Weekly Report for Week Ending May
23, 2002
The LIGO Executive Committee
Agenda for Monday May 27, 2002:
Monday, May 27, 2002 is a holiday. There will be no Executive
Committee Meeting.
Special Announcements:
Weekly
Report Highlights
LSC Issues (Weiss)
no report
LIGO I Construction/LIGO Laboratory
Administration (Lindquist)
LIGO Weekly Site Telecon (Lindquist)
There was a site teleconference held on Thursday,
May 23, 2002. The following items were discussed:
Action 109: estimates for furnishing the
new buildings have been provided. This action is closed. Suggest
change requests should be submitted.
Brunt Construction (Livingston): objecting
vociferously about items being added to punch list. However, these
are items that are not new, but could not be checked previously (e.g.,
roll up door not tied down prperly and vibrates when air conditioning turned
on). Rest of list is being done except for a few contentious items
that probably will not get done (e.g., crane stops).
Audio Visual Procurement: received four
proposals. Lot of disparity in cost of labor proposed.
New personnel:
Valera Frolov starts August 5 in Louisiana
Vagesh Parameshwariah starts July 1 in Hanford
Peter Shawhan starts October 1 at Caltech.
Property: Ed Chargois reports that he has
some leads for furniture for the new buildings.
The list of current actions revised to reflect
the status of open actions assigned through May 23, 2001 may be found at
ACTION
LIST.
PROPERTY
MANAGEMENT (Chargois)
From: Ed Chargois <chargois_e@ligo.caltech.edu>
DOCUMENT
CONTROL CENTER (Turner, Mak)
>From: Linda Turner
- turner@ligo.caltech.edu>
Web pages for the DCC give
simple how-to's for document numbering, easy access to the latest on-line
documents, and search capabilities for the DCC database.
Take
a look. . .
ACCOMPLISHMENTS
>
From: Cleveland Mak <mak_c@ligo.caltech.edu>
ACTIVITY
-
Processed and distributed 6 DCN's.
-
Progress continues on conversion of old charge account files to electronic
form.
-
Electronic document activity was steady for this period.
-
Continued working on contractual close-out files.
|
05/23/02
|
Packages
|
Faxes
|
|
In
|
22
|
33
|
|
Out
|
12
|
25
|
COST SCHEDULE
CONTROL SYSTEMS (Cunningham, Brambila, Kaufman)
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS
PAYABLE HISTORY DATA .

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
-
Completed the new subcontract to JaniKare for LLO, change order #1 to Moon
Security, change order #2 to Coastal Bridge, change order #1 to Metropolitan
Electronic, change order #5 to Meshkov, and change order #7 to High Precision.
-
Presently working on change order #5 to SIOM, change order #1 to E.G.O.,
and a new order to Sauviac and Dang for architectural services.
-
Received four proposals for the AV system at LHO. The proposals are being
evaluated and a decision will probably be reached next week.
From: Florence Kaufman <fkaufman@ligo.caltech.edu>
SUBCONTRACTS MANAGEMENT (Petrac,
Jasnow)
From: irena@ligo.caltech.edu (Irena Petrac)
From: Ed Jasnow <jasnow@ligo.caltech.edu>
CONSTRUCTION:
-
The contractor continues to make progress on completing the punch list
required to finish the building. It is anticipated that the building will
be complete by the end of the month.
-
A claim has been submitted by the siding contractor for the LHO OSB East
Building resulting from his cutting the stainless steel siding 20 inches
too short. The claim is currently being reviewed.
-
Four proposals were received for providing the audio/visual equipment for
the LHO OSB East Building auditorium. The low proposal is just over $80,000,
which is below the $100,000 budgeted for this item.
OPERATIONS:
-
We are currently reviewing a proposal to allow the LLO access road to be
used as a landing strip for airplanes used to spray the trees surrounding
the site. Issues such as liability, safety, etc. are being investigated.
SUPPORT (Baldon, Torres, Lloyd,
Tischler)
>Irene Baldon
-
Processed the paper work for eleven (11) new/revised trip and there are
six (6) trips in various stages of completion before ticketing can be done
and paper work completed.
-
Completed twelve (12) Expense Reports and there are twenty-four (24) reports
yet to be done.
-
Reconciled forty-three (43) P-Card items this week which requires phone
calls to hotels to track down which traveler incurred which charge and
pulling each traveler's file to assure that charges are correct for each
airline fee.
-
Assisted a couple of P-Card holders who were/are out of town/country with
their reconciling and/or expense reporting.
-
Completed all thirty-eight (38) SURF Student travel arrangements and made
arrangements for hotel reservations for those coming in before SURF Housing
is available and advised students on shuttles where necessary.
-
Worked on the preparation and distribution of the Travel/Vacation Itinerary
for May 20, 2002.
-
Performed normal recording and filing associated with Travel and Reimbursement.
-
Also performed miscellaneous duties as requested by various members of
the LIGO Project here at Caltech as well as from members of the staffs
of each of the two (2) sites.
-
I continue to do MIT's travel to the sites for installation activities
and also to assist them wherever possible.
>Dorothy Lloyd
-
Processed the usual invoices for payment. Tracked and followed up on invoice
problems, and reviewed and recorded payments processed by Esther the week
of May 13. For the total number of incoming invoices received for this
period see "Cost Schedule Control Systems" report by Esther Cunningham.
-
Processed the usual requisitions and change orders.
-
Continue to monitor contract and blanket order encumbrance and notify task
managers when supplements are needed.
-
Managed to get in some filing.
-
Jim continues with data entry in the LIGO database and helping out in the
DCC.
>Rita Torres
-
Formatted incoming Attachment B from GEO. Submitted this to the DCC out
box. Formatted reports from Stanford and Southern University, these are
now in review. Posted Stanford Attachment A on the small web page for review.
-
Continue to track progress of orders placed for M. Smith while he's away.
I'm submitting the incoming partial orders to S. Vass. Also chased info
on an item returned to Mike after it was sent out for repair.
-
Updated site trips. Attended an informative meeting on issues relating
to fabrication accounts. Unearthed a couple of templates for the GoF group.
Arranged for an eye exam and laser training.
-
Began update to the addresses contained in the LSC-ALL alias. For now I
am accessing only the LIGO portion. Most updates will conform to the lastname_first
initial format, however there will still be exceptions. Thanks to the Sys
Admin group for giving me the tools to do this task.
-
Placed several Pcard orders. Reconciled 59 this period.
-
INFORMATION : US postal rates change on June 30, 2002. Visit -- http://www.usps.com/ratecase
>From: Ryan Tischler <rtischle@ligo.caltech.edu>
-
Meeting with Linda and Bill to discuss consistent/standard template design.
-
Health insurance research and escort to hospital.
-
More work on press kit and coordination/details for next meeting.
-
Organizing recent group photos for posting to LIGO website. Waiting
for Veronica's return to Pasadena.
-
Coordination of LHO and LLO site photos (tentative) depending on results
before Linda leaves on vacation (Thurs.).
-
Space workshop (tentative) depending on Cindy's return from jury duty.
-
Familiarizing myself with maintenance of citonly email list.
-
Beginning details on SURF/LIGO orientation.
-
Assist Barry in Donna's absence (Friday) if needed
Advanced LIGO (Frey)
From: Thomas Frey <tfrey@ligo.caltech.edu>
Progress Period from 05.17 to 05.23
Accomplishments:
-
Weekly Advanced LIGO Project Controls meeting was not held this week.
-
Continued to work with Primavera regarding an outstanding technical issue
and received a program patch that I am now using and testing.
-
Advanced LIGO MRE Proposal (Highest Priority)
-
Per direction of Gary, Dennis, David, and Phil, I am updating the presentation
from November with most current data for meeting to be scheduled in June.
-
Continuing the development of the Cost Estimate.
-
The following is a summary of status by sub system:
-
COC - Work on action items per second review continues. Next meeting
date has not been scheduled.
-
PSL - Next meeting date has not been scheduled.
-
AOS - Work on action items continues. Next meeting date has not been
scheduled.
-
IO - Work on action items continues. Next meeting date has
not been scheduled.
-
SUS - Working with SUS group to incorporate current comments.
-
SEI - Work on action items continues. Next meeting date has not been
scheduled.
-
ISC - Corresponding with Mike Zucker to meet at MIT to make significant
progress towards developing an estimate. Planning to take a trip
to MIT the week of June 17th.
-
LDAS - Followed up with Albert
-
All other subsystems have yet to be scheduled for their first review.
These dates are pending per direction from Gary Sanders and Dennis Coyne.
-
Continue to update the TNI Schedule and incorporate any changes.
-
Data pending to revise plan to version 3 due to additional efforts to isolate
noise.
-
Updated the plan with progress as of 05.17.02 and posted to site.
-
Sent out update data requests for progress as of 05.31.02.
-
Continue to update the LASTI Schedule and incorporate any changes.
-
Updated the plan with progress as of 05.17.02 and posted to site.
-
Sent out update data requests for progress as of 05.31.02.
-
Project Plan for the 40-Meter Lab Upgrade continues.
-
Updated the plan with progress as of 05.17.02 and posted to site.
-
Sent out update data requests for progress as of 05.31.02.
-
Cost Book Tool.
-
ROSTER DATABASE:
-
Continue work on my action items providing BK with needed data.
-
COST BOOK DATABASE:
-
Gang of 5+:
-
Started work on procurement documents per request of Phil / Gina / Dot.
-
DCAA - Work continues on the incurred cost audit.
-
Nothing new to report (All Quiet on the Western Front).
-
Development of the Advanced LIGO Project Controls Guidebook continues.
-
Project Web Site for posting schedule and progress related data continues
to be updated with the latest and greatest.
Schedule 05.24 to 05.30:
-
Out of the office Friday the 24th of May. (Vacation)
-
Next weekly Advanced LIGO Project Controls meeting is to be scheduled for
early June. Subject: MRE Cost and Proposal Development.
-
Advanced LIGO MRE Proposal (Highest Priority Task)
-
Highest priority is the development of the Cost Estimate.
-
Will continue to pursue all other sub system schedules.
-
PSL - Will complete estimate and schedule changes.
-
AOS - Continue inputting changes to and prepare for next meeting TBD.
-
IO - Continue inputting changes to and prepare for next meeting TBD.
-
SUS - Continue inputting changes to and prepare for next meeting TBD.
-
Will update the plan when data is made available.
-
SEI - Continue inputting changes and prepare for next meeting TBD.
-
COC - Work on action items by Garilynn continues. Anticipate schedule
changes prior to next meeting TBD.
-
ISC - Will plan travel to MIT and meet with Mike Zucker to develop details.
-
LDAS - Will work with Albert to develop details.
-
Will issue updated meeting minutes for every subsystem as action items
from most recent review are completed.
-
Will Continue to update the TNI Schedule and incorporate any changes.
-
Will update the plan with progress as of 05.31.02 and post to site
by the 5th.
-
Will Continue to update the LASTI Schedule and incorporate any changes.
-
Will update the plan with progress as of 05.31.02 and post to site
by the 5th.
-
Will continue updating the 40 meter schedule and incorporate any changes.
-
Will update the plan with progress as of 05.31.02 and post to site
by the 5th.
-
Roster Database
-
Will continue to work with BK and executing action items.
Cost Book Tool development continues. (Highest Priority Task)
-
Mapping and formatting of OPS cost data for input will now continue with
co-operative agreement approved.
-
Will continue to work with BK executing action items.
-
Cost Book Tool development continues. (Highest Priority Task)
-
Mapping and formatting of OPS cost data for input will now continue with
co-operative agreement approved.
-
Will continue to work with BK executing action items.
-
Gang of 5+
-
Will continue to work on procurement documents.
-
Will continue to provide support to PL for DCAA audit(s).
-
Will continue the development of the Advanced LIGO Project Web Site.
-
Will continue the development of the Advanced LIGO Project Controls Guide
Book.
Reports (Lindquist)
August 1 we are scheduled to submit an annual work plan to the NSF for
LIGO FY 2003 Operations. We are modifying the first draft budget
for FY 2003 based on the current staffing plan.
Change Control/Contingency (Lindquist)
The following additional
change request has been submitted:
|
CR-010012
Revision B |
WBS 1.4.4.1
|
Closeout Construction Budgets
for Initial Computer Equipment Complement at the Sites
|
P. Lindquist
|
Human
Resources (Akutagawa)
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
-
Various personnel/payroll /HR related work.
Quality/Safety (Tyler)
>From: Bill Tyler <tyler@ligo.caltech.edu>
-
The Gang of Five plus Others (GoF+) met with G. Sanders to review the completion
plan/status of the few remaining action items. Most of the GoF+ effort
is now completed. The new web-page is almost finished with some work remaining
on DCC links and the LIGO "templates" file/link.
-
Worked with Linda Turner to complete an updated/edited Vacuum Qualification
procedure for review and approval by the LIGO Vacuum Review Board.
LIGO Hanford Observatory (LHO) Operations
(Raab)
Summary of Commissioning Activities
at LIGO Hanford Observatory
(see elog for details - if it's not in the elog, it didn't happen...)
4k IFO investigations
Bill Kells finished up the mode cleaner leveling reducing all but the
MC3 bounce peak. Dave Barker is working with Stan and Rolf on getting the
new 4k DSC system integrated into the EDCU, BURT and Conlog systems and
writing perl scripts to generate 4k DSC screens to allow modifications
to MEDM screens to be propagated quickly through all optics. Effort has
gone into checking out the digital suspension controllers after the software
changes to DSCs. All mirrors damp. Damping gains have been set on all core
optics. Single arm locks have been obtained on both arms, with good enough
stability on x arm to get a preliminary single-arm measurement of frequency
noise. The y arm is not so stable and this is under investigation. Glitches
in the PSL power were discovered in the process of connecting and analyze
fast intensity channels. Problems with the slow actuation were also discovered.
These are being worked.
2k IFO investigations
Building upon the enhanced robustness of the IFO since the "bursty"
coil driver was repaired, we have now been able to run the interferometer
with much less optical attenuation (8-11 times less) before the antisymmetric
photodiode. Locking is generally robust even with the high light levels.
This has successfully overcome the dark noise that had been limiting performance
at frequencies above approximately 500 Hz in spectra taken since last January.
(See figure at http://apex.ligo-wa.caltech.edu/~fjr/data_2k/H2_history.pdf
) Now, with approximately an order of magnitude less attenuation, we have
approximately 4-5 times better displacement sensitivity at these frequencies
and another factor of 4-5 margin above dark noise. Of course that means
we have new noise to investigate, which we are doing. Mike Landry has provided
a test version of a calibration "button" that automatically delivers calibrated
displacement spectra for a given configuration. This greatly facilitates
noise investigations.
Data Acquisition, Remote Control Rooms, LDAS Mods
Dave Barker is reworking the new EDCU system for the LHO DAQ. Testing
will continue on this system at LHO over the next week. Work is ongoing
to integrate the frame builders with the new T3 and QFS files systems introduced
by LDAS. Dave is also supporting setup of the remote control stations at
MITand CIT.
FACILITIES
Asphalt work was done last week and siding continues to look good.
Otto is away at school being certified as a "water-system operator" to
comply with state health regs. He will return next week with more construction
results.
LIGO Livingston Observatory (LLO) Operations
(Coles)
Commissioning at LLO: This week we have installed or upgraded
many aspects of the interferometer system. New LSC software (already
in use at LHO) which makes it possible to easily implement a wide range
of digital filters (even on the fly) at multiple points within the
various control loops has been implemented. A new LSC 1.2 GHZ DCU
replaced the previous 1 GHZ controller and a new timing module and timing
distribution were implemented to reduce the RF cross talk to the Pentek
inputs. Daniel Sigg installed a new version of the DTT tool which
adds many new features relative to the previous version. The mode
cleaner board was modified to allow a reduction in the cross-over frequency.
The micro-seismic feedforward system was tuned up to remove some bugs and
enhance the filtering. A lot of effort went into tuning up the common mode
servo by changing some of the filter characteristics in the CARM and DARM
paths. A new intensity stabilization servo is being installed
this week by Rich Abbott, Peter King, and Flavio. Intensity stabilization
at the MC output is in progress.
The most recent spectrum is at http://www.ligo-la.caltech.edu/ilog/pub/groups/detector/logs/2002/images/05/22/rana-1022102901.pdf
GC: Setting up a testbed for working with VPN configurations.
The more I read about VPNs on the Cisco PIX the more evident it becomes
that we will have to implement NAT and static routing on the PIX. I am
going to try and set up a VPN independent of the PIX using Solaris' implementation
of IPSec and SunScreen Lite. I will be using Solaris for Intel, an Ultra
10, and a blade 100 for the test. I am investigating LDAP for a global
address book for the observatory. Fixing a couple of problems with the
LLO web page. Working with Bonnie to show her what she will have to learn
and what is involved in maintaining some of the web pages here at LLO.
(Shannon Roddy)
LDAS:
-
Ordered 48 snagless strain-relieved network cables for the new beowulf
clusters, the order has already been shipped yesterday and should be here
either at the end of this week or at the beginning of the next week.
-
Received 2 racks, 4 set of outlets, 8 wheels for the racks, two sets of
back rails.
-
Together with Rus set up new racks behind the old ones in the mass storage
room in place of the back shelf.
-
Helped Dan to reconfigure T3s.
-
Resumed experiments with DB2 replication.
(Igor)
Seismic Amelioration: Work continues on gathering quotes from
vendors on the heat treat, coating, and joining of the spring assemblies.
Additionally, Efforts to Wire EDM the pre-isolator spring have been started
with Reliable EDM of Houston. I am waiting to here back from them very
soon.
Most of my week has been spent working on implementing the pre-isolator
design into the BSC and HAM stacks then utilizing techniques to successfully
produce a finite element model that reflects the physical model. This is
still part of the effort refine the 6x6 stiffness matrix that I have been
working on.
Efforts also include the ongoing search for a materials test lab that
can test to failure the pre-isolator springs. LSU has two tensile testers:
One will test to 80 kips while a large on will test to 500,000 lbs and
has a six inch stroke on the load cell. The professor in charge is out
of town but will return Tuesday. I am still looking for a commercial solution.(Marcel)
SCIENCE & ENGINEERING SUPPORT (Coyne)
Seismic Upgrade Project
Dennis Coyne reporting
External Pre-Isolation
-
Mohana is doing the rack-mounted receiver interface module pcb layout and
is in the process of choosing the chassis. The boards for the L4C/IPS interface
are here as well as the chassis to put them in. We will stuff a board and
test it immediately.
-
Ken Mason revised the spring/actuator assembly to incorporate a support
brace from wall-to-wall to increase the stiffness. FEA on the stiffness
is pending. This brace also permits (with set screws) complete assembly
on the bench prior to installation. The coarse actuation changes have delayed
the major pieces in fabrication by ~ 2 weeks.
-
Double-start, counter-wound spring (Marcel Hammond):
1. Fabrication (traditional NC machining)
has begun on a single prototype in maraging steel (300?) from bar stock.
Machining expected to be completed by 5/23. In parallel investigating EDM
as a potentially cheaper alternative. Also getting quotes (price &
delivery) for maraging in pipe form to reduce machining costs. A heat treat
process has been defined by the maraging steel provider. Looking for a
heat treater for the prototype (2 requests for quote out – pending reply).
Plan to chromium plate the prototype, as recommended by Dan DeBra. Cleaning/passivation
process defined by the maraging steel provider. Plan to lead-silver solder
join the end caps to the spring body. Plating will be done before soldering
– the soldered areas will be masked off.
2. Stiffness and frequency analysis: updates
still in progress. Need to get a better “read-out” of the rotational compliance.
Need to perform an analysis of the integrated spring/structure assembly.
-
Rich Mittleman will post the measurement data for the LASTI BSC SEI driving
point impedance measurements for the team to review and compare to analysis.
-
Connectorized L4C interface: design still pending.
Hydraulic External Pre-Isolation (HEPI)
-
Hydraulic Pump Station (Ken Mailand, Rich Abbott):
1. CONSTRUCTION: Basic station Finished.
2. MOTOR SPEED CONTROL: Wired and tested 'ready to run'
3. PRESSURE LEAK TEST : Had to re-do a number of the solder joints
that were done poorly by the CIT plumbers. 'air 80/100 psi' done. 'Operating
Pressure' test: 225 psi nitrogen leak test ~ thur 5/25 [fill fitting req'd
for accumulators, due 5-25}
4. DESIGN: A future modification to the reservoir filler cap for a
float level sensor.
5. LAYOUT DRAWING: I have finished a scale plan view and partial elevation
[acad 2D] layout drawing, of station component assembly.
6. HARDWARE ASSEMBLY: Resistors Finished and Installed.
7. LONG TUBE RUN: Finished.
8. TEST LOAD: Finished.
9. Rich has been ordering the inevitable parts needed for the pump
servo.
-
Jonathan Kern is working with Ken Mason and Myron MacInnis at MIT this
week. Corwin has completed the changes to the bellows shield assembly we
agreed upon, and handed over to us his complete hydraulic actuator CAD
model. Ken has imported Corwin's changes into his spring/actuator
assembly for the Hydraulic External Pre-Isolator (HEPI) and we're working
to check the integration.
-
Jonathan, Ken Mason & Myron are also going over the installation procedures
for LASTI; seeing how much of the PEPI fixturing and procedures will be
adaptable to HEPI. Our discussions have made plain that we need to develop
a test and measurement to carefully equalize the tension of the EPI springs
to assure no yaw is introduced when we release the stops.
-
Jonathan completed re-templating Amit's nozzle drawing, and ordered a quantity
of nozzles for LASTI. Amit is working on a procedure for adjustment and
calibration of the servo valve. Parker informs us that an order for the
assembly of the servo valves with our custom nozzles will take 3 to 4 weeks.
-
Passive RC manifold (“block”): performing analysis. Will send a copy of
the prototype to Ken Mailand.
-
Distribution manifold design: pending.
Electro-Magnetic External Pre-Isolator (MEPI)
Received electro-magnetic actuator order.
Greg has taken measurements of the interaction between the EM actuator
and the L4C geophones. Data reduction pending.
CDS Software
Dennis Coyne summarizing from elogs at LLO:
-
Rolf installed new LSC software. This is essentially the same code as LHO2k,
except TM and BS output filters, which are hardcoded in LHO2k, are now
user defineable. This code change required an MV162 to be installed as
the EPICS interface. The l1iscsuper is still in the crate, but is not being
used.
-
The front end CPU is still a 1GHz Pentium, but it tends to become fully
loaded with only 4-5 test points. Changed out l1lscl0 for a new 1.2 GHz
pentium. Only gained a test point or two before we saw ADC noise again.
-
Rana locked the LLO IFO using the new LSC code. No real problems except
for the 'too many test points making noise' problem. Implemented some new
filters giving x10 more low frequency gain and more phase margin for the
DARM loop. We were able to use the new 'on the fly' feature to switch the
old filters with the new ones with the IFO in lock.
-
Installed new variable timing delay modules (“dual” timing, i.e. allows
the DAC clocking with a time shifted clock). Installed the LSC front end
code which makes use of the new timing module. Mike has modified the two
pentek modules in this crate to use the separate DAC clock inputs. However,
this version of the software only makes use of the timing module polling
(instead of polling the ADC) and does not yet make use of the separate
DAC clock. I want to test in this mode first to see if the ADC noise is
reduced.
-
A summary of the software changes and the state of the commissioning of
the software is given in this elog
entry (username: reader, password; readonly)
CDS Hardware
Jay Heefner
-
Differential Driver/Receivers: Two of each type of module have been tested.
The output/input referred noise is ~100nV/rtHz which is sufficient for
operation with both the pentek ADC and DAC. The bandwidth is ~10KHz. Common
mode rejection for freq<10KHz is greater then 60dB and is typically
greater then 80 dB. 30 of each type of board are bring stuffed in preparation
for installation.
-
Optical Lever Whitening: The schematic for the new board is 75% complete
and should be ready for final review by next week.
Rich Abbott, Falvio Nocera, Ben Abbott
Progress made on installation of new VME based Intensity
Stabilization Servo (ISS) by Flavio, Peter King and Rich Abbott. First
look at RIN before the MC is at 2e-7 as measured by independent PD. Initial
TFs being taken and more to follow. All VME based controls are functional
(Gain, test relays and read back channels). Still need to work on stabilization
after the MC which will be attempted on Thursday. We worked through some
problems with the DCPD that we are using, and now it seems to function
well. The DCPD is a fully differential design (by Ben Abbott) and incorporates
features which allows the servo card to send out an active AC coupling
signal to the DCPD to implement auto-zero function.
Sander Liu
Micro-Seismic Signal Processor:
-
Remote interface Box - 12 units are being build. Chassis design is done,
will review all dimensions called out before sending out for fabrication.
-
Post Processor - Testing of the first article is complete. Will begin to
build 12 units as soon as man power is available.
PSL
PeterKing
The PSL Lab's BeamScan diagnostic has been returned
for repair to Photon Inc. A broken cable is the prime suspect reason as
to why the head is spinning faster than the nominal 10 Hz.
Optics Analysis
Erika D’Ambrosio
I spent some time in revisiting the work done on
the parametric instability. I sent out the proof to Physics Letters
A, which has accepted the article and is ready to publish it.
I am also trying to collect the large amount of informations
on the sidebands imbalance in order to present those in a simplified and
organic form, for Bill to check over when he is back. I decided not to
include any estimation of what the impact of the sidebands imbalance would
be on the strain sensitivity. This delicate point is something Bill and
I have a lot to work on, because there is an overall issue related with
the bandwidth of the sidebands, for the isolated recycling cavity and for
the full interferometer locked case, that in the past has been considered
the same. In the meantime I have been checking some of the analytical results
on the sidebands imbalance by the FFT-code, so that all the statements
we are claiming, based on our mathematical analysis are tested by a more
sophisticated numerical tool.
Optical Contamination Cavities
Lee Cardenas, Liyuan Zhang
Cavity#1 Locked.
-
Ring Down ~ 24.85 x 10-6 microseconds ± 2.1 x 10-8
microseconds. Vacuum pump ~ 4 x 10-8 torr (previously
ring down ~ 23.32 microseconds with pump 4 x 10-6 torr).
-
Beat Frequency ~ 86.0815 MHz.
Cavity#2 Locked and with mineral test sample
in it. Exactly one month of pumping.
-
4/18/02 Ring down ~ 33.1217 microseconds, Vacuum pump ~ 7 x 10-9
torr (without test sample) - Beat Frequency ~ 74.4098 MHz.
-
4/22/02 Mineral oil test sample installed into cavity chamber.
-
4/23/02 Ring down with mineral oil test sample ~ 30.8409 microseconds,
after one day of pumping Vacuum pump ~ 4 x 10-4 torr.
-
4/29/02 Ring down --------------------------------- ~ 31.6308 microseconds.
-
5/22/02 Ring Down --------------------------------- ~ 32.0185 microseconds,
after one month of pumping Vacuum pump ~ 7.5 x 10-9 torr.
-
Ring down getting normal with time and vacuum pumping.
-
Beat frequency ~ 74.3987 MHz.
RGA is finally working and the sum of AMU(41,43,53,55
& 57) ~ 5 x 10-9 torr.
[D. Coyne Note: The results from the mineral oil
sample are still being evaluated. Another week or two of data will be taken.
Initial results at high pressure indicated a significant increase in absorption
rate. At low pressure the rate is not yet discernable. Results yet to be
properly scaled to LIGO conditions.]
Transmission Test Set-Up.
-
Breadboard optical table 2ft x 4ft x 2 inches thick acquired.
-
Design and fabrication of a steel base support table is on going.
Material ordered and welding will proceed.
-
Most of the Optics (1/2 wave plate, Isolator, mirror, lens, photodetector
and lock-in amplifier) are ready.
-
Attenuator and chopper needed.
-
NPRO Laser Model: 126-1064-700, S/N 415, obtained from Shanti. Beam
waist measurement will proceed.
Misc.. Tasks.
-
Installed a metro rack next to the cavity #2 and all the equipment from
the floor are up on the shelf. This created more room for the transmission
test set-up.
-
Cleaned and fixed the lab.
DMT
John Zweizig
-
This week I have been writing an alarm handler which will be used to summarize
abnormal conditions seen by the DMT monitors and to notify operators of
these conditions. I have also written the client interface API that wil
be used by the monitors to communicate with the Alarm Handler.
40 Meter Interferometer (Weinstein)
Activity at the 40m has been intense, with as many as a dozen people
working on various things around the lab. We have had several cases in
which one person's activity has caused problems for others. SO, here's
a reminder about RULE #1: coordinate any potentially disruptive activity
(PSL work, crate rebooting, rack/crate wiring, vacuum work, even moving
an EPICS slider), with the Laser Operator in charge (usually either Dennis
Ugolini or Steve Vass).
Suspension Controllers and Mode Cleaner length controls (B. Abbott,
Heefner, Taylor, Ugolini)
-
Digital suspension controller Front End and epics software for the mode
cleaner mirrors was installed last Friday/Monday. This is the new digital
suspension controller system that is currently being installed at H4K as
well, featuring modular banks of digital filters everywhere.
-
After several small problems (loose cables or wires, fuses, etc), were
fixed, all three mode cleaner optics (MC1, MC2, MC3) were released from
earthquake stops, allowed to swing free, and sensible OSEM sensor signals
were seen. Jay and Ben turned on the damping, checked the sign of the servos,
tuned the gain a bit, and now all three optics are being sensibly damped
in position, pitch, yaw, and side. A laser pointer, acting as a simple
optical lever, was used to verify that the optics really were being damped.
SO, a day or 2 after installation, the system worked like a charm. Congratulations
to all, and special thanks to Jay, Ben, Alex, and Rolf.
-
A few OSEMs show more oscillation (at ~ 3 Hz) than others, especially in
MC2 (which is in a small chamber with a little seismic stack). At first,
we thought the motion was so excessive that it might make it difficult
to do the length control, but now it doesn't look so bad. Still, we will
re-measure the MC2 stack transfer function, as well as the transfer function
of the table that the chamber is sitting on, soon.
-
Jay is currently getting the watchdogs working, which shut down suspension
control if the RMS signals from the OSEMs get too large (signifying a malfunction
of the system). This requires modifications to the cables that run the
signal from the SOS dewhiteners to the coil drivers. With this in place,
we hope to leave the three MC suspensions loose and damped, from now on.
-
Bob has finished wiring the cross-connect for the mode cleaner length controls
rack (1Y2). Ben is still assembling the remaining modules that we need
(RFPD interface board, length control servo board, and an MVME162 for the
EPICS controls). The remaining wiring for the MC length control, which
should be finished in the next few days, is: the cables from front panel
to cross-connect and front panel to front panel, the RFPD itself and the
cable to the rack, and a cable from the length control servo board to the
suspension controller rack.
-
Bob will go through all the wiring that has been installed in the last
week, and strain relief and tie down all the cables, take care to make
sure everything is grounded correctly, and is well labelled.
-
On at least 2 occasions, rebooting the suspension controller front end
crate has caused the vacuum control EPICS cpu to hang with a "network connection
lost" error, requiring a reboot. This is a very unsatisfactory situation,
with no good explanation of why it is happening. Jay says that have a similar
problem at the sites. It's not clear that we can live with this!
Mode Cleaner (Ugolini, Vass, Miyakawa):
-
Now that the three MC suspensions are damped, it should be possible to
align all the MC optics, including the reflected and transmitted beam in-vacuum
optics. Dennis, Steve, and Osamu will pursue this in the next day.
-
On Monday, Dave Reitze visited the lab. We went over the LIGO MC installation
and commissioning test plan, and he gave us lots of advice on aligning
the three suspended optics. Thanks, Dave!
-
The optical spectum analyzer (tropel) for the inout optics diagnostic beamline
was broken and was sent out for repair. It has been returned, and Osamu
has been trying to make it work. He had to insert a lens in the beamline
in order to get it aligned with sufficient signal in the transmitted photodiode
to make a measurement. The signal is not very strong, even through we believe
that sufficient light (a few mW) is incident. It may be that the Tropel
is still broken. In any case, we will need another, so we will order one
ASAP.
-
Osamu is laying out the sensing optical train for the mode cleaner reflected
and transmitted beams (IMCR and IMCT). He and Dennis are going over a list
of items that have not yet been delivered, or maybe have not yet been ordered.
-
Prominent on the list of items that had not yet been ordered is the pockels
cell for the resonant sidebands (33.207 MHz). Steve ordered this, rush,
from New Focus on Monday. They promise delivery in less than 2 weeks. We
need this in order to measure the MC length.
-
The IMCR and IMCT beams must get to their respective optical sensing tables
through beam tubes which we won't have for a couple of weeks (see below).
In the meantime, we'll make some temporary beam tubes.
-
We also await camera mounts for viewing the suspened optics. While we wait,
Steve will set up a temporary system so that we can view the suspended
optics with our Watek cameras during alignment.
-
Our goal is to have the MC optics aligned by the end of this week, and
length controlled by the end of next week.
DAQ (Rolf, Ivanov):
-
Alex Ivanov installed a new DAQ system, featuring support for a second
reflective memory loop (for all front end fast controls: suspension controllers
and global LSC and ASC), and a new database /cvs/cds/caltech/chans/master.config
to log the new suspension controller fast channels.
-
Still to do: the EPICS slow channels for the new suspension controllers.
-
He also installed a new frame builder for 16-sec frames.
-
The DAQ frame logging has been flaky, with several days of interruptions
in the last week. This is believed to be due to flakiness with the RAID
array, causing the DAQ system to choke. However, it has been difficult
to diagnose the problem (for example, there's no indication of one of the
disks failing, as they have many times before). Alex backed up our trend
frames, wiped the RAID array clean, allowed it to rebuild itself, copied
the trand frames back on, and resumed logging frames. So far, there has
been no problems, but we'll keep watching.
PSL: Starting Monday, the PSL PMC servo started misbehaving, losing
lock quickly. No idea why; there's no evidence of change in the beam, so
the suspicion lies with electronics, or some noise source (like the 7 kHz
noise that was observed in the frequency stability servo, which we haven't
yet diagnosed). Dennis found that by lowering the gain of the servo from
30 dB to 15 or 18 dB allows it to lock robustly. These 2 problems will
be investigated soon.
Optics (Billingsley, Armandula): Helena has compiled all the
documentation on the polished and coated optics that she has inspected.
REO will start coating the core optics on July 8th. It will take approximately
3 weeks to coat all the parts. The ETMs will be coated first, followed
by the ITMs, the Beam Splitters and then the SRM's and PRM's. They are
working on the tooling and everything is going smoothly so far.
Computing: Lisa Bogue and Mike Pedraza has set up a secure wireless
access point on our martian network (40MARS), and installed a wireless
laptop for use as an EPICS monitor screen. Two more laptops will be installed
soon.
Facilities and vacuum envelope (Vass, Jones):
-
Our newly repaired V1 valve has a pneumatic nitrogen leak. This requires
a new part, from VAT in Switzerland, that we hope to receive in 2 weeks.
Meanwhile, we can live without it.
-
Larry reports that Four beam tube assemblies (3 @ AP, 1 @ SP&MC) should
be ready early in the week of 6/3. Next week is remotely possible.
-
The machining of the housings for the camera boxes should be finished later
this week, making these items complete.
-
The machining of the parts for the SP&MC table cover may be completed
late this week or early next week. Then it needs anodizing. So, should
be ready early in the week of 6/3.
-
The 40m storage cage, cat-free, has been cleaned out. Ed Chargois has disposed
of most of the stuff that was there.
South Annex Bake Ovens (Taylor, Cardenas):
-
All ovens are idle, and on standby.
-
Bob installed a new SRS ionization and pirani gauges onto the main volume
of bake chamber #E, and will test it on Thursday.
Bob has designed a jig to hold optics (ranging from 1" up to our 5"
test masses) securely during baking in his ovens.
Thermal Noise Interferometer (Libbrecht)
This week we put together a number of measurements, made over the last
few weeks, into a breakdown of the different noise sources that contrubute
to the TNI. We have a number of total noise curves, going back to December
of last year, and we thought it would be interesting to try and identify
the limiting noise sources in various frequency ranges. Attached are two
plots, one for the South Arm Cavity (SAC) taken in December of last year
and one for the North Arm Cavity (NAC) taken less than a month ago. Each
plot includes both a total noise curve, measured with the arm cavity locked,
and a series of noise curves from different sources.
The first, and perhaps most obvious, noise source is laser-frequency
noise. This is shown in purple on the enclosed plots and was obtained by
measuring the free-running laser frequency noise (see last
week's report ) and then dividing by the appropriate loop gain for
the mode cleaner. In the North Arm Cavity (NAC), laser-frequency noise
is dominant from about 5kHz to 20kHz, and the less-than-optimal phase margin
at the unity-gain frequency (just over 10kHz) accounts for the observed
bump in the total noise. SAC's laser-frequency noise is lower than NAC's
because the gain of the mode cleaner was higher when the SAC data was taken,
and the better phase-margin prevented a bump at the mode cleaner's unity-gain
frequency. SAC's total noise in December was dominated by laser-frequency
noise over a fairly narrow band between 6kHz and 10kHz, as expected.
The second noise source we looked at was laser-frequency noise imposed
on the laser by seismic noise in the mode-cleaner cavity. We were only
able to measure this up to about 45Hz, and it shows up at the same level
in both measurements. This noise source is shown in red on both plots.
The third, and most interesting to us, noise source is from the electronics
in the servo filters, shown in green on both plots. SAC's noise curve was
dominated by electronic noise only at comparitavely high frequencies (above
12kHz), and the use of a passive notch filter in December gave rise to
the bump at 27.5kHz.
NAC, on the other hand, is dominated by electronic noise over many frequencies
and at a comparitavely high level! This is largely due to the fact that
NAC's optical gain is lower than SAC's, but particulars to the design of
the NAC servo that make it easier to lock than SAC's December configuration
contribute also.
The straight lines are theoretical thermal noise expectations for SAC,
also plotted with NAC's data for comparison: bulk thermal noise in red,
and the upper bound set by SAC in cyan (blue-green). Niether curve accounts
for coating thermal noise. It is evident from these plots that electronic
noise must be reduced substatially in NAC before any thermal-noise measurements
can be made, and SAC's electronic noise could be reduced as well.

LASTI (Zucker)
LASTI (MacInnis, Mason, Mittleman, Ottaway, Rollins, Shoemaker, Zucker)
Vacuum envelope: Myron completed installation of the membrane
air dryer unit and the pump station is now running unattended without the
need to change cylinders for seal gas. MZ changed turbo controller
settings to more sensitive trip conditions for increased safety (this will
require temporary bypassing when roughing down from atmosphere, but that's
considered a minor penalty for the improved security in normal operation).
External pre-isolators: Jonathan Kern visited us this week from
LLO. He visited the LASTI lab, reviewed the drawing packages, and also
discussed installation staging and fixturing, piping standards, service
procedures and hydraulic fluid leak containment with us.
Ken Mason is at Southbridge Sheet Metal today inspecting the first article
EPI weldments; expected to ship next week if all is well. BEI has
shipped the remainder of the MEPI actuators and they arrived in good shape
(no chipped magnets seen so far).
Prestabilized laser: Dave and Jamie achieved success with the
improved frequency stabilization servo. Unity gain bandwidth of 400
kHz was achieved using the new circuit topology, with further increase
likely if some trivial photodetector-related limits are also taken care
of. Unfortunately, an electronics fault (possibly a blown PA-85) happened
right after these new results, so there is a delay in fully characterizing
the new topology.
Data Analysis and Computing (Lazzarini)
>From Kent Blackburn
Simulation and Modeling (Bhawal)
Signal propagation in Hanford 2km
-
John Zweizig, Matt and Biplab discussed about signal propagation in IFO
and implication of using interferometer channels other than the GW channel
as vetoes for Burst candidates. We are yet to decide how these questions
should be tackled and how exactly the measurements in model to be done
so that meaningful conclusions for the actual IFO canbe arrived at.
Mode Mismatch and Locking Studies (Biplab)
-
The instability problem encountered in locking Han2k beyond a certain degree
of mismatch (as reported last week) could be solved by recalibrating the
input matrix at that state and then continuing with new input matrix for
more mismatched states.
-
Got another puzzling result - It is possible to lock IFO at two different
sets of mirror positions (starting from two different initial conditions)
while nothing in IFO changes. Matt and I are trying to resolve this.
Code Development and Maintenance (Ed Maros)
-
Continued on configuration issues
-
Worked some on compiling e2e software on CACR systems
Alfi (Melody)
-
Implementing the 'Find' feature for alfi5. Worked on some problem reports.
LIGO Data Analysis System
Software Systems (Blackburn)
Caltech (Blackburn)
-
The new TCL Channel data socket interface was implemented late last week
and tested over the weekend. The development LDAS system showed a phenomenal
0.03% failure rate for the more than 30,000 jobs sent through over the
weekend. We were also able to send jobs through the system at twice the
pre-TCL Channel rate. Unfortunately, we learned on Monday that the dataConditionAPI
was not using the TCL Channel data socket interface to connect to the wrapperAPI.
When it was modified to use the new interface, jobs started to fail at
this socket interface between the dataConditionAPI and the wrapperAPI with
a failure rate of about 50%. We have spent a solid two days since discovering
this working on understanding the reason and implementing a fix that meets
our schedule demands for a code freeze June 3rd. As of today, we think
we have this fixed (patched may be a better word). We will need to perform
extensive tests over night to determine the reliability of this fix.
-
The implementation of the new web page LDAS username and password application
is well under way. The LDAS system is now using an encrypted password file
and the controlMonitorAPI has been modified to support the new requirements
for this password file and has a socket interface for the web page script
to automatically update the password file on any LDAS system that runs
the new LDAS release.
-
Efforts to evaluate the compatibility of the new GCC compiler release (3.1)
with the LDAS and LDCG environment have been nothing less than frustrating.
The changes to GCC are significant and many of our development tools are
also impacted by the change. LDAS itself will need changes (for the better)
in areas associated with namespaces and C++ class method scope rules.
-
We are working closely in the LSUG meetings to assure a coordinated release
of both LDAS and LAL/LALwrapper for the Science Run.
Caltech (McWhorter)
-
I worked on compiling LDAS with gcc-3.1
-
I updated automake and autoconf to the latest versions. Work towards
getting LDAS to be compatible with these new versions is ongoing.
The problems that have been resolved so far are some of the macros were
named in a way that made them look like GNU macros but were really LDAS-specific
macros. Libtool integration is not working with autoconf, I don't
know why yet.
-
I reviewed datacondAPI code and found that FFTs are done synchronously.
I reviewed FFTW documentation and found the FFTW API is not fully threadsafe,
but can be threaded more than we are threading it. Basically, FFTW
plans have to be created and destroyed synchronously but actual calculations
can be done asynchronously. I verified this by modifying a FFTW test
program I wrote last week to use multiple threads. I work on this
as a low priority item only when I was waiting on a compile for the gcc-3.1
project.
-
I debugged some problems with the old version of automake. I found
two problems before I stated working on upgrading autoconf and automake.
I had cloned Mary's dev environment when I started, which sets the CPPFLAGS
environment variable, which for some reason is confusing gcc-3.1 (does
not confuse gcc-3.0.4). This caused problems with GNU extensions
to the STL, which gcc-3.1 has moved to different include directories and
different namespaces when compiling.
-
I coded a workaround in build_ldas that gets around a strange problem with
ldas configure scripts (generated automatically by autoconf) find Object
Space headers with the old versions of autoconf and automake. The
problem is very stange. Configure will not find Object Space unless
CPPFLAGS is set (which breaks hash_map, see the previous item) or build_ldas
*does not* set --with-ospace=/ldcg. This implies there is a off-by-one
bug somewhere. This problem was the most compelling reason to try
upgrading autoconf and automake.
-
I did a little analysis in trying to figure out the best approach for resolving
namespace issues with gcc-3.1 in our code. For whatever reason, gcc has
moved things from std:: that will likely just be moved back in a later
release. The new namesspace is __gnu_cxx::, which clearly is not
acceptible. I'm leaning towards a #define but need to do a little
research to see if there are some items that are more likely to be adopted
as a standard later, e.g. hash_map probably has a better chance than rope
(i.e. I think rope will be renamed to lstring or long_string or something
devoid of platform-dependant UNIX-like humor). When I feel more comfortable
with the issue I'll propose my solution.
Caltech (Edward Maros)
-
Debugged some issues with the TCL Channel interface for ObjectSpace.
-
Created new repository for LDAS's secure web pages.
-
Added round(), ceil(), and floor() actions.
-
TimeBoundedFreqSequence< T > UDT. This class is derived from FrequencySequence<
T > and has start and end time metadata.
-
Frequency data from frames are now ingested as TimeBoundedFreqSequence<
T > instead of FrequencySequence< T >. This allows them to be appropriate
objects for the wrapperAPI.
Caltech (Masha Barnes)
-
Working on cgi script to handle ldas users passwords. Already implemented:
-
Added resource file that contains administrators information, available
LDAS sites.
-
Script now sends email to administrators when new request is submitted.
-
User provided information is stored in site specific file.
Caltech (Phil Ehrens)
-
Converted datacond API server socket to wrapper API to use Tcl channel
based socket functions.
-
Converted LDAS password file handling to use encryption. Worked with Mary
Lei and Masha Barnes to develop protocols for managing user information
between a web page on a secure server, the control and monitor API, and
the manager API.
-
Added job specific history generation support to the frameAPI and made
the generation of history records the default behavior for concatFrameData
so that dataPipeline jobs could access and manipulate the data in the history
records if required.
-
Added encrypted mode to manager's operator socket at the request of Peter
Shawhan. It is now possible to submit job requests to LDAS through
an encrypted channel which uses an extremely difficult to predict salting
method.
-
Fixed API removal and adding routines so that it is now possible to add
and remove API's dynamically from a running LDAS system. API's can
be moved from one machine to another by first removing them and then adding
them on the new machine. Port assignments are preserved when the API name
is the same as an API formerly removed and subsequently added.
-
Added memory usage panic detection to the bgerror function for LDAS API's.
If an LDAS API generates a bgerror because of the inability to allocate
memory, the memory usage limit for the API will be dropped to 1Mb, causing
the API to be restarted if the baseline memory usage exceeds that value.
The responsible administrators for the API will be notified via e-mail
both of the memory allocation failure, and the change made to the baseline
memory usage limit.
Caltech (Mary Lei)
-
cntlmonAPI and utilities: modified cntlmonAPI to retrieve info and
do updates for the new users queue structure; encrypt password file when
transmitting to client; testing cgi interface cmd for adding and updating
users.
-
eventmonAPI: replaced datasocket with tcl channel data sockets;
removed extra server sockets; on shutdown, wait for all threads and destruct
all objects to prevent segmentation fault; tested with pipeline cmds.
-
metadataAPI and ligolwAPI: on shutdown, wait for all threads and
destruct all objects to prevent segmentation fault.
-
cmonClient updates: handle decryption of new password file passed
from server; remove emergency socket by having updates through operator
socket;
-
LDAS testing - created test data to add and update users; testing cntlmonAPI
interface
Caltech (Salzman)
-
Converted the last test script to use Peter's library for sending jobs.
I am waiting for some added functionality in the library to convert the
looping script and the dc MDC scripts.
-
Incorporated an example sft and tfcluster jobs in the looping script 'repertoire'.
-
Tested persistent sockets with the 'demo' server/client scripts and found
the -linger option to be helpful. It looks like that fixed the problem
with datacond too.
-
Spoke with Philip about adding new tests for datacond actions. I
will be working on this for the rest of the week.
Caltech (Charlton)
NO REPORT (on vacation)
Caltech (Shawhan)
-
We worked out a protocol to encrypt the LDAS password when a user submits
a user command to LDAS. This has been implemented on the ldas-dev
system and in the guild and LDASJob client software (only used when communicating
with ldas-dev, at present). The use of this encryption protocol is optional
at present, but will probably become mandatory (at least for some of the
LDAS systems) when the next version of LDAS is released. This change should
be transparent to users as long as they use the standard client software
(guild, LDASJob, getMeta, etc.), but plain Tcl scripts will need to be
changed over to using the LDASJob package.
Hanford (Mendell)
-
Worked with LDAS to debug jobs that request SFT data.
-
Discovered a bug in the LALDemod function. I also requested that this function
return, in addition to the maximum likelihood estimator statistic, the
demodulated frequency series that it produces for each polarization. Worked
with the AEI group to get the problem fixed and the changes made.
I believe these have been checked into CVS.
-
Finished working with Maria Alessandra in Milwaukee to incorporate the
latest LALDemod function into the knownpulsardemod DSO. The code changes
needed are under control, but I still have quite a bit of code to add to
my knownpulsardemod dso to get everything working. I also need to
add code to unpack SFT data from LDAS (once this is working) and put it
into the input structures used by the LALDemod function.
Hardware Systems (Anderson)
Caltech (Dan Kozak)
-
Planned and executed LLO and LHO changeover to a SAN topology using inter-switch
links (ISLs) and translation mode on the FC switches so that various machines
(most importantly the frame builders and dataserver) will be able to share
QFS filesystems containing the frame data. This is ongoing, but we
expect to complete the work by the end of today.
Caltech (Al Wilson)
-
Worked on the setup procedure for the new machines for the Beowulf nodes
at LHO and LLO. Setup and got running the new release of Systemimager 2.0.1
Caltech (Stuart Anderson)
-
Coordinated activities related to the Fibre Channel disk storage reconfiguration
at LHO and LLO.
-
Researched Gigabit Ethernet cards for Linux to upgrade Beowulf and Datacon
servers to 1000BaseSX connections for most LDAS systems.
-
Started evaluating RedHat 7.3 suitability for an LDAS OS upgrade after
S1.
MIT (Keith Bayer)
-
Compressing LDAS network to single layer.
-
Researching equipment suggested by Caltech for TB NAS device.
-
Compiling MIT network bandwidth data.
Livingston (Igor Yakushin)
-
Ordered 48 snag-less strain-relieved network cables for the new beowulf
clusters, the order has already been shipped yesterday and should be here
either at the end of this week or at the beginning of the next week.
-
Received 2 racks, 4 set of outlets, 8 wheels for the racks, two sets of
back rails.
-
Together with Rus set up new racks behind the old ones in the mass storage
room in place of the back shelf.
-
Helped Dan to reconfigure T3s.
-
Resumed experiments with DB2 replication.
Hanford (Greg Mendell)
-
This week I have worked with Stuart Anderson and Dan Kozak to reconfigure
the Sun T3 disk cache at LHO. So far we have moved fiber channel
cards and fiber, and updated zoning on the fiber channel switches, so that
the ldas gateway, dataserver, and metaserver hosts, and the cds framebuilder
fb3, can all direct connect via fiber channel to see 10+ TBs of disk space.
Dan is working to set up QFS file systems on this disk space. The T3 disk
space in use by the cds fb0 framebuilder remains unchanged and will do
so until some time after S1.
-
A conflict between the world wide numbers of two T3s was identified. I
am coordinating with Stuart and Sun to resolve the conflict. One
T3 will remain disconnected until this is fixed (a temporary loss of 0.5
TBs.)
General Computing (Wallace)
MIT (Keith)
-
Beginning MU7 upgrade on all Solaris machines
-
Installed wireless keyboard/mouse in conference room
-
Spec'd out AIT3 tape device
-
Unboxed books from move to NW22
-
Received SB1000 from Caltech (Sigg)
-
(w/ Larry) setup virtual control room SB1000's
-
Purchased printer
Livingston (Shannon)
-
Setting up a test-bed for working with VPN configurations. The more
I read about VPNs on the Cisco PIX the more evident it becomes that we
will have to implement NAT and static routing on the PIX. I am going
to try and set up a VPN independent of the PIX using Solaris' implementation
of IPSec and SunScreen Lite. I will be using Solaris for Intel, an
Ultra 10, and a blade 100 for the test.
-
-Investigating LDAP for a global address book for the observatory.
-
Fixing a couple of problems with the LLO web page. Working with Bonnie
to show her what she will have to learn and what is involved in maintaining
some of the web pages here at LLO.
Hanford (Christine)
-
Dealt with a network outage. It required reboots and troubleshooting
of our equipment, then when we were fairly certain that it was not our
equipment, it took many phone calls trying to find after hours support
personnel at the network provider's offices. The problem was finally
resolved the following morning.
-
Provided various user support related to the network outage, e-mail addressing,
network usage, modem problems, buying new computers and remote access to
our computers.
-
Continued work on a cgi to put the work permit form on the web.
CIT (Mike)
-
Loaded a Laptop for the Loaner pool.
-
Upgraded and reloaded a PC for a visitor's workstation.
-
Set up a cubicle on the second floor of W/B.
-
Started loading a new 2U server to replace a webserver for DCC that is
currently having some hardware issues. The current OS on the old server
is NT4.0 and I am loading the new server with 2000 server.
-
Helped Lisa setup a wireless network and DHCP server at the 40Meter.
-
Finished up loading three new laptops for 40 Meter with all GC software
and additional engineering software, and have transferred them over to
40Meter.
-
Onsite User/Phone support, This week I had a lot of hardware/software issues
with multiple users plus cleaning up a few computers from viruses _'very
time consuming' but have cleaned these users computers and are now virus
free.
CIT (Lisa)
-
With Mike's help, configured and installed a wireless network on the 40meter
martian network. The wireless network was installed with the maximum
number of security features that wireless currently allows. Any one
who needs access to that network should contact me for information.
-
Enabled encryption on all of the GC wireless APs. Use of wep is optional.
Keith at MIT told me the orinoco silver cards can't function with wep enabled
on the AP's. We have many different brands of cards out there. If
any one has any trouble accessing the network, please let me know.
-
Setup secure shell tunneling of textedit for Rita and Ryan. This
is to allow them to maintain the cit and lsc mailing lists.
-
Did a test install and configuration of Perlfect Search on vega.
This is a set of free perl scripts that allow a google-like search/index
of a web site including pdf documents. This is an easy way to increase
the search capabilities for DCC documents. A demo of the engine is
at this URL: Perlfect
Search (There are only about 8 documents that are indexed so try searching
for ligo, lazzarini or mode to get sample results.) One limitation of the
system is that documents that were scanned as images instead of text do
not get indexed.
CIT (Veronica)
-
Collecting the files of the presentations made at the 2002 GWAD workshop.
Have burned the ones that I already have onto a CD; they keep coming daily.
Made several minor updates to the LIGO website. Working on the Presentations
script for the Elba Conference.
-
CaJAGWR: need to discuss with Kip and Gary possible improvements to the
video setup that we currently have for taping the seminars. Also, did the
usual up-keep of the website.
CIT (Larry)
-
Worked with Keith and finished off a good portion of the remote control
room setup for MIT. The equipment still needs to be put in its final location
and there are a few other logistical issues to be worked out. However,
the system can be used in its present form.
-
Worked with Keith on gathering data concerning network performance between
the LIGO MIT and other LIGO locations. Still more work to do and Keith
will report on the findings. Did not have enough time to finish all of
the to-do items at MIT so I will be returning in a few months to work on
a few more tasks.
-
Received the rest of the SUN equipment for the remote control room at CIT.
The second system is now up and running in the SSCR. There are a few more
logistical items that need to be worked out with Dave but the system can
now be used as is.
-
Started getting information on OTP Smart cards. This is being looked into
as a way to secure the remote control rooms and their usage.
-
Worked a few PC issues. A couple more machines that had viruses on them.
However, no damage was done and the virus-scan s/w was able to clean things
up. Along that same line, we are adding a number of domain/host names to
the e-mail denial access list, on a daily basis. Hopefully, this will cut
down on the spam and porn related e-mails.
-
Installed a number of h/w peripherals on different PC's and SUN boxes.
-
Worked with Rita and Ryan on the new mailing lists that they will be maintaining.
-
Worked with Christine and Richard on resolving the network problem at Hanford.
John McCoy and PNL is working on getting us a few more contacts, so when
our main contact is not there we can still get something resolved. Just
as a side note the ESNet technician was helpful in checking things out
and making sure the problem was not on their end.
-
Working on a number of procurements to help with the Video Conferencing
and other related items.
LIGO II/Advanced R&D (Sanders)
>From: Janeen Romie
AdLIGO Suspensions
Working on stiffening up the MC suspension structure.
Submitted drawing formats, instructions for use and drawing practices
documents.
>From: ctorrie
Advanced LIGO Suspensions
Visit to the Institute for Gravitational Research (IGR) in Glasgow,
Scotland.
May 1st - 20th
For the last 2 weeks I have been working at the IGR at the University
of Glasgow. In the course of my visit I attended the PPARC funding
review for the IGR; visited the Rutherford Appleton Laboratory in Cambridge,
England; spent the day with Dr. Caroline Cantley, a senior Engineer who
is about to start work in the Institute; attended one of the days at the
annual GEO 600 Review; presented the drawings and plans for the mode-cleaner
control prototypes; discussed the plans and time scales for the electronics
that GEO will supply for the controls prototypes for MIT and CIT; and gave
a presentation on how to use the MATLAB pendulum design model.
I will submit separate reports regarding my visit to Rutherford and
discussions arising from the drawing review and electronics update.
I also helped Russell Jones, Alastair Grant, Mike Plissi work
on several experiments and prototypes, for advanced LIGO, in the laboratory.
Over the course of the 2 weeks we: -
1) tested several ways of adjusting the height of the cantilever blades.
2) designed and tested an improved method for adjusting and clamping
the position of the coil former in its clamp
3) set up a planned test of some eddy current dampers on a triple pendulum.
(Firstly we had to set up and install a new XYZ drive system under an existing
prototype triple pendulum before we could install the new eddy current
dampers and adjustable arms.)
All of the parts are almost in place for testing this effect in both
the longitudinal and vertical directions.
As an aside Russell Jones, the young engineer at Glasgow is now trained
in SOLIDWORKS to level I, same level as Janeen and I. They also hope to
have a second young engineer trained in the next couple of months.
Quad at MIT
Rich Mittleman has implemented the proposed upgrade to the quad at MIT
in order to try and solve the problem of the undamped pitch mode. The improvements
are noticeable and Norna, Rich and I have been looking at these over the
last day or so.
Controls Prototype - Mode Cleaner
Janeen and I are working on the proposed changes suggested at the drawing
review at Caltech and Glasgow. In particular I have been working with Russell
Jones in Glasgow on the new drawings and an assembly of the new coil clamping
and adjusting mechanism.
>From: GariLynn Billingsley
Advanced LIGO Optics
Phone conference with Goodrich regarding further compensating polish:
We have decided that it will probably be a longer run and, therefore, cost
more to do the measurement as specified, i.e., subtract side one from the
bulk measurement. I will change the specification to state that subtraction
of Side 1 is not required, but may be done to more accurately represent
the bulk compensation. Of course if they can get under 10 nm rms
without subtracting side one, all the better, it's certainly an easier
measurement analysis.
Goodrich will provide surface measurements per the specification and
their prior bid. These measurements may be done after the next round
of polishing.
Goodrich does have data from a visual inspection which will be sent.
This inspection was beyond their typical inspection. A 200W light
was used and linear sleeks were found front and back. Linear sleeks
are not something one would expect from CCP.
We at Caltech have done a visual surface inspection on the 250 mm sapphire
piece: Side one is in worse shape than side two, it shows a lot of
circular sleeks of diameter ~12 mm as well as a faint spiral pattern.
Side two showed a stronger spiral pattern, but only faint circular sleeks
similar to those on side one.
There were bubbles breaking through on both sides (no surprise there!)
We did not find scratches on either side.
This is a significantly different finding than Goodrich. Perhaps
it would be a good idea if I made a trip out there when the optic goes
so that we can compare techniques.
Goodrich will put together an estimate for the next run, the previous
guess was that the run would be about 11K.
Goodrich will put together an estimate for the cost of compensating
Sapphire of similar quality, but 314 x 130 mm in size. They are to
assume they would compensate the central 300 mm diameter, but will note
roughly how the cost would change if only the central 215 were compensated.
They are to assume an initial surface of 100 nm rms figure and 4 angstrom
roughness. They will also assume a requirement of < 10 nm rms
transmitted (S2/Bulk) and 4 angstrom roughness (similar to the current
spec goals).
>From: Helena Armandula
Advanced LIGO Coatings - "Q" Substrates
MLD's coatings break down when annealed at temperatures higher than
500 degrees C. To determine the optimum temperature to anneal the
"Q" substrates coated with 30 alternate layers of Ta2O5/SiO2, witness pieces
coated on the same run have been annealed as follows:
-
P/N 8203 at 400 C. This part looks good under the dark field microscope.
-
P/N's 8107 and 8174 at 450 C. 8107 shows a few more defects than
the previous but it does not look very bad.
-
P/N 8233 baked at 500 C. Has lots of small scatter points and a small bubble.
-
P/N 8118 has not been annealed - This one is to be annealed at Stanford
at 500 degrees C or higher.
These parts were sent to Roger Route. He'll take absorption measurements
and make a recommendation on the annealing temperature for the "Q" samples.
The next run at MLD will be 30 alternate quarter wave layers of NbO2/SiO2.
The substrates are at their facility waiting to be coated.
>From: Phil Willems
No report--Elba.
>From: Mark Barton
No report--Elba.
>From: Riccardo DeSalvo (prepared by Hareem Tariq)
Mike
1) Ordered and received resistors and thermistors to set up the mock
heat capacity puck which will be then used as the test bed for preparing
for the measurement. Mapped the resistivity puck channels to be used for
the mock heat capacity test. Ready to put things together next week.
2) With the help of Phil calculated the resonant frequency for the Metglass
(used the young's modulus and other constants for the MoRuB) to be 676
Hz for a 25mm long, 3mm wide (these dimensions were from the rough setup
Mike and Kelin put together) and 27 micron thin reed. This was done for
building the actuation setup for Q-factor measurement. Recalculation will
be done, with different reed dimensions to bring the resonant frequency
down.
Mike, Hareem, Eric
1) Brian from Quantum Design (QD) installed yet another cryopump which
had been tested at QD. At Caltech we found that the flapper valve failed
once and the pressure gauge was faulty this time. Brian is returning with
a newly tested, this time more thoroughly, cryopump next week.
2) Borrowed a Pirani gauge and controller etc. from Steve Vaas to continue
systematic debugging of the system. At Eric's advice we are running measurements
to pinpoint which unit, out of cryostat, controller and the computer, is
really faulty.
3) Mike was appointed the point man here at Caltech to keep track of
QD and cryostat in a meeting with Eric and Ken. Mark Seeback (Customer
service head) and Stefano Spagna (chief Engineer) were contacted at QD
to help solve the urgent problem. QD has offered us some time on their
company cryostat in San Diego for conducting our measurements if the system
is not fixed next week.
Hareem
1) Changed different parameters, on the machine and sample, for splatting
MoRuB samples in order to get an optimum amorphous surface from the splat.
Finally produced a splat with almost 80% amorphous surface which is waiting
to be scanned once I get some free time on the X-ray diffraction machine.
2) Prepared samples of appropriate size for MoRuBSi and MoRuBSiAlP to
be splatted and checked. Preparing more MoRuB alloy as the one big chunk
from Carnegie Mel. does not seem to be uniform in composition.
4) Checked the (AuSn)Ti braze by etching the Molybdenum alloy with Murkami's
reagent and the braze with HF. The material was brazed under Argon atmosphere.
The eutectic of AuSn is at around approximately 231 degrees Celsius but
braze did not wet the alloy even at 250. I tried ramping the temperature
by 20 degrees to 400 but that did not help either. Jan has a similar experience
with braze and suggested that I go to higher temperatures. Will test the
braze next week with all four different etchants I prepared and also will
continue ramping the temperature until the right one is found.
5) Started getting ready the sample of MoRuB for the conductivity measurement
at QD.
Kelin, Mike, Phil
1) Setup an actuator test for Q-factor measurement. Used capacitive
force to oscillate a Metglass reed but the maximum voltage supply available
(32V) did not produce a deflection. Phil is providing with a power supply
of over 100V next week.
2) Looked for a commercial actuator but did not find an appropriate
one. On Phil's advice will just use a simple Cu plate for capacitive actuation.
3) Working on getting things ready for the installation of Q-factor
measurement in Phil's vacuum chamber.
Alessandro
work on vertical accelerometers.
No news from Akiteru
For additional information about this report, contact sanders@ligo.caltech.edu