5/21, ~ 3 wk delivery. Ordered 12 DPY2S Parker
differential proportional valves on 5/28, ~ 1 mo delivery (These are the
standard valves. Special testing and calibration using our procedure will
increase the price and delay delivery). Returned to Stanford Wednesday
and am meeting with Dennis and the group here today and tomorrow. Goal
here is to learn more of the test and qualification procedure for the valve,
and to document the procedure for LIGO.
-
Actuator Bellows (Jonathan Kern): Provided Hyspan with drawings
for the revised details of the weld-assist/shield rings on 5/28. They will
reply soon with a price for the LASTI units.
-
Pump Station (Ken Mailand): Mechanical construction of the prototype
station (including the distribution line and the load) destined for LASTI
(after.servo control implementation and testing), has been completed. The
Motor speed controls are wired and tested and ready to go. 'Operating Pressure'
test at 225 psi nitrogen has been completed (reservoir partly filled, ran
test ~5-30). Designed a future modification to the reservoir filler
cap for a float level sensor. I have finished a scale plan view and partial
elevation [acad 2D] layout drawing, of station component assembly.
Electro-Magnetic External Pre-Isolator (MEPI)
Greg Harry is measuring the magnetic field strength
generated by the electro-magnetic actuators as part of an effort to determine
the coupling factor to the test mass magnets and assure ourselves that
it is acceptable.
CDS Hardware
Rich Abbott and Peter King reporting
Installed the VME based intensity servo board and
newly designed differential photo-detectors (designed by Ben Abbott) at
LLO last week. After getting everything installed, the system was
quickly put online by Flavio, Peter King and Rich A. The suppressed
RIN level was measured "outside the loop" to be about 2 x 10-7
at about 150 Hz rising to 3.0 x 10-7 at 10 kHz. The suppression
was consistent with the available loop gain in the servo. An attempt
was made to close the outer loop, but due to large MC power fluctuations
resulting from the daytime ground motion, the loop had insufficient dynamic
range. The PSL generic DAQ interface was re-wired to accommodate
the signals available from the intensity servo. Whilst the signals
were the same, namely the servo error point and the actuator signal, where
the signals came from on the P2 connector was different.
Flavio continued on to LHO for installation on both
interferometers there this week.
Sander Liu
LEMO Antialiasing Filter Chassis: Prepared DCN
No.E020580 to correct output signal polarity for channels 3, 19 and 32
on new builds using PCB D990147 Rev B circuit boards.
Seismic Signal Processor:
-
Remote Interface Box - Twelve circuit boards have been built. Waiting for
chassis (delivery in about three weeks) to complete task.
-
Post Processor - Work on building twelve circuit boards is in progress.
Expect completion by the end of this week.
PSL
PeterKing
Rack mountable power supplies for the PSL rack arrived
this week and will be installed. These will replace the 5 units that
are delicately balanced already there.
Optics Analysis
Erika D’Ambrosio
Sadly it took a considerable amount of time for me
and Ray Beausoleil to make the paper on Melody successfully submitted because
the fonts and the versions embedded for the compilation of our draft failed
to work when uploaded on the electronic system that was not able to generate
any postscript file. Anyway we succeeded at last! The other paper I am
having troubles with is the one on the sidebands imbalance. I generated
much more graphs trying to include only those that are useful for the "theme"
that is making clear statements on the physical causes for the imbalance.
I am still interested in understanding the coupling
with the oscillator phase noise and I talked with Guido Mueller who happened
to be in Caltech. He looked at my analytical calculations and said he is
going to spend some time on this problem. I started to think on how to
measure the "oscillator phase noise" since it should be possible by inducing
an artificial time-delay. Those measurements have not been done and in
the Ligo documents I only found the "required" values.
Optical Contamination Cavities
Lee Cardenas, Liyuan Zhang
OTF Lab: continuing measurements on both cavities
everyday.
Cavity#1: Ring down is 24.7742 microseconds
and its Beat frequency is 86.0815 MHz.
Cavity #2 with mineral oil test sample in it:
Ring
Down is 31.2098 microseconds. Its Beat Frequency is 74.4012 MHz.
In cavity 2 containing the mineral oil sample, the
surface absorption keeps at a saturated level of ~2ppm, and its ringdown
measurements show a big fluctuation, which is probably due to a big change
of the room temperature since the cavity system is very close to the air
condition port.
We have this situation with the room temperature as
it changes overnight about 20F. This causes the cavity to go out
of lock. We are monitoring the room temperature daily.
P.King made good suggestion as to have control with
the computer the slow actuator voltage of the NPRO to compensate temperature
changes in the cavity. We will look into this possibility (Lab view
program).
-
The transmission test set up is on going. Breadboard base support is in
the shop to be welded.
-
The new NPRO Laser S/N 415 is running as right now and the power is 754
mw. This laser is on the transmission optical table and it will be used
for the that purpose only until?
I have sent the NPRO S/N 256 (Not functional from
RSE LAB/CIT) to Lightwave for repair. This laser is only 100mw of
power. I would like to use this laser for the transmission test set up
once it is repaired and the new NPRO S/N 415 to be used for the third contamination
cavity.
Misc Tasks: 12.5
MHZ, 5watts power amplifier are being fixed. Placed orders, etc.
40 Meter Interferometer (Weinstein)
Suspended mass mode cleaner (Ugolini, Miyakawa, Vass):
-
Now that the suspension controllers are in place (see below), effort is
underway to align all three suspensions of our 13.5 m mode cleaner, using
a procedure outlined by Dave Reitze. Much use is made of pitch and yaw
offsets on the digital suspension controllers. Work is proceeding well,
and all three suspensions are now very close to correct alignment; the
job should be finished by the end of the week.
-
Watek cameras are looking at the three suspended optics. The image quality
on the monitors was extremely poor until Mike Zucker alerted Steve to the
existence of a "low-light level" switch on the cameras; the image is now
much improved. Camera housings (to shield ambient light and protect the
camera and viewport) should be delivered by 6/5.
-
The Watek looking North is supposed to see MC1 and MC3, but the mirror
it looks through is too small. Larry Jones is drawing up parts for a wider
mirror, so that the camera can see both suspended optics.
-
Assembly of the MC reflected and transmitted optical sensing train has
been on hold while needed parts trickle in. We expect to have almost everything
by the end of the week.
-
Osamu has gotten a decent signal out of the repaired optical spectrum analyzer
(Tropel), with a 2% transmission. He's now commissioning the two RF sideband
EOMs (Pockels cells) in the IOO (29.486 and 33.207 MHz; the latter was
just ordered and received in one week!), and will look for these sidebands
with the Tropel.
Suspension Controllers and Mode Cleaner length controls (B. Abbott,
Heefner, Taylor, Ugolini, Miyakawa):
-
The digital suspension controller system is working well on all three mode
cleaner suspended optics. The controllers are left on (damping) 24x7, routinely.
Various loose ends are being worked on at a low level: refinements to EPICS
screens; getting all relevant channels into the DAQ; finalizing the timing
system; tuning the gains for all degrees of freedom; measuring the transfer
functions and noise.
-
Jay's Watchdogs are in place to shut down the controllers if they start
acting crazy.
-
Ben and Bob are wiring up the Mode Cleaner controls rack (1Y2), including
the cables to the sensing table. The last of the required modules should
be in by the end of the week. Ben is bringing over the RF photodiodes and
WFS's by the end of the week.
-
Dave Barker, Alex Ivanov, and Jay have set up an AutoBURT system at the
40m, which has been logging snapshots hourly since May 23. Now we need
to pick some reliable default snapshots, and arrange for them to be automatically
restored when a crate is rebooted.
DAQ (Rolf, Ivanov): There haven't been any DAQ frame logging interruptions
in the last week, ever since Alex rebuilt the RAID array.
PSL:
-
The PSL has been behaving stably for the last week. Several outstanding
problems remain to be investigated when we get a chance: PSL PMC servo
becomes unstable at the nominal gain (30 dB), and has been operating at
18 dB; the PSL FSS system exhibits a large 7 kHz noise peak; mode matching
in the IOO to the mode cleaner has not been checked and there is reason
to believe that it is not right.
-
From Rich Abbott: The VME controlled intensity servo was installed at LLO
last week. Thanks to the excellent test environment at the 40m lab, we
were able to pre-check all the electronics and iron out the bugs prior
to getting on the road. The installation went very well without any major
hitches. Thanks to all involved.
Optics (Billingsley, Armandula): GariLynn, Helena, and Alan met
to go over the status of the polished core optics. Most optics have visible
scratches, but mostly within tolerance. A scratch in the central 10 mm
of SRM01 brings it out of tolerance, and we discussed sending it back to
CSIRO to polish it out before coating. Since then, GariLynn has determined
that the scratch is very small (20 um by 2 um), so we will live with it.
All core optics go out for polishing by REO on July 8, and Helena will
be there to observe. It will take approximately 3 weeks to coat all the
parts.
Computing:
-
Lisa Bogue and Mike Pedraza have set up a secure wireless access point
on our martian network (40MARS), and installed three wireless laptops for
use as an EPICS monitor screen. HOWEVER, the laptop screens are too small
for some EPICS screens! Worse, there is something very unstable in the
network; the screens often hang for many minutes before recovering or losing
the connection. To be diagnosed...
-
Lisa is preparing a tape backup system for our disk server, op140m.
-
In the last week, we have not seen the vacuum control EPICS cpu hang with
a "network connection lost" error, requiring a reboot. This was plagueing
us last week. We will keep an eye out...
STACIS seismic isolation system (Ugolini): Two bad STACIS isolators
were shipped back to TMC for repair. They have been repaired, and have
been shipped back to us. We expect them any day now.
Facilities and vacuum envelope (Vass, Jones):
-
Our newly repaired V1 valve has a pneumatic nitrogen leak. This requires
a new part, from VAT in Switzerland, that we hope to receive in 1 week.
Meanwhile, we can live without it.
-
Steve had all the 40m cranes inspected by the same guys who inspect the
CES cranes. Next week they will be back to do a load test, and then certify
that the cranes are operating properly.
-
From Larry: SP&MC table cover: short pieces already in anodizing, long
pieces going out today; expect completion on 6/5.
-
Camera housings: small parts are complete; housings machining and welding
are complete; housings have been sent out for clear anodizing (my mistake;
I hadn't marked out this note on the drawing, only canceled it verbally);
expect completion on 6/5.
-
Beam tubes: short pieces already in anodizing; long tube going out today;
spun angle rings were received 5/28 and found to be made wrong (ID was
made too small), were sent back for rework; once corrected, will need to
be anodized; anticipate completion on 6/7, if things go well.
South Annex Bake Ovens (Taylor, Cardenas):
-
Bob sent two malfunctioning RGA heads out for evaluation / repair.
-
The new SRS ionization and pirani gauges installed onto the main volume
of bake chamber #E check out ok.
-
The 2nd new large bake oven (oven #F) is nearing completion. Plumbing parts
for this oven are being baked out.
-
Bob and Steve ordered calibrated leaks (LIGO calibrated mix) for the bake
ovens and the 40m vacuum system.
Thermal Noise Interferometer (Libbrecht)
This week we began looking at ways to reduce the electronic noise in
the TNI. As a first step, we looked at where the electronic noise came
from in the current configuration. As it turns out, most of our noise comes
from the first SR560 in our servo filter, and with our present setup there
is no way to substantially reduce this noise.
Our spec requires that the input noise of our servo filter be 30nV/rHz
or less to give an equivalent length noise of 10-19 m/rHz. Our
chain of passive circuits and SR560's, while allowing us to lock during
the day, does not meet this requirement. Jay Heefner offered some advice
on how to achieve this in a custom-built circuit, and we have started,
with his help, designing a unit to replace our SR560-based prototype electronics.
We also measured the noise in our active notch filters directly and
got approximately 5nV/rHz, punctuated by a number of peaks at 60Hz and
its harmonics. Fortunately, these filters can meet our noise requirements
and can be retained when we replace the rest of the servo filters. We are
working on ways to eliminate the 60Hz harmonics.
Kyle Barbary, the first TNI SURF student for this summer, started work
this week.
LASTI (Zucker)
LASTI (MacInnis, Mason, Mittleman, Ottaway, Rollins, Shoemaker, Zucker)
No report.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
SimLIGO
(Matt) Continuing work on the common mode
servo.
Mechanical simulation
(Virginio)
-
New 3D Suspension model included in e2e. Some technical problems needs
to be fixed.
-
Draft of the documentation of the new 3D Suspension will be released
soon.
-
Debugging of the new mechanical simulation engine MSE2 under progress.
-
Written few new simple programs to test each one of the objects of the
new release of MSE.
FFT and E2E for Mode Mismatch
(Biplab)
E2E runs (including upto 4th order modes) and FFT runs match each other
quite well for carrier fields in various cases of mismatch. For sidebands,
the order of magnitude of power in various modes agree in most cases.
One important point is 06 or 60 power comes out to be more than 04 or 40
in FFT. Trying to understand if this is a real physical effect or some
artefact.
Alfi
(Bruce)
-
Completed parser changes neccessary for new implementation of connections
and junctions.
-
Completed some work on parser for eventual separate generation of modeler
files (.box) and Alfi files (.alfi).
-
Closed several PRs for small bugs in the parser.
-
Working on window sizing issues for edit windows.
(Melody)
-
Continued on the implementation of the 'Find' feature for alfi5.
LIGO Data Analysis System
Software Systems (Blackburn)
Work continues on improving the reliability of the LDAS software reliability
in preparation for this next release. The phenomenal performance from three
weeks ago has yet to be reproduced as needed functionality has introduced
stability issues along the way. At one point this week the system was approximately
a thousand times less stable. We have worked very hard and almost recovered
two of those three orders of magnitude. A primary source of trouble has
been in the form of memory leaks introduced in new code that wasn't adequately
unit tested before being committed to the system repository. Everyone is
now more aware of the importance of unit testing and progress is once again
being made.
A new interface to the data socket allowing "linger" parameters to be
set on LDAS APIs that write through the client socket was incorrectly being
used. This has now been removed from client side writers. New
log files were added to the system to allow graphically monitoring of memory
usage for each of the APIs. The recent rash of memory leaks discovered
in the system necessitated this.
The job status web pages now capture the particular dynamically loaded
shared object being loaded in the dataPipeline.
We've had a rather large number of core files to contend with from the
system this week. These were primarily due to the large memory leaks and
the incorrect usage of the linger option in the client side data sockets.
It was also discovered that the objectSpace C++ socket library was not
recompiled when we rebuilt our C++ compiler on May 9th. Several problems
with exceptions were seen in these core files which lead us to this discovery.
Since the recompile, this problem has not been seen.
Work continues on the development of the cgi web pages for managing
LSC requests for LDAS usernames and passwords. The interface now communicates
with LDAS using various security steps (including encryption techniques).
The ParaSoft company has finally come through with our new license for
the Insure++ software development tool we use for debugging various aspects
of our C++ code.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
-
Stress tested new SAN filesystems at LLO/LHO by copying reduced data set
frame files between them. Collected performance numbers for analysis.
-
Worked on getting multiple inter-switch links working on the archive system
(as a test for future SAN expansion at the sites). So far this isn't
working, but I'm talking to Sean at Sun about it.
(Al Wilson)
-
Flattened the network on the CIT, TEST, DEV systems so that there is only
one file server per LDAS system.
-
Worked on final tweaks for the System Imager disk for the cloning of nodes
in LLO and LHO in two weeks. I will be at LLO in the first part of the
week and LHO the second half of the week of 6/9-6/15.
MIT
(Keith Bayer)
-
Compressed LDAS network (eliminated 10.5.X.X).
-
Fixed mount point options.
-
Troubleshot Foundry switch problems.
-
Received 8GigE/72port Foundry switch.
-
Researching Solaris 9 licensing at MIT.
Livingston
(Igor Yakushin)
-
Performing extensive tests for metadatabase replication from sites.
Tested various 2,3 node configurations.
-
Faulty disk replaced on gateway.
-
Received 48 new PCs. Building the racks together with Rus and Mike.
Hanford
(Greg Mendell)
-
The reconfiguration of our T3 disk cache at LHO is complete and the conflict
between the World Wide Numbers of two T3s was fixed by Sun. LDAS
and the CDS fb3 framebuilder are running again at LHO.
-
Testing of the new configuration for E8 and S1 is underway. The archiving
of data to disk and to tape during E8 will be similar to that during E6
and E7. An RDS data set will also be produced during E8 and some
disk space will need to be made free before the beginning of the run.
Data Analysis Activities (Lazzarini)
Mendell:
-
Continued working with LDAS to debug jobs that request SFT data.
This now works well enough under some options that I can start updating
my DSO to unpack SFT sent to it by the wrapper, but it still fails due
to issues with identifying the primary when the -concatenate option is
set to false. LDAS is working to fix this last bug. Also, it
was determined that certain metadata about the SFTs will need to be put
into the database during SFT generation. This involves additional coding
in the knownpulsardemod DSO. For now, this information will be parsed
from log and record files that were kept by the scripts that managed the
SFT generating jobs.
-
Several enhancements and a bug fix where made to the LALDemod function.
I am adding code to my knownpulsardemod DSO to get it to work with the
previous and latest changes. Once this is completed much testing
will be needed. Plans for another MDC will need to be made between S1 and
S2 under consultation with the PULG group.
Shawhan:
-
I have been learning to use EventTool to do statistical analysis of the
inspiral event candidates found in the E7 data, and to evaluate various
prospective veto criteria.
Lazzarini:
-
Working with Virgo (Ricci/Rome and Mours/Annecy) we drafted a joint letter
of intent to perform transoceanic data transmission tests as part of our
respective projects' participation in iVDGL(US) and DataGrid(Italy/France).
The activity will take place in the context of the already existing NDAS
(network data analysis server) that has been set up by Marka(LIGO), Mours(Virgo),
and Williams(CACR).
General Computing (Wallace)
MIT:
(Keith)
-
Began setup/install of SB1000 & SB100
-
Installed MU7 / various freeware packages on several GC computers
-
Investigating spam relay from ligo
-
Installed software on library computer
-
Backed up Marie's computer
-
Setting up wireless router in NW22
-
Still working on WAN performance issues. Generated backup data and passed
it to MIT ITS group.
Livingston:
(Shannon)
-
Investigating LDAP configurations. Checking to see if the security and
reliability has improved. Also checking out the NIS+ compatibility.
-
Just FYI the version 6.0 of StarOffice appears to be a major improvement
over 5.2.
Hanford:
(Christine)
-
Completed cgi for the work permit form on the web.
-
Provided miscellaneous user support and dealt with several procurement
issues.
(Larry)
-
Talked with PNL about the network outage the Observatory had last week.
They are working on getting LIGO a few more numbers to contact in-case
of any future problems. Also, the equipment that went down is old and they
have no replacement. This will be brought up in the meeting Albert has
with PNL and NoaNet, next week.
CIT:
(Lisa)
-
Started looking into an sftp problem Albert is having. I believe
it is a disconnect between openSSH and the SSH we have installed on GC.
I need to build a test box to determine if this is true.
-
I have all the pieces for the new luna and have started the build.
-
Surf time is upon us. Created new account, moved a couple of computers
around.
-
Helped Mike out with Pherkab license issues.
(Veronica)
-
Posted the Elba 2002 Conference presentations that I already have, at the
conference's website. The files keep coming in, they will be posted as
they arrive. Posted the final version of the Elba 2002 program on the web.
-
Working on the Policies and Procedures online manual.
-
Per Linda's request, looking into the setup of the DCC database; need to
change the setup so that the database allows entry of older documents,
e.g. 1979.
-
Posted several updates to the LIGO website.
-
Made a few minor changes to the graphics of the LIGO Press and Media Kit
webpages. Working on the LIGO Timeline webpage.
-
Per Albert's request, looking into how to set up an LSC computing resources
information webpages; we need to have an online resource request form and
report for for completed activities.
-
CaJAGWR: updated the seminars webpage.
(Mike)
-
Loaded a new computer for GariLynn with (2000 PRO) for this computer came
preloaded with XP. Plus I loaded all GC software and a few engineering
packages. I swapped her old computer and setup the new computer in
her office.
-
Upgraded Norton Anti Virus software on all NT Servers.
-
Working on finishing up Pherkab by replacing this server with a 2U server
that is going to be running 2000 server, this will replace the previous
server that is loaded with NT4.0 Server. I thought had it ready to go but
when I put this server into circulation I found that there is much more
work to be done. I hope to have the new server up and running before the
end of this week.
-
Loading a PC for visitor's workstation to set up another cubicle on the
second floor of W/B.
-
In the 40Meter I had to work on laptops to finalize some network settings.
-
Alan Weinstein was having problems with his office PC and laptop I went
and corrected the PC problems and am still looking into the laptop problem.
(Larry)
-
Reviewing the FY03 budget with Albert.
-
Working on OS reloads for the sandbox units. One should be finished this
week and the others when I get back from travel. Along the same line
we are building a new LIGO Web server and docuserv server. These
are new units and should be good for a couple of years.
-
Debugged a couple of printer problems. Mostly bad print files hanging up
the system.
-
Minor adjusting of parameters on some of the SUN boxes and the IDEAS application.
-
Checking out machines with viruses, spammed mail and other related issues.
The e-mail blocking list is still growing on a daily basis.
-
Finally decided on a WEB cam to use. The ToUcam proved to work well on
the PC, MAC and under LINUX. However, Philips is no longer producing the
unit for the U.S.. So I am now looking for another unit of the same quality.
-
Tracking a number of purchases and so far things are going well in that
department.
LIGO II/Advanced R&D (Sanders)
>From: Janeen Romie
AdLIGO Suspensions
Nothing to report.
>From: ctorrie
Advanced LIGO Suspensions
Mode Cleaner: Working on the comments collected from both
LIGO and GEO on the drawings. Larry Jones is helping to implement new ideas
to some of the designs. Russell Jones and I are trying to migrate all of
the drawings to SOLIDWORKS and incorporate the new templates and notation.
(Previously the drawings were a mixture of AutoCAD and SOLIDWORKS.)
Prototypes for SURFS: Workshop has almost completed the
parts that are required for the tests planned for the 2 SURF students.
I accepted the majority of these parts this week and have checked through
them.
Coil Assembly: Russell Jones and I have finished the drawings
and assembly for the coil former and clamp. These have now been sent to
get 3 sets made at a local machine shop in Glasgow. The plan is to
follow these 3 assemblies through to the point where they have the LED,
PD's, cabling etc.. installed.
>From: Riccardo DeSalvo (prepared by Hareem Tariq)
Mike
-
Calculated the voltage needed to displace the Glasmet sample (in Q-Factor
measurements). The displacement observed varies as the voltage squared.
It looks like 32 volts (like we used last week) causes a deflection of
about 1 micrometer (which explains why we didn't see it). At 100 volts,
though, we should see a deflection on the order of a millimeter. I hope
to try this next week in Phil's lab.
-
Purchased 1.5 in. x 1.75 in. prototype circuit boards from MarVac for use
in our mock heat capacity puck. I cut a piece off from this that is just
large enough to be mounted on the resistivity puck. I designed a circuit
and soldered it to the board. I haven't connected the leads to the resistivity
puck yet, because it is clear now that we need to make our own cable. Hareem
and I found a nice cable in the Synchrotron. I may need to purchase a 12-pin
lemo on Monday to get it working. I also found some thermal conductive
glue which I used to connect the heater with one of the thermistors on
the circuit.
-
I've started the documentation of our Cryostat problem, as recommended
by Riccardo. This includes an estimate of time spent and Helium usage.
-
Of course, more work (and problems) with the Cryostat. Hareem and I replaced
the pressure gauge that failed when Bryan and Mike were here to replace
our last cryopump. Since then, we have been doing a very thorough troubleshooting
procedure. It appears that we are able to achieve HiVac with both the Model
6000 and the computer attached and keep it there (very stable) overnight.
This was very promising. However, some problems were experienced as soon
as we tried the same thing with the baffles and sample installed. We're
not sure the exact cause yet. A TTO Measurement on QDs Nickel sample was
attempted on Friday, but the data collected indicates a problem either
with the cryostat or with our measurement parameters.
-
Calls to QD haven't produced much of a response -- most of the people are
away (including Mark), and Ron and Robert were not able to tell me the
status of their cryopump tests (on two occasions) which leads me to believe
they may have dropped the ball on this problem again. I will need to talk
to Stefano early next week.
-
Kelin and I mounted the optical disc in Phil's lab.
Hareem
-
Found a problem when the (AuSn)Ti braze failed to wet or melt the MoRuB
sample even at 500 degree Celsius. Apparently the MoRuB when annealed to
high temperatures >450 Celsius, undergoes physical changes and my sample
became brittle at 500 degrees. I found out that this effect had already
been investigated by Bill Johnson. et al. in 1982 and the results were
published.
-
I can push the crystalline effect to higher annealing temperatures by reducing
the Boron content in the MoRuB alloy. Therefore I made another alloy with
16 percent atomic weight of Boron instead of 18 percent. Prepared alloy
with 18 percent atomic weight of Boron as well so that tests can be conducted
on both alloys, under same conditions, for the effects of annealing as
well as brazing.
-
To solve the problem of brazing I prepared another braze with AuSi alloy.
The advantage of this composition is that it is a simpler composition with
a single eutectic at 363 Celsius and no intermolecular bonds form at higher
temperatures.
-
Prepared samples for splat quencher of MoRuBSilAlP, MoRuBSi, MoRuB.
Szabi, Alessandro, Akiteru and Riccardo, in Elba.
-
Several nice LIGO reports from Szabi.
-
Alessandro reported on horizontal and the new vertical accelerometers developments.
-
Akiteru reported on the SAS Fabry Perot interferometer results in Hongo,
0.6 micron R.M.S. above 100 mHz fully passive (before switching on the
inertial damping).
-
Riccardo reported on interest in developing low frequency GW interferometers
and on glassy metal advances.
For additional information about this report, contact sanders@ligo.caltech.edu