Weekly Report for Week Ending April
11, 2002
The LIGO Executive Committee
Agenda for Monday April 22, 2002 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
A meeting of the LIGO Change Control Board
has been scheduled. Time permitting we will address the standard
agenda items below:
-
Announcements
-
LSC Issues (Weiss)
-
Comments on Weekly Report
-
WBS 1 LIGO I Construction (Lindquist)
-
Field Change Orders/Contingency Liens/Change Requests
-
WBS 2 LIGO Lab Operations
-
Administration (Lindquist)
-
Sites (Raab, Coles, Shoemaker, Sanders)
-
Detector (Whitcomb, Coyne)
-
Campus Research Facilities (Weinstein (40 Meter), Libbrecht (TNI), Zucker(LASTI))
-
Data Analysis and Computing (Lazzarini)
-
WBS 3 and 4 Advanced R&D and LIGO II
(Sanders)
Executive Committee only 11:30 - noon
Topics:
Special Items:
Special Announcements:
Weekly
Report Highlights
LSC Issues (Weiss)
no report
LIGO I Construction/LIGO Laboratory
Administration (Lindquist)
LIGO Weekly Site Telecon (Lindquist)
A site teleconference was held on Thursday, April
18, 2002. The following items were discussed:
-
Next week site teleconference will be dedicated
Outreach Presentations.
-
Cost Status - endo-of-March costs (excluding
R&D) running at 87 percent of budget. First few months are low,
but expect to catch up due to time lags transferring to new Cooperative
Agreement. Staffing costs are at 90 percent of budget.
-
Livingston Construction - the contractor indicates
that he will be finished by the end of April.
-
Hanford Construction - siding still not on
site. The contractor has provided a revised schedule with work arounds.
Still holding to original completion.
-
Hanford Audio/Visual Equipment - Livingston
to provide copy of their statement of work to use as a template.
Hanford has four prospective bidders.
-
Personnel - Katrina Carter starts at Livingston
as an Operator Specialist.
SURF - we expect 34 SURF students to show
up in June. Of these, 24 will be at Caltech and five at each site.
The list of current actions revised to reflect the
status of open actions assigned through April 18, 2001 may be found at
ACTION
LIST.
PROPERTY
MANAGEMENT (Chargois)
From: Ed Chargois <chargois_e@ligo.caltech.edu>
DOCUMENT
CONTROL CENTER (Turner, Mak)
>From: Linda Turner
- turner@ligo.caltech.edu>
Web pages for the
DCC give simple how-to's for document numbering, easy access to the latest
on-line documents, and search capabilities for the DCC database. Take
a look. . .
ACCOMPLISHMENTS
-
Processed a couple more LSC presentations
that straggled in.
-
Redistilled about 8 LSC presentations that
ended up with only a cover sheet in the .pdf version. These have
now been transferred to docspublic.
-
Met with Dennis to review a multi-page drawing
submitted to determine the best way to number and maintain version control.
Am in the process of issuing a specification for the drawing consisting
of the list of drawings originally in the submitted package.
-
Met with a Canon representative for a demonstration
on a Canon CD-4050 scanning workstation. It is a great machine but,
unfortunately, doesn't do color scanning. I was under the impression
that it was color capable and was disappointed to find out otherwise.
-
Searched for three work orders from the past
for the DCAA auditors. Only one of the three was in the DCC.
-
Continued to work on the upcoming rollout
of the new LIGO procedure and policy manual.
-
Continued to work with Ryan and Dave on the
press kit being assembled. Worked with Cleveland on scanning the
many news clippings collected during the past three years. The DCC
numbers assigned to each still need to be imbedded on the document.
-
Sent out email for the upcoming Cinco de Mayo
lunch on May 3rd. Made up the tickets and food sign-up sheets as
well.
-
Worked on several problem documents electronically
submitted to the DCC. Many of them involved numbering inconsistencies,
revision discrepancies, and other such difficulties. Reminder
to LIGO staff: Please make sure that as a minimum, each document
submitted has a LIGO number, author's name, and date. It's surprising
how many documents are missing one of more of these essential pieces of
information!
>
From: Cleveland Mak <mak_c@ligo.caltech.edu>
ACTIVITY
-
Scanned approximately 40 documents for press kit.
-
Progress continues on conversion of old charge account files to electronic
form.
-
In the process of processing numerous electronic documents submitted to
the DCC. Several documents seem to have problems with them.
| 04/18/02 |
Packages |
Faxes |
| In |
30 |
45 |
| Out |
10 |
27 |
Press here to access
the DOCUMENT CONTROL CENTER
WEB PAGE.
COST SCHEDULE
CONTROL SYSTEMS (Cunningham, Brambila, Kaufman)
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS
PAYABLE HISTORY DATA .

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
-
Completed internal modifications to Katherine Creath,
Wyko, Oliver McCullough, Hytec, and Allied Engineering. Completed C/O #1
to Reliable Office, and C/O #10 to Teknicircuits. Working on C/Os #12 and
#13 to Brunt Construction.
-
Working with Bill Tyler on obtaining more information
and figures on the JPL workorder with Raytheon.
From: Florence Kaufman <fkaufman@ligo.caltech.edu>
-
Assisted with providing and reviewing items requested for DCAA budget.
-
Completed and posted report for FP2001 Operations as of March 2002 on network.
-
Worked on projection of expenditures for 40Meter Lab Operations.
-
Responded to request from Federal Accounting for funding realignments.
-
Prepared a schedule of budget increases required due to increase in benefit
rate.
-
Financial reports can be found at: http://docuserv.ligo.caltech.edu/~fireport
SUBCONTRACTS MANAGEMENT (Petrac,
Jasnow)
From: irena@ligo.caltech.edu (Irena Petrac)
-
Nothing significant to report.
From: Ed Jasnow <jasnow@ligo.caltech.edu>
CONSTRUCTION:
-
Work is proceeding slowly on the final punch list items
for the LLO Staging Building. The contract is still scheduled to be completed
by April 30.
-
The siding has not been delivered for the LHO OSB East
Building, so the contractor is re-arranging his schedule around this delay
in order to keep the original schedule intact.
-
Four potential proposers have been identified to provide
the A/V equipment for the LHO OSB East Building. A request for proposal
is now being prepared to send out to acquire this equipment.
OPERATIONS:
-
The personal injury lawsuit brought by a contractor
injured at Livingston has been settled as a result of mediation. The settlement
amount will be covered by Caltech insurance.
-
A seminar for all foreign nationals
on the LIGO staff will be held on Friday, May 3. This will be conducted
by Marjory Gooding, Director of theInternational Scholars Office at Caltech.
The sites will be connected by videoconference.
SUPPORT (Baldon, Torres, Lloyd,
Tischler)
>Irene Baldon
-
Processed the paper work for seventeen (17) new/revised
trip, eight (8) completed/ticketed trips awaiting the necessary paper work,
and thirty-Six (36) trips in various stages of completion before ticketing
can be done and paper work completed (mostly SURF 2002 students).
-
Completed four (4) Expense Reports and there are thirteen
(13) reports yet to be done.
-
Reconciled twenty-nine (29) P-Card items this week (one-hundred-twenty-three
(23) for the month) which require extensive telephoning to vendors in order
to track down which traveler incurred which charge.
-
Started working on the LIGO/REU/SURF Program with Dr.
Libbrecht. Twenty-nine (29) students have responded to my initial inquiry
for travel and four (4) have been completed at this time, with twenty-five
(25) still being worked out.
-
Worked on the preparation and distribution of the Travel/Vacation
Itinerary for April 15, 2002. Performed normal recording and filing associated
with Travel and Reimbursement. Also performed miscellaneous duties as requested
by various members of the LIGO Project here at Caltech as well as from
members of the staffs of each of the two (2) sites.
-
I continue to do MIT's travel to the sites for installation
activities and also to assist them wherever possible.
>Dorothy Lloyd
-
Continue to work with Ruth on closing out complete POs
with remaining encumbrances.
-
Processed the usual flow of invoices for payment, and
also tracked and followed up on some invoice problems. Reviewed and recorded
payments processed by Esther the week of April 8. For the total number
of incoming invoices received for this period see "Cost Schedule Control
Systems" report by Esther Cunningham.
-
Processed the usual requisitions and change orders.
-
Continue to monitor contract and blanket order encumbrance
and notify task managers when supplements are needed.
-
Jim continues with data entry in the LIGO database and
helping out in the DCC.
>Rita Torres
-
My computer slowed down drastically as it battled a
virus. Many thanks to Mike Pedraza who worked tirelessly to remedy the
situation. Thanks to Mike's care, I lost no files.
-
Posted on the small web page for review documents from
Pennsylvania State. Notified V. Kondrashov of LSC documents available for
posting on the web.
-
Completed Lase-R Shield purchase for eye wear replacement
shields, these should arrive soon.
-
Returned for credit several pieces to CVI, and Polytec.
Placed Pcard orders, and chased lots of invoices this week. Reconciled
52 this period.
-
Updated site trips. Change to LIGO roster this week:
visitor Youichi Aso.
>From: Ryan Tischler <rtischle@ligo.caltech.edu>
-
Cinco de Mayo celebration planning.
-
Have most templates and will begin formatting a standard
template for each one, consistent with one another.
-
Meeting with photographers and securing bids for upcoming
brochure.
-
Completed press clipping service and now finalizing
press kit.
-
Beginning coordination of SURF/LIGO orientation, this
in conjunction with GoF.
-
Preparation for GoF meeting on 4-22.
-
Reconciled p-card and travel this week.
Advanced LIGO (Frey)
From: Thomas Frey <tfrey@ligo.caltech.edu>
Progress Period from 04.12 to 04.18
Accomplishments:
-
Weekly Advanced LIGO Project Controls meeting was not
held this week. Next meeting date has not been scheduled.
-
I was delegated a new task this week by Gary and Peter
F. to implement a web based calendar application to assist the commissioning
group with logistics and coordination. After researching some products
that are available, per Larry's recommendation, we are going to pursue
a solution through Caltech's ITS group. I have a kickoff and recon
meeting scheduled with Jennifer Davis of ITS and Larry for Monday at 9:30am
at Steele. For more information see http://cdp.caltech.edu/
and http://www.steltor.com/index.cfm?flash=no.
-
Followed up with Primavera regarding an outstanding
technical issue and received a program patch that I am now using and testing.
-
Advanced LIGO MRE Proposal (Highest Priority)
-
Continuing the development of the Cost Estimate.
-
Continue to pursue all other sub system schedules.
Continue to review all subsystem schedules and incorporating new target
dates per DCC Doc. No. LIGO-M020121-A by Dennis Coyne.
-
Updated web site with latest data.
-
The following is a summary of status by sub system:
-
COC - Work on action items per second review continues.
Next meeting date has not been scheduled.
-
PSL - Finished inputting changes to the cost book and
schedule. Next meeting date has not been scheduled.
-
AOS - Work on action items continues. Inputting
/ reviewing data provided by David S. Next meeting date has not been
scheduled.
-
IO - Work on action items continues. Next
meeting date has not been scheduled.
-
SUS - Working with SUS group to incorporate current
comments. Janeen is still executing the update and has submitted
any data pending a review at the end of this month. Executing outstanding
action items and preparing revised meeting minutes.
-
SEI - Work on action items continues. Next meeting
date has not been scheduled.
-
ISC - Continue to review data.
-
All other subsystems have yet to be scheduled for their
first review. These dates are pending per direction from Gary Sanders
and Dennis Coyne.
-
Continue to update the TNI Schedule and incorporate
any changes.
-
Updated the plan with progress as of 04.12.02 and
posted to site.
-
Sent out update data requests for progress as of 05.03.02.
-
Continue to update the LASTI Schedule and incorporate
any changes.
-
Updated the plan with progress as of 04.12.02 and
posted to site.
-
Sent out update data requests for progress as of 05.03.02.
-
Project Plan for the 40-Meter Lab Upgrade continues.
-
Updated the plan with progress as of 04.12.02 and
posted to site.
-
Sent out update data requests for progress as of 05.03.02.
-
Cost Book Tool.
-
ROSTER DATABASE:
-
Continue work on my action items providing BK with needed
data.
-
COST BOOK DATABASE:
-
Online help is current with most recent system changes.
Procedure is being reviewed for changes.
-
DCAA - Work continues on the incurred cost audit.
-
Prepared / revised 4 transmittals.
-
Development of the Advanced LIGO Project Controls Guidebook
continues.
-
Project Web Site for posting schedule and progress related
data continues to be updated with the latest and greatest.
Schedule 04.19 to 04.25:
-
Next weekly Advanced LIGO Project Controls meeting to
be scheduled. Per Gary, we will be scheduling a meeting before the
end of the month.
-
Continue effort getting the web based calendar system up and running for
the commissioning group.
-
Advanced LIGO MRE Proposal (Highest Priority Task)
-
Highest priority is the development of the Cost Estimate.
-
Will continue to pursue all other sub system schedules.
-
PSL - Will complete estimate and schedule changes.
-
AOS - Continue inputting changes to and prepare for
next meeting TBD. (New data from David to be input).
-
IO - Continue inputting changes to and prepare for next
meeting TBD.
-
SUS - Continue inputting changes to and prepare for
next meeting TBD.
-
Will update the plan with progress as of 03.29.02 and
post to site by the 5th.
-
SEI - Continue inputting changes and prepare for next
meeting TBD.
-
COC - Work on action items by Garilynn continues.
Anticipate schedule changes prior to next meeting TBD.
-
ISC - Finish review of data. Input data and change
WBS as requested.
-
Will issue updated meeting minutes for every subsystem
as action items from most recent review are completed.
-
Will Continue to update the TNI Schedule and incorporate
any changes.
-
Will update the plan with progress as of 05.03.02 and
post to site by the 7th.
-
Will Continue to update the LASTI Schedule and incorporate
any changes.
-
Will update the plan with progress as of 05.03.02 and
post to site by the 7th.
-
Will continue updating the 40 meter schedule and incorporate
any changes.
-
Will update the plan with progress as of 05.03.02 and
post to site by the 7th.
-
Roster Database
-
Will continue to work with BK and executing action items.
Cost Book Tool development continues. (Highest
Priority Task)
-
Mapping and formatting of OPS cost data for input will
now continue with co-operative agreement approved.
-
Will continue to work with BK executing action items.
-
Will continue to provide support to PL for DCAA audit(s).
-
Will continue the development of the Advanced LIGO Project
Web Site.
-
Will continue the development of the Advanced LIGO Project
Controls Guide Book.
Reports (Lindquist)
I have distributed a DRAFT quarterly report for
the Construction effort (end of February) for review and comment.
Change Control/Contingency (Lindquist)
The following change requests have been submitted:
CR-010012
Revision B |
WBS 1.4.4.1 |
Closeout Construction Budgets for Initial Computer Equipment Complement
at the Sites |
P. Lindquist |
| CR-020002 |
WBS 1.3 (OPS) |
CDS Remote Control Room |
D. Coyne |
| CR-020003 |
WBS 1.3 (OPS) |
Fine Actuators for the LIvingston Input Test Masses |
D. Coyne |
| CR-020004 |
WBS 1.2 |
Underrun ISC Budgets (Construction) |
S. Whitcomb |
| CR-020005 |
ALL WBS (OPs) |
Increased Benefits Rate |
P. Lindquist |
| CR-020006 |
WBS 1.3, 1.6 |
Technical and Engineering Support Increased Requirements for FY 2002 |
D. Coyne |
A reminder that we will be doing a LIGO Change Control
Board during the Executive Committee Meeting on Monday, April 22, 2002
at 10:30 am PDT in the SCR.
Press for the latest Contingency
Needs Projection.
Human Resources (Akutagawa)
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
-
Various personnel/payroll /HR related work.
Quality/Safety (Tyler)
>From: Bill Tyler <tyler@ligo.caltech.edu>
No report this week.
LIGO Hanford Observatory (LHO) Operations
(Raab)
No report this week.
LIGO Livingston Observatory (LLO) Operations
(Coles)
From: "Gerry Stapfer" <gerry@ligo-la.caltech.edu>
Control Room: (Rich Riesen) MEDM on screen help files are
50% completed. Mode Cleaned AutoLocking installed and operational.
Spiricon and Image acquisition software now installed and operational on
a Control Room computer. All PEM Microphones have been installed
and are operational.
6 MEDM screens are now available for web viewing. Larger, higher
capacity on-board batteries have been installed on the Weather Stations
at both ends.
CDS: (Russ) Installed new shielded cables on the Pentek boards in 1X9
and at both end station. Completed testing of the newly modified
SEI feed forward system at both end stations.
Optics and Installation: (Jonathan) Yesterday I met all day with Mike
Yeatman, the installer of our Laser Safety Interlock System for an initial
closeout! Happily, the system is functioning properly, all perimeter
doors are alarmed the workstation in the Control Room has now been setup
with an Operator's Console that now erupts with an audible alarm
and a graphic popup of violations. He's also replaced the defective
camera on the observation deck. Began coordinating with Stanford
and MIT to receive the handoff of drawings for the EPI. Obtained
appropriate software to manipulate the source files. Completed and
installed new ITM cameras and scatterometers, along with a photometric
camera in the vertex.
Detector/Technical Support (Whitcomb,
Coyne)
See
also the daily electronic logs for the installation and commissioning activities:
LHO
COMMISSIONING
2km Commissioning
Rolf Bork
-
Installed new LSC code on LHO2k. This code includes new digital filter
sections. Code was tested, as far as sweeping filters, etc.
We locked one arm last night and attempting full lock tonight.
Stan reporting:
David Shoemaker and Robert Scofield have taken transfer functions of
a shaker on the HAM9 support beams as a possible means to damp the stack
modes. No definitive answer yet, but it doesn't look crazy.
4-k Commissioning
Luca Matone
On Thursday night, the 4k Yarm was locked, for the first time, with
the Common Mode servo enabled. The UGF was set to 1kHz, with the ETMY/MC_L
and MC_L/MC_AO crossovers a little below 100Hz. To achieve this, the MC
crossover was lowered (19.2dB -> 6dB in slider unites) and the Output Matrix
filters for ETMY were enabled. As a result, the error point (AS_I) was
decreased by ~10x @ 200Hz (with respect to locking without the CM enabled).
The PSD of the control signal for ETMY was also attenuated (~100x) between
1kHz and 100Hz: the control signal was sent upstream, to the MC_L and MC_AO
paths, not only to ETMY.
Rolf Bork
Made some fixes for LHO 4k:
-
Modified LSC,ASC and end station code to send floating
point LSC/ASC outputs to digital suspension controllers to avoid truncation
prior to application of filters in DSC.
-
Fixed end station test points in DSC.
Stan reporting:
Nergis, Daniel, and Peter have continued to work on the common mode
servo, pushing it as far as it can go on a single arm. The next step
is to see what it can do on the full interferometer.
LLO
COMMISSIONING
Rai Weiss reporting:
Work on the interferometer
Noise:
Measurements of the residual angular noise in the optical lever servoes
were carried out. The noise is about a factor 100 below our current limits
at 100 Hz.
Measurements of the frequency noise of the laser continue.
The correlations between the various error signals are being measured
to establish if the noise is leakage from an unregulated quadrature. The
most significant correlations we have observed are between the two channels
at the antisymmetric port. The relevance to the noise is being investigated.
Initial results of a study to establish the mirror "sweet" spots (the
places where the mirror rotation does not couple into the cavity length)
has been put into the log. The study may have uncovered a small systematic
unbalance in the suspension and test mass we had not noticed before.
A continuing and important background task is to clean up the RFI and
computer generated pulses that are flooding the system. A program to introduce
shielded cables, to make the grounding and isolation more rational has
been going forward for the past month. There has been a reduction in the
pickup of line frequency harmonics but there is still much to do.
Operational improvements:
Some of the locking sequences are now part of computer driven auto locking
scripts and at times the instrument will reacquire with little human intervention.
The tidal servo using the fine actuators at the end test masses has
been installed and is functioning. The common and differential mode control
signals of the interferometer now automatically stay within the coil controller
bounds - a significant step in aiding uninterrupted operation.
Subsystem development:
Scatterometers have been installed to view the high reflectivity surfaces
of all the cavity test masses. The signals developed will be divided by
the output of the cavity power monitors to maintain a continuing record
of changes in the mirror scattering.
More work has been done on the wavefront sensor optics - it is a long
job and we will have a celebration when this wavefront sensor subsystem
is finally working.
Jay Heefner
The cables to and from the penteks in rack 1X9 were replaced with shielded
ribbons and the observed noise at the output of the LSC whitening boards
was reduced by a factor of 2. The dominant noise in the signal is due to
polling the pentek. The second largest noise source is the 2^22 Hz clock.
Both of these noise sources should be reduced significantly when the differential
driver/receivers and the new ISC timing fanout baords are installed.
SCIENCE
& ENGINEERING SUPPORT
Seismic Retrofit
Dennis Coyne reporting
The conceptual design review was held last Friday
morning, April 12th. Documentation for the Review is still available
here,
and has been submitted to the DCC on-line archives. The review committee’s
report is pending, but all felt it was a good review.
Electronics
layout drawings have been prepared for the EPI and AID approaches,
aimed at the initial LASTI implementation with dSpace controllers, but
with provision fro migration to VME based control.
A revised
schedule has been posted. (Note: ignore the installation phase which
is unrealistically short in this schedule; This phase requires more thought.)
It still appears to be feasible to meet a Jan 2003 start of installation
but with little or no schedule margin.
[Note: Progress reporting is light below, because the team’s weekly
meeting was canceled due to the review.]
External Pre-Isolation
Hydraulic External Pre-Isolation (HEPI)
Jonathan Kern is scheduling a trip to Stanford and Caltech to discuss
details of the hydraulic actuator assembly that he will take the lead on
for the prototype fabrication for the LASTI integration tests. He will
also visit Caltech to meet with Ken Mailand and get familiarity with the
pump station.
Pump Station:
-
CONSTRUCTION: Assembly has started, waiting on wood spacers for motor and
reservoir. Plumbing lengths are being cut and prepared for soldering Screw
in fittings being cleaned for assembly with sealer. Reservoir internal
strainers, sight gage, thermometer, filler and breather being assembled.
-
DESIGN: The mounting brackets for the accumulators, filters, and plumbing
supports are in progress .
-
LAYOUT DRAWING: Ken Mailand has finished a scale plan view and partial
elevation [acad 2D] layout
drawing, of station component assembly.
-
HARDWARE ASSEMBLY: The three resistors need final assembly, we will use
two, one at 40 and one at 70 psi drop. One 40psi backup for second RC assembly.
The accumulators arrived Friday 4-19 are waiting on a seal fitting to arrive,
ref one sent to Brian Lantz to test performance and to compare with others
previously tested.
-
LONG TUBE RUN: Support frame and coil assembly is finished. ref. Test taps
at the 60 foot mark [shortest run] and 180 foot mark [Longest]
-
TEST LOAD: Parts are being prepared and plumbing lengths cut to fit existing
available space.
Electro-Magnetic External Pre-Isolator (MEPI)
Nothing significant to report
Internal Stack Damping
All six degrees of freedom were closed (SISO) on the HAM-like demonstrator
in the Lauritsen high bay.
CDS Software
Rolf Bork reporting
CDS Hardware
Jay Heefner
PSL
Peter King
More measurements were taken of the NPRO laser whilst it was locked
to the reference cavity using the power actuator. Within the loop
bandwidth, the intensity noise is reduced by approximately 10 dB when the
laser is locked. Otherwise there do not appear to be any detrimental
effects.
Rich Abbott, Flavio Nocera
Schematic development is complete on the ISS. Board layout began
today (17 April). The board layout process should take less than
a week.
Optical Modeling
Erika D'Ambrosio
SB Imbalance:
the problem with the CACR allocation permission is fixed and I was
able to do many simulations with a view to finally wrap up the SB Imbalance
analysis for the steady case, that is, the perturbations we considered
do not depend on time.
Mirror maps:
the details of the runs performed by Prof. Ganezer have been discussed
and it seems that indeed the sensitivity of Ligo II to microroughness is
higher just
because of the Finesse.
Bill Kells
New interesting item is that Erika and I are actively in dialog with
Ken Ganezer (CSDH) on the results they presented at the LSC meeting on
performance of a Dual recycling ifo vs mirror surface scatter quality.
We are uncovering a lot of interpretation and "translation" disparities
which significantly alter the apparent implication of their original results.
A full analysis is underway.
Optics Testing
Lee Cardenas
Contamination cavity #2, Still locked. Mr. Zhang and I,
are continuing taking data of ring down and beat frequency everyday. The
ring down is 33us and the beat frequency 74 Mhz. same as previous measurements.
Contamination cavity# 1 It is locked. But, we still have the same
situation as before. ring down is still 48us. (the one previously
reported by J.Camp is 36us) and the transmission power is only 6mw with
an input power of 110mw. Bill kells still advise us for us to find
out the reason why is a longer decay. We are going to change the
two modematch lenses for a shorter focal length and re-align it.
The other alternative will be to switch this cavity for the third one that
it is sitting in the side and compare. But, Our priority is to test
the mineral oil ASAP.
I have the mineral oil and the test bars already baked by Bob Taylor(40m
South Annex).
I have given (4) test bars to Dr. R. De Salvo for the samples of Kapton
paint.
We will be installing the test bars with the mineral oil as soon as
we get our digital oscilloscopes that we gave to Paul Russel (electronics)
to have them calibrated.
Core Optics Support
Mike Smith
The input Faraday isolator polarizer, which generates the REFL beam,
will induce astigmatism onto the REFL beam. This effect only happens to
the reflected beam; the transmitted beam is unchanged. The amount is fairly
small with the glan-laser polarizer that is currently being used in LIGO;
however, if a glan-Brewster polarizer were to be used, the astigmatism
would be significant, as shown below:
glan-laser polarizer (normal entrance and exit faces)-- diameter
H=0.94, diameter V=1.00
glan-Brewster polarizer (Brewster's angle entrance and exit faces)--
diameter H=1.32, diameter V=1.00
LSC/ASC/DSC
Rich Abbott, Mohana Mageswaran
-
Mohana finished testing the variable timing board with the help of Lori.
The design is fully functional and additional units are being prepared
in the tech shop.
-
Spent time preparing diagrams for the SEI review last Friday. It
was a good thing as we now have neat packets of information that we are
dividing among our resources.
-
Finishing the schematic for the field interface module of the L4C.
PCB layout will begin tomorrow (18 April) and should only take a few days.
Jay Heefner
State code, operator screens and databases for the input crate of the
LHO 4K DSC are nearly complete and operational in the test stand.
Rolf Bork
Lori tested new timing modules. Next week, we will run further
tests and begin software to integrate their use in LSC. Lori is also
finishing/testing new ASC code for use on LHO2k.
Alex and Khan continued work on integration of new digital filters into
DSC. Hongyu is working on the EPICS interfaces. Alex also further
optimized the new digital filter code for better speed performance.
Microseismic and Tidal Correction
Jay Heefener
LLO Tidal System
The tidal hardware and software for the LLO Tidal System has been installed
and tested at LLO. The hardware was tested by using ezcaservo slaved to
the LSC output to ETMX and controlling with the tidal offset slider. Early
tests were successful and the CARM signal was kept near zero over a several
hour period. In the process it was found that the anti-image monitor did
not have sufficient gain to be effective, so the gain was increased to
+19 on the boards at both the X and Y ends.
40 Meter Interferometer (Weinstein)
April 19, 2002
-
Our new postdoc, Osamu Miyakawa of Tokyo University (a student of Seiji's
who did an RSE experiment with his own suspended mass interferometer) arrived
today, and is settling in (360 WB, x3049, miyakawa_o@ligo.caltech.edu ).
Please make him feel welcome!
-
We expect a visit from the Polish Public TV tomorrow (Friday 9 am).
-
Status of 13 meter suspended mass mode cleaner at the 40m:
-
All three suspended optics are in place in the vacuum chambers.
-
The beam from the PSL and IOO train is all lined up on MC1 and MC3.
-
We only have one stand-alone analog suspension controller, with the gain
set too high; so we can't damp the optics, and thus, cannot align MC2 (which
is 13 meters away from MC3).
-
Ben, Bob, Jay, Rolf, and crew are working towards getting our digital suspension
controllers ready ASAP.
-
We are preparing the input mode cleaner reflected and input mode cleaner
transmitted sensing beams, as well as the electroncis for mode cleaner
length and alignment sensing and control.
-
We hope to have it all together within a month!
-
Suspension Controllers & other CDS (Ben Abbott):
-
Dennis informed me that he noticed a large ammount of electronic noise
coming from one of the suspension satellite boxes. I brought it back to
the shop, and it tested out fine. In putting it back in situ, I noticed
that one of the IDC 64 connectors had been all but disconnected from its
cable. After fixing this, the noise wasn't evident, but more involved testing
might reveal more information.
-
The ISS DC photodiode pcb file is just about finished, and will go to the
boardhouse tomorrow.
-
Dennis and I populated 1Y2 (mode cleaner LSC and ASC controls) with its
crates and some of the modules.
-
I continue working on the photodiodes that will be needed for the mode
cleaner controls.
-
I mailed back yet another failed IBM RAID disk. It should come back some
time in the next two weeks.
-
Bob is about finished with wiring the power on the suspension controller
racks (1Y4 and 1Y5), and is about to start on the 1Y2 cross-connects.
-
Dennis has brought over from LHO the digital suspension controller epics
screens, and the IOO controls screens, and is modifying them for the 40m.
Ditto, for the databases.
-
Optical Layout (Smith):
-
IO Diagnostics, IMC_R and IMC_T: A layout for temporarily placing the IMC_R
ISC components on the AP table near the output chamber was completed. However,
because the electronic cable lengths would be different due to the additional
length from the intended location south of the PSL table, the layout will
probably not be implemented.
-
A current inventory list and order list for all of the ISC table components
is being generated. Mike is leaving for 6 weeks (honeymoon and stint at
VIRGO), so he will go over the installation of the IMC_R and IMC_T optical
train with Dennis early next week.
-
Many of the 45degree beamsplitters in these optical trains were ordered
for the wrong polarization, so new orders are going out.
-
OPTICAL LEVER OBJECTIVE LENS: A further analysis showed that a finite conjugate
design concept for a compact 40m objective lens is unacceptably sensitive
to positioning errors of the first-stage focus lens. An afocal design concept
will be studied to determine if it will be satisfactory.
-
Mike is thinking about a redesign of the input Faraday isolator, using
Brewster angle polarizing beamsplitters to minimize back-reflection; but
the resultant SP beam will be astigmatic.
-
Optics (Billingsley, Armandula):
-
Our beamsplitter, power recycling and signal recycling optics have come
back from polishing by CSIRO. They are being inspected by Helena and measured
by GariLynn, then they will go out for coating by REO. Helena has already
looked at the two beamsplitters.
-
CSIRO is still polishing our 5" test masses. Hope to get the 3 ITMs and
3 ETMs in a few weeks.
-
PSL and IOO (Ugolini, Vass, B.Abbott, Smith):
-
The PSL, and its two servos, continue to perform stably.
-
Still need to fully optimize and re-characterize the mode matching, FSS,
and PMC servos (noise spectra, transfer functions), since this most recent
re-build.
-
PSL diognostic optical train remains to be laid out and commissioned.
-
A beam tube and viewport shield was installed between the PSL enclosure
and the output optic chamber.
-
Because the PSL table is 1.5" to the west of where it was placed on Mike
Smith's Autocad layout, the beam did not enter the vacuum chamber in the
right place; this became evident when we installed the beam tube. Steve
has moved the IOO optical train 1.5" to the east to compensate, and re-steered
the beam into the output optic chamber.
-
Facilities and vacuum envelope (Vass):
-
Steve had the AP1 table (4' x 6') moved to the vertex area, and bolted
to the floor.
-
Larry has optical table enclosures, and beam tubes, in process in the Caltech
shop.
-
Larry has designs for mounts for sony cameras looking through viewports
at suspended optics, which protect the cameras and viewports. They are
in the shop and should be ready in 2-3 weeks.
-
Ben is arranging to have another rack be moved from the X arm to the Y
arm (between 1Y3 and 1Y4; I guess it will be called 1Y10), and bolted down.
-
Caltech HVAC is bringing in subcontractors to bid on improving the AC in
our new control room.
-
We are currently at atmosphere.
-
South Annex Bake Ovens (Taylor, Cardenas):
-
Bake oven #D, old chamber is ready and in standby.
-
Bake oven #E, new chamber is ready and in standby.
-
Bake oven #B, small chamber is ready and in standby.
-
Bake oven #C, small chamber just finished baking the (7) bars of Stainless
steel for the OTF Lab.
-
Bake oven #F, is in progress of getting prepared.
-
Bob Taylor is preparing to bake optical quality viewports in oven #E.
INCIDENT REPORT:
Location: 40m South Annex baking oven room.
Time: ~6:45pm Thursday, April 11
Report: baking oven heating tape shorted out and caused overheating
insulation that resulted smoking. Steve vented the room, disconnected heaters,
removed smoking insulation and took it outside. No damage was done. By
this time security and fire department showed up and confirmed that it
was safe to reenter room and smoke alarm was reset.
Response: Extra insulation was added to bake ovens. Post emergency
response list on entrance door to South Annex baking oven room. Will obtain
and install oxygen sensors.
Thermal Noise Interferometer (Libbrecht)
From: Eric Black <black_e@ligo.caltech.edu>
This week we identified one prominent source of noise in the TNI: a
15.75kHz oscillation on ground caused by one of our closed-circuit video
monitors. This signal couples into the second sr560 in our servo filter,
and the height of the resulting peak in our data is proportional to the
gain in this amplifier. More importantly, harmonics of 15.75kHz also appear
in our data, leading us to suspect that our prominent and regular peak
at 31.5kHz is not, as we had first suspected, a mechanical resonance.
We also identified a similar peak in the photothermal experiment, caused
by one of the R.F. signal generators in that experiment.
LASTI (Zucker)
No report this week.
Data Analysis and Computing (Lazzarini)
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
E2E Physics meeting
In Thursday's Physics meeting, we discussed the short and long term
plans of some of the e2e activities. Details may be found available at
http:/www.ligo.caltech.edu/~e2e. Discussion on the rest of the topics
will continue at next Wednesday's meeting.
Mechanical simulation
(Virginio)
- Final debugging stage for better 3D model for the LIGO I suspensions.
This model now includes the bounce and the right coupling with the roll
mode of the mirror. The wires flexural stiffness has also been
added. This model has been done using a quite general
maple program, which is able to provide the dynamics of the system if the
analytical expression of the Lagrangian is given. Implementation into e2e
is underway in parallel.
- Still working with Giancarlo Cella on the first release of MSE2, which
will provide the thermal noise calculation of the simulated mechanical
systems.
LIGO I simulation system
(Matt) Began testing of COC and LSC sub-systems in SimLIGO.
Code development and maintenance
(Hiro) fixing some bugs.
(Biplab) Testing recent guoy-phase and mismatch related changes.
(Ed Maros)
- Finished first draft of Makefile.am changes for JAlfi
- Minor port support for Linux.
Alfi
(Bruce)
Last week's report:
- Out sick half the week.
- Working on a new and better implementation of connections
and junctions in Alfi5.
(Melody)
- Fixed some PRs which included enhancing the settings value editor
for alfi5. Continuing on fixing some refresh problems with the popup
menus.
LIGO Data Analysis System
Software Systems (Blackburn)
The majority of the week has been spent identifying and fixing bugs
in the pre-release versions of LDAS. On Monday we pushed a pre-release
version onto LDAS-TEST so that the members of the LSC that are developing
search codes would be able to test their codes against this new version
of LDAS. This pre-release version was found to have a very high failure
rate and once a new version of LAL and LAL-wrapper needed to be pushed,
we took that opportunity to upgrade LDAS to a new pre-release version as
well. This version was having about an 11% false failure rate in our nightly
testing. The primary cause of these failures were a set of bugs in the
managerAPI, diskCacheAPI, and mpiAPI. These were fixed on Wednesday
and the test results for Wednesday night indicated that we have now reduced
the false failure rate from about 11% down to about 0.25%. This is
a tremendous accomplishment and places us back in the ballpark of the failure
rate that we experienced in the pre-release version of LDAS used in the
E7 run last December.
We have begun the process of pushing the pre-release versions of LDAS
to the Laboratory LDAS systems. At this time the pre-release version of
LDAS is successfully running at LHO and MIT (in addition to already being
on DEV and TEST). We will be working to get this pre-release versio of
LDAS up at LLO today. Also, we have placed this pre-release version onto
the new CIT system (which currently lacks a beowulf cluser).
We have completed about 40% of our required test suite used in qualifying
an LDAS release. At this time on one major problem remains that needs attention
for this release. The system does not allow Process Frames produced by
earlier jobs to be reused in dataPipeline later dataPipeline commands.
This is being looked into today. We also have significant documentation
preparations still to make to the system before the release. There are
several minor issues which will not hold up this release.
One minor change to the wrapperAPI forces it to buffer the messages
between the wrapperAPI and the mpiAPI to not occur more frequently than
once every 2 seconds - system tunable with the resource file. This was
needed because a lot of poorly organized search codes are requesting to
send messages at rates higher than unix allows without major unix reconfigurations.
A new problem tracking catagory was added to the LDAS GNATs system for
GUILD this week.
The actual release date of LDAS will be closely coupled to the tests
of the search codes by LSC authors. We will wait for an a-o-k before finalizing
the release in the event that we resolve our internal issues before the
search codes are adequately tested against this new release.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
* Continued HPSS migration from Redwoods/3590s to 9940s.
* More HPSS user directory reconfiguration and account maintenance.
* Worked on resetting everything after one big HPSS failure.
* Helped Igor at LLO with Qlogic HBA firmware, T3 pSOS and FC switch
firmware upgrades.
* Helped Keith at MIT with Qlogic HBA firmware upgrade.
* Still working to get StorageTek to make good on replacing the Ultra
10.
* LIGO SAN testbed:
After much assistance from LSC/Sun to identify the problem (a SAM vs.
Sun FC driver problem) SAM-QFS has finally mounted and unmounted a tape!!
(Al Wilson)
* Released BB for LHO.
* Setup BB for LLO.
* Learning AIDE as a free alternative to tripwire for intrusion detection.
* Upgraded LHO, LLO, MIT, DEV, and TEST to the latest ldas-linux patch
set including openssh.
(Stuart Anderson)
* Pushed new LDAS pre-release versions to LHO, LLO, and MIT. This involved
finishing the upgrade of all LDAS computers to openssh-3.1p1 for security
reasons.
* Investigating the use of VPNs to solve the inter-LDAS Database communication
problem.
* Moved the LDAS archive server from the CACR network to the new LIGO
Gigabit Ethernet network at Caltech.
MIT
(Keith Bayer)
* Upgraded HBA firmware.
* Loaded several LLO super reduced set data.
* Loaded LLOcoin data out to lancelot for developers.
* Installed Ethernet card in lancelot and inspected cabling requirements
to attach it to SF880.
* Started investigation into roll-our-own cheap pc/raid array.
Livingston
(Igor Yakushin)
* Upgraded firmware on T3s and switches.
* Upgraded fiber channel firmware on gateway and metaserver.
* Working on setting up replication between DB2 databases at LLO and
Caltech.
(Shannon Roddy)
* Worked on the GC firewall configuration to allow db2 traffic in and
out of LLO to Igor's machines. There are still some issues, but as
far as I can tell the problem is on the db2 machines and not the firewall.
I will follow up on this with Igor.
Hanford
(Greg Mendell)
* Finished worked with Igor and Julien to get an E7 reduced data set
onto tape and sent to MIT. The tapes were sent on Mon Apr 15.
* Tapes with LHO E7 data returned from UWM on Tue Apr 16.
* Sun replaced the DC converters in the SunFire 880 ldas dataserver
on Fri Apr 12. (Originally Sun had come on Tue Apr 9 to do this, but found
they did not have enough part to complete the job.)
* Assisted with the pre-release of the new version LDAS at LHO.
Data Analysis Activities (Lazzarini)
Mendell:
For The Weekly Report: Apr. 18, 2002; Data Analysis Update:
1) Updated the knownpulsardemod DSO to handle the new version of the
LALUnitPair data structure. Ran tests in stand-alone mode, check the code
into cvs, and ran test on the LDAS-TEST system, verifying the this code
runs correctly with the new prereleased versions of lal, lalwrapper, ldas.
2) David Chin reports that he has verified that his new clean locked
segments posted Apr 6 are valid. I will regenerate SFTs on the E7 data
at the sites once the new release of lal, lalwrapper, and ldas is pushed
to the sites.
3) Currently updating job scripts to run with the new prerelease of
ldas to further test the system. I will especially be testing the
ability of the new release of ldas to read in frequency series data
from the proc structure of an SFT frame file.
General Computing (Wallace)
MIT:
(Keith)
-Installed new printer in NW22, created print queue, tested on various
o/s's
-Troubleshot old laser printer 'tiny'
-Started investigation into tape robot
Livingston:
(Shannon)
-Reinstalled a windows 2000 domain at LLO. This was set up a
while back, but there was no redundancy designed into the domain.
As Microsoft software does, the domain server crashed the last time.
It also would not restore from the backups. This time I have taken
4 spare machines that people have had replaced recently and set them up
as servers with the domain data replicated between all four servers.
I have joined the windows 2000 professional machines into the domain so
that I can manage software updates, hardware inventories, etc. Also
this allows people to have "roaming profiles" on the windows machines,
if they want to utilize them.
-Received a couple of laptops in. I am currently installing software
on one.
-Spent several hours on the phone with Cisco tech support to try and
work on some configuration issues with the PIX firewall. I believe
that long term, we will have to change the network topology and addressing
schemes here at LLO to make full use of the PIX. I have been discussing
this with Larry.
-Installed a "CD Server" on the LLO network. This allows me to
copy images of CDs and leave them in a dedicated machine so that they are
accessible by ftp, NFS, Windows Networking, www, etc. This means
that no one should lose any more CDs from now on. They will still
have to get the serial number for software, but they will not need a copy
of the media.
-Installed a 4' high wall mount 19" rack in the new building.
This is to accommodate the patch panels etc. for the networking in the
new building.
-Set up Norton Anti Virus so that it is centrally administered by me.
Everyone's virus updates etc are controlled from a central server now.
There is also a central quarantine and a central log. Norton now
notifies me if there is a virus found on any machine that I have set up
in this manner.
-Ordered some spare batteries and chargers for the Dell laptops we
have here.
-Installed a 160 GB hard drive in Marcel's computer.
(Tom)
-The network usage for Livingston can be found at : http://kahuna.net.lsu.edu/mrtg/ligo.html
Hanford:
(Larry)
-Working on the WAN issue. So far we have received some quotes from
NoaNet and Albert is working out the issue of connecting to the Internet2
system. Technically things are looking positive. There are a number
of items that we still need to work out but so far it looks like NoaNet
will be able to accommodate us on most of them.
CIT:
(Mike)
-Rebuilt two PC's and reloaded OS and General Computing Software for
visitors that started on 4-15 and 4-18.
-Moved equipment around by replacing monitors and computers, for two
visitors that started this week. Reloaded OS and GC software on three
Laptops.
-Went through Linda T.'s Laptop and corrected multiple software errors
and added upgrade patches plus service pack 2. Everything seems to be running
fine for now.
-I have been continuing to work on updating our list for the PHP webserver
database; I just about have this done as far as the PC's go.
-Larry and I ran new cable drops to new control room in the sub basement
conference room at bridge annex and one office.
-Had to reload a computer due to a virus that corrupted the OS. I restored
this from a Ghost image.
-I had a lot of onsite user support this week that included networking,
printing, e-mail, software and virus problems that I had to work out with
users.
(Veronica)
- LIGO website: made yet another version of the new LIGO Science Links
webpage. Added several links that were left out. Posted various updates
to the LIGO website. The LSC website has been transferred to a web
server of its own; I went through the scripts to make sure everything runs
smoothly, the link structure is preserved, and that nothing is left out.
Posted more LSC March meeting talks. Working on the LIGO Policies
and Procedures website. Meeting with Ryan about the new LIGO Press
Kit website; started working on the website layout.
- CaJAGWR: posted Tinto's talk as video and pdfs. Updated the seminars
page.
(Lisa)
- Fixed the php installation on vega. Restored the inventory
system to that. Mike has been actively loading it with accurate data.
This still needs some work regarding how mac addresses are handled.
- spent the majority of the week working on the mailserver vacation
problem -- this has involved quite a lot of troubleshooting regarding dependencies
in the development environment that don't show up in any of the documentation.
The problem with the vacation messaging has shown up on another of other
platforms, but the general UNIX community is stumped about how to fix it.
(Larry)
-Back to working procurement issues. Foundry still owes information
on a purchase from last year. Trying to get a double charge from ITS taken
off. Placed, multiple computer and equipment orders for different groups.
Working on a order of new units for the 40M.
-Tried to spend some time working on the vacation problem but have
not been able to get much done with it other than running tests for Lisa.
-Restored a number of directories for different people. The backup
system Lisa has in place saved quite a bit of time.
-Worked a number of cable issues. Switch cables and cables for the
new control room.
-Windows XP has been a topic of discussion and found so far that it
does not work well in our invironment. There are network, wireless, driver
and application issues. Presently, the sysadmin group still recommends
using Win2K if one needs to run under Microsoft.
-The group is working on changing the wireless setup. Working on setting
up a standard configuration so the user will have minimal changes to make
when going from one site to another.
-Working a couple of security related issues. Mostly viruses and some
other minor incidents. After talking with ITS and their problems, we've
been going pretty good on keeping the number incidents down.
-Working on documentation for a number of items. The GC policy has
a few changes to be made but so far it is looking pretty good.
LIGO II/Advanced R&D (Sanders)
From: GariLynn Billingsley <Billingsley_G@ligo.caltech.edu>
Homogeneity Compensation - Goodrich has delivered the 25 cm sapphire
blank with compensating polish.
I've measured the homogeneity of the piece. The good news is
that they have compensated the inhomogeneity of the piece. See the image
at http://www.ligo.caltech.edu/~coreopt/GoodrichComp.JPG This represents
the central 150 mm diameter of the piece. The measurement is through
side 2 (see below) reflecting off side 1 and back through the bulk.
I have not subtracted side 1, yet, this is the situation where the homogeneity
appears best.
See the Goodrich data at: http://docuserv.ligo.caltech.edu/docs/internal/C/C020137-02.pdf
(yes the first page is blank..oops.) I believe they have subtracted surface
1 in this view. The blob at 8 o'clock may correspond to what I measure
at 12 or 6 o'clock.
The bad news is that the piece appears badly scratched, either that
or it has something on the surface that doesn't clean with acetone and
methanol. The surface specifications were waived in this instance
because the piece has several bubbles breaking through the surface, Goodrich
can't possibly control the bubbles. However it is interesting to
note that most of the "inhomogeneity" now comes from the scratches and
circular machining marks.
The other bad news is that they appear to have confused which side they
should be working on. What was a nice 4nm surface on side 1(former)
is now the compensatED surface (the new side2) This is proven by the characteristic
defects at the bottom of both upper images at http://www.ligo.caltech.edu/~coreopt/SurfacesPostComp.JPG
This image shows the clockwise change of the surfaces
Surface 1 before Goodrich (upper left)
Surface 1 after Goodrich (now surface 2 the "compensated" surface)(upper
right)
Surface 2 before Goodrich (lower right)
Surface 2 after Goodrich (now surface1)
It's interesting that (speaking currently now) the compensating polish
compensates for an error polished into Side one (did they try compensation
on this surface at one time?), yet the specification calls for the side
one data to be subtracted from the inhomogeneity. The exact text of the
specification is:
"Figuring of surface 2 is intended for compensation of bulk
inhomogeneity of the index of refraction of the mirror blank. There is
no explicit requirement for the surface alone, only in combination with
the bulk material. The optical path difference of the surface/bulk is measured
in transmission through surface 2, passing through the material, reflected
from surface 1, passing again through the material and again in transmission
through surface 2. All requirements under this heading refer to this double
pass measurement.
The real contribution of surface errors on surface 1 are removed
from this measurement using an independent phase map of surface 1."
I will be in touch with Goodrich regarding these results.
From: Helena Armandula <ahelena@ligo.caltech.edu>
Silicate bonding - Heavy Glass
Bonded four 1/2" dia. pieces of heavy glass (#24935 from Viox) to fused
silica substrates, using a silicate solution. The parts were not
flat to the 1/10 wave specified, so, about a couple of hours after bonding
some separation appeared. Two of the bonded parts were taken apart
4 hours after bonding. I will attempt to correct the flatness on these
pieces and re-bond them. The remaining bonded substrates will be
cured for some time before being tested for strength.
From: ctorrie <ctorrie@ligo.caltech.edu>
Suspensions
-
Janeen and I have been working on the final drawings and assemblies for
the prototype Mode Cleaner suspension.
-
Norna, Janeen and I have been looking at the parameters for the Recycling
Mirror suspension.
-
At the April SUS design telecon we discussed whether or not the rough Quad
should come to Caltech this summer. A final decision on this has been delayed
until next month.
-
Norna and I met with Mike Plissi, Russell Jones and Alastair Grant in Glasgow
to discuss the details of my visit in May.
Mark Barton
Added the corrected thermal noise code to my triple pendulum model,
bringing it up to date with the quad model.
For additional information about this report, contact sanders@ligo.caltech.edu